GENERAL ABSTRACT (name of the water body)

Amount in
S. No. Description of item
lakhs of Rs.
1 Works Head
a De-siltation

b Bund strengthening and tol wall

Walking Path and Children play


c
ARRANGEMENT

d Steps

e Branding

Activities Total
2 Miscellaneous
Inauguration, handing over and
i purchase of small tools (10% on
Activities expenditure)
3 Administration
Need Assessment Study (with
i surveying, mapping, testing, etc.),
Preparation of DPRs
ii Cost of IA (overheads etc.)
Grand TOTAL
A B S T R A C T - DESILTATION
S.
Quantity Rate Per Amount in Rs.
No.
1 2 4 5 6
Clearing thick jungle growth ( less than 50
percent open space ) including bushes upto
1 30 cm / parthenium and other weeds
including burning or disposing off the same as
directed etc., complete.

2 Excavation for foundation in all kinds of soil


including boulders upto 0.30 m diameter for dam,
spillway, intake structure and other appurtenant
works and placing the excavated soil neatly in
dump area or disposing off the same as directed
etc.,

2 Conveyance charges for silt

3 Dewatering for 4 shifts for Desiltation

4 Revetment removal and refitting charges

Total Amount Rs.

A B S T R A C T - BUND
S.
Quantity Rate Per Amount in Rs.
No.
1 2 4 5 6
1 Clearing thick jungle growth ( less than 50
percent open space ) including bushes upto
30 cm / parthenium and other weeds
including burning or disposing off the same as
directed etc., complete.

2 Providing homogeneous embankment using soil


from approved borrow area in layers of 25 to 30
cm before compaction including cost of all
materials, machinery, labour, all operations such as
excavation, sorting out, transportation, spreading
soil in layer of specified thickness, breaking clods,
sectioning, watering, compacting to density control
of not less than 95 percent or as stipulated using
Sheep foot roller / Vibratory roller/ 8 to 10 tonne
power roller etc., complete with initial lead
upto 1 km and all lifts.

3 Toe wall With RR, Pointing


4 80 mts x 2 ft Hallow bricks wall for bund with
paints lms
Total Amount Rs.
A B S T R A C T - Walking Path ARRANGEMENT

Name of work : 0

S.
Quantity Rate Per Amount in Rs.
No.
1 2 4 5 6
1 Excavation for foundation in all kinds of soil
including boulders upto 0.30 m diameter for dam,
spillway, intake structure and other appurtenant
works and placing the excavated soil neatly in
dump area or disposing off the same as directed
etc., complete with initial lead upto 1 km and all
lifts.

2 Providing and laying insitu vibrated M-10 ( 28 days


cube compressive strength not less than 10 N / sq
mm ) grade cement concrete using 40 mm down
size approved, clean, hard, graded aggregates for
foundation filling including cost of all materials,
machinery, labour, formwork, cleaning, batching,
mixing, placing in position, levelling, vibrating,
finishing, curing etc., complete with initial lead
upto 50 m and all lifts. ( Cement content : 220 kg
/ cum )

4 Laying of tiles including all material, labour


and machinery

5 Children playing / Exercise bars provision (LS)

6 Exterior paints on the wall surrounded on 4


sides

Total Amount Rs.

A B S T R A C T - Steps & Others

S.
Quantity Rate Per Amount in Rs.
No.
1 Excavation for foundation in all kinds of soil
including boulders upto 0.30 m diameter for dam,
spillway, intake structure and other appurtenant
works and placing the excavated soil neatly in
dump area or disposing off the same as directed
etc., complete with initial lead upto 1 km and all
lifts.
2 Providing and laying insitu vibrated M-10 ( 28 days
cube compressive strength not less than 10 N / sq
mm ) grade cement concrete using 40 mm down
size approved, clean, hard, graded aggregates for
foundation filling including cost of all materials,
machinery, labour, formwork, cleaning, batching,
mixing, placing in position, levelling, vibrating,
finishing, curing etc., complete with initial lead
upto 50 m and all lifts. ( Cement content : 220 kg
/ cum )

3 Providing and laying insitu vibrated M-15 ( 28 days


cube compressive strength not less than 15 N / sq
mm ) grade cement concrete using 40 mm down
size approved, clean, hard, graded aggregates
including cost of all materials, machinery, labour,
formwork, centering, scaffolding, cleaning,
batching, mixing, placing in position, levelling,
vibrating, finishing, curing etc.,complete for plain
concrete works with initial lead upto 1 km and all
lifts. ( Cement content : 260 kg /cum with use of
super plasticiser,CA : 0.90 cum, Blending Ratio of
CA -- 50:30:20, FA : 0.40 cum)

Total Amount Rs.

A B S T R A C T - Branding
S.
Quantity Rate Per Amount in Rs.
No.

1 2 4 5 6
1 Iron Name boards on the bund, including
labor charges for pits digging, filling with
CC including 20 mm stones

2 Stone plaque including material, labor


for constructing brick wall

Total Amount