PRESUPUESTO - DE MANO DE OBRA

OBRA: REHABILITACION DE MUROS Y COLUMNAS


PROPIETARIO:
UBICACION:
FECHA: MAYO 2019

ITEM DESCRIPCIÓN UND METRADO P.UNIT PARCIAL SUB TOTAL


01.00.00 Demolicion S/ 1,079.73
01.01.00 Muros m² 24.49 S/ 30.00 S/ 734.73
01.02.00 Vigas ml 3.80 S/ 25.00 S/ 95.00
01.03.00 Columnas Unid 1.00 S/ 150.00 S/ 150.00
01.04.00 Zapatas Unid 1.00 S/ 100.00 S/ 100.00
02.00.00 Cimiento Corrido ml 3.80 S/ 70.00 S/ 266.00 S/ 266.00
03.00.00 Sobrecimiento ml 3.80 S/ 30.00 S/ 114.00 S/ 114.00
04.00.00 Asentado de Ladrillo m² 10.08 S/ 25.00 S/ 252.00 S/ 252.00
05.00.00 Zapatas Und 1 S/ 100.00 S/ 100.00 S/ 100.00
06.00.00 Columnas Und 1 S/ 100.00 S/ 100.00 S/ 100.00
TOTAL S/ 1,911.73

AGREGADOS - CERCO PERIMÉTRICO

ITEM MATERIAL UND METRADO P.UNIT PARCIAL


01.00.00 HORMIGÓN m³ 1.50 S/ 45.00 S/ 67.64
02.00.00 PIEDRA GRANDE m³ 1.00 S/ 65.00 S/ 65.00
03.00.00 CONFITILLO m³ 0.50 S/ 70.00 S/ 35.00
04.00.00 ARENA GRUESA m³ 1.46 S/ 45.00 S/ 65.54
05.00.00 CEMENTO ROJO ( MOCHICA ) Bolsas 21 S/ 27.00 S/ 562.75
06.00.00 LADRILLODE CHULUCANAS Und 503 S/ 0.37 S/ 186.29
07.00.00 CLAVOS DE 2 1/2" Kg 2 S/ 4.50 S/ 9.00
08.00.00 CLAVOS DE 3" Kg 1 S/ 4.50 S/ 4.50
09.00.00 Alambre #16 Kg 4 S/ 3.80 S/ 15.20 40
10.00.00 Ø 1/4" Varillas 7 S/ 7.30 S/ 51.10
11.00.00 Ø 3/8" Varillas 2 S/ 16.00 S/ 32.00
12.00.00 Ø 1/2" Varillas 3 S/ 29.80 S/ 89.40

TOTAL S/ 1,183.42

NOTA: TENER EN CUENTA QUE LOS VALORES DE P.UNIT DE LOS MATERIALES VARIAN SEGÚN LOS
PROVEEDORES, POR LO CUAL ESTOS VALORES SON CONSIDERADOS APROXIMADOS.