Proyecto: "CONSTRUCCIÓN EDIFICIO CARRERA DE MINAS UNSXX" PLAZO DE EJE


UBICACIÓN: FACULTAD DE TECNOLOGIA CARRETERA CATAVI
BENEFICIARIO: CARRERA DE INGENIERIA DE MINAS DE LA UNSXX MONTO CONTRATO:
MONTO CONTRATO MODIFIC
Nº P/UNIT CONTRATO O
Nº DESCRIPCION DEL ITEM UNID.
ITEM BS, V. Contrato

1 (M01) - OBRAS INICIALES


1 INSTALACION DE FAENAS GLB 8204.98 1.00
2 LETRERO DE OBRA PZA 3143.35 1.00

2 (M02) - ESTRUCTURA HºAº


1 REPLANTEO Y TRAZADO M2 10.11 313.79
2 EXCAVACION 0-2 M TERRENO DURO M3 88.32 536.26
3 SOLADURA DE PIEDRA MANZANA M2 25.75 313.79
4 RELLENO Y COMPACTADO C/EQUIPO MATERIAL COMUN M3 35.06 296.59
5 HORMIGON POBRE E=5CM M3 690.84 15.69
6 HºSº ZAPATAS R=210KG/CM2 M3 2321.45 233.68
7 HºSº VIGAS DE ARRIOSTRE R=210KG/CM2 M3 1426.63 33.26
8 HºSº COLUMNAS R=210KG/CM2 M3 3144.13 61.9
9 HºSº VIGAS R=210KG/CM2 M3 2650.36 148.19
10 HºSº LOSA C/VIGUETAS IN SITU 2 DIREC R=210KG/CM2 M2 491.80 889.51
11 HºSº LOSA C/VIGUETAS IN SITU 1 DIREC R=210KG/CM2 M2 316.17 427.37
12 HºSº LOSA LLENA R=210KG/CM2 M3 2971.35 22.09
13 HºSº MURO CAJA DE ASCENSOR M3 2211.78 32.19
14 HºSº ESCALERAS R=210KG/CM2 M3 2661.51 30.17
15 HºSº MUROS DE PARAPETO R=210KG/CM2 M3 2498.14 14.68
16 ACERO ESTRUCTURAL FY= 5000 KG/CM2 KG 14.68 78,326.65
HORMIGON CICLOPEO R=210KG/CM2 (50%P. DESPLAZADORA) M3 972.52

3 (M03) - ESTRUCTURA CUBIERTA


1 CUBIERTA CHAPA TRAPEZOIDAL C/ESTRUC. METALICA M2 360.32 290.38
2 ANCLAJE PARA CERCHA METALICA PZA 457.14 16
3 CUMBRERA DE CALAMINA CHAPA TRAPEZOIDAL ML 107.52 21.43

4 (M04) - ESTRUCTURA CASCO


1 ESTRUCTURA METALICA P/CASCO GLB 40072.38 1
2 COLUMNA METALICA TUBO REDONDO 200X50MM PZA 1246.15 6
3 PROTECTORES PLANCHA E= 0.75 MM CASCO M2 360.44 51.36
4 ANCLAJE PARA COLUMNA METALICA PZA 1029.61 6

5 (M05) - ESTRUCTURA TANQUE BAJO


1 EXCAVACION 0-2 M TERRENO DURO M3 55.20 68.01

1
Proyecto: "CONSTRUCCIÓN EDIFICIO CARRERA DE MINAS UNSXX" PLAZO DE EJE
UBICACIÓN: FACULTAD DE TECNOLOGIA CARRETERA CATAVI
BENEFICIARIO: CARRERA DE INGENIERIA DE MINAS DE LA UNSXX MONTO CONTRATO:
MONTO CONTRATO MODIFIC
Nº P/UNIT CONTRATO O
Nº DESCRIPCION DEL ITEM UNID.
ITEM BS, V. Contrato

2 RELLENO Y COMPACTADO C/EQUIPO MATERIAL COMUN M3 31.75 28.18


3 HORMIGON POBRE E=5CM M3 690.84 1.56
4 HORMIGON SIMPLE R=210KG/CM2 M3 2650.36 11.67
5 ACERO ESTRUCTURAL FY= 5000 KG/CM2 KG 14.68 691.85
6 HORMIGON CICLOPEO R=210KG/CM2 (50%P. DESPLAZADORA) M3 972.52 0.53
7 MURO PORTANTE VISTO E=20CM (LADRILLO GAMBOTE) M2 365.43 6.09
8 PROV. Y COL. TAPA METALICA PZA 417.65 2

6 (M06) - INSTALACION AGUA POTABLE


1 REPLANTEO Y CONTROL LINEAS DE TUBERIA ML 5.73 258.39
2 EXCAVACION 0-2 M TERRENO DURO M3 55.20 8.07
3 RELLENO MANUAL C/TIERRA CERNIDA (S/MAT) M3 81.47 8.06
4 PROV. Y TEND. TUBERIA PVC ESQ. 40 D=1 1/2" ML 25.17 27.43
5 PROV. Y TEND. TUBERIA PVC ESQ. 40 D=1" ML 17.87 70.34
6 PROV. Y TEND. TUBERIA PVC ESQ. 40 D=3/4" ML 10.58 31.42
7 PROV. Y TEND. TUBERIA PVC ESQ. 40 D=1/2" ML 8.15 104.85
8 PROV. Y TEND. TUBERIA F.G. D=2" ML 130.33 7.69
9 PROV. Y TEND. TUBERIA F.G. D=1 1/2" ML 68.68 16.66
10 PROV. Y COL. LLAVE DE PASO D=2" PZA 442.28 2
11 PROV. Y COL. LLAVE DE PASO D=1 1/2" PZA 377.37 1
12 PROV. Y COL. LLAVE DE PASO D=1" PZA 135.41 6
13 PROV. Y COL. LLAVE DE PASO D=3/4" PZA 117.70 7
14 PROV. Y COL. LLAVE DE PASO D=1/2" PZA 85.84 16
15 PROV. Y COL. EQUIPO DE BOMBEO GLB 6773.15 1
16 ACCESORIOS E INSTALACIONES TANQUE BAJO GLB 3144.16 1
17 PROV. Y COL. TANQUE ELEVADO PREFABRICADO GLB 12210.72 1
18 DESINFECCION DE TUBERIAS ML 1.40 258.39
19 DESINFECCION DE TANQUE BAJO M3 12.02 18
20 PRUEBA HIDRAULICA ML 3.86 258.39

7 (M07) - DESAGUE SANITARIO Y PLUVIAL


1 REPLANTEO Y CONTROL LINEAS DE TUBERIA ML 5.73 207.83
2 EXCAVACION 0-2 M TERRENO DURO M3 55.20 41.12
3 ASIENTO PARA TUBERIAS CAMA DE ARENA M3 131.74 5.03
4 RELLENO MANUAL C/TIERRA CERNIDA (S/MAT) M3 81.47 36.59
5 PROV. Y COL. REJILLA DE PISO PZA 56.72 17.00
6 PROV. Y COL. CAJA INTERCEPTORA PZA 71.37 16.00
7 PROV. Y COL. CAJA DESGRASADORA PZA 92.62 1.00

2
Proyecto: "CONSTRUCCIÓN EDIFICIO CARRERA DE MINAS UNSXX" PLAZO DE EJE
UBICACIÓN: FACULTAD DE TECNOLOGIA CARRETERA CATAVI
BENEFICIARIO: CARRERA DE INGENIERIA DE MINAS DE LA UNSXX MONTO CONTRATO:
MONTO CONTRATO MODIFIC
Nº P/UNIT CONTRATO O
Nº DESCRIPCION DEL ITEM UNID.
ITEM BS, V. Contrato

8 PROV. Y COL. TUBO DESAGUE PVC D=2" ML 42.71 64.05


9 PROV. Y COL. TUBO DESAGUE PVC D=4" ML 85.25 143.78
10 CAMARA INSPECCION HºCº SENCILLA H<1M PZA 565.33 11.00
11 CAMARA INSPECCION HºCº SENCILLA H>1M PZA 706.67 1.00
12 PROV. Y COL. CANALETA 10X10CM ACERO GALVANIZADO ML 110.57 44.80
13 PROV. Y COL. BAJANTE PLUVIAL PVC D=4" ML 101.49 164.88
14 PROV. Y COL. BAJANTE SANITARIA PVC D=4" ML 104.72 89.96

8 (M08) - OBRAS FINALES


1 LIMPIEZA GENERAL Y RETIRO DE ESCOMBROS GLB 3552.81 1

9 (M09) - ARQUITECTONICO
1 IMPERMEABILIZACION DE SOBRECIMIENTO M2 45.49 30.31
2 MURO LADRILLO CERAMICO 6 H E=15 CM. M2 141.60 2,994.87
3 CONTRAPISO DE H° S/LOSA CARPETA E=3CM M2 90.92 1,482.04
4 CORDON DE ACERA H°S° 0,20X0,40 CM ML 141.68 399
5 EMPEDRADO Y CONTRAPISO DE HORMIGON PARA ACERA M2 144.96 556
6 PISO DE CERAMICA RUSTICA PARA ACERAS M2 144.29 556
7 PISO DE CERAMICA ESMALTADA DE ALTO TRAFICO M2 144.29 1,674.07
8 ZOCALO DE CERAMICA ESMALTADA ML 42.52 1,224.00
9 PISO DE PORCELANATO M2 267.12 233
10 ZOCALO DE PORCELANATO ML 47.72 119
11 PISO MACHIEMBRE CON ENVIGADO M2 568.92 47.5
12 TARIMA DE MACHIEMBRE M2 568.92 43.86
13 MESONES GRANITO EN LAVORATORIOS Y COCINETA ML 1120.90 48
14 REVESTIMIENTO DE GRADAS CON GRANITO M2 326.54 119.78
15 ZOCALO DE MOSAICO GRANITICO ML 174.45 126.82
16 REVOQUE INTERIOR DE CEMENTO M2 113.94 828
17 REVESTIMIENTO DE CERAMICA S/MURO H=TOTAL M2 161.97 828
18 REV. EXTERIOR CAL CEMENTO M2 98.16 1,854.00
19 REVOQUE DE YESO BAJO LOSA M2 63.12 1,504.00
20 REVOQUE INTERIOR DE YESO SOBRE MURO M2 62.12 3,492.00
21 CIELO FALSO BAJO LOSA M2 55.93 70.6
22 CIELO FALSO ACUSTICO M2 248.16 243
23 PINTURA INTERIOR - LATEX M2 27.29 3,680.00
24 PINTURA EXTERIOR - LATEX M2 26.56 1,310.00
25 MARCOS DE MADERA PARA PUERTAS ML 162.46 410.2
26 PUERTA DE BAÑO TIPO CONTRAPLACA INC. QUINCALLERIA M2 927.85 42.85

3
Proyecto: "CONSTRUCCIÓN EDIFICIO CARRERA DE MINAS UNSXX" PLAZO DE EJE
UBICACIÓN: FACULTAD DE TECNOLOGIA CARRETERA CATAVI
BENEFICIARIO: CARRERA DE INGENIERIA DE MINAS DE LA UNSXX MONTO CONTRATO:
MONTO CONTRATO MODIFIC
Nº P/UNIT CONTRATO O
Nº DESCRIPCION DEL ITEM UNID.
ITEM BS, V. Contrato

27 PUERTA INTERIOR TIPO CONTRAPLACA INC. QUINCALLERIA M2 927.41 90.2


28 VIDRIO TEMPLADO 10MM M2 956.02 58

4
Proyecto: "CONSTRUCCIÓN EDIFICIO CARRERA DE MINAS UNSXX" PLAZO DE EJE
UBICACIÓN: FACULTAD DE TECNOLOGIA CARRETERA CATAVI
BENEFICIARIO: CARRERA DE INGENIERIA DE MINAS DE LA UNSXX MONTO CONTRATO:
MONTO CONTRATO MODIFIC
Nº P/UNIT CONTRATO O
Nº DESCRIPCION DEL ITEM UNID.
ITEM BS, V. Contrato

29 VENTANAS CARPINTERIA DE ALUMINIO PIEL DE VIDRIO M2 611.28 147.5


30 VENTANAS ALUMINIO CORREDIZAS VIDRIO 4MM INC. QUINC M2 502.13 339.91
31 BARANDA DE ALUMINIO H=1,10M CON VIDRIO E=8MM M2 743.59 141.3
32 PROV. E INST. INODORO PZA 1006.68 18
33 PROV. E INST. DE LAVAMANOS C\ PEDESTAL PZA 864.52 10
34 PROV. Y COLOCADO DE DUCHAS PZA 3508.39 2
35 PROVISION Y COLOCADO DE URINARIOS PZA 508.72 8
36 PROV. Y COL. LAVAPLATOS 1 DEPOSITO 1 FREGADERO PZA 1253.56 5
37 IMPERMEABILIZACION DE LOSA M2 210.11 190
38 LETRAS DE ALUMINIO FUNDIDAS 40 X 22 CM PZA 262.88 17
39 PLACA DE ENTREGA DE OBRA PZA 1163.46 1
40 AREAS VERDES Y JARDINERIA M2 78.54 1,300.00
41 LIMPIEZA Y RETIRO DE ESCOMBROS GLB 2748.82 1

10 (M10) - ELECTRICO
1 ILUMINACION FLUORESCENTE (INCL. LUMIN. 2X40 W) PZA 287.54 264
2 ILUMINACION INCANDECENTE 100 W PTO 161.87 3
3 PROV. Y COLOC. DE INTERRUPTORES DOBLES PTO 91.98 4
4 PROV. Y COLOC. DE INTERRUPTORES SIMPLES PTO 86.46 54
5 PROV. Y COLOC. DE CONMUTADOR DOBLE PTO 97.88 10
6 PROV. Y COLOC. DE CONMUTADOR SIMPLE PTO 97.88 11
7 CAJA PARA 5 DISYUNTORES UNIPOLAR PZA 231.52 5
8 DISYUNTORES DE 16 AMP UNIPOLAR PZA 51.17 5
9 DISYUNTORES DE 20 AMP UNIPOLAR PZA 51.17 49
10 DISYUNTORES DE 32 AMP UNIPOLAR PZA 58.25 12
11 DISYUNTORES DE 40 AMP UNIPOLAR PZA 107.82 1
12 DISYUNTORES DE 40 AMP BIPOLAR PZA 107.82 1
13 DISYUNTOR TRIFASICO DE 80 AMP PZA 346.27 1
14 LUMINARIA DE EMERGENCIA PTO 129.38 46
15 TOMACORRIENTE DOBLE PTO 103.73 146
16 TOMACORRIENTE CON TIERRA PTO 135.59 27
17 SENSOR DE MOVIMIENTO TIPO TECHO PZA 223.11 38
18 SENSOR DE MOVIMIENTO TIPO PARED PZA 218.39 1
19 CAMARA DE SEGURIDAD PZA 494.30 10
20 DVR PARA CAMARAS PZA 1508.20 1
21 TOMA TELEFONICA PTO 151.84 8
22 TOMA DE RED PZA 439.57 35
23 HAP DE SALIDAS PZA 529.90 1

5
Proyecto: "CONSTRUCCIÓN EDIFICIO CARRERA DE MINAS UNSXX" PLAZO DE EJE
UBICACIÓN: FACULTAD DE TECNOLOGIA CARRETERA CATAVI
BENEFICIARIO: CARRERA DE INGENIERIA DE MINAS DE LA UNSXX MONTO CONTRATO:
MONTO CONTRATO MODIFIC
Nº P/UNIT CONTRATO O
Nº DESCRIPCION DEL ITEM UNID.
ITEM BS, V. Contrato

24 CAJA DE BARRAS PARA 4 BARRAS PZA 2829.08 4


25 MEDIDOR MONOFASICO PZA 866.12 1
26 MEDIDOR TRIFASICO PZA 4131.82 1
27 CAJA DE DISTRIBUCION DE CIRCUITOS ESPECIALES PZA 131.92 4
28 BOMBA DE AGUA DE 2 HP PZA 5316.48 1
29 JABALINA PARA TIERRA PZA 1242.95 8
30 PARARAYO FRANKLIN PZA 20776.79 1
31 JABALINA PARA PARARAYO 5/8" DE 2,5M PZA 8702.55 8
32 TRANSFORMADOR TRIFASICO DE 50 KVA TIPO MOCHILA PZA 94040.52 1
33 CABLE # 1 MCM ML 33.71 70
34 CABLE # 6 AWG ML 22.61 25
35 CABLE # 8 AWG ML 18.71 50

6
Proyecto: "CONSTRUCCIÓN EDIFICIO CARRERA DE MINAS UNSXX" PLAZO DE EJE
UBICACIÓN: FACULTAD DE TECNOLOGIA CARRETERA CATAVI
BENEFICIARIO: CARRERA DE INGENIERIA DE MINAS DE LA UNSXX MONTO CONTRATO:
MONTO CONTRATO MODIFIC
Nº P/UNIT CONTRATO O
Nº DESCRIPCION DEL ITEM UNID.
ITEM BS, V. Contrato

11 (M11) - NUEVOS ITEMS


1 CIMIENTOS DE HºCº R=210KG/CM2 (%P.DESPLAZADOR) M3 820.98
2 RELLENADO Y COMPACTADO C/PROV. Y EQUIP. M3 179.73
3 DINTEL DE LADRILLO ARMADO ML 72.38

TOTAL SEGÚN CONTRATO


FIRMAS AUTORIZADAS

POR

7
CERTIFICADO DE CONTRATO MODIFICADO
DE EJECUCION: 354 dias calendario

6983219.46 Bs.
MODIFICATORIO: 78069.87 Bs.
NTRATO ORIGINAL AVANCE DE OBRA

P.Contrato EJECUTADO FALTANTES TOTAL REAJUSTADO

Bs.- CANTIDAD IMPORTE CANTIDAD IMPORTE CANTIDAD IMPORTE

11348.33 11348.33 0.00 11348.33


8204.98 1.00 8204.98 0.00 1.00 8204.98
3143.35 1.00 3143.35 0.00 1.00 3143.35

3233379.96 2221490.18 13366.19 2234856.37


3172.43 313.79 3172.43 0.00 313.79 3172.43
47362.48 536.26 47362.48 0.00 536.26 47362.48
8080.09 176.14 4535.61 0.00 176.14 4535.61
10398.45 296.59 10398.45 0.00 296.59 10398.45
10839.28 15.69 10839.28 0.00 15.69 10839.28
542476.44 231.82 538158.54 0.00 231.82 538158.54
47449.71 31.68 45195.64 0.00 31.68 45195.64
194621.65 44.61 140259.64 1.74 5470.79 46.35 145730.43
392756.85 95.95 254302.04 0.00 95.95 254302.04
437461.02 636.45 313006.11 0.00 636.45 313006.11
135121.57 310.83 98275.12 0.00 310.83 98275.12
65637.12 0.97 2882.21 0.00 0.97 2882.21
71197.20 16.28 36007.78 0.00 16.28 36007.78
80297.76 18.27 48625.79 0.00 18.27 48625.79
36672.70 0 0.00 0.00 0.00 0.00
1149835.22 45,536.04 668469.07 26.40 387.55 45,562.44 668856.62
0.00 0.00 7.72 7507.85 7.72 7507.85

114248.11 0.00 0.00 0.00


104629.72 0.00 0.00 0.00 0.00
7314.23 0.00 0.00 0.00 0.00
2304.15 0.00 0.00 0.00 0.00

72239.14 0.00 0.00 0.00


40072.38 0.00 0.00 0.00 0.00
7476.90 0.00 0.00 0.00 0.00
18512.20 0.00 0.00 0.00 0.00
6177.66 0.00 0.00 0.00 0.00
0.00
50388.85 35187.79 1801.38 36989.17
3754.15 38.52 2126.30 0.00 38.52 2126.30

8
DE EJECUCION: 354 dias calendario

6983219.46 Bs.
MODIFICATORIO: 78069.87 Bs.
NTRATO ORIGINAL AVANCE DE OBRA

P.Contrato EJECUTADO FALTANTES TOTAL REAJUSTADO

Bs.- CANTIDAD IMPORTE CANTIDAD IMPORTE CANTIDAD IMPORTE

894.72 0.00 0.00 0.00 0.00


1077.71 0.78 538.86 0.00 0.78 538.86
30929.70 8.68 23005.12 0.00 8.68 23005.12
10156.36 613.22 9002.07 122.71 1801.38 735.93 10803.45
515.45 0.53 515.44 0.00 0.53 515.44
2225.47 0.00 0.00 0.00 0.00
835.30 0.00 0.00 0.00 0.00

35838.72 0.00 0.00 0.00


1480.57 0.00 0.00 0.00 0.00
445.46 0.00 0.00 0.00 0.00
656.65 0.00 0.00 0.00 0.00
690.41 0.00 0.00 0.00 0.00
1256.98 0.00 0.00 0.00 0.00
332.42 0.00 0.00 0.00 0.00
854.53 0.00 0.00 0.00 0.00
1002.24 0.00 0.00 0.00 0.00
1144.21 0.00 0.00 0.00 0.00
884.56 0.00 0.00 0.00 0.00
377.37 0.00 0.00 0.00 0.00
812.46 0.00 0.00 0.00 0.00
823.90 0.00 0.00 0.00 0.00
1373.44 0.00 0.00 0.00 0.00
6773.15 0.00 0.00 0.00 0.00
3144.16 0.00 0.00 0.00 0.00
12210.72 0.00 0.00 0.00 0.00
361.75 0.00 0.00 0.00 0.00
216.36 0.00 0.00 0.00 0.00
997.39 0.00 0.00 0.00 0.00

62329.04 0.00 0.00 0.00


1190.87 0.00 0.00 0.00 0.00
2269.82 0.00 0.00 0.00 0.00
662.65 0.00 0.00 0.00 0.00
2980.99 0.00 0.00 0.00 0.00
964.24 0.00 0.00 0.00 0.00
1141.92 0.00 0.00 0.00 0.00
92.62 0.00 0.00 0.00 0.00

9
DE EJECUCION: 354 dias calendario

6983219.46 Bs.
MODIFICATORIO: 78069.87 Bs.
NTRATO ORIGINAL AVANCE DE OBRA

P.Contrato EJECUTADO FALTANTES TOTAL REAJUSTADO

Bs.- CANTIDAD IMPORTE CANTIDAD IMPORTE CANTIDAD IMPORTE

2735.58 0.00 0.00 0.00 0.00


12257.25 0.00 0.00 0.00 0.00
6218.63 0.00 0.00 0.00 0.00
706.67 0.00 0.00 0.00 0.00
4953.54 0.00 0.00 0.00 0.00
16733.67 0.00 0.00 0.00 0.00
9420.61 0.00 0.00 0.00 0.00

3552.81 0.00 0.00 0.00


3552.81 0.00 0.00 0.00 0.00

3033789.89 34085.95 9226.38 43312.33


1378.80 0.00 0.70 31.84 0.70 31.84
424073.59 240.72 34085.95 12.88 1823.81 253.60 35909.76
134747.08 0.00 3.36 305.49 3.36 305.49
56530.32 0.00 0.00 0.00 0.00
80597.76 0.00 1.65 239.18 1.65 239.18
80225.24 0.00 0.00 0.00 0.00
241551.56 0.00 0.00 0.00 0.00
52044.48 0.00 0.00 0.00 0.00
62238.96 0.00 0.00 0.00 0.00
5678.68 0.00 0.00 0.00 0.00
27023.70 0.00 0.00 0.00 0.00
24952.83 0.00 0.00 0.00 0.00
53803.20 0.00 0.00 0.00 0.00
39112.96 0.00 0.00 0.00 0.00
22123.75 0.00 0.00 0.00 0.00
94342.32 0.00 11.86 1351.33 11.86 1351.33
134111.16 0.00 0.00 0.00 0.00
181988.64 0.00 0.00 0.00 0.00
94932.48 0.00 0.00 0.00 0.00
216923.04 0.00 0.00 0.00 0.00
3948.66 0.00 0.00 0.00 0.00
60302.88 0.00 0.00 0.00 0.00
100427.20 0.00 0.00 0.00 0.00
34793.60 0.00 13.72 364.40 13.72 364.40
66641.09 0.00 4.90 796.05 4.90 796.05
39758.37 0.00 0.00 0.00 0.00

10
DE EJECUCION: 354 dias calendario

6983219.46 Bs.
MODIFICATORIO: 78069.87 Bs.
NTRATO ORIGINAL AVANCE DE OBRA

P.Contrato EJECUTADO FALTANTES TOTAL REAJUSTADO

Bs.- CANTIDAD IMPORTE CANTIDAD IMPORTE CANTIDAD IMPORTE

83652.38 0.00 2.17 2012.48 2.17 2012.48


55449.16 0.00 0.00 0.00 0.00

11
DE EJECUCION: 354 dias calendario

6983219.46 Bs.
MODIFICATORIO: 78069.87 Bs.
NTRATO ORIGINAL AVANCE DE OBRA

P.Contrato EJECUTADO FALTANTES TOTAL REAJUSTADO

Bs.- CANTIDAD IMPORTE CANTIDAD IMPORTE CANTIDAD IMPORTE

90163.80 0.00 2.48 1515.97 2.48 1515.97


170679.01 0.00 0.00 0.00 0.00
105069.27 0.00 0.00 0.00 0.00
18120.24 0.00 0.00 0.00 0.00
8645.20 0.00 0.00 0.00 0.00
7016.78 0.00 0.00 0.00 0.00
4069.76 0.00 0.00 0.00 0.00
6267.80 0.00 0.00 0.00 0.00
39920.90 0.00 3.74 785.81 3.74 785.81
4468.96 0.00 0.00 0.00 0.00
1163.46 0.00 0.00 0.00 0.00
102102.00 0.00 0.00 0.00 0.00
2748.82 0.00 0.00 0.00 0.00

366104.61 0.00 0.00 0.00


75910.56 0.00 0.00 0.00 0.00
485.61 0.00 0.00 0.00 0.00
367.92 0.00 0.00 0.00 0.00
4668.84 0.00 0.00 0.00 0.00
978.80 0.00 0.00 0.00 0.00
1076.68 0.00 0.00 0.00 0.00
1157.60 0.00 0.00 0.00 0.00
255.85 0.00 0.00 0.00 0.00
2507.33 0.00 0.00 0.00 0.00
699.00 0.00 0.00 0.00 0.00
107.82 0.00 0.00 0.00 0.00
107.82 0.00 0.00 0.00 0.00
346.27 0.00 0.00 0.00 0.00
5951.48 0.00 0.00 0.00 0.00
15144.58 0.00 0.00 0.00 0.00
3660.93 0.00 0.00 0.00 0.00
8478.18 0.00 0.00 0.00 0.00
218.39 0.00 0.00 0.00 0.00
4943.00 0.00 0.00 0.00 0.00
1508.20 0.00 0.00 0.00 0.00
1214.72 0.00 0.00 0.00 0.00
15384.95 0.00 0.00 0.00 0.00
529.90 0.00 0.00 0.00 0.00

12
DE EJECUCION: 354 dias calendario

6983219.46 Bs.
MODIFICATORIO: 78069.87 Bs.
NTRATO ORIGINAL AVANCE DE OBRA

P.Contrato EJECUTADO FALTANTES TOTAL REAJUSTADO

Bs.- CANTIDAD IMPORTE CANTIDAD IMPORTE CANTIDAD IMPORTE

11316.32 0.00 0.00 0.00 0.00


866.12 0.00 0.00 0.00 0.00
4131.82 0.00 0.00 0.00 0.00
527.68 0.00 0.00 0.00 0.00
5316.48 0.00 0.00 0.00 0.00
9943.60 0.00 0.00 0.00 0.00
20776.79 0.00 0.00 0.00 0.00
69620.40 0.00 0.00 0.00 0.00
94040.52 0.00 0.00 0.00 0.00
2359.70 0.00 0.00 0.00 0.00
565.25 0.00 0.00 0.00 0.00
935.50 0.00 0.00 0.00 0.00

13
DE EJECUCION: 354 dias calendario

6983219.46 Bs.
MODIFICATORIO: 78069.87 Bs.
NTRATO ORIGINAL AVANCE DE OBRA

P.Contrato EJECUTADO FALTANTES TOTAL REAJUSTADO

Bs.- CANTIDAD IMPORTE CANTIDAD IMPORTE CANTIDAD IMPORTE

0.00 0.00 53675.92 53675.92


0.00 0 0.00 12.28 10081.63 12.28 10081.63
0.00 0 0.00 216.7 38947.49 216.70 38947.49
0.00 0 0.00 64.2 4646.80 64.20 4646.80

6983219.46 2302112.25 78069.87 2380182.12


CUADRO
(M01) - OBRAS INICIALES
(M02) - ESTRUCTURA HºAº
(M03) - ESTRUCTURA CUBIERTA
(M04) - ESTRUCTURA CASCO
(M05) - ESTRUCTURA TANQUE BAJO
(M06) - INSTALACION AGUA POTABLE
(M07) - DESAGUE SANITARIO Y PLUVIAL
(M08) - OBRAS FINALES
(M09) - ARQUITECTONICO
(M10) - ELECTRICO
(M11) - NUEVOS ITEMS
SUBTOTAL ORDEN DE CAMBIO
SUBTOTAL ITEMS ADICIONALES
TOTAL ORDENES DE CAMBIO Y NUEVOS ITEMS
TOTAL CONTRATO MODIFICADO (Bs)
Son: Siete millones cincuenta cinco mil ochocientos d

PORCENTAJE DE EJECUCION MODIFICADO

14
MONTO EJECUTADO 2302112.25
HOJA Nº

% DE SALDOS

AVANCE
CANTIDAD MONTO BS.-
0.00

0.00
100.00 0.00 0.00
100.00 0.00 0.00

1018684.00
100.00 0.00 0.00
100.00 0.00 0.00
56.13 137.65 3544.49
100.00 0.00 0.00
100.00 0.00 0.00
99.20 0.00 0.00
95.25 0.00 0.00
74.88 19.03 59832.79
64.75 52.24 138454.81
71.55 253.06 124454.91
72.73 116.54 36846.45
4.39 21.12 62754.91
50.57 15.91 35189.42
60.56 11.90 31671.97
0.00 14.68 36672.70
58.17 32,817.01 481753.71
100.00 7.72 7507.85

114248.11
0.00 290.38 104629.72
0.00 16.00 7314.23
0.00 21.43 2304.15

72239.14
0.00 1.00 40072.38
0.00 6.00 7476.90
0.00 51.36 18512.20
0.00 6.00 6177.66

17002.44
56.64 29.49 1627.85

15
MONTO EJECUTADO 2302112.25
HOJA Nº

% DE SALDOS

AVANCE
CANTIDAD MONTO BS.-
0.00

0.00 28.18 894.72


50.00 0.78 538.86
74.38 2.99 7924.58
106.37 201.34 2955.67
100.00 0.00 0.01
0.00 6.09 2225.47
0.00 2.00 835.30

35838.72
0.00 258.39 1480.57
0.00 8.07 445.46
0.00 8.06 656.65
0.00 27.43 690.41
0.00 70.34 1256.98
0.00 31.42 332.42
0.00 104.85 854.53
0.00 7.69 1002.24
0.00 16.66 1144.21
0.00 2.00 884.56
0.00 1.00 377.37
0.00 6.00 812.46
0.00 7.00 823.90
0.00 16.00 1373.44
0.00 1.00 6773.15
0.00 1.00 3144.16
0.00 1.00 12210.72
0.00 258.39 361.75
0.00 18.00 216.36
0.00 258.39 997.39

62329.04
0.00 207.83 1190.87
0.00 41.12 2269.82
0.00 5.03 662.65
0.00 36.59 2980.99
0.00 17.00 964.24
0.00 16.00 1141.92
0.00 1.00 92.62

16
MONTO EJECUTADO 2302112.25
HOJA Nº

% DE SALDOS

AVANCE
CANTIDAD MONTO BS.-
0.00

0.00 64.05 2735.58


0.00 143.78 12257.25
0.00 11.00 6218.63
0.00 1.00 706.67
0.00 44.80 4953.54
0.00 164.88 16733.67
0.00 89.96 9420.61

3552.81
0.00 1.00 3552.81

3008930.32
2.31 31.01 1410.64
8.47 2,767.03 391811.45
0.23 1,485.40 135052.57
0.00 399.00 56530.32
0.30 557.65 80836.94
0.00 556.00 80225.24
0.00 1,674.07 241551.56
0.00 1,224.00 52044.48
0.00 233.00 62238.96
0.00 119.00 5678.68
0.00 47.50 27023.70
0.00 43.86 24952.83
0.00 48.00 53803.20
0.00 119.78 39112.96
0.00 126.82 22123.75
1.43 839.86 95693.65
0.00 828.00 134111.16
0.00 1,854.00 181988.64
0.00 1,504.00 94932.48
0.00 3,492.00 216923.04
0.00 70.60 3948.66
0.00 243.00 60302.88
0.00 3,680.00 100427.20
1.05 1,323.72 35158.00
1.19 415.10 67437.15
0.00 42.85 39758.37

17
MONTO EJECUTADO 2302112.25
HOJA Nº

% DE SALDOS

AVANCE
CANTIDAD MONTO BS.-
0.00

2.41 92.37 85664.86


0.00 58.00 55449.16

18
MONTO EJECUTADO 2302112.25
HOJA Nº

% DE SALDOS

AVANCE
CANTIDAD MONTO BS.-
0.00

1.68 149.98 91679.77


0.00 339.91 170679.01
0.00 141.30 105069.27
0.00 18.00 18120.24
0.00 10.00 8645.20
0.00 2.00 7016.78
0.00 8.00 4069.76
0.00 5.00 6267.80
1.97 193.74 40706.71
0.00 17.00 4468.96
0.00 1.00 1163.46
0.00 1,300.00 102102.00
0.00 1.00 2748.82

366104.61
0.00 264.00 75910.56
0.00 3.00 485.61
0.00 4.00 367.92
0.00 54.00 4668.84
0.00 10.00 978.80
0.00 11.00 1076.68
0.00 5.00 1157.60
0.00 5.00 255.85
0.00 49.00 2507.33
0.00 12.00 699.00
0.00 1.00 107.82
0.00 1.00 107.82
0.00 1.00 346.27
0.00 46.00 5951.48
0.00 146.00 15144.58
0.00 27.00 3660.93
0.00 38.00 8478.18
0.00 1.00 218.39
0.00 10.00 4943.00
0.00 1.00 1508.20
0.00 8.00 1214.72
0.00 35.00 15384.95
0.00 1.00 529.90

19
MONTO EJECUTADO 2302112.25
HOJA Nº

% DE SALDOS

AVANCE
CANTIDAD MONTO BS.-
0.00

0.00 4.00 11316.32


0.00 1.00 866.12
0.00 1.00 4131.82
0.00 4.00 527.68
0.00 1.00 5316.48
0.00 8.00 9943.60
0.00 1.00 20776.79
0.00 8.00 69620.40
0.00 1.00 94040.52
0.00 70.00 2359.70
0.00 25.00 565.25
0.00 50.00 935.50

20
MONTO EJECUTADO 2302112.25
HOJA Nº

% DE SALDOS

AVANCE
CANTIDAD MONTO BS.-
0.00

53675.92
100.00 12.28 10081.63
100.00 216.70 38947.49
100.00 64.20 4646.80

1.12 4752605.11
CUADRO RESUMEN
0.00
13366.19
0.00
0.00
1801.38
0.00
0.00
0.00
9226.38
0.00
53675.92

78069.87
4752605.11
nes cincuenta cinco mil ochocientos diez y ocho 55/100 Bs,