Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
PRESUPUESTO ( Bs/. ) CONTRATO MODIFICADO AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO ACTUAL
ITEM DESCRIPCION
UNIDAD METRADO C.U. PRESUPUESTO METRADO MONTO METRADO PARCIAL %DE AVANCE METRADO PARCIAL %DE AVANCE METRADO PARCIAL %DE AVANCE METRADO PARCIAL %DE AVANCE
:CONSTRUCCIÓN EDIFICIO ACADÉMICO CARRERA INGENIRÍA DE MINAS UNS XX 6,983,219.46 0.00 2,232,838.51 31.97% 0.00 0.00% 2,302,112.25 32.97% 4,681,107.21 67.03%
> OBRAS INICIALES 11,348.33 0.00 11,348.33 100.00% 0.00 0.00% 11,348.33 100.00% 0.00 0.00%
1 INSTALACION DE FAENAS GLB 1.00 8,204.98 8,204.98 - 0.00 1.00 8,204.98 100.00% - - 0.00% 1.00 8,204.98 100.00% 0.00 0.00 0.00%
2 LETRERO DE OBRA PZA 1.00 3,143.35 3,143.35 - 0.00 1.00 3,143.35 100.00% - - 0.00% 1.00 3,143.35 100.00% 0.00 0.00 0.00%
> ESTRUCTURA HºAº 3,233,379.96 0.00 2,221,490.18 68.70% 0.00 0.00% 0.00 2,221,490.18 68.70% 1,011,889.78 31.30%
3 REPLANTEO Y TRAZADO M2 313.79 10.11 3,172.42 - 0.00 313.79 3,172.42 100.00% - - 0.00% 313.79 3,172.42 100.00% 0.00 0.00 0.00%
4 EXCAVACION 0-2 M TERRENO DURO M3 536.26 88.32 47,362.48 - 0.00 536.26 47,362.48 100.00% - 0.00% 536.26 47,362.48 100.00% 0.00 0.00 0.00%
5 SOLADURA DE PIEDRA MANZANA M2 313.79 25.75 8,080.09 - 0.00 176.14 4,535.61 56.13% - - 0.00% 176.14 4,535.61 56.13% 137.65 3,544.48 43.87%
6 RELLENO Y COMPACTADO C/EQUIPO MATERIAL COMUN M3 296.59 35.06 10,398.45 0.00 296.59 10,398.45 100.00% - 0.00% 296.59 10,398.45 100.00% 0.00 0.00 0.00%
7 HORMIGON POBRE E=5CM M3 15.69 690.84 10,839.28 - 0.00 15.69 10,839.28 100.00% - - 0.00% 15.69 10,839.28 100.00% 0.00 0.00 0.00%
8 HºSº ZAPATAS R=210KG/CM2 M3 233.68 2,321.45 542,476.44 - 0.00 231.82 538,158.54 99.20% - - 0.00% 231.82 538,158.54 99.20% 1.86 4,317.90 0.80%
9 HºSº VIGAS DE ARRIOSTRE R=210KG/CM2 M3 33.26 1,426.63 47,449.71 - 0.00 31.68 45,195.64 95.25% - - 0.00% 31.68 45,195.64 95.25% 1.58 2,254.07 4.75%
10 HºSº COLUMNAS R=210KG/CM2 M3 61.90 3,144.13 194,621.65 - 0.00 44.61 140,259.64 72.07% - 0.00% 44.61 140,259.64 72.07% 17.29 54,362.01 27.93%
11 HºSº VIGAS R=210KG/CM2 M3 148.19 2,650.36 392,756.85 - 0.00 95.95 254,302.04 64.75% - - 0.00% 95.95 254,302.04 64.75% 52.24 138,454.81 35.25%
12 HºSº LOSA C/VIGUETAS IN SITU 2 DIREC R=210KG/CM2 M2 889.51 491.80 437,461.02 - 0.00 636.45 313,006.11 71.55% - - 0.00% 636.45 313,006.11 71.55% 253.06 124,454.91 28.45%
13 HºSº LOSA C/VIGUETAS IN SITU 1 DIREC R=210KG/CM2 M2 427.37 316.17 135,121.57 - 0.00 310.83 98,275.12 72.73% - - 0.00% 310.83 98,275.12 72.73% 116.54 36,846.45 27.27%
14 HºSº LOSA LLENA R=210KG/CM2 M3 22.09 2,971.35 65,637.12 - 0.00 0.97 2,882.21 4.39% - - 0.00% 0.97 2,882.21 4.39% 21.12 62,754.91 95.61%
15 HºSº MURO CAJA DE ASCENSOR M3 32.19 2,211.78 71,197.20 - 0.00 16.28 36,007.78 50.57% - - 0.00% 16.28 36,007.78 50.57% 15.91 35,189.42 49.43%
16 HºSº ESCALERAS R=210KG/CM2 M3 30.17 2,661.51 80,297.76 - 0.00 18.27 48,625.79 60.56% - - 0.00% 18.27 48,625.79 60.56% 11.90 31,671.97 39.44%
17 HºSº MUROS DE PARAPETO R=210KG/CM2 M3 14.68 2,498.14 36,672.70 - 0.00 - - 0.00% - - 0.00% - - 0.00% 14.68 36,672.70 100.00%
18 ACERO ESTRUCTURAL FY= 5000 KG/CM2 KG 78,326.65 14.68 1,149,835.22 - 0.00 45,536.04 668,469.07 58.14% - - 0.00% 45,536.04 668,469.07 58.14% 32,790.61 481,366.15 41.86%
> ESTRUCTURA CUBIERTA 114,248.11 0.00 - 0.00% 0.00 0.00% 0.00 0.00% 114,248.11 100.00%
1 CUBIERTA CHAPA TRAPEZOIDAL C/ESTRUC. METALICA M2 290.38 360.32 104,629.72 - 0.00 0.00% - - 0.00% 290.38 104,629.72 100.00%
2 ANCLAJE PARA CERCHA METALICA PZA 16.00 457.14 7,314.23 - 0.00 0.00% - - 0.00% 16.00 7,314.23 100.00%
3 CUMBRERA DE CALAMINA CHAPA TRAPEZOIDAL ML 21.43 107.52 2,304.15 - 0.00 0.00% - - 0.00% 21.43 2,304.15 100.00%
> ESTRUCTURA CASCO 72,239.14 0.00 - 0.00% 0.00 0.00% 0.00 0.00% 72,239.14 100.00%
1 ESTRUCTURA METALICA P/CASCO GLB 1.00 40,072.38 40,072.38 - 0.00 0.00% - - 0.00% 1.00 40,072.38 100.00%
2 COLUMNA METALICA TUBO REDONDO 200X50MM PZA 6.00 1,246.15 7,476.90 - 0.00 0.00% - - 0.00% 6.00 7,476.90 100.00%
3 PROTECTORES PLANCHA E= 0.75 MM CASCO M2 51.36 360.44 18,512.20 - 0.00 0.00% - - 0.00% 51.36 18,512.20 100.00%
4 ANCLAJE PARA COLUMNA METALICA PZA 6.00 1,029.61 6,177.66 - 0.00 0.00% - - 0.00% 6.00 6,177.66 100.00%
> ESTRUCTURA TANQUE BAJO 50,388.85 0.00 35,187.79 69.83% 0.00 0.00% 35,187.79 69.83% 15,201.06 30.17%
1 EXCAVACION 0-2 M TERRENO DURO M3 68.01 55.20 3,754.15 - 0.00 38.52 2,126.30 56.64% - - 0.00% 38.52 2,126.30 56.64% 29.49 1,627.85 43.36%
2 RELLENO Y COMPACTADO C/EQUIPO MATERIAL COMUN M3 28.18 31.75 894.72 - 0.00 - 0.00% - - 0.00% - 0.00 0.00% 28.18 894.72 100.00%
3 HORMIGON POBRE E=5CM M3 1.56 690.84 1,077.71 - 0.00 0.78 538.86 50.00% - - 0.00% 0.78 538.86 50.00% 0.78 538.85 50.00%
4 HORMIGON SIMPLE R=210KG/CM2 M3 11.67 2,650.36 30,929.70 - 0.00 8.68 23,005.12 74.38% - - 0.00% 8.68 23,005.12 74.38% 2.99 7,924.58 25.62%
5 ACERO ESTRUCTURAL FY= 5000 KG/CM2 KG 691.85 14.68 10,156.36 - 0.00 613.22 9,002.07 88.63% - - 0.00% 613.22 9,002.07 88.63% 78.63 1,154.29 11.37%
6 HORMIGON CICLOPEO R=210KG/CM2 (50%P. DESPLAZADORA) M3 0.53 972.52 515.45 - 0.00 0.53 515.44 100.00% - - 0.00% 0.53 515.44 100.00% 0.00 0.01 0.00%
7 MURO PORTANTE VISTO E=20CM (LADRILLO GAMBOTE) M2 6.09 365.43 2,225.47 - 0.00 - 0.00% - - 0.00% - 0.00 0.00% 6.09 2,225.47 100.00%
8 PROV. Y COL. TAPA METALICA PZA 2.00 417.65 835.30 - 0.00 - 0.00% - - 0.00% - 0.00 0.00% 2.00 835.30 100.00%
> INSTALACION AGUA POTABLE 35,838.72 0.00 - 0.00% 0.00 0.00% 0.00 0.00% 35,838.72 100.00%
1 REPLANTEO Y CONTROL LINEAS DE TUBERIA ML 258.39 5.73 1,480.57 - 0.00 0.00% 0.00% 258.39 1,480.57 100.00%
2 EXCAVACION 0-2 M TERRENO DURO M3 8.07 55.20 445.46 - 0.00 0.00% 0.00% 8.07 445.46 100.00%
3 RELLENO MANUAL C/TIERRA CERNIDA (S/MAT) M3 8.06 81.47 656.65 - 0.00 0.00% 0.00% 8.06 656.65 100.00%
4 PROV. Y TEND. TUBERIA PVC ESQ. 40 D=1 1/2" ML 27.43 25.17 690.41 - 0.00 0.00% 0.00% 27.43 690.41 100.00%
5 PROV. Y TEND. TUBERIA PVC ESQ. 40 D=1" ML 70.34 17.87 1,256.98 - 0.00 0.00% 0.00% 70.34 1,256.98 100.00%
6 PROV. Y TEND. TUBERIA PVC ESQ. 40 D=3/4" ML 31.42 10.58 332.42 - 0.00 0.00% 0.00% 31.42 332.42 100.00%
7 PROV. Y TEND. TUBERIA PVC ESQ. 40 D=1/2" ML 104.85 8.15 854.53 - 0.00 0.00% 0.00% 104.85 854.53 100.00%
8 PROV. Y TEND. TUBERIA F.G. D=2" ML 7.69 130.33 1,002.24 - 0.00 0.00% 0.00% 7.69 1,002.24 100.00%
9 PROV. Y TEND. TUBERIA F.G. D=1 1/2" ML 16.66 68.68 1,144.21 - 0.00 0.00% 0.00% 16.66 1,144.21 100.00%
10 PROV. Y COL. LLAVE DE PASO D=2" PZA 2.00 442.28 884.56 - 0.00 0.00% 0.00% 2.00 884.56 100.00%
11 PROV. Y COL. LLAVE DE PASO D=1 1/2" PZA 1.00 377.37 377.37 - 0.00 0.00% 0.00% 1.00 377.37 100.00%
12 PROV. Y COL. LLAVE DE PASO D=1" PZA 6.00 135.41 812.46 - 0.00 0.00% 0.00% 6.00 812.46 100.00%
13 PROV. Y COL. LLAVE DE PASO D=3/4" PZA 7.00 117.70 823.90 - 0.00 0.00% 0.00% 7.00 823.90 100.00%
14 PROV. Y COL. LLAVE DE PASO D=1/2" PZA 16.00 85.84 1,373.44 - 0.00 0.00% 0.00% 16.00 1,373.44 100.00%
UNIVERSIDAD NACIONAL SIGLO XX
PRESUPUESTO ( Bs/. ) CONTRATO MODIFICADO AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO ACTUAL
ITEM DESCRIPCION
UNIDAD METRADO C.U. PRESUPUESTO METRADO MONTO METRADO PARCIAL %DE AVANCE METRADO PARCIAL %DE AVANCE METRADO PARCIAL %DE AVANCE METRADO PARCIAL %DE AVANCE
15 PROV. Y COL. EQUIPO DE BOMBEO GLB 1.00 6,773.15 6,773.15 - 0.00 0.00% 0.00% 1.00 6,773.15 100.00%
16 ACCESORIOS E INSTALACIONES TANQUE BAJO GLB 1.00 3,144.16 3,144.16 - 0.00 0.00% 0.00% 1.00 3,144.16 100.00%
17 PROV. Y COL. TANQUE ELEVADO PREFABRICADO GLB 1.00 12,210.72 12,210.72 - 0.00 0.00% 0.00% 1.00 12,210.72 100.00%
18 DESINFECCION DE TUBERIAS ML 258.39 1.40 361.75 - 0.00 0.00% 0.00% 258.39 361.75 100.00%
19 DESINFECCION DE TANQUE BAJO M3 18.00 12.02 216.36 - 0.00 0.00% 0.00% 18.00 216.36 100.00%
20 PRUEBA HIDRAULICA ML 258.39 3.86 997.39 - 0.00 0.00% 0.00% 258.39 997.39 100.00%
> DESAGUE SANITARIO Y PLUVIAL 62,329.04 0.00 - 0.00% 0.00 0.00% 0.00 0.00% 62,329.04 100.00%
1 REPLANTEO Y CONTROL LINEAS DE TUBERIA ML 207.83 5.73 1,190.87 - 0.00 0.00% 0.00% 207.83 1,190.87 100.00%
2 EXCAVACION 0-2 M TERRENO DURO M3 41.12 55.20 2,269.82 - 0.00 0.00% 0.00% 41.12 2,269.82 100.00%
3 ASIENTO PARA TUBERIAS CAMA DE ARENA M3 5.03 131.74 662.65 - 0.00 0.00% 0.00% 5.03 662.65 100.00%
4 RELLENO MANUAL C/TIERRA CERNIDA (S/MAT) M3 36.59 81.47 2,980.99 - 0.00 0.00% 0.00% 36.59 2,980.99 100.00%
5 PROV. Y COL. REJILLA DE PISO PZA 17.00 56.72 964.24 - 0.00 0.00% 0.00% 17.00 964.24 100.00%
6 PROV. Y COL. CAJA INTERCEPTORA PZA 16.00 71.37 1,141.92 - 0.00 0.00% 0.00% 16.00 1,141.92 100.00%
7 PROV. Y COL. CAJA DESGRASADORA PZA 1.00 92.62 92.62 - 0.00 0.00% 0.00% 1.00 92.62 100.00%
8 PROV. Y COL. TUBO DESAGUE PVC D=2" ML 64.05 42.71 2,735.58 - 0.00 0.00% 0.00% 64.05 2,735.58 100.00%
9 PROV. Y COL. TUBO DESAGUE PVC D=4" ML 143.78 85.25 12,257.25 - 0.00 0.00% 0.00% 143.78 12,257.25 100.00%
10 CAMARA INSPECCION HºCº SENCILLA H<1M PZA 11.00 565.33 6,218.63 - 0.00 0.00% 0.00% 11.00 6,218.63 100.00%
11 CAMARA INSPECCION HºCº SENCILLA H>1M PZA 1.00 706.67 706.67 - 0.00 0.00% 0.00% 1.00 706.67 100.00%
12 PROV. Y COL. CANALETA 10X10CM ACERO GALVANIZADO ML 44.80 110.57 4,953.54 - 0.00 0.00% 0.00% 44.80 4,953.54 100.00%
13 PROV. Y COL. BAJANTE PLUVIAL PVC D=4" ML 164.88 101.49 16,733.67 - 0.00 0.00% 0.00% 164.88 16,733.67 100.00%
14 PROV. Y COL. BAJANTE SANITARIA PVC D=4" ML 89.96 104.72 9,420.61 - 0.00 0.00% 0.00% 89.96 9,420.61 100.00%
> OBRAS FINALES 3,552.81 0.00 - 0.00% 0.00 0.00% 0.00 0.00% 3,552.81 100.00%
1 LIMPIEZA GENERAL Y RETIRO DE ESCOMBROS GLB 1 3552.81 3,552.81 - 0.00 1.00 3,552.81 100.00%
> ARQUITECTONICO 3,033,789.89 0.00 34,085.95 1.12% 0.00 0.00% 34,085.95 1.12% 2,999,703.94 98.88%
1 IMPERMEABILIZACION DE SOBRECIMIENTO M2 30.31 45.49 1,378.80 - 0.00 - 0.00% - 0.00 0.00% 30.31 1,378.80 100.00%
2 MURO LADRILLO CERAMICO 6 H E=15 CM. M2 2,994.87 141.60 424,073.59 - 0.00 240.72 34,085.95 8.04% 240.72 34,085.95 8.04% 2,754.15 389,987.64 91.96%
3 CONTRAPISO DE H° S/LOSA CARPETA E=3CM M2 1,482.04 90.92 134,747.08 - 0.00 - 0.00% - 0.00 0.00% 1,482.04 134,747.08 100.00%
4 CORDON DE ACERA H°S° 0,20X0,40 CM ML 399.00 141.68 56,530.32 - 0.00 - 0.00% - 0.00 0.00% 399.00 56,530.32 100.00%
5 EMPEDRADO Y CONTRAPISO DE HORMIGON PARA ACERA M2 556.00 144.96 80,597.76 - 0.00 - 0.00% - 0.00 0.00% 556.00 80,597.76 100.00%
6 PISO DE CERAMICA RUSTICA PARA ACERAS M2 556.00 144.29 80,225.24 - 0.00 - 0.00% - 0.00 0.00% 556.00 80,225.24 100.00%
7 PISO DE CERAMICA ESMALTADA DE ALTO TRAFICO M2 1,674.07 144.29 241,551.56 - 0.00 - 0.00% - 0.00 0.00% 1,674.07 241,551.56 100.00%
8 ZOCALO DE CERAMICA ESMALTADA ML 1,224.00 42.52 52,044.48 - 0.00 - 0.00% - 0.00 0.00% 1,224.00 52,044.48 100.00%
9 PISO DE PORCELANATO M2 233.00 267.12 62,238.96 - 0.00 - 0.00% - 0.00 0.00% 233.00 62,238.96 100.00%
10 ZOCALO DE PORCELANATO ML 119.00 47.72 5,678.68 - 0.00 - 0.00% - 0.00 0.00% 119.00 5,678.68 100.00%
11 PISO MACHIEMBRE CON ENVIGADO M2 47.50 568.92 27,023.70 - 0.00 - 0.00% - 0.00 0.00% 47.50 27,023.70 100.00%
12 TARIMA DE MACHIEMBRE M2 43.86 568.92 24,952.83 - 0.00 - 0.00% - 0.00 0.00% 43.86 24,952.83 100.00%
13 MESONES GRANITO EN LAVORATORIOS Y COCINETA ML 48.00 1,120.90 53,803.20 - 0.00 - 0.00% - 0.00 0.00% 48.00 53,803.20 100.00%
14 REVESTIMIENTO DE GRADAS CON GRANITO M2 119.78 326.54 39,112.96 - 0.00 - 0.00% - 0.00 0.00% 119.78 39,112.96 100.00%
15 ZOCALO DE MOSAICO GRANITICO ML 126.82 174.45 22,123.75 - 0.00 - 0.00% - 0.00 0.00% 126.82 22,123.75 100.00%
16 REVOQUE INTERIOR DE CEMENTO M2 828.00 113.94 94,342.32 - 0.00 - 0.00% - 0.00 0.00% 828.00 94,342.32 100.00%
17 REVESTIMIENTO DE CERAMICA S/MURO H=TOTAL M2 828.00 161.97 134,111.16 - 0.00 - 0.00% - 0.00 0.00% 828.00 134,111.16 100.00%
18 REV. EXTERIOR CAL CEMENTO M2 1,854.00 98.16 181,988.64 - 0.00 - 0.00% - 0.00 0.00% 1,854.00 181,988.64 100.00%
19 REVOQUE DE YESO BAJO LOSA M2 1,504.00 63.12 94,932.48 - 0.00 - 0.00% - 0.00 0.00% 1,504.00 94,932.48 100.00%
20 REVOQUE INTERIOR DE YESO SOBRE MURO M2 3,492.00 62.12 216,923.04 - 0.00 - 0.00% - 0.00 0.00% 3,492.00 216,923.04 100.00%
21 CIELO FALSO BAJO LOSA M2 70.60 55.93 3,948.66 - 0.00 - 0.00% - 0.00 0.00% 70.60 3,948.66 100.00%
22 CIELO FALSO ACUSTICO M2 243.00 248.16 60,302.88 - 0.00 - 0.00% - 0.00 0.00% 243.00 60,302.88 100.00%
23 PINTURA INTERIOR - LATEX M2 3,680.00 27.29 100,427.20 - 0.00 - 0.00% - 0.00 0.00% 3,680.00 100,427.20 100.00%
24 PINTURA EXTERIOR - LATEX M2 1,310.00 26.56 34,793.60 - 0.00 - 0.00% - 0.00 0.00% 1,310.00 34,793.60 100.00%
25 MARCOS DE MADERA PARA PUERTAS ML 410.20 162.46 66,641.09 - 0.00 - 0.00% - 0.00 0.00% 410.20 66,641.09 100.00%
26 PUERTA DE BAÑO TIPO CONTRAPLACA INC. QUINCALLERIA M2 42.85 927.85 39,758.37 - 0.00 - 0.00% - 0.00 0.00% 42.85 39,758.37 100.00%
27 PUERTA INTERIOR TIPO CONTRAPLACA INC. QUINCALLERIA M2 90.20 927.41 83,652.38 - 0.00 - 0.00% - 0.00 0.00% 90.20 83,652.38 100.00%
28 VIDRIO TEMPLADO 10MM M2 58.00 956.02 55,449.16 - 0.00 - 0.00% - 0.00 0.00% 58.00 55,449.16 100.00%
29 VENTANAS CARPINTERIA DE ALUMINIO PIEL DE VIDRIO M2 147.50 611.28 90,163.80 - 0.00 - 0.00% - 0.00 0.00% 147.50 90,163.80 100.00%
30 VENTANAS ALUMINIO CORREDIZAS VIDRIO 4MM INC. QUINC M2 339.91 502.13 170,679.01 - 0.00 - 0.00% - 0.00 0.00% 339.91 170,679.01 100.00%
UNIVERSIDAD NACIONAL SIGLO XX
PRESUPUESTO ( Bs/. ) CONTRATO MODIFICADO AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO ACTUAL
ITEM DESCRIPCION
UNIDAD METRADO C.U. PRESUPUESTO METRADO MONTO METRADO PARCIAL %DE AVANCE METRADO PARCIAL %DE AVANCE METRADO PARCIAL %DE AVANCE METRADO PARCIAL %DE AVANCE
31 BARANDA DE ALUMINIO H=1,10M CON VIDRIO E=8MM M2 141.30 743.59 105,069.27 - 0.00 - 0.00% - 0.00 0.00% 141.30 105,069.27 100.00%
32 PROV. E INST. INODORO PZA 18.00 1,006.68 18,120.24 - 0.00 - 0.00% - 0.00 0.00% 18.00 18,120.24 100.00%
33 PROV. E INST. DE LAVAMANOS C\ PEDESTAL PZA 10.00 864.52 8,645.20 - 0.00 - 0.00% - 0.00 0.00% 10.00 8,645.20 100.00%
34 PROV. Y COLOCADO DE DUCHAS PZA 2.00 3,508.39 7,016.78 - 0.00 - 0.00% - 0.00 0.00% 2.00 7,016.78 100.00%
35 PROVISION Y COLOCADO DE URINARIOS PZA 8.00 508.72 4,069.76 - 0.00 - 0.00% - 0.00 0.00% 8.00 4,069.76 100.00%
36 PROV. Y COL. LAVAPLATOS 1 DEPOSITO 1 FREGADERO PZA 5.00 1,253.56 6,267.80 - 0.00 - 0.00% - 0.00 0.00% 5.00 6,267.80 100.00%
37 IMPERMEABILIZACION DE LOSA M2 190.00 210.11 39,920.90 - 0.00 - 0.00% - 0.00 0.00% 190.00 39,920.90 100.00%
38 LETRAS DE ALUMINIO FUNDIDAS 40 X 22 CM PZA 17.00 262.88 4,468.96 - 0.00 - 0.00% - 0.00 0.00% 17.00 4,468.96 100.00%
39 PLACA DE ENTREGA DE OBRA PZA 1.00 1,163.46 1,163.46 - 0.00 - 0.00% - 0.00 0.00% 1.00 1,163.46 100.00%
40 AREAS VERDES Y JARDINERIA M2 1,300.00 78.54 102,102.00 - 0.00 - 0.00% - 0.00 0.00% 1,300.00 102,102.00 100.00%
41 LIMPIEZA Y RETIRO DE ESCOMBROS GLB 1.00 2,748.82 2,748.82 - 0.00 - 0.00% - 0.00 0.00% 1.00 2,748.82 100.00%
> ELECTRICO 366,104.61 0.00 - 0.00% 0.00 0.00% 0.00 0.00% 366,104.61 100.00%
1 ILUMINACION FLUORESCENTE (INCL. LUMIN. 2X40 W) PZA 264.00 287.54 75,910.56 - 0.00 0.00% 0.00% 264.00 75,910.56 100.00%
2 ILUMINACION INCANDECENTE 100 W PTO 3.00 161.87 485.61 - 0.00 0.00% 0.00% 3.00 485.61 100.00%
3 PROV. Y COLOC. DE INTERRUPTORES DOBLES PTO 4.00 91.98 367.92 - 0.00 0.00% 0.00% 4.00 367.92 100.00%
4 PROV. Y COLOC. DE INTERRUPTORES SIMPLES PTO 54.00 86.46 4,668.84 - 0.00 0.00% 0.00% 54.00 4,668.84 100.00%
5 PROV. Y COLOC. DE CONMUTADOR DOBLE PTO 10.00 97.88 978.80 - 0.00 0.00% 0.00% 10.00 978.80 100.00%
6 PROV. Y COLOC. DE CONMUTADOR SIMPLE PTO 11.00 97.88 1,076.68 - 0.00 0.00% 0.00% 11.00 1,076.68 100.00%
7 CAJA PARA 5 DISYUNTORES UNIPOLAR PZA 5.00 231.52 1,157.60 - 0.00 0.00% 0.00% 5.00 1,157.60 100.00%
8 DISYUNTORES DE 16 AMP UNIPOLAR PZA 5.00 51.17 255.85 - 0.00 0.00% 0.00% 5.00 255.85 100.00%
9 DISYUNTORES DE 20 AMP UNIPOLAR PZA 49.00 51.17 2,507.33 - 0.00 0.00% 0.00% 49.00 2,507.33 100.00%
10 DISYUNTORES DE 32 AMP UNIPOLAR PZA 12.00 58.25 699.00 - 0.00 0.00% 0.00% 12.00 699.00 100.00%
11 DISYUNTORES DE 40 AMP UNIPOLAR PZA 1.00 107.82 107.82 - 0.00 0.00% 0.00% 1.00 107.82 100.00%
12 DISYUNTORES DE 40 AMP BIPOLAR PZA 1.00 107.82 107.82 - 0.00 0.00% 0.00% 1.00 107.82 100.00%
13 DISYUNTOR TRIFASICO DE 80 AMP PZA 1.00 346.27 346.27 - 0.00 0.00% 0.00% 1.00 346.27 100.00%
14 LUMINARIA DE EMERGENCIA PTO 46.00 129.38 5,951.48 - 0.00 0.00% 0.00% 46.00 5,951.48 100.00%
15 TOMACORRIENTE DOBLE PTO 146.00 103.73 15,144.58 - 0.00 0.00% 0.00% 146.00 15,144.58 100.00%
16 TOMACORRIENTE CON TIERRA PTO 27.00 135.59 3,660.93 - 0.00 0.00% 0.00% 27.00 3,660.93 100.00%
17 SENSOR DE MOVIMIENTO TIPO TECHO PZA 38.00 223.11 8,478.18 - 0.00 0.00% 0.00% 38.00 8,478.18 100.00%
18 SENSOR DE MOVIMIENTO TIPO PARED PZA 1.00 218.39 218.39 - 0.00 0.00% 0.00% 1.00 218.39 100.00%
19 CAMARA DE SEGURIDAD PZA 10.00 494.30 4,943.00 - 0.00 0.00% 0.00% 10.00 4,943.00 100.00%
20 DVR PARA CAMARAS PZA 1.00 1,508.20 1,508.20 - 0.00 0.00% 0.00% 1.00 1,508.20 100.00%
21 TOMA TELEFONICA PTO 8.00 151.84 1,214.72 - 0.00 0.00% 0.00% 8.00 1,214.72 100.00%
22 TOMA DE RED PZA 35.00 439.57 15,384.95 - 0.00 0.00% 0.00% 35.00 15,384.95 100.00%
23 HAP DE SALIDAS PZA 1.00 529.90 529.90 - 0.00 0.00% 0.00% 1.00 529.90 100.00%
24 CAJA DE BARRAS PARA 4 BARRAS PZA 4.00 2,829.08 11,316.32 - 0.00 0.00% 0.00% 4.00 11,316.32 100.00%
25 MEDIDOR MONOFASICO PZA 1.00 866.12 866.12 - 0.00 0.00% 0.00% 1.00 866.12 100.00%
26 MEDIDOR TRIFASICO PZA 1.00 4,131.82 4,131.82 - 0.00 0.00% 0.00% 1.00 4,131.82 100.00%
27 CAJA DE DISTRIBUCION DE CIRCUITOS ESPECIALES PZA 4.00 131.92 527.68 - 0.00 0.00% 0.00% 4.00 527.68 100.00%
28 BOMBA DE AGUA DE 2 HP PZA 1.00 5,316.48 5,316.48 - 0.00 0.00% 0.00% 1.00 5,316.48 100.00%
29 JABALINA PARA TIERRA PZA 8.00 1,242.95 9,943.60 - 0.00 0.00% 0.00% 8.00 9,943.60 100.00%
30 PARARAYO FRANKLIN PZA 1.00 20,776.79 20,776.79 - 0.00 0.00% 0.00% 1.00 20,776.79 100.00%
31 JABALINA PARA PARARAYO 5/8" DE 2,5M PZA 8.00 8,702.55 69,620.40 - 0.00 0.00% 0.00% 8.00 69,620.40 100.00%
32 TRANSFORMADOR TRIFASICO DE 50 KVA TIPO MOCHILA PZA 1.00 94,040.52 94,040.52 - 0.00 0.00% 0.00% 1.00 94,040.52 100.00%
33 CABLE # 1 MCM ML 70.00 33.71 2,359.70 - 0.00 0.00% 0.00% 70.00 2,359.70 100.00%
34 CABLE # 6 AWG ML 25.00 22.61 565.25 - 0.00 0.00% 0.00% 25.00 565.25 100.00%
35 CABLE # 8 AWG ML 50.00 18.71 935.50 - 0.00 0.00% 0.00% 50.00 935.50 100.00%
VALORIZACION Nº 06 3 DE OCTUBRE
VALORIZACION Nº 07 3 DE NOVIEMBRE
VALORIZACION Nº 08
VALORIZACION Nº 09
PRORRIDRE – PRASTER
CONSTRUCCÓN EDIFICIO ACADEMICO CARRERA INGENIERIA DE MINAS UNS XX
6,000,000.00
1,800,000.00
1,600,000.00
5,000,000.00
1,400,000.00
4,000,000.00
1,200,000.00
EN NUEVOS SOLES
3,000,000.00
DESE MBOLSO
1,000,000.00
800,000.00
2,000,000.00
600,000.00
1,000,000.00
400,000.00
-
13-jul-15
200,000.00 13-ago-15 13-sep-15 13-oct-15 13-nov-15 13-dic-15 13-ene-16 13-feb-16 13-mar-16 13-abr-16
MESES
VALORIZAC. ACUMUL. PROGAMADA 0.00 69,963.32 629,056.00 584,260.68 765,366.37 239,587.37 961,766.26 647,655.00 209,682.47 1,199,211.00
VALORIZAC. ACUMUL. EJECUTADA 0.00 0.00 417,502.38 161,775.93 130,186.35 158,157.15 386,731.19 410,087.23 147,654.75 301,939.04
DESEMBOLSO 0.00 0.00 0.00 119,333.94 574,512.37 254,113.12 - 480,717.44 - -
MES 13 DEJULIO 13 DE AGOSTO 13 DE SEPTIEMBRE 13 DE OCTUBRE 13 DE NOVIEMBRE 13 DE DICIEMBRE 13 DE ENERO 13 DE FEBRERO 13 DE MARZO ABRIL
AÑO 2,015 2,016
LEYENDA PROGRAMADO: EJECUTADO: DESEMBOLSO:
VALORIZACION
Nº VAL. ACTUAL VAL. ACUMUL. VAL. SALDO
00 0.00 0.00 6,983,219.46
01 188,078.23 188,078.23 6,795,141.23
02 417,502.38 605,580.61 6,377,638.85
03 161,775.93 767,356.54 6,215,862.92
04 130,186.35 897,542.89 6,085,676.57
05 158,157.15 1,055,700.04 5,927,519.42
06 386,731.19 1,442,431.23 5,540,788.23
07 410,087.23 1,852,518.46 5,130,701.00
08 147,654.75 2,000,173.21 4,983,046.25
09 301,939.04 2,302,112.25 4,681,107.21
% AVANCE 32.97% 67.03%
UNS XX
Informe Mensual “Construcción Canal Principal Irrigación Yanarico Prog. 3+156.55 al 14+511.68” Correspondiente al Mes de Enero del 2,008
GOBIERNO REGIONAL PUNO
PRORRIDRE
2 Obras de Arte Und 130 1.70 0.01 52.00 0.40 113.70 0.87 16.3 12.54%
Acueducto Und 1 - - - - - - 1 100.00%
Alcantarilla Und 11 1.70 0.15 3.00 0.27 4.70 0.43 6.3 57.27%
Caída Und 4 - - 1.00 0.25 1.00 0.25 3 75.00%
Canoa A = 1.5 m. Und 2 - - - - - - 2 100.00%
Canoa Tipo Vehicular Und 3 - - - - - - 3 100.00%
Cruce Puente Vehicular CABANA Und 1 1.00 1.00 - - 1.00 1.00 0 0.00%
Entrega Pluvial Und 13 - - 13.00 1.00 13.00 1.00 0 0.00%
Entrega Pluvial + Salvavidas Und 6 2.00 0.33 - - 2.00 0.33 4 66.67%
Pase Peatonal Und 47 42.00 0.89 23.00 0.49 65.00 1.38 -18 -38.30%
Puente Vehicular Und 4 1.00 0.25 - - 1.00 0.25 3 75.00%
Salvavidas Und 16 14.00 0.88 12.00 0.75 26.00 1.63 -10 -62.50%
Toma Lateral Und 11 - - - - - - 11 100.00%
Toma Simple Und 11 - - - - - - 11 100.00%
CUADRO DE RESUMEN
COSTO REFERENCIAL DEL EXPEDIENTE (A) 3,750,098.42
COSTO ADICIONAL EJECUTADO POR OBRAS NECESARIAS (E) 320,252.65
COSTO TOTAL DE OBRA ACUMULADO (A)+(E) 4,070,351.07
PORCENTAJE DE ADICIONAL EJECUTADO (E)/(A) 8.54%
VALORIZACIÓN ACUMULADA AL MES (E) 539,145.99
% AVANCE FISICO ACTUAL ACUMULADO (C)/(A)*100 14.38%
Excavaciòn Manual
Comp.P/Estructura
Acero de Refuerzo
Trazos y replanteo
C°f'c=210 kg/cm2
Piedra asentada y
Baranda Metálica
C°f'c=175 kg/cm2
Plancha Metalica
Plancha Metalica
de obras de arte
Compuerta Tipo
Compuerta Tipo
Compuerta Tipo
Compuerta Tipo
Compuerta Tipo
proteccion (m3)
f'c=140+30%PM
f'c=175+30%PM
Mat.Excedente
Izaje 0.50x0.50
Izaje 0.40x0.30
Izaje 0.50x0.40
Izaje 0.40x0.35
Izaje 0.20x0.20
Enrrocado de
emboquillada
6.10x1.25m
3.80x1.20m
Ydesencof.
N° Progrevisva Obra de Arte
Limpieza y
J.Asfaltica
Encofrado
desbroce
J.W.stop
P/Estruc.
Relleno
kg/cm2
kg/cm2
C°C°
Elim.
C°C°
s
1 6+275.80 Toma lateral – 14 MD
2 6+536.05 Salvavidas
3 6+677.55 Alcantarilla (cruce río porotoyo)
4 6+823.50 Toma lateral –15 MD
5 6+885.55 Pase peatonal 21.30 21.30 6.29 3.12 3.50 6.29 1.93 38.91 122.62 11.10
6 6+905.65 Salvavidas
7 7+066.75 Toma simple – MD
8 7+153.00 Alcantarilla cruce dren
9 7+158.28 Partidor ( canal – A Canal -B )
10 7+196.27 Puente vehicular
11 7+525.00 Toma lateral –16 MD
12 7+570.65 Pase peatonal 11.10
13 7+664.25 Toma simple - MI
14 7+674.45 Pase peatonal 11.10
15 7+750.00 Rápida
16 7+840.00 Puente vehicular
47 9+871.20 Toma simple – MD
48 9+898.50 Rápida
49 9+997.50 Puente vehicular
51 0+235.40 Pase peatonal
52 0+239.15 Entrega superficial
53 0+477.50 Pase peatonal
54 0+557.75 Toma simple – MD
55 0+691.55 Pase peatonal
56 0+704.25 Entrega superficial
57 0+793.55 Pase peatonal
58 0+933.50 Puente vehicular
59 0+983.00 Toma simple - MI
60 1+007.40 Pase peatonal
61 1+023.00 Partidor
TOTAL 21.30 21.30 0.00 6.29 3.12 3.50 0.00 6.29 1.93 0.00 0.00 38.91 122.62 0.00 0.00 33.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Obra :
META
Departament Puno Provincia LAMPA Distrito CABANILLA
Obra :
META
Departament Puno Provincia LAMPA Distrito CABANILLA
04.00.00 CONCRETOS
04.01.00 CONCRETO F'C= 140 KG/CM2 + 30% PM - M3
de la hoja de metrados resumen de obras de arte 1 - 0.00
08.00.00 VARIOS
Obra :
META
Departament Puno Provincia LAMPA Distrito CABANILLA
ACEROS DE REFUERZO
Nº PARTIDA UNIDAD Nº VECES CANTIDAD LONGITUD PESO F` PARCIAL TOTAL
1.00 ACEROS 0.00
1.01 f´ long. inferior losa kg 0.56 0.00
1.02 f´ trans. inferior losa kg 1.02 0.00
1.03 f´ long.superior losa kg 0.56 0.00
1.04 f´ trans.superior losa kg 0.56 0.00
1.05 As sardinel kg 1.02 0.00
1.06 As sardinel estribos kg 0.56 0.00
AFEC. PPTAL :
MES - NOVIEMBRE
FECHA DE FECHA D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L
No APELLIDOS Y NOMBRES CARGO D.N.I. AFP COD.AFILIADO TOTAL
INGRESO NACIMIENTO 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
LEYENDA.
DIAS LABORADOS : (X), FERIADOS : (FE), DIAS NO LABORADOS : ( ) DOMINICALES (D)
JORNAL JORNAL
M E S E S ACUMULADO SALDO
Nº
Nº JORNAL
Nº DESCRIPCION DEL PERSONAL PERSONAL
ABRIL MAYO JUNIO JULIO AGOSTO SETIEMBRE OCTUBRE NOVIEMBRE DICIEMBRE
PROG. PROG.
NºJº % Nº Jº %
Nº Pº Nº Jº Nº Pº Nº Jº Nº Pº Nº Jº Nº Pº Nº Jº Nº Pº Nº Jº Nº Pº Nº Jº Nº Pº Nº Jº Nº Pº Nº Jº Nº Pº Nº Jº
Nº Pº: Nº DE PERSONAL
Nº Jº: Nº DE JORNAL
A.- PERSONAL TEC. ADMINIS. SEGÚN EXP. TECNICO TIEMPO DE EJECUCION DE OBRA PROGRAMADO RESUMEN
SUB TOTAL
SUB TOTAL
ITEM CARGO CANT. MES COSTO CONTRATO DETALLE JUN JUL AGO SET OCT NOV DIC ACUMULADO OBS.
1 S/. 40,000.00 PORCENTAJE 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SUPERVISOR DE OBRA
MONTO - - - - 0.00 -
2 S/. 40,000.00 PORCENTAJE 0.00% 0.00% 0.00% 0.00% 8.75% 5.25% 0.00% 14.00% 14.00%
RESIDENTE DE OBRA
MONTO - - 3,499.90 2,100.00 - 5,599.90 5,599.90
3 S/. 40,000.00 PORCENTAJE 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% -
ASISTENTE TECNICO DE OBRA 01
MONTO - - - - - - 0.00 -
4 S/. 20,000.00 PORCENTAJE
ADMINISTRADOR DE OBRA
MONTO
5 S/. 20,000.00 PORCENTAJE
ASISTENTE ADMINISTRATIVO
MONTO
6 S/. 20,000.00 PORCENTAJE
MAESTRO DE OBRA B
MONTO
7 S/. 22,000.00 PORCENTAJE
TECNICO LABORATORISTA
MONTO - - - - - 0.00 -
TOTAL S/. 77,803.97 S/. 306,699.84 0.00 0.00 0.00 0.00 31,910.10 31,646.67 29,248.33 21,763.52 92,805.10 30.26%
TOTAL PAGADO PLANILLAS S/. 0.00 0.00 31,910.10 31,646.67 29,248.33 21,763.52 92,805.10 30.26%
OBRA :
EJECUTA : PRORRIDRE
EQUIPO : VOLQUETE DOBLE EJE MARCA : VOLVO MODELO :
PROPIETARIO PLACA :
OPERADOR MODELO :
FECHA PERIODO Desde: 01/09/09 Hasta: 30/09/09
RESUMEN COMBUSTIBLE
TOTAL PETROLEO 200 GALONES
TOTAL GASOLINA 120 GALONES
CONTROLADOR DE MAQUINARIA ING RESIDENTE DE OBRA ING SUPERVISOR DE OBRA DIRECTOR DE OBRAS
GOBIERNO REGIONAL PUNO
PRORRIDRE
(H-M) MONTO
CANT. P.U. PARCIAL DIC ENE FEB MAR ABR (H - M) V-1 V-2 V-3 (H-M) (S/.) (H-M) (S/.)
(S/.)
1 TRACTOR SOBRE ORUGA MUNICIPALIDADA NUÑOA HM 1000.00 170.00 170,000.00 20.00 50.00 80.00 100.00 10.00 260.00 44,200.00 740.00 3,400 8,500 13,600 260.00 44,200.00 740.00 125,800.00
2 VOLQUETE MUNICIPALIDADA NUÑOA - 0.00 0.00 0.00 0.00 0 0 0 0.00 0.00 0.00 0.00
3 VOLQUETE MUNICIPALIDADA NUÑOA - 0.00 0.00 0.00 0 0 0 0.00 0.00 0.00 0.00
4 CARGADOR FRONTAL MUNICIPALIDADA NUÑOA - 0.00 0.00 0.00 0 0 0 0.00 0.00 0.00 0.00
5 VOLQUETE MUNICIPALIDADA NUÑOA - 0.00 0.00 0.00 0 0 0 0.00 0.00 0.00 0.00
6 - 0.00 0.00 0.00 0 0 0 0.00 0.00 0.00 0.00
7 - 0.00 0.00 0.00 0 0 0 0.00 0.00 0.00 0.00
8 - 0.00 0.00 0.00 0 0 0 0.00 0.00 0.00 0.00
9 - 0.00 0.00 0.00 0 0 0.00 0.00 0.00 0.00
TOTAL S/. 170,000.00 44,200.00 44,200.00 125,800.00
RESUMEN RESUMEN
N° COMBUSTIBLE UNIDAD AÑO 2,009 AÑO 2,010 HORAS MAQ CANT COMBUST
JUN JUL AG SET OCT NOV DIC ENE FEB MAR TOTAL
A EQUIPO PESADO
SALDOS SALDOS
EJECUCION MENSUAL
DESCRIPCION EQUIPO LIVIANO SEGÚN EXPEDIENTE TOTAL ACUMULADO TOTAL SALDO TOTAL ACUMULADO TOTAL SALDO
U.M. P.U. CANT. H/M MONTO S/. JUN JUL AGO SET OCT NOV H/M % H/M % MONTO. S/. % MONTO. S/. %
CAMIONETA PU-2325 HM 170.00 12000:00:00 85,000.00 158:20:00 158:20:00
MEZCALDORA DE CONCRETO
VIBRADORA DE CONCRETO
TEODOLITO
ALMECENERO DE OBRA ASISTENTE ADMINISTRATIVO ING. RESIDENTE DE OBRA Vº Bº ING. SUPERVISOR Vº Bº DIRECTOR DE OBRAS
GOBIERNO REGIONAL PUNO
PRORRIDRE
INGRESO EGRESO
SALDO INGRESO
ITEM MATERIAL UND ACUMULADO SALDO
ANTERIOR FECHA PROVEEDOR CANT FECHA PARTIDAS CANT
ALMACENERO DE OBRA ASISTENTE ADMINISTRATVO RESIDENTE DE OBRA SUPERVISOR DE OBRA DIRECTOR DE OBRAS
GOBIERNO REGIONAL PUNO
PRORRIDRE
ALMACENERO DE OBRA ASISTENTE ADMINISTRATVO RESIDENTE DE OBRA SUPERVISOR DE OBRA DIRECTOR DE OBRAS
Página 30
EQUIPO LIVIANO
1 Mezcladora De Concreto 9 -11 P3 17,099.18 0.00 0.00 -
2 Vibradora de Concreto 8HP con manguera de1 1/2 x6m (*) 1,105.41 4,224.00 0.00 4,224.00 1.00 4,224.00
4 Motobomba Cent. 4"x4" de 13HP Marca Honda(*) 2,121.95 3,996.00 0.00 3,996.00 1.00 3,996.00
5 Manguera de Succion de agua de 4" x 6m 0.00 0.00 -
6 Manguera de Descarga de agua de 4" x 40m PVC Tipo Manga 0.00 0.00 -
7 Miras y jalones 6,246.45 0.00 0.00 -
16 Tanque Estacionario/incluye pintado (*) 19,178.50 0.00 19,178.50 1.00 19,178.50
17 Cortadora de madera (encofrado)(*) 178.00 0.00 178.00 1.00 178.00
SUB-TOTAL S/. S/. 26,572.98 SUB-TOTAL S./ S/. 27,576.50
TOTAL BIENES MUEBLES S/. 956,453.13 S/. 380,073.18
(*); COMPRA DE EQUIPO LIVIANO
6.5.11.65 ALQUILER DE BIENES INMUEBLES
1 Amacen y/o residencia Glb 3,000.00 600.00 100.00 700.00 1.00 700.00
SUB-TOTAL S/. S/. 3,000.00 S/. 700.00
IMPERMEABILIZACION DE SOBRECIMIENTO
MURO LADRILLO CERAMICO 6 H E=15 CM.
1378.80 1378.80
424073.59 72 125 244266.389
JUNIO 30