Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
- 0-13153
CONSTRUCTION OF DEEP GRAVITY LINES TO LINK SHAMHA AND
SHAHAMA AREAS
25.06.19 0
REVIEWED BY
PREPEARED BY QA/QC APPROVED BY
DATED HSE (NAME & Manager PM Details of Amendment Revision
SIGN) (NAME & (NAME & SIGN)
SIGN)
Page 1 of 11
Contents:
1.0 Introduction
4.0 Attachments
Page 2 of 11
1.0 Introduction
This method statement is going to explain the complete procedure, how workers safely will
go inside the ongoing tunnels and completed tunnels.
The method statement covers that the workers must go inside the tunnels by using the
following safety measures to do checking/maintenance/repair activities.
o Ventilation
o Lighting
o Communication
o Training
o Monitoring
o Access/Egress
o Emergency Arrangements
It is proposed to use the micro tunneling method to install GRP sewer lines between.
During the different stages of construction of these tunnels it will be inevitable that staff
must enter the either ongoing or completed lines.
The main reasons for staff entering the lines while tunneling is ongoing
are:
The main reasons for staff entering the lines after tunneling is completed
are:
Page 3 of 11
1. Opening and subsequent removal/closing of IJS’s
2. Removal of tunnel services
3. Grouting of overbreak (annulus)
4. Lamination
5. Cleaning of line
The following measures/precautions will be taken to ensure the safety of all staff entering
the tunnel during and after tunneling:
24” centrifugal (2200W, flow 290m³/min) combined with 8”/ 200mm ducting. Ducting can be PVC
pipes, semi-rigid duct or flexible duct hose.
DIA: 6600mm
Radius: 3300 mm= 3.3 meters
Length: 150 meters (Assumed maximum drive)
Volume: 22/7*0.6*0.6*150= 5,129 m3
Page 4 of 11
12” centrifugal fan producing 52 m³/min, combined with 300mm ducting.
Ducting can be PVC pipes, se
mi-rigid duct or flexible duct hose.
DIA: 6600 mm
Radius: 3300 mm= 3.3 meters
Length: 85 meters (maximum drive)
Volume: 22/7*0.9*0.9*85= 2,906 m3
Fresh air requirement for per person by (OSHAD) = 5.7m3/minute i.e. 0.095 m3/second
Flow rate=41.6 m3/min
Maximum no, of workers allowed to work inside the shaft at a given time= 41.6/5.7 i.e. 8 persons
DIA: 2000mm
Radius: 1000 mm= 1.0 meters
Length: 550 meters (maximum drive)
Volume: 22/7*1.0*1.0*550= 1728 m3
Fresh air requirement for per person by (OSHAD) = 5.7m3/minute i.e. 0.095 m3/second
Flow rate=0.76 m3/sec
Maximum no, of workers allowed to work inside the shaft at a given time= 0.76/0.095 i.e. 8 persons
Page 5 of 11
3.3 Proper Lighting:
Throughout the tunnel a 110 Volt lighting system will be installed with bulbs @
every 4 meter and in addition to this each staff member entering the tunnel will
have a headlight to provide task specific lighting during maintenance/repair work. As
a backup torches will be provided. The TBM and the trailing powerpack can are
equipped with tube lighting which will be switched on when required. (cannot be on
permanently as it interferes with the tunneling guidance laser)
Page 6 of 11
3.4 Proper Communication:
The control cabin, shaft control panel, IJS measuring boxes and the TBM are all
equipped with telephones connected to each other via the TBM’s data cable for
2000mm line (HERRENKNECHT).
For 1800 and 1200 (ISEKI) the communication is only at TBM machine connected to
Control cabin, for the tunnel line Walkie talkies with operatives for communication
and standby supervisor.
Besides the above-mentioned communication system, the following staff with have
handheld radios to ensure continuous communication:
Shift supervisor
TBM operator
Rigger
Crane operator
Shaft foreman
Emergency contact details will be clearly displayed across the site and all staff will
receive clear instruction/training on how to act in case of an emergency.
Page 7 of 11
JGI’s HSE department will strive to continuously improve all staff’s understanding
of the risks associated with working in a confined space by giving regular toolbox
talks and training. File containing all certificates will be kept at site.
A minimum of 3 units will be on site to ensure 1 unit is always inside the shaft, 1
unit is kept on standby to be used inside the tunnel and 1 unit is spare/charging
with supervisor or HSE Team member.
Page 8 of 11
To ensure staff entering the tunnel can move as freely as possible within the
constraints of a pipe, all tunnel services will be placed on brackets (round brackets
with multiple hooks)
By using these brackets, the only areas where there is limited access are the
Intermediate Jacking Stations (IJS).
Page 9 of 11
Once the TBM is removed from the reception pit the risks remain the same but are reduced as the
staff will be working in a pipe which is now open at both ends rather than closed at one end as
during tunneling. The moment the IJS’s are closed the risks reduce even further as the GRP
becomes a smooth pipe rather than an interrupted one giving easier access. All the precautions
mentioned above will stay in place until all work in a particular line has been completed.
Page 10 of 11
Samir HSE Officer (Baniyas) 056-3379620
Page 11 of 11