Sei sulla pagina 1di 32

JURISDICTION : SUPREME COURT OF WESTERN AUSTRALIA

IN CIVIL

CITATION : SAMSUNG C&T CORPORATION -v- DURO


FELBUERA AUSTRALIA PTY LTD [2016] WASC 193

CORAM : LE MIERE J

HEARD : 23 MAY 2016

DELIVERED : 28 JUNE 2016

FILE NO/S : CIV 1552 of 2016

BETWEEN : SAMSUNG C&T CORPORATION


Plaintiff

AND

DURO FELBUERA AUSTRALIA PTY LTD


Defendant

Catchwords:

Arbitration Agreements - Declaratory relief - Stay application - Kompetenz-


Kompetenz - Whether there is an agreement to arbitrate - Where there are both
arbitration and jurisdiction clauses agreed by the parties - Where arbitration
agreement covers the dispute - Section 7 of the International Arbitration Act -
Proceedings stayed - Turns on own facts

Legislation:

Arbitration Act 1996 (UK), s 9


Commercial Arbitration Act 2010 (NSW), s 8
International Arbitration Act (Singapore), s 10
International Arbitration Act 1974 (Cth), s 7, s 8, s 16
New York Convention, Art II
Rules of the Supreme Court 1971 (WA), O 16 r 6, O 18 r 16
Supreme Court Act 1935 (WA), s 25
UNCITRAL Model Law on International Commercial Arbitration, Art 8

Result:

Proceedings stayed
The matters are referred to arbitration

Category: A

Representation:

Counsel:
Plaintiff : Dr A S Bell SC & Mr E M Heenan
Defendant : Mr S K Dharmananda SC & Mr T J Porter

Solicitors:
Plaintiff : Herbert Smith Freehills
Defendant : Jones Day

Case(s) referred to in judgment(s):

Ace Capital Ltd v CMS Energy Corp [2008] EWHC 1843 (Comm)
Bakri Navigation Company Ltd v Owners of Ship 'Golden Glory' Glorious
Shipping SA [1991] FCA 179; (1991) 217 ALR 152
Comandate Marine Corp v Pan Australia Shipping Pty Ltd [2006] FCAFC 192;
(2006) 157 FCR 45
Duro Felguera Australia Pty Ltd v Samsung C&T Corporation [2015] WASC 484
Duro Felguera Australia Pty Ltd v Samsung C&T Corporation [2016] WASC 119
Electricity Generation Corporation v Woodside Energy Ltd [2014] HCA 7; (2014)
251 CLR 640
Flint Inc NZ Ltd v Huhtamaki Australia Pty Ltd [2004] VSCA 166; (2014) 289
FLR 30
Golden Ocean Group Ltd v Humpuss Intermoda Transportasi Tpk Ltd [2013]
EWHC 1240
Joint Stock Co 'Aeroflot Russian Airlines' v Berezovsky [2013] EWCA CIV 784; 2
Lloyd's Rep 242
Monde Petroleum SA v Westernzagros Ltd [2015] EWHC 67 (Comm)
Rinehart v Rinehart (No 3) [2016] FCA 539
Rinehart v Welker [2012] NSWCA 95
Robotunits Pty Ltd v Mennel [2015] VSC 268
Sulamerica Sia Macional De Seguros SA v Enesa Engenharia SA [2012] EWHC
42 (Comm)
Tanning Research Laboratories Inc v O'Brien [1990] HCA 8; (1990) 169 CLR 332
Tomolugen Holdings Ltd v Silica Investors Ltd [2015] SGCA 57
1 LE MIERE J:

Summary

2 An unincorporated joint venture of the defendant, Duro, and Forge


Group Constructions Pty Ltd (Forge) entered into a contract (the
Subcontract) with the plaintiff, Samsung. The Subcontract contains a
dispute resolution clause, cl 42, which includes an arbitration agreement.
Samsung terminated the Subcontract. Samsung and Duro entered into a new
contract (the Interim Subcontract) by executing a Term Sheet. A term of the
Term Sheet provides that the Interim Subcontract is on the same terms as the
Subcontract as modified by the terms set out in the Term Sheet and its
schedules for the performance of the works. The Term Sheet contains a
governing law clause and a jurisdiction clause but no separate arbitration
agreement.

3 Disputes arose under both the Subcontract and the Interim Subcontract.
Samsung issued a notice of arbitration against Duro in respect of various
claims under the Subcontract. In the arbitration Duro has made claims for
the purpose of set-off. As least some those claims (the Duro Claims) arise
under the Interim Subcontract.

4 Samsung has commenced this proceeding in which it claims declaratory


relief. In substance Samsung seeks declarations to the effect that there is no
binding arbitration agreement between it and Duro which covers the Duro
Claims, the jurisdiction clause in the Term Sheet covers those claims and
hence this court is the proper forum for the determination of the Duro
Claims. No other relief is sought.

5 Duro says that the Interim Subcontract includes an arbitration


agreement on the terms of cl 42 of the Subcontract and hence the arbitral
tribunal has jurisdiction to determine the Duro Claims and those claims must
be determined by arbitration. Duro seeks to stay the proceedings pursuant to
s 7 of the International Arbitration Act 1974 (Cth) (the Act) or alternatively
seeks an order that the proceeding be dismissed on the ground that the
proceeding concerns the jurisdiction of the duly constituted arbitral tribunal
and the court has no jurisdiction to interfere with arbitral proceedings or in
the further alternative, that, if it has jurisdiction, the court should dismiss the
proceeding as a matter of discretion.

6 The central issue in this proceeding, and in Duro's application to stay or


dismiss the proceeding, is whether the Interim Subcontract includes an
arbitration agreement in the terms of cl 42 of the Subcontract. I determined
that, for considerations of case management, Samsung's application for
declarations and Duro's application for a stay of, or dismissal of, the
proceeding should be heard together.

7 For the reasons which follow, I have concluded that an arbitration


agreement in the terms of cl 42 of the Subcontract is a term of the Interim
Subcontract, that this proceeding involves the determination of a matter that,
in pursuance of the arbitration agreement, is capable of settlement by
arbitration and therefore this proceeding should be stayed and referred to
arbitration.

Facts

8 The essential facts are not in dispute. The unincorporated joint venture
of Duro and Forge entered into the Subcontract with Samsung to engineer,
procure, construct and commission works in relation to the Roy Hill iron ore
mining, rail and port project (Subcontract Works). The Subcontract contains
a dispute resolution clause, cl 42, which provides that if a dispute is not
resolved after a notice of dispute has been given and the parties have
conferred the dispute shall be referred to arbitration. On 21 February 2014
Samsung terminated the Subcontract, as it was entitled to do, on the ground
that an administrator had been appointed to Forge.

9 On or about 24 February 2014 Samsung and Duro executed an


instrument entitled Subcontract Term Sheet (Term Sheet) dated, and to take
effect from, 21 February 2014 by which Duro agreed to continue to perform
the works set out in Schedule 2 to the Term Sheet (Duro Works) which will
apply as a binding agreement between them (Interim Subcontract). The
Duro Works were a subset of the Subcontract Works and were essentially
the part of the Subcontract Works which Duro and Forge had agreed would
be performed by Duro. The Term Sheet provides that the Interim
Subcontract is on the same terms as the Subcontract as modified by the
terms set out in the Term Sheet and its schedules for the performance of the
Duro Works. The Term Sheet provides that the parties will negotiate in
good faith and make such additional changes as are logically or practicably
required considering the Duro Works and execute a Substitute Subcontract
which is based on the terms of the Subcontract as modified in the Term
Sheet as soon as reasonably possible. No Substitute Subcontract was entered
into. The Term Sheet contains a governing law clause (cl 3.2(a)) and a
jurisdiction clause (cl 3.2(b)). The Term Sheet contains no separate
arbitration agreement.

10 Disputes arose under both the Subcontract and the Interim Subcontract.
On 23 December 2015 Duro issued notices of dispute under each of the
Subcontract (the Subcontract Notice of Dispute) and the Interim Subcontract
(Interim Subcontract Notice of Dispute). On 17 February 2016 Duro issued
a notice of dispute which consolidated the Subcontract Notice of Dispute
and the Interim Subcontract Notice of Dispute. On 17 March 2016 Samsung
issued a notice of arbitration against Duro in respect of various claims under
the Subcontract (Notice of Arbitration). By letter of 17 March 2016 to the
Singapore International Arbitration Centre (SIAC) Samsung requested that
SIAC administer the arbitration between Samsung and Duro. On 18 March
2016 Duro issued its response to the Notice of Arbitration (Response). The
Response included various claims for the purpose of set off against
Samsung. Those claims, insofar as they arise under the Interim Subcontract,
concern claims to:

(a) payment of amounts allegedly outstanding to Duro for the


performance of works under the Interim Subcontract in excess of
$58,836,000;

(b) payment for additional works allegedly carried out by Duro under the
Interim Subcontract; and

(c) declarations that Duro has no liability to Samsung in respect of


liquidated damages under the Interim Subcontract and alleged defect
rectification costs under the Interim Subcontract;

(Duro Claims).

This proceeding

11 On 5 April 2016, Samsung commenced this action by writ of summons.


In its indorsement of claim Samsung refers to the Notice of Arbitration
issued by Samsung on 17 March 2016 and Duro's response to the Notice of
Arbitration which includes the Duro Claims. Samsung asserts that the Duro
Claims are claims arising under the Interim Subcontract and are subject to
the dispute resolution procedure in the jurisdiction clause, cl 3.2(b), of the
Term Sheet and asserts that the proper forum for the determination of the
Duro Claims is this court. Samsung claims:

(a) a declaration that the Duro Claims constitute 'proceedings arising out
of or in connection with this agreement' for the purposes of cl 3.2(b)
of the Term Sheet;

(b) a declaration that the proper forum for the determination of the Duro
Claims is the Supreme Court of Western Australia;

(c) a declaration that the parties have not agreed to resolve the Duro
Claims by arbitration.

12 Duro seeks to stay the proceedings pursuant to s 7 of the Act and article
8 of the UNCITRAL Model Law on International Commercial Arbitration
adopted by the United Nations Commission on International Trade Law
(Model Law), which by s 16 of the Act has the force of law in Australia.
Alternatively, Duro says that the proceeding concerns the jurisdiction of the
duly constituted arbitral tribunal and the court has no jurisdiction to interfere
with arbitral proceedings and should dismiss this proceeding on the grounds
that the court has no jurisdiction. In the further alternative Duro says that if
the court has jurisdiction it should not grant the relief sought by Samsung as
a matter of discretion. Finally, Duro says that if the court does not stay the
proceeding or dismiss it on the ground of lack of jurisdiction or for
discretionary reasons the court should dismiss the proceeding on the basis
that Samsung's grounds for relief are not made out.

Tribunal decision on jurisdiction

13 On 13 June 2016, after I had heard the applications in this matter, the
arbitral tribunal delivered its decision on Samsung's submission that the
arbitral tribunal did not have jurisdiction over counterclaims and claims for
setoff brought by Duro in respect of the Duro Claims. I received from each
party written submissions whether the tribunal's decision should be provided
to the court. I have decided not to give leave to Duro to reopen its case to
adduce evidence of the tribunal's decision for the following reasons.

14 Once an application has been heard, there is no right to deliver any


further evidence or submissions without leave. The overriding principle to
be applied in exercising the discretion to give leave to reopen is whether the
interests of justice are better served by allowing or rejecting the application
to reopen. In the case of an application to reopen to admit fresh evidence
relevant factors include why the evidence was not called at the hearing and
the materiality of the evidence to the issues in dispute and whether the
admission of the evidence would have produced a different result. Clearly,
the evidence could not have been admitted at the hearing. The principal
issue is the materiality of the decision of the tribunal.

15 Duro advances three arguments in favour of the court receiving the


tribunal's decision. The first is that the tribunal's decision is relevant to the
avoidance of inconsistent judgments. Samsung says that the premise that the
tribunal decision and the decision of the court may give rise to inconsistent
judgments is false. Samsung says that no relief is sought against the
arbitrators nor is any declaration as to the scope of the arbitrator's
jurisdiction being pursued by Samsung in these proceedings. I agree.

16 Duro submits that Samsung contends, in opposition to the stay sought


by Duro, that the arbitration agreement in the Subcontract has become
inoperative within the meaning of s 7(5) of the Act. Duro says that the court
has a discretion to either determine that question of inoperativeness or to
grant a stay and permit that issue to be resolved by the arbitral tribunal and
that a factor relevant to the exercise of that discretion is whether there has
been or will be related proceedings addressing the arbitrability issue between
the parties. If the arbitrability dispute has been addressed or resolved in
other proceedings, the court will be anxious to do what it can to minimise
the risk of inconsistent judgments and provide for orderly case management:
Golden Ocean Group Ltd v Humpuss Intermoda Transportasi Tpk Ltd
[2013] EWHC 1240, [59(7)] (Popplewell J) (Golden Ocean), Rinehart v
Rinehart (No 3) [2016] FCA 539, [124(d)] (Gleeson J). Therefore Duro
says the tribunal decision is relevant to this discretionary factor.

17 I do not accept Duro's argument. In this case, the relevant issue is


whether the Interim Subcontract contains an arbitration agreement in the
terms of cl 42 of the Subcontract, not whether cl 42 of the Subcontract has
been rendered inoperative. Holmes and Brown 'The International
Arbitration Act 1974 a Commentary' (2nd ed), at [S7-21] refer to Bakri
Navigation Company Ltd v Owners of Ship 'Golden Glory' Glorious
Shipping SA [1991] FCA 179; (1991) 217 ALR 152. The parties were
involved in a dispute arising out of negotiations for the sale of a ship. The
plaintiffs sought a declaration that there was a binding contract for the sale
of the ship and obtained the arrest of the ship. After the initiation of court
proceedings and before the application for a stay under s 7 of the Act was
made, the parties entered into a further agreement which allowed the release
of the ship which resolved certain claims in proceedings before the court.
Gummow J found that there was a concluded contract of sale which
contained an arbitration agreement. Gummow J then considered the terms of
the subsequent undertaking to the court and the agreement which had been
reached between the parties that allowed for the release of the ship. His
Honour found that the subject matter of this later agreement was the whole
of the proceeding before the court and not merely the release of the ship. In
the circumstances the subsequent agreement effected a variation of the
arbitration agreement which rendered it 'inoperative or ineffective in respect
of the claims involved in the proceedings before the court'. Gummow J was
of the view that 'inoperative' describes an arbitration agreement which
although not void ab initio has for some reason ceased to have effect for the
future. This may be because the arbitration agreement may have ceased to
operate by reason of some further agreement between the parties. The court
found that the term requiring arbitration had, sofar as the claims of the
plaintiff were concerned, become inoperative by reason of the further
agreement between the parties.

18 In this case the arbitration agreement in the Subcontract does not apply
to the Duro Claims because they arise out of the Interim Subcontract. The
arbitration agreement in the Subcontract survives the termination of the
Subcontract but it does not apply to claims which arise out of the Interim
Subcontract not the Subcontract. The Interim Subcontract does not render
the arbitration agreement in the Subcontract inoperative sofar as the Duro
Claims are concerned. The question is whether there is an arbitration
agreement in the Interim Subcontract which applies to the Duro Claims.

19 In my opinion the question of whether the Term Sheet renders the


arbitration agreement in the Subcontract inoperative sofar as the Duro
Claims are concerned does not arise in this proceeding. Accordingly, there
is no risk of inconsistent findings in this proceeding and in the proceedings
before the arbitral tribunal whether the arbitration agreement in the
Subcontract covers the Duro Claims or is inoperative sofar as those claims
are concerned.

20 Secondly, Duro says that the tribunal's decision is relevant to


Samsung's urgency argument. Samsung contends that if, contrary to its
submission, the Interim Subcontract contains an arbitration agreement in the
terms of cl 42 of the Subcontract then Samsung relies on the carve out or
exception provided for by cl 42.5 for urgent declaratory relief. Samsung
says that the time to assess the urgency of the declaratory relief is at the time
the proceedings seeking such relief are initiated and heard. That urgency is
not to be reassessed on an ongoing basis after argument has closed to
determine if the urgent declaratory relief exception applies. I agree. The
delivery of the tribunal's decision does not affect whether the relief sought
by Samsung in this proceeding is urgent declaratory relief.

21 The third reason advanced by Duro is that the tribunal's decision is


relevant to the utility of the declaratory relief sought by Samsung in this
proceeding. Duro says that a decision on jurisdiction by a properly
constituted tribunal in the exercise of an unchallenged jurisdiction resolves
the question of jurisdiction as between the parties. Where a question of
jurisdiction has been so resolved, a declaration by a court has no utility.
Duro says this is reinforced by the fact that there is an appeal process from a
decision of a tribunal on a plea as to jurisdiction to the High Court of
Singapore: s 10(3) International Arbitration Act (Singapore).

22 Samsung says that the existence of the appeal mechanism re-enforces


the utility of these proceedings. Both the Subcontract and the Interim
Subcontract are governed by Western Australian law. A decision by this
court would be of assistance to the High Court of Singapore should an
appeal be commenced against the tribunal's decision irrespective of the
content of the tribunal's decision.

23 In my view, the tribunal decision might affect the exercise of the court's
discretion whether or not to grant the declarations sought by Samsung if the
court determined that the Interim Subcontract does not contain an arbitration
clause and the proper forum for the determination of the Duro Claims is this
court. However, as I have decided that the Interim Subcontract contains an
arbitration agreement in the terms of cl 42 of the Subcontract no question
arises whether I should exercise the discretion to make the declarations
sought by Samsung.

The court's jurisdiction

24 I will deal at the outset with Duro's submission that the court has no
jurisdiction to grant the relief sought by Samsung.

25 Section 25(6) of the Supreme Court Act 1935 (WA) gives the court
power to make declarations of right without granting consequential relief.
Order 18 rule 16 of the Rules of the Supreme Court 1971 (WA) provide that
no action or other proceedings shall be open to objection on the ground that
a merely declaratory judgment or order is sought and the court may make
binding declarations of right whether or not any consequential relief is or
could be claimed. The existence of the right is a matter going to the
discretion rather than to the jurisdiction to grant declaratory relief.
Declaratory relief must be directed to the determination of legal
controversies and not to answering abstract or hypothetical questions. There
is a real controversy whether the Interim Subcontract contains an arbitration
agreement in the terms of cl 42 of the Subcontract and whether the
arbitration agreement covers the Duro Claims.

26 Article 16 of the Model Law provides that the arbitral tribunal may rule
on its own jurisdiction, including any objections with respect to the existence
of the arbitration agreement. This provision gives effect to the principle of
kompetenz-kompetenz or compétence-competénce which is that the arbitral
tribunal may independently rule on the question of whether it has
jurisdiction, including any objections with respect to the existence of the
arbitration agreement, without having resort to a court.

27 Neither the Act nor the Model Law has removed the jurisdiction of the
court to grant declaratory relief in relation to the existence of an arbitration
agreement. The court has jurisdiction to grant the declaratory relief sought
by Samsung. Declaratory relief is discretionary. It is not necessary to
consider the exercise of the court's discretion in this case because for the
reasons which follow I have determined that the court should stay the
proceedings pursuant to s 7(2) of the Act.

Section 7 of the Act

28 Section 7 of the Act provides for the enforcement of an arbitration


agreement by a court in which a party has commenced proceedings covered
by the arbitration agreement staying the proceeding and referring the parties
to arbitration. Section 7(1) prescribes the arbitration agreements to which
the section applies. The section applies to the arbitration agreement at cl 42
of the Subcontract and the arbitration agreement in the Interim Subcontract
on those terms, if there is such an agreement in the Interim Subcontract.
That is not in dispute.

29 Section 7(2) of the Act prescribes when the court will stay an
arbitration agreement to which the section applies. It is in these terms:
Subject to this Part, where:
(a) proceedings instituted by a party to an arbitration agreement to which this
section applies against another party to the agreement are pending in the
court; and

(b) the proceedings involve the determination of a matter that, in pursuance of


the agreement, is capable of settlement by arbitration;

on the application of a party to the agreement, the court shall, by order, upon such
conditions (if any) as it thinks fit, stay the proceedings or so much of the
proceedings as involves the determination of that and refer the parties to arbitration
in respect of that matter.

30 Accordingly, to enliven the court's power to stay this proceeding, Duro


must establish that this proceeding involves the determination of a matter
that, in pursuance of an arbitration agreement in the Interim Subcontract on
the terms of the arbitration agreement in cl 42 of the Subcontract, is capable
of settlement by arbitration. Determining whether a matter the
determination of which is involved in the proceedings is capable of
settlement by arbitration requires the identification of the matter or matters
in the proceedings, the existence of an arbitration agreement and the scope
of the arbitration agreement.

Article 8 of the Model Law

31 Article 8(1) of the Model Law provides:


A court before which an action is brought in a matter which is the subject of an
arbitration agreement shall, if a party so requests not later than when submitting his
first statement on the substance of the dispute, refer the parties to arbitration unless
it finds that the agreement is null and void, inoperative or incapable of being
performed.

Whether the court should refer the parties to arbitration under Article 8
depends on whether the dispute or claim in the proceeding is a matter that is
subject to an arbitration agreement.

32 Article 8 operates independently from, but in a similar manner to s 7 of


the Act. In the circumstances of this case whether the conditions for
ordering a stay under s 7(2) of the Act or Article 8 of the Model Law are
made out depend on the same considerations. In each case, the principal
issue between the parties is the existence of a relevant arbitration agreement.
The issue is whether the Interim Subcontract includes an arbitration
agreement on the terms of the arbitration agreement in cl 42 of the
Subcontract. In the circumstances, I will consider whether the conditions for
the court ordering a stay under s 7(2) of the Act are made out. It is not
necessary to consider separately whether a stay should be ordered under
Article 8.

The threshold question

33 Samsung says that there is no arbitration agreement in the Interim


Subcontract. Duro says that an arbitration agreement in the terms of cl 42 of
the Subcontract is a term of the Interim Subcontract, that the Duro Claims
are within the scope of that arbitration agreement and hence this court must
stay the proceeding and refer the matter to arbitration.

34 The authors of Dicey, Morris & Collins, The Conflict of Laws (15th ed)
say at [16.075] that there is a general principle of the law of international
arbitration that the arbitral tribunal has the power to determine its own
jurisdiction. This is known as the principle of kompetenz-kompetenz or
compétence-compétence. The principle does not require that a tribunal has
the exclusive power to determine its jurisdiction, nor that the court may not
determine whether the tribunal has jurisdiction before the tribunal has ruled
on its jurisdiction.

35 In this case, the issue is whether there is an agreement to arbitrate in the


Interim Subcontract and hence an agreement to arbitrate which covers the
Duro Claims. The kompetenz-kompetenz principle has the potential to give
rise to friction with the regime set out in the Act (and the Model Law),
which mandates a stay of court proceedings in favour of arbitration when the
conditions of a grant of a stay are satisfied. Specifically, under s 7(2) of the
Act the court must stay court proceedings which involve the determination
of a matter that, in pursuance of the arbitration agreement, is capable of
settlement by arbitration. A court hearing a stay application under s 7(2) of
the Act will necessarily have to take a view on the existence and scope of the
arbitration agreement in question. Only then can it decide whether a stay
must be granted under s 7(2) of the Act. The friction which I have referred
to may arise because any determination made by the court on the existence
and scope of the arbitration agreement may well intrude into the authority of
the arbitral's tribunal's kompetenz-kompetenz.

36 Where, on an application for a stay under s 7(2) of the Act, there is a


dispute whether any relevant arbitration agreement exists there is a threshold
question - what standard of review should the court adopt in determining the
existence and scope of the arbitration agreement. There are two competing
views of the approach the court should take. The first is that the court
should only undertake a prima facie review of the existence and scope of the
arbitration agreement. Thus, if the court is satisfied on a prima facie
standard that the conditions for the grant of a stay, that is there is an
arbitration agreement which covers the dispute at hand, have been met, it
should grant the stay and defer to the arbitral tribunal the determination of
whether those conditions have been satisfied. In Tomolugen Holdings Ltd v
Silica Investors Ltd [2015] SGCA 57 (Tomolugen Holdings), the Singapore
Court of Appeal referred to that as the prima facie approach. This approach
preserves the arbitral tribunal's kompetenz-kompetenz to examine the
existence and scope of its jurisdiction afresh and determine it fully:
Tomolugen Holdings at [29].

37 The second approach is that the court should determine on the balance
of probabilities the existence and scope of the arbitration agreement when it
hears a stay application. On this view, the court grants a stay if, and only if,
it is satisfied that the requirements for a grant of a stay have in fact been met.
The Singapore Court of Appeal referred to this as the full merits approach.
This approach has the advantage of expedience in that it allows the court to
pronounce with finality on an arbitral tribunal's jurisdiction in the first
instance, instead of deferring the question to the arbitral tribunal, only to
face the prospect of the same question coming back to the court in the event
of an appeal against the arbitral tribunal's jurisdictional ruling, or if the
unsuccessful party in the arbitration resists enforcement of the arbitral award
or applies to set it aside on the basis of the arbitral tribunal's lack of
jurisdiction: Tomolugen Holdings at [30].

38 This case is unusual in that if the court follows the full merits approach
in determining Duro's application for a stay, it will at the same time, leaving
aside questions of discretion, determine the merits of Samsung's claims in
the court proceeding.

39 Section 9 of the Arbitration Act 1996 (UK) provides that a party to an


arbitration agreement against whom legal proceedings are brought in respect
of a matter which under the agreement is to be referred to arbitration may
apply to the court to stay the proceeding so far as they concern that matter.
The English courts generally adopt the full merits approach when hearing
stay applications under s 9 of the Arbitration Act 1996 (UK) subject to a
residual discretion to stay the court proceedings under the court's inherent
jurisdiction so as to allow the arbitral tribunal to make a determination on its
own jurisdiction instead. Section 9 of the UK Act is in different terms from
s 7(2) of the Act. However, they are similar and both are similar to Article 8
of the Model Law and all are based on Article II(3) of the New York
Convention. Furthermore, the reasoning in the English cases applies to the
approach a court should take to s 7(2) of the Act notwithstanding the
differences in the language of the provisions.

40 In Golden Ocean at [59] Popplewell J summarised the principles


applicable to a situation where C brings proceedings against D in relation to
matters which D claims, but C disputes, are governed by an arbitration
agreement which confers kompetenz-kompetenz on the arbitral tribunal.
Popplewell J's summary includes the following principles:
(1) Section 9(1) permits the grant of a stay under the section only if D is party
to a written arbitration agreement which has agreed to refer to arbitration the
matters in respect of which C has brought the proceedings. Section 9(1) is
concerned with whether an agreement to arbitrate was concluded. It is not
concerned with whether such agreement is valid or enforceable or continues
in existence, which is the subject matter of s 9(4). It is also concerned with
whether the scope of the agreement to arbitrate extends to the matters in
issue between the parties in their substantive dispute. To bring himself
within the scope of section 9, D must establish that such an agreement was
concluded, and that its terms apply to the underlying dispute...

...

(5) It is for D to satisfy the court that he comes within s 9(1) before the court
can grant relief under that section. It is not enough for him to show merely
an arguable case that he is party to a concluded arbitration agreement which
has agreed to refer to arbitration the matters in respect of which C has
brought the proceedings. Unless the court is satisfied that that is so, there is
no jurisdiction under the section to stay proceedings. The court must
therefore determine the dispute if it affects the question whether D comes
within s 9(1). If it cannot do so on the written evidence at the hearing of the
application, it must direct a trial of that issue before granting a stay under s
9. It may however decline to direct a trial of the issue and grant a stay under
its inherent jurisdiction without resolving the issue.

41 The English position was also summarised by Aikens LJ, with whom
Mann J and Laws LJ agreed, in Joint Stock Co 'Aeroflot Russian Airlines' v
Berezovsky [2013] EWCA CIV 784; 2 Lloyd's Rep 242 (Berezovsky):
[T]here is a burden on the party asserting that there is: (a) a concluded arbitration
agreement as defined in the 1996 Act; and (b) that it covers the disputes that are the
subject of the court proceedings, to prove that this is the case. This is borne out by
the authorities. If the party seeking a stay cannot prove both (a) and (b), then there
is no jurisdiction to grant a stay under section 9(1) and (4) of the AA 1996.
However, if the court considers that it cannot decide those issues for itself in a
summary fashion on the written evidence, it has two other options, as this court
made clear in Ahmed Al-Naimi (T/A Buildmaster Construction Services) v
Islamic Press Agency Inc. It can direct an issue to be tried, pursuant to CPR Pt
62.8(3), or it can stay the proceedings (under its inherent jurisdiction) so that the
putative arbitral panel can decide the issue of the existence of the arbitration
agreement, pursuant to section 30 of the AA 1996. If the court decides that it will
and can determine whether or not there was a concluded arbitration agreement on
the written evidence before it then, in my view, the authorities establish that it is for
the party asserting the existence of the concluded arbitration clause to prove it on a
balance of probabilities. As I point out below, the position appears to be different if
the court decides, on an application for a stay, that it cannot, on the materials before
it, determine whether there was a concluded arbitration agreement.

Under section 9(4) the court 'shall grant a stay' unless 'satisfied' that the arbitration
agreement is 'null and void, [or] inoperative … '. This means, in my view, that
once the first party has established the existence of an apparently concluded
relevant arbitration agreement and that it covers the matters in dispute in the
proceedings, it is for the party resisting a stay to 'satisfy' the court that the
apparently existing arbitration agreement is 'null and void'. That was the position
under the old law, ie section 1 of the Arbitration Act 1975, which provision first
gave statutory effect in English law to the New York Convention. This court has
said that this remains the position under the AA 1996, albeit without elaborating on
its reasoning [73] - [74].

42 In Tomolugen Holdings the Singapore Court of Appeal departed from


the English position and adopted the prima facie approach.

43 The issue was recently addressed by Gleeson J in Rinehart v Rinehart


(No 3), when considering an application that the court stay the proceedings
before it under s 8(1) of the Commercial Arbitration Act 2010 (NSW) which
provides:
A court before which an action is brought in a matter which is the subject of an
arbitration agreement must, if a party so requests not later than when submitting the
party's first statement on the substance of the dispute, refer the parties to arbitration
unless it finds that the agreement is null and void, inoperative or incapable of being
performed.

In that case, there was a dispute as to the enforceability of various alleged


arbitration agreements and as to the scope of the alleged arbitration
agreements. The respondents contended that those issues should be resolved
by arbitration. The applicants contended that they should be determined by
the court. Gleeson J held that the language of s 8(1) and s 16 and the
authorities her Honour considered led to the conclusion that the existence of
an apparently valid arbitration agreement is sufficient to establish for the
purposes of s 8(1) and s 16 of the NSW Act that there is a valid arbitration
agreement between the parties to the court proceedings. The next question
was whether the dispute in the court proceedings, or any part of it, fell within
the scope of the arbitration agreement. The parties seeking the stay must
prove that the dispute in the court proceedings falls within the scope of the
arbitration agreement. However, there is a question as to the standard to
which the applicant for a stay must prove that a matter is the subject of the
arbitration agreement. Gleeson J referred to two contending standards of
proof that the proceeding is brought in a matter which is the subject of
arbitration agreement:

(a) does it require an arguable case or sustainable argument that the


matters(s) in the court proceedings are the subject of an arbitration
agreement; or

(b) does it require the parties seeking the stay to prove, on the balance of
probabilities, that matter(s) in the court proceedings are the subject of
an arbitration agreement?

Gleeson J referred to a number of authorities including Golden Ocean,


Berezovsky and Robotunits Pty Ltd v Mennel [2015] VSC 268, [297] and
concluded:
In my view, the approach in Robotunits is consistent with the approach articulated
in Berezovsky, which I respectfully consider to be correct for the reasons given by
Aitkens LJ. Thus, in my view, the correct approach is to decide on the balance of
probabilities whether, on the proper interpretation of the relevant arbitration
agreement, a matter arising in the proceeding falls within the scope of the
agreement. This will generally involve a characterisation of the matter, without an
assessment of the merits of the disputes arising from the matter. However, in some
cases, it may be necessary to consider the merits of a claim or defence said to be the
subject of an arbitration agreement in order to be satisfied that there is a relevant
'matter'. For example, if the application of the release is a matter which falls within
the scope of an arbitration agreement, the mere fact that the release's application is
asserted will not justify a finding as to the existence of a matter the subject of the
arbitration agreement if there is no sustainable argument that the release potentially
operates to bar or preclude the claims the subject of the dispute.

44 I will follow the full merits approach adopted by Gleeson J in Rinehart


v Rinehart (No 3), Popplewell J in Golden Ocean and Aikens LJ in
Beresovsky. Section 8 of the Commercial Arbitration Act 2010 (NSW) and
s 9 of the Arbitration Act 1996 (UK) are in different terms to s 7(2) of the
Act but are to a similar effect. The question in Rinehart v Rinehart (No 3)
is different from that in this case. In this case the Duro Claims clearly fall
within the scope of an arbitration agreement in the terms of cl 42 of the
Subcontract modified to apply to the Interim Subcontract; the question is
whether an arbitration agreement in those terms is a term of the Interim
Subcontract under which the Duro Works are to be performed. In my
opinion the correct approach to that question is to decide on the balance of
probabilities whether, on the proper interpretation of the Interim
Subcontract, the arbitration agreement is a term of the Interim Subcontract
and hence whether the Duro Claims fall within the scope of an arbitration
agreement in the Interim Subcontract. If the party seeking a stay cannot
prove the existence of an arbitration agreement that covers the disputes that
are the subject of the court proceedings then the conditions for staying the
proceedings under s 7(2) of the Act have not been met.

45 In Berezovksy Aikens LJ said that if the court considers that it cannot


decide that issue for itself in a summary fashion on the written evidence, it
has two other options. It can direct an issue to be tried or it can stay the
proceedings under its inherent jurisdiction so that the putative arbitral panel
can decide the issue of the existence of the arbitration agreement. In this
case the court is able to determine whether or not there is an existing
arbitration agreement that covers the disputes in this proceeding. That
matter was fully argued before the court.

46 In this case, the question comes down to whether the terms of the
Interim Subcontract include an arbitration agreement in the terms of cl 42 of
the Subcontract. I will now turn to that question.

Terms of Term Sheet are terms of Interim Subcontract

47 Samsung says that the terms of the Term Sheet, including cl 3.2(b), are
terms of the Interim Subcontract. Clause 3.2 is:
Governing Law

(a) This Term Sheet is governed by the law in force in Western Australia.

(b) Each party irrevocably submits to the non-exclusive jurisdiction of courts


exercising jurisdiction in Western Australia and courts of appeal from them
in respect of any proceedings arising out of or in connection with this
agreement. Each party irrevocably waives any objection to the venue of any
legal process in these courts on the basis that the process has been brought
in an inconvenient forum.

(c) In any court proceedings arising out of or related to this Term Sheet or the
Interim Subcontract, the court shall award to the prevailing party, if any, the
costs and legal fees reasonably incurred by the prevailing party in
connection with the court proceedings.

48 Samsung says that cl 3.2(b) is inconsistent with an arbitration


agreement in the terms of cl 42 of the Subcontract. Clause 42 is:
42.1 Notice of dispute

If a difference or dispute (together called a 'Dispute') between the parties arises in


connection with the subject matter of the Subcontract, including Dispute
concerning:

(a) a Contractor's Representative's Direction; or

(b) a Claim

Then either party shall, by hand or by registered post, give the other and the
Contractor's Representative a written notice of Dispute adequately identifying and
providing details of the Dispute.

Notwithstanding the existence of a Dispute, the parties shall, subject to clauses 39


and 40 and clause 42.5, continue to perform the Subcontract.

42.2 Conference

Within 14 days after receiving a notice of Dispute, the parties shall confer at least
once to resolve the Dispute or to agree on methods of doing so. At every such
conference each party shall be represented by a person having authority to agree to
such resolution or methods. All aspects of every such conference except the fact of
occurrence shall be privileged.

If the Dispute has not been resolved within 28 days of service of the notice of
Dispute or such longer period as the parties may agree in writing, that Dispute shall,
subject to the Dispute being a Pass Through Claim and the operation of the Pass
Through Provisions, be and is hereby referred to arbitration.

42.3 Arbitration

The arbitration shall be administered by the Singapore International Arbitration


Centre with the UNCITRAL Arbitration Rules. The appointing authority shall be
the Singapore International Arbitration Centre. The number of arbitrators shall be
three. The language used in the arbitral proceedings shall be English. The place of
arbitration shall be Singapore.

42.4 Joinder and Consolidation Disputes

...

42.5 Summary Relief

Nothing herein shall prejudice the right of a party to institute proceedings to


enforce payment due under the Sub-contract or to seek injunctive or urgent
declaratory relief.

49 Therefore, Samsung says, the terms of the Subcontract as modified by


the terms set out in the Term Sheet and its schedules for the performance of
the Duro Works do not include an arbitration agreement in the terms of the
second paragraph of cl 42.2 of the Subcontract.

50 Duro says that the terms of the Interim Sub-contract include a dispute
resolution clause in the terms of cl 42 of the Subcontract, which includes the
arbitration agreement. Duro advances two separate grounds in support of
that contention. First, Duro says that the Term Sheet is an instrument
separate from the Interim Subcontract and the jurisdiction clause in the Term
Sheet is not a term of the Interim Subcontract. Secondly, Duro says that if
the jurisdiction clause in the Term Sheet is a term of the Interim Subcontract,
it is not inconsistent with and does not modify the dispute resolution clause
of the Subcontract, including the arbitration agreement, by excluding it and
therefore the arbitration agreement is a term of the Interim Subcontract.

Governing clause is part of Interim Subcontract

51 Duro says that the Term Sheet contains transitional provisions that
cause the Interim Subcontract to come into effect, terms that address the
negotiation and execution of the Substitute Subcontract and terms that
address matters arising from the termination of the Subcontract. Duro says
that the governing law and jurisdiction clauses, cl 3.2(a) and (b), of the Term
Sheet are not terms of the Interim Subcontract. I do not agree for the
following reasons.

52 The Term Sheet is an instrument by which the parties made a legally


enforceable agreement or agreements. The agreement or agreements relate
to Duro performing the Duro Works which the Term Sheet describes as the
Interim Subcontract, to the negotiation and execution of a further
replacement contract which is described as a Substitute Subcontract and to
the continuation of Duro's liability under the Subcontract. In my opinion it
is not accurate or helpful to describe the Term Sheet as an agreement
separate and distinct from the Interim Subcontract. The relevant issue is
whether cl 3.2 of the Term Sheet is a term of or applying to the Interim
Subcontract. That is a question of construction.

53 Section 3 of the operative part of the Term Sheet, in which cl 3.2(b) is


found, is headed 'General'. That is some indication that it applies to the
whole of the agreement or agreements created by the Term Sheet. Clause
3.2(a) says that the Term Sheet is governed by the law in force in Western
Australia. The ordinary and natural meaning of that provision is that the
agreement or agreements in the Term Sheet are governed by the law of
Western Australia, not that the instrument alone is governed by Western
Australian law or that some of the arrangements or promises in the Term
Sheet are governed by the law of Western Australia but not others. Clause
3.2(b) provides that each party submits to the non-exclusive jurisdiction of
Western Australian courts in respect of any proceedings arising out of or in
connection with 'this agreement'. The natural and ordinary meaning of that
provision is that it applies to the whole of the agreement created by the Term
Sheet, including the arrangements or promises which constitute the Interim
Subcontract.

54 Clause 3.2(b) is a term of, or applies to, the Interim Subcontract which
is an agreement in the Term Sheet. The next question is whether cl 3.2(b) of
the Term Sheet is inconsistent with and modifies the terms of the
Subcontract so as to result in the arbitration agreement in cl 42 of the
Subcontract not being a term of the Interim Subcontract.

The Interim Subcontract and the terms of the Subcontract

55 To determine whether the Interim Subcontract includes a term in the


same terms as the arbitration agreement in cl 42 of the Subcontract the court
must first construe the incorporating clause in the Term Sheet in order to
determine the width of the incorporation of the terms of the Subcontract into
the Interim Subcontract. The incorporating cl 2(a) is:
The parties agree and acknowledge that, on and from the Start Date, Duro will
continue to perform the scope of works set out in Schedule 2 (Duro Works) under
this Term Sheet which will become legally binding on the parties and will apply as
a binding agreement between the parties (Interim Subcontract), and Duro shall in
good faith continue to perform the Duro Works under the Interim Subcontract. The
Interim Subcontract is on the same terms as the Subcontract as modified by the
terms set out in this Term Sheet and its schedules for the performance of the Duro
Works. The parties acknowledge and agree to negotiate in good faith and make
such additional changes as are logically or practicably required considering the
Duro Works and execute a Substitute Subcontract which is based on the terms of
the Subcontract, as modified in this Term Sheet, as soon as reasonably possible.

56 The meaning of a term of a commercial contract is to be determined by


what a reasonable business person would have understood that term to mean;
it will require consideration of the language used by the parties, the
surrounding circumstances known to them and the commercial purpose or
objects to be secured by the contract: Electricity Generation Corporation v
Woodside Energy Ltd [2014] HCA 7; (2014) 251 CLR 640 [35].

57 The sentence 'the Interim Subcontract is on the same terms as the


Subcontract as modified by the terms set out in this Term Sheet and its
schedules for the performance of the Duro Works' is arguably ambiguous.
The words 'for the performance of the Duro Works' might be read to be
qualifying the words 'the terms set out in this Term Sheet' and 'the schedules'
or they might be read as qualifying only the words 'the schedules'. The
ordinary grammatical meaning of the sentence is that the words 'for the
performance of the Duro Works' refer to the subject which immediately
precedes them, the schedules, and not the words 'this Term Sheet'. The
ordinary grammatical meaning of the sentence is that the Interim
Subcontract is on the same terms as the Subcontract as modified by the
terms set out in the Term Sheet and the Schedules.

58 I have set out earlier in these reasons the circumstances in which the
Interim Subcontract was made. Samsung terminated the Subcontract on 21
February 2014. Samsung and Duro then entered into a replacement
subcontract for Duro to continue to perform the Duro Works, which was a
subset of the Subcontract Works which Duro had been performing under the
Subcontract. The Interim Subcontract was to be a temporary contract until
they negotiated and executed a replacement contract which was referred to
in the Term Sheet as the Substitute Subcontract. The parties agreed that the
Interim Subcontract and subsequently the Substitute Subcontract are to be on
the same terms as the Subcontract with some modifications. Obviously, the
scope of works and subcontract sum had to be modified or altered. Those
things and some other key terms and conditions as set out in Schedule 1 to
the Term Sheet were modified or altered. The purpose of the Interim
Subcontract was to make a temporary contract by which Duro continued to
perform part of the original Subcontract Works on the same terms as the
Subcontract with modifications until the parties negotiated and executed a
replacement contract - the Substitute Subcontract - on the terms and
conditions of the Subcontract as modified by the Schedules of the Term
Sheet, that is the key terms and conditions set out in Schedule 1, the scope of
works set out in Schedule 2 and the new procurement milestones and
liquidated damages set out in Schedule 3 and any other terms and conditions
the parties consider are reasonable or necessary that directly relate to the
terms and conditions as set out in those Schedules. In those circumstances cl
2.1(a) means that the Interim Subcontract is on the same terms as the
Subcontract except as modified by the terms and conditions set out in the
Schedules to the Term Sheet and any other modifications or alternations
made expressly or by necessary implication by the terms of the Term Sheet.
To put that another way, the meaning of cl 2.1(a) is that the terms of the
Subcontract are modified by the terms of the Term Sheet only to the extent
that they are inconsistent with a term or terms of the Term Sheet or a term or
terms of the Term Sheet show a clear intention that the term or terms of the
Subcontract are not to be terms of the Interim Subcontract or are altered or
supplemented by a term or terms of the Term Sheet.

59 That approach is consistent with the arguments advanced by the parties.


Samsung argued that cl 3.2 of the Term Sheet is inconsistent with an
arbitration agreement in the terms of cl 42 of the Subcontract and therefore
the arbitration agreement is not a term of the Interim Subcontract. Duro
argued that the arbitration agreement in the Subcontract and cl 3.2 of the
Term Sheet may stand together and are both terms of the Interim
Subcontract.

Samsung says the Arbitration Agreement is excluded from the Interim Sub-
contract

60 Samsung says that cl 3.2 of the Term Sheet is inconsistent with an


arbitration agreement in the terms of cl 42 of the Subcontract for the
following reasons. Clause 3.2 of the Term Sheet addresses the concepts of
governing law and jurisdiction. It is fundamentally different from the
dispute resolution clause in cl 42 of the Subcontract. It is inconsistent with
that clause which requires any disputes that were notified and not able to be
resolved consensually to be referred to arbitration. There is no equivalent in
the Term Sheet and no reference at all to arbitration. Rather, the parties in
the Interim Subcontract have moved from one form of dispute resolution,
arbitration, which had been used in the Subcontract, to a different form of
dispute resolution in the Interim Subcontract - dispute resolution by judicial
determination. Clause 3.2(b) has a wide reach. The words 'any proceedings'
are of wide import. The expressions 'arising out of or in connection with'
and 'arising out of or related to' are to be given a wide or generous
construction: Comandate Marine Corp v Pan Australia Shipping Pty Ltd
[2006] FCAFC 192; (2006) 157 FCR 45 [162] - [166].

61 Samsung referred to Monde Petroleum SA v Westernzagros Ltd [2015]


EWHC 67 (Comm) (Monde Petroleum), [44] in which Popplewell J said
that a new and inconsistent dispute resolution provision raises the
presumption that the parties intended to impeach the dispute resolution
agreement within the earlier agreement. In Monde Petroleum
Westernzagros engaged Monde under a consultancy services agreement
(CSA) to assist Westernzagros in conducting and maintaining an exploration
and production sharing agreement which Westernzagros was negotiating
with the Kurdistan Regional Government in Iraq. The CSA contained an
arbitration clause. Westernzagros stopped paying the monthly fee invoiced
by Monde under the CSA and purported to terminate it. Westernzagros
disputed that the unpaid amounts invoiced by Monde, which included a
milestone payment, were due. The parties then entered into a termination
agreement, under which Westernzagros was to pay Monde's disputed
invoices in full and there was a mutual release and waiver of all claims by
each party against the other in respect of the CSA. The termination
agreement included a clause that the agreement shall be governed by and
construed in accordance with the laws of England and Wales and the parties
'herein irrevocably attorn to the exclusive jurisdiction of the courts of
England and Wales'. Monde brought proceedings in the Commercial Court
and also commenced arbitration proceedings but later withdrew its
arbitration claims. Westernzagros counterclaimed in the arbitration seeking
declarations of non-liability under the CSA. The arbitral tribunal held that it
had no jurisdiction to determine Westernzagros' counterclaims for
declaratory relief. Westernzagros contended that the arbitration agreement
and the CSA was not terminated or superseded by the termination
agreement. Monde contended that it was. Popplewell J held that the
arbitration clause in the CSA was superseded by the jurisdiction clause in the
termination agreement. Popplewell J held that where there was more than
one agreement between the same parties, and they contained conflicting
dispute resolution provisions, the presumption of one stop adjudication
dictated that the parties would not be taken to have intended that a particular
kind of dispute would fall within the scope of each of two inconsistent
jurisdiction agreements. The provisions would fall to be construed on the
basis that they were mutually exclusive in the scope of their application,
rather than overlapping, if the language and surrounding circumstances so
allowed. The jurisdiction clause in the termination agreement had to be
construed on the basis that the parties were likely to have intended that it
should supersede the clause in the earlier agreement and apply to all disputes
arising out of both agreements. The language of the termination agreement
was supportive of the presumption that the parties had intended to supersede
the arbitration clause in the first agreement. It had been expressed to be an
exclusive jurisdiction clause, its wording suggested that the parties had
intended a formulation that would include disputes as to what rights were
extant under the first agreement at the time of the termination agreement and
the verb 'attorn' suggested a transfer of jurisdiction, not merely a conferral of
jurisdiction.

Duro says arbitration agreement is not inconsistent with jurisdiction clause

62 Duro referred to English cases considering an exclusive jurisdiction


clause and an arbitration agreement. In Ace Capital Ltd v CMS Energy
Corp [2008] EWHC 1843 (Comm) the claimant, as lead underwriter under
certain insurance policies, applied for an injunction to restrain the insured, a
Michigan corporation, from continuing proceedings commenced by it
against the underwriters in Michigan. The policies contained an English law
and arbitration clause and also a service of suit or jurisdiction clause. The
claimant sought an injunction precluding the Michigan company from
proceeding in Michigan arguing that the service of suit clause did not entitle
the Michigan company to sue the underwriters on the merits in the US.
Christopher Clarke J granted an injunction restraining the Michigan
company from proceeding in Michigan. Christopher Clarke J said:
The arbitration clause in the present case does not exclude any particular grievances
from arbitration. On the contrary it provides that all disputes arising under, out of,
or in relation to the policy shall be arbitrated. In those circumstances the law's
policy in favour of arbitration provides a strong impetus (i) not to read the Service
of Suit clause as removing from the scope of arbitration, at the option of the
assured, the sort of disputed claim most likely to arise under a policy, i.e. for
payment: and (ii) to confine the clause so as to not to give the assured an option to
have determined in any court of the Union the merits of disputes which the parties
agreed to have determined by LCIA arbitration.
Such an interpretation still leaves the Service of Suit clause with meaningful scope.
It enables the assured to found jurisdiction in any US Court, including its home
court, to declare the arbitrable nature of the dispute, to compel arbitration, to
declare the validity of an award, to enforce an award, or to confirm the jurisdiction
of US courts on the merits in the event that the parties agree to dispense with
arbitration. Use of the clause for those purposes would not detract from the
arbitration clause. The fact that the New York Convention should mean that there
ought to be little difficulty in enforcing a London award in the United States does
not mean that there is no benefit in having an acceptance of personal jurisdiction by
Ace in each State of the Union [81] - [82].

63 In Sulamerica Sia Macional De Seguros SA v Enesa Engenharia SA


[2012] EWHC 42 (Comm) the claimant insurers instituted arbitration
proceedings and upon the insured defendant obtaining a temporary anti-suit
injunction in Brazil, the claimant applied to the English court for an anti-suit
injunction. The contract contained Brazilian law and exclusive jurisdiction
clauses but also provided for London arbitration if mediation failed. The
arbitration clause incorporated the supervisory jurisdiction of the English
courts and the governing law of the agreement to arbitrate was English law.
The judge granted the claimant's application, finding that giving full width to
the Brazilian exclusive jurisdiction clause would have effectively excluded
the right to arbitrate and this was not the parties' intention. The court said:
The English courts, when faced with an exclusive jurisdiction clause and an
arbitration agreement, look to the strong legal policy in favour of arbitration and the
assumption that the parties, as rational businessmen, are likely to have intended any
dispute arising out of the relationship into which they have entered to be decided by
the same tribunal. Unless expressly provided otherwise, the parties must be taken
to have agreed on a single tribunal for the resolution of all disputes. A liberal
approach to the words chosen by the parties in their arbitration clause must now be
accepted as part of our law. I follow in this regard the comments of Christopher
Clarke J. In the present case, on the construction that I have held, all disputes or
differences can be and must be referred to arbitration under the terms of Condition
12, but if that is so, what is left of the exclusive jurisdiction of the courts of Brazil
under Condition 7? The answer is very little in practice - much the same as found
by Christopher Clarke J in paragraph 82 of the ACE decision. It enables the parties
to found jurisdiction in a court in Brazil to declare the arbitrable nature of the
dispute, to compel arbitration, to declare the validity of the award, lo enforce the
award, or to confirm the jurisdiction of the Brazilian courts on the merits in the
event that the parties agree to dispense with arbitration. It specifically operates to
prevent the parties proceeding in another court on the merits. Use of the Condition
7 rights for these purposes does not detract from the arbitration clause but gives the
meaning. Furthermore, enforcement in Brazil against Brazilian parties is self-
evidently a realistic possibility [47] - [48].
64 Samsung submits that Ace Capital and Sulamerica and other cases
referred to by Duro have no bearing in the present situation because they
involved cases where the parties' contract included both a jurisdiction and
arbitration clause in one contract. The court in each of those cases was
required to determine, between the two clauses, which should be given
priority or how they should or could be read together. Further, Samsung
says, Australian courts do not approach the construction of commercial
contracts with any predisposition in favour of arbitration or presumptive
approach to questions of construction of arbitration clauses and refers to
Rinehart v Welker [2012] NSWCA 95 [120] - [122] Bathurst CJ and [204]
per McColl JA in support of that proposition.

65 In Rinehart v Welker the appellant sought an order that proceedings


brought by the respondents alleging misconduct in the appellant's conduct as
trustee of a family trust of which they were the beneficiaries be stayed on the
basis that the respondents had earlier signed a settlement deed requiring
them to refer disputes under the settlement deed to confidential mediation
and arbitration. Bathurst CJ considered the construction and scope of the
relevant clause of the settlement deed. His Honour said that the approach to
be adopted in relation to the construction of such clauses is no different to
the construction of any other contractual provisions: they are to be
construed objectively. His Honour said that arbitration clauses should not be
construed narrowly. But the words of the clause cannot be given a meaning
they do not have to satisfy a perceived commercial purpose: the scope of
disputes covered by an arbitration clause must depend on the language of the
clause. Further, it is not appropriate to construe arbitration clauses
irrespective of language in accordance with the presumption that the parties
are likely to have intended any dispute arising out of the relationship into
which they have entered to be decided by the same tribunal unless the
language makes it clear the certain questions were intended to be excluded:
[120] - [121].

Approach to construing arbitration and jurisdiction clauses

66 Each of the cases referred to by the parties considered different


circumstances and different questions from those which arise in this case.
Nevertheless, they support the following principles or approach. First, it is
to be presumed that rational business people who are parties to contracts
dealing with the same or a related subject matter intend all questions arising
out of their legal relationship to be determined in the same forum. Secondly,
the possibility of fragmentation may be inherent in the scheme of the parties'
agreements and clear agreements must be given effect to even if this may
result in a degree of fragmentation in the resolution of disputes between the
parties. Thirdly, such fragmentation is productive of increased expense and
delay and gives rise to a risk of inconsistent findings between a court and an
arbitral tribunal which rational businessmen are likely to have intended to
avoid. Fourthly, in the final analysis, the question whether a jurisdiction
clause in a subsequent agreement is inconsistent with and supersedes an
arbitration agreement in an earlier agreement is a question of construction
and the words of the subsequent agreement are to be given effect so far as it
is commercially rational to do so.

Arbitration agreement is a term of Interim Subcontract

67 I approach the question of whether cl 3.2 of the Term Sheet is


inconsistent with an arbitration agreement in the terms of cl 42 of the
Subcontract and hence whether the arbitration agreement is incorporated in
to the Interim Subcontract by considering the text, context and purpose of
the terms of the Term Sheet. For the following reasons I conclude that an
arbitration agreement in the terms of cl 42 of the Subcontract is a term of the
Interim Subcontract.

68 It is possible to construe cl 3.2(b) of the Term Sheet and cl 42 of the


Subcontract in a way that allows them to co-exist. Clause 42 can be read
harmoniously with cl 3.2(b) by construing the 'proceedings' to which cl
3.2(b) refers to be proceedings which a party may institute under the terms
of the dispute resolution clause in the terms of cl 42 of the Subcontract or
other proceedings which a party may commence consistently with cl 42.
Clause 3.2(b) of the Term Sheet does not provide that each party submit to
the jurisdiction of Western Australian courts in respect of any difference or
dispute arising out of or in connection with the Interim Subcontract but
rather provides for submission in respect of 'any proceedings' arising out of
or in connection with the agreement. That is, if a party commences in a
Western Australian court a proceeding which arises out of or in connection
with the agreement then the other party submits to the jurisdiction of the
Western Australian court. The dispute resolution clause, cl 42 of the
Subcontract, whilst providing that any difference or dispute between the
parties which arises in connection with the subject matter of the Subcontract
is to be referred to arbitration, at cl 42.5 provides for three instances where a
party may institute proceedings - a party may institute proceedings to
enforce payment due under the Subcontract or to seek injunctive or urgent
declaratory relief. Duro has twice within the last few months commenced
such proceedings for an interlocutory injunction restraining Samsung from
taking any step to enforce the Security under the Subcontract: Duro
Felguera Australia Pty Ltd v Samsung C&T Corporation [2015] WASC
484; Duro Felguera Australia Pty Ltd v Samsung C&T Corporation [2016]
WASC 119. There are other proceedings which the parties to the Interim
Subcontract might commence consistently with the arbitration agreement in
cl 42 of the Subcontract including proceedings to enforce any arbitration
award or to confirm the jurisdiction of the Western Australian courts on the
merits in the event that the parties agree to dispense with or waive the right
to arbitration.

69 The Term Sheet is a brief document. It provides that the Interim


Subcontract is on the same terms as the Subcontract as modified by the
terms set out in the Term Sheet and the schedules. That is, the terms of the
Subcontract are to be terms of the Interim Subcontract except insofar as they
are modified by the Term Sheet and the schedules. The arbitration
agreement in the Subcontract provides for the resolution of all differences
and disputes between the parties in connection with the subject matter of the
Subcontract including claims which are widely defined. The jurisdiction
clause in the Term Sheet does not provide for the resolution of all such
differences or disputes. It provides only for 'proceedings' arising out of or in
connection with the agreement. The natural and ordinary meaning of the
jurisdiction clause is that it provides for each party to submit to the non-
exclusive jurisdiction of Western Australian courts in respect of relevant
proceedings. It does not provide that all disputes or differences arising out
of or in connection with the Interim Subcontract are to be resolved by
litigation.

70 Considerations of commercial convenience favour construing the Term


Sheet to incorporate an arbitration agreement in the terms of cl 42 of the
Subcontract. Indeed, the result of construing the jurisdiction clause, together
with cl 2.1(a) of the Term Sheet to displace the arbitration agreement results
in a commercially inconvenient outcome which should not be readily
attributed to rational business people. The arbitration agreement in cl 42
survived the termination of the Subcontract. Therefore, any disputes falling
within that arbitration agreement must be referred to arbitration. The Interim
Subcontract provides for Duro to continue to perform some of the work that
was the subject of the Subcontract. It would be inconvenient if disputes
concerning work under the Subcontract must be referred to arbitration and
disputes concerning the continuation of the work under the Interim
Subcontract must be resolved by litigation. Furthermore, the Term Sheet
provides by cl 2.2(b), subject to clause 2.1(a), if directed by Samsung, Duro
will execute a Substitute Subcontract that incorporates the terms and
conditions of the Subcontract as modified by schedules of the Term Sheet
together with any other terms and conditions that Samsung and Duro
consider are reasonable or necessary that directly relate to the terms and
conditions as set out in the schedules of the Term Sheet. That is, in the
absence of any other terms and conditions agreed by Samsung and Duro,
Samsung may direct Duro to execute a Substitute Subcontract that
incorporates the terms and conditions of the Subcontract as modified by
schedules of the Term Sheet not as modified by cl 3.2 of the Term Sheet.
Therefore, such a Substitute Subcontract would include an arbitration
agreement in the terms of cl 42 of the Subcontract. The result, if the
arbitration agreement in those terms is not part of the Interim Subcontract
would be that disputes concerning works under the Subcontract would be
referred to arbitration, the continuation of the works under the Interim
Subcontract would be resolved by litigation in Western Australian courts and
the continuation of the works under the Substitute Subcontract would be
referred to arbitration. That is an outcome business people are unlikely to
have intended.

Relief claimed by Samsung is within scope of the arbitration agreement

71 A 'matter' for the purposes of s 7(2) means some right or liability in


dispute which is susceptible of settlement as a discrete controversy: cf
Tanning Research Laboratories Inc v O'Brien [1990] HCA 8; (1990) 169
CLR 332 (Tanning Research) per Deane and Gaudron JJ; Flint Inc NZ Ltd
v Huhtamaki Australia Pty Ltd [2004] VSCA 166; (2014) 289 FLR 30
(Fink Ink).

72 A 'matter' is something more than a mere issue that falls for decision:
cf Tanning Research per Deane and Gaudron JJ. In Comandate Marine
Corp v Pan Australia Shipping Pty Ltd Allsop J said in construing s 7(2)(b)
of the International Arbitration Act:
… the word 'matter' in s 7(2)(b) can be seen to be a reference to the differences
between the parties or the controversy that are or is covered by the terms of the
arbitration agreement. That is, such part (or all) of the differences that fall within
the scope of the arbitration agreement. It is that body of differences which is to be
capable of settlement by arbitration.

The above approach conforms to the requirement expressed in Tanning Research


to ascertain the 'matter' by reference to the subject matter in dispute and the
substantive questions for determination in the proceedings and, necessarily, by
reference to the scope of the arbitration agreement [235] - [238].

73 A 'matter' for the purposes of s 8(1) may or may not comprise the whole
dispute in any given court proceeding: Tanning Research per Deane and
Gaudron JJ; Fink Ink at 53 [87(c)] per Nettle JA.

74 The dispute between the parties in this court proceeding is whether the
Duro Claims constitute 'proceedings arising out of or in connection with this
agreement' for the purposes of cl 3.2(b) of the Term Sheet and are therefore
to be determined in this court or whether they are a dispute between the
parties arising in connection with the subject matter of the Interim
Subcontract and by reason of an arbitration agreement in the Interim
Subcontract in the terms of cl 42 of the Subcontract are to be referred to
arbitration. I have found that there is in the Interim Subcontract an
arbitration agreement in the terms of cl 42 of the Subcontract. The Duro
Claims are a dispute between the parties which arises in connection with the
subject matter of the Interim Subcontract and therefore disputes which are
to be referred to arbitration. It follows that this proceeding involves the
determination of a matter that, in pursuance of the agreement, is capable of
settlement by arbitration unless the matter is excluded from the scope of the
arbitration agreement by cl 42.5 of the Subcontract as incorporated into the
Interim Subcontract.

75 Clause 42.5 contains a qualification to, or carve out from, the


agreement to refer disputes to arbitration. Clause 42.5 carves out from the
arbitration agreement the right of a party to institute proceedings to seek
urgent declaratory relief. The relief sought must in fact be urgent, a matter
to be determined objectively. Clause 42.5 must be read in the context of the
dispute resolution provisions of the contract as a whole. Those provisions
show the parties preference that disputes arising under the contract are to be
decided by arbitration. This preference may be set at naught if cl 42.5 is not
limited to cases which are in fact urgent. In my opinion the Duro Claims are
not urgent. There is no reason of urgency that they should not be determined
in the arbitration. The declarations sought by Samsung cannot derive
urgency from the need to resolve the Duro Claims urgently. There is no
reason of urgency that whether the Duro Claims fall within an arbitration
agreement in the Interim Subcontract should not be resolved by the arbitral
tribunal.

The proceedings should be stayed

76 The Interim Subcontract includes an arbitration agreement in the terms


of cl 42 of the Subcontract. The scope of the arbitration agreement covers
the determination of the Duro Claims. That is, the parties have agreed by the
Interim Subcontract, incorporating an arbitration agreement in the terms of
cl 42 of the Subcontract, that the Duro Claims are to be determined by
arbitration. In substance the matter in controversy in this proceeding is
whether the Duro Claims are within the jurisdiction of the arbitral tribunal to
which disputes under the arbitration agreement are to be referred. The
answer is that they are. This proceeding involves the determination of a
matter that, in pursuance of the arbitration agreement in the Interim
Subcontract, is capable of settlement by arbitration. Section 7(2) of the Act
requires that the court stay the proceeding and refer the parties to arbitration
in respect of that matter. It is unnecessary to determine Duro's alternative
claims. It is inappropriate to do so given the basis on which I have found
that the proceedings should be stayed.

Conclusion

77 The proceedings should be stayed and the whole of the matter or


matters the subject of this proceeding should be referred to arbitration.

CatchwordArray: Arbitration Agreements - Declaratory relief - Stay application - Kompetenz-Kompetenz -


Whether there is an agreement to arbitrate - Where there are both arbitration and jurisdiction clauses
agreed by the parties - Where arbitration agreement covers the dispute - Section 7 of the International
Arbitration Act - Proceedings stayed - Turns on own facts

Potrebbero piacerti anche