ACTIVITY LIST OF ACTIVITIES

NO.

1 Site Survey/ Inspection

2 Mobilization

3 Clearing and Grubbing

4 Construction of Bunkhouse and Temporary Utilities

5 Construction of Temporary Fence

6 Lay-outing/Staking-out

7 Site Excavation and Leveling

8 Excavation for Septic Tank and Drainage system

9 Fabrication of form-works for Septic Tank and Drainage system

10 Fabrication of re-bars for Septic Tank and Drainage system

11 Installation of forms for Septic Tank and Drainage system

12 Installation of Scaffolds for Septic Tank and Drainage system

13 Pouring of Concrete

14 Curing of Concrete

15 Column, Footing, and Wall Footing Excavation

16 Fabrication Column and Footing forms

17 Fabrication of Re-bars for Columns and Footings

18 Installation of Re-bars for Columns and Footings

19 Pouring of Concrete Footings

20 Curing of Concrete

21 Installation of Scaffolds for Ground Floor Columns

22 Installation of forms for Ground Floor Columns

23 Pouring of Concrete for Ground Floor Columns

24 Removal of Forms for Ground Floor Columns

25 Curing of Concrete

26 Fabrication of Re-bars for Plinth Beam

27 Installation of Forms for Plinth Beam

28 Installation of Re-bars for Plinth Beam

29 Pouring of Concrete for Plinth Beam

30 Removal of Forms for Plinth Beam

31 Curing of Concrete

32 Back-filling of Excavations

33 Grading and Gravel fill on slab-on-grade

34 Installation of Re-bars for slab-on-grade


VILLARIAS, MARIAN NIKKA M.

35 Installation of Electric and Plumbing conduits for slab-on-grade

36 Pouring of Concrete

37 Curing of Concrete

38 Fabrication of form-works for 2nd Floor beams and lintel beams

39 Fabrication of Re-bars for 2nd Floor beams and lintel beams

40 Installation of scaffolds for 2nd Floor beams and lintel beams

41 Installation of Re-bars for 2nd Floor beams and lintel beams

42 Installation of forms for 2nd Floor beams and lintel beams

43 Fabrication of form-works for 2nd floor suspended slab

44 Fabrication of 2nd suspended slab re-bars

45 Installation of scaffolds for 2nd floor suspended slab

46 Installation of forms for 2nd floor suspended slab

47 Installation of re-bars for 2nd floor suspended slab

48 Installation of Electrical and Plumbing conduits for 2nd Floor suspended slab

49 Pouring of Concrete for 2nd level beams and suspended slabs

50 Removal of forms

51 Curing of Concrete

52 Installation of CHB wallings for ground floor

PLATE NO.1

LIST OF ACTIVITIES

PROJECT TITLE: PROPOSED CONSTRUCTION OF G+3, CATEGORY III QUARTER AT PHUENTSHOLING

PROJECT LOCATION: THIMPHU, BHUTAN