Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
To cite this article: Kartik Modi, Harshal Lowalekar & N.M.K. Bhatta (2018): Revolutionizing supply
chain management the theory of constraints way: a case study, International Journal of Production
Research, DOI: 10.1080/00207543.2018.1523579
Revolutionizing supply chain management the theory of constraints way: a case study
Kartik Modia , Harshal Lowalekarb∗ and N.M.K. Bhattab∗∗
a Godrej & Boyce Mfg Co Ltd, Mumbai, India; b Indian Institute of Management Indore, Indore, India
(Received 30 January 2018; accepted 4 September 2018)
This research describes in detail an application of theory of constraints (TOC) and its resulting benefits on the supply chain
performance of India’s largest lock manufacturing company over a period of seven years. Using TOC’s thinking process,
the core constraints that had limited the company’s performance in the areas of production, distribution, supply group and
projects were identified and eliminated. TOC’s unique approach helped the company achieve a significant reduction in its
finished goods, raw material and work-in-process inventories at various levels across the supply chain. The stock-outs and
excess in the distribution system nearly disappeared. The existing lead times saw a drastic reduction while the availability of
items increased to nearly 100% despite significant decrease in inventory levels in the supply chain. The inventory turns of the
distributors and retailers more than tripled and their profitability increased significantly. The overall sales of the company
grew nearly three times during the six years post TOC implementation. TOC’s holistic approach helped the company to
double its profits and improve its cash position during the Great Recession.
Keywords: TOC; current reality tree; replenishment solution; CCPM
1. Introduction
Theory of constraints (TOC) claims that all real-life systems are inherently simple, not complex (Goldratt and Cox 1984;
Goldratt 1990; Dettmer 1997; Goldratt 2008; Schragenheim, Dettmer, and Patterson 2009; Cox III and Schleier 2010). It
also suggests that most of the so-called problems observed in such systems are not really problems but merely symptoms
which are present due to very few root-causes or constraints (Dettmer 1997, 1998). Moreover, treating such symptoms does
not result in a substantial improvement in performance and the only way to eliminate such symptoms is by addressing the
true constraints of the system (Goldratt 1994; Scheinkopf 1999; Goldratt 2008).
This research shows how TOC’s idea of inherent simplicity is valid even for large supply chains which have been
traditionally considered to be very complex (Lambert, Cooper, and Pagh 1998; Lambert and Cooper 2000). What makes
the task of managing typical supply chains so complicated is the fact that there are a large number of suppliers who supply
a large variety of raw materials to multiple manufacturing sites who then produce a huge variety of products, by different
processes, and ship them, using several methods of transportation, to a vast number of direct customers and OEMs located
all across the world (Davis 1993). The presence of high degree of uncertainty at the level of suppliers, production and
customers further adds to the confusion (Davis 1993). The main contribution of this research is to demonstrate through a
case study that:
(1) Even large supply chains are inherently simple.
(2) Multitude of problems observed in supply chains such as poor responsiveness, low flexibility, high inventory levels,
low availability, limited product variety, slow rate of new product introduction, inferior forecasts, poor coordination,
low profitability are merely symptoms originating from a very few root causes.
(3) Simple solutions do exist for solving seemingly complex supply chain issues and such solutions invariably involve
addressing the root causes. Companies can achieve a real turnaround by focussing only on these core problems
instead of trying to improve multiple aspects of their supply chains independently.
(4) Most of the root causes are in the form of policies which are based on age-old assumptions and companies cannot
achieve real improvement until they rid themselves of such policies.
(5) TOC can provide a powerful way of achieving effective supply chain integration by eliminating impediments in
implementation (see Power 2005) due to its capability to generate win-win solutions for multiple stakeholders.
We take a case of supply chain of India’s largest lock manufacturing company with a strength of nearly 1000 employees
and selling 1200 SKUs through a network of more than 1000 distributors and 20,000 retailers spread across 600 cities in
the country. Until 2008, the company was making small incremental growth in its revenues and profits despite being the
market leader. Domestic and international competitors were closing the gaps in distribution and luring its channel partners.
Production was facing problems of huge work-in-process (WIP), long lead times, poor quality levels and was struggling
to achieve monthly plans. It was unable to cope up with the changing needs of the market. Due to company’s poor due
date performance on its customised orders, the projects of many institutional customers were regularly getting delayed.
Because of a huge variety of SKUs it was also becoming increasingly difficult to manage the distribution business. There
was a significant mismatch between what the market required and what was being supplied. A large variety of SKUs was
not available at most of the distributors and retailers. The distributors and retailers were struggling with the problems of
chronic shortage of some SKUs and huge surplus of others. Their return on investment (ROI) was extremely low and they
were facing serious cash problems due to carrying huge inventories. The company was unable to introduce new products
regularly and its market share was falling.
We show in this research how TOC’s thinking process (TP) tools were used to identify the core constraints that had
limited the performance of supply chain of the case company. Using a rigorous cause and effect analysis, a limited set of
factors which were responsible for a large variety of problems in the supply chain were identified. TOC-based solutions
were implemented over a period of seven years to eliminate the identified set of constraints. TOC’s unique approach led to a
complete turnaround in the supply chain performance of the case company. The alignment of the entire business enterprise
including people, suppliers, distributors and dealers at all levels, functions and geographies with the TOC way of working
helped the company to sustain the performance over a long period of time.
2. Literature review
The development of the TOC methodology is credited to Dr. Eliyahu Goldratt who introduced the basic tenets of TOC
through a business novel titled ‘The Goal’ (see Goldratt and Cox 1984). ‘The Goal’ demonstrated how the throughput of
manufacturing operations was limited due to very few constraints and chasing for local efficiencies in such systems could
lead to disastrous results (Goldratt and Cox 1984). Goldratt gave further details of the TOC methodology in his latter books
where he showed how this methodology was not restricted to manufacturing systems and could be applied to other real-life
systems as well (see Goldratt 1990). He suggested that constraints of physical nature were easier to identify and eliminate
as compared to policy constraints which were quite prevalent for majority of systems (Goldratt 1990). In order to identify
such policy constraints he provided some logical tools which came to be known as the ‘Thinking Process Tools’ in TOC
literature (Dettmer 1998). While the initial applications of TOC were limited to manufacturing, Goldratt showed how TOC
can be applied to distribution (Goldratt 1994), technology management (Goldratt, Schragenheim, and Ptak 2000), projects
(Goldratt 1997), sales and marketing (Goldratt 1994; Goldratt, Eshkoli, and Brownleer 2009), finance (Goldratt 1991),
managing people and developing strategy (Goldratt 1999).
A comprehensive review of the published literature on TOC body of knowledge can be found in Rahman (1998),
Mabin and Balderstone (1999) and Blackstone (2001). Kim, Mabin, and Davies (2008) gives a detailed review of published
literature on TOC thinking processes ( TOCTPs).
Woeppel (2016) explains how TOC should be implemented in manufacturing organisations. Mabin and Balder-
stone (2003) and Noreen, Smith, and Mackey (1995) describe several successful TOC applications in manufacturing
companies. Umble, Umble, and Murakami (2006) and Pegels and Watrous (2005) describe the implementation of TOC
and resulting benefits in two separate manufacturing firms. Boyd and Cox III (1997) demonstrate the usefulness of cause
and effect trees in understanding the effects of in-plant performance measures through a case study of a manufacturing plant.
Scoggin, Segelhorst, and Reid (2003) describe an application of TOCTP in identifying and eliminating core problems in a
manufacturing environment.
TOC has also been applied in the domains of strategy formulation (Boyd, Gupta, and Sussman 2001), project manage-
ment (Rand 2000; Umble and Umble 2000), performance measurement (LockamyIII and Spencer 1998; Noreen, Smith,
and Mackey 1995; Boyd and Cox III 1997; Smith 1999; Wahlers and Cox 1994), enterprise resource planning (Umble and
Umble 2001), services (Siha 1999; Klein and Harowitz 1996; Motwani, Klein, and Harowitz 1996) and supply chain man-
agement (Simatupang, Wright, and Sridharan 2004; Rahman 2002). Some important applications of TP tools have also been
reported in poultry industry (Chaudhari and Mukhopadhyay 2003), blood banking (Lowalekar and Ravi 2017), aerospace
industry (Chou, Lu, and Tang 2012) and healthcare (Breen, Burton-Houle, and Aron 2002). Pacheco Lacerda, Augusto Cas-
sel, and Henrique Rodrigues (2010) show an application of TP tools along with service engineering concepts in improving
processes at a higher education institution. Sadat, Carter, and Golden (2013) develop a TOC-based model for the health
systems funded by public. Spector (2011) discusses the case where a firm’s business model itself is its primary constraint
International Journal of Production Research 3
instead of the internal, external or a strategic constraints. Gupta, Sahi, and Chahal (2013) develop a unique TOC-based
framework to improve a firm’s market orientation for maximising its business performance.
Some of the recent works by Sobreiro and Nagano (2012), Sobreiro, Mariano, and Nagano (2014) and de Souza et al.
(2013) look at the performance of TOC-based best product-mix heuristic and compare it to other established methodologies
such as MILP. Oglethorpe and Heron (2013) identify and categorise major constraints observed in the context of local food
supply chains in the UK through multiple case studies. Tsou (2013) uses time series methods to dynamically adjust the
target inventory levels in supply chains facing continuously changing demand. Costas et al. (2015) show the application of
TOC in reducing the bullwhip effect in supply chains using a multi-agent simulation model. Gupta and Andersen (2012) and
Gupta and Andersen (2018) show using simulation how local measurements of throughput dollar days and inventory dollar
days can significantly improve the entire supply chain performance. A recent stream of papers has focused exclusively on
studying and/or enhancing the performance of the Drum Buffer Rope (DBR) method in high variety job shops and flow
shops (Thürer et al. 2017), pure and general flow shops (Thürer and Stevenson 2018) and shops with shifting bottlenecks
(Thürer et al. 2017; Thürer and Stevenson 2018).
While there are plenty of studies which discuss TOC implementation in different parts of organisations we did not come
across any comprehensive study in the published literature which describes an application of TOCTP and an end-to-end
implementation of TOC solutions in large supply chains. The main contribution of this research is to demonstrate, through
a real-life case study, how to plan for an enterprise-wide implementation of TOC which includes suppliers, production,
engineering, distributors and retailers.
(1) Retail customers: Retail customers consist of the contractors, carpenters, architects and end users who purchase
locks and security systems from the company’s dealers and retailers. The retail distribution business amounts to
65% of the division’s total revenue.
(2) Institutional Customers: The institutional customers primarily consist of project management consultants, site
engineers, purchase managers and architectural firms who often require customised products and security solutions.
Locks are graded in terms of five levels of security strength. The security strengths 1 to 4 consist of mechanical locks,
which are typically mass customised, while the security strength 5 consists of electronic locks, which are typically made to
order (MTO). The basic lock production system at Godrej Locks is shown in Figure 1. The pins used in a lock are made
by machining while the cylinders, washers, plates, bolts and casings are manufactured using die-casting, press-working and
machining. Some components are also sourced from external suppliers. Godrej also sells some locks which are imported
from other countries.
In 2008, GL was under tremendous pressure to maintain its profitability and market share. Seventy per cent of the locks
market in India was controlled by unorganised players. The entry of several foreign-based players, depreciation of currency,
slow growth of real estate, increase in labour costs and increased imports from China had further eroded its sales. Driven
by the need to create a win-win relationship for itself, its channel partners and its customers, to raise entry barriers for the
competition and to achieve rapid growth the company decided to go ahead with an enterprise-wide implementation of TOC
in 2008.
(2) Unsatisfied suppliers: Suppliers experienced lot of disruptions in their production schedules and suffered from
poor capacity utilisation due to frequent changes in GL orders. They also ended up with unwanted stocks at the
end of each month. They complained that GL was not ready to increase margins on the raw materials and instead
pressurised them to show year-on-year reduction in costs.
(3) Misalignment of production with the market demand: Marketing complained that the actual production quantities
of various SKUs were not as per the monthly production plan; some SKUs were under produced while others were
over produced. In some cases, raw materials were diverted to produce certain items which had low demand at the
expense of others with high demand.
(4) Huge inventories in production: To maintain high efficiencies items were produced in large batches inside the plant.
The level of raw material and WIP inventories in production was huge.
(5) Unclear priorities between MTO and make to stock (MTS): Higher priority in production was given to MTO over
MTS items. But MTO fetched much lesser margins as institutional customers negotiated hard on the prices.
(6) Conflicts between production and marketing: Production often complained that marketing used to accept cus-
tomised orders without checking the current load on the plant. There were frequent changes in the production
plans during the month and a significant amount of time and capacity was lost in making and breaking set-ups.
Marketing, on the other hand, claimed that production was not flexible enough to meet the changing market
needs.
(7) High production costs: The inventory carrying and maintenance costs were very high. The defect rate in production
was also quite high which led to increased rejection and rework. Numerous cost reduction programmes and kaizens
were initiated in the plant. Several labour intensive operations were outsourced to take advantage of cheaper labour.
GL was also increasing the share of imported goods from China instead of making them in-house. While such
programmes claimed to have reduced costs significantly their true benefits on the bottom line were not visible.
4.5. New product development, new product introduction andengineered to order projects
(1) Slow pace of new product introduction: Engineering was under tremendous pressure to come up with newer and
better products. Sales and marketing were unable to provide useful inputs to engineering on the real customer
needs. The distributors were not excited about keeping new products. Despite spending large sums of money on
development and advertising new products were not available in several regions.
(2) Lack of resources: New product development (NPD), new product introduction (NPI) and engineered to order
(ETO) projects took more resources, time and budget than planned and still failed on the quality standards. The
scope and priorities of such projects was also frequently changed which created regular conflicts between resource
and project managers.
Many of the UDEs described above are quite commonly observed in other supply chains (see Shah 2009; Jacobs, Chase,
and Lummus 2014; Christopher 2016; Hugos 2018). Applications of TOC to eliminate some of the UDEs in the context
of supply chains have also been reported in literature. For example, (Umble, Umble, and Murakami 2006) report an appli-
cation of TOC in case of a Japanese manufacturing company struggling with the problems of long lead times, poor due
date performance, huge WIP, high inventory levels, over and under production, high operating costs, etc. Goldratt (1994),
Goldratt (2008), Goldratt, Eshkoli, and Brownleer (2009), Schragenheim, Dettmer, and Patterson (2009) and Vector Con-
sulting (2015) use a cause and effect approach to identify and eliminate the root causes behind various supply chain problems
such as large inventory levels, slow rate of new product introduction, poor forecast accuracy, shortage and excess of items,
etc. Schragenheim, Dettmer, and Patterson (2009) and Cox III and Schleier (2010) address the issue of MTO-MTS joint
6 K. Modi et al.
production and vendor reliability. Goldratt (1999) discusses the problems of ineffective marketing and month-end syn-
drome. Goldratt (1997), Newbold (1998), Steyn (2001) and Leach (1999) describe the TOC approach for solving problems
in projects such as high project durations, frequent budget, time and cost overruns.
(119) they were not able to keep up with the changing orders (121) and could not always deliver all the raw materials
required as per the final plan (123). As procuring raw materials from other suppliers at a short notice was often quite
expensive3 (124) purchasing was generally not keen on buying those items which were in shortage at the last moment
(128). As a result the production did not always receive all the raw materials required as per the final monthly production
plan (129).
8 K. Modi et al.
The other effect of GL changing its orders continuously was that the suppliers used to experience a lot of disruption
in their production schedules (125). Due to its stronghold over the suppliers, the division was able to get away with not
accepting the items which did not figure in the final production order (122) thereby leaving suppliers with some unwanted
stock every month (126). This led to poor overall capacity utilisation at the suppliers (127) and increased their costs. Also
their inability to supply all the raw materials as desired by Godrej (123) despite long replenishment lead times (114) created
an additional pressure.
It is worth noting that the effects of changing orders downstream in the supply chain were worst felt at the suppliers’
end (bullwhip effect) thus making capacity planning extremely difficult. Due to large fluctuations in the order sizes, most of
the suppliers needed to work with temporary employees and could not maintain a stable workforce, which had implications
for quality. They were under constant pressure from purchasing to become exclusive suppliers for the company and to show
year-on-year reduction in their manufacturing costs.
the entire order (339). Sometimes short cuts were taken to minimise the delays (341) which further affected the quality
(342) and ultimately increased the rework and rejection rates (343). Due to poor due date performance the quoted lead
times at GL for future customised orders kept increasing (340). Because of regular delays in customised orders, the insti-
tutional customers had to suffer heavy losses (345). Added to that the problems of low quality, missed operations and long
quoted lead times meant that the institutional customers were not happy with the current performance of the division (346).
Long lead times also meant higher outstanding amount with the institutional customers (348) and long cash conversion
cycles.
10 K. Modi et al.
The end result of over and under production was that the final production quantities were not in line with the monthly
plans (220). Production complained that delivery issues were because of marketing accepting orders and promising unre-
alistic times without checking current load on the system (349). Marketing, on the other hand, blamed production for not
being fast and flexible enough (347) and for not producing what the market wanted (227). It is ironic that while the pro-
duction was criticised for not meeting the monthly plan, the plan itself was based on SKU level sales forecasts which were
highly inaccurate (224). In fact, in a push based system, it was even inappropriate to call them sales forecasts. They were
production forecasts at best as marketing was essentially forecasting based on the past production. There was no real data
on what the market really wanted as what was not produced could never be sold and hence would not show up in the sales
data. The end result of all this was that the production quantities of different SKUs were completely out of sync with the
actual demand at the distributors’ end (226). It is safe to say that what was being produced by GL had little or no correlation
with the what the end consumer really wanted.
retailers were not fully aware of the features and benefits of Godrej products. The sales team also could not spend time to
understand from the retailers what kind of products the end consumers really wanted. Thus sales was not providing critical
inputs required for developing new products.
6. TOC implementation
TOC’s TP clearly showed that a limited set of constraints10 were responsible for poor performance of the entire GL supply
chain. In fact, most of these constraints were traditional company policies and practices which were based on some age-old
beliefs (Figure 9). It was obvious from the CRTs that if GL had to show radical improvement it was necessary to find ways
to eliminate these constraints. Also, any action that did not address these constraints was not likely to make any significant
impact.
In order to eliminate the identified constraints the company implemented TOC’s solutions in the areas of finance
and measurements (Throughput Accounting), production (Drum-Buffer-Rope), distribution (Replenishment Solution) and
projects (Critical Chain). The details of these solutions are provided in the next four subsections.
cost in rupees, waited in any part of the system. RRD indicated the magnitude of the total outstanding amount, in rupee days,
with the external partners. The new set of measurements for various people in the company are summarised in Table 1.
Based on their throughput-volume (T-volume) values the existing SKUs werecategorised into four buckets (see
Figure 10). For the low and medium T-volume SKUs a strategy of product rationalisation was adopted because of their
low contribution to the profit. The SKUs with high and very high T-volume were given the highest priority. Efforts were
made by marketing to maximise the sales of such SKUs.
International Journal of Production Research 15
just to keep efficiencies high at all stages in production, would only lead to build up of either WIP (in case the constraint
is internal) or finished goods inventory (in case the constraint is in the market), without actually increasing the throughput
of the system (Goldratt and Cox 1984; Schragenheim and Ronen 1990; Noreen, Smith, and Mackey 1995; Mabin and
Balderstone 1999).
Before implementing DBR, GL took few steps to bring down the existing production lead times by simplifying the
existing system. Production was segregated into components production and assembly plants and two separate warehouses
were constructed: (1) Components Finished Goods (CFG) warehouse to store the components and (2) Finished Goods (FG)
warehouse to store the assembled locks. De-linking the two stages was also useful in terms of aggregating demand at the
components level. The CFG warehouse also made it possible to provide single and explicit priorities for the components
production. The mode of production of all the items (MTA or MTO) inside the two plants was then changed to the DBR
system, the details of which are presented in next two subsections.
code system was used to determine the priority of MTO orders on the shop floor. The production buffer time was divided in
three zones and the orders running in the red zone were expedited to avoid missing the committed due dates.
About one-third of the total plant capacity was reserved exclusively for MTO. The internal CCRs were found and effec-
tively elevated to have at least 20% protective capacity. It was estimated that more than 20% of protective capacity was
required when dealing with the new clients. The work centre reports were also utilized to locate the most loaded stations.
Whenever a centre showed a work load of more than three days measures were taken to decrease its load such as over-
time, running on sundays, changes in shifts, transferring work to other centre if possible, etc. Whenever the protective
capacity dropped below 20% an alarm was raised and when it dropped below 10% any increase in sales was frozen to safe-
guard the current commitments. Delivery commitment for MTO was purely given on the basis of then available protective
capacity.
while increasing the overall throughput (Goldratt 1994; Schragenheim, Dettmer, and Patterson 2009; Schragenheim and
Dettmer 2000).
In order to get the buy-in from the distributors for the new TOC way of working Godrej Locks prepared an offer
document which explained in detail (similar to Section 5.3) how the challenges faced by the distributors were because of
the policies and actions of the company and its personnel. Some of the major changes proposed in the offer document were:
• GL salespersons targets would be changed from primary sales to secondary sales.
• Monthly target would be replaced by weekly targets (for secondary sales) in order to smoothen the sales, purchases
and hence the cash flow. Moreover, instead of lump-sum growth over the previous year, the aim would be to get
1% growth in sales week-on-week (WoW).
• Stock levels would be fixed by GL for every SKU kept in the distributor warehouse and no supply would be made
beyond this level.
• The distributors would provide information about the sales of different SKUs every day to GL so that they could
be replenished with the same quantity the next day.
• For any bulk or customised SKUs, distributors would place a separate order which would be treated as
an MTO.
The offer itself was titled ‘Inventory Turns Mafia Offer’ since it was aimed at increasing the distributor inventory turns
thereby increasing their ROI (see Goldratt 1994 and Cox III and Schleier 2010 for further details on mafia offers).
In the first phase the replenishment solution was implemented only till the level of the distributors with an objective of
ensuring 100% availability of SKUs in the distributor warehouses. In order to do so GL arranged for proper warehouse space
at the factory, branch and distributor levels in the specified regions (see Figure 11). To obtain the information of their daily
sales of various SKUs from the distributors, a simple but highly effective web-based system, known as dealer replenishment
system (DRS), was developed. DRS also provided reports on the secondary sales, closing inventory and buffer colour status
for SKUs at distributor warehouses.
The buffer level for any item in the distributor warehouse was determined based on the maximum possible consumption
in the average time required to replenish the item from the branch warehouse. The replenishment time was simply equal
to the transportation time from the branch warehouse to the distributor warehouse because of the 100% availability at the
branch warehouse. Similar formula was used to set the buffer levels in the branch warehouses. Accordingly, production or
purchase orders (for the traded items) and stock transfer orders for shipment from one stocking point to another immediate
stocking point downstream were generated in the ERP system. These orders were modified to incorporate the minimum
batch size, standard packing size and full truck load considerations.
The inventory levels at various warehouses were continuously monitored and suitably adjusted by DRS once in every
two to four weeks. A dynamic buffer management (DBM) system was employed to continuously monitor and adjust the
buffer levels in the various warehouses and for expediting related decisions.
The implementation began with a pilot of few selected distributors from different regions to ascertain the benefits of the
new system and to eliminate any lingering concerns from everyone’s mind. Once the pilot was successful GL went ahead
with a blitzkrieg nation-wide implementation within two weeks covering majority of the distributors based on their sales
value. These distributors were then presented a detailed ‘Inventory Turns’ offer. The success stories from the pilot were
cited as examples for reinforcement.
In the second phase of the implementation, the replenishment solution was rolled out to the retailers. Here, a major
challenge was to get the daily sales data from the retailers. This was overcome with the help of a simple mobile application
that made capturing the retailer sales data possible. Measurements in the system were further changed from secondary sales
to the tertiary sales from the retail outlets. The underlying philosophy behind this change was that unless and until an end
user bought a product, no one in the supply chain made any sale. Motivated by its overwhelming success, the replenishment
offer was eventually extended even to the international markets.
7. TOC results
Under the frequent replenishment system for raw materials with adequate stock-based buffers the shortage of raw materials
nearly disappeared and the inventory levels maintained in the stores reduced. The effective capacity of the plant increased
due to DBR since it was no longer producing items for future consumption at the expense of the ones required in the
immediate future. Because of choking the release of orders as per the capacity of the constraint and reduction in batch sizes,
the WIP in production fell sharply. Due to reduction in WIP and increased raw material availability, the manufacturing lead
times decreased significantly. The reduction in Yo-Yo operations reduced the lead times further and improved the quality
levels. As a result, the quoted lead times for MTO items decreased significantly and the on-time delivery for customised
orders improved greatly. Due to the frequent replenishment from plant and adequate stock buffers the availability of the MTA
items in finished goods warehouses increased to nearly 100%. Managing the production of MTO and MTA items became
simpler due to the common priority system based on buffer colour status. Due to the elimination of monthly production
value as the primary measurement, the tendency to ‘produce whatever is available’ in production disappeared. As the plant
only produced what was pulled from the finished goods warehouse and not based on erroneous monthly level forecasts, the
misalignment between the production and the actual demand from the distributors was minimised.
As a result of tremendous shrinkage in the lead times coupled with full availability of MTA items in its warehouses it
became possible for GL to promise a one stop solution for reliable delivery of customised orders. GL developed a mafia
offer for its institutional customers which promised them ‘reliability and speed of supplies from a single source’. This was
a remarkable offer as the institutional customers could never get a full kit of customised solutions from a single supplier in
the past. It also allowed GL to charge higher premium. Another mafia offer called as the ‘Vendor Managed Inventory’ offer
was developed for OEMs who were promised 100% availability of the critical SKUs in their warehouses at all times.
As the practice of the distributors deciding their order quantities gave way to automatic replenishment, their tendency
of ordering in bulk quantities towards the end of the month disappeared. Since the entire system worked on simple replen-
ishment the dependency on sophisticated forecasting algorithms was eliminated (Goldratt 1999). Due to the removal of
erroneous forecasts the resulting misalignment between the distributors’ stocks and the secondary sales was eliminated. As
the distributors’ stocks were replenished daily the inventory levels of different SKU held by the distributors reduced while
their availability increased significantly. Moreover, since the distributors were charged only for the items they sold and not
22 K. Modi et al.
for what they purchased, they were no more constrained by the cash blocked in huge piles of inventory. The release of
enormous amount of shelf space and cash allowed GL to stock more variety of SKUs at the distributor warehouses without
any additional risk for the distributors. A similar phenomenon was observed at the retailers who were also replenished on a
frequent basis. Due to the disappearance of excess stocks with the distributors and retailers their tendency of offering huge
discounts also vanished thereby improving the throughput from the existing products. Since the distributors and the retailers
did not struggle with cash problems, the credit collection period and the receivables reduced significantly (Figure 12(h)) and
the cash position of the division improved substantially (Figure 12(d)). The average inventory turns at the distributors more
than tripled thereby increasing their ROI. Moreover, stocking new higher throughput items further boosted their profits (and
that of everyone else in the supply chain). Their aversion to stocking newer SKUs and catering to more number of retailers
also vanished. The overall acceptance of new products by the retail increased. Because of the small replenishment lead times
between any two consecutive stocking points in the system GL became much closer to the end consumer (Goldratt 1999).
Due to less overall inventory in the supply chain it was possible to respond more quickly to the real market demand. The
rate of new product introduction became faster. The contribution of new products introduced in last three years (rolling) in
the total sales, also known as the New Product Vitality, increased (Figure 12(i)). The number of distributors and retailers
with GL itself increased significantly (Figure 13(e,f)). More than 800 distributors in 400 + cities joined the TOC way of
working (Figure 13(d)). The share of such distributors went up from 76% to 97%.
The division was able to eliminate the month-end syndrome by eliminating the monthly targets. The focus in sales and
marketing shifted from only selling to new ‘local area marketing and customer awareness initiatives’. The salespersons
did not have to run around to liquidate the excess stocks with the distributors and were able to actively participate in
demand generation activities. Specialized training programmes were designed for the influencers such as carpenters (through
carpenter clubs) and retailer salespersons. The number of carpenters in Godrej Locks Carpenter Club increased by 5 times
since 2008 and the growth in sales from such members increased by 55% from 2012 to 2014. The salespersons also imparted
training to the retailers on the features and usage of different products and were able to provide valuable feedback to
engineering for creating new line of products. The number of retailer salesmen trained by the company increased four-fold
since 2011. Moreover, the focus of the sales team shifted to promoting those products which gave higher throughput. The
sales of Hi-End locks (in the security strength of 3, 4, 5) more than doubled due to the product prioritisation initiatives.
International Journal of Production Research 23
Another major advantage of the pull-based system was that the inventories reduced as one moved from the factory ware-
house to the distributors. Pulling inventory upstream in the supply chain was advantageous as forecast error was minimal
upstream and the benefits of demand aggregation further lowered the inventory requirements in the chain (Goldratt 1994).
As a result the production planning at the plant and the suppliers14 became very smooth. The tendency to locally optimise
at all levels also reduced under the pull-based replenishment and new set of measurements. This helped the Godrej supply
chain to effectively counter the phenomenon of bullwhip effect.
The sales from customised solutions grew at a steady growth (Figure 13(h)). The sales from key accounts grew at
a CAGR (compounded annual growth rate) of 52%. The number of real estate developers with the company increased
2.5 times. The domestic retail and institutional sales grew by more than 200% (Figure 13(b,c)). The overall sales of GL
grew at 25%, twice the rate of the industry itself (12.5%) and it was able to double its profits within two years of TOC
implementation. Godrej Locks’ market share increased by nearly 35% and the gap with the nearest competitor widened
further. The major results from TOC implementation are summarised in Table 2.
of recording the sales of SKUs only at the end of the day. But since most of the records were kept manually this
proved to be very difficult. Another method was tried by recording the stock levels at such outlets only once in 2 to
3 days. This also did not work well as it caused frequent interference at the retail outlets and, at the same time, the
company needed to employ extra persons just to get the stock details.
(4) To grow sales and throughput the company decided to develop and grow adjacencies in architectural hardware
products. This resulted in a sudden increase in the range of products and put pressure on the entire supply chain to
work as per the TOC principles. It took few months to stabilise the system. During this period, however, there was a
lot of confusion and it required a huge effort in terms of recalibrating of the existing systems, regular communication
across all levels and educating the people in the entire value chain.
(5) Due to a slowdown in the real estate marker over the past few years, the developers have been demanding standard
and cheaper products. This has increased the pressure on maintaining the throughput.
9. Conclusion
This research provides a roadmap for implementing TOC in large supply chains. The case study shows how TOC can help
such supply chains in identifying few faulty policies which are limiting their growth. Most of the times such policies are
formulated on the basis of some age-old assumptions which are no longer valid and they can be truly disastrous as they
promote the behaviour of local optimisation. Such traditional policies can be found at all levels in supply chains including
production, distribution, marketing, sales, finance and projects. Moreover, because traditional policies are most difficult for
anyorganisation to change, companies can gain a true competitive advantage by successfully eliminating such constraints
(Goldratt 1999). As TOC presents a holistic approach of looking at large systems it can be extremely useful for the supply
chain managers in designing suitable policies which can align multiple stakeholders in the direction of the common goal.
One of the main contributions of this work is to show that simple solutions do exist, even for seemingly complex supply
chains, and that companies can eliminate a large variety of problems commonly observed in such supply chains and achieve
remarkable results in shorter time frames by focusing their attention only on a few constraints instead of trying to improve
in a piecemeal fashion all parts of their supply chains.
Notes
1. It is explained in Section 6 in detail how Godrej eliminated just these constraints and in the process eliminated most of the UDEs.
International Journal of Production Research 25
2. Large batch sizes was especially a problem with those suppliers who were supplying to multiple companies like Godrej. The lead
times of such suppliers could be really large because of huge WIP.
3. In some cases it was not even possible to get materials at short notice or in short quantities as many suppliers have a minimum order
size policy.
4. Quite clearly it was an accounting invention where an item produced during the month was recorded as an asset on the company
balance sheet. Since the asset was recorded at a value higher than the raw material costs after incorporating the ‘conversion costs’, it
was possible to make accounting profits just by producing items and storing them even if there was no immediate demand for such
items.
5. Because of the Little’s Law.
6. Since the distributors were ordering about one month worth of stock for a given SKU at a time they were able to order only a limited
variety of SKUs due to the cash constraint.
7. In most cases the next order was placed only at the start of the next month. Thus the items that ran out of stock in the first week
continued to be missing for the rest of month. Moreover, any shortage with distributors invariably resulted in a shortage in the entire
region as retailers could not get the desired supply for a long time.
8. The extent of lost sales at GL was directly dependent on the amount of time the fast selling SKUs were out of stock multiplied by the
throughput of such SKUs. While it was not easy to measure the extent of lost sales, the company estimated that it could be as high
as the current profits or even more. For similar problems involving assessing the impact of lost sales on the system performance the
readers may refer to (Goldratt 2008) and (Goldratt, Eshkoli, and Brownleer 2009).
9. A shortage invariably meant a lost-sales for the company as the retailer would push for a competitor’s product.
10. Entities numbered (101), (201), (301), (302), (310), (401), (422), (424), (506), (512), (607), (613) in Figures 2–8.
11. GL implemented the simplified version of DBR, also known as S-DBR, in which the market was assumed to be the ultimate constraint
(Schragenheim and Dettmer 2000). The plant did not have bottlenecks under S-DBR and operated with a capacity constrained
resource (CCR) with protective capacity and planned load (Schragenheim, Dettmer, and Patterson 2009).
12. Two more colours were commonly used: (1) black (B) to represent stock-outs and (2) white (W) to represent buffer exceeding green).
13. The time buffer for each product family was set equal to the half of the present lead time.
14. The number of suppliers covered under the milk-run system had been increasing steadily since 2008 (Figure 13(g)).
Disclosure statement
No potential conflict of interest was reported by the authors.
Supplemental data
Supplemental data for this article can be accessed here https://doi.org/10.1080/00207543.2018.1523579.
References
Blackstone, J. H.. 2001. “Theory of Constraints-a Status Report.” International Journal of Production Research 39 (6): 1053–1080.
Boyd, L. H, and Cox III, J. F.. 1997. “A Cause-and-Effect Approach to Analyzing Performance Measures.” Production and Inventory
Management Journal 38 (3): 25.
Boyd, L., M. Gupta, and L. Sussman. 2001. “A New Approach to Strategy Formulation: Opening the Black Box.” Journal of Education
for Business 76 (6): 338–344.
Breen, A. M., Burton-Houle, T., and Aron, D. C.. 2002. “Applying the Theory of Constraints in Health Care: Part 1-the Philosophy.”
Quality management in healthcare 10 (3): 40–46.
Chaudhari, C., and S. Mukhopadhyay. 2003. “Application of Theory of Constraints in an Integrated Poultry Industry.” International
Journal of Production Research 41 (4): 799–817.
Chou, Y.-C., Lu, C.-H., and Tang, Y.-Y.. 2012. “Identifying Inventory Problems in the Aerospace Industry Using the Theory of
Constraints.” International Journal of Production Research 50 (16): 4686–4698.
Christopher, M. 2016. Logistics & Supply Chain Management. Harlow: Pearson.
Cohen, I., A. Mandelbaum, and A. Shtub. 2004. “Multi-Project Scheduling And Control: A Process-based Comparative Study of the
Critical Chain Methodology and Some Alternatives.” Project Management Journal 35: 39–50.
Consulting, V. 2015. Apparent in Hindsight. Mumbai: TV18 Broadcast Ltd.
Costas, J., B. Ponte, de la Fuente, D., R. Pino, and J. Puche. 2015. “Applying Goldratt?s Theory of Constraints to Reduce the Bullwhip
Effect Through Agent-based Modeling.” Expert Systems with Applications 42 (4): 2049–2060.
Cox III, J., and J. Schleier. 2010. Theory of Constraints Handbook. New York: McGraw-Hill.
Davis, T. 1993. “Effective Supply Chain Management.” Sloan Management Review 34 (4): 35.
de Souza, F. B., Sobreiro, V. A., Nagano, M. S., and de Souza Manfrinato, J. W.. 2013. “When Less is Better: Insights from the Product
Mix Dilemma from the Theory of Constraints Perspective.” International Journal of Production Research 51 (19): 5839–5852.
Dettmer, H. W. 1997. Goldratt’s Theory of Constraints: A Systems Approach to Continuous Improvement. Milwaukee, WI: ASQ Quality
Press.
Dettmer, H. W. 1998. Breaking the Constraints to World-Class Performance. Milwaukee, WI: ASQ Quality Press.
26 K. Modi et al.
Goldratt, E. M. 1990. Theory of Constraints: What is This Thing Called the Theory of Constraints and How Should It be Implemented.
Great Barrington, MA: North River Press.
Goldratt, E. M. 1991. The Haystack Syndrome. Great Barrington, MA: North River Press.
Goldratt, E. M. 1994. It’s Not Luck. Great Barrington, MA: North River Press.
Goldratt, E. M. 1997. Critical Chain. Great Barrington, MA: North River Press.
Goldratt, E. M. 1999. TOC Self Learning Program. Accessed Nov 8, 2017. https://www.toc-goldratt.com/en/product/gsp-on-distribution-
and-supply-chain-pull-system-and-replenishment.
Goldratt, E. M. 2008. The Choice. Great Barrington, MA: North River Press.
Goldratt, E. M., and J. Cox. 1984. The Goal: A Process of Ongoing Improvement. Great Barrington, MA: North River Press.
Goldratt, E. M., I. Eshkoli, and J. Brownleer. 2009. Isn’t it Obvious?. Great Barrington, MA: North River Press.
Goldratt, E. M., and Fox, R. E.. 1986. The Race. Croton-on-Hudson, NY: North river press.
Goldratt, E. M., E. Schragenheim, and Ptak, C. A.. 2000. Necessary but not Sufficient. Great Barrington, MA: North River Press.
Gupta, M., and S. Andersen. 2012. “Revisiting Local TOC Measures in an Internal Supply Chain: A Note.” International Journal of
Production Research 50 (19): 5363–5371.
Gupta, M., and S. Andersen. 2018. “Throughput/Inventory Dollar-Days: TOC-Based Measures for Supply Chain Collaboration.”
International Journal of Production Research12: 1–17.
Gupta, M. C., Sahi, G. K., and H. Chahal. 2013. “Improving Market Orientation: The Theory of Constraints-based Framework.” Journal
of Strategic Marketing 21 (4): 305–322.
Hugos, M. H. 2018. Essentials of Supply Chain Management. Hoboken, NJ: John Wiley & Sons.
Jacobs, F. R., Chase, R. B., and Lummus, R. R.. 2014. Operations and Supply Chain Management. New York, NY: McGraw-Hill/Irwin.
Kim, S., Mabin, V. J., and J. Davies. 2008. “The Theory of Constraints Thinking Processes: Retrospect and Prospect.” International
Journal of Operations & Production Management 28 (2): 155–184.
Klein, J. M. D., and R. Harowitz. 1996. “The Theory of Constraints in Services: Part 1 – The Basics.” Managing Service Quality 6 (1):
53–56.
Lambert, D. M., and Cooper, M. C.. 2000. “Issues in Supply Chain Management.” Industrial Marketing Management 29 (1): 65–83.
Lambert, D. M., Cooper, M. C., and Pagh, J. D.. 1998. “Supply Chain Management: Implementation Issues and Research Opportunities.”
The International Journal of Logistics Management 9 (2): 1–20.
Leach, L. P. 1999. “Critical Chain Project Management Improves Project Performance.” Project Management Journal 30: 39–51.
Lockamy III, A., and M. Spencer. 1998. “Performance Measurement in a Theory of Constraints Environment.” International Journal of
Production Research 36 (8): 2045–2060.
Lowalekar, H., and Ravi, R. R.. 2017. “Revolutionizing Blood Bank Inventory Management Using the TOC Thinking Process: An Indian
Case Study.” International Journal of Production Economics 186: 89–122.
Mabin, V. J., and S. J. Balderstone. 1999. The World of the Theory of Constraints: A Review of the International Literature. Boca Raton,
FL: CRC Press.
Mabin, V. J., and Balderstone, S. J.. 2003. “The Performance of the Theory of Constraints Methodology: Analysis and Discussion of
Successful TOC Applications.” International Journal of Operations & Production Management 23 (6): 568–595.
Motwani, J., D. Klein, and R. Harowitz. 1996. “The Theory of Constraints in Services: Part 2 – Examples from Health Care.” Managing
Service Quality 6 (2): 30–34.
Newbold, R. C. 1998. Project Management in the Fast Lane: Applying the Theory of Constraints. Boca Raton, FL: CRC Press.
Noreen, E., D. Smith, and J. T. Mackey. 1995. The Theory of Constraints and its Implications for Management Accounting. Great
Barrington, MA: North River Press.
Oglethorpe, D., and G. Heron. 2013. “Testing the Theory of Constraints in UK Local Food Supply Chains.” International journal of
operations & production management 33 (10): 1346–1367.
PachecoLacerda, D., R. AugustoCassel, and L. HenriqueRodrigues. 2010. “Service Process Analysis Using Process Engineering And The
Theory of Constraints Thinking Process.” Business Process Management Journal 16 (2): 264–281.
Pegels, C. C., and C. Watrous. 2005. “Application of the Theory of Constraints to a Bottleneck Operation in a Manufacturing Plant.”
Journal of Manufacturing Technology Management 16 (3): 302–311.
Power, D.. 2005. “Supply Chain Management Integration and Implementation: A Literature Review.” Supply Chain Management: An
International Journal 10 (4): 252–263.
Rahman, S.-u. 1998. “Theory of Constraints: A Review of the Philosophy and Its Applications.” International Journal of Operations &
Production Management 18 (4): 336–355.
Rahman, S.-u. 2002. “The Theory of Constraints’ Thinking Process Approach to Developing Strategies in Supply Chains.” International
Journal of Physical Distribution & Logistics Management 32 (10): 809–828.
Rand, G. K. 2000. “Critical Chain: The Theory of Constraints Applied to Project Management.” International Journal of Project
Management 18 (3): 173–177.
Sadat, S., Carter, M. W., and B. Golden. 2013. “Theory of Constraints for Publicly Funded Health Systems.” Health Care Management
Science 16 (1): 62–74.
Scheinkopf, L. J. 1999. Thinking for a Change: Putting the TOC Thinking Processes to Use. Boca Raton, FL: CRC Press.
Schragenheim, E., and H. W. Dettmer. 2000. Manufacturing at Warp Speed: Optimizing Supply Chain Financial Performance. Boca
Raton, FL: CRC Press.
International Journal of Production Research 27
Schragenheim, E., and Dettmer, H. W. 2000. “Simplified Drum-Buffer-Rope: A Whole System Approach to High Velocity Manufactur-
ing.” Goal Systems International. Accessed 1 January 2018. http://www.goalsys.com/books/documents/S-DBRPaper.pdf.
Schragenheim, E., H. W. Dettmer, and J. W. Patterson. 2009. Supply Chain Management at Warp Speed: Integrating the System from End
to End. Boca Raton, FL: CRC Press.
Schragenheim, E., and B. Ronen. 1990. “Drum-Buffer-Rope Shop Floor Control.” Production and Inventory Management Journal 31
(3): 18–22.
Schragenheim, E., and B. Ronen. 1991. “Buffer Management: A Diagnostic Tool for Production Control.” Production and Inventory
Management Journal 32 (2): 74.
Scoggin, J. M., Segelhorst, R. J., and Reid, R. A.. 2003. “Applying the TOC Thinking Process in Manufacturing: A Case Study.”
International Journal of Production Research 41 (4): 767–797.
Shah, J. 2009. Supply Chain Management: Text and Cases. New Delhi: Pearson Education India.
Siha, S. 1999. “A Classified Model for Applying the Theory of Constraints to Service Organizations.” Managing Service Quality: An
International Journal 9 (4): 255–264.
Simatupang, T. M., Wright, A. C., and R. Sridharan. 2004. “Applying the Theory of Constraints to Supply Chain Collaboration.” Supply
Chain Management: An International Journal 9 (1): 57–70.
Smith, D. 1999. The Measurement Nightmare: How the Theory of Constraints can Resolve Conflicting Strategies, Policies, and Measures.
Boca Raton, FL: CRC Press.
Sobreiro, V. A., Mariano, E. B., and Nagano, M. S.. 2014. “Product Mix: The Approach of Throughput p er Day.” Production Planning
& Control 25 (12): 1015–1027.
Sobreiro, V. A., and Nagano, M. S.. 2012. “A Review and Evaluation on Constructive Heuristics to Optimise Product Mix Based on the
Theory of Constraints.” International Journal of Production Research 50 (20): 5936–5948.
Spector, Y. 2011. “Theory of Constraint Methodology Where the Constraint is the Business Model.” International Journal of Production
Research 49 (11): 3387–3394.
Stein, R. E. 2003. Re-Engineering the Manufacturing System: Applying the Theory of Constraints. Boca Raton, FL: CRC Press.
Steyn, H. 2001. “An Investigation into The Fundamentals of Critical Chain Project Scheduling.” International Journal of Project
Management 19 (6): 363–369.
Steyn, H. 2002. “Project Management Applications of the Theory of Constraints Beyond Critical Chain Scheduling.” International
Journal of Project Management 20 (1): 75–80.
Thürer, M., T. Qu, M. Stevenson, Li, C. D., and Huang, G. Q.. 2017. “Deconstructing Bottleneck Shiftiness: The Impact of Bottleneck
Position on Order Release Control in Pure Flow Shops.” Production Planning & Control 28 (15): 1223–1235.
Thürer, M., and M. Stevenson. 2018. “Bottleneck-Oriented Order Release with Shifting Bottlenecks: An Assessment by Simulationa.”
International Journal of Production Economics 197: 275–282.
Thürer, M., and M. Stevenson. 2018. “On the Beat of the Drum: Improving the Flow Shop Performance of THe Drum–Buffer–Rope
Scheduling Mechanism.” International Journal of Production Research 56 (9): 3294–3305.
Thürer, M., M. Stevenson, C. Silva, and T. Qu. 2017. “Drum-Buffer-Rope and Workload Control in High-Variety Flow and Job Shops
with Bottlenecks: An Assessment by Simulation.” International Journal of Production Economics 188: 116–127.
Tsou, C.-M. 2013. “On the Strategy of Supply Chain Collaboration Based on Dynamic Inventory Target Level Management: A Theory
of Constraint Perspective.” Applied Mathematical Modelling 37 (7): 5204–5214.
Umble, M., and E. Umble. 2000. “Manage Your Projects for Success: An Application of the Theory of Constraints.” Production and
Inventory Management Journal 41 (2): 27.
Umble, M. , E. Umble, and S. Murakami. 2006. “Implementing Theory of Constraints in a Traditional Japanese Manufacturing
Environment: The Case of Hitachi Tool Engineering.” International Journal of Production Research 44 (10): 1863–1880.
Umble, M., E. Umble, and Von Deylen, L.. 2001. “Integrating Enterprise Resources Planning and Theory of Constraints: A Case Study.”
Production and Inventory Management Journal 42 (2): 43.
Wahlers, J. L., and Cox, J. F.. 1994. “Competitive Factors and Performance Measurement: Applying the Theory of Constraints to Meet
Customer Needs.” International Journal of Production Economics 37 (2-3): 229–240.
Woeppel, M. 2016. Manufacturer’s Guide to Implementing the Theory of Constraints. Boca Raton, FL: CRC Press.