Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
2. No pipes with weld slag and spatters will be accepted at Blasting/Painting yard.
3. Whenever corrections are required as per the requirement, the pipe fabricator shall do it.
5. No Hot work is permitted on the pipe after coating. Hence all hot work activities like
external wrap coating, welding of support saddles etc. shall be completed before the pipe is
given for coating.
6. DCPPL/IOCL shall inspect the Pipes when they are delivered at DCPPL’s shop/yard.
These check points to be conformed and record in Coating Material Inspection report.
Note: - Coating Material shall be stored in a cool and dry place at temperature below 24 0 C (Preferably in
an Air Conditioned container/Room).
D) APPLICATION CONDITION:
3. Record will be maintained throughout the execution period. Reading will be taken once in
every 4 hours up to the time work is in progress. The frequency of reading should be
increased during adverse weather conditions.
4. While working in unfavorable weather conditions ( like monsoons ) check no flash rusting of
the blasted surface is take place till the time it receives a coat.
5. In case temperature goes below 10 deg C warming up the work front like use of halogen
lights, room heaters etc. to be adopted.
6. Humidity is to be taken at the location where the blasting/coating operations are taking
place.
a. Before welding of pipes edges, 50 mm from both the edges should be checked for
cleanliness. Mechanical/Solvent Cleaning should be carried out to remove the welding flux,
oil, grease etc form the pipe.
b. For Pipe low diameter pipes viz. 50mm to 500 mm, internal coating machine would be used.
First the inspection boom with WEBCAM would be allowed to check the surface wellness.
f. For pipes 600mm dia and above, weld joint would be coated manually and the procedure
would be followed as mentioned form step a to e.
1. Curing: The Initial cure and Final Cure shall be as given in respective product data sheets.
The data sheets give cure times as at 25 deg centigrade. The initial cure time shall come
down with increase in ambient temperature. The initial cure time is judged by touching the
coated surface with a gloved hand. Total track freeness shall indicate initial cure releasing
the Coated Component for further processing activities like, final coats, grinding, buffing
cleaning, DFT & holiday testing etc.
2. The final cure has relevance to taking the coated component into service. Hence, irrespective
of ambient temperatures the final cure period in terms of days as given in data sheet shall be
adhered to. Client will be specially informed by site personnel regarding the date when the
coated vessel/Pipe can be taken into service by means of an entry in the Final inspection
format.
3. Finish: It is to be noted that the coating will follow the profile of the substrate. Any
unevenness or other defects in the substrate will be in the finished coating also.
On completion of testing, any defects should be locally repaired as per the above Repair
procedure.