ATTACHMENT-5-3 CONSTRUCTION PROGRESS SUMMARY TABLE PER AREA

Progress for Week Ending : 30-Dec-16


A700 C600 C700 B600, C100~C500
Overall
(HMU Area) (Admin Bldg. Area) (Marine Area) (Off Site & Tank Area)
SL.NO. FWBS Summary Description
7.15% 8.38% 15.37% 69.10% 100%
Plan Actual Plan Actual Plan Actual Plan Actual Plan Actual
1 1000 General Civil 100.00% 100.00% 100.00% 99.93% 100.00% 100.00% 100.00% 99.99% 100.00% 99.99%
2 2000 Concrete Structure 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
3 3000 Steel Structure 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
4 4000 Building 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
5 5000 Equipment 100.00% 99.29% 100.00% 100.00% 100.00% 100.00% 99.88% 100.00% 99.74%
5 5000 Tank 100.00% 100.00% 100.00% 100.00%
6 6100 Piping Fabrication 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
7 6200 A/G Piping Installation 100.00% 96.52% 100.00% 100.00% 100.00% 99.48% 100.00% 99.46% 100.00% 99.04%
8 6300 U/G Piping Installation 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
9 7000 Instrumentation & Control 100.00% 98.72% 100.00% 100.00% 100.00% 97.36% 100.00% 99.87% 100.00% 99.23%
10 8000 Electrical 100.00% 99.82% 100.00% 99.90% 100.00% 99.73% 100.00% 99.90% 100.00% 99.85%
11 9000 Insulation 100.00% 34.41% 100.00% 76.54% 100.00% 77.19% 100.00% 68.60%
12 A000 Painting 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
13 B000 Fireproofing 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%

Total 100.00% 96.81% 100.00% 99.88% 100.00% 99.27% 100.00% 99.62% 100.00% 99.35%