Market Conditions :
Contract Particulars : Cost Fluctuation : Competitive Tender List
Type of Contract: X Yes RM Int/JV/L
Schedule of Rates/
Spec & Drawings Serial
Provisional Sum RM
Contract Period Stip. by Client : 1 month Prime Cost Sum RM
Contract Period Offered by Builders : x Preliminaries RM
Number of Tenders Issued : X Contingencies RM
Number of Tenders Received : X Contract Sum RM X
*** PG - PAGE
CL - CLAUSE
Elemental Cost Analysis - Form 2 0
(As per Form1)
SUMMARY OF ELEMENTAL COSTS
GROSS FLOOR AREA: 6 m2 (For One Typcial Block) TENDER DATE :
Preliminaries Shown Separately
Element Total Cost Cost/m2 Elemental Elemental Element Reinforced Reinforcement Formwork
Of Element GFA Unit Unit Rate Ratio Concrete
RM RM Quantity RM per m2 GFA m3 kg m2
1 Substructure
1A Piling
1B Work Below Lowest Floor Finis #REF! #REF! X X X
Group Elemental Total #REF! #REF!
2 Superstructure
2A Frame #REF! #REF! X X X
2B Upper Floors X X X
2C Roof x x
2D Stairs
2E External Walls #REF! #REF!
2F Windows & External Doors X X
2G Internal Wall & Partitions
2H Internal Doors
Group Element Total - -
3 Finishes
3A Internal Wall Finishes X X
3B Internal Floor Finishes X X
3C Internal Ceiling Finishes X X
3D External Finishes X X
Group Element Total X
4 Fittings and Furnishings
5 Services
5A Sanitary Appliances X X
5B Plumbing Installation
5C Refuse Disposal
5D Air Conditioning & Ventilation Requirement given
System
5E Electrical Installation
5F Fire Protection Installation
5G Lift & Conveyor Installation
5H Communication Installation
5J Special Installation
5K Builder's Profit & Attendance
on Services
5L Builder's Work In Connection
With Services
Group Element Total X
Sub-total exc. External Works,
Preliminaries & Provisional Sum
6 External Works
6A Site Work
6B Drainage
6C External Services
6D Ancillary Buildings
6E Recreational Facilities
Preliminaries
***PG - PAGE
CL - CLAUSE
Elemental Cost Analysis - Form 3
BRIEF SPECIFICATION
GROSS FLOOR AREA : (As per Form 1) TENDER DATE :
ELEMENT SPECIFICATION
1 Substructure
1A Piling
1B Work Below Lowest Floor Finish x
2 Superstructure
2A Frame x
2B Upper Floors Not applicable
2C Roof x
2D Stairs Not applicable
2E External Walls x
2F Windows & External Doors x
2G Internal Wall & Partitions
2H Internal Doors
3 Finishes
3A Internal Wall Finishes x
3B Internal Floor Finishes x
3C Internal Ceiling Finishes
3D External Finishes x
5 Services
5A Sanitary Appliances x
5B Plumbing Installation
5C Refuse Disposal
5D Air Conditioning & Ventilation System
5E Electrical Installation
5F Fire Protection Installation
5G Lift & Conveyor Installation
5H Communication Installation
5J Special Installation
5K Builder's Profit & Attendance on Services
5L Builder's Work In Connection With Services
6 External Works
6A Site Work
6B Drainage
6C External Services
6D Ancillary Buildings
6E Recreational Facilities
*** PG - PAGE