Sei sulla pagina 1di 6

Elemental Cost Analysis - Form 1

JOB TITLE : X CLIENT : X

LOCATION : X TENDER DATE : X

INFORMATION ON TOTAL PROJECT

Project and Contract Information

Project Details and Site Conditions : Contract :

Market Conditions :
Contract Particulars : Cost Fluctuation : Competitive Tender List
Type of Contract: X Yes RM Int/JV/L

Basis of Tender: Open No x


Open/Selected
Bills of Quantities x Competition x Government

Bills of Approx. Quantity Negotiated Private x

Schedule of Rates/
Spec & Drawings Serial

Provisional Sum RM
Contract Period Stip. by Client : 1 month Prime Cost Sum RM
Contract Period Offered by Builders : x Preliminaries RM
Number of Tenders Issued : X Contingencies RM
Number of Tenders Received : X Contract Sum RM X

ANALYSIS OF SINGLE BUILDING


Design/Shape Information
Accommodation and Design Features : PG 4 - CL 3 (Design/shape information for single buildings)
Functional Unit : Design/Shape : PG 4 - CL 3
Areas : Percentage of Gross Floor Area
Lower Ground Floor m2
Ground Floor X m2 a) Below Ground Floor
Upper Floor m2 External Wall Area = X Construction %
GROSS FLOOR AREA - m2 Gross Floor Area X
= X b) Single-storey
Usable Area m2 Construction %
Circulation Area m 2

Ancillary Area m2 Storey Heights : c) 2-Storey


Internal Division m2 Construction %
GROSS FLOOR AREA m2 Av. Below Grd Floor -m
d) 3-Storey
Floor Space NOT Enclosed :Did not specify in the manual m2 At Ground Floor -m Construction %

Roof Area : m2 Above Ground Floor -m e) 4 - Storey


(Structural and Plant Rooms) Construction %

Brief Cost Information


Contract Sum RM X Functional Unit Cost excluding external
Provisional Sum RM Works :
Prime Cost Sum RM
Preliminaries RM being --- % of remainder
Contingencies RM being --- % of contract Sum
Contract Sum
less Contingencies RM X

*** PG - PAGE
CL - CLAUSE
Elemental Cost Analysis - Form 2 0
(As per Form1)
SUMMARY OF ELEMENTAL COSTS
GROSS FLOOR AREA: 6 m2 (For One Typcial Block) TENDER DATE :
Preliminaries Shown Separately
Element Total Cost Cost/m2 Elemental Elemental Element Reinforced Reinforcement Formwork
Of Element GFA Unit Unit Rate Ratio Concrete
RM RM Quantity RM per m2 GFA m3 kg m2
1 Substructure
1A Piling
1B Work Below Lowest Floor Finis #REF! #REF! X X X
Group Elemental Total #REF! #REF!
2 Superstructure
2A Frame #REF! #REF! X X X
2B Upper Floors X X X
2C Roof x x
2D Stairs
2E External Walls #REF! #REF!
2F Windows & External Doors X X
2G Internal Wall & Partitions
2H Internal Doors
Group Element Total - -
3 Finishes
3A Internal Wall Finishes X X
3B Internal Floor Finishes X X
3C Internal Ceiling Finishes X X
3D External Finishes X X
Group Element Total X
4 Fittings and Furnishings
5 Services
5A Sanitary Appliances X X
5B Plumbing Installation
5C Refuse Disposal
5D Air Conditioning & Ventilation Requirement given
System
5E Electrical Installation
5F Fire Protection Installation
5G Lift & Conveyor Installation
5H Communication Installation
5J Special Installation
5K Builder's Profit & Attendance
on Services
5L Builder's Work In Connection
With Services
Group Element Total X
Sub-total exc. External Works,
Preliminaries & Provisional Sum
6 External Works
6A Site Work
6B Drainage
6C External Services
6D Ancillary Buildings
6E Recreational Facilities

Group Elemental Total

Preliminaries

TOTAL (less provisional sum)

***PG - PAGE
CL - CLAUSE
Elemental Cost Analysis - Form 3

BRIEF SPECIFICATION
GROSS FLOOR AREA : (As per Form 1) TENDER DATE :
ELEMENT SPECIFICATION
1 Substructure
1A Piling
1B Work Below Lowest Floor Finish x

2 Superstructure
2A Frame x
2B Upper Floors Not applicable
2C Roof x
2D Stairs Not applicable
2E External Walls x
2F Windows & External Doors x
2G Internal Wall & Partitions
2H Internal Doors

3 Finishes
3A Internal Wall Finishes x
3B Internal Floor Finishes x
3C Internal Ceiling Finishes
3D External Finishes x

4 Fittings & Furnishings

5 Services
5A Sanitary Appliances x
5B Plumbing Installation
5C Refuse Disposal
5D Air Conditioning & Ventilation System
5E Electrical Installation
5F Fire Protection Installation
5G Lift & Conveyor Installation
5H Communication Installation
5J Special Installation
5K Builder's Profit & Attendance on Services
5L Builder's Work In Connection With Services

6 External Works
6A Site Work
6B Drainage
6C External Services
6D Ancillary Buildings
6E Recreational Facilities

*** PG - PAGE
CL - CLAUSE