Project Title: Marriot Grand Ballroom

Contract Package No. 02 CONCRETE WORKS

Document Title:

Method Statement for Painting Works

REVISION HISTORY

MARK DATE DESCRIPTION MEPF CIVIL / STRUCTURAL

A1 1st Submission

GENERAL CONTRACTOR
Prepared By: NGCB CQC

Checked By: QA/QC Head


NGCB DATE
PROJECT MANAGEMENT
Mechanical Engineer

Reviewed by: Electrical Engineer


EELHI Civil Engineer
Architect

Project Manager
Approved By:
Sr. Project Manager
EELHI

CONTRACTOR’S DOCUMENT No.: MGB-MS-021-AR-005 REVISION A1

MGB-MS-021-AR-005 Page 1
TABLE OF CONTENT

1. PURPOSE
2. SCOPE AND APPLICATON OF WORKS
3. REFERENCES
4. DEFINITIONS AND ABBREVIATIONS
5. SPECIFICATION CLAUSE
6. RESOURCES AND MOBILIZATION
7. CONSTRUCTION EQUIPMENT
8. PERSONNEL
9. MATERIALS
10. CONSTRUCTION PROCEDURE AND METHODOLOGY
11. TESTING AND INSPECTION
12. RESPONSIBILITY
13. DESIGN DRAWINGS
14. QUALITY ASSURANCE
15. HEALTH AND SAFETY
16. ORGANIZATIONAL CHART
17. INSPECTION
18. ATTACHEMENTS

___________________________________________________________________________

1. PURPOSE

This method of statement defines that the Painting Work to be conducted in the site are in
compliance with the Architectural Works Technical Specification and approve Construction
Methodology. And the Materials to be used for specific works are in compliance with the approved
design and material approvals. And will ensure that work procedures are in compliance with the
Project Safety Plan. The inspection will be based from the Project Quality Plan. The inspection is
associated quality procedures and an approved Inspection and Test Plan for the concrete repair
works.

2. SCOPE OF WORK

The work method is summarized as follows:

2.1. Construction Equipment


2.2. Materials to be used
2.3. Work Procedure
2.4. Site Preparation
2.5. Application of painting
2.6. Handling and Storage of epoxy painting
2.7. Responsibility
2.8. Inspection and test plan

3. REFERENCES

This method statement has been prepared with reference to the following documents:

3.1. Approved Architectural Works Technical Specification


3.2. Submitted approved Rectification Materials
3.3. Approved Project Safety Plan
3.4. Approved Project Quality Plan
3.5. Approved Inspection Test Plan

MGB-MS-021-AR-005 Page 2
4. DEFINITIONS AND ABREVIATIONS

4.1. EL - Elevation
4.2. MM - Millimeter
4.3. OC - On Center
4.4. ITP - Inspection Test Plan
4.5. MS - Method Statement
4.6. PM - Painting Manual

5. SPECIFICATION CLAUSE

The specification requirements for Painting works are described within Project Technical
Specification of Architectural Works and For Construction Design Drawings as follows:

5.1. Technical Specification for Structural Works

5.1.1. Summary
5.1.1.1. Section includes surface preparation and application of paint systems on the
following interior substrates:
5.1.1.1.1. Concrete
5.1.1.1.2. Steel
5.1.1.1.3. Galvanized metal
5.1.1.1.4. Aluminum ( not anodized or otherwise coated )
5.1.1.1.5. Wood
5.1.1.1.6. Gypsum board
5.1.1.1.7. Plaster

5.1.2.Action Submittals
5.1.2.1. Product Data: For each type of product. Include preparation requirements and
application instructions
5.1.2.2. Samples for Verification: For each type of paint system and in each color and gloss
of topcoat
5.1.2.2.1. Step coats on samples to show each coat required for system
5.1.2.2.2. Label each coat of each sample
5.1.2.2.3. Label each sample for location and application area
5.1.2.3. Product List: For each product indicated include the following:
5.1.2.3.1. Cross-reference to paint system and locations of application areas. Use
same designations indicated on drawings and in schedules

5.1.3.Products:
5.1.3.1. MANUFACTURERS
5.1.3.1.1. Manufacturers: Subject to compliance with requirements, provide products by
one of the following:
5.1.3.1.1.1. Pacific Paints and Oil Manufacturing, INC. (Boysen Paints)
5.1.3.1.1.2. Charter Chemical and Coating Corporation (Davies Paints)
5.1.3.1.1.3. H – Chem Industries

5.1.3.2. PAINTING, GENERAL


5.1.3.2.1. MPI Standards: Provide products that comply with MPI standards indicated
and that are listed in its “MPI” Approved Products List
5.1.3.2.2. Material Compatibility:
5.1.3.2.2.1. Provide materials for use within each paint system are compatible with
one another and substrates indicated, under conditions of service and
application as demonstrated by manufacturer, based on testing and field
experience.
5.1.3.2.2.2. For each coat in a paint system, provide system, provide products
recommended in writing by manufacturers of topcoat for use in paint
system and on substrate indicated.
5.1.3.2.2.3. Colors: As indicated in a color schedule

MGB-MS-021-AR-005 Page 3
5.1.4.Quality Assurance
5.1.4.1.1.1. Mock-ups: Apply mock-ups of each paint system indicated and each
color and finish selected to verify preliminary selections made under
sample submittals and to demonstrate aesthetic effects and set quality
standards for materials and execution.
5.1.4.1.1.1.1. Architect will select one surface to represent surfaces and
conditions for application of each paint system specified in part 3
5.1.4.1.1.1.2. Final approval of color selections will be based on mock-ups
5.1.4.1.1.1.3. Approval of mock-ups does not constitute approval of deviations
from the contract documents contained in mock-ups unless Architect
specially approves such deviations writing.
5.1.4.1.1.1.4. Subject to compliance with requirements, approved mock-ups
may become part of the completed work if undisturbed at time of
substantial completion

6. RESOURCES AND MOBILIZATION

The Accessibility at the site will be planned and subject for approval. The Safety of the staff, workers
and material delivery also concentrate on the plan in order to mobilize in accordance from the project
requirements. All the materials to be used are subject for submittal and approval in accordance with
the Architectural Work Technical Specification.

The General Contractor (NGCB) will notify the schedule one day before the actual mobilization of the
staff, workers, equipment.

It is understood that NGCB will be responsible for the provision for the transportation of materials to
complete the works including temporary construction water and power supplies and lighting system.

7. CONSTRUCTION EQUIPMENT

This Method of Statement for Painting Works has been envisaged that no major equipment will be
required by this activity. The typical construction equipment requirements are as listed below and will
be used up to the completion of the activities.

7.1. PPE for all staff and workers


7.2. Preparation Tools (cleaning equipment and sanding materials/equipment)

8. PERSONNEL

For this Rubbed Concrete works will be organized by both General Contractor and Nominated
Subcontractor. All the personnel shall be fully competent and trained to carry out all works associated
with the Rubbed Concrete. They shall have attended the required contractor’s safety induction and
will abide by the Health and Safety Plan, policy and procedures as well as environmental plan. It is
envisaged that the installation will be conducted by the followings:

8.1. Finishing Manager


8.2. Site Architect/Engineer
8.3. Quality Control Engineer
8.4. Foreman
8.5. Painter
8.6. Labor

9. MATERIALS
The Materials for rubbed concrete works shall be prepared and inspected at the NGCB site
warehouse before the retouching Works. The retouching works will be done at site using a manual
procedure provided by NGCB and as per specifications by supplier/manufacturer.

All materials delivered to the site will be inspected by NGCB Engineers In-charge together with the
QA/QC Inspectors and EELHI Inspectors to check if the materials are in accordance with the site
requirement and conform to the approved design and material qualification. A sample of mix

MGB-MS-021-AR-005 Page 4
materials shall be inspected at site and tested before the retouching works; rejected materials shall
not be accepted and shall be returned to supplier.

The inward inspection of materials will be carried out in accordance with the relevant QA/QC
procedures and or approved Project Quality Control Plan and manufacturer’s / specification of
suppliers.

Note: No materials shall be permitted to enter and/or installed inside the jobsite without inspection
and approval from CQC Engineers upon arrival at jobsite.

10. CONSTRUCTION PROCEDURE AND METHODOLOGY

10.1. Before Application


Before the painting works, the following are required to be carried out:

10.1.1. Identifying on rectification procedure needed


10.1.2. Securing Material submittal and ITP are with approved status.
10.1.3. Check if the materials have been inspected and ready for fabrication
10.1.4. Check that the site access to the work area available, clean and safe.
10.1.5. Check if the temporary services provisions are available.

10.2.DELIVERY & INSPECTION OF MATERIALS FOR PAINTING WORKS

10.2.1. All delivered materials shall be inspected upon arrival on site. The inspection shall be
advised, in advance, as required by the ITP and in accordance with the Project Quality
Plans
10.2.2. The delivered materials shall be in accordance with the approved design technical
specification and approved material submittal.
10.2.3. Material approvals in form of approved SRF and all applicable documentations and
certifications shall be available during incoming material inspection.
10.2.4. Any materials delivered in the site that are not complying with the approved material
submittals and structural technical specification or rejected by EELHI Engineer shall
either be returned to the supplier or stored in the site at a suitable quarantine area.
10.2.5. The materials shall be free from defects or damaged, and still workable.

10.3.SETTING OUT OF WORKS

10.3.1. Generally, prior to commencement of the delivery of materials for Painting, the setting
out of the works shall be conducted to determine the location and design.
10.3.2. The setting out of the works shall be on the basis of an “approved for construction
drawings and or approved shop drawings”.
10.3.3. Any discrepancy between the common reference point on the approved for construction
drawings and the actual site provisions shall be notified to EEHLI and an NCR shall be
raised.
10.3.4. Work shall not proceed when weather conditions detrimentally affect the quality of
rectification materials.

10.4.RUBBED CONCRETE PROCEDURE

10.4.1. General: check the area of concrete to be rectify, if sanding is needed


10.4.2. Clean and remove dirt from the concrete
10.4.3. Use Baufix on uneven surfaces to correct the plumbness/alignment of the concrete
10.4.4. Before application of skimcoat, concrete must be moistened enough
10.4.5. Mix the skimcoat materials in accordance with the manufacturers instruction
10.4.6. Application of the mixed skimcoat materials shall be performed within the working life of
the skimcoat system
10.4.7. Unused mixed materials which have reached the end of the working life shall be
removed from the jobsite
10.4.8. Smoothen the skim coat with soft paintbrush or trowelled smooth.

MGB-MS-021-AR-005 Page 5
11. TESTING AND INSPECTION

11.1. Inspection: Examine the delivered materials at the site. Application procedures and
preparation will be examined by the engineer, if it will comply to the requirements
specified
11.2. Check each surface of retouched area if acceptable or not acceptable. If there’s any
defect from rectified area, immediately repair the defects.

12. RESPONSIBILITY
The Contractor (NGCB) will be supervising all activities in the site through Construction
Supervisors, Foreman and skilled workers at the site. The QA/QC Inspectors will be
responsible for arranging and controlling the inspection and testing activities with the
EELHI Inspectors.

13. DESIGN AND DRAWINGS


The Construction Designs and Material Specifications for the Painting work shall be submitted and
subject for approval of the consultant through Material Submittal, Submittal Review Form Made by
NGCB and NSC before the work starts.

14. QUALITY ASSURANCE


The execution of work will strictly follow the Project Quality Plan

15. HEALTH AND SAFETY PLAN


The execution of work will strictly follow the Project Safety Manual.

16. ORGANIZATIONAL CHART


As per Organizational Chart of the Project

17. INSPECTION TEST PLAN


As per attached ITP

18. ATTACHEMENTS
 Checklist for inspection of incoming material for Painting work materials.
 Checklist for Inspection of Painting Work

MGB-MS-021-AR-005 Page 6