Sei sulla pagina 1di 6

NUEVE DE PLUMA POULTRY CORPORATION

PROPOSED FOUR (4) UNITS POULTRY AGRIFRAME


BUILDING SYSTEMS (PABS)
BACOLOR, PAMPANGA

METHODOLOGY OF RECTIFICATION
(For Pre-Fabricated Structure)

Submitted By:

Prepared By: Checked By:

Engr. Alldrine B. Muñoz Engr. Rezziel L. Magtoto


Estimator Engineering Manager

Checked By: Approved By: Conformed:

________________________
Engr. Robby V. Teresa Ms. Riolyn T Domingo Owner / Representative
Structural Engineer General Manager (Signature Over Printed Name)

1|Page
Methodology of Rectification

Upon inspection, we found out that the misalignment of the structural steel columns was
due to the significant cracks on the substructures creating permanent wide gaps. And as
observed, there is no movement occurred on the Roof Framing and Ceiling Framing of the
affected structures. One significant inherent characteristics of steel especially cold-formed steel,
is flexibility, in which it could sway due to lateral movements but would go back to its original
position. Since no buckling or deformation occurred on the steel columns, we will dismantle the
materials on the affected area. Then, realign the columns. After the realignment of the column,
we will provide cross braces on every other area/bays of the affected section. See the step by
step process of the rectification below.

Realignment of Structural Steel Columns.

1. Dismantling of the existing installed materials at the affected portion of the building
using bay by bay method. Materials to be dismantle are as follows:
A. Roofing Panels
B. Ceiling Panels an Insulations.
C. Roof Purlins
D. Ceiling Frames
E. Struts
F. Roof Beams
G. Insulated Walls

*Affected portion/bays of the Building 6-7

2|Page
2. Realigning of the misaligned steel column. The columns will follow the displaced
position of the concrete pedestal. See the plan attached for details.

*See the movement on the concrete column.

3|Page
3. Reinstallation of the dismantled materials.

Note: Reinstallation of dismantled materials will start right after the rectification on the sub-
structure is finished.

4. Final inspection/punchlist of rectification works.

NOTE: Rectification works will start seven (7) days after the approval of this proposed
methodology. Repairs will take 21-30 days.

RECOMMENDATION FOR SUB-STRUCTURE


Rectification for Sub-structure is also required through:
A.) Providing additional tie beam on the affected column bays.

***** END OF METHODOLOGY *****

4|Page
Philippine Steelframing Corporation – Nueve De
Pluma/Mr. Paulo Caluag Agreement

Philippine Steelframing Corporation have agreed that expenses for the


rectification of the damages will be shouldered by the company. Rectification will
start seven (7) working days after the payment of the current billing amounting of
Three Million Nine Hundred Twenty Thousand Pesos (3,920,000.00).

Conformed::

Ms. Riolyn T. Domingo Mr. Paulo Caluag


Philippine SteelFraming Corporation OWNER
(General Manager) (Signature over Printed Name)

5|Page
6|Page

Potrebbero piacerti anche