EARNED VALUE $600
PLANNED VALUE $700
Develop landscaping plan and 25 $500 50% Yes $700 (10 extra
schedule hours)
Dig Sprinkler Trench 110 $1100 ($10/hour) 27.5% Yes $800 (Complete in
Only planned to achieved 55% through today ($600) 80 hours)
8000
7000
6000
5000
4000
3000
2000
1000
0
100 400 300 800 1000 1400 400 600 1500 800 700 500
Jan Feb March April May June July August September October November December
$4900/5600 = 0.875
For every dollar spent, you only receive $ 0.875 worth of value!
© 2016 Core Performance Concepts Inc.
Any questions?
Upcoming Webinar
Core Concepts & Project Insight
PM in Theory
Risk Management - Critical Success Factor
Wednesday, April 12, 2017
8 AM PT/11 AM ET
IT
Product
PM Training Methodology Leadership
Training
and Agile
See you next time!