(TOYO Work No.) CLASS AREA DIS TYP REQ NO SEQ SHEET REV. P.O No: AXBJ001
BA121011 VD 60 FNC ITP AXBJ001 0001 - 2 Date: 25 February 2019
(Vendor Work No.)
F-9028320 Vendor Doc. No.: F-9028320-4000 Page 1 of 17
□AP APPROVED
□AN APPROVED AS NOTED
□RE NOT APPROVED (Re-Submit)
□RV REVIEWED
□RN REVIEWED WITH NOTES
□NR NOT BE RETURNED
RETURN DATE
Please revise the typo
on sheet 14 of 17 when
submit MDR
PROJECT ORIGINATOR
FINAL
2 25-02-2019 Final RG SF DF
1 22-02-2019 Final RG SF DF
0 11-02-2019 Final RG SF DF
DATE
REV ISSUE PURPOSE PREPARE CHECKED APPROVED AUTHORIZED
ISSUED
(TOYO Work No.) CLASS AREA DIS TYP REQ NO SEQ SHEET REV. P.O No: AXBJ001
BA121011 VD 60 FNC ITP AXBJ001 0001 - 2 Date: 25 February 2019
(Vendor Work No.)
F-9028320 Vendor Doc. No.: F-9028320-4000 Page 2 of 17
Revision History
STAGE PROCESS ACTIVITY ACCEPTANCE CRITERIA VERIFICATION RECORD FABRICATOR INITIAL / DATE UOPC INITIAL / DATE TOYO INITIAL / DATE CAP INITIAL / DATE NOTE
WPS/PQR
(WATER SEAL DRUM - WITH
ED-000-STA-SPC-0001 / ASME SEC IX / AWS
THREE PWHT CYCLES &
A ED-000-STA-SPC-0007 / D1.1 (FOR STRUCTURAL APPROVED WPS/PQR H A A R
IMPACTS TO MINIMUM -45C &
ED-000-STA-SPC-0009 FABRICATION)
ADDITIONAL TESTING PER
SPECIFICATIONS)
FABRICATOR FORMAT
MEETING
ED-000-STA-SPC-0007 /
B WELD MAP REQUIREMENTS OF APPROVED WELD MAP H A A A
ED-000-STA-SPC-0009
CUSTOMER
SPECIFICATION
C NDE PROCEDURES
ED-000-STA-SPC-0001 /
1 RADIOGRAPH (RT) ED-000-STA-SPC-0007 / ASME SEC V ARTICLE 2 APPROVED RT PROCEDURE H A A A
ED-000-STA-SPC-0009
ED-000-STA-SPC-0001 /
ASME SEC V ARTICLE 4
2 ULTRASONIC (UT) ED-000-STA-SPC-0007 / APPROVED UT PROCEDURE H A A A
&5
ED-000-STA-SPC-0009
ED-000-STA-SPC-0001 /
3 LIQUID PENETRANT (PT) ED-000-STA-SPC-0007 / ASME SEC V ARTICLE 6 APPROVED PT PROCEDURE H A A A
ED-000-STA-SPC-0009
ED-000-STA-SPC-0001 /
4 MAGNETIC PARTIAL (MT) ED-000-STA-SPC-0007 / ASME SEC V ARTICLE 7 APPROVED MT PROCEDURE H A A A
ED-000-STA-SPC-0009
ED-000-STA-SPC-0001 /
HARDNESS TEST APPROVED HARDNESS TEST
5 HARDNESS TEST ED-000-STA-SPC-0007 / H A A A
PROCEDURE PROCEDURE
ED-000-STA-SPC-0009
ED-00-FNC-MRQ-
6 PMI APPROVED PMI PROCEDURE H A A A
AXBJ001
STAGE PROCESS ACTIVITY ACCEPTANCE CRITERIA VERIFICATION RECORD FABRICATOR INITIAL / DATE UOPC INITIAL / DATE TOYO INITIAL / DATE CAP INITIAL / DATE NOTE
PD-00-TRS-DOC-
0002_R0 / ED-000-STA-
G PACKING PROCEDURE APPROVED DRAWINGS SUBMITTED PROCEDURE H V A A
SPC-0001 / ED-000-STA-
SPC-0008
ED-00-FNC-MRQ-
AXBJ001 / ED-000-STA-
APPROVED DRAWINGS /
SPC-0001 / ED-000-STA- MTR / MATERIAL TRACEABILITY
A MATERIAL VERIFICATION ASME SEC II / COUNTRY H R/W R R 2&3
SPC-0007 / ED-000-STA- MAP/INDEX
OF ORIGIN RESTRICTION
SPC-0008 / ED-000-STA-
SPC-0009
C DISH HEADS
ED-00-FNC-MRQ- APPROVED UT
1 UT THICKNESS VERIFICATION UT REPORT WITH MAP V R R R
AXBJ001 PROCEDURE
ED-00-FNC-MRQ-
AXBJ001 / ED-000-STA-
APPROVED DRAWINGS /
SPC-0001 / ED-000-STA- INSPECTION REPORT / SHOP
D MATERIAL PREP & FIT UP APPROVED WPS/PQR / V R R R
SPC-0007 / ED-000-STA- TRAVELER
ASME SEC VII DIV 1
SPC-0008 / ED-000-STA-
SPC-0009
STAGE PROCESS ACTIVITY ACCEPTANCE CRITERIA VERIFICATION RECORD FABRICATOR INITIAL / DATE UOPC INITIAL / DATE TOYO INITIAL / DATE CAP INITIAL / DATE NOTE
ED-00-FNC-MRQ-
AXBJ001 / ED-000-STA-
APPROVED DRAWINGS /
SPC-0001 / ED-000-STA- INSPECTION REPORT / SHOP
E IN PROCESS FABRICATION APPROVED WPS & ASME V V R R
SPC-0007 / ED-000-STA- TRAVELER
SEC VIII DIV 1
SPC-0008 / ED-000-STA-
SPC-0009
ED-00-FNC-MRQ-
AXBJ001 / ED-000-STA-
SPC-0001 / ED-000-STA- APPROVED WPS/PQR / INSPECTION REPORT / SHOP
2 WELDING PROCESS V V R R
SPC-0007 / ED-000-STA- ASME SEC IX TRAVELER
SPC-0008 / ED-000-STA-
SPC-0009
ED-00-FNC-MRQ- APPROVED MT
3 MT (100% ON BACK GOUGING) MT REPORT WITH MAP H R R R
AXBJ001 PROCEDURE
ED-000-STA-SPC-0001 /
WQR RECORD / WELDER
F WELDER QUALIFICATIONS ED-000-STA-SPC-0007 / ASME SEC IX H V R R
TRACEABILITY MAP/INDEX
ED-000-STA-SPC-0008
ED-00-FNC-MRQ-
AXBJ001 / ED-000-STA-
FINAL DIMENSIONAL
SPC-0001 / ED-000-STA- INSPECTION REPORT / SHOP
G INSPECTION AFTER ALL APPROVED DRAWINGS H W RI R
SPC-0007 / ED-000-STA- TRAVELER
WELDING IS COMPLETE
SPC-0008 / ED-000-STA-
SPC-0009
ED-00-FNC-MRQ-
AXBJ001 / ED-000-STA-
APPROVED DRAWINGS /
SPC-0001 / ED-000-STA- INSPECTION REPORT / SHOP
H FINAL WELDING INSPECTION APPROVED WPS & ASME H W RI R
SPC-0007 / ED-000-STA- TRAVELER
SEC VIII DIV 1
SPC-0008 / ED-000-STA-
SPC-0009
STAGE PROCESS ACTIVITY ACCEPTANCE CRITERIA VERIFICATION RECORD FABRICATOR INITIAL / DATE UOPC INITIAL / DATE TOYO INITIAL / DATE CAP INITIAL / DATE NOTE
ED-00-FNC-MRQ-
AXBJ001 / ED-000-STA-
SPC-0001 / ED-000-STA- APPROVED DRAWINGS /
1 VT (100% OF ALL WELDS) VT REPORT WITH MAP V V R R
SPC-0007 / ED-000-STA- ASME SEC VIII DIV 1
SPC-0008 / ED-000-STA-
SPC-0009
ED-00-FNC-MRQ-
RT (100% FOR CROSS WELDS APPROVED RT
AXBJ001 / ED-000-STA-
2 & 10% FOR OTHER BUTT PROCEDURE / ASME SEC RT REPORT WITH MAP V R RI R
SPC-0008 / ED-000-STA-
WELDS) VII DIV 1 UW-51
SPC-0009
PT OR MT (100% OF FILLET
ED-00-FNC-MRQ-
WEDS, LIFTING LUG WELDS &
AXBJ001 / ED-000-STA- APPROVED PT/MT
3 ALL TEMPORARY PT / MT REPORT WITH MAP H R R R
SPC-0008 / ED-000-STA- PROCEDURE
ATTACHMENTS WELD AREAS
SPC-0009
REMOVED)
ED-00-FNC-MRQ-
AXBJ001 / ED-000-STA-
SPC-0001 / ED-000-STA- APPROVED DRAWINGS /
1 VT (100% OF ALL WELDS) VT REPORT WITH MAP V R R R
SPC-0007 / ED-000-STA- ASME B31.3
SPC-0008 / ED-000-STA-
SPC-0009
ED-00-FNC-MRQ-
UT (100% OF ALL FULL
AXBJ001 / ED-000-STA- APPROVED UT
2 PENETRATION WELDS) UT REPORT WITH MAP H R R R
SPC-0008 / ED-000-STA- PROCEDURE
(CATEGORY A, B & D)
SPC-0009
INSPECTION & TEST PLAN
Page 7 of 17
F-9028320
CUSTOMER NAME AND PO NO:
CHANDRA ASRI PETROCHEMICAL / TOYO ENGINEERING CORPORATION PO BA121011-AXBJ001 REV2
WO NO: F-9028320
STAGE PROCESS ACTIVITY ACCEPTANCE CRITERIA VERIFICATION RECORD FABRICATOR INITIAL / DATE UOPC INITIAL / DATE TOYO INITIAL / DATE CAP INITIAL / DATE NOTE
PT OR MT (100% ON ALL
ACCESSIBLE INSIDE SURFACE ED-00-FNC-MRQ-
OF PRESSURE RETAINING AXBJ001 / ED-000-STA- APPROVED PT/MT
3 PT / MT REPORT WITH MAP H R R R
WELDS & ACCESSIBLE SPC-0008 / ED-000-STA- PROCEDURE
INTERNAL ATTACHMENT SPC-0009
WELDS)
ED-00-FNC-MRQ-
AXBJ001 / ED-000-STA-
HARDNESS TEST (100% OF ALL APPROVED HARDNESS HARDNESS TEST REPORT WITH
4 SPC-0001 / ED-000-STA- H R R R
PRESSURE RETAINING WELDS) TEST PROCEDURE MAP
SPC-0007 / ED-000-STA-
SPC-0009
ED-00-FNC-MRQ-
PNEUMATIC LEAK TEST ON AXBJ001 / ED-000-STA- APPROVED DRAWINGS
O LEAK TEST REPORT WITH MAP H R R R
REINFORCING PAD (100%) SPC-0008 / ED-000-STA- ASME VIII DIV. 1
SPC-0009
ED-00-FNC-MRQ-
AXBJ001 / ED-000-STA-
APPROVED HYDRO TEST
SPC-0001 / ED-000-STA-
P HYDRO TEST PROCEDURE / ASME SEC HYDRO TEST REPORT H W H R
SPC-0007 / ED-000-STA-
VIII DIV 1
SPC-0008 / ED-000-STA-
SPC-0009
APPROVED DRAWINGS /
INSPECTION REPORT / SHOP
C MATERIAL PREP & FIT UP APPROVED WPS / ASME V R R R
TRAVELER
B31.3
APPROVED DRAWINGS /
INSPECTION REPORT / SHOP
D IN PROCESS FABRICATION APPROVED WPS & ASME V V R R
TRAVELER
B31.3
STAGE PROCESS ACTIVITY ACCEPTANCE CRITERIA VERIFICATION RECORD FABRICATOR INITIAL / DATE UOPC INITIAL / DATE TOYO INITIAL / DATE CAP INITIAL / DATE NOTE
FINAL DIMENSIONAL
INSPECTION REPORT / SHOP
F INSPECTION AFTER ALL APPROVED DRAWINGS H W RI R
TRAVELER
WELDING IS COMPLETE
APPROVED DRAWINGS /
INSPECTION REPORT / SHOP
G FINAL WELDING INSPECTION APPROVED WPS & ASME H W RI R
TRAVELER
B31.3
APPROVED RT
RT (100% OF ALL BUTT ED-00-FNC-MRQ-
2 PROCEDURE; ASME RT REPORT WITH MAP V R R R
WELDS) AXBJ001
B31.3
EGF COMBUSTION
V STRUCTURE, PANELS & WIND
FENCE
APPROVED DRAWINGS /
INSPECTION REPORT / SHOP
B MATERIAL PREP & FIT UP APPROVED WPS / AWS V R R R
TRAVELER
D1.1
APPROVED DRAWINGS /
INSPECTION REPORT / SHOP
C IN PROCESS FABRICATION APPROVED WPS / AWS V R R R
TRAVELER
D1.1
APPROVED DRAWINGS /
DIMENSIONAL / VISUAL INSPECTION REPORT / SHOP
E APPROVED WPS / AWS H R/W RI R
INSPECTION TRAVELER
D1.1 / ISO 13920 LEVEL B
INSPECTION REPORT / SHOP
1 SHELL PANELS APPROVED DRAWINGS V V R R
TRAVELER
NOZZLES & ATTACHMENT INSPECTION REPORT / SHOP
2 APPROVED DRAWINGS V V R R
LOCATION & PROJECTION TRAVELER
INSPECTION REPORT / SHOP
3 BEAM / COLUMNS / BRACES APPROVED DRAWINGS V R R R
TRAVELER
INSPECTION & TEST PLAN
Page 9 of 17
F-9028320
CUSTOMER NAME AND PO NO:
CHANDRA ASRI PETROCHEMICAL / TOYO ENGINEERING CORPORATION PO BA121011-AXBJ001 REV2
WO NO: F-9028320
STAGE PROCESS ACTIVITY ACCEPTANCE CRITERIA VERIFICATION RECORD FABRICATOR INITIAL / DATE UOPC INITIAL / DATE TOYO INITIAL / DATE CAP INITIAL / DATE NOTE
STANDARD DRAWINGS
D222475-00060-BN R1 INSPECTION REPORT / SHOP
F L & P FABRICATION V R R R
D222475-00060-BM R1 TRAVELER
D222475-00060-BL R1
APPROVED DRAWINGS /
INSPECTION REPORT / SHOP
G FINAL WELDING INSPECTION APPROVED WPS / AWS H V RI R
TRAVELER
D1.1
H NDE
STAGE PROCESS ACTIVITY ACCEPTANCE CRITERIA VERIFICATION RECORD FABRICATOR INITIAL / DATE UOPC INITIAL / DATE TOYO INITIAL / DATE CAP INITIAL / DATE NOTE
APPROVED DRAWINGS /
INSPECTION REPORT / SHOP
C MATERIAL PREP & FIT UP APPROVED WPS / ASME V R R R
TRAVELER
B31.3
APPROVED DRAWINGS /
INSPECTION REPORT / SHOP
D IN PROCESS FABRICATION APPROVED WPS & ASME V V R R
TRAVELER
B31.3
FINAL DIMENSIONAL
INSPECTION REPORT / SHOP
F INSPECTION AFTER ALL APPROVED DRAWINGS H W RI R
TRAVELER
WELDING IS COMPLETE
APPROVED DRAWINGS /
INSPECTION REPORT / SHOP
G FINAL WELDING INSPECTION APPROVED WPS & ASME H W RI R
TRAVELER
B31.3
APPROVED RT
ED-00-FNC-MRQ-
2 RT (100% OF ALL BUTT WELDS) PROCEDURE; ASME RT REPORT WITH MAP V R R R
AXBJ001
B31.3 SEC. 345.9
PT OR MT (100% OF ALL
APPROVED PT/MT
WELDS NOT RT'D. THIS ED-00-FNC-MRQ-
3 PROCEDURE; ASME PT / MT REPORT WITH MAP H R R R
INCLUDES ATTACHMENT AXBJ001
B31.3 SEC. 345.9
WELDS)
APPROVED RT
ED-00-FNC-MRQ-
2 RT (5% OF ALL BUTT WELDS) PROCEDURE; ASME RT REPORT WITH MAP V R R R
AXBJ001
B31.3 SEC. 345.9
APPROVED PT/MT
PT OR MT (10% OF BRANCH ED-00-FNC-MRQ-
3 PROCEDURE; ASME PT / MT REPORT WITH MAP H R R R
CONNECTIONS ) AXBJ001
B31.3 SEC. 345.9
INSPECTION & TEST PLANPage 11 of 17
F-9028320
CUSTOMER NAME AND PO NO:
CHANDRA ASRI PETROCHEMICAL / TOYO ENGINEERING CORPORATION PO BA121011-AXBJ001 REV2
WO NO: F-9028320
STAGE PROCESS ACTIVITY ACCEPTANCE CRITERIA VERIFICATION RECORD FABRICATOR INITIAL / DATE UOPC INITIAL / DATE TOYO INITIAL / DATE CAP INITIAL / DATE NOTE
APPROVED RT
ED-00-FNC-MRQ-
2 RT (5% OF ALL BUTT WELDS) PROCEDURE; ASME RT REPORT WITH MAP V R R R
AXBJ001
B31.3 SEC. 345.9
APPROVED PT/MT
PT OR MT (10% OF BRANCH ED-00-FNC-MRQ-
3 PROCEDURE; ASME PT / MT REPORT WITH MAP H R R R
CONNECTIONS ) AXBJ001
B31.3 SEC. 345.9
HYDRO TESTING
N
REQUIREMENTS
STAGE PROCESS ACTIVITY ACCEPTANCE CRITERIA VERIFICATION RECORD FABRICATOR INITIAL / DATE UOPC INITIAL / DATE TOYO INITIAL / DATE CAP INITIAL / DATE NOTE
APPROVED DRAWINGS /
INSPECTION REPORT / SHOP
C MATERIAL PREP & FIT UP APPROVED WPS / ASME V R R R
TRAVELER
B31.3
APPROVED DRAWINGS /
INSPECTION REPORT / SHOP
D IN PROCESS FABRICATION APPROVED WPS & ASME V V R R
TRAVELER
B31.3
FINAL DIMENSIONAL
INSPECTION REPORT / SHOP
F INSPECTION AFTER ALL APPROVED DRAWINGS H W RI R
TRAVELER
WELDING IS COMPLETE
APPROVED DRAWINGS /
INSPECTION REPORT / SHOP
G FINAL WELDING INSPECTION APPROVED WPS & ASME H W RI R
TRAVELER
B31.3
H NDE
STAGE PROCESS ACTIVITY ACCEPTANCE CRITERIA VERIFICATION RECORD FABRICATOR INITIAL / DATE UOPC INITIAL / DATE TOYO INITIAL / DATE CAP INITIAL / DATE NOTE
APPROVED DRAWINGS /
INSPECTION REPORT / SHOP
B MATERIAL PREP & FIT UP APPROVED WPS / ASME V R R R
TRAVELER
B31.3
APPROVED DRAWINGS /
INSPECTION REPORT / SHOP
C IN PROCESS FABRICATION APPROVED WPS & ASME V V R R
TRAVELER
B31.3
FINAL DIMENSIONAL
INSPECTION REPORT / SHOP
E INSPECTION AFTER ALL APPROVED DRAWINGS H W RI R
TRAVELER
WELDING IS COMPLETE
APPROVED DRAWINGS /
INSPECTION REPORT / SHOP
F FINAL WELDING INSPECTION APPROVED WPS & ASME H W RI R
TRAVELER
B31.3
G NDE
APPROVED RT
RT (10% OF BUTT WELDS PER ED-00-FNC-MRQ-
2 PROCEDURE; ASME RT REPORT WITH MAP V R R R
WELDER) AXBJ001
B31.3
APPROVED PT/MT
PT OR MT (100% OF FILLET ED-00-FNC-MRQ-
3 PROCEDURE; ASME PT / MT REPORT WITH MAP H R R R
WEDS & LIFTING LUG WELDS) AXBJ001
B31.3
STAGE PROCESS ACTIVITY ACCEPTANCE CRITERIA VERIFICATION RECORD FABRICATOR INITIAL / DATE UOPC INITIAL / DATE TOYO INITIAL / DATE CAP INITIAL / DATE NOTE
ED-00-ELE-SPC-0014 /
APPROVED DRAWINGS / INSPECTION REPORT / SHOP
A PANEL INSPECTION ED-00-INC-SPC-0001 / H W W W
APPROVED DATA SHEET TRAVELER
ED-00-INC-SPC-0002
ED-00-ELE-SPC-0014 /
APPROVED DRAWINGS / INSPECTION REPORT / SHOP
B WIRING CHECK ED-00-INC-SPC-0001 / H W W W
APPROVED DATA SHEET TRAVELER
ED-00-INC-SPC-0002
ED-00-FNC-MRQ-
C FAT (LCP / PLC / EWS / HMI) UOPC FAT PROCEDURE FAT REPORT H W W W
AXBJ001
AUTOMATED ON-OFF
E
BUTTERFLY VALVE
FUNCTIONAL TEST TO
INCLUDE: VISUAL INSPECTION,
DIMENSIONAL CHECK,
OPERATING DIAGRAM, CHECK
OF INDIVIDUAL COMPONENTS,
FUNCTIONAL TEST OF
CONTROL CIRCUIT, LIMIT APPROVED DATA SHEET
INSPECTION REPORT / SHOP
1 SWITCH FUNCTION CHECK, ED-00-INC-SPC-0002 EGF-VD-60-FNC-DAT- H W W W
TRAVELER
VALVE OPERATING TEST WITH AXBJ001-0009
PNEUMATIC ACTUATOR (OPEN
/ CLOSED / FAILURE
OPERATION WITH MINIMUM AIR
PRESSURE SUPPLIED),
typo, Calibration &
OPENING & CLOSING TIMING function
TEST
X COATING
STAGE PROCESS ACTIVITY ACCEPTANCE CRITERIA VERIFICATION RECORD FABRICATOR INITIAL / DATE UOPC INITIAL / DATE TOYO INITIAL / DATE CAP INITIAL / DATE NOTE
XI SHIPPING PREPARATION
PD-00-TRS-DOC-
0001_R0 / ED-000-STA-
A MARKING AND TAGGING APPROVED DRAWINGS APPROVED PACKING LIST H W R R
SPC-0001 / ED-000-STA-
SPC-0008
PD-00-TRS-DOC-
APPROVED PACKING
0001_R0 / ED-000-STA-
B PACKING INSPECTION LIST / APPROVED APPROVED PACKING LIST H W R R
SPC-0001 / ED-000-STA-
PROCEDURE
SPC-0008
XII FINAL DATA PACKET ED-000-STA-SPC-0001 UOPC V150 / UOPC X-150 DATA BOOK V R R R
COMPLIANCE WITH PO /
A UOPC INSPECTION RELEASE CUSTOMER SPEC. APPROVED DWGS / INSPECTION RELEASE FORM H H H H
APPLICABLE CODE
COMPLIANCE WITH PO /
B TOYO INSPECTION RELEASE CUSTOMER SPEC. APPROVED DWGS / INSPECTION RELEASE FORM H H H H
APPLICABLE CODE
COMPLIANCE WITH PO /
CHANDRA ASRI INSPECTION
C CUSTOMER SPEC. APPROVED DWGS / INSPECTION RELEASE FORM H H H H
RELEASE
APPLICABLE CODE
STAGE PROCESS ACTIVITY ACCEPTANCE CRITERIA VERIFICATION RECORD FABRICATOR INITIAL / DATE UOPC INITIAL / DATE TOYO INITIAL / DATE CAP INITIAL / DATE NOTE
NOTES:
1 FIRST ARTICLES SHALL BE NOTIFIED TO UOPC FOR WITNESS INSPECTION.
2 ALL CMTR FOR THE MAIN MATERIAL, THE PRESSURE RETAINING PARTS AND FORCE BEARING PARTS SHALL BE EN 10204 3.1 CERTIFICATES.
MATERIALS FROM CHINA, INDIA & ITALY ARE NOT ACCEPTABLE FOR PRESSURIZED PARTS AND CRITICAL PARTS OF THE EQUIPMENT. UOPC CHINA CASTING
3
ARE EXEMPT FROM THIS RESTRICTION.
CLIENT SPECIFICATION
ED-00-CPL-SPC-0010_A222475-00018AO-0 ENGINEERING SPECIFICATION FOR PAINTING WORKS
ED-00-ELE-SPC-0014_A222475-00040J-1 ELECTRICAL SPECIFICATION FOR CABLES AND WIRES FOR PT PETROKIMIA BUTADIENE INDONESIA
ED-00-PIP-SPC-0004_ES_PIPING MATERIAL
ED-00-PIP-SPC-0007_A222475-00018AG-1_ES_THERMAL INSULATION
PD-00-TRS-DOC-0001_R0 PACKING MARKING INSTRUCTION
PD-00-TRS-DOC-0002_R0 SHIPPING INSTRUCTION
ED-000-STA-SPC-0007 REQUIREMENT FOR GENERAL WELDING FOR PRESSURE CONTAINING EQUIPMENT
ED-000-STA-SPC-0008 GENERAL REQUIREMENT TO VENDOR FOR PRESSURE VESSEL FABRICATION
ED-000-STA-SPC-0009 INSPECTION AND TESTING OF VESSELS AND HEAT EXCHANGER
A53015-8030C-3 ENGINEERING SPECIFICATION VESSEL STANDARD
ED-000-STA-SPC-0001 A53015-8030C-4, ED-00-VS-SPC-E_D101 ENGINEERING SPECIFICATION VESSEL STANDARD
ED-00-FNC-MRQ-AXBJ001 rev.1 MATERIAL REQUISITION FOR ENCLOSED GROUND FLARE
ED-00-INC-SPC-0002 Rev 2 CONTROL AND SHUTDOWN SYSTEM
ED-00-INC-SPC-0001 Rev.0 ENGINEERING SPECIFICATION FOR INSTRUMENTATION
INSPECTION CODES
EACH INSPECTOR MUST BE INFORMED AT LEAST 14 CALENDAR DAYS IN ADVANCE OF A HOLD POINT. THE RELEVANT INSPECTOR MUST BE
H* = PRESENT. A SIGNED REPORT OR SIGNED INSPECTION WAIVER IS NEEDED BEFORE VENDOR MAY PROCEED BEYOND A MARKED HOLD
POINT.
WITNESS POINT - EACH INSPECTOR MUST BE INFORMED AT LEAST 14 CALENDAR DAYS IN ADVANCE OF A WITNESS POINT. THE VENDOR
W* = MAY PROCEED WITHOUT THE PRESENCE OF THE INSPECTOR PROVIDED THE CORRECT NOTIFICATION OF THE WITNESS POINT HAS BEEN
GIVEN BY THE VENDOR. THE REPORTS WILL BE SUBMITTED LATER TO THE RELEVANT INSPECTOR.
INSPECTIONS FOR HOLD & WITNESS POINTS HAVE TO BE ORGANIZED DURING NORMAL WORKING DAYS FROM MONDAY UNTIL FRIDAY AND
*
DURING NORMAL WORKING HOURS FROM 7.30h until 18.00h
A= APPROVAL OF DOCUMENTATION - APPROVAL OF DOCUMENTS ARE REQUIRED BEFORE CONTRACTOR CAN PROCEED.
Page 17 of 17
STAGE PROCESS ACTIVITY ACCEPTANCE CRITERIA VERIFICATION RECORD FABRICATOR INITIAL / DATE UOPC INITIAL / DATE TOYO INITIAL / DATE CAP INITIAL / DATE NOTE
V= VERIFY - VENDOR HAS CARRIED OUT AN INSPECTION TO CONFIRM THE EXECUTED WORKS MEET THE SPECIFIED REQUIREMENTS
RANDOM INSPECTION - INSPECTIONS DONE AT RANDOM DURING THE INSPECTION VISITS, THESE INSPECTIONS NEED NO SPECIAL
RI=
REPORTS OR WAIVER.
UOPC RECOMMENDS THE SUPPLIER CREATE A DETAILED INSPECTION TEST PLAN FOR EACH PIECE OF EQUIPMENT LISTED IN THE PURCHASE ORDER TO
INSURE COMPLIANCE TO ALL NOTED REQUIREMENTS.
EACH INSPECTION ACTIVITY, REQUIRING REPORTS OR NOT, MENTIONED IN THE MANUFACTURER'S ITP, SHALL BE SIGNED IN THE MANUFACTURER'S ITP WHEN
THE ACTIVITY IS PERFORMED.