Sei sulla pagina 1di 1
Lesson 6 * Adding and Tracking Defects To view the status values selected for this graph, click the Configure Outstanding Defects link. The Configure Outstanding Defects dialog box opens. Visible Defeot Statue By default, New, Open, and Reopen are selected. Click OK to close the Configure Outstanding Defects dialog box. Linking Defects to Tests You can link a test in your test plan to a specific defect in the Defects Grid. This is useful, for example, when a new test is created specifically for a known defect. By creating linkage, you can determine if the test should be run based on the status of the defect. Note that you can also link the defect to other entities, such as requirements. A defect can be linked directly or indirectly to an entity. When you add a defect link to an entity, Quality Center adds a direct link to this entity and indirect links to other related entities ‘The following diagram illustrates the flow of indirect linkage: ole eels us

Potrebbero piacerti anche