 History
Group Companies
Business Overview
People

Products & Services


Resources
Projects

Financial Overview
Sunil Hitech : Preferred Partner..
Contact details

2
1984 „Sunil Engineering Works‟
Promoter Ratnakar. M. Gutte

1994 major breakthrough by mega order


Evolution from BHEL at Chandrapur…

Followed by consecutive orders in


Madhya Pradesh and Rajasthan

1998 „Sunil Hitech Engineers Pvt Ltd‟

2004 Again a major break-through order


from NTPC

2006 2nd March 2006 company was


listed on Bombay Stock Exchange &
National Stock Exchange with 9 times
over subscription of Initial Public
Offering (IPO).
Same year company declared a
dividend of 10% for the complete year.
3
2007 Diversified in Hydro Project (4.5 MW
from AHPL at Sechi, HP) and T&D
segment.
Evolution 2008 Received a First EPC Project in ICPP
for 6000 TCD Sugar Plant & 30 MW Co-
Generation Plant and 60 KLPD Distillery
with 1.8 MW Co Gen incineration Boiler at
Gangakhed (MS)

2009 Major breakthrough of “Civil,


Structural & Arch. Work” from BHEL-
PSWR for 2x250 MW Main Plant at
MPPGCL Sarni # 10 &11

Followed by consecutive orders from

- L&T at 3x660 MW MAHAGENCO - Koradi


(MS) & 2X600 MW DB Power - Champa
(CG) site
- Avantha Power at 2x600 MW Jahbua Power
(MP) site
- BHEL at 1 x 600MW SCCL / Singreni (AP)
site.
4
Pan-India network with presence in
more than 11 states

Evolution 2010 Breakthrough of 1 x 250MW


Balance of Plant (BOP) package on
EPC basis at Parli # 8, MSPGCL

- 2012 Foray in 800 MW Boiler erection


from DOOSAN at NTPC – Kudgi site.

- 2013 Diversified in Road project from


NHAI at Munger, Bihar and Building
Construction at PWD/Punjab

- 2014 Diversified in Atomic Power


Project from BHEL at NPCIL
Kakrapar, Surat, Gujrat.
Received order for complete Civil work
including Fabrication & erection of
Piping of CW System & Makeup Water
System at 2x800MW NTPC/LARA.

5
VISION

To contribute to the task of


Evolution development in power, process and
infrastructure area meeting the
benchmarks set by customers in terms
of quality, price and schedules and
satisfy them on consistent basis

6
History

 Group Companies
Business Overview
People

Products & Services


Resources
Projects

Financial Overview
Sunil Hitech : Preferred Partner..
Contact Details

7
Group
Companies Sunil Hi Tech Engineers Ltd
(Public Limited and Listed)
ISO 9001 and OHSAS 18001 Certified

Sunil Hitech India Infra Private Limited


(Infrastructure Development Company)

SEAM Industries Ltd


(Heavy Fabrication & Manufacturing Shop)
ISO 9001 and OHSAS 18001 Certified

Gangakhed Sugar & Energy Ltd


6000TCD Sugar Plant and
30 MW Co gen Plant
60 KLPD Distillery with 1.8 MW Co Gen

8
History
Group Companies
 Business Overview
People

Products & Services


Resources
Projects

Financial Overview
Sunil Hitech : Preferred Partner..
Contact Details

9
Business
Overview

SUNIL HITECH
ENGINEERS LTD.

ROADS & STEEL & MANUFAC BUILDING


NUCLEAR THERMAL
BRIDGES METALS –TURING CONSTN

National Balance of BTG Boiler Residential/


Sinter plant STG Work
Highways Plant Installation Pr. Parts Commercial

Steel Piping
Bridges Melting O&M T&D IBR/NON Industrial
shop IBR

Billet
Tanks & High rise
Storage
Vessels Buildings
Shed

Technologi
Castor
cal
Shop
Structure

BOF, CCP
Plant
10
ISO
Credential

OHSAS 18001 : 2007 ISO 9001 : 2008

11
Business
Overview

End to End Solutions

Design & Engineering

Planning & Scheduling

Project Management

12
Valued
Customer

• Bharat Heavy Electricals Ltd • DOOSAN India Ltd


• MAHAGENCO • GAIL (India) Limited
• NTPC Ltd. • Mahadiscom
• Larsen & Toubro Ltd • Madhya Pradesh Power
Gen. Co.Ltd
• Tata Projects Ltd
• Punj Lloyd Ltd
• Jindal Group & JSW Ltd.
• Reliance Energy Limited
• Avanta Power & Infrastructure Ltd.
• Mahatransco
• Abir Infrastructure Ltd.
• Gammon India Ltd.
13
Valued
Customer

• NCC Ltd. (Nagarjuna Constn. Co. • Lanco infratech Ltd


Ltd)
• Steel Authority of India Ltd (SAIL) • APGENCO
• Chattissgarh SPGCL • Shandong Elect Power
Costnstruction Corp. China
• Adani Power Ltd., • RINL, Visakhapatnam.
• Gujrat Industries Power Co. Ltd • Sterlite Industries , BALCO
• BGR Energy System Ltd. • Jayprakash Associates Ltd
• National Highway Authority of • NBCC
India (NHAI)

•Alstom Bharat Forge Power Ltd. • Thermax


14
QUALITY

Quality Assurance Aspects


• Prior approval of vendors
• Well formulated project specific quality plan
• Adherence to relevant standards & codes
• Empowered quality team
• Regular training of personnel
• Continuous up gradation of work methodology through state of -the-
art techniques
Quality Control Measures
• Well equipped material testing laboratories at all sites
• Regular inspection & testing of incorporated materials
• Adherence to approved inspection procedures for various processes
• Minimizing ‘non-conformance’ by using statistical techniques
15
SAFETY

Safety Measures at our Construction Sites

• Trained safety officers at all sites


• On-site safety awareness programmes
• Motivating Workforce for ensuring safe working conditions
• Compulsory use of Personal Protective Equipments (PPE) & safety
net.
• Barricading open cut out areas & excavated pits
• Electrical Safety, Earthing etc.
• Proper scaffolding systems with adequate cross bracing
• Fire protective extinguishers

16
History
Business Overview
 People

Products & Services


Resources
Projects

Financial Overview
Sunil Hitech : Preferred Partner..
Contact Details

17
People power is the
secret of our growth
Our recognition and
rewards for achievement
begins at the workmen’s
level.
We have set up I-COM
an in-house training
institute that trains
around 150 students
every year. 18
Organization

Mr. Ratnakar. M. Gutte : Chairman


Mr. Sunil. R. Gutte : Managing Director
Mrs. Sudhamati. R. Gutte : Whole Time Director
Mr. Vijay. R. Gutte : Director (Finance)
Mr. Anupam Dhiman : Director (Operation)
Mr. C. Venkataramana : Executive Director
Mr. Anil Aurangabadkar : Independent Director
Mr. Dilip. Y. Ghanekar : Independent Director
Mr. Parag. A. Sakalikar : Independent Director
Mr. Sajid Ali : Independent Director
Mr. Siddharth R. Mehta : Independent Director
Mr. Sonyabapu. S. Waghmare : Independent Director 19
History
Business Overview
People

 Products & Services


Resources
Projects

Financial Overview
Sunil Hitech : Preferred Partner..
Contact Details

20
Product Profile - Projects
POWER SECTOR INDUSTRY SECTOR
1 Boilers & Aux 125~ 800 MW EPC work of Sugar & Co-Gen
Plant
2 Steam Turbine & Aux Oil Storage Tanks
3 BOP EPC works of 250~800MW Civil and Structural works
4 Civil works up to 800MW units Piping systems
5 Structures 125~ 800 MW Pre Engineering Building
6 Critical Piping Fabrication and Erection of
Structures in Steel Plant for
7 Large Dia. Piping & LP Piping • Sintering plant
8 Fuel Oil Systems
POWER SECTOR • Technological Structures
9 Coal Handling Plant & Str. • Steel Melting Shop
10 Cooling Tower (IDCT) • Billet Storage shed
11 RCC Chimney & Its Steel Flue • Castor, BOF and CCP Plants
12 Mini Hydro Civil Works • Universal Rail Beam
13 33kv/66kv/132kv/220kv/ 400kv • Shot Blasting & Painting
Sub Stations
14 Large Storage Sheds • Material Handling Structures &
Eqpt. Erection
21
Boilers and its Auxiliaries

Erection, Testing & Commissioning of Boiler


and its Auxiliaries up to 800 MW.

Boiler Auxiliaries like STG, ESP, Fans, Mills,


APH, Ducting, Critical Piping, LP Piping,
CW/Large Dia. Piping, Ash Slurry and Ash
Disposal Piping

Coal Handling & Ash Handling Plants.


Fabrication & Erection of Steel Chimney Flues.

22
Super Structures & Technological Structure

Fabrication & Erection of Heavy / Super


& Technological Structures for Power
Stations (up to 800 MW units)

-Bunkers ( 10000 to 15000 MT)


-Turbine Generator Building ( 10000 to
12000 MT)

Steel and Metal Industry

-Fabrication & Erection of Technological


Structures
-Structural Steel Works for Castor Shop
-Structural Steel Works for Steel Melt
Shop
-Structural Steel Works for Blast Furnace

Complete installation of Sinter Plant


excluding equipment erection

Sand/Shot Blasting and Painting Works


23
Civil Projects
Civil work (up to 800 MW) DB Power – Ash Silo
EPC – BOP package Bunker foundations
• Foundations
Boiler, ESP, Mills, Fans, CHP,
Pumps PHB, Pipe Rack, Bunker etc
• Raw water reservoir & pump House
• APH composite bldg, Fly ash silo,
L & T Koradi - Service Bldg.
Ash slurry pump
• ESP Control room
• Main Plant Building
• Service Bldg, ETP & Time office Bldg.
• DG & Compressor House Bldg.
• CW Pump house
• Fuel Oil Handling Plant
• Ash Handling Plant
• Coal Handling Plant
Raw Water Reservoir & Pump House

24
Civil Projects
Civil work (upto 800 MW)
EPC – BOP package Koradi (660MW) – TG Deck
• Water treatment plant
a) Pre treatment plant
b) Post treatment plant
• Wagon Trippler, tunnel, control room
• Transformer Yard
• RCC Chimney
• TG Deck
Cooling Tower (IDCT)

HYDRO POWER PLANTS


Civil & Hydro Mechanical Works. Radial &
Vertical Gates, Fabrication of Penstock
Pre water treatment Plant

25
25
TRANSMISSION & DISTRIBUTION
TRANSMISSION

EHV Transmission lines upto 132 kV , 220


kV , 400 kV

EHV Substations upto 132 kV , 220 kV ,


400 kV

Erection, Testing, Commissioning of Power


Transformers upto 200 MVA, C & R
Panels, SCADA System, PLCC
Equipments, HT Capacitors.

Construction of Control Room for EHV


Substation, Cable trenches.

Construction of Heavy consignment roads


for carrying out transformers and other
equipments upto 250 MT.

Earthing system for the entire substation.

26
TRANSMISSION & DISTRIBUTION

DISTRIBUTION

Sub-Transmission lines for 11, 22 & 33 kV.


Substations for 33/11 kV & 22/11 kV upto
10 MVA rating.

Erection, Testing & Commissioning of Pole


Mounted & Plinth Mounted Distribution
Transformers upto 630 kVA rating.

Distribution Network including UG cable


from 1.1 kV upto 33 kV.

27
Product Profile - Manufacturing
BOILER PARTS ESP PARTS
1 Technological Structures Collecting Plates
2 Super heaters & Re Heaters Emitting Electrodes
3 Economizers & Fin Tubes GD Screens
4 High Pressure Bends Support Insulators & Housing
5 Short Radius Bends CERM & EERM System
6 Bunkers Supply of misc. ESP internals
7 Headers
8 Tanks & Vessels
9 Water Wall panels
10 HP & LP Piping

28
Fabrication Shop – Unit 1

Located at 5 Star Industrial Zone


Area, MIDC Butibori, Nagpur.
Just 30 KM away from
International Airport, Nagpur.
Total Area : 1, 56, 519 Sq. Mtr.
(In Acres: 39.12) including
residential land

Unit # 1
Total Area = 30,784 sq. m.
Closed Shed –
Shed-1 : 36 x 36 Meter
Shed-2 : 30x 100 Meter
Open Fabrication Area –
45 x 120 Meter
29
29
Fabrication Shop – Unit 2
Unit# 2
Total Area = 75,138 sq. m.
Open Fabrication Area :
200 x 300 Meter.

Closed Shed – Shed-1 : 30 x 150 Meter


Closed Shed- Shed-2 & Shed-3 :
30 x 50 Meter (each) 30
30
History
Business Overview
People

Products & Services

 Resources
Projects

Financial Overview
Sunil Hitech : Preferred Partner..
Contact Details

31
300 T American 9310 01
230 T Manitowac 4100W 02
150 T Demag TC 500 01
150 T Link Belt LS 528 02
150 T Manitowac 4000 01
150 T Manitowac4000vicon 02
150 T Manitowac4000W 02
136 T LinkBeltLS 518 01
130 T Manitowac 3900W 01
125 T American 7530 01
120 T Lima 1200C 02
100 T American 7260 01
Major Cranes
100 T American 998C 03
100 T Lima 1250SC 01
100 T LinkBelt LS 418 01
100 T LS 418J 01
100 T RB 61B 01
90 T Lorain-L790 01
90 T Manitowac3900 01
80 T Kobelco 880S 01
75T P&H 70TON 02
75 T ALC 955 01
75 T Lima700TC 01
75 T LinkBelt HC218 01
75 T LinkBelt LS 318 02
75 T Manitowac2900W 01
32
75 T Tata P&H 955 01
75 T TFC-280 01
70 T Lima 7070 01
70 T Lima SC 75C 01
70 T ZoomlionQUY 70 12
65 T Kohering 665 01
65 T LORAIN Kohering655 01
60 T American7260 01
60 T FMC LinkBelt LS118 01
60 T Manitowac3500 01
55 T Lima 65C 01
55 T LORAIN Kohering455 01
55 T P&H 550 03
50 T Kohering550 01
50 T LS 108BS 01 Major Cranes
45 T LinkBelt LS 108 01
45 T LS 108B 01
40 T American 4260 03
40 T Demag B410LC 01
40 T LS 108BJ 01
40 T LS108B 01
40 T NCK 450 01
40 T P&H 440 01
40 T P&H 5040 01
35 T Kobelco, P&H 335, Sumitommo 09
25T-18T TATA P&H 335,, PPN, Grove 04
30 T Hydra crane 02
16 T Hydra crane 01
14 T Hydra crane 09
12 T Hydra crane 72
10 T Hydra crane 87
8T Hydra crane 06
33
BATCHING PLANT 30M3 09

CRUSHER 150TPH 03
TRANSIST MIXERS 6M3 18

CONCRETE PUMP 14M3 10


BOOM PLACER 02
HIWA 16
Back hoe Loader (JCB) 03
Wheel Loader (JCB) 03 Civil
TIPPERS 05
EXCAVATORS 05 Equipments
COMPACTORS 05
DEWATERING PUMP 14M3 15
VIBTO ROLLER 03

TOTAL STATION 09

LAB EQUIPMENT 5 SETS

BAR BENDING M/C 26

BAR CUTTING M/C 27

WEIGHT BRIDGE 07

Motor Grader 01

34
WELDING EQUIPMENTS

Welding Generators (K-320/45) 129


Welding Rectifier 450/600A 1951
Welding Inverter M/c 83
Submerged Arc Welding M/c 08
Co2/MIG Welding Machines 225
Argon Welding Sets 105 Welding &
Diesel Power Generator 28 Quality

NDT EQUIPMENTS
Radiography Source Camera 04
MPT Equipments 01
S.R. Equipments 04
Ultrasonic Machines 02
Ultrasonic Thickness Gauge 08

35
• Can complete RCC work to the tune
of 3,00,000 Cum in a year

• Can achieve 8,000 to 10,000 Cum of


peak Concreting in a month per site.

• Can complete 250 MW Boiler works


in 16-18 months & 500 MW Boiler in
28-29 months CAPABILITIES

• Can fabricate and erect 1,25,000 MT


of Structures in a year.

• Can achieve 2,500 - 3,500 MT of peak


fabrication & erection in a month per
site.
• Can complete more than 60,000 high-
pressure joints in Overhauling &
Maintenance works in a year.

36
• Ability to complete 75,000 Non IBR
Field weld joints in a year.

• Have in-house capabilities for


Radiography, UT & MPT.

• Possess more than 80 Crawler Cranes


of capacity 8T to 300T & 175nos of
Hydra cranes CAPABILITIES

• Possess more than 2500 nos. of


Welding Equipments.

• Engineering Drawing detailing by state


of the art software (Stru Cad of ACE
CAD Software system, UK) & dedicated
team for the same.

37
• Breakthrough of
Rs 4880M BOP EPC job
from MAHAGENCO of Parli 250mw unit

• Achieved 2,18,500 Cum Concreting in 2011-


12
• Achieved 7nos. TG Deck casting in 10
months from 250MW to 660MW

• Exceeded 1,00,000mt of Boiler erection and KEY


1,00,000 mt of Structure Fabrication and ACHIEVMNTS
Erection in the year 2008-09 & 2009-10

• Commissioned NTPC – Mauda, Rihand &


Vindhyachal 500 MW units in 27to 28 months

• HT of 500mw Boilers done in a schedule of


9 to 12 months in 5 Units

•Achieved13500mt of Boiler erection in a


year @ Mauda and Bhusawal and 16800 MT
@ Rihand

38
• Executed in 18months Rs.3500M
Gangakhed Sugar & energy Project on
turnkey basis

• Achieved 18500mt of Fabrication &


17500mt erection for Steel works of
2x600mw Hissar in a year

• Completed the tallest transfer point of KEY


CHP & Bunker works of the country’s first ACHIEVMNTS
660mw Super Critical Unit @ Sipat.

• Won 6 safety awards in the year 2012-13 &


4 Safety awards in the year 2013-14.

• Has diversified into Boiler component


manufacturing of 3000mt / month

• Achieved 20,407 MT Boiler erection in a


year (2013-14) at 500MW Vindhyachal NTPC
# 13 which creates new bench mark in BHEL
-PSWR
39
Construction Manager 32
Resident Engineers 55
Engineers 305
Supervisors 204
Materials Management 115
Safety Officers 62
QA / QC Engineers 54
HR & Admin Officers 30 Human
NDT Technicians 20 Resources
Operators & Technicians 460
Electricians 85
H.P. Welders 100
LP Welders 1000
Mill Wright Fitters 45
Pipe Fitters & Fabrication 100
Steel Fabricators 105
Mechanical Foremen 70
Skilled & Semiskilled 10,000

40
History
Business Overview
People

Products & Services


Resources

 Projects

Financial Overview
Sunil Hitech : Preferred Partner..
Contact Details

41
Network in 13 States

MAHARASHTRA HARYANA
Parli # 6&7 Khaperkheda Panipat Hissar
Paras # 2 Chandrapur#7 Halluwas Dahina
Mauda #1 Bhusawal#3&4 Yamunanagar Gurgaon
Tiroda # 1,2,3,4&5 Butibori#1&2
Ratnagiri#1,2,3&4 Nagpur -MIHAN RAJASTHAN
Kalyan Pune
Suratgarh Giral
MADHYA PRADESH Chhabra#1&2 Kota
Vindhyachal # 7,8,9,10,11 &12 Barsingsar#1&2
Bina Amarkantak
Malwa#1

42
Network in 13 States

UTTAR PRADESH PUNJAB GUJRAT


Gailpata Rihand#4,5&6 Bhatinda Dahej Ukai
Parichha Unchahar Mangrol# 3&4
Harduaganj# 8&9 TAMILNADU
KARNATAKA
Dadri # 5&6 Neyveli
Bellary – JSW Bellary – KPCL
Vellor #1&2
CHATTISGARH ORISSA
Korba Raigarh JPL ANDHRA PRADESH Talcher
Sipat#1,2,3,4&5 Tamnar#3 Vizag – RINL
Bhilai#1 Dongamahua/JSPL Simhandri#3&4 HIMACHAL PRADESH
Sechi

43
13 States… 30 Projects

• Projects 37, 589 MW


• Structural Fabrication Erection 6,49,888 MT
•Boiler & Equipment Erection 5,73,607 MT
•Critical Piping 17,500 MT

•Earthwork excavation 76,77,446 M3


•Concreting 7,97,316 M3
•Radiography Testing (RT) 21,18,750 CMS
•Magnetic particle testing (MPT) 2,35,833 CMS
•Ultrasonic Testing (UT) 4,06,250 CMS
44
Projects Completed – Structural sites

Andhra Pradesh
RINL / Vizag steel plant –
Visakhapatnam Steel Plant/RINL: 6.3 MTPA Billet Storage Sheds
Steel plant Expansion Structural Works of Length : 3 x 600 Mtrs.
99,100,101,35,15 Package (60,000MT)

Chhattisgarh
• Sipat/NTPC #1,2&3:
3x660 MW SG Area structural steel Package

• 2x500 MW Sipat /NTPC#4&5:


SG & TG Area Civil & Structure work
3X660 MW & 2X500 MW NTPC:
• 4x250 MW Raigarh /JSPL#1,2,3,4: Sipat –I&II
Main Plant Structure

•2x600 MW Tamnar /JSPL#3:


Main Plant Structure (Bolted Structure)
Gujarat
• 2x125 MW Mangrol/GIPCL#3&4:
Structural Steel Work, Lignite Storage Shed

45
Projects Completed – Structural sites

Haryana Bellary JSW Steel plant – Sinter plant


• 2x600 MW Hissar /HPGCL#1&2:
Main Plant Structural Work

•2x300 MW Yamunanagar/Reliance#2 :
Main Plant Structure

• HPGCL, Panipat
Structure Steel Work for TG & Mill Bay,

Karnataka
• Bellary /JSW Steel Ltd: Bellary KPCL
Structure of Sinter Plant in 7 MTPA

•Bellary /KPCL#2 :
1x500 MW SG & TG Area Structural Works

• 4x300 MW Bellary /JSW Steel & Energy #


1,2,3,4 : General Structure steel & allied work

46
Projects Completed – Structural sites

Maharashtra Reliance / Butibori # 1&2


• 3x660 MW Tiroda /ADANI # 1,2,3,4&5:
Main Plant Structure

• 2 x 500MW Bhusawal /MSPGCL# 4 & 5:


Main Plant Structure & Chumary Building

• 2 x 300 MW Butibori/Reliance# 1&2:,


Bunker & Main Plant Structure,

• 2 X 250 MW Parli/MSPGCL:
SG ,TG structure & CHP of Unit# 6 and 5 x 660 MW Tiroda – Adani # 1,2,3,4&5
Main Plant Structure, Bunker Belt Extn.
System, RCC Chimney Flue of Unit#7

• 2 x 210MW Khaparkheda/MSPGCL #3&4:


Main Plant Structures

• 2X250 MW Paras/MSPGCL:
SG,TG Structure & Fuel Oil Handling System
of Unit#1 and Main Plant Structure, RCC 47
Chimney Flue of Unit# 2
Projects Completed – Structural sites

• 4 x 300MW Ratnagiri/JSW #1,2,3&4 :


MIHAND / MADC – Ware House
Main Plant Structure ,
Port Handling Structure (Jaigarh)

• Nagpur -MIHAN/MADC : Construction


of ware house Pre Engineering Building

Madhya Pradesh
• 2x500 MW Vindhyachal/NTPC # 7&8:
Main Plant Structure

• 2x500 MW Vindhyachal/NTPC # 9&10: JSW Ratnagiri – Port Handling Str.


Main Plant Structure and CW Piping
fabrication work

• 2x250 MW Bina /JAYPEE associate :


Main Plant Structure & CHP

•1x210 MW Amarkantak/MPPGCL # 5:
Structure and CW Piping Work

48
Projects Completed – Structural sites

Odisha
• 4x500 MW Talcher/NTPC: Vindhyachal / NTPC
SG and TG Area Civil Package, Structure
and Ash Piping

Punjab
• 2x250 MW Bhatinda/PSEB:
Bunker Structure

Rajasthan
• 3x250 MW Suratgarh/RRVUNL :
Main Plant Structure, Boiler and Auxiliaries Paras Fuel Oil System
• 2x250 MW Chhabra/RRVUNL#1&2:
Main Plant Structure
• 2x125 MW Giral/RRVUNL #2 :
Main Plant Structure
• 1x195 MW Kota /RRVUNL #7 :
Structural Work

Tamil Nadu
• 2x250 MW Neyveli Lignite Ltd-II:
Expansion Main plant structural works 49
Projects Completed – Structural sites

3 x 500 MW Vallur/NTECL # 1&2:


Main Plant Structural NTPC Talchar Site

• Ennore/TNEB:
Renovation of Boiler Structure

Uttar Pradesh
PATA/GAIL: (Structural Steel Works)
GCU Petrochemical Plant

2x80, TPH HRSG Pata/GAIL:


Structure work
NTPC Rihand # 3 & 4
2 x 500 MW Rihand/NTPC: Misc. Structures
and 250 Meter RCC Chimney flue

2x210 MW Parichha/UPRVUNL#3&4:,
Main Plant Structures

2x250 MW Parichha/UPRVUNL # 5&6:


Main Plant Structure
50
Projects Completed – Boiler & its Auxillaries sites

Andra Pradesh
• 2x500 MW Simhadri/NTPC # 4&5 Simhadri / NTPC Site
Boiler # 5 and Rotating Parts# 4&5

Chhattisgarh
• 1 X 250 MW Bhilai/BESCPL # 1:
Boiler and Auxiliaries, Ash slurry Piping
• 2 x 135 MW Dongamahua/JSPL # 3 & 4:
Boiler & its Auxiliaries, STG and Material
Management.
• 1 x 500 MW Sipat /NTPC # 5:
ESP work Ukai / GSECL
• 1 x 250 MW Raigarh /JSPL # 4:
ESP work
• 1 x 275 TPH Korba:
Boiler Work
• 2 x 135 TPH BALCO # 2 & 3:
Boiler and its auxiliaries

Gujarat
•1 x 500MW Ukai /GSECL: 51
Boiler & its Auxiliaries
Projects Completed – Boiler & its Auxillaries sites

•2x125 MW Mangrol /GIPCL # 3 & 4: 4X300 MW, JSW/Ratnagiri


CFBC Boiler #3 & CW Piping # 3&4 Boiler, STG, ESP – 2 units
Structural work – 4 units
Port handling Structures &
Haryana Equipment
• 2x300 MW Yamunanagar/Reliance#1&2 :,
Non-Pressure Parts & ESP#1&2

Maharastra
• 1 x 500MW Bhusawal /MSPGCL # 4:
Boiler & its Auxiliaries
2x500 mw Bhusawal
• 1 x 500 MW Khaparkheda/MSPGCL:
Boiler # 4
Extension project, Boiler and its Auxiliaries Structure # 3 & 4
and Construction of Ash Bund

•1X500 MW Chandrapur/MSPGCL:
Boiler Auxiliaries

• 2x300MW Ratnagiri/JSW # 1 & 3:


Boiler and its Auxiliaries, and Material
Handling work 52
Projects Completed – Boiler & its Auxillaries sites

Paras site
• 1x300 MW Butibori /Reliance#1&2:
Boiler auxiliaries, and Critical Piping

• 1X250 MW Parli/MSPGCL #6:


Boiler & its Auxiliaries

• 1x250 MW Parli/MSPGCL #7: Boiler & its


Auxiliaries, LD Piping, and MS Pipeline

•1X250 MW Paras/MSPGCL#1:
Fuel Oil Handling System
Khaparkheda site
• 1 x 250 MW Paras/MSPGCL # 2:
Boiler & its Auxiliaries and MS Pipeline

•1x210 MW Khaparkheda/MSPGCL:
Boiler # 3 Misc. Work

53
Projects Completed – Boiler & its Auxillaries sites

Madhya Pradesh
Rihand/NTPC # 5&6
• 1 x 500 MW Vindyachal /NTPC # 11:
Boiler and its auxiliaries

•2 x 600 MW Malwa /MPPGCL # 1:


Critical Piping # 1

Rajasthan
• 2x125 MW Barsingsar/NLC # 1 & 2:
CFBC Boiler and its auxiliaries, Material
management
Barsingsar #1&2 (CFBC Boiler)
Uttar Pradesh
• 2 x 500 MW Rihand/ NTPC # 4&5:
Boiler & its auxiliaries

• 1 x 210 MW Unchahar/ NTPC # 5:


Boiler auxiliaries

• 2 x 490 MW Dadri / NTPC # 5 & 6:


ESP Work
54
Projects Completed – STG WORK

Uttar Prasesh 2X500 MW, NTPC/RIHAND -STG # 5&6


• 2 x 500 MW Rihand/ NTPC # 5&6

Maharastra
• 1 x 250 MW Parli/MSPGCL #7

• 2 x 300MW Ratnagiri/JSW # 1 & 3:

• 2 x 300 MW Butibori /Reliance#1 & 2:

Chhattisgarh 2X300 MW, JSW/Ratnagiri STG # 1&3


• 2 x 135 MW Dongamahua/JSPL # 3 & 4:
2x300 MW Butibori RIL # 1&2

55
Projects Completed – Transmission & Distribution WORK

Maharastra:

• Kalyan /MSEDCL : 22 kV Lines & Sub-station of APDRP-Job


• Chandrapur /MSEDCL : Transmission, Distribution of button line and Sub-station
on turnkey
• Magarpatta /MSETCL : Erection and Construction of 220/822 kV Sub-station
• Bhandup /MSEDCL : Design, Supply, Construction, Erection & Testing of
22/11 kV and 22/22 kV Sub-station under Urban Zone,
Thane.

220 KV Substation at MSETCL Magarpatta Pune 22 Kv Substation at MSEDCL,


Kalyan, Mumbai

56
Projects Completed – Transmission & Distribution WORK

• Aurangabad /MSEDCL : Erection and Testing of Transmission line and Sub-station


of Single Phase DTC of under APDRP)

• Wathar & Bambawade/ : Erection and Construction of 220/33 kV and


(Pune) MSETCL 132/33 kV Sub-station

Haryana
• Halluwas, Dahina and Gurgaon/HVPNL
: 66 kV and 132 kV Sub-station

132 kV Substation, Bambawade 66 Kv Substation at HVPNL, Haryana.

57
Projects Completed – Civil WORK

Chhattisgarh
Parli Residential Bldg.
• 2 x 500 MW NTPC-HSCL/Sipat # 4 & 5

Odhisa
• 2 x 500 MW NTPC/Talchar

Andhra Pradesh
•1X210 MW, VV Reddynagar/APGENCO, Civil
Foundation Work of Boiler and TG Deck

Maharastra
SECHI – Hydro project
• Gangakhed Sugar Plant & 30 MW Co Gen plant
• Parli MSPGCL – Staff Quarter & School
Buildings
• Gangakhed - Staff Quarter Buildings

HIMACHAL PRADEAH

2 X2.5 MW HYDRO POWER PLANTS AT SECHI


Civil & Hydro Mechanical Works.
Radial Gates, Vertical Gates
Fabrication of Penstock 58
Present Order Book – Rs. 35 Billions

• Projects 20,530 MW •Earthwork excavation 1,37,600 M3


• Structural Fabrication Erection 50,000 MT •Concreting 2,00,000 M3
•Boiler & Equipment Erection 2,55,000 MT •Radiography Testing (RT) 17,25,000 CMS
•Critical Piping 15,000 MT •Magnetic Particle Testing (MPT) 2,00,000 CMS
•Ultrasonic Testing (UT) 3,60,000 CMS

59
Presence in 11 States… 32 Projects

MAHARASHTRA CHATTISGARH TAMILNADU


Parli-BOP #8 Mauda # 3 Singhitarai#1&2 (ABIR) Tamnar # 4 Vellor #3
Chandrapur#9 Solapur # 1&2 Champa (DB Power) Nawapara#1&2 ORISHA
Koradi # 8,9&10 Nagpur –VNIT Rajnandgaon LARA (NTPC) Cuttak
UTTAR PRADESH ANDHRA PRADESH Dharliparli
Meja# 1&2 BIHAR
Vizag – RINL, Thermax
Kanpur – KDA Barauni Munger –NHI
Singreni – BHEL,SCCL
MADHYA PRADESH KARNATAKA
Bhawanpadu (ABIR)#1&2
Vindhyachal#13 Jhabua#1 Kudgi# 3
Hyderabad -HGCL
Sarni #10&11 Malwa#2 PUNJAB
GUJRAT Bhatinda
Kakrapar - NPCIL Tarn Taran
60
Ongoing Project – CW Piping Work

Malwa (600MW) Piping


Chhattisgarh

• 3 X 800MW LARA/NTPC/ DOOSAN :


CW System and Make up Water System # 1, 2
& 3 (Order Value 56.23 Cr.)

Odisha

2x800 MW , Dharlipali /NTPC#1&2


CW System and Make up Water System.
(Order Value: 81.06 Cr.)
DB Power / L&T site
Uttar Pradesh

2x660 MW , Meja /NTPC#1&2


CW System and Make up Water System.
(Order Value: 174.9 Cr.)

61
Ongoing Project – Civil & Structural Work

Andhra Pradesh L & T Koradi site.


•1x600MW Singareni /BHEL #1:
-Civil, Structure & Architectural work of Main
plant, and Switch yard package
-Cooling Tower (IDCT)

Chhattisgarh
• 2 x 600 MW Champa/DB Power # 1&2:
Civil, Structural and Architectural Works of
BTG, BOP Main Plant

Maharashtra DB Power / L&T site


• 1 x 250 MW Parli /MSPGCL#8:
Engineering Procurement & Construction
(EPC) of Balance of Plant (BOP) Package

• 3 x 660 MW Koradi /MSPGCL # 8, 9 & 10:


Main Plant Civil, Structural and Architectural
Works
62
Ongoing Project – Civil & Structural Work

Madhya Pradesh BHEL Sarni - TG Deck


• 1 x 600 MW Jhabua/Avanta Power # 1:
Civil, Structure and Architectural Works of
Main Plant, CHP work

• 2 x 250 MW Satpura /MPPGCL # 10 & 11:


Main Plant Civil, Structural and Architectural
Works

Punjab
PWD/ Bhatinda & Tarn Tarn: Construction
of Central Sudhar Ghar
Parli (BOP) – Service Bldg ESP Control Bldg. Transformer Yard

63
Ongoing Project – Structural Work

Andhra Pradesh
2X600 MW Singhitarai /ABIR Site
• 6.3 MTPA Visakhapatnam Steel Power House Bldg.
Plant/RINL: Steel plant Expansion
Structural Works
Bihar
• 1 x 250MW Barauni/ BSEB # 9:
Structural steel work
Chhattisgarh
• 2x600 MW Tamnar /JSPL#4:
Main Plant Structure (Bolted Structure)
•2x600 MW Singhitarai – ABIR # 1 & 2:
Bunker Structure, P.House Bldg. & CHP 2X600 MW Tamnar JSPL site
Rajnandgoan/Lanco :
• Supply and Erection of Polysilicon shed of
1500 TPA Lanco Solar Manufacturing Plant
Maharastra
• 2x660MW NTPC Mauda TPP # 3&4,
Supply, Fabrication & Erection of Bunker &
Bunker Structure
Tamil Nadu
3 x 500 MW Vallur/NTECL # 3:
Main Plant Structural 64
Ongoing Project – Building Construction Work

WaterGreens - Nagpur
WaterGreens – Jaitala Nagpur

• G+7 , 4 Tower Buildings


• 1.5 lacks Sq. foot

Royalty – Ramdaspeth, Nagpur

• 7 Bungalows on 7 Floors
Green Acres - Goa

Green Acres – Goa

• G+4 , 5 Tower Buildings


• 1.5 lacks Sq. foot

65
Ongoing Project – Building Construction Work

Andhra Pradesh WaterGreens - Nagpur


•2 x 600 MW SCCL, Singrani TPP
Construction of Residential Buildings/
Staff Quarter (G+1 Type), GM
Bungalow .

•Construction Administrative Building/


Canopies at Toll Plaza (Pkg 5&6) at
Hyderabad

Maharastra
NTPC Mauda
•2 x 500 MW NTPC Mauda STPP
Civil work of Administrative &
Residential Buildings.

•CPWD/VNIT, Nagpur : Construction


of Class room complex

Uttar Pradesh
•KDA Kanpur
Construction of EWS Houses 22 Bolcks
(G+3) 66
Ongoing Project – Boiler & its Aux

Andhra Pradesh
•2 x 660 MW Bhawanpadu/Abir Infra. Ltd 2 x 600 MW Singhitarai – ABIR # 1&2
# 1&2 : Boiler & its auxiliaries and
Material Management

•Vishakahpatnam/Thermax :
120 MW BFC Boiler and piping work.

Chhattisgarh
•1 X 800MW LARA/NTPC/ DOOSAN :
Boiler, Material Management Package
2 x 300 MW Nawapara # 1&2, TRN Energy
•2 x 600 MW Singhitarai/Abir Infra. Ltd #
1&2 : Boiler & its auxiliaries and Material
Management

• 2 x 300MW Nawapara/TRN Energy #


1&2: Boiler & its auxiliaries.

Karnataka
• 1 X 800MW Kudgi/NTPC/ DOOSAN
# 3: Boiler and Material Management. 67
Ongoing Project – Boiler & its Aux.

Maharashtra Vindhyachal / NTPC # 13 (500MW)


• 1 x 500 MW Chandrapur/MSPGCL # 9:
Boiler Vertical Package

• 1 x 660 MW Mauda / NTPC # 3:


Boiler & its Auxiliaries Package

Madhya Pradesh
• 2 x 600 MW Malwa /MPPGCL # 1 & 2:
Boiler # 2 and Critical piping # 1

•1 x 500 MW Vindhyachal # 13 Mauda / NTPC # 3 (660MW)


Boiler & its Auxiliaries

Orissa
1 x 350 MW Cuttack/KVK Nilanchal # 1:
Boiler and its auxiliaries

Tamil Nadu
1 x 500 MW Vallur/NTECL # 3:
ESP#3 Works
68
Ongoing Project – STG Work

Gujrat
1 x 700 MWe Kakrapar Atomic Power
Project,Nuclear Power Corporation India
Ltd./BHEL # 3, STG & Piping work
Maharashtra
•2x660 MW Solapur-NTPC/Alstom#1&2
STG Work
Madhya Pradesh
• 1 x 500 MW Vindhyachal # 13
STG Package
2x660MW ASLTOM/NTPC Solapur site

Malwa # 1 (600MW) – Critical piping Pkg

69
Ongoing Project – T&D

Nagpur Region

Supply, Testing, Transport, Construction, Erection,


Testing and Commissioning of Distribution Lines,
Distribution Transformers of Various Capacities &
33/11 KV Sub Stations, Other Allied Works, Including
Five Years Guarantee Period for Power
transformers, Distribution Transformer with Allied
Equipment and Two Years Guarantee Period for
Other Works in Nagpur (Rural) & Nagpur (Urban)
Zone for RAPDRP

Kolhapur Region

Supply, Test, Transport, Construction, Erection,


Testing and Commissioning of Distribution Lines,
Distribution Transformers of Various Capacities &
33/22/11 KV Sub Stations, Other Allied Works,
Including Five Years Guarantee Period for Power
transformers, Distribution Transformer with Allied
Equipment and Two Years Guarantee Period for
Other Works in Kolhapur Zone for RAPDRP

70
Ongoing Project – Road & Bridge Projects

BIHAR :

National Highway Authority of India –


Munger site

Construction of Approaches to Rail - Cum -


Road Bridge across River Ganga at Munger
Ghat near Munger from Km 0.00 (km 74.7 of
NH-80) to km 9.394 (start point of Rail-cum-
Road Viaduct) and km 0.075 (end point of
Rail-cum-Road Viaduct) to km 5.198 (km
262.8 of NH-31) in State of Bihar Package
No. RD/BH/2

Total Project Cost: INR 235 Cr

Total Length : 14.5 KM

71
71
Karnataka :

Ministry of Roads and Transport and


Highways – Madhugiri to Mulbagal

Rehabilitation and upgrading to 2-lanes / 2-


Lane with paved shoulders configuration and
Strengthening of Madhugiri to Mulbagal
section (km 343.800 to km 483.151) of NH-
234 under Phase –I of NHIIP [Pkg. No:
NHIIP- KA-234-10]- Information regarding
execution of agreement of Lot-I.

Total project Cost (In Cr): 122.02 INR

Total Length (In Km) : 56.53

72
72
West Bengal :

Ministry of Roads and Transport and


Highways – Bankura to Purulia

Rehabilitation and upgrading to 2-lanes / 2-


Lane with paved shoulders configuration and
Strengthening of Bankura – Purulia Road
Section (km 0.00 to 84.00) of NH-60A in the
State of West Bengal under Phase-I of
Natinal Highways Inter-connectivity
Improvement Projects (NHIIP).

Total project Cost (In Cr): 322 INR

Total Length (In Km) : 84.00

73
73
Ongoing Project – Municipal Solid Waste
Patna:

Bihar Urban Infrastructure Develoment


Corporation and Patna Municipal
Corporation

Design, Finance, Development, Construction,


Operation, Maintenance, Management and
transfer of a Regional Municipal Solid Waste
to Energy (Electricity) and land fill Facility at
Patna in Bihar

Total project Cost : INR 225 Cr

Capacity of Project : 1000 TPD

Power Generation : 11.5 MW

74
74
Kolhapur:

Kolhapur Municipal Corporation

Develop a MSW Processing Facility for


treating the MSW collected from the city of
Kolhapur on Design, Build, Finance, Operate
and Transfer (the "DBFOT") basis.

Total project Cost : INR 25 Cr

Capacity of Project : 200 TPD

Power Generation : 2 MW

75
75
Ongoing Project – Solar Power

Solapur :

Solar Energy Corporation of India

Develop, Own, Design, Finance, Construct,


Commission, Operate and Maintain a 5 MW
Solar Power Project in the State of
Maharashtra under JNNSM Phase II Batch I.

Total project Cost : INR 42.5 Cr

Power Generation : 5 MW

76
76
History
Business Overview
People

Products & Services


Resources
Projects

 Financial Overview
Sunil Hitech : Preferred Partner..
Contact Details

77
(Rs. In Millions) 2011-12 2012-13 2013-14
Sales 9772 12617 15844
Paid up Capital 122 122 136
Reserve & Surplus 2602 3005 3299
Book Value per Share (Amt. in Rs.) 222 254 255
Cash Accruals 627 686 575
Profit before Tax 531 556 481
Profit after Tax 301 356 292
Earnings per share 25 29 24
Gross Block 1611 1975 2036
Promoter’s Equity ( % ) 53.2% 53.2% 64.4%
78
OUR
BANKERS

UCO Bank, Nagpur Axis Bank


Union Bank of India, Nagpur Punjab National Bank
IDBI BANK, Nagpur Kotak Mahindra
HSBC Bank, Mumbai Karur Vysyaya Bank
Oriental Bank of Commerce Canara Bank
Bank of India, Nagpur Syndicate Bank
ICICI Bank State Bank of Travancore

79
Facilities we enjoy…
Existing Proposed
(Rs. In Millions) (Rs. In Millions)
Fund Based

Cash Credit 3000 3250


Term Loan 0 0

Total 3000 3250

Non Fund Based

Letter of Credit 2000 2750

Bank Guarantee 6500 8650

Total 8500 11400


80
RECENT
GROWTH

20000 18000
15379
15000 12617
9772
10000 8153

5000

0
2010-11 2011-12 2012-13 2013-14 2014-15 (Plan)

* Consolidated
81
History
Business Overview
People

Products & Services


Resources
Projects

Financial Overview

 Sunil Hitech : Preferred Partner..


Contact Details

82
Preferred
Partner • Competitive rates
• Timely execution capability
• High Quality & Safety Standard
• Financially Strong
• Highly diversified Product profile
• Largely owned construction equipment Bank
• Experience of more than 15 years
• Network in more than 13 States

83
84
History
Business Overview
People

Products & Services


Resources
Projects

Financial Overview
Sunil Hitech : Preferred Partner..

 Contact Details

85
Contact Us

HEAD OFFICE:
Thank 97, EAST HIGH COURT ROAD,
RAMDASPETH,
You !! NAGPUR 440 010,
MAHARASHTRA (INDIA)
PH No: 0712 – 6685200 (400 Lines)
Fax no : 0712 2562091
Web Site: www.sunilhitech.com
Email : info@sunilhitech.com

CORPORATE OFFICE:

602, TRADE CENTRE


BANDRA KURLA COMPLEX
MUMBAI 400 051,
MAHARASHTRA (INDIA)
PH No : 022 – 61872400
Fax No : 022 – 61872455
Email : wr@sunilhitech.com

86

Potrebbero piacerti anche