Sei sulla pagina 1di 175

BCES CONS2.1.1.1.

PCC 1:4:8 (1 cement : 4 couarse sand : 8 graded stone aggregate


Details of cost of 1 CUMTR Thk
Proporation 1 : 4 : 8

Sr. No. Items Unit Volume Rate


Materials

1.00
CEMENT 3% 3.17 250
wastage 0.10 250
Constant 0.11
Sand 20% 0.44 1271
wastage 0.09 1271
Aggregate 0.88 777
wastage 10% 0.09 777
Shuttering 1 Sqmtr 1.00 138.85
escalation 1.00 0

Total Material
Labour
Shuttering Labour 1 45
Escalation 1 0
Scaffoloding(L) 1
Scaffolding (L) Escalation 10% 1 0
Labour Rate poring 1 225
Labour Rate Escalation 0% 1 0
Supporting Labout 10% 270 1 27
Escalation 0% 1 0
Add for mixing & transport 1 160
Escalation 0% 1 0

Total (Labour + Material)


Add for Hire Charges & Maintenance of mixer, sundries & contingencies %

Profit & Overhead


Cost per unit
mm
mm

Amount Remark

792.50
25.00
0.00
559.24
114.39
683.76
69.93
138.85
0

2383.67 A

45.00
0.00
0.00
0.00
225.00
0.00
27.00
0.00
160.00
0.00
457.00 B
2840.67 C= A + B
0.00

2840.67 D

0.00 E
2840.67
BCES CONS2.1.1.2.
PCC 1:3:6 (1 cement : 3 couarse sand : 6 graded stone aggregate
Details of cost of 1 CUMTR Thk
Proporation 1 : 3 : 6

Sr. No. Items Unit Volume Rate


Materials

CUM 1.00
CEMENT 3% 4.12 250
wastage 0.12 250
Constant 0.14
Sand 20% 0.43 1271
wastage 0.09 1271
Aggregate 0.86 777
wastage 10% 0.09 777
Shuttering 1 Sqmtr 1.00 138.85
escalation 1.00 0

Total Material
Labour
Shuttering Labour 1 45
Escalation 1 0
Scaffoloding(L) 1
Scaffolding (L) Escalation 10% 1 0
Labour Rate poring 1 225
Labour Rate Escalation 0% 1 0
Supporting Labout 10% 270 1 27
Escalation 1 0
Add for mixing & transport 1 160
Escalation 0% 1 0

Total (Labour + Material)


Add for Hire Charges & Maintenance of mixer, sundries & contingencies %

Profit & Overhead


Cost per unit
mm
mm

Amount Remark

1030.00
30.00
0.00
545.26
109.31
666.67
69.93
138.85
0.00

2590.011 A

45.00
0.00
0.00
0.00
225.00
0.00
27.00
0.00
160.00
0.00
457.00 B
3047.01 C= A + B
0.00

3047.01 D

0.00 E
3047.01
BCES CONS2.1.1.2. (a)
PCC 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate
Details of cost of 1 CUMTR Thk
Proporation 1 : 2 : 4

Sr. No. Items Unit Volume Rate


Materials

CUM 1.00
CEMENT 3% 6.50 250
wastage 0.20 250
Constant 0.23
Sand 20% 0.451 1271
wastage 0.09 1271
Aggregate 0.90 777
wastage 10% 0.09 777
Shuttering 1 Sqmtr 1.00 138.85
Escalation 1.00 0

Total Material
Labour
Shuttering Labour 1 45
Escalation 1 0
Scaffoloding(L) 1
Scaffolding (L) Escalation 10% 1 0
Labour Rate poring 1 225
Labour Rate Escalation 0% 1 0
Supporting Labout 10% 270 1 27
Escalation 0% 1 0
Add for mixing & transport 1 160
Escalation 0% 1 0

Total (Labour + Material)


Add for Hire Charges & Maintenance of mixer, sundries & contingencies %

Profit & Overhead


Cost per unit
mm
mm

Amount Remark

1625.00
50.00
0.00
573.22
109.31
700.85
69.93
138.85
0.00

3267.161 A

45.00
0.00
0.00
0.00
225.00
0.00
27.00
0.00
160.00
0.00
457.00 B
3724.16 C= A + B
0.00

3724.16 D

0.00 E
3724.16
BCES CONS2.1.1.3.
M15 grade concrete with minimum cementitious content of 325 kg/cum.
Details of cost of 1 CUMTR Thk
Proporation 1 : :

Sr. No. Items Unit Volume Rate


Materials

RMC M15 1 3281


wastage 2% 0.02 3281
CEMENT 41.21
wastage 3% 1.24
Constant 1.43
Sand 0.00
wastage 20% 0.00
Aggregate 0.00
wastage 10% 0.00
Shuttering 1 Sqmtr 1.00 138.85
Escalation 1.00 138.85
Cement slurry 0.10 1.00 0

Total Material
Labour
Shuttering Labour 1 45
Escalation 1 0
Scaffoloding(L) 1
Scaffolding (L) Escalation 10% 1 0
Labour Rate poring 1 225
Labour Rate Escalation 0% 1 0
Supporting Labour 10% 270 1 22.5
Escalation 0% 1 0
Add for mixing & transport 1
Escalation 10% 1 0

Total (Labour + Material)


Add for Hire Charges & Maintenance of mixer, sundries & contingencies %

Profit & Overhead


Cost per unit
mm
mm

Amount Remark

3281.00 incl.buttering
65.62

0.00
0.00
0.00
0.00
0.00
0.00
138.85
0.00
0.00

3485.47

45.00
0.00
0.00
0.00
225.00
0.00
22.50
0.00
0.00
0.00
292.50 B
3777.97 C= A + B
0.00

3777.97 D

0.00 E
3777.97
BCES CONS2.1.2.1.1.
R.C.C. Footing (Concrete with Greenseal 100 or equivalent admixture as per manufacturers specification)
Details of cost of 1 CUMTR Thk
Proporation 1 : :

Sr. No. Items Unit Volume Rate


Materials

RMC M30 1 3888


wastage 2% 0.02 3888
CEMENT 41.21
wastage 3% 1.24
Constant 1.43
Sand 0.00
wastage 20% 0.00
Aggregate 0.00
wastage 10% 0.00
Other
Shuttering 1 Sqmtr 1.50 138.85
Escalation 1.50 138.85
Cement slurry 0.10 1.00 0
Waterproofing admixture

Total Material
Labour
Shuttering Labour 1.5 75
Escalation 0% 1.5 0
Scaffoloding(L) 1
Scaffolding (L) Escalation 10% 1 0
Labour Rate poring 1 225
Labour Rate Escalation 0% 1 0
Supporting Labour 10% 337.5 1 33.75
Escalation 0% 1 0
Add for mixing & transport 1
Escalation 10% 1 0

Total (Labour + Material)


Add for Hire Charges & Maintenance of mixer, sundries & contingencies %

Profit & Overhead


Cost per unit
nufacturers specification)
mm
mm

Amount Remark

3888.00
77.76

0.00
0.00
0.00
0.00
0.00
0.00

208.28
0.00
0.00

4174.04

112.50
0.00
0.00
0.00
225.00
0.00
33.75
0.00
0.00
0.00
371.25 B
4545.29 C= A + B
0.00

4545.29 D

0.00 E
4545.29
BCES CONS2.1.2.1.1.
R.C.C. Plinth Beams (Concrete with Greenseal 100 or equivalent admixture as per manufacturers specification)
Details of cost of 1 CUMTR Thk
Proporation 1 : :

Sr. No. Items Unit Volume Rate


Materials

RMC M30 1 3888


wastage 2% 0.02 3888
CEMENT 41.21
wastage 3% 1.24
Constant 1.43
Sand 0.00
wastage 20% 0.00
Aggregate 0.00
wastage 10% 0.00
Other
Shuttering 9 Sqmtr 9.00 227.63
wastage 0% 1.50 138.85
Cement slurry 0.10 1.00 0
Waterproofing admixture

Total Material
Labour
Shuttering Labour 9 82
Escalation 0% 9 0
Scaffoloding(L) 1
Scaffolding (L) Escalation 10% 1 0
Labour Rate poring 1 225
Labour Rate Escalation 0% 1 0
Supporting Labour 13% 963 1 125.19
Escalation 0% 1 0
Add for mixing & transport 1
Escalation 10% 1 0

Total (Labour + Material)


Add for Hire Charges & Maintenance of mixer, sundries & contingencies %

Profit & Overhead


Cost per unit
er manufacturers specification)
mm
mm

Amount Remark

3888.00
77.76

0.00
0.00
0.00
0.00
0.00
0.00

2048.67
0.00
0.00

6014.43

738.00
0.00
0.00
0.00
225.00
0.00
125.19
0.00
0.00
0.00
1088.19 B
7102.62 C= A + B
0.00

7102.62 D

0.00 E
7102.62
BCES CONS2.1.2.1.3
R.C.C. Beam at Upper Podium level (with height of scaffolding, shuttering & staging as showin in the drawing)
Details of cost of 1 CUMTR Thk
Proporation 1 : :

Sr. No. Items Unit Volume Rate


Materials

RMC M30 1 3888


wastage 2% 0.02 3888
CEMENT 41.21
wastage 3% 1.24
Constant 1.43
Sand 0.00
wastage 20% 0.00
Aggregate 0.00
wastage 10% 0.00
Other
Shuttering 7.6 Sqmtr 7.60 227.63
wastage 0% 7.60 227.63
Cement slurry 0.10 1.00 0
Waterproofing admixture

Total Material
Labour
Shuttering making 7.6
Escalation 0% 7.6 0
Shuttering Labour 7.6 110
Escalation 0% 7.6
Scaffoloding(L) 1
Scaffolding (L) Escalation 10% 1 0
Labour Rate poring 1 225
Labour Rate Escalation 0% 1 0
Supporting Labour 13% 1061 1 137.93
Escalation 0% 1 0
Add for mixing & transport 1
Escalation 10% 1 0

Total (Labour + Material)


Add for Hire Charges & Maintenance of mixer, sundries & contingencies %

Profit & Overhead


Cost per unit
ging as showin in the drawing)
mm
mm

Amount Remark

3888.00
77.76

0.00
0.00
0.00
0.00
0.00
0.00

1729.99
0.00
0.00

5695.75

0.00
0.00
836.00
0.00
0.00
0.00
225.00
0.00
137.93
0.00
0.00
0.00
1198.93 B
6894.68 C= A + B
0.00

6894.68 D

0.00 E
6894.68
BCES CONS2.1.2.1.4
R.C.C. Slab and Upper Podium level (with height of scaffolding, shuttering & staging as showin in the drawing)
Details of cost of 1 CUMTR Thk
Proporation 1 : :

Sr. No. Items Unit Volume Rate


Materials

RMC M30 1 3888


wastage 2% 0.02 3888
CEMENT 41.21
wastage 3% 1.24
Constant 1.43
Sand 0.00
wastage 20% 0.00
Aggregate 0.00
wastage 10% 0.00
Other
Shuttering 6.85 Sqmtr 6.85 164
wastage 0% 6.85 164
Cement slurry 0.10 1.00 0
Waterproofing admixture

Total Material
Labour
Shuttering making 6.85
Escalation 0% 6.85 0
Shuttering Labour 6.85 110
Escalation 0% 7.6
Scaffoloding(L) 1
Scaffolding (L) Escalation 10% 1 0
Labour Rate poring 1 225
Labour Rate Escalation 0% 1 0
Supporting Labour 13% 978.5 1 127.205
Escalation 0% 1 0
Add for mixing & transport 1
Escalation 10% 1 0

Total (Labour + Material)


Add for Hire Charges & Maintenance of mixer, sundries & contingencies %

Profit & Overhead


Cost per unit
ging as showin in the drawing)
mm
mm

Amount Remark

3888.00
77.76

0.00
0.00
0.00
0.00
0.00
0.00

1123.40
0.00
0.00

5089.16

0.00
0.00
753.50
0.00
0.00
0.00
225.00
0.00
127.21
0.00
0.00
0.00
1105.71 B
6194.87 C= A + B
0.00

6194.87 D

0.00 E
6194.87
BCES CONS2.1.2.1.5
Stilt Floor Slab
Details of cost of 1 CUMTR Thk
Proporation 1 : :

Sr. No. Items Unit Volume Rate


Materials

RMC M30 1 3888


wastage 2% 0.02 3888
CEMENT 41.21
wastage 3% 1.24
Constant 1.43
Sand 0.00
wastage 20% 0.00
Aggregate 0.00
wastage 10% 0.00
Other
Shuttering 7.6 Sqmtr 7.60 227.6
wastage 0% 7.60 227.6
Cement slurry 0.10 1.00 0
Waterproofing admixture

Total Material
Labour
Shuttering making 7.6
Escalation 0% 7.6 0
Shuttering Labour 7.6 110
Escalation 0% 7.6
Scaffoloding(L) 1
Scaffolding (L) Escalation 10% 1 0
Labour Rate poring 1 225
Labour Rate Escalation 0% 1 0
Supporting Labour 13% 1061 1 137.93
Escalation 0% 1 0
Add for mixing & transport 1
Escalation 10% 1 0

Total (Labour + Material)


Add for Hire Charges & Maintenance of mixer, sundries & contingencies %

Profit & Overhead


Cost per unit
mm
mm

Amount Remark

3888.00
77.76

0.00
0.00
0.00
0.00
0.00
0.00

1729.76
0.00
0.00

5695.52

0.00
0.00
836.00
0.00
0.00
0.00
225.00
0.00
137.93
0.00
0.00
0.00
1198.93 B
6894.45 C= A + B
0.00

6894.45 D

0.00 E
6894.45
BCES CONS2.1.2.1.6
Stilt Floor Slab
Details of cost of 1 CUMTR Thk
Proporation 1 : :

Sr. No. Items Unit Volume Rate


Materials

RMC M30 1 3888


wastage 2% 0.02 3888
CEMENT 41.21
wastage 3% 1.24
Constant 1.43
Sand 0.00
wastage 20% 0.00
Aggregate 0.00
wastage 10% 0.00
Other
Shuttering 5.045 Sqmtr 5.045 227.6
wastage 0% 5.045 227.6
Cement slurry 0.10 1.00 0
Waterproofing admixture

Total Material
Labour
Shuttering making 7
Escalation 0% 7 0
Shuttering Labour 7 110
Escalation 0% 7
Scaffoloding(L) 1
Scaffolding (L) Escalation 10% 1 0
Labour Rate poring 1 225
Labour Rate Escalation 0% 1 0
Supporting Labour 13% 995 1 129.35
Escalation 0% 1 0
Add for mixing & transport 1
Escalation 10% 1 0

Total (Labour + Material)


Add for Hire Charges & Maintenance of mixer, sundries & contingencies %

Profit & Overhead


Cost per unit
mm
mm

Amount Remark

3888.00
77.76

0.00
0.00
0.00
0.00
0.00
0.00

1148.24
0.00
0.00

5114.00

0.00
0.00
770.00
0.00
0.00
0.00
225.00
0.00
129.35
0.00
0.00
0.00
1124.35 B
6238.35 C= A + B
0.00

6238.35 D

0.00 E
6238.35
BCES CONS2.1.2.1.7
First Floor Beams
Details of cost of 1 CUMTR Thk
Proporation 1 : :

Sr. No. Items Unit Volume Rate


Materials

RMC M30 1 3888


wastage 2% 0.02 3888
CEMENT 41.21
wastage 3% 1.24
Constant 1.43
Sand 0.00
wastage 20% 0.00
Aggregate 0.00
wastage 10% 0.00
Other
Shuttering 8 Sqmtr 8.000 227.6
wastage 0% 8.000 227.6
Cement slurry 0.10 1.00 135
Waterproofing admixture

Total Material
Labour
Shuttering making 8
Escalation 0% 8 0
Shuttering Labour 8 110
Escalation 0% 8
Scaffoloding(L) 8 35
Scaffolding (L) Escalation 10% 8 0
Labour Rate poring 1 247
Labour Rate Escalation 0% 1 0
Supporting Labour 13% 1127 1 146.51
Escalation 0% 1 0
Add for mixing & transport 1
Escalation 10% 1 0

Total (Labour + Material)


Add for Hire Charges & Maintenance of mixer, sundries & contingencies %

Profit & Overhead


Cost per unit
mm
mm

Amount Remark

3888.00
77.76

0.00
0.00
0.00
0.00
0.00
0.00

1820.80
0.00
135.00

5921.56

0.00
0.00
880.00
0.00
280.00
0.00
247.00
0.00
146.51
0.00
0.00
0.00
1553.51 B
7475.07 C= A + B
0.00

7475.07 D

0.00 E
7475.07
BCES CONS2.1.2.1.8
First Floor Slab
Details of cost of 1 CUMTR Thk
Proporation 1 : :

Sr. No. Items Unit Volume Rate


Materials

RMC M30 1 3888


wastage 2% 0.02 3888
CEMENT 41.21
wastage 3% 1.24
Constant 1.43
Sand 0.00
wastage 20% 0.00
Aggregate 0.00
wastage 10% 0.00
Other
Shuttering (M) 7 Sqmtr 7.000 164
Escalation 10% 1.000
Staging Scafolding (M) 7 7.000 135
Cement slurry 0.10 1.00
Waterproofing admixture

Total Material
Labour
Shuttering making 7
Escalation 0% 7 0
Shuttering Labour 7 110
Escalation 0% 7
Scaffoloding(L) 7 35
Scaffolding (L) Escalation 10% 7 0
Labour Rate poring 1 247
Labour Rate Escalation 0% 1 0
Supporting Labour 13% 1017 1 132.21
Escalation 0% 1 0
Add for mixing & transport 1
Escalation 10% 1 0

Total (Labour + Material)


Add for Hire Charges & Maintenance of mixer, sundries & contingencies %

Profit & Overhead


Cost per unit
mm
mm

Amount Remark

3888.00
77.76

0.00
0.00
0.00
0.00
0.00
0.00

1148.00
0.00
945.00

6058.76

0.00
0.00
770.00
0.00
245.00
0.00
247.00
0.00
132.21
0.00
0.00
0.00
1394.21 B
7452.97 C= A + B
0.00

7452.97 D

0.00 E
7452.97
BCES CONS2.1.2.1.9
R.C.C. Beam at all levels
Details of cost of 1 CUMTR Thk
Proporation 1 : :

Sr. No. Items Unit Volume Rate


Materials

RMC M30 1 3888


wastage 2% 0.02 3888
CEMENT 41.21
wastage 3% 1.24
Constant 1.43
Sand 0.00
wastage 20% 0.00
Aggregate 0.00
wastage 10% 0.00
Other
Shuttering (M) 10.5 Sqmtr 10.500 227.63
Escalation 0% 10.500 227.63
Scafolding (M) 1.000
Cement slurry 0.10 1.00
Waterproofing admixture

Total Material
Labour
Shuttering making 10.5 0
Escalation 0% 10.5 0
Shuttering Labour 10.5 125
Escalation 0% 10.5 0
Scaffoloding(L) 1 0
Scaffolding (L) Escalation 10% 1 0
Labour Rate poring 1 375
Labour Rate Escalation 0% 1 0
Supporting Labour 13% 1687.5 1 219.375
Escalation 0% 1 0
Add for mixing & transport 1
Escalation 10% 1 0

Total (Labour + Material)


Add for Hire Charges & Maintenance of mixer, sundries & contingencies %

Profit & Overhead


Cost per unit
mm
mm

Amount Remark

3888.00
77.76

0.00
0.00
0.00
0.00
0.00
0.00

2390.12
0.00
0.00

6355.88

0.00
0.00
1312.50
0.00
0.00
0.00
375.00
0.00
219.38
0.00
0.00
0.00
1906.88 B
8262.75 C= A + B
0.00

8262.75 D

0.00 E
8262.75
BCES CONS2.1.2.1.11
Staircase
Details of cost of 1 CUMTR Thk
Proporation 1 : :

Sr. No. Items Unit Volume Rate


Materials

RMC M30 1 3888


wastage 2% 0.02 3888
CEMENT 41.21
wastage 3% 1.24
Constant 1.43
Sand 0.00
wastage 20% 0.00
Aggregate 0.00
wastage 10% 0.00
Other
Shuttering (M) 8.79 Sqmtr 8.790 243
Escalation 0% 8.790 243
Scafolding (M)
Cement slurry 0.10 1.00
Waterproofing admixture

Total Material
Labour
Shuttering making 8.79 0
Escalation 0% 8.79 0
Shuttering Labour 8.79 125
Escalation 0% 8.79 0
Scaffoloding(L) 1
Scaffolding (L) Escalation 10% 1 0
Labour Rate poring 1 375
Labour Rate Escalation 0% 1 0
Supporting Labour 13% 1473.8 1 191.588
Escalation 0% 1 0
Add for mixing & transport 1
Escalation 10% 1 0

Total (Labour + Material)


Add for Hire Charges & Maintenance of mixer, sundries & contingencies %

Profit & Overhead


Cost per unit
mm
mm

Amount Remark

3888.00
77.76

0.00
0.00
0.00
0.00
0.00
0.00

2135.97
0.00
0.00

6101.73

0.00
0.00
1098.75
0.00
0.00
0.00
375.00
0.00
191.59
0.00
0.00
0.00
1665.34 B
7767.07 C= A + B
0.00

7767.07 D

0.00 E
7767.07
BCES CONS2.1.2.2
a) RCC Columns
Details of cost of 1 CUMTR Thk
Proporation 1 : :

Sr. No. Items Unit Volume Rate


Materials

RMC M40 1 4280


wastage 2% 0.02 4280
CEMENT 41.21
wastage 3% 1.24
Constant 1.43
Sand 0.00
wastage 20% 0.00
Aggregate 0.00
wastage 10% 0.00
Other
Shuttering (M) 9.46 Sqmtr 9.460 192
Escalation 0% 9.460 192
Scafolding (M)
Cement slurry 0.10 1.00
Waterproofing admixture

Total Material
Labour
Shuttering making 9.46 0
Escalation 0% 9.46 0
Shuttering Labour 9.46 125
Escalation 0% 9.46 0
Scaffoloding(L) 1
Scaffolding (L) Escalation 10% 1 0
Labour Rate poring 1 375
Labour Rate Escalation 0% 1 0
Supporting Labour 13% 1557.5 1 202.475
Escalation 0% 1 0
Add for mixing & transport 1
Escalation 10% 1 0

Total (Labour + Material)


Add for Hire Charges & Maintenance of mixer, sundries & contingencies %

Profit & Overhead


Cost per unit
mm
mm

Amount Remark

4280.00
85.60

0.00
0.00
0.00
0.00
0.00
0.00

1816.32
0.00
0.00

6181.92

0.00
0.00
1182.50
0.00
0.00
0.00
375.00
0.00
202.48
0.00
0.00
0.00
1759.98 B
7941.90 C= A + B
0.00

7941.90 D

0.00 E
7941.90
BCES CONS2.1.2.2
b) Lift pardi
Details of cost of 1 CUMTR Thk
Proporation 1 : :

Sr. No. Items Unit Volume Rate


Materials

RMC M40 1 4280


wastage 2% 0.02 4280
CEMENT 41.21
wastage 3% 1.24
Constant 1.43
Sand 0.00
wastage 20% 0.00
Aggregate 0.00
wastage 10% 0.00
Other
Shuttering (M) 9.22 Sqmtr 9.220 275.22
Escalation 0% 9.220 275.22
Scafolding (M)
Cement slurry 0.10 1.00
Waterproofing admixture

Total Material
Labour
Shuttering making 9.22 0
Escalation 0% 9.22 0
Shuttering Labour 9.22 125
Escalation 0% 9.22 0
Scaffoloding(L) 1
Scaffolding (L) Escalation 10% 1 0
Labour Rate poring 1 375
Labour Rate Escalation 0% 1 0
Supporting Labour 13% 1527.5 1 198.575
Escalation 0% 1 0
Add for mixing & transport 1
Escalation 10% 1 0

Total (Labour + Material)


Add for Hire Charges & Maintenance of mixer, sundries & contingencies %

Profit & Overhead


Cost per unit
mm
mm

Amount Remark

4280.00
85.60

0.00
0.00
0.00
0.00
0.00
0.00

2537.53
0.00
0.00

6903.13

0.00
0.00
1152.50
0.00
0.00
0.00
375.00
0.00
198.58
0.00
0.00
0.00
1726.08 B
8629.20 C= A + B
0.00

8629.20 D

0.00 E
8629.20
BCES CONS2.2.2.2b
a) TMT bars (high yield strength deformed bars - Fe 500 conforming to IS 1786)
Details of cost of 1 MTON Thk
Proporation : Ht/W

Sr. No. Items Unit Volume Rate


Materials

STEEL 1 38500
wastage 5% 0.05 38500
Chair & pins & unauthorized laps 0% 0.00 38000
Rolling margin 0.00 38000
Cover Blocks MT 1.00 100
wastage 0% 0.00
Binding wire Gl (entire proj) 10 Kg. 10.00 66
wastage

Total Material
Labour
Scaffolding (L) 1
Scaffolding (L) Escalation 10% 1 0
Labour Rate 1 2850
Labour Rate Escalation 0% 1 0
Supporting Labour 8.50% 1 242.25
Escalation 0% 1
ADD for Chamfering 1
Escalation 10% 1
Total Labour
Total (Labour + Material)
Add for Hire Charges & Maintenance of mixer, sundries & contingencies %

Profit & Overhead


Cost per unit
Amount Remark

38500.00
1925.00
0.00
0.00
100.00
0.00
660.00
0.00
0.00

41185.00

0.00
0.00
2850.00
0.00
242.25
0.00
0.00
0.00
3092.25
44277.25
0.00

44277.25 D

0.00 E
44277.25
BCES CONS2.2.1 (a)
a) TMT bars (high yield strength deformed bars - Fe 415 conforming to IS 1786)
Details of cost of 1 MTON Thk
Proporation : Ht/W

Sr. No. Items Unit Volume Rate


Materials

STEEL 1 38000
wastage 5% 0.05 38000
Chair & pins & unauthorized laps 0% 0.00 38000
Rolling margin 0.00 38000
Cover Blocks MT 1.00 100
wastage 0%
Binding wire Gl (entire proj) 10 Kg. 10.00 66
wastage

Total Material
Labour
Scaffolding (L) 1
Scaffolding (L) Escalation 10% 1 0
Labour Rate 1 2850
Labour Rate Escalation 0% 1 0
Supporting Labour 8.50% 1 242.25
Escalation 0% 1
ADD for Chamfering 1
Escalation 10% 1
Total Labour
Total (Labour + Material)
Add for Hire Charges & Maintenance of mixer, sundries & contingencies %

Profit & Overhead


Cost per unit
Amount Remark

38000.00
1900.00
0.00
0.00
100.00
0.00
660.00
0.00
0.00

40660.00

0.00
0.00
2850.00
0.00
242.25
0.00
0.00
0.00
3092.25
43752.25
0.00

43752.25 D

0.00 E
43752.25
BCES CONS2.2.1 (a)
c) Mild steel
Details of cost of 1 MTON Thk
Proporation : Ht/W

Sr. No. Items Unit Volume Rate


Materials

MILD STEEL 1 34000


wastage 5% 0.05 34000
Chair & pins & unauthorized laps 0% 0.00 34000
Rolling margin 0% 0.00 34000
Cover Blocks MT 1.00 100
wastage 0%
Binding wire Gl (entire proj) 10 Kg. 10.00 66
wastage

Total Material
Labour
Scaffolding (L) 1
Scaffolding (L) Escalation 0% 1 0
Labour Rate 1 2850
Labour Rate Escalation 0% 1 0
Supporting Labour 8.50% 1 242.25
Escalation 0% 1
ADD for Chamfering 1
Escalation 0% 1
Total Labour
Total (Labour + Material)
Add for Hire Charges & Maintenance of mixer, sundries & contingencies %

Profit & Overhead


Cost per unit
Amount Remark

34000.00
1700.00
0.00
0.00
100.00
0.00
660.00
0.00
0.00

36460.00

0.00
0.00
2850.00
0.00
242.25
0.00
0.00
0.00
3092.25
39552.25
0.00

39552.25 D

0.00 E
39552.25
BCES CONS 3.1
Providing and constructing 230mm or more thick masonry in
Details of cost of 1 Cu mtr Brick work 230
Proporation 1 : 6 Joint 10

Sr. No. Items Unit Volume Rate


Materials
Fly ash bricks 0.0026 378.8
wastage 5% 18.9
MORTER 5% 397.7
Volume of brick work M3 1
Wet volume of BW M3 0.22
Add Due to frog filling 0% M3 0.22
total Dry Volume 0.3333 M3 0.29
CEMENT
Cement required for 1m 17.8333 % Bags 5.136
wastage required 3% % Bags 0.15
cement incl wastage 5.29
Total Cement Reqd 1.52 1.52 250
SAND 0.178 Cu mtr 0.31
wastage considered 20% % Cu mtr 0.06
Scafolding (M) Rs.1/SFT Cu mtr 0.368 1270.44
Total Sand required 1 43.5
Total Material
Labour
Add for morter mixing
Misc 1% 0 0
Scaffolding (L) 1 39.1
Scaffolding (L) Escalation 0% 1 0
Total Labour 1 413.04
Escalation 0% 1 0
Supporting Labour 1

Total Labour
Total (Labour + Material)
Add for Hire Charges & Maintenance of mixer, sundries & contingencies %

Add Profit & Overhead


Cost per cu mtr of Brick Masonry
mm THK
mm THK

Amount Remark

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
380.00

467.52
43.50
891.02

0.00
0.00
39.10
0.00
413.04
0.00
0.00
0.00
452.14
1343.16
0.00

1343.16

0.00
1343.16
BCES CONS3.2
WORK 150 MM THIK with Band
Details of cost of 1 Sq mtr Brick work 150
Proporation 1 : 4 Joint 10

Sr. No. Items Unit Volume Rate


Materials
Bricks 0.11 0.24 Nos 37.88
wastage considered 5% 1.89
Total Bricks Required 39.77
Volume of brick work M3 0
Wet volume of BW M3 0.03
Add Due to frog filling 2% M3 0.03
total Dry Volume 0.3333 M3 0.04
CEMENT
Cement required for 1m3 26.75 % Bags 7.704
wastage required 3% % Bags 0.23
cement incl wastage 7.94
Total Cement Reqd 0.3 0.30 250
SAND 0.267 Cu mtr 0.04
wastage considered 20% % Cu mtr 0.01
Total Sand required Cu mtr 0.049 1270.44
Scafolding (M) Rs.1/CFT 1.0 10
RCC BAND MATERIAL 1.0 37.7
Total Material
Labour
Add for morter mixing 0.04
Misc 1% 0
Scaffolding (L) 1 9
Scaffolding (L) Escalation 0% 1 0
RCC BAND Labour 1 20.99
Total Labour 1 63
Supporting Labour 1

Total Labour
Total (Labour + Material)
Add for Hire Charges & Maintenance of mixer, sundries & contingencies %

Add Profit & Overhead


Cost per Sq. mtr of Brick Masonry
mm THK
mm THK

Amount Remark

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
75.00

62.25
10.00
37.70
184.95

0.00
0.00
9.00
0.00
20.99
63.00
0.00
0.00
92.99
277.94
0.00

277.94

0.00
277.94
BCES CONS3.2
WORK 150 MM THIK without Band
Details of cost of 1 Sq mtr Brick work 150
Proporation 1 : 4 Joint 10

Sr. No. Items Unit Volume Rate


Materials
Bricks 0.11 0.24 Nos 37.88
wastage considered 5% 1.89
Total Bricks Required 39.77
Volume of brick work M3 0
Wet volume of BW M3 0.03
Add Due to frog filling 2% M3 0.03
total Dry Volume 0.3333 M3 0.04
CEMENT
Cement required for 1m3 26.75 % Bags 7.704
wastage required 3% % Bags 0.23
cement incl wastage 7.94
Total Cement Reqd 0.3 0.30 250
SAND 0.267 Cu mtr 0.04
wastage considered 20% % Cu mtr 0.01
Total Sand required Cu mtr 0.049 1270.44
Scafolding (M) Rs.1/CFT 1.0 10
RCC BAND MATERIAL 0.0 37.7
Total Material
Labour
Add for morter mixing 0.04
Misc 1% 0
Scaffolding (L) 1 9
Scaffolding (L) Escalation 0% 1 0
RCC BAND Labour 0 20.99
Total Labour 1 63
Supporting Labour 1

Total Labour
Total (Labour + Material)
Add for Hire Charges & Maintenance of mixer, sundries & contingencies %

Add Profit & Overhead


Cost per Sq. mtr of Brick Masonry
mm THK
mm THK

Amount Remark

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
75.00

62.25
10.00
0.00
147.25

0.00
0.00
9.00
0.00
0.00
63.00
0.00
0.00
72.00
219.25
0.00

219.25

0.00
219.25
BCES CONS3.3
MASONRY WORK 150MM THK (BOXING) with Band
Details of cost of 1 Sq mtr Brick work 150
Proporation 1 : 4 Joint 10

Sr. No. Items Unit Volume Rate


Materials
Bricks 0.11 0.24 Nos 37.88
wastage considered 5% 1.89
Total Bricks Required 39.77
Volume of brick work M3 0
Wet volume of BW M3 0.03
Add Due to frog filling 2% M3 0.03
total Dry Volume 0.3333 M3 0.04
CEMENT
Cement required for 1m3 26.75 % Bags 7.704
wastage required 3% % Bags 0.231
cement incl wastage 7.94
Total Cement Reqd 0.30 0.30 250
SAND 0.267 Cu mtr 0.04
wastage considered 20% % Cu mtr 0.01
Total Sand required Cu mtr 0.049 1270.44
Scafolding (M) Rs.1/CFT 1.0 10
RCC BAND MATERIAL 1.0 37.7
Total Material
Labour
Add for morter mixing 0.04
Misc 1% 0
Scaffolding (L) 1 9
Scaffolding (L) Escalation 0% 1 0
RCC BAND Labour 1 20.99
Total Labour 15% 1 78
Supporting Labour 1

Total Labour
Total (Labour + Material)
Add for Hire Charges & Maintenance of mixer, sundries & contingencies %

Add Profit & Overhead


Cost per Sq. mtr of Brick Masonry
mm THK
mm THK

Amount Remark

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
75.00

62.25
10.00
37.70
184.95

0.00
0.00
9.00
0.00
20.99
78.00
0.00
0.00
107.99
292.94
0.00

292.94

0.00
292.94
BCES CONS3.4 MLDL
WORK 100 MM THK
Details of cost of 1 Sq mtr Brick work 150
Proporation 1 : 4 Joint 10

Sr. No. Items Unit Volume Rate


Materials
Bricks 0.11 0.24 Nos 37.88
wastage considered 5% 1.89
Total Bricks Required 39.77
Volume of brick work M3 0.1
Wet volume of BW M3 0.02
Add Due to frog filling 2% M3 0.02
total Dry Volume 0.3333 M3 0.03
CEMENT
Cement required for 1m3 26.75 % Bags 7.704
wastage required 3% % Bags 0.231
cement incl wastage 7.94
Total Cement Reqd 0.23 0.23 250
SAND 0.267 Cu mtr 0.03
wastage considered 20% % Cu mtr 0.01
Total Sand required Cu mtr 0.038 1270.44
Scafolding (M) Rs.1/CFT 1.0 10
RCC BAND MATERIAL 1.0 32.3
Total Material
Labour
Add for morter mixing 0.03
Misc 1% 0
Scaffolding (L) 1 9
Scaffolding (L) Escalation 0% 1 0
RCC BAND Labour 1 16.15
Total Labour 1 63
Supporting Labour 1

Total Labour
Total (Labour + Material)
Add for Hire Charges & Maintenance of mixer, sundries & contingencies %

Add Profit & Overhead


Cost per Sq. mtr of Brick Masonry
mm THK
mm THK

Amount Remark

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
57.50

48.28
10.00
32.30
148.08

0.00
0.00
9.00
0.00
16.15
63.00
0.00
0.00
88.15
236.23
0.00

236.23

0.00
236.23
BCES CONS3.4
Providing and applying 12 mm thick plaster A B C D
Details of cost of 1 Sq mtr Cement Plaster Thk
Proporation 1 : 4

Sr. No. Items Unit Volume Rate


Materials
Cement required 26.75% Bags 7.70 250
wastage 3% Bags 0.23 250
Sand Cu mtr 1.07 1270
wastage 20% Cu mtr 0.21 1270

Volume of wet mortar M3 0.01200


Increase for filling depression 5% 0.00060
Dry Volume 0.33 0.00420
Total volume of dry mortar M3 0.01680
Total volume of cement required 0.00336
Cement required in bags 0.092 Bags 0.09683
Add for wastage 3% % 0.00290
Total Cement Reqd 0.09973 250
Sand 0.01344
wastage 20% % 0.00269
Total Sand required 0.016 1270
Other Material
W/p compound/nonshrink compo 2% M2 1.00 15
wastage 0% 1.00 0
Polypropaline fibre per bag 0.10 25
Wastage 3% 0.10 0.75
Hackad m2 1.00
G.I. Chicken mesh PVC m2 1.00 8
Scafolding charges (M) M2 1.00 7.0
Total Material
Labour each 0.5
HEAD MASON each 10
MASON each 15
Waterman ls 0.01
Add for mixing 1
Misc Hacking 1 7.5
Misc Screening of sand 1
Scaffolding (L) 1 6.36
Scaffolding (L) Escalation 0% 1 0
Labour Rate 1 63
Labour Rate Escalation 0% 1 0
Supporting Labour 13% 1 8.19
Escalation 0%
Total Labour
Total (Labour + Material)
Add for Hire Charges & Maintenance of mixer, sundries & contingencies %

Profit & Overhead %


Cost per 100 Sqft. of Cement Plaster Rate per Cum
Rate of cement plaster per Sqft
E
12 mm

Amount Remark

1925.00
57.50
1358.90
266.70
3608.10

0.00
0.00
0.00
0.00
0.00
0.00
24.93

0.00
20.32
0.00
15.00
0.00
2.50
0.08
0.00
8.00
7.00
77.83
0
0
0
0
0.00
7.50
0.00
6.36
0.00
63.00
0.00
8.19
0.00
85.05
162.88
0.00

162.88

0.00
162.88
162.88
BCES CONS4.2
CEILING PLASTER A B C D
Details of cost of 1 Sq mtr Cement Plaster Thk
Proporation 1 : 4

Sr. No. Items Unit Volume Rate


Materials
Cement required 26.75% Bags 7.7040 250
wastage 3% Bags 0.2311 250
Sand Cu mtr 1.0693 1270
wastage 20% Cu mtr 0.2139 1270

Volume of wet mortar M3 0.00900


Increase for filling depression 5% 0.00045
Dry Volume 0.33 0.00315
Total volume of dry mortar M3 0.01260
Total volume of cement required 0.00252
Cement required in bags Bags 0.07262
Add for wastage 3% % 0.00218
Total Cement Reqd 0.07480 250
Sand 0.01008
wastage 20% % 0.00202
Total Sand required 0.01210 1270
Other Material
W/p compound/nonshrink compo 2% M2 1.00 15
wastage 1.00 0
Polypropaline fibre per bag 0.07 25
Wastage 3% 0.07 0.75
Hackad m2 1.00
G.I. Chicken mesh PVC m2 1.00 8
Scafolding charges (M) M2 1.00 7.0
Total Material
Labour each 0.5
HEAD MASON each 10
MASON each 15
Waterman ls 0.01
Add for mixing 1
Misc Hacking 1 7.5
Misc Screening of sand 1
Scaffolding (L) 1 6.36
Scaffolding (L) Escalation 0% 1 0
Labour Rate 1 63
Labour Rate Escalation 0% 1 0
Supporting Labour 13% 1 8.19
Escalation 0%
Total Labour
Total (Labour + Material)
Add for Hire Charges & Maintenance of mixer, sundries & contingencies %

Profit & Overhead %


Cost per 100 Sqft. of Cement Plaster Rate per Cum
Rate of cement plaster per Sqft
E
9 mm

Amount Remark

1926.00
57.78
1358.01
271.65
3613.44

0.00
0.00
0.00
0.00
0.00
0.00
18.70

0.00
15.37
0.00
15.00
0.00
1.75
0.05
0.00
8.00
7.00
65.87
0
0
0
0
0.00
7.50
0.00
6.36
0.00
63.00
0.00
8.19
0.00
85.05
150.92
0.00

150.92

0.00
150.92
150.92
BCES CONS4.3
DUCT PLASTER A B C D
Details of cost of 1 Sq mtr Cement Plaster Thk
Proporation 1 : 4

Sr. No. Items Unit Volume Rate


Materials
Cement required 26.75% Bags 7.7040 250
wastage 3% Bags 0.2311 250
Sand Cu mtr 1.0693 1270
wastage 20% Cu mtr 0.2139 1270

Volume of wet mortar M3 0.01000


Increase for filling depression 5% 0.00000
Dry Volume 0.33 0.00000
Total volume of dry mortar M3 0.02000
Total volume of cement required 0.00300
Cement required in bags Bags 0.10000
Add for wastage 3% % 0.00000
Total Cement Reqd 0.10000 250
Sand 0.01000
wastage 20% % 0.00000
Total Sand required 0.01600 1270
Other Material
W/p compound 0% M2 0.00 35
wastage 1.00 0
Polypropaline fibre per bag 0.10
Wastage 3% 0.10 0.75
Hackad m2 1.00
G.I. Chicken mesh PVC m2 1.00
Scafolding charges (M) M2 1.00 7.0
Total Material
Labour each 0.5
HEAD MASON each 10
MASON each 15
Waterman ls 0.01
Add for mixing 1
Misc Hacking 1 7.5
Misc Screening of sand 1
Scaffolding (L) 1 6.36
Scaffolding (L) Escalation 0% 1 0
Labour Rate 1 63
Labour Rate Escalation 0% 1 0
Supporting Labour 13% 1 8.19
Escalation 0%
Total Labour
Total (Labour + Material)
Add for Hire Charges & Maintenance of mixer, sundries & contingencies %

Profit & Overhead %


Cost per 100 Sqft. of Cement Plaster Rate per Cum
Rate of cement plaster per Sqft
E
9 mm

Amount Remark

1926.00
57.78
1358.01
271.65
3613.44

0.00
0.00
0.00
0.00
0.00
0.00
25.00

0.00
20.32
0.00
0.00
0.00
0.00
0.08
0.00
0.00
7.00
52.40 0.52
0
0
0
0
0.00
7.50
0.00
6.36
0.00
63.00
0.00
8.19
0.00
85.05
137.45
0.00

137.45

0.00
137.45
137.45
4.4
BCES CONS
DUCT PLASTER A B C D
Details of cost of 1 Sq mtr Cement Plaster Thk
Proporation 1 : 4

Sr. No. Items Unit Volume Rate


Materials
Cement required 26.75% Bags 7.7040 250
wastage 3% Bags 0.2311 250
Sand Cu mtr 1.0693 1270
wastage 20% Cu mtr 0.2139 1270

Volume of wet mortar M3 0.01200


Increase for filling depression 5% 0.00060
Dry Volume 0.33 0.00420
Total volume of dry mortar M3 0.01680
Total volume of cement required 0.00340
Cement required in bags Bags 0.09680
Add for wastage 3% % 0.00290
Total Cement Reqd 0.09970 250
Sand 0.01340
wastage 20% % 0.00270
Total Sand required 0.02000 1270
Total Material
Details of cost of 1 Sq mtr Cement Plaster Thk
Proporation 1 : 3
SECOND COAT
II Items Unit Volume Rate
Materials
Materials
Cement required 35.67% Bags 10.2720 250
wastage 3% Bags 0.308 250
Sand Cu mtr 1.069 1270
wastage 20% Cu mtr 0.2140 1270

Volume of wet mortar M3 0.00800


Increase for filling depression 0% 0.00000
Dry Volume 0.33 0.00300
Total volume of dry mortar M3 0.01100
Total volume of cement required 0.00300
Cement required in bags Bags 0.07700
Add for wastage 3% % 0.00200
Total Cement Reqd 0.07900 250
Sand 0.00800
wastage 20% % 0.00200
Total Sand required 0.01000 1270
Total Material
Other Material
W/p compound 2% 0.18 35
nonshrink compound 1.00 15
wastage 1.00 0
Polypropaline fibre per bag 0.18 25
Wastage 3% 0.18 0.75
Hackad m2 1.00
G.I. Chicken mesh PVC m2 1.00 8.0
Scafolding charges (M) M2 1 12
Total Material
Total Material

Labour
Add for dripmould, offsets, wata, patta etc. 1 20
Misc Hacking 1 7.5
Misc Screening of sand 0.03
Scaffolding (L) 1 11
Scaffolding (L) Escalation 0% 1 0
Labour Rate 1 95.45
Labour Rate Escalation 0% 1 0
Supporting Labour 13% 1 12.4085
Escalation 0% 1 0
Total Labour
Total (Labour + Material)
Add for Hire Charges & Maintenance of mixer, sundries & contingencies %

Profit & Overhead %


Total (Labour + Material)
Cost per Sqft of Cement Plaster
E
9 mm

Amount Remark

1926.00
57.78
1358.01
271.65
3613.44

0.00
0.00
0.00
0.00
0.00
0.00
24.93

0.00
25.40
50.33 0.45
8 mm

Amount Remark

2568.00
77.00
1357.63
271.78
4274.41

0.00
0.00
0.00
0.00 45.90
0.00
0.00
19.75

0.00
12.70
32.45 0.45
6.27
15.00
0.00
4.50
0.14
0.00
8.00
12.00
45.90 0.46
123.3 1.23

20.00
7.50
0.00
11.00 146.36
0.00
95.45
0.00
12.41
0.00
146.36
269.66
0.00

269.66

0.00
269.66
269.66
5.1
BCES CONS
Ent. Flooring A B C D
Details of cost of 1 Sq mtr Cement Plaster Thk
Proporation 1 : 6

Sr. No. Items Unit Volume Rate


Materials
Italian Marble m2 1.00 3229.2
wastage 15% 0.15 3229.2
Cement required 17.8 % Bags 5.14
wastage 3% Bags 0.15
0% M3 0.21 250
AGGREGATE 0.04
Sand 30% Cu mtr 0.01 1270
wastage 15% Cu mtr 0.00 1270
GRIT 70% 0.03 600
wastage 15% 0.0047 600
Neat cement slurry 2 KG.M2 Bags 0.0400 250
wastage 3% 0.0012 250
White cement slurry 4.50 KG.M2 Bags 0.09 660
wastage 3% 0.00 660
POP COVERING 1.00 0
Polymer base pigment
Total Material
Labour
Scaffolding (L) 1
Scaffolding (L) Escalation 10% 1 0
Labour Rate 1 900
Labour Rate Escalation 0% 1 0
Supporting Labour 0% 1 0
Escalation 10% 1 0
Total Labour
Total (Labour + Material)
Rmtr %

Profit & Overhead %


E
40 mm

Amount Remark

3229.20
484.38
0.00
0.00
52.50
0.00
12.70
2.54
18.00
2.82
10.00
0.30
59.40
1.85
0.00
0.00
3873.69 38.79

0.00
0.00
900.00
0.00
0.00
0.00
900.00
4773.69
0.00

4773.69

0.00
4773.69 SQM
0.00 SQFT
5.2
BCES CONS
Ent. Lobby Skirting A B C D
Details of cost of 1 RMTR Thk
Proporation 1 : 1 Ht

Sr. No. Items Unit Volume Rate


Materials
Italian Marble 0.15 3229.2
wastage 15% 0.02 3229.2
Cement required (WC) 1860 KG Bags 37.20
wastage 3% Bags 1.12
0.0015 M3 0.06 660
AGGREGATE 0.00
Sand Cu mtr 0.00 1270
wastage 15% Cu mtr 0.00 1270
GRIT 0.00 600
wastage 15% 0.0000 600
Neat cement slurry KG.M2 Bags 0.0000 250
wastage 3% 0.0000 250
White cement slurry KG.M2 Bags 0.00 660
wastage 3% 0.00 660
POP COVERING 1.00 0
Pigment
Total Material
Labour
Scaffolding (L) 1
Scaffolding (L) Escalation 10% 1 0
Labour Rate 1 150
Labour Rate Escalation 0% 1 0
Supporting Labour 0% 1 0
Escalation 10% 1 0
ADD for Chamfering 1 25
Escalation 1 0
Total Labour
Total (Labour + Material)
Add for Hire Charges & Maintenance of mixer, sundries & contingencies %

Profit & Overhead %


E
10 mm
150 mm

Amount Remark

484.38
72.66
0.00
0.00
39.60
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
596.64 38.79

0.00
0.00
150.00
0.00
0.00
0.00
25.00
0.00
175.00
771.64
0.00

771.64

0.00
771.64 RMT
234.70 Rft
5.3
BCES CONS
DADO A B C D
Details of cost of 1 SQM Thk
Proporation 1 : 1 Ht

Sr. No. Items Unit Volume Rate


Materials
Italian Marble 1 3229.2
wastage 15% 0.15 3229.2
BAL Diamonstar White Bags/m2 Bags 10.76
wastage 3% Bags 0.32
Cement required 1860 KG Bags 37.20
wastage 3% Bags 1.12
0% M3 0.46 660
AGGREGATE 0.02
Sand Cu mtr 0.00
wastage 15% Cu mtr 0.00 1270
GRIT 0.00 600
wastage 15% 0.0000 600
Neat cement slurry KG.M2 Bags 0.0000 0
wastage 3% 0.0000 0
White cement slurry KG.M2 Bags 0.00 660
wastage 3% 0.00 660
POP COVERING 1.00
Pigment 0.12 0.12 40
SS Pins 1.00 35
Scafolding(M) 1.00 10
Total Material
Labour
Scaffolding (L) 1 9
Scaffolding (L) Escalation 0% 1 0
Labour Rate 1 950
Labour Rate Escalation 0% 1 0
Supporting Labour 0% 1 0
Escalation 10% 1 0
ADD for Chamfering 1 0
Escalation 10% 1 0
Total Labour
Total (Labour + Material)
Add for Hire Charges & Maintenance of mixer, sundries & contingencies %

Profit & Overhead %


E
12 mm
1000 mm

Amount Remark

3229.20
484.38
0.00
0.00
0.00
0.00
303.60
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
4.80
35.00
10.00
4066.98 38.79

9.00
0.00
950.00
0.00
0.00
0.00
0.00
0.00
959.00
5025.98
0.00

5025.98

0.00
5025.98 SQM
1532.30 Sft
5.40
BCES CONS
DADO A B C D
Details of cost of 1 Rmtr Thk
Proporation 1 : 1 Ht

Sr. No. Items Unit Volume Rate


Materials
Italian Marble 0.2 3229.2
wastage 15% 0.03 3229.2
BAL Diamonstar White Bags/m2 Bags 10.76
wastage 3% Bags 0.32
Cement required 1860 KG Bags 37.20
wastage 3% Bags 1.12
0.0024 M3 0.09 660
AGGREGATE 0.00
Sand Cu mtr 0.00
wastage 15% Cu mtr 0.00 1270
GRIT 0.00 600
wastage 15% 0.0000 600
Neat cement slurry KG.M2 Bags 0.0000 0
wastage 3% 0.0000 0
White cement slurry KG.M2 Bags 0.00 660
wastage 3% 0.00 660
POP COVERING M2 0.20
Pigment 0.12 M2 0.20 40
SS Pins M2 0.20
Scafolding(M) M2 0.20 5
Total Material
Labour
Scaffolding (L) 0.2 4.54
Scaffolding (L) Escalation 0% 0.2 0
Labour Rate 1 226
Labour Rate Escalation 0% 1 0
Supporting Labour 0% 1 0
Escalation 10% 1 0
ADD for Chamfering 1 0
Escalation 10% 1 0
Total Labour
Total (Labour + Material)
Add for Hire Charges & Maintenance of mixer, sundries & contingencies %

Profit & Overhead %


E
12 mm
200 mm

Amount Remark

645.84
96.88
0.00 32.5
0.00
0.00
0.00
59.40
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
8.00
0.00
1.00
811.12 8.05

0.91
0.00
226.00
0.00
0.00
0.00
0.00
0.00
226.91
1038.02
0.00

1038.02

0.00
1038.02 Rmtr
314.70
5.50
BCES CONS
Deck flooring
Details of cost of 1 Sq mtr cement plaster Thk
Proporation 1 : 6

Sr. No. Items Unit Volume Rate


Materials
Antiskid ceramic tile m2 1.0 484.38
wastage 5% 0.05 484.38
Cement required 17.8 % Bags 5.14
wastage 3% Bags 0.15

0.04 M3 0.21 250


AGGREGATE 0.04
Sand 30% Cu mtr 0.01 1270
wastage 15% Cu mtr 0.00 1270
GRIT 70% 0.03 600
wastage 15% 0.0047 600
Neat cement slurry 2 KG.M2 Bags 0.0400 250
wastage 3% 0.0012 250
Black cement 4.50 KG.M2 Bags 0.09 250
wastage 3% 0.0028 250
POP COVERING M2 1.00
Polymer Base Pigment 0.12 M2 1.00

Total Material
Labour
Scaffolding (L) 1 10
Scaffolding (L) Escalation 0% 1 0
Labour Rate 1 175
Labour Rate Escalation 0% 1 0
Supporting Labour 13% 1 22.75
Escalation 0% 1 0
Total Labour
Total (Labour + Material)
Add for Hire Charges & Maintenance of mixer, sundries & contingencies %

Profit & Overhead %


40 mm

Amount Remark

484.38
24.22
0.00
0.00
0.00
0.00
52.50
0.00
12.70
2.54
18.00
2.82
10.00
0.30
22.50
0.70
0.00
0.00

630.66 6.36

10.00
0.00
175.00
0.00
22.75
0.00
207.75
838.41
0.00

838.41

0.00
838.41 SQM
78.30 SQFT
5.50
BCES CONS
DADO
Details of cost of 1 Rmtr Thk
Proporation 1 : 1 Ht

Sr. No. Items Unit Volume Rate


Materials
Tiles 1.0 484.38
Wastage 5% 0.05 484.38
BAL Diamondstar White Bags/m2 Bags 10.76
wastage 3% Bags 0.32
Cement required 1860 KG Bags 37.20
Wastage 3% Bags 1.12
0.0120 M3 0.46 250
AGGREGATE 0.02
Sand Cu mtr 0.00
wastage 15% Cu mtr 0.00
GRIT 0.00
wastage 15% 0.0000 0
Neat cement slurry 2 KG.M2 Bags 0.0000 0
wastage 3% 0.0000 0
White Cement KG.M2 Bags 0.00
wastage 3% 0.0000 0
POP COVERING M2 1.00
Pigment 0.12 M2 0.12 40
SS Pins 1.00
Scafolding (M) 1.00 0
Total Material
Labour
Acid clenaing 1 10
Scaffolding (L) Escalation 0% 1 0
Labour Rate 1 186
Labour Rate Escalation 0% 1 0
Supporting Labour 13% 1 24.18
Escalation 0%
ADD for Chamfering
Escalation 0% 1 0
Total Labour
Total (Labour + Material)
Add for Hire Charges & Maintenance of mixer, sundries & contingencies %

Profit & Overhead %


12 mm
1000 mm

Amount Remark

484.38
24.22
0.00 32.5
0.00
0.00
0.00
115.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
4.80
0.00
0.00
628.40 6.36

10.00
0.00
186.00
0.00
24.18

0.00
220.18
848.58
0.00

848.58

0.00
848.58 SQM
258.70 SQFT
5.7.1
BCES CONS
VITRIFIED FLOORING
Details of cost of 1 Sq mtr cement plaster Thk
Proporation 1 : 6

Sr. No. Items Unit Volume Rate


Materials
Vetrified Tiles m2 1.0 968.76
Wastage 5% 0.05 968.76

Cement required 17.8 % Bags 5.14


Wastage 3% Bags 0.15
0% M3 0.21 250
AGGREGATE 0.04
Sand 30% Cu mtr 0.01 1271
wastage 15% Cu mtr 0.00 1271
GRIT 70% 0.03 600
wastage 15% 0.0048 600
Neat cement slurry 2 KG.M2 Bags 0.0400 250
wastage 3% 0.0012 250
White Cement 4.50 KG.M2 Bags 0.09 250
wastage 3% 0.0030 250
POP COVERING M2 1.00 0
Pigment 0.12 M2 1.00 15

Total Material
Labour
Acid clenaing 1
Scaffolding (L) Escalation 10% 1 0
Labour Rate 1 195
Labour Rate Escalation 0% 1 0
Supporting Labour 13% 1 25.35
Escalation 0%

1 0
Total Labour
Total (Labour + Material)
Add for Hire Charges & Maintenance of mixer, sundries & contingencies %

Profit & Overhead %


40 mm

Amount Remark

968.76
48.44

0.00
0.00
52.50
0.00
12.71
2.54
18.00
2.88
10.00
0.30
22.50
0.75
0.00
15.00

1154.38 6.36

0.00
0.00
195.00
0.00
25.35

0.00
220.35
1374.73
0.00

1374.73

0.00
1374.73 SQM
128.20 SQFT
5.7.1
BCES CONS
VITRIFIED FLOORING
Details of cost of 1 Sq mtr cement plaster Thk
Proporation 1 : 6

Sr. No. Items Unit Volume Rate


Materials
Vetrified Tiles m2 1.0 592.02
Wastage 5% 0.05 592.02

Cement required 17.8 % Bags 5.14


Wastage 3% Bags 0.15
0.04 M3 0.21 250
AGGREGATE 0.04
Sand 30% Cu mtr 0.01 1271
wastage 15% Cu mtr 0.00 1271
GRIT 70% 0.03 600
wastage 15% 0.0048 600
Neat cement slurry 2 KG.M2 Bags 0.0400 250
wastage 3% 0.0012 250
White Cement 4.50 KG.M2 Bags 0.09 250
wastage 3% 0.0030 250
POP COVERING M2 1.00 0
Pigment 0.12 M2 1.00 15

Total Material
Labour
Acid clenaing 1
Scaffolding (L) Escalation 10% 1 0
Labour Rate 1 195
Labour Rate Escalation 0% 1 0
Supporting Labour 13% 1 25.35
Escalation 0%

1 0
Total Labour
Total (Labour + Material)
Rmtr

Profit & Overhead %


40 mm

Amount Remark

592.02
29.60

0.00
0.00
52.50
0.00
12.71
2.54
18.00
2.88
10.00
0.30
22.50
0.75
0.00
15.00

758.80 6.36

0.00
0.00
195.00
0.00
25.35

0.00
220.35
979.15
0.00

979.15

0.00
979.15 SQM
91.40 SQFT
5.50
BCES CONS
DADO
Details of cost of 1 Rmtr Thk
Proporation 1 : 1 Ht

Sr. No. Items Unit Volume Rate


Materials
Tiles 1.0 484.38
Wastage 5% 0.05 484.38
BAL Diamondstar White Bags/m2 Bags 10.76
wastage 3% Bags 0.32
Cement required 1860 KG Bags 37.20
Wastage 3% Bags 1.12
0.0120 M3 0.46 250
AGGREGATE 0.02
Sand 70% Cu mtr 0.00
wastage 15% Cu mtr 0.00
GRIT 30% 0.00
wastage 15% 0.0000 0
Neat cement slurry KG.M2 Bags 0.0000 0
wastage 3% 0.0000 0
White Cement KG.M2 Bags 0.00
wastage 3% 0.0000 0
POP COVERING M2 1.00
Pigment 0.12 M2 0.12 40
SS Pins M2 1.00
Scafolding (M) M2 1.00 0
Total Material
Labour
Acid clenaing 1 10
Scaffolding (L) Escalation 0% 1 0
Labour Rate 1 186
Labour Rate Escalation 0% 1 0
Supporting Labour 13% 1 24.18
Escalation 0%
ADD for Chamfering
Escalation 0% 1 0
Total Labour
Total (Labour + Material)
Add for Hire Charges & Maintenance of mixer, sundries & contingencies %

Profit & Overhead %


12 mm
1000 mm

Amount Remark

484.38
24.22
0.00 32.5
0.00
0.00
0.00
115.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
4.80
0.00
0.00
628.40 6.28

10.00
0.00
186.00
0.00
24.18

0.00
220.18
848.58
0.00

848.58

0.00
848.58 SQM
258.70 SQFT
5.8.a
BCES CONS
Skirting
Details of cost of 1 Rmtr Thk
Proporation 1 : 1 Ht

Sr. No. Items Unit Volume Rate


Materials
Tiles 0.1 968.76
Wastage 5% 0.01 968.76
BAL Diamondstar White Bags/m2 Bags 10.76
wastage 3% Bags 0.32
Cement required 1860 KG Bags 37.20
Wastage 3% Bags 1.12
0.0120 M3 0.05 250
AGGREGATE 0.00
Sand Cu mtr 0.00
wastage 15% Cu mtr 0.00 1270
GRIT 0.00 600
wastage 15% 0.0000 600
Neat cement slurry KG.M2 Bags 0.0000 0
wastage 3% 0.0000 0
White Cement KG.M2 Bags 0.00 660
wastage 3% 0.0000 660
POP COVERING M2 0.10
Pigment 0.12 M2 0.0012 40
SS Pins M2 0.10
Scafolding (M) M2 0.10 0
JAD finish RM 1.00 0
Total Material
Labour
JAD Finish (L) 1 6.81
Escalation 1 0
Scaffolding (L) 1
Scaffolding (L) Escalation 0% 1 0
Labour Rate 1 50
Labour Rate Escalation 0% 1 0
Supporting Labour 13% 1 6.5
Escalation 0% 1
ADD for Chamfering 1
Escalation 0% 1 0
Total Labour
Total (Labour + Material)
Add for Hire Charges & Maintenance of mixer, sundries & contingencies %

Profit & Overhead %


12 mm
100 mm

Amount Remark

96.88
4.84
0.00 32.5
0.00
0.00
0.00
12.50
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.05
0.00
0.00
0.00
114.27 1.14

6.81
0.00
0.00
0.00
50.00
0.00
6.50
0.00
0.00
0.00
63.31
177.58
0.00

177.58

0.00
177.58 Rmtr
54.00 Rft
5.8.b
BCES CONS MLDL
Skirting
Details of cost of 1 Rmtr Thk
Proporation 1 : 1 Ht

Sr. No. Items Unit Volume Rate


Materials
Italian marble 0.1 592.02
Wastage 5% 0.01 592.02
BAL Diamondstar White Bags/m2 Bags 10.76
wastage 3% Bags 0.32
Cement required 1860 KG Bags 37.20
Wastage 3% Bags 1.12
0.0120 M3 0.05 250
AGGREGATE 0.00
Sand Cu mtr 0.00
wastage 15% Cu mtr 0.00 1270
GRIT 0.00 600
wastage 15% 0.0000 600
Neat cement slurry KG.M2 Bags 0.0000 0
wastage 3% 0.0000 0
White Cement KG.M2 Bags 0.00 660
wastage 3% 0.0000 660
POP COVERING M2 0.10
Pigment 0.12 M2 0.0012 40
SS Pins M2 0.10
Scafolding (M) M2 0.10 0
JAD finish RM 1.00 0
Total Material
Labour
JAD Finish (L) 1 6.81
Escalation 1 0
Scaffolding (L) 1
Scaffolding (L) Escalation 0% 1 0
Labour Rate 1 50
Labour Rate Escalation 0% 1 0
Supporting Labour 13% 1 6.5
Escalation 0% 1
ADD for Chamfering 1
Escalation 0% 1 0
Total Labour
Total (Labour + Material)
Add for Hire Charges & Maintenance of mixer, sundries & contingencies %

Profit & Overhead %


12 mm
100 mm

Amount Remark

59.20
2.96
0.00 32.5
0.00
0.00
0.00
12.50
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.05
0.00
0.00
0.00
74.71 0.74

6.81
0.00
0.00
0.00
50.00
0.00
6.50
0.00
0.00
0.00
63.31
138.02
0.00

138.02

0.00
138.02 Rmtr
41.90 Rft
5.90
BCES CONS
DADO
Details of cost of 1 SQM Thk
Proporation 1 : 1 Ht

Sr. No. Items Unit Volume Rate


Materials
tiles 1 592.02
Wastage 5% 0.05 592.02
BAL Diamondstar White Bags/m2 Bags 10.76
wastage 3% Bags 0.32
Cement required 1860 KG Bags 37.20
Wastage 3% Bags 1.12
0.0120 M3 0.46 250
AGGREGATE 0.02
Sand Cu mtr 0.00
wastage 15% Cu mtr 0.00 1270
GRIT 0.00 600
wastage 15% 0.0000 600
Neat cement slurry KG.M2 Bags 0.0000 0
wastage 3% 0.0000 0
White Cement KG.M2 Bags 0.00 660
wastage 3% 0.0000 660
POP COVERING M2 1.00
Pigment 0.12 M2 0.1200 40
SS Pins M2 1.00
Scafolding (M) M2 1.00 0

Total Material
Labour
Scaffolding (L) 1
Scaffolding (L) Escalation 1 0
Labour Rate 1 186
Labour Rate Escalation 0% 1 0
Supporting Labour 13% 1 24.8
Escalation 1
ADD for Chamfering 1
Escalation 1 0
Total Labour
Total (Labour + Material)
Add for Hire Charges & Maintenance of mixer, sundries & contingencies %

Profit & Overhead %


12 mm
1000 mm

Amount Remark

592.02
29.60
0.00 32.5
0.00
0.00
0.00
115.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
4.80
0.00
0.00

741.42 7.41

0.00
0.00
186.00
0.00
24.80
0.00
0.00
0.00
210.80
952.22
0.00

952.22

0.00
952.22 Sqm
290.10
5.10
BCES CONS
Trade
Details of cost of 1 RMTR Thk
Proporation 1 : 6 Ht

Sr. No. Items Unit Volume Rate


Materials
Indian Marble m2 0.25 1506.96
Wastage 15% 0.0375 1506.96

Cement required 17.8 % Bags 5.14


Wastage 3% Bags 0.15
0.01 M3 0.03 250
AGGREGATE 0.01
Sand 30% Cu mtr 0.00165 1271
wastage 15% Cu mtr 0.00025 1271
GRIT 70% 0.0039 600
wastage 15% 0.0005 600
Neat cement slurry 2 KG.M2 Bags 0.0400 250
wastage 3% 0.0015 250
Black Cement 4.50% KG.M2 Bags 0.09 250
wastage 3% 0.0030 250
POP COVERING 0.25 0
Polymer Base Pigment 0.0000 15

Total Material
Labour
Scaffolding (L) 1
Scaffolding (L) Escalation 1 0
Labour Rate 1 319.5
Labour Rate Escalation % 1 0
Supporting Labour 13% 1 41.535
Escalation 1

Total Labour
Total (Labour + Material)
Rmtr

Profit & Overhead %


20 mm
25

Amount Remark

376.74
56.51

0.00
0.00
7.50
0.00
2.10
0.32
2.34
0.30
10.00
0.38
22.50
0.75
0.00
0.00

479.43 4.78

0.00
0.00
319.50
0.00
41.54
0.00

361.04
840.47
0.00

840.47

0.00
840.47 PM
5.11
BCES CONS
RISER
Details of cost of 1 RMTR Thk
Proporation 1 : 6 Ht

Sr. No. Items Unit Volume Rate


Materials
tiles 0.15 1506.96
Wastage 15% 0.0225 1506.96
BAL Diamondstar White Bags/m2 Bags 10.76
Wastage 3% Bags 0.32
Cement required 1860 KG Bags 37.20
Wastage 3% Bags 1.12
0.01 M3 0.07 250
AGGREGATE 0.00
Sand Cu mtr 0.00
wastage 15% Cu mtr 0.00
GRIT 0.00 600
wastage 15% 0.00 600
Neat cement slurry KG.M2 Bags 0.0000 250
wastage 3% 0.00 250
Black Cement KG.M2 Bags 0.00 250
wastage 3% 0.00 250
POP COVERING 0.15 0
Pigment 0.12 0.018 40
SS Pins 0.15
Scafolding (M) 0.15

Total Material
Labour
Scaffolding (L) 1
Scaffolding (L) Escalation 1 0
Labour Rate 1 200
Labour Rate Escalation 0% 1 0
Supporting Labour 13% 1 26
Escalation 0% 1
ADD for Chamfering 1
Escalation 0% 1
Total Labour
Total (Labour + Material)
Add for Hire Charges & Maintenance of mixer, sundries & contingencies %

Profit & Overhead %


12 mm
150

Amount Remark

226.04
33.91
0.00 32.5
0.00
0.00
0.00
17.50
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.72

278.17 2.78

0.00
0.00
200.00
0.00
26.00
0.00
0.00
0.00
226.00
504.17
0.00

504.17

0.00
504.17 Rmtr
153.60 Rft
5.12
BCES CONS
Marble flooring stair, lift lobby
Details of cost of 1 Sq mtr cement plaster Thk
Proporation 1 : 6

Sr. No. Items Unit Volume Rate


Materials
m2 1.00 1506.96
Wastage 15% 0.1500 1506.96

Cement required 17.8 % Bags 5.14


Wastage 3% Bags 0.15
0.04 M3 0.21 250
AGGREGATE 0.04
Sand 30% Cu mtr 0.01 1271
wastage 15% Cu mtr 0.002 1271
GRIT 70% 0.03 600
wastage 15% 0.00 600
Neat cement slurry 2 KG.M2 Bags 0.0400 250
wastage 3% 0.0015 250
Black Cement 4.5 KG.M2 Bags 0.09 250
wastage 3% 0.0028 250
POP COVERING 1.00 0
Polymer base Pigment 1.00 15

Total Material
Labour
Scaffolding (L) 1
Scaffolding (L) Escalation 1 0
Labour Rate 1 655
Labour Rate Escalation 0% 1 0
Supporting Labour 13% 1 85.15
Escalation 1

Total Labour
Total (Labour + Material)
Rmtr

Profit & Overhead %


40 mm

Amount Remark

1506.96
226.04
0.00 32.5
0.00
0.00
0.00
52.50
0.00
12.71
2.54
18.00
2.88
10.00
0.38
22.50
0.70
0.00
15.00

1870.21 18.75

0.00
0.00
655.00
0.00
85.15
0.00

740.15
2610.36
0.00

2610.36

0.00
2610.36 SQM
243.00 SQFT
5.13
BCES CONS
Skirting
Details of cost of 1 Rmtr Thk
Proporation 1 : 6 Ht

Sr. No. Items Unit Volume Rate


Materials
Italian marble 0.10 1506.96
Wastage 15% 0.0150 1506.96
BAL Diamondstar White Bags/m2 Bags 10.76
Wastage 3% Bags 0.32
Cement required 1860 KG Bags 37.20
Wastage 3% Bags 1.12
0.0012 M3 0.05 250
AGGREGATE 0.00
Sand Cu mtr 0.00
wastage 15% Cu mtr 0.00 1270
GRIT 0.00 600
wastage 15% 0.00 600
Neat cement slurry KG.M2 Bags 0.0000 250
wastage 3% 0.00 250
White Cement KG.M2 Bags 0.00 250
wastage 3% 0.00 250
POP COVERING M2 0.10 0
Pigment 0.12 M2 0.01 40
SS Pins M2 0.10
Scafolding (M) M2 0.10
JAD Finish M2 0.10
Total Material
Labour
JAD finish (L) 1 6.81
Escalation 0% 1 0
Scaffolding (L) 1
Scaffolding (L) Escalation 0% 1 0
Labour Rate 1 125
Labour Rate Escalation 0% 1 0
Supporting Labour 13% 1 16.25
Escalation 0% 1
ADD for Chamfering 1
Escalation 0% 1
Total Labour
Total (Labour + Material)
Add for Hire Charges & Maintenance of mixer, sundries & contingencies %

Profit & Overhead %


Profit & Overhead %
12 mm
100 mm

Amount Remark

150.70
22.60
0.00 32.5
0.00
0.00
0.00
12.50
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.50

186.30 1.85

6.81
0.00
0.00
0.00
125.00
0.00
16.25
0.00
0.00
0.00
148.06
334.36
0.00

334.36
0.00
334.36 Rmtr
101.60 Rft
5.14
BCES CONS
Sloping Skirting
Details of cost of 1 Rmtr Thk
Proporation 1 : 6 Ht

Sr. No. Items Unit Volume Rate


Materials
0.25 1506.96
Wastage 15% 0.0375 1506.96
BAL Diamondstar White Bags/m2 Bags 10.76
Wastage 3% Bags 0.32
Cement required 1860 KG Bags 37.20
Wastage 3% Bags 1.12
0.0030 M3 0.11 250
AGGREGATE 0.00
Sand Cu mtr 0.00
wastage 15% Cu mtr 0.00 1270
GRIT 0.00 600
wastage 15% 0.00 600
Neat cement slurry KG.M2 Bags 0.0000 0
wastage 3% 0.00 0
White Cement KG.M2 Bags 0.00 660
wastage 3% 0.00 660
POP COVERING M2 0.25 0
Pigment 0.12 M2 0.03 40
SS Pins M2 0.25
Scafolding (M) M2 0.25
JAD Finish RM 1.00
Total Material
Labour
JAD finish (L) 1 6.81
Escalation 0% 1 0
Scaffolding (L) 1
Scaffolding (L) Escalation 0% 1 0
Labour Rate 1 140
Labour Rate Escalation 0% 1 0
Supporting Labour 13% 1 18.2
Escalation 0% 1
ADD for Chamfering 1
Escalation 0% 1
Total Labour
Total (Labour + Material)
Add for Hire Charges & Maintenance of mixer, sundries & contingencies %

Profit & Overhead %


Profit & Overhead %
12 mm
250 mm

Amount Remark

376.74
56.51
0.00 32.5
0.00
0.00
0.00
27.50
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
1.20

461.95 4.63

6.81
0.00
0.00
0.00
140.00
0.00
18.20
0.00
0.00
0.00
165.01
626.96
0.00

626.96
0.00
626.96 Rmtr
191.50 Rft
5.15
BCES CONS
Trade
Details of cost of 1 RMTR Thk
Proporation 1 : 6

Sr. No. Items Unit Volume Rate


Materials
KOTHA m2 0.25 387
Wastage 22% 0.0500 387

Cement required 17.8 % Bags 5.1360


Wastage 3% Bags 0.1541
0.01 M3 0.0265 250
AGGREGATE 0.0055
Sand 30% Cu mtr 0.0017 1271
wastage 15% Cu mtr 0.0002 1271
GRIT 70% 0.0039 600
wastage 15% 0.0006 600
Neat cement slurry 2 KG.M2 Bags 0.0400 250
wastage 3% 0.0012 250
Black Cement 4.50% KG.M2 Bags 0.0900 250
wastage 3% 0.0027 250
POP COVERING 0.2500 0
Polymer Base Pigment 0.2500 0

Total Material
Labour
Scaffolding (L) 1
Scaffolding (L) Escalation 1 0
Labour Rate 1 229
Labour Rate Escalation % 1 0
Supporting Labour 13% 1 29.77
Escalation 1

Total Labour
Total (Labour + Material)
Rmtr

Profit & Overhead %


20 mm
250

Amount Remark

96.75
19.35

0.00
0.00
6.63
0.00
2.16
0.25
2.34
0.36
10.00
0.30
22.50
0.68
0.00
0.00

161.31 1.63

0.00
0.00
229.00
0.00
29.77
0.00

258.77
420.08
0.00

420.08

0.00
420.08 RM
5.16
BCES CONS
RISER
Details of cost of 1 RMTR Thk
Proporation 1 : 1 Ht

Sr. No. Items Unit Volume Rate


Materials
tiles 0.15 387
Wastage 22% 0.0330 387
BAL Diamondstar White Bags/m2 Bags 10.76
Wastage 3% Bags 0.32
Cement required 1860 KG Bags 37.20
Wastage 3% Bags 1.12
0.0018 M3 0.07 250
AGGREGATE 0.00
Sand Cu mtr 0.00
wastage 15% Cu mtr 0.00
GRIT 0.00 600
wastage 15% 0.00 600
Neat cement slurry KG.M2 Bags 0.0000 250
wastage 3% 0.00 250
Black Cement KG.M2 Bags 0.00 250
wastage 3% 0.00 250
POP COVERING M2 0.15 0
Pigment 0.12 M2 0.15 0
SS Pins M2 0.15
Scafolding (M) M2 0.15

Total Material
Labour
Scaffolding (L) 1
Scaffolding (L) Escalation 1 0
Labour Rate 1 125
Labour Rate Escalation 0% 1 0
Supporting Labour 13% 1 16.25
Escalation 0% 1
ADD for Chamfering 1
Escalation 0% 1
Total Labour
Total (Labour + Material)
Add for Hire Charges & Maintenance of mixer, sundries & contingencies %

Profit & Overhead %


12 mm
150

Amount Remark

58.05
12.77
0.00 32.5
0.00
0.00
0.00
17.50
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

88.32 0.88

0.00
0.00
125.00
0.00
16.25
0.00
0.00
0.00
141.25
229.57
0.00

229.57

0.00
229.57 Rmtr
69.90 Rft
5.17
BCES CONS
KOTHA flooring stair, lift lobby
Details of cost of 1 Sq mtr cement plaster Thk
Proporation 1 : 6

Sr. No. Items Unit Volume Rate


Materials
m2 1.00 387
Wastage 22% 0.2200 387

Cement required 17.8 % Bags 5.14


Wastage 3% Bags 0.15
0.02 M3 0.11 250
AGGREGATE 0.02
Sand 30% Cu mtr 0.01 1271
wastage 15% Cu mtr 0.00105 1271
GRIT 70% 0.02 600
wastage 15% 0.0024 600
Neat cement slurry 2 KG.M2 Bags 0.0400 250
wastage 3% 0.0015 250
Black Cement 4.5 KG.M2 Bags 0.09 250
wastage 3% 0.0028 250
POP COVERING 1.00 0
Polymer base Pigment 1.00 0

Total Material
Labour
Scaffolding (L) 1
Scaffolding (L) Escalation 0% 1 0
Labour Rate 1 325
Labour Rate Escalation 0% 1 0
Supporting Labour 13% 1 42.25
Escalation 0% 1

Total Labour
Total (Labour + Material)
Rmtr

Profit & Overhead %


20 mm

Amount Remark

387.00
85.14
0.00 32.5
0.00
0.00
0.00
27.50
0.00
12.71
1.33
12.00
1.44
10.00
0.38
22.50
0.70
0.00
0.00

560.70 18.75

0.00
0.00
325.00
0.00
42.25
0.00

367.25
927.95
0.00

927.95

0.00
927.95 SQM
85.40 SQFT
5.18
BCES CONS
Skirting
Details of cost of 1 Rmtr Thk
Proporation 1 : 1 Ht

Sr. No. Items Unit Volume Rate


Materials
KOTHA 0.10 387
Wastage 22% 0.0220 387
BAL Diamondstar White Bags/m2 Bags 10.76
Wastage 3% Bags 0.32
Cement required 1860 KG Bags 37.20
Wastage 3% Bags 1.12
0.0012 M3 0.05 250
AGGREGATE 0.00
Sand Cu mtr 0.00
wastage 15% Cu mtr 0.00 1270
GRIT 0.00 600
wastage 15% 0.00 600
Neat cement slurry KG.M2 Bags 0.0000 0
wastage 3% 0.00 0
White Cement KG.M2 Bags 0.00 660
wastage 3% 0.00 660
POP COVERING M2 0.10 0
Pigment 0.12 M2 0.01 0
SS Pins M2 0.10 0
Scafolding (M) M2 0.10 0
JAD Finish M2 0.10 0
Total Material
Labour
JAD finish (L) 1 6.81
Escalation 0% 1 0
Scaffolding (L) 1
Scaffolding (L) Escalation 0% 1 0
Labour Rate 1 125
Labour Rate Escalation 0% 1 0
Supporting Labour 13% 1 16.25
Escalation 0% 1
ADD for Chamfering 1
Escalation 0% 1
Total Labour
Total (Labour + Material)
Add for Hire Charges & Maintenance of mixer, sundries & contingencies %

Profit & Overhead %


Profit & Overhead %
12 mm
100 mm

Amount Remark

38.70
8.51
0.00 32.5
0.00
0.00
0.00
12.50
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
59.71 0.59

6.81
0.00
0.00
0.00
125.00
0.00
16.25
0.00
0.00
0.00
148.06
207.77
0.00

207.77
0.00
207.77 Rmtr
63.00 Rft
5.19
BCES CONS
Sloping Skirting
Details of cost of 1 Rmtr Thk
Proporation 1 : 1 Ht

Sr. No. Items Unit Volume Rate


Materials
0.25 387
Wastage 22% 0.0550 387
BAL Diamondstar White Bags/m2 Bags 10.76
Wastage 3% Bags 0.32
Cement required 1860 KG Bags 37.20
Wastage 3% Bags 1.12
0.0030 M3 0.11 250
AGGREGATE 0.00
Sand Cu mtr 0.00 1271
wastage 15% Cu mtr 0.00 1271
GRIT 0.00 600
wastage 15% 0.00 600
Neat cement slurry KG.M2 Bags 0.0000 0
wastage 3% 0.00 0
White Cement KG.M2 Bags 0.00 660
wastage 3% 0.00 660
POP COVERING M2 0.25
Pigment 0.12 M2 0.25
SS Pins M2 0.25
Scafolding (M) M2 0.25
JAD Finish RM 1.00
Total Material
Labour
JAD finish (L) 1 6.81
Escalation 0% 1 0
Scaffolding (L) 1
Scaffolding (L) Escalation 0% 1 0
Labour Rate 1 140
Labour Rate Escalation 0% 1 0
Supporting Labour 13% 1 18.2
Escalation 0% 1
ADD for Chamfering 1
Escalation 0% 1
Total Labour
Total (Labour + Material)
Add for Hire Charges & Maintenance of mixer, sundries & contingencies %

Profit & Overhead %


Profit & Overhead %
12 mm
250 mm

Amount Remark

96.75
21.29
0.00 32.5
0.00
0.00
0.00
27.50
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

145.54 1.47

6.81
0.00
0.00
0.00
140.00
0.00
18.20
0.00
0.00
0.00
165.01
310.55
0.00

310.55
0.00
310.55 Rmtr
95.10 Rft
5.20
BCES CONS
CLADING
Details of cost of 1 SQM Thk
Proporation 1 : 1 Ht

Sr. No. Items Unit Volume Rate


Materials
1.00 1506.96
Wastage 15% 0.1500 1506.96
BAL Diamondstar White Bags/m2 Bags 10.76
Wastage 3% Bags 0.32
Cement required 1860 KG Bags 37.20
Wastage 3% Bags 1.12
0.0120 M3 0.46 250
AGGREGATE 0.02
Sand Cu mtr 0.00
wastage 15% Cu mtr 0.00 1270
GRIT 0.00 600
wastage 15% 0.00 600
Neat cement slurry KG.M2 Bags 0.0000 0
wastage 3% 0.00 0
White Cement KG.M2 Bags 0.00 660
wastage 3% 0.00 660
POP COVERING 1.00
Pigment 0.12 0.12 40
SS Pins 1.00 0
Scafolding (M) 1.00

Total Material
Labour

Scaffolding (L) 1
Scaffolding (L) Escalation 0% 1 0
Labour Rate 1 750
Labour Rate Escalation 0% 1 0
Supporting Labour 13% 1 97.5
Escalation 0% 1
ADD for Chamfering 1
Escalation 0% 1
Total Labour
Total (Labour + Material)
Add for Hire Charges & Maintenance of mixer, sundries & contingencies %

Profit & Overhead %


12 mm
1000 mm

Amount Remark

1506.96
226.04
0.00 32.5
0.00
0.00
0.00
115.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
4.80
0.00

1852.80 18.53

0.00
750.00
0.00
97.50
0.00
0.00
0.00
847.50
2700.30
0.00

2700.30

0.00
2700.30 SQM
823.20 Sft
5.21
BCES CONS
DADO
Details of cost of 1 SQM Thk
Proporation 1 : 1 Ht

Sr. No. Items Unit Volume Rate


Materials
0.2 1506.96
Wastage 15% 0.03 1506.96
BAL Diamondstar White Bags/m2 Bags 10.76
wastage 3% Bags 0.32
Cement required 1860 KG Bags 37.20
Wastage 3% Bags 1.12
0.0024 M3 0.09 250
AGGREGATE 0.00
Sand Cu mtr 0.00
wastage 15% Cu mtr 0.00 1270
GRIT 0.00 600
wastage 15% 0.0000 600
Neat cement slurry KG.M2 Bags 0.0000 0
wastage 3% 0.0000 0
White Cement KG.M2 Bags 0.00 660
wastage 3% 0.0000 660
POP COVERING M2 0.20
Pigment 0.12 M2 0.20 40
SS Pins M2 0.20
Scafolding (M) M2 0.20 0

Total Material
Labour
Scaffolding (L) 1
Scaffolding (L) Escalation 1 0
Labour Rate 1 180
Labour Rate Escalation 0% 1 0
Supporting Labour 13% 1 23.4
Escalation 1
ADD for Chamfering 1
Escalation 1 0
Total Labour
Total (Labour + Material)
Add for Hire Charges & Maintenance of mixer, sundries & contingencies %

Profit & Overhead %


12 mm
200 mm

Amount Remark

301.39
45.21
0.00 32.5
0.00
0.00
0.00
22.50
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
8.00
0.00
0.00

377.10 3.71

0.00
0.00
180.00
0.00
23.40
0.00
0.00
0.00
203.40
580.50
0.00

580.50

0.00
580.50 Rmtr
175.00 Rft
5.21
BCES CONS
DADO
Details of cost of 1 SQM Thk
Proporation 1 : 1 Ht

Sr. No. Items Unit Volume Rate


Materials
0.2 1506.96
Wastage 15% 0.03 1506.96
BAL Diamondstar White Bags/m2 Bags 10.76
wastage 3% Bags 0.32
Cement required 1860 KG Bags 37.20
Wastage 3% Bags 1.12
0.0024 M3 0.09 250
AGGREGATE 0.00
Sand Cu mtr 0.00
wastage 15% Cu mtr 0.00 1270
GRIT 0.00 600
wastage 15% 0.0000 600
Neat cement slurry KG.M2 Bags 0.0000 0
wastage 3% 0.0000 0
White Cement KG.M2 Bags 0.00 660
wastage 3% 0.0000 660
POP COVERING M2 0.20
Pigment 0.12 M2 0.20 40
SS Pins M2 0.20
Scafolding (M) M2 0.20 0

Total Material
Labour
Scaffolding (L) 1
Scaffolding (L) Escalation 1 0
Labour Rate 1 180
Labour Rate Escalation 0% 1 0
Supporting Labour 13% 1 23.4
Escalation 1
ADD for Chamfering 1
Escalation 1 0
Total Labour
Total (Labour + Material)
Add for Hire Charges & Maintenance of mixer, sundries & contingencies %

Profit & Overhead %


12 mm
200 mm

Amount Remark

301.39
45.21
0.00 32.5
0.00
0.00
0.00
22.50
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
8.00
0.00
0.00

377.10 3.71

0.00
0.00
180.00
0.00
23.40
0.00
0.00
0.00
203.40
580.50
0.00

580.50

0.00
580.50 Rmtr
175.00 Rft
5.23
BCES CONS
Basin Counter
Details of cost of 0.8 SQM Thk
Proporation 1 : 1 Ht

Sr. No. Items Unit Volume Rate


Materials

Granite 0.36 1722.24


wastage 10% 0.036 1722.24
Granite 1.7 0.1 0.17 1722
wastage 10% 0.017 1722
M2 0.583
Kuddapa
wastage 0.4 323
22% 0.08 323
BAL Diamondstar White Bags/m2 Bags 10.76
wastage 3% Bags 0.32
Cement required 1860 KG Bags 37.20
Wastage 3% Bags 1.12
0% M3 0.17 250
AGGREGATE 0.01
Sand Cu mtr 0.00
wastage 15% Cu mtr 0.00 1270
GRIT 0.00 600
wastage 15% 0.0000 600
Neat cement slurry KG.M2 Bags 0.0000 0
wastage 3% 0.0000 0
White Cement KG.M2 Bags 0.00 660
wastage 3% 0.0000 660
POP COVERING M2 0.36
Pigment 0.12 M2 0.36 40
SS Pins / adheasive Rmtr 0.80 225
Scafolding (M) M2 0.36 0

Total Material
Labour
Scaffolding (L) 0.8
Scaffolding (L) Escalation 10% 0.8 0
Labour Rate 0.8 1975
Labour Rate Escalation 0% 0.8 0
Supporting Labour 13% 0.8 256.75
Escalation 0% 0.8
ADD for Chamfering 0.8
Escalation 10% 0.8 0
Total Labour
Total (Labour + Material)
Add for Hire Charges & Maintenance of mixer, sundries & contingencies %
Add for Hire Charges & Maintenance of mixer, sundries & contingencies %

Profit & Overhead %


For 8 Rmtr
12 mm
450 mm

Amount Remark

620.01
62.00
292.74
29.27

116.28
25.58
0.00 32.5
0.00
0.00
0.00
42.50
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
14.40
180.00
0.00

1382.78 13.69

0.00
0.00
1580.00
0.00
205.40
0.00
0.00
0.00
1785.40
3168.18
0.00
0.00

3168.18

0.00
3168.18 Rmtr
3943.00
5.24
BCES CONS
Kitchen Platform
Details of cost of 5.42 Rmtr Thk
Proporation 1 : 4 Ht/W

Sr. No. Items Unit Volume Rate


Materials

Granite top 3.252 1722.24


Facia granite 0.4065 1722.24
wastage 10% 3.29265 1722.24
Marble 5.42 0.6 3.252 430.4
Vertical support 4 0.6 0.8 1.92 430.4
wastage 15% 0.7758 430.4

22%
BAL Diamondstar White Bags/m2 Bags 10.76
wastage 3% Bags 0.32
Cement required 1860 KG Bags 37.20
Wastage 3% Bags 1.12
0.0390 M3 1.50 250
Cement required 26.8 % Bags 7.70
wastage 3% Bags 0.23
0.04 M3 0.31 250
AGGREGATE 0.04
Sand 70% Cu mtr 0.03 1271
wastage 15% Cu mtr 0.0045 1270
GRIT 0.01 600
wastage 15% 0.002 600
Neat cement slurry KG.M2 Bags 0.0000 0
wastage 3% 0.0000 0
White Cement KG.M2 Bags 0.00 660
wastage 3% 0.0000 660
POP COVERING M2 3.25
Pigment 0.12 M2 3.25 40
SS Pins / adheasive Rmtr 5.42 150
Scafolding (M) M2 3.25 0

Total Material
Labour
Scaffolding (L) 5.42
Scaffolding (L) Escalation 5.42 0
Labour Rate 5.42 1795
Labour Rate Escalation 0% 5.42 0
Supporting Labour 13% 1 233.35
Escalation 5.42
ADD for Chamfering 5.42
Escalation 5.42 0
Total Labour
Total (Labour + Material)
Add for Hire Charges & Maintenance of mixer, sundries & contingencies %

Profit & Overhead %


12 mm
600 mm

Amount Remark

5600.72
700.09
5670.73
1399.66
826.37
333.90

0.00 32.5
0.00
0.00
0.00
375.00

77.50
0.00
38.13
5.72
6.00
1.20
0.00
0.00
0.00
0.00
0.00
130.00
813.00
0.00

15978.03 158.64

0.00
0.00
9728.90
0.00
233.35
0.00
0.00
0.00
9962.25
25940.28
0.00

25940.28

0.00
25940.28 Rmtr
4765.00
5.25
BCES CONS
Window Sill
Details of cost of 1 Rmtr Thk
Proporation 1 : 1 Ht

Sr. No. Items Unit Volume Rate


Materials

Granite 0.3 1722.24


wastage 10% 0.03 1722.24

BAL Diamondstar White Bags/m2 Bags 10.76


wastage 3% Bags 0.32
Cement required 1860 KG Bags 37.20
Wastage 3% Bags 1.12
0.0036 M3 0.14 250

AGGREGATE 0.00
Sand Cu mtr 0.00
wastage 15% Cu mtr 0.00 1270
GRIT 0.00 600
wastage 15% 0.00 600
Neat cement slurry KG.M2 Bags 0.00 0
wastage 3% 0.00 0
White Cement KG.M2 Bags 0.00 660
wastage 3% 0.00 660
POP COVERING M2 0.30
Pigment 0.12 M2 0.30 40
SS Pins / adheasive Rmtr 0.30
Scafolding (M) M2 0.30 0

Total Material
Labour
Scaffolding (L) 1
Scaffolding (L) Escalation 1 0
Labour Rate 1 280
Labour Rate Escalation 0% 1 0
Supporting Labour 13% 1 36.4
Escalation 1
ADD for Chamfering 1
Escalation 1 0
Total Labour
Total (Labour + Material)
Add for Hire Charges & Maintenance of mixer, sundries & contingencies %

Profit & Overhead %


Profit & Overhead %
12 mm
300 mm

Amount Remark

516.67
51.67

0.00 32.5
0.00
0.00
0.00
35.00

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
12.00
0.00
0.00

615.34 6.04

0.00
0.00
280.00
0.00
36.40
0.00
0.00
0.00
316.40
931.74
0.00

931.74
0.00
931.74 Rmtr
280.70 Rft
5.26
BCES CONS
Window Sill
Details of cost of 1 Rmtr Thk
Proporation 1 : 1 Ht

Sr. No. Items Unit Volume Rate


Materials

Turkish 0.3 1722.24


wastage 10% 0.03 1722.24

BAL Diamondstar White Bags/m2 Bags 10.76


wastage 3% Bags 0.32
Cement required 1860 KG Bags 37.20
Wastage 3% Bags 1.12
0.0036 M3 0.14 250

AGGREGATE 0.00
Sand Cu mtr 0.00
wastage 15% Cu mtr 0.00 1270
GRIT 0.00 600
wastage 15% 0.00 600
Neat cement slurry KG.M2 Bags 0.00 0
wastage 3% 0.00 0
White Cement KG.M2 Bags 0.00 660
wastage 3% 0.00 660
POP COVERING M2 0.30
Pigment 0.12 M2 0.30 40
SS Pins M2 0.30
Scafolding (M) M2 0.30 0

Total Material
Labour
Scaffolding (L) 1
Scaffolding (L) Escalation 1 0
Labour Rate 1 280
Labour Rate Escalation 0% 1 0
Supporting Labour 13% 1 36.4
Escalation 1
ADD for Chamfering 1
Escalation 1 0
Total Labour
Total (Labour + Material)
Add for Hire Charges & Maintenance of mixer, sundries & contingencies %

Profit & Overhead %


Profit & Overhead %
12 mm
300 mm

Amount Remark

516.67
51.67

0.00 32.5
0.00
0.00
0.00
35.00

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
12.00
0.00
0.00

615.34 6.04

0.00
0.00
280.00
0.00
36.40
0.00
0.00
0.00
316.40
931.74
0.00

931.74
0.00
931.74 Rmtr
280.70 Rft
5.27
BCES CONS
Toilet Door frame
Details of cost of 5.42 Rmtr Thk
Proporation 1 : 4 Ht/W

Sr. No. Items Unit Volume Rate


Materials

Granite top 0.23 1722.24


Facia granite 1722.24
wastage 15% 0.23 1722.24

BAL Diamondstar White Bags/m2 Bags 10.76


wastage 3% Bags 0.32
Cement required 1860 KG Bags 37.20
Wastage 3% Bags 1.12
0.0390 M3 0.07 250
Cement required 26.8 % Bags 7.70
wastage 3% Bags 0.23
0.04 M3 0.01
AGGREGATE 0.00
Sand 70% Cu mtr 0.00
wastage 15% Cu mtr 0.00
GRIT 30% 0.00 600
wastage 15% 0.00 600
Neat cement slurry KG.M2 Bags 0.00 0
wastage 3% 0.00 0
White Cement KG.M2 Bags 0.00 660
wastage 3% 0.00 660
POP COVERING M2 0.23
Pigment 0.12 M2 0.23 40
SS Pins / adheasive Rmtr 1.00 150
Scafolding (M) M2 0.23 0

Total Material
Labour
Scaffolding (L) 5.42
Scaffolding (L) Escalation 5.42 0
Labour Rate 5.42 1795
Labour Rate Escalation 0% 5.42 0
Supporting Labour 13% 1 233.35
Escalation 5.42
ADD for Chamfering 5.42
Escalation 5.42 0
Total Labour
Total (Labour + Material)
Add for Hire Charges & Maintenance of mixer, sundries & contingencies %
Add for Hire Charges & Maintenance of mixer, sundries & contingencies %

Profit & Overhead %


12 mm
150 mm

Amount Remark

396.12
0.00
396.12

0.00 32.5
0.00
0.00
0.00
17.50

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
9.20
150.00
0.00

968.93 9.61

0.00
0.00
9728.90
0.00
233.35
0.00
0.00
0.00
9962.25
10931.18
0.00
0.00

10931.18

0.00
10931.18 Rmtr
4765.00
6.1.1.
BCES CONS
Main Door Frame : Section 6" x 3" Rebate of 55 mm African Teak wood
Details of cost of 5.42 Rmtr Thk
Proporation 2325 1075 Mtr

Sr. No. Items Unit Volume Rate


Materials

African Teak Frame mtr 5.725 786


wastage 0% 786

anchor fastener
wastage 0% no 8.00 22
Foam filling no 1.00 170
Wastage 0% 0.00
Total Material
Labour
Scaffolding (L) 5.7
Scaffolding (L) Escalation 10% 5.7 0
Labour Rate no 325 5.7 56.8
Labour Rate Escalation 0% 5.7 0
Supporting Labour 0% 5.7
Escalation 10% 5.7 0

0
Total Labour
Total (Labour + Material)
Rmtr

Profit & Overhead %


150 mm
60 mm

Amount Remark

4499.85 0.051525
0.00

176.00
170.00
0.00
4845.85 48.46

0.00
0.00
323.76
0.00
0.00
0.00
0.00
0.00
323.76
5169.61
0.00

5169.61

0.00
5169.61 No
903.20 Rmtr
6.1.1. - 2
BCES CONS
Main Door Frame : Section 6" x 3" Rebate of 55 mm Red Miranti Wood
Details of cost of 5.42 Rmtr Thk
Proporation 2325 1075 Mtr

Sr. No. Items Unit Volume Rate


Materials

Red Miranti mtr 5.725 400


wastage 0% 400

anchor fastener 8.00 22


wastage 0% no
Foam filling no 1.00 170
Wastage 0% 0.05 170
Total Material
Labour
Scaffolding (L) 5.7
Scaffolding (L) Escalation 10% 5.7 0
Labour Rate no 325 5.7 56.8
Labour Rate Escalation 0% 5.7 0
Supporting Labour 0% 5.7
Escalation 10% 5.7 0

0
Total Labour
Total (Labour + Material)
Rmtr

Profit & Overhead %


150 mm
60 mm

Amount Remark

2290.00 2290
0.00

176.00
0.00
170.00
8.50
2644.50 26.45

0.00
0.00
323.76
0.00
0.00
0.00
0.00
0.00
323.76
2968.26
0.00

2968.26

0.00
2968.26 No
518.70 Rmtr
6.2.1.
BCES CONS
Internal Door Frame
Details of cost of 1 Rmtr Thk
Proporation 2325 875 Mtr

Sr. No. Items Unit Volume Rate


Materials

Red Miranti Frame mtr 5.525 307.7


wastage 0% 0 307.7

anchor fastener
wastage 0% no 8.00 22
Foam filling no 1.00 170
Wastage 0% 0.00
Total Material
Labour
Scaffolding (L) 5.5
Scaffolding (L) Escalation 10% 5.5 0
Labour Rate no 325 5.5 58.8
Labour Rate Escalation 0% 5.5 0
Supporting Labour 0% 5.5
Escalation 10% 5.5 0

0
Total Labour
Total (Labour + Material)
Rmtr

Profit & Overhead %


100 mm
60 mm

Amount Remark

1700.04 2290
0.00

176.00
170.00
0.00
2046.04 20.46

0.00
0.00
323.40
0.00
0.00
0.00
0.00
0.00
323.40
2369.44
0.00

2369.44

0.00
2369.44 No
518.70 Rmtr
6.3.1
BCES CONS
Main door shutter
Details of cost of 1 SQM
Proporation 2325 875 Mtr

Sr. No. Items Unit Volume


Materials

Flush door shutter sqm 2.44


wastage 0% 0
Bidding patti (Ghana Teak) Rmtr 6.75
wastage 5% 0.3375
Veneer "Wenge Century" 3 mm Thk 2 sqm 4.88
wastage 5% 0.244
anchor fastener
wastage 0% no 0.00
Foam filling no 1.00
wastage 0% 0.00
Melamine polish 2 sides 2.44
Enamel paint 0 sides 2.44
Consumables
Total Material
Labour
Scaffolding (L) 2.4
Scaffolding (L) Escalation 10% 2.4
Labour Rate no 1320 2.4
Labour Rate Escalation 0% 2.4
Supporting Labour 0% 2.4
Escalation 10% 2.4

Total Labour
Total (Labour + Material)
Rmtr %

Profit & Overhead %


Thk 45 mm
60 mm

Rate Amount Remark

3498.3 8535.85
3498 0.00
49.2 332.10
49.2 16.61
645.8 3151.50
645.8 157.58
0.00
0.00
0.00
0.00
431 1051.64
81 197.64
0.00
Total Material 13442.92 143.77

0.00
0 0.00
465.71 1117.70
0 0.00
0.00
0 0.00
0.00
0 0.00
Total Labour 1117.70
Total (Labour + Material) 14560.62
% 0.00

14560.62

% 0.00
14560.62 No
6355.00 Sqm
6.3.2
BCES CONS
For Staircase Door
Details of cost of 1 SQM
Proporation 2100 1200 Mtr

Sr. No. Items Unit Volume


Materials

Solid core flush door shutter (FR) sqm 2.52


wastage 0% 0
Bidding patti (Ghana Teak) Rmtr 6.6
wastage 5% 0.33
Veneer "Wenge Century" 4 mm Thk 1 side sqm 2.52
wastage 5% 0.126
anchor fastener
wastage 0% no 0.00
Foam filling no 1.00
wastage 0% 0.00
Consumables incl
Melamine polish 1 side 2.52
Enamel paint 1 side 2.52
Hardwares 1.00
Total Material
Labour
Scaffolding (L) 2.5
Scaffolding (L) Escalation 10% 2.5
Labour Rate no 900 2.5
Labour Rate Escalation 0% 2.5
Supporting Labour 0% 2.5
Escalation 10% 2.5

Total Labour
Total (Labour + Material)
Rmtr %

Profit & Overhead %


Thk 45 mm
mm

Rate Amount Remark

3498.3 8815.72
3498.3 0.00
49.2 324.72
49.2 16.24
807.3 2034.40
807.3 101.72
0.00
0.00
0.00
0.00
0.00
431 1086.12
81 204.12
100 100.00
Total Material 12683.03 126..81

0.00
0 0.00
357 892.50
0 0.00
0.00
0 0.00
0.00
0 0.00
Total Labour 892.50
Total (Labour + Material) 13575.53
% 0.00

13575.53

% 0.00
13575.53 No
5389.40 Sqm
6.3.3
BCES CONS
For Staircase Door
Details of cost of 1 SQM
Proporation 2100 1000 Mtr

Sr. No. Items Unit Volume


Materials

Solid core flush door shutter (FR) sqm 2.1


wastage 0% 0
Bidding patti (Ghana Teak) Rmtr 6.2
wastage 5% 0.31
Veneer "Wenge Century" 4 mm Thk 1 side sqm 2.1
wastage 5% 0.105
anchor fastener
wastage 0% no 0.00
Foam filling no 1.00
wastage 0% 0.00
Consumables 1.00
Melamine polish 1 side 2.10
Enamel paint 1 side 2.10
Hardwares
Total Material
Labour
Scaffolding (L) 2.1
Scaffolding (L) Escalation 10% 2.1
Labour Rate no 900 2.1
Labour Rate Escalation 0% 2.1
Supporting Labour 0% 2.1
Escalation 10% 2.1

Total Labour
Total (Labour + Material)
Rmtr %

Profit & Overhead %


Thk 45 mm
mm

Rate Amount Remark

3498.3 7346.43
3498.3 0.00
49.2 305.04
49.2 15.25
807.3 1695.33
807.3 84.77
0.00
0.00
0.00
0.00
100 100.00
431 905.10
81 170.10
0.00
Total Material 10622.02 106.21

0.00
0 0.00
429 900.90
0 0.00
0.00
0 0.00
0.00
0 0.00
Total Labour 900.90
Total (Labour + Material) 11522.92
% 0.00

11522.92

% 0.00
11522.92 No
5486.00 Sqm
6.4.1.
BCES CONS
For Bedroom Door
Details of cost of 1 SQM
Proporation 2325 900 Mtr

Sr. No. Items Unit Volume


Materials

Solid core flush door shutter (FR) sqm 2.09


wastage 0% 0
Bidding patti (Ghana Teak) Rmtr 6.45
wastage 5% 0.3225
Veneer "Wenge Century" 4 mm Thk side sqm 0
wastage 0
anchor fastener
wastage 0% no 0.00
Foam filling no 1.00
wastage 0% 0.00
Consumables 1.00
Hardwares
Synthetic Enamel Paint 2 sides 2.09

Total Material
Labour
Scaffolding (L) 2.1
Scaffolding (L) Escalation 10% 2.1
Labour Rate no 800 2.1
Labour Rate Escalation 0% 2.1
Supporting Labour 0% 2.1
Escalation 10% 2.1

Total Labour
Total (Labour + Material)
Rmtr %

Profit & Overhead %


Thk 40 mm
mm

Rate Amount Remark

914.9 1912.14
914.9 0.00
49.2 317.34
49.2 15.87
807.3 0.00
807.3 0.00
0.00
0.00
0.00
0.00
100 100.00
0.00
81 169.29

Total Material 2514.64 26.86

0.00
0 0.00
382 802.20
0 0.00
0.00
0 0.00
0.00
0 0.00
Total Labour 802.20
Total (Labour + Material) 3316.84
% 0.00

3316.84

% 0.00
3316.84 No
1665.70 Sqm
6.5.1
BCES CONS
For Toilet Door
Details of cost of 1 SQM
Proporation 2325 750 Mtr

Sr. No. Items Unit Volume


Materials

Solid core flush door shutter (FR) sqm 1.74


wastage 0% 0
Bidding patti (Ghana Teak) Rmtr 6.15
wastage 5% 0.3075
Veneer "Wenge Century" 4 mm Thk side sqm 0
wastage 0
anchor fastener
wastage 0% no 0.00
Foam filling no 1.00
wastage 0% 0.00
Consumables 1.00
Hardwares
Synthetic Enamel Paint 2 sides 1.74

Total Material
Labour
Scaffolding (L) 1.7
Scaffolding (L) Escalation 10% 1.7
Labour Rate no 800 1.7
Labour Rate Escalation 0% 1.7
Supporting Labour 0% 1.7
Escalation 10% 1.7

Total Labour
Total (Labour + Material)
Rmtr %

Profit & Overhead %


Thk 35 mm
mm

Rate Amount Remark

968.8 1685.71
968.8 0.00
49.2 302.58
49.2 15.13
807.3 0.00
807.3 0.00
0.00
0.00
0.00
0.00
100 100.00
0.00
81 140.94

Total Material 2244.36 23.89

0.00
0 0.00
459 780.30
0 0.00
0.00
0 0.00
0.00
0 0.00
Total Labour 780.30
Total (Labour + Material) 3024.66
% 0.00

3024.66

% 0.00
3024.66 No
1828.50 Sqm
6.5.1 (2)
BCES CONS
For Duct Door
Details of cost of 1 SQM
Proporation 2100 750 Mtr

Sr. No. Items Unit Volume


Materials

Solid core flush door shutter (FR) sqm 1.58


wastage 0% 0
Bidding patti (Ghana Teak) Rmtr 5.7
wastage 5% 0.285
Veneer "Wenge Century" 4 mm Thk side sqm 0
wastage 0
anchor fastener
wastage 0% no 0.00
Foam filling no 1.00
wastage 0% 0.00
Consumables 1.00
Melamine polish 0 side 1.58
Synthetic Enamel Paint 2 sides 1.58
Hardwares
Total Material
Labour
Scaffolding (L) 1.6
Scaffolding (L) Escalation 10% 1.6
Labour Rate no 600 1.6
Labour Rate Escalation 0% 1.6
Supporting Labour 0% 1.6
Escalation 10% 1.6

Total Labour
Total (Labour + Material)
Rmtr %

Profit & Overhead %


Thk 35 mm
mm

Rate Amount Remark

968.8 1530.70
968.8 0.00
49.2 280.44
49.2 14.02
807.3 0.00
807.3 0.00
0.00
0.00
0.00
0.00
100 100.00
431 680.98
81 127.98

Total Material 2734.13 21.25

0.00
0 0.00
381 609.60
0 0.00
0.00
0 0.00
0.00
0 0.00
Total Labour 609.60
Total (Labour + Material) 3343.73
% 0.00

3343.73

% 0.00
3343.73 No
1761.60 Sqm
6.5.2
BCES CONS
For Kitchen Door Shutter
Details of cost of 1 SQM
Proporation 2325 900 Mtr

Sr. No. Items Unit Volume


Materials

Flush Door Shutter sqm 2.09


wastage 0% 0
Bidding patti (Ghana Teak) Rmtr 6.45
wastage 5% 0.3225
Veneer "Wenge Century" 4 mm Thk 0 side sqm 0
wastage 0% 0
anchor fastener
wastage 0% no 0.00
Foam filling no 1.00
wastage 0% 0.00
Melamine polish 0 side 1.58
Enamel Paint 2 sides 1.58
Consumables 1.00
Total Material
Labour
Scaffolding (L) 2.1
Scaffolding (L) Escalation 10% 2.1
Labour Rate no 1220 2.1
Labour Rate Escalation 0% 2.1
Supporting Labour 0% 2.1
Escalation 10% 2.1

Total Labour
Total (Labour + Material)
Rmtr %

Profit & Overhead %


Thk 45 mm
mm

Rate Amount Remark

3229.2 6749.03
3229.2 0.00
49.2 317.34
49.2 15.87
645.8 0.00
645.8 0.00
0.00
0.00
0.00
0.00
431 680.98
81 127.98
100 100.00
Total Material 7991.20 75.28

0.00
0 0.00
583 1224.30
0 0.00
0.00
0 0.00
0.00
0 0.00
Total Labour 1224.30
Total (Labour + Material) 9215.50
% 0.00

9215.50

% 0.00
9215.50 No
4180.70 Sqm
BCES CONS
POP COVERING FOR FLOORING
Details of cost of 1 SQM
Proporation 1 1 Mtr

Sr. No. Items Unit Volume


Materials

POP Covering of 8 to 10 mm thk (1


bag covers 1.20 sqm) POP (20 KG) =
65 Rs.)
sqm 1

sqm
Polythene paper of 500 Gauge used
to cover the flooring (1 kg = 67.6 Rs.)
(output 1 kg = (12 x6.56) = 78.72 sqft
= 7.31 sqm.)
1

Total Material
Labour

Labour required for laying and sqm 1


clearing

Total Labour
Labour rate per Sqm
Rmtr %

Profit & Overhead %


Thk 10 mm
mm

Rate Amount Remark

50.00 50.00

9.3 9.30

Total Material 59.30 1.25 Constant

20.00 20.00

Total Labour 20.00


Labour rate per Sqm 79.30 1.15 Constant
% 0.00

79.30 Sqm

% 0.00
79.30 Sqm
79.30 Sqm
BCES CONS
1.7 Providing and doing 230 mm thk. Dry rubble soiling
Details of cost of With rubble brought from SQM
Size outside
Mtr
wastage
Sr. No. Items Unit Volume
Materials

Soiling Cum 0.23


Wastage 15% Cum
Chips (Kapchi) Cum 0.05
Wastage 10% Cum
Compaction Cum 1.00
Murum Free Supply Cum 0.05
Material rate per Sqm
Labour charges Sqm 1.00
Labour rate per Sqm
Total Labour
Total (Labour + Material)

Profit & Overhead %


Rate per Sqm
Thk 230 mm
mm

Rate Amount Remark

529.2 121.72
18.26
776.16 38.81
3.56
5.00 5.00
0.00 0.00
Sqm 187.34
20.00 20.00
Sqm 20.00
Total Labour 20.00
Total (Labour + Material) 207.34

% 0.00
Rate per Sqm 207.34
Rate per Cum 887.70

Potrebbero piacerti anche