SECTION I
INSTRUCTION TO BIDDERS
June , 2019
华油惠博普科技股份有限公司
China Oil HBP Science & Technology Corporation Ltd.
TABLE OF CONTENTS
The ITB are and shall remain the property of CONTRACTOR and are
transmitted to BIDDER solely for the purpose of preparing and
submitting a PROPOSAL by BIDDERS in accordance therewith.
BIDDER shall keep confidential and shall not release any part of the
ITB to any third party, other than to have the third party prepare
and submit to BIDDER a PROPOSAL for part of the work.
2.3 “BID CLOSING DATE AND TIME” means the end date and time by
which BIDDER’s response to the ITB must be received by
CONTRACTOR.
2.4 “BID PERIOD” shall mean the time between the issuance of the ITB
and the BID CLOSING DATE AND TIME.
The Garraf field is situated in the southern part of Iraq, in the Thi Qar
Governorate, some 5 km Northwest of Al Rifa’I city and 85 km North of
Nasiriyah. Garraf is an anticlinal structure aligned Northwest-
Southeast, about 31 km long and 10 km wide.
2
Garraf Field Location
4.1 Within 48 hours after receipt of this ITB, BIDDERS shall submit their
acknowledgement of receipt of the ITB package and make a
confirmation of intent to or not to submit a bid thereof by email to
CONTRACTOR representative mentioned below:
Email: waqar@china-hbp.com
4.2 The BIDDER shall appoint a lawful attorney and authorize him to
execute all the necessary matters related. A format of Power of
Attorney is enclosed in Section II of this ITB as ATTACHMENT II -2.
The Power of Attorney shall be included in Technical PROPOSAL.
7.1 GENERAL
BIDDERS shall submit their PROPOSAL on the basis of the terms and
conditions of the ITB documents. Failure to prepare bid PROPOSAL
in accordance with the specifications, terms and conditions will be
cause for disqualification.
7.2 LANGUAGE
In the event that the BIDDER is advised to visit and examine the site
of the work and its surroundings to obtain for itself on its own
responsibility all information that may be necessary for preparing the
PROPOSAL. The cost of visiting the site shall be at BIDDER’s own
expense and the BIDDER shall take all risks, if any, in this regard.
8.1 BIDDER shall submit a Technical Proposal package as per the following
table of content with proper numbered sections.
a) BIDDER’s Profile
b) Project Organization;
c) Personnel Qualification
d) BIDDER’s Experiences;
e) Project Execution Plan;
f) Project Management
g) Litigation
h) Company Registration with Ministry of Trade, IRAQ
i) Other matters at BIDDER’s discretion;
BIDDER shall state the full name and activities of its company, place
and date of incorporation, company structure and shall also state the
name and activities of its subsidiaries, affiliate and associate
companies, if any. Notwithstanding the above, BIDDER is required to
provide information as per ATTACHMENT I-4 BIDDER’s Profile.
BIDDER shall provide preliminary Project Execution Plan (PEP) for the
WORK in accordance with the requirements stipulated under this
clause.
The PEP shall include with respect to all phases and aspects of the
WORK, including details of the deliverables/output of each activity. The
PEP shall include the following information, but is not limited to:
a) Project Management
b) Engineering
c) Contracting and Procurement
d) Project Control and Planning
e) Construction/Installation
f) Commissioning
g) Project Controls
h) QA/QC
i) HSES
8.1.7 Litigation
If BIDDER, have been involved in any litigation in the last ten (10)
years, the nature and status of litigation shall be described and
submitted under BIDDER letterhead accompanied by its appointed
legal entity cover note.
8.2.1 The successful BIDDER shall sign the Subcontract with CONTRACTOR
per the Form & Conditions of SUBCONTRACT provided in Section II.
BIDDER shall state the deviations of SUBCONTRACT with the provided
format TTACHMENT II-11 Statement of Deviations for Form & Conditions
of SUBCONTRACT. BIDDER shall confirm that anything not stated in the
deviations will comply fully with Form & Conditions of SUBCONTRACT.
Any BIDDER’s deviations are not in the “Statement of Deviations” may be
disqualified and rejected by CONTRACTOR.
8.2.2 The bid price shall be quoted in US Dollar (USD). Quotations in any
other currency shall be nullified and rejected.
7
The bid PROPOSAL shall be received no later than 18:00, July 10th,
2019 (IRAQ Time), unless CONTRACTOR extends the said date in
writing. PROPOSALS received after above mentioned date shall not
be taken into consideration.
12.1 CONTRACTOR is neither bound to accept any bid submitted nor the
lowest bid submitted and also reserves the right to accept or reject any or
all of the bid PROPOSALS received at its sole discretion and without any
explanation.
If for any good reason BIDDER desires more time to present its bid
PROPOSAL, it may request a time extension in writing. If the request hereof is
granted, all BIDDERS will then be notified of the extension hereof and no bids
will be opened until the new due date has expired. No extensions will be taken
into consideration during the last one week of the bid period
15.0 AWARD OF SUBCONTRACT
9
CONTRACTOR expects to SUBCONTRACT with the successful
BIDDER as a single entity and subcontract by successful BIDDER is
not allowed.
16.0 LAW
16.1 This Bid shall be construed in accordance with and governed by the
Laws of China (without reference to its rules as to conflicts of law).
16.2 BIDDERS shall also be fully aware of the Iraqi laws and regulations
including but not limited to those of Tax, Labor, Social Security,
Customs duties and their latest amendments.
19.0 CONFIDENTIALITY
19.1 BIDDER has agreed as a condition of receiving this ITB that BIDDER
shall keep the contents of this ITB strictly confidential and shall use only
such information necessary for the preparation of the Bid. The disclosure
of information in this ITB to BIDDER hereunder shall not be construed
as granting to BIDDER a license or any rights under copyright, trade
secret or any patents. A format of Confidentiality Undertaking is
enclosed in Section II of this ITB as ATTACHMENT II -3 for BIDDER to
follow.
10
19.2 BIDDER shall not disclose to any third party all or any part of the
information disclosed by CONTRACTOR or otherwise obtained by
BIDDER in the course of and/or as a result of the performance of the Bid
preparation hereunder.
If such disclosure is required by law or requested by governmental or
regulatory agency or legal or arbitration or other legal proceedings
between BIDDER and CONTRACTOR, BIDDER shall notify
CONTRACTOR in writing of contents of such disclosure in advance.
21.0 OTHERS
21.1 Unless and until such time a formal Subcontract is prepared and
executed, BIDDER’s PROPOSAL together with CONTRACTOR’s
acceptance thereof and signing of letter of intent shall constitute a
binding SUBCONTRACT.
21.2 BIDDER shall provide access, including audit access, to its personnel,
records, documents and the like as may be required for any
reasonable purposes, including verification of the levels and types
and services to be provided by the BIDDER.
22.0 ATTACHMENTS
11