ISWARABENA SDN BHD Doc. Ref.

: ISB/MSM/PVD/01
REV. NO. : 0
METHOD STATEMENTS MANUAL ISSUE DATE : 09/04/2019
PAGE : 1 OF 2
PREFABRICATED VERTICAL DRAINS

1.0 OBJECTIVE

The objective of this method statement is to carry out Prefabricated Vertical Drain (PVD) for
PROPOSED CONSTRUCTION AND COMPLETION OF EARTHWORKS AND OTHER
RELATED WORKS FOR DEVELOPMENT OF PHASE 2 (R11), AT BANDAR BUKIT RAJA 2,
MUKIM KAPAR, DISTRICT OF KLANG, SELANGOR DARUL EHSAN FOR MESSR. SIME
DARBY USJ DEVELOPMENT SDN. BHD.

2.0 SCOPE

The scope of this method statement applies for Prefabricated Vertical Drain (PVD) at Bukit Raja
R11 project.

3.0 REFERENCE

ISO 9000:2007 Clauses 6.3, 7.1 & 7.5


Drawings
Field Density Test Record
Method Statement – Survey Works for Earthworks
Method Statement – Site Clearing
Project Specifications
Drainage Works Inspection Checklist

4.0 DEFINITION

N/A

5.0 RESPONSIBILITY

Project Manager
Project Engineer
Field Surveyor
Lab Technician
Site Supervisor

6.0 MATERIALS

Sand, Drain roll, Alidrain HB65 Prefabricated Vertical Drain or equivalent, Anchor Plate

7.0 HANDLING AND STORAGE OF MATERIALS

Handling : Handling of all fills materials using excavator and dump truck.

Storage : All suitable material to be used on site shall be stored at designated area.
ISWARABENA SDN BHD Doc. Ref. : ISB/MSM/PVD/01
REV. NO. : 0
METHOD STATEMENTS MANUAL ISSUE DATE : 09/04/2019
PAGE : 2 OF 2
PREFABRICATED VERTICAL DRAINS

8.0 PLANT, MACHINERY, EQUIPMENT & TOOLS

Excavator, PVD hydraulic gear drive, Mandrel

9.0 PREPARATORY WORKS

Working platform

10.0 WORK METHODOLOGY

10.1 Identify and ascertain that the areas to carry out the PVD works as per drawings.

10.2 To ensure automated data logger is on PVD rig.

10.3 Working platform prepared by earthworks contractor and mark the location /point of PVD point
(Triangular Grid Spacing of PVD at 1.1m or 1.2m c/c)

10.4 Laying Non-Woven Geotextile TS 20 before laying spread, level and compact 400mm thick
drainage blanket as per determine in the drawing

10.5 Carry out the installation of predefine depth will define by client / consultant or as per mention
in drawing.

10.6 Setting out and marked with peg to define the actual position of drain in triangular spacing as
per shown on drawing.

10.7 The individual of drain position will be marked by pulling a nylon string and the anchor plate will
be used to mark the position of drain.

10.8 The drain roll is mounted on the side of leader allowing the drain to fed into the mandrel through
a series of rollers.

10.9 Installed the mandrel to the design depth, once the mandrel clears to ground surface the drain
will be cut off 200mm above ground level (as per drawing).

10.10 Repeat the 10.5 – 10.8 step for all of the PVD point.

10.11 Lay, spread and compact the final layer (200 – 300mm) of sand blanket.

10.12 Carry out the construction of dewatering point as per directed by S.O / R.E

10.13 Construct the scupper drain using the approved granular material to drain out the water into the
drainage ditch.