Sei sulla pagina 1di 11

Asset Accounting

Last Update: 07/02/19 8:58 AM

Create Write-Up ABZU

Publisher Information

File
426367241.doc
Link 1

Link 2

Link 3

Link 4

Job Role

Asset Periodic Processing

Insert Job Role rows as necessary.

Last changed on: 07/02/19 Work Instruction


SAP 4.6C
Version: Final Page: 1 of 11
Asset Accounting

CHANGE HISTORY
Update the following table as necessary when this document is changed.

Date Name Change Description

Last changed on: 07/02/19 Work Instruction


SAP 4.6C
Version: Final Page: 2 of 11
Asset Accounting

ABZU - Create Write-Up

TOPIC OBJECTIVES

Business Process Procedure Overview


Background
A write-up is generally understood to be a later change to the valuation of an asset.
This change can take different forms, depending on the reasons for the change.
There are two common reasons for write-ups:
1. You forgot to capitalize an asset in a fiscal year that is now closed, and this
omission must now be corrected (write-ups to APC are usually called post-
capitalization). Current year income statement gets a credit for the extent of
post-capitalization amount given the assumption that the Vendor invoice was
booked as an expense in the previous fiscal year.
2. The value adjustments (depreciation) that you calculated in the past were too
high. You must now correct this error using a write-up in the current fiscal
year. Excessive depreciation generally results from:
 The use of incorrect depreciation terms (incorrect expected useful life,
incorrect depreciation key)
 Unplanned depreciation, which is no longer valid in the current situation
 A later reduction in the acquisition and production costs of an asset (for
example, due to a subsequent credit memo).

Scenario
This system task is used to post write-Up. SABIC America will rarely be performing
the Post-Capitalization transactions since these scenarios are very remote.

Prerequisites
None.

PROCEDURAL STEPS

Menu Path SAP menu  Accounting  Financial Accounting  Fixed


Assets  Posting  Manual Value Correction  ABZU -
Write-Up.
Transaction Code ABZU

Last changed on: 07/02/19 Work Instruction


SAP 4.6C
Version: Final Page: 3 of 11
Asset Accounting

CASE FLOW DIAGRAM

Ordinary
depreciation
Post using
Increased book
Yes corresponding
Existing Post a write up Determine reason value
transaction type
assets ?? for write up

Tax
depreciation

Last changed on: 07/02/19 Work Instruction


SAP 4.6C
Version: Final Page: 4 of 11
Asset Accounting

Perform the following steps of how to Create Write-Up using the information below:

Menu Path: Accounting  Financial Accounting  Fixed Assets  Posting  Manual Value
Correction  ABZU - Write-Up.

Transaction Program Screen Sequenc Description


e
ABZU Create Write-Up
Client Language User Data Job Role
WI-FI-ABZU_01 Asset Periodic Processing

SAP Easy Access

1. Double Click on ABZU - Write-Up

Last changed on: 07/02/19 Work Instruction


SAP 4.6C
Version: Final Page: 5 of 11
Asset Accounting

Write-up: Initial Screen

2. Update the following required and optional fields:

Field Name Description Values


Asset This is the number which, together with the asset sub- Example: 5217000
number, identifies a fixed asset in Asset Accounting.

3. Click the Enter button.

Last changed on: 07/02/19 Work Instruction


SAP 4.6C
Version: Final Page: 6 of 11
Asset Accounting

Choose Value Area

4. Click <checkbox> to deactivate the MACRS depreciation area.

5. Click the Enter button.

Last changed on: 07/02/19 Work Instruction


SAP 4.6C
Version: Final Page: 7 of 11
Asset Accounting

Create Asset Transaction: Write-up ordinary and special depreciation

6. Update the following required and optional fields:

Field Name Description Values


Ord. dep. Enter the write-up value. Example: 3000
Text Contains an explanatory text on the line item. Example: Depreciation
Correction

7. Click Dep. areas . Button .

Last changed on: 07/02/19 Work Instruction


SAP 4.6C
Version: Final Page: 8 of 11
Asset Accounting

Area: 31 Group Curr

8. Click the Enter button.

Area: 32 BkDep(g.cur)

9. Click the Enter button.


Last changed on: 07/02/19 Work Instruction
SAP 4.6C
Version: Final Page: 9 of 11
Asset Accounting

10. Click Display document Button to confirm the entries. The following
document is displayed.
Create Asset Transaction: Write-up ordinary and special depreciation

11. Click the Save button.

Last changed on: 07/02/19 Work Instruction


SAP 4.6C
Version: Final Page: 10 of 11
Asset Accounting

Write-up: Initial Screen

12. The message bar displays “Asset Transaction posted with document no. 5200
10001201”

The system task is complete.

Launch WEB HELP

Last changed on: 07/02/19 Work Instruction


SAP 4.6C
Version: Final Page: 11 of 11