INSPECTION TEST RECORD (ITR) - A

NEUTRAL EARTHING RESISTOR E34-A


Project No.
Project Title
Facilities
INFORMATION
Tag no. System / Sub System no.
Voltage Frequency
Resistance Rating (A/t)
Location IP Rating
Manufacturer Serial no.
Model No. Ref. Drawing nos.
INSPECTION / TEST OK N/A P/L No.
Documents required for verification.
a. NER GA, datasheet and connection diagram
1
b. Packing list
c. Location drawing /substation equipment layout
Verify to ensure that all construction / installation activities have been
2
completed.
Verify any differences between nameplate details against approved
3
drawings and data sheets.
Verify equipment certification meets the area classification
4
requirements.
Verify all associated cables installed, identified, glanded and
5
terminated in accordance with the approved drawings.
Check equipment for mechanical damages (dents/scratches, corrosion,
6
broken handles etc.)
Verify unit internally and externally clean and covers securely fastened
7
with all fixing screws installed.
Verify Earth connection is properly installed and secured as per project
8
specification.
9 Check resistor insulators.
10 Inspect the Neutral Earth Isolating switch.
Identify the spares and special tools supplied, if any including keys, and
record the storage location.

SI. No Item Quantity Location


11

12 Record any defects/shortcomings in the system punch-list.


Verify no dust inside Enclosure /Cabinet / Panel and insulation surfaces
13
are clean.
Verify Instruments & its Accessories /Electrical equipment/Panel
14
externally clean.
COMMENT(S) AND ADDITIONAL INFORMATION

`
COMPLETED BY VERIFIED BY ACCEPTED BY
Designation
Company
Name
Signature
Date