Project No. Project Title Facilities INFORMATION Conductor size System / Sub System no. From To Location Operating Voltage Ref. Drawing nos. INSPECTION / TEST OK N/A P/L No. Documents required: 1 a) Layout drawings b) Pole installation details Verify to ensure that all construction / installation activities have been 2 completed. Confirm the grounding and lightning protection are completed as per 3 specifications and drawings. 4 Pole Check list completed 5 Line sag check list completed 6 Line Joints integrity tested. 7 Verify space heaters, instruments, indication lamps, control switches, Verify no dust inside Enclosure /Cabinet / Panel and insulation surfaces 8 are clean. Verify Instruments & its Accessories /Electrical equipment/Panel 9 externally clean. COMMENT(S) AND ADDITIONAL INFORMATION