TYPE KPMATSU PC-200

ESCAVATOR
1.1 Bucket capacity V 1 m3
1.2 Bucket factor FB 0.9
1.3 Efficiency factor FE 0.67
1.4 Cycle time TC 0.375 min
1.5 Productivity per hour Q 96.48 m3/h
1.6 Coeficient of equipment E10 0.01036484 per/h

Wheel loader
2.1 Bucket Factor FB 1.1 m3
2.2 Capacity V 3
2.3 Eficiency Factor FE 0.83
2.4 Cycle time TC 0.52
a Loading T1 0.05
waktu buang 0.2
waktu kembali 0.2
b Unloading T2 0.07
2.5 Poductivity per hour Q 316.038462
2.6 Coeficient of equipment E15 0.00316417
m km
JARAK 500 0.5
Dump truck (6 m3)
3.1 Capacity V 6
3.2 Efficiency factor FE 0.83
3.3 Avrage loading trip velocity V1 10
3.4 Average unloading trip velocity V2 20
3.5 Cycle time TC 8.23
a Loading time T1 1.5
b unloading time T2 3
c other (loadind waith) T3 3.73
3.6 productivity per hour Q 36.300272
3.7 coeficient of equipment E09 0.027548

Dump truck (20 m3)


3.1 Capacity V
3.2 Efficiency factor FE
3.3 Avrage loading trip velocity V1
3.4 Average unloading trip velocity V2
3.5 Cycle time TC
a Loading time T1
b unloading time T2
c other (loadind waith) T3
3.6 productivity per hour Q
3.7 coeficient of equipment E09
Kekuatan
Motor Grader 12dk
Thick of spreading t 0.3 m
4.1 Spreading length LS 200 m
4.2 efective width b 3.7 m
4.3 efficiency factor FE 0.6
4.4 Average velocity V1 4 km/h
4.5 No of passing n 4
4.6 Cycle time TC 4.20 min
a Time for one passing T1 3 min
b Other (back to start ponit) T2 1.20 min
5.7 Productivity per hour Q 475.714286 m3/h
4.8 Coefficient of equipment E13 0.0021021 coef/hour

Capacity m3 4 m3
Water tank trcuk
5.1 Volume cum 4 m3
5.2 Water required per cum of dense material WC 0.07 m3
5.3 No of passing n 1
5.4 Efficiency factor FE 0.8
5.5 productivity per hour Q 45.71 m3/h
5.6 Coeficient of equipment E23 0.021875 coef/h

Type cat CB54B


Vibratory roller
Thicknes of compaction t 0.2 m
6.1 Average velocity V 1.5 km/h
6.2 Effective width b 1.5 m
6.3 No of passing n 5 nos
6.4 Efficiency factor FE 0.83
6.5 Productivity per hour Q 74.7 m3/h
6.6 Coefficeint of equipment E19 0.01338688 coef/h
Rubber tire roller
type CAT CW34
Thicknes t
7.1 Average velocity V km/h
7.2 Effective width b m
7.3 No of passing n
7.4 Efficiency factor FE
7.5 Productivity per hour Q #DIV/0! m3/h
7.6 Coeficient of equipment E05 #DIV/0! coef/h

Air Compressor
8.1 Air pressure capacity V 324 m2/h
8.2 Efficiency factor FE 0.8
8.3 Q Q 259.2 m2/h
8.4 Coeficient E05 0.00385802 coef/h

Aspalt sprayer
Model CAD 8550
Recarge distance m 2000 m

9.1 Capacity V 850 liter


9.2 Spraying speed SP 6500 l/h
9.3 Recarge speed RP 4000 l/h
9.4 Factor efficiency FE 0.83
9.5 Equipment factor FA 0.65
9.6 Cycle time TC 18.75 min
a Time in loading condition T1 4 min
b Time in Recarge condition T2 2 min
c Recarge time T3 12.75 min
9.7 Productivity per hour Q 1.46744 m3/h
9.8 Coeficient of equipment E05 0.68145887 coef/h
Asphalt finisher
Model Nagato SA 41/40hp
10.1 Spreading speed V 250 m/h
10.2 Thicknes t m
10.3 Width b 7m
10.4 Efficeincy factor FA
10.5 Spraying distance L m
10.6 Cycle time TC 0 min
10.7 Productivity per hour Q #DIV/0! m3/h
10.8 Coeficient of equipment E05 #DIV/0! coef/h

Asphalt mixing plant


11.1 Capacity V 120.3 m3/h
11.2 Efficiency factor FA 0.8
11.3 Productivity per hour Q 96.24 m3/h
11.4 Coeficient E05 0.01039069 coef/h
Dump truck (15 m3)
3.1 Capacity V 3.1
3.2 Efficiency factor FE 3.2
3.3 Avrage loading trip velocity V1 3.3
3.4 Average unloading trip velocity V2 3.4
3.5 Cycle time TC 3.5
a Loading time T1 a
b unloading time T2 b
c other (loadind waith) T3 c
3.6 productivity per hour Q 3.6
3.7 coeficient of equipment E09 3.7

Dump truck (23)


3.1 Capacity V 3.1
3.2 Efficiency factor FE 3.2
3.3 Avrage loading trip velocity V1 3.3
3.4 Average unloading trip velocity V2 3.4
3.5 Cycle time TC 3.5
a Loading time T1 a
b unloading time T2 b
c other (loadind waith) T3 c
3.6 productivity per hour Q 3.6
3.7 coeficient of equipment E09 3.7
Dump truck (18 m3)
Capacity V
Efficiency factor FE
Avrage loading trip velocity V1
Average unloading trip velocity V2
Cycle time TC
Loading time T1
unloading time T2
other (loadind waith) T3
productivity per hour Q
coeficient of equipment E09

Dump truck (33 m3)


Capacity V
Efficiency factor FE
Avrage loading trip velocity V1
Average unloading trip velocity V2
Cycle time TC
Loading time T1
unloading time T2
other (loadind waith) T3
productivity per hour Q
coeficient of equipment E09
Prices of Equipment

No Name Price /Unit Capacity Units Hp Kode


1 Dump-Truck 5.5 TON $ 29,000.00 5.5 ton 120 E42
2 Dum truck truck 10 ton $ 56,000.00 10 ton 190 E44
3 Water tangker 5000 liter $ 29,000.00 5 ton 120 E86
4 Escavator volvo EC 200D $ 115,000.00 1 m3 167 E10
5 Whell loader L956F $ 70,000.00 3 m3 217 E82
6 Bulldozer $ 120,000.00 155 E7
7 Motor Grader $ 152,000.00 >100 hp 135 E61
8 Vibration roller $ 66,000.00 5 to 8 ton 82 E17
9 Three axle tamdem roller 6 to 8 ton 55 E14
10 Tamdem roller RS8200 $ 70,000.00 20 ton 173 E69
11 Pneumatic tyre rollers $ 58,550.00 9 ton 100.5 E71
12 Diesel generator (generator set) $ 5,900.00 135 kva 180 E36
13 Air compressor $ 2,000.00 5000 l/m 60 E30
14 Aspalt sprayer $ 20,000.00 850 liter 4 E3
15 Aspalt finisher $ 110,000.00 10 ton 72.4 E2
16 Aspalt mixing plant $ 220,000.00 50 Ton/h 294 E1
17 Concrete mixing plant (batching plan) $ 75,000.00 60 m3/h 120 E8
18 Stone Crusher $ 89,000.00 50 Ton/h 220 E21
19 Concrete mixer $ 2,000.00 5 m3/h 14 E06
20 Concrete mixer trucks $ 75,000.00 8 m3 158 E49
URAIAN ANALISA ALAT

No Uraian

A URAIAN PERALATAN
Jenis peralatan
Tenaga
Kapasitas
Alat baru :

Alat yang dipakai :

B Biaya pasti perjam kerja


1 Nilai sisa alat =
2
Faktor angsuran modal =

3 Biaya pasti perjam kerja

a. Biaya pengembalian modal =

b. Asuransi dll =

Biaya Pasti perjam =

C. BIAYA OPERASI PERJAM KERJA

1 Bahan bakar = (0,125 Ltr/Hp/Jam) x Pw x Ms

2 Pelumas = (0,02 - 0,01 Ltr/Hp/Jam)xPwxMp

3 Perawatan dan perbaikan =

4 Operator =
5 Pembantu Operator =

Biaya Operasi perjam =

D Total Biaya Sewa alat / jam =

E Lain-lain
1 Tingkat suku bunga
2 Upah operator / sopir
3 Upah Pembantu operator / sopir
4 Bahan bakar bensin
5 Bahan bakar solar
6 Minyak pelumas

No Uraian

A URAIAN PERALATAN
Jenis peralatan
Tenaga
Kapasitas
Alat baru :

Alat yang dipakai :

B Biaya pasti perjam kerja


1 Nilai sisa alat =
2
Faktor angsuran modal =

3 Biaya pasti perjam kerja

a. Biaya pengembalian modal =

b. Asuransi dll =

Biaya Pasti perjam =

C. BIAYA OPERASI PERJAM KERJA

1 Bahan bakar = (0,125 Ltr/Hp/Jam) x Pw x Ms

2 Pelumas = (0,02 - 0,01 Ltr/Hp/Jam)xPwxMp

3 Perawatan dan perbaikan =

4 Operator =
5 Pembantu Operator =
Biaya Operasi perjam =

D Total Biaya Sewa alat / jam =

E Lain-lain
1 Tingkat suku bunga
2 Upah operator / sopir
3 Upah Pembantu operator / sopir
4 Bahan bakar bensin
5 Bahan bakar solar
6 Minyak pelumas

No Uraian

A URAIAN PERALATAN
Jenis peralatan
Tenaga
Kapasitas
Alat baru :

Alat yang dipakai :

B Biaya pasti perjam kerja


1 Nilai sisa alat =
2
Faktor angsuran modal =

3 Biaya pasti perjam kerja

a. Biaya pengembalian modal =

b. Asuransi dll =

Biaya Pasti perjam =

C. BIAYA OPERASI PERJAM KERJA

1 Bahan bakar = (0,125 Ltr/Hp/Jam) x Pw x Ms


2 Pelumas = (0,02 - 0,01 Ltr/Hp/Jam)xPwxMp

3 Perawatan dan perbaikan =

4 Operator =
5 Pembantu Operator =

Biaya Operasi perjam =

D Total Biaya Sewa alat / jam =

E Lain-lain
1 Tingkat suku bunga
2 Upah operator / sopir
3 Upah Pembantu operator / sopir
4 Bahan bakar bensin
5 Bahan bakar solar
6 Minyak pelumas

No Uraian

A URAIAN PERALATAN
Jenis peralatan
Tenaga
Kapasitas
Alat baru :

Alat yang dipakai :

B Biaya pasti perjam kerja


1 Nilai sisa alat =
2
Faktor angsuran modal =

3 Biaya pasti perjam kerja

a. Biaya pengembalian modal =

b. Asuransi dll =
Biaya Pasti perjam =

C. BIAYA OPERASI PERJAM KERJA

1 Bahan bakar = (0,125 Ltr/Hp/Jam) x Pw x Ms

2 Pelumas = (0,02 - 0,01 Ltr/Hp/Jam)xPwxMp

3 Perawatan dan perbaikan =

4 Operator =
5 Pembantu Operator =

Biaya Operasi perjam =

D Total Biaya Sewa alat / jam =

E Lain-lain
1 Tingkat suku bunga
2 Upah operator / sopir
3 Upah Pembantu operator / sopir
4 Bahan bakar bensin
5 Bahan bakar solar
6 Minyak pelumas

No Uraian

A URAIAN PERALATAN
Jenis peralatan
Tenaga
Kapasitas
Alat baru :

Alat yang dipakai :

B Biaya pasti perjam kerja


1 Nilai sisa alat =
2
Faktor angsuran modal =
3 Biaya pasti perjam kerja

a. Biaya pengembalian modal =

b. Asuransi dll =

Biaya Pasti perjam =

C. BIAYA OPERASI PERJAM KERJA

1 Bahan bakar = (0,125 Ltr/Hp/Jam) x Pw x Ms

2 Pelumas = (0,02 - 0,01 Ltr/Hp/Jam)xPwxMp

3 Perawatan dan perbaikan =

4 Operator =
5 Pembantu Operator =

Biaya Operasi perjam =

D Total Biaya Sewa alat / jam =

E Lain-lain
1 Tingkat suku bunga
2 Upah operator / sopir
3 Upah Pembantu operator / sopir
4 Bahan bakar bensin
5 Bahan bakar solar
6 Minyak pelumas

No Uraian

A URAIAN PERALATAN
Jenis peralatan
Tenaga
Kapasitas
Alat baru :

Alat yang dipakai :


B Biaya pasti perjam kerja
1 Nilai sisa alat =
2
Faktor angsuran modal =

3 Biaya pasti perjam kerja

a. Biaya pengembalian modal =

b. Asuransi dll =

Biaya Pasti perjam =

C. BIAYA OPERASI PERJAM KERJA

1 Bahan bakar = (0,125 Ltr/Hp/Jam) x Pw x Ms

2 Pelumas = (0,02 - 0,01 Ltr/Hp/Jam)xPwxMp

3 Perawatan dan perbaikan =

4 Operator =
5 Pembantu Operator =

Biaya Operasi perjam =

D Total Biaya Sewa alat / jam =

E Lain-lain
1 Tingkat suku bunga
2 Upah operator / sopir
3 Upah Pembantu operator / sopir
4 Bahan bakar bensin
5 Bahan bakar solar
6 Minyak pelumas

No Uraian

A URAIAN PERALATAN
Jenis peralatan
Tenaga
Kapasitas
Alat baru :

Alat yang dipakai :

B Biaya pasti perjam kerja


1 Nilai sisa alat =
2
Faktor angsuran modal =

3 Biaya pasti perjam kerja

a. Biaya pengembalian modal =

b. Asuransi dll =

Biaya Pasti perjam =

C. BIAYA OPERASI PERJAM KERJA

1 Bahan bakar = (0,125 Ltr/Hp/Jam) x Pw x Ms

2 Pelumas = (0,02 - 0,01 Ltr/Hp/Jam)xPwxMp

3 Perawatan dan perbaikan =

4 Operator =
5 Pembantu Operator =

Biaya Operasi perjam =

D Total Biaya Sewa alat / jam =

E Lain-lain
1 Tingkat suku bunga
2 Upah operator / sopir
3 Upah Pembantu operator / sopir
4 Bahan bakar bensin
5 Bahan bakar solar
6 Minyak pelumas
No Uraian

A URAIAN PERALATAN
Jenis peralatan
Tenaga
Kapasitas
Alat baru :

Alat yang dipakai :

B Biaya pasti perjam kerja


1 Nilai sisa alat =
2
Faktor angsuran modal =

3 Biaya pasti perjam kerja

a. Biaya pengembalian modal =

b. Asuransi dll =

Biaya Pasti perjam =

C. BIAYA OPERASI PERJAM KERJA

1 Bahan bakar = (0,125 Ltr/Hp/Jam) x Pw x Ms

2 Pelumas = (0,02 - 0,01 Ltr/Hp/Jam)xPwxMp

3 Perawatan dan perbaikan =

4 Operator =
5 Pembantu Operator =

Biaya Operasi perjam =

D Total Biaya Sewa alat / jam =

E Lain-lain
1 Tingkat suku bunga
2 Upah operator / sopir
3 Upah Pembantu operator / sopir
4 Bahan bakar bensin
5 Bahan bakar solar
6 Minyak pelumas

No Uraian

A URAIAN PERALATAN
Jenis peralatan
Tenaga
Kapasitas
Alat baru :

Alat yang dipakai :

B Biaya pasti perjam kerja


1 Nilai sisa alat =
2
Faktor angsuran modal =

3 Biaya pasti perjam kerja

a. Biaya pengembalian modal =

b. Asuransi dll =

Biaya Pasti perjam =

C. BIAYA OPERASI PERJAM KERJA

1 Bahan bakar = (0,125 Ltr/Hp/Jam) x Pw x Ms

2 Pelumas = (0,02 - 0,01 Ltr/Hp/Jam)xPwxMp

3 Perawatan dan perbaikan =

4 Operator =
5 Pembantu Operator =

Biaya Operasi perjam =


D Total Biaya Sewa alat / jam =

E Lain-lain
1 Tingkat suku bunga
2 Upah operator / sopir
3 Upah Pembantu operator / sopir
4 Bahan bakar bensin
5 Bahan bakar solar
6 Minyak pelumas

No Uraian

A URAIAN PERALATAN
Jenis peralatan
Tenaga
Kapasitas
Alat baru :

Alat yang dipakai :

B Biaya pasti perjam kerja


1 Nilai sisa alat =
2
Faktor angsuran modal =

3 Biaya pasti perjam kerja

a. Biaya pengembalian modal =

b. Asuransi dll =

Biaya Pasti perjam =

C. BIAYA OPERASI PERJAM KERJA

1 Bahan bakar = (0,125 Ltr/Hp/Jam) x Pw x Ms

2 Pelumas = (0,02 - 0,01 Ltr/Hp/Jam)xPwxMp

3 Perawatan dan perbaikan =


3 Perawatan dan perbaikan =

4 Operator =
5 Pembantu Operator =

Biaya Operasi perjam =

D Total Biaya Sewa alat / jam =

E Lain-lain
1 Tingkat suku bunga
2 Upah operator / sopir
3 Upah Pembantu operator / sopir
4 Bahan bakar bensin
5 Bahan bakar solar
6 Minyak pelumas

No Uraian

A URAIAN PERALATAN
Jenis peralatan
Tenaga
Kapasitas
Alat baru :

Alat yang dipakai :

B Biaya pasti perjam kerja


1 Nilai sisa alat =
2
Faktor angsuran modal =

3 Biaya pasti perjam kerja

a. Biaya pengembalian modal =

b. Asuransi dll =

Biaya Pasti perjam =

C. BIAYA OPERASI PERJAM KERJA


1 Bahan bakar = (0,125 Ltr/Hp/Jam) x Pw x Ms

2 Pelumas = (0,02 - 0,01 Ltr/Hp/Jam)xPwxMp

3 Perawatan dan perbaikan =

4 Operator =
5 Pembantu Operator =

Biaya Operasi perjam =

D Total Biaya Sewa alat / jam =

E Lain-lain
1 Tingkat suku bunga
2 Upah operator / sopir
3 Upah Pembantu operator / sopir
4 Bahan bakar bensin
5 Bahan bakar solar
6 Minyak pelumas

No Uraian

A URAIAN PERALATAN
Jenis peralatan
Tenaga
Kapasitas
Alat baru :

Alat yang dipakai :

B Biaya pasti perjam kerja


1 Nilai sisa alat =
2
Faktor angsuran modal =

3 Biaya pasti perjam kerja

a. Biaya pengembalian modal =


b. Asuransi dll =

Biaya Pasti perjam =

C. BIAYA OPERASI PERJAM KERJA

1 Bahan bakar = (0,125 Ltr/Hp/Jam) x Pw x Ms

2 Pelumas = (0,02 - 0,01 Ltr/Hp/Jam)xPwxMp

3 Perawatan dan perbaikan =

4 Operator =
5 Pembantu Operator =

Biaya Operasi perjam =

D Total Biaya Sewa alat / jam =

E Lain-lain
1 Tingkat suku bunga
2 Upah operator / sopir
3 Upah Pembantu operator / sopir
4 Bahan bakar bensin
5 Bahan bakar solar
6 Minyak pelumas

No Uraian

A URAIAN PERALATAN
Jenis peralatan
Tenaga
Kapasitas
Alat baru :

Alat yang dipakai :

B Biaya pasti perjam kerja


1 Nilai sisa alat =
2
Faktor angsuran modal =

3 Biaya pasti perjam kerja

a. Biaya pengembalian modal =

b. Asuransi dll =

Biaya Pasti perjam =

C. BIAYA OPERASI PERJAM KERJA

1 Bahan bakar = (0,125 Ltr/Hp/Jam) x Pw x Ms

2 Pelumas = (0,02 - 0,01 Ltr/Hp/Jam)xPwxMp

3 Perawatan dan perbaikan =

4 Operator =
5 Pembantu Operator =

Biaya Operasi perjam =

D Total Biaya Sewa alat / jam =

E Lain-lain
1 Tingkat suku bunga
2 Upah operator / sopir
3 Upah Pembantu operator / sopir
4 Bahan bakar bensin
5 Bahan bakar solar
6 Minyak pelumas

No Uraian

A URAIAN PERALATAN
Jenis peralatan
Tenaga
Kapasitas
Alat baru :
Alat yang dipakai :

B Biaya pasti perjam kerja


1 Nilai sisa alat =
2
Faktor angsuran modal =

3 Biaya pasti perjam kerja

a. Biaya pengembalian modal =

b. Asuransi dll =

Biaya Pasti perjam =

C. BIAYA OPERASI PERJAM KERJA

1 Bahan bakar = (0,125 Ltr/Hp/Jam) x Pw x Ms

2 Pelumas = (0,02 - 0,01 Ltr/Hp/Jam)xPwxMp

3 Perawatan dan perbaikan =

4 Operator =
5 Pembantu Operator =

Biaya Operasi perjam =

D Total Biaya Sewa alat / jam =

E Lain-lain
1 Tingkat suku bunga
2 Upah operator / sopir
3 Upah Pembantu operator / sopir
4 Bahan bakar bensin
5 Bahan bakar solar
6 Minyak pelumas

No Uraian
A URAIAN PERALATAN
Jenis peralatan
Tenaga
Kapasitas
Alat baru :

Alat yang dipakai :

B Biaya pasti perjam kerja


1 Nilai sisa alat =
2
Faktor angsuran modal =

3 Biaya pasti perjam kerja

a. Biaya pengembalian modal =

b. Asuransi dll =

Biaya Pasti perjam =

C. BIAYA OPERASI PERJAM KERJA

1 Bahan bakar = (0,125 Ltr/Hp/Jam) x Pw x Ms

2 Pelumas = (0,02 - 0,01 Ltr/Hp/Jam)xPwxMp

3 Perawatan dan perbaikan =

4 Operator =
5 Pembantu Operator =

Biaya Operasi perjam =

D Total Biaya Sewa alat / jam =

E Lain-lain
1 Tingkat suku bunga
2 Upah operator / sopir
3 Upah Pembantu operator / sopir
4 Bahan bakar bensin
5 Bahan bakar solar
6 Minyak pelumas
No Uraian

A URAIAN PERALATAN
Jenis peralatan
Tenaga
Kapasitas
Alat baru :

Alat yang dipakai :

B Biaya pasti perjam kerja


1 Nilai sisa alat =
2
Faktor angsuran modal =

3 Biaya pasti perjam kerja

a. Biaya pengembalian modal =

b. Asuransi dll =

Biaya Pasti perjam =

C. BIAYA OPERASI PERJAM KERJA

1 Bahan bakar = (0,125 Ltr/Hp/Jam) x Pw x Ms

2 Pelumas = (0,02 - 0,01 Ltr/Hp/Jam)xPwxMp

3 Perawatan dan perbaikan =

4 Operator =
5 Pembantu Operator =

Biaya Operasi perjam =

D Total Biaya Sewa alat / jam =

E Lain-lain
1 Tingkat suku bunga
2 Upah operator / sopir
3 Upah Pembantu operator / sopir
4 Bahan bakar bensin
5 Bahan bakar solar
6 Minyak pelumas

No Uraian

A URAIAN PERALATAN
Jenis peralatan
Tenaga
Kapasitas
Alat baru :

Alat yang dipakai :

B Biaya pasti perjam kerja


1 Nilai sisa alat =
2
Faktor angsuran modal =

3 Biaya pasti perjam kerja

a. Biaya pengembalian modal =

b. Asuransi dll =

Biaya Pasti perjam =

C. BIAYA OPERASI PERJAM KERJA

1 Bahan bakar = (0,125 Ltr/Hp/Jam) x Pw x Ms

2 Pelumas = (0,02 - 0,01 Ltr/Hp/Jam)xPwxMp

3 Perawatan dan perbaikan =

4 Operator =
5 Pembantu Operator =
Biaya Operasi perjam =

D Total Biaya Sewa alat / jam =

E Lain-lain
1 Tingkat suku bunga
2 Upah operator / sopir
3 Upah Pembantu operator / sopir
4 Bahan bakar bensin
5 Bahan bakar solar
6 Minyak pelumas

No Uraian

A URAIAN PERALATAN
Jenis peralatan
Tenaga
Kapasitas
Alat baru :

Alat yang dipakai :

B Biaya pasti perjam kerja


1 Nilai sisa alat =
2
Faktor angsuran modal =

3 Biaya pasti perjam kerja

a. Biaya pengembalian modal =

b. Asuransi dll =

Biaya Pasti perjam =

C. BIAYA OPERASI PERJAM KERJA

1 Bahan bakar = (0,125 Ltr/Hp/Jam) x Pw x Ms


2 Pelumas = (0,02 - 0,01 Ltr/Hp/Jam)xPwxMp

3 Perawatan dan perbaikan =

4 Operator =
5 Pembantu Operator =

Biaya Operasi perjam =

D Total Biaya Sewa alat / jam =

E Lain-lain
1 Tingkat suku bunga
2 Upah operator / sopir
3 Upah Pembantu operator / sopir
4 Bahan bakar bensin
5 Bahan bakar solar
6 Minyak pelumas

No Uraian

A URAIAN PERALATAN
Jenis peralatan
Tenaga
Kapasitas
Alat baru :

Alat yang dipakai :

B Biaya pasti perjam kerja


1 Nilai sisa alat =
2
Faktor angsuran modal =

3 Biaya pasti perjam kerja

a. Biaya pengembalian modal =

b. Asuransi dll =
Biaya Pasti perjam =

C. BIAYA OPERASI PERJAM KERJA

1 Bahan bakar = (0,125 Ltr/Hp/Jam) x Pw x Ms

2 Pelumas = (0,02 - 0,01 Ltr/Hp/Jam)xPwxMp

3 Perawatan dan perbaikan =

4 Operator =
5 Pembantu Operator =

Biaya Operasi perjam =

D Total Biaya Sewa alat / jam =

E Lain-lain
1 Tingkat suku bunga
2 Upah operator / sopir
3 Upah Pembantu operator / sopir
4 Bahan bakar bensin
5 Bahan bakar solar
6 Minyak pelumas
URAIAN ANALISA ALAT

Uraian Kode Koefisien Satuan Keterangan

Dum truck 3 m3 125 ps E42


Pw 120.00 Hp
Cp 4.00 ton
A. Umur Eknomi A 5.00 Tahun
B. Jam Kerja dalam 1 tahun W 2,000.00 Jam
C. Harga alat B 29,000.00 $ US
A. Umur Eknomi A' 5.00 Tahun
B. Jam Kerja dalam 1 tahun W' 2,000.00 Jam
C. Harga alat (*) B' 29,000.00 $ US

10% x B C 2,900.00 $ US
i x (1+i)^ A'
D 0.2400 -
(1+i )^A'-1

( B-C)x D
E 3.13 $ US
W'
0,002 x B
F 0.03 $ US
W'

(E+F) G 3.16 $ US

H1 15.00 $ US

I 9.00 $ US

(12,5% ) x B'
K 1.813 $ US
W'
( 1 Org/Jam) x U1 L 1.10 $ US
( 3 Org/Jam) x U2 M 1.95 $ US

( H+I+K+L+M) P 28.86 $ US

(G + P) T 32.02 $ US
i 20.00 % /Thn
U1 1.10 $US/Jam
U2 0.65 $US/Jam
Mb 1.05 Ltr
Ms 1.00 Ltr
Mp 7.50 Ltr

Uraian Kode Koefisien Satuan Keterangan

Dum truck truck 10 ton E44


Pw 190.00 Hp
Cp 10.00 ton
A. Umur Eknomi A 5.00 Tahun
B. Jam Kerja dalam 1 tahun W 2,000.00 Jam
C. Harga alat B 56,000.00 $ US
A. Umur Eknomi A' 5.00 Tahun
B. Jam Kerja dalam 1 tahun W' 2,000.00 Jam
C. Harga alat (*) B' 56,000.00 $ US

10% x B C 5,600.00 $ US
i x (1+i)^ A'
D 0.2400 -
(1+i )^A'-1

( B-C)x D
E 6.05 $ US
W'
0,002 x B
F 0.06 $ US
W'

(E+F) G 6.10 $ US

H1 23.75 $ US

I 14.25 $ US

(12,5% ) x B'
K 3.500 $ US
W'
( 1 Org/Jam) x U1 L 1.10 $ US
( 3 Org/Jam) x U2 M 1.95 $ US
( H+I+K+L+M) P 44.55 $ US

(G + P) T 50.65 $ US

i 20.00 % /Thn
U1 1.10 $US/Jam
U2 0.65 $US/Jam
Mb 1.05 Ltr
Ms 1.00 Ltr
Mp 7.50 Ltr

Uraian Kode Koefisien Satuan Keterangan

Water tangker 5000 liter E86


Pw 120.00 Hp
Cp 5000 liter
A. Umur Eknomi A 5.00 Tahun
B. Jam Kerja dalam 1 tahun W 2,000.00 Jam
C. Harga alat B 29,000.00 $ US
A. Umur Eknomi A' 5.00 Tahun
B. Jam Kerja dalam 1 tahun W' 2,000.00 Jam
C. Harga alat (*) B' 29,000.00 $ US

10% x B C 2,900.00 $ US
i x (1+i)^ A'
D 0.2400 -
(1+i )^A'-1

( B-C)x D
E 3.13 $ US
W'
0,002 x B
F 0.03 $ US
W'

(E+F) G 3.16 $ US

H1 15.00 $ US
I 9.00 $ US

(12,5% ) x B'
K 1.813 $ US
W'
( 1 Org/Jam) x U1 L 1.10 $ US
( 3 Org/Jam) x U2 M 1.95 $ US

( H+I+K+L+M) P 28.86 $ US

(G + P) T 32.02 $ US

i 20.00 % /Thn
U1 1.10 $US/Jam
U2 0.65 $US/Jam
Mb 1.05 Ltr
Ms 1.00 Ltr
Mp 7.50 Ltr

Uraian Kode Koefisien Satuan Keterangan

Escavator volvo EC 200D E10


Pw 167.00 Hp
Cp 1.00 M3
A. Umur Eknomi A 5.00 Tahun
B. Jam Kerja dalam 1 tahun W 1,600.00 Jam
C. Harga alat B 115,000.00 $ US
A. Umur Eknomi A' 5.00 Tahun
B. Jam Kerja dalam 1 tahun W' 1,600.00 Jam
C. Harga alat (*) B' 115,000.00 $ US

10% x B C 11,500.00 $ US
i x (1+i)^ A'
D 0.2400 -
(1+i )^A'-1

( B-C)x D
E 15.53 $ US
W'
0,002 x B
F 0.14 $ US
W'
(E+F) G 15.67 $ US

H1 20.88 $ US

I 12.53 $ US

(12,5% ) x B'
K 8.984 $ US
W'
( 1 Org/Jam) x U1 L 2.00 $ US
( 3 Org/Jam) x U2 M 1.95 $ US

( H+I+K+L+M) P 46.33 $ US

(G + P) T 62.00 $ US

i 20.00 % /Thn
U1 2.00 $US/Jam
U2 0.65 $US/Jam
Mb 1.05 Ltr
Ms 1.00 Ltr
Mp 7.50 Ltr

Uraian Kode Koefisien Satuan Keterangan

Whell loader L956F E82


Pw 217.00 Hp
Cp 3.00 M3
A. Umur Eknomi A 5.00 Tahun
B. Jam Kerja dalam 1 tahun W 1,600.00 Jam
C. Harga alat B 70,000.00 $ US
A. Umur Eknomi A' 5.00 Tahun
B. Jam Kerja dalam 1 tahun W' 1,600.00 Jam
C. Harga alat (*) B' 70,000.00 $ US

10% x B C 7,000.00 $ US
i x (1+i)^ A'
D 0.2400 -
(1+i )^A'-1
( B-C)x D
E 9.45 $ US
W'
0,002 x B
F 0.09 $ US
W'

(E+F) G 9.54 $ US

H1 27.13 $ US

I 16.28 $ US

(12,5% ) x B'
K 5.469 $ US
W'
( 1 Org/Jam) x U1 L 1.10 $ US
( 3 Org/Jam) x U2 M 1.95 $ US

( H+I+K+L+M) P 51.92 $ US

(G + P) T 61.46 $ US

i 20.00 % /Thn
U1 1.10 $US/Jam
U2 0.65 $US/Jam
Mb 1.05 Ltr
Ms 1.00 Ltr
Mp 7.50 Ltr

Uraian Kode Koefisien Satuan Keterangan

Bulldozer E7
Pw 155.00 Hp
Cp
A. Umur Eknomi A 5.00 Tahun
B. Jam Kerja dalam 1 tahun W 1,600.00 Jam
C. Harga alat B 120,000.00 $ US
A. Umur Eknomi A' 5.00 Tahun
B. Jam Kerja dalam 1 tahun W' 1,600.00 Jam
C. Harga alat (*) B' 120,000.00 $ US

10% x B C 12,000.00 $ US
i x (1+i)^ A'
D 0.2400 -
(1+i )^A'-1

( B-C)x D
E 16.20 $ US
W'
0,002 x B
F 0.15 $ US
W'

(E+F) G 16.35 $ US

H1 19.38 $ US

I 11.63 $ US

(12,5% ) x B'
K 9.375 $ US
W'
( 1 Org/Jam) x U1 L 1.10 $ US
( 3 Org/Jam) x U2 M 1.95 $ US

( H+I+K+L+M) P 43.43 $ US

(G + P) T 59.78 $ US

i 20.00 % /Thn
U1 1.10 $US/Jam
U2 0.65 $US/Jam
Mb 1.05 Ltr
Ms 1.00 Ltr
Mp 7.50 Ltr

Uraian Kode Koefisien Satuan Keterangan

MOTOR GRADER > 100 HP E61


Pw 135.00 Hp
Cp (-) M3
A. Umur Eknomi A 5.00 Tahun
B. Jam Kerja dalam 1 tahun W 1,600.00 Jam
C. Harga alat B 152,000.00 $ US
A. Umur Eknomi A' 5.00 Tahun
B. Jam Kerja dalam 1 tahun W' 1,600.00 Jam
C. Harga alat (*) B' 152,000.00 $ US

10% x B C 15,200.00 $ US
i x (1+i)^ A'
D 0.2400 -
(1+i )^A'-1

( B-C)x D
E 20.52 $ US
W'
0,002 x B
F 0.19 $ US
W'

(E+F) G 20.71 $ US

H1 16.88 $ US

I 10.13 $ US

(12,5% ) x B'
K 11.875 $ US
W'
( 1 Org/Jam) x U1 L 2.00 $ US
( 3 Org/Jam) x U2 M 1.95 $ US

( H+I+K+L+M) P 42.83 $ US

(G + P) T 63.54 $ US

i 20.00 % /Thn
U1 2.00 $US/Jam
U2 0.65 $US/Jam
Mb 1.05 Ltr
Ms 1.00 Ltr
Mp 7.50 Ltr
Uraian Kode Koefisien Satuan Keterangan

Vibration roller E17


Pw 82.00 Hp
Cp 5>8 ton
A. Umur Eknomi A 5.00 Tahun
B. Jam Kerja dalam 1 tahun W 1,600.00 Jam
C. Harga alat B 66,000.00 $ US
A. Umur Eknomi A' 5.00 Tahun
B. Jam Kerja dalam 1 tahun W' 1,600.00 Jam
C. Harga alat (*) B' 66,000.00 $ US

10% x B C 6,600.00 $ US
i x (1+i)^ A'
D 0.2400 -
(1+i )^A'-1

( B-C)x D
E 8.91 $ US
W'
0,002 x B
F 0.08 $ US
W'

(E+F) G 8.99 $ US

H1 10.25 $ US

I 6.15 $ US

(12,5% ) x B'
K 5.156 $ US
W'
( 1 Org/Jam) x U1 L 1.10 $ US
( 3 Org/Jam) x U2 M 1.95 $ US

( H+I+K+L+M) P 24.61 $ US

(G + P) T 33.60 $ US

i 20.00 % /Thn
U1 1.10 $US/Jam
U2 0.65 $US/Jam
Mb 1.05 Ltr
Ms 1.00 Ltr
Mp 7.50 Ltr

Uraian Kode Koefisien Satuan Keterangan

Tamdem roller RS8200 E69


Pw 173.00 Hp
Cp 20.00 TON
A. Umur Eknomi A 10.00 Tahun
B. Jam Kerja dalam 1 tahun W 1,600.00 Jam
C. Harga alat B 70,000.00 $ US
A. Umur Eknomi A' 5.00 Tahun
B. Jam Kerja dalam 1 tahun W' 1,600.00 Jam
C. Harga alat (*) B' 70,000.00 $ US

10% x B C 7,000.00 $ US
i x (1+i)^ A'
D 0.2400 -
(1+i )^A'-1

( B-C)x D
E 9.45 $ US
W'
0,002 x B
F 0.09 $ US
W'

(E+F) G 9.54 $ US

H1 21.63 $ US

I 12.98 $ US

(12,5% ) x B'
K 5.469 $ US
W'
( 1 Org/Jam) x U1 L 2.00 $ US
( 3 Org/Jam) x U2 M 1.95 $ US

( H+I+K+L+M) P 44.02 $ US
(G + P) T 53.56 $ US

i 20.00 % /Thn
U1 2.00 $US/Jam
U2 0.65 $US/Jam
Mb 1.05 Ltr
Ms 1.00 Ltr
Mp 7.50 Ltr

Uraian Kode Koefisien Satuan Keterangan

Pneumatic tyre rollers E71


Pw 100.50 Hp
Cp 9.00 ton
A. Umur Eknomi A 5.00 Tahun
B. Jam Kerja dalam 1 tahun W 1,600.00 Jam
C. Harga alat B 58,550.00 $ US
A. Umur Eknomi A' 5.00 Tahun
B. Jam Kerja dalam 1 tahun W' 1,600.00 Jam
C. Harga alat (*) B' 58,550.00 $ US

10% x B C 5,855.00 $ US
i x (1+i)^ A'
D 0.2400 -
(1+i )^A'-1

( B-C)x D
E 7.90 $ US
W'
0,002 x B
F 0.07 $ US
W'

(E+F) G 7.98 $ US

H1 12.56 $ US

I 7.54 $ US

(12,5% ) x B'
K 4.574 $ US
K 4.574 $ US
W'
( 1 Org/Jam) x U1 L 2.00 $ US
( 3 Org/Jam) x U2 M 1.95 $ US

( H+I+K+L+M) P 28.62 $ US

(G + P) T 36.60 $ US

i 20.00 % /Thn
U1 2.00 $US/Jam
U2 0.65 $US/Jam
Mb 1.05 Ltr
Ms 1.00 Ltr
Mp 7.50 Ltr

Uraian Kode Koefisien Satuan Keterangan

Diesel generator (generator set) E36


Pw 180.00 Hp
Cp 135.00 kva
A. Umur Eknomi A 5.00 Tahun
B. Jam Kerja dalam 1 tahun W 1,600.00 Jam
C. Harga alat B 5,900.00 $ US
A. Umur Eknomi A' 5.00 Tahun
B. Jam Kerja dalam 1 tahun W' 1,600.00 Jam
C. Harga alat (*) B' 5,900.00 $ US

10% x B C 590.00 $ US
i x (1+i)^ A'
D 0.2400 -
(1+i )^A'-1

( B-C)x D
E 0.80 $ US
W'
0,002 x B
F 0.01 $ US
W'

(E+F) G 0.80 $ US
H1 22.50 $ US

I 13.50 $ US

(12,5% ) x B'
K 0.461 $ US
W'
( 1 Org/Jam) x U1 L - $ US
( 3 Org/Jam) x U2 M 1.95 $ US

( H+I+K+L+M) P 38.41 $ US

(G + P) T 39.21 $ US

i 20.00 % /Thn
U1 - $US/Jam
U2 0.65 $US/Jam
Mb 1.05 Ltr
Ms 1.00 Ltr
Mp 7.50 Ltr

Uraian Kode Koefisien Satuan Keterangan

Air compressor E30


Pw 60.00 Hp
Cp 5,000.00 l/m
A. Umur Eknomi A 5.00 Tahun
B. Jam Kerja dalam 1 tahun W 1,600.00 Jam
C. Harga alat B 2,000.00 $ US
A. Umur Eknomi A' 5.00 Tahun
B. Jam Kerja dalam 1 tahun W' 1,600.00 Jam
C. Harga alat (*) B' 2,000.00 $ US

10% x B C 200.00 $ US
i x (1+i)^ A'
D 0.2400 -
(1+i )^A'-1

( B-C)x D
E 0.27 $ US
W'
0,002 x B
F 0.00 $ US
W'

(E+F) G 0.27 $ US

H1 7.50 $ US

I 4.50 $ US

(12,5% ) x B'
K 0.156 $ US
W'
( 1 Org/Jam) x U1 L - $ US
( 3 Org/Jam) x U2 M 1.95 $ US

( H+I+K+L+M) P 14.11 $ US

(G + P) T 14.38 $ US

i 20.00 % /Thn
U1 - $US/Jam
U2 0.65 $US/Jam
Mb 1.05 Ltr
Ms 1.00 Ltr
Mp 7.50 Ltr

Uraian Kode Koefisien Satuan Keterangan

Aspalt sprayer E3
Pw 4.00 Hp
Cp 850.00 LITER
A. Umur Eknomi A 5.00 Tahun
B. Jam Kerja dalam 1 tahun W 1,600.00 Jam
C. Harga alat B 20,000.00 $ US
A. Umur Eknomi A' 5.00 Tahun
B. Jam Kerja dalam 1 tahun W' 1,600.00 Jam
C. Harga alat (*) B' 20,000.00 $ US
10% x B C 2,000.00 $ US
i x (1+i)^ A'
D 0.2400 -
(1+i )^A'-1

( B-C)x D
E 2.70 $ US
W'
0,002 x B
F 0.03 $ US
W'

(E+F) G 2.73 $ US

H1 0.50 $ US

I 0.30 $ US

(12,5% ) x B'
K 1.563 $ US
W'
( 1 Org/Jam) x U1 L - $ US
( 3 Org/Jam) x U2 M 1.95 $ US

( H+I+K+L+M) P 4.31 $ US

(G + P) T 7.04 $ US

i 20.00 % /Thn
U1 - $US/Jam
U2 0.65 $US/Jam
Mb 1.05 Ltr
Ms 1.00 Ltr
Mp 7.50 Ltr

Uraian Kode Koefisien Satuan Keterangan

Aspalt finisher E2
Pw 72.40 Hp
Cp 10.00 TON
A. Umur Eknomi A 5.00 Tahun
B. Jam Kerja dalam 1 tahun W 1,600.00 Jam
C. Harga alat B 110,000.00 $ US
A. Umur Eknomi A' 5.00 Tahun
B. Jam Kerja dalam 1 tahun W' 1,600.00 Jam
C. Harga alat (*) B' 110,000.00 $ US

10% x B C 11,000.00 $ US
i x (1+i)^ A'
D 0.2400 -
(1+i )^A'-1

( B-C)x D
E 14.85 $ US
W'
0,002 x B
F 0.14 $ US
W'

(E+F) G 14.99 $ US

H1 9.05 $ US

I 5.43 $ US

(12,5% ) x B'
K 8.594 $ US
W'
( 1 Org/Jam) x U1 L 2.00 $ US
( 3 Org/Jam) x U2 M 1.95 $ US

( H+I+K+L+M) P 27.02 $ US

(G + P) T 42.01 $ US

i 20.00 % /Thn
U1 2.00 $US/Jam
U2 0.65 $US/Jam
Mb 1.05 Ltr
Ms 1.00 Ltr
Mp 7.50 Ltr

Uraian Kode Koefisien Satuan Keterangan


Aspalt mixing plant E1
Pw 294.00 Hp
Cp 50.00 TON/H
A. Umur Eknomi A 5.00 Tahun
B. Jam Kerja dalam 1 tahun W 1,600.00 Jam
C. Harga alat B 220,000.00 $ US
A. Umur Eknomi A' 5.00 Tahun
B. Jam Kerja dalam 1 tahun W' 1,600.00 Jam
C. Harga alat (*) B' 220,000.00 $ US

10% x B C 22,000.00 $ US
i x (1+i)^ A'
D 0.2400 -
(1+i )^A'-1

( B-C)x D
E 29.70 $ US
W'
0,002 x B
F 0.28 $ US
W'

(E+F) G 29.98 $ US

H1 36.75 $ US

I 22.05 $ US

(12,5% ) x B'
K 17.188 $ US
W'
( 1 Org/Jam) x U1 L 2.00 $ US
( 3 Org/Jam) x U2 M 1.95 $ US

( H+I+K+L+M) P 79.94 $ US

(G + P) T 109.91 $ US

i 20.00 % /Thn
U1 2.00 $US/Jam
U2 0.65 $US/Jam
Mb 1.05 Ltr
Ms 1.00 Ltr
Mp 7.50 Ltr
Uraian Kode Koefisien Satuan Keterangan

Stone Crusher E21


Pw 220.00 Hp
Cp 50.00 TON/H
A. Umur Eknomi A 5.00 Tahun
B. Jam Kerja dalam 1 tahun W 1,600.00 Jam
C. Harga alat B 89,000.00 $ US
A. Umur Eknomi A' 5.00 Tahun
B. Jam Kerja dalam 1 tahun W' 1,600.00 Jam
C. Harga alat (*) B' 89,000.00 $ US

10% x B C 8,900.00 $ US
i x (1+i)^ A'
D 0.2400 -
(1+i )^A'-1

( B-C)x D
E 12.02 $ US
W'
0,002 x B
F 0.11 $ US
W'

(E+F) G 12.13 $ US

H1 27.50 $ US

I 16.50 $ US

(12,5% ) x B'
K 6.953 $ US
W'
( 1 Org/Jam) x U1 L 2.00 $ US
( 3 Org/Jam) x U2 M 1.95 $ US

( H+I+K+L+M) P 54.90 $ US

(G + P) T 67.03 $ US
i 20.00 % /Thn
U1 2.00 $US/Jam
U2 0.65 $US/Jam
Mb 1.05 Ltr
Ms 1.00 Ltr
Mp 7.50 Ltr

Uraian Kode Koefisien Satuan Keterangan

Concrete mixing plant (batching plan) E8


Pw 120.00 Hp
Cp 60.00 m3/h
A. Umur Eknomi A 5.00 Tahun
B. Jam Kerja dalam 1 tahun W 1,600.00 Jam
C. Harga alat B 75,000.00 $ US
A. Umur Eknomi A' 5.00 Tahun
B. Jam Kerja dalam 1 tahun W' 1,600.00 Jam
C. Harga alat (*) B' 75,000.00 $ US

10% x B C 7,500.00 $ US
i x (1+i)^ A'
D 0.2400 -
(1+i )^A'-1

( B-C)x D
E 10.13 $ US
W'
0,002 x B
F 0.09 $ US
W'

(E+F) G 10.22 $ US

H1 15.00 $ US

I 9.00 $ US

(12,5% ) x B'
K 5.859 $ US
W'
( 1 Org/Jam) x U1 L 2.00 $ US
( 3 Org/Jam) x U2 M 1.95 $ US
( H+I+K+L+M) P 33.81 $ US

(G + P) T 44.03 $ US

i 20.00 % /Thn
U1 2.00 $US/Jam
U2 0.65 $US/Jam
Mb 1.05 Ltr
Ms 1.00 Ltr
Mp 7.50 Ltr

Uraian Kode Koefisien Satuan Keterangan

Concrete mixer E06


Pw 14.00 Hp
Cp 5.00 m3/h
A. Umur Eknomi A 5.00 Tahun
B. Jam Kerja dalam 1 tahun W 1,600.00 Jam
C. Harga alat B 2,000.00 $ US
A. Umur Eknomi A' 5.00 Tahun
B. Jam Kerja dalam 1 tahun W' 1,600.00 Jam
C. Harga alat (*) B' 2,000.00 $ US

10% x B C 200.00 $ US
i x (1+i)^ A'
D 0.2400 -
(1+i )^A'-1

( B-C)x D
E 0.27 $ US
W'
0,002 x B
F 0.00 $ US
W'

(E+F) G 0.27 $ US

H1 1.75 $ US
I 1.05 $ US

(12,5% ) x B'
K 0.156 $ US
W'
( 1 Org/Jam) x U1 L - $ US
( 3 Org/Jam) x U2 M 1.95 $ US

( H+I+K+L+M) P 4.91 $ US

(G + P) T 5.18 $ US

i 20.00 % /Thn
U1 - $US/Jam
U2 0.65 $US/Jam
Mb 1.05 Ltr
Ms 1.00 Ltr
Mp 7.50 Ltr

Uraian Kode Koefisien Satuan Keterangan

Concrete mixer trucks E49


Pw 158.00 Hp
Cp 8.00 m3/h
A. Umur Eknomi A 5.00 Tahun
B. Jam Kerja dalam 1 tahun W 1,600.00 Jam
C. Harga alat B 75,000.00 $ US
A. Umur Eknomi A' 5.00 Tahun
B. Jam Kerja dalam 1 tahun W' 1,600.00 Jam
C. Harga alat (*) B' 75,000.00 $ US

10% x B C 7,500.00 $ US
i x (1+i)^ A'
D 0.2400 -
(1+i )^A'-1

( B-C)x D
E 10.13 $ US
W'
0,002 x B
F 0.09 $ US
W'
(E+F) G 10.22 $ US

H1 19.75 $ US

I 11.85 $ US

(12,5% ) x B'
K 5.859 $ US
W'
( 1 Org/Jam) x U1 L 2.00 $ US
( 3 Org/Jam) x U2 M 1.95 $ US

( H+I+K+L+M) P 41.41 $ US

(G + P) T 51.63 $ US

i 20.00 % /Thn
U1 2.00 $US/Jam
U2 0.65 $US/Jam
Mb 1.05 Ltr
Ms 1.00 Ltr
Mp 7.50 Ltr
256.19
HARGA SEWA ALAT PER JAM

No Name HARGA SEWA/JAM


1 Dump-Truck 5.5 TON $ 32.02 224.1645
2 Dum truck truck 10 ton $ 50.65 354.578 250
3 Water tangker 5000 liter $ 32.02 1063.328 1312.5
4 Escavator volvo EC 200D $ 62.00 1667.078
5 Whell loader L956F $ 61.46 6.67
6 Bulldozer $ 59.78 0.167
7 Motor Grader $ 63.54
8 Vibration roller $ 33.60
9 Three axle tamdem roller 0.38
10 Tamdem roller RS8200 $ 53.56
11 Pneumatic tyre rollers $ 36.60
12 Diesel generator (generator set) $ 39.21
13 Air compressor $ 14.38
14 Aspalt sprayer $ 7.04
15 Aspalt finisher $ 42.01
16 Aspalt mixing plant $ 109.91
17 Concrete mixing plant (concrete batching plan) $ 44.03
18 Stone Crusher $ 67.03
19 Concrete mixer 5.18
20 Concrete mixer trucks 51.63
DAFTAR HARGA MATERIAL DISTRIK DILI
AGENCIA DESENVOLVIMENTO NACIONAL

NO URAIAN SATUAN

1 Tanah urug M3 $ 5.00


2 Sirtu M 3
$ 10.00
3 Pasir urug M3 $ 10.00
4 Pasir pasang M 3
$ 21.00
5 Pasir beton M 3
$ 21.00
6 Pasir Plesteran M3 $ 25.00
7 Batu kali M 3
$ 25.00
8 Batu belah 15/20 M 3
$ 28.00
9 Batu belah 20/40 M 3
$ 25.00
10 Batu pecah 2/3 M 3
$ 45.00
11 Batu pecah 3/5 M 3
$ 45.00
12 Batu pecah 5/7 M 3
$ 45.00
13 Kerikil/batu pecah M 3
$ 45.00
14 Batu belah M 3
$ 20.00
15 Semen Portland kg $ 0.16
16 Semen Gresik kg $ 0.16
17 Semen Kupang kg $ 0.16
18 Semen Bosowa kg $ 0.15
19 Semen Yi Sen kg $ 0.14
20 Semen Warna kg $ 0.70
21 Nat kg $ 1.60
Polos (12meter)
1 Besi beton 6mm Btg $ 2.93
2 Besi beton 8mm Btg $ 5.30
3 Besi beton 10mm Btg $ 7.50
4 Besi beton 12mm Btg $ 11.00
5 Besi beton 13mm Btg $ 12.75
6 Besi beton 16mm Btg $ 18.50
7 Besi beton 19mm Btg $ 20.00
8 Besi beton 22mm Btg $ 41.40
9 Besi beton 25mm Btg $ 55.40
10 Besi beton 28mm Btg
11 Besi beton 29mm Btg
12 Besi beton 32mm Btg
13 Besi beton 36mm Btg
14 Besi beton kg $ 1.05
15 besi angker Q 8 " kg $ 1.10
Ulir (12 meter)
1 Besi beton 6mm Btg
2 Besi beton 8mm Btg $ 5.70
3 Besi beton 10mm Btg $ 7.80
4 Besi beton 12mm Btg $ 12.50
5 Besi beton 13mm Btg $ 13.40
6 Besi beton 16mm Btg $ 21.80
7 Besi beton 19mm Btg $ 29.10
8 Besi beton 22mm Btg $ 41.50
9 Besi beton 25mm Btg $ 57.00
10 Besi beton 28mm Btg
11 Besi beton 29mm Btg $ 58.50
12 Besi beton 32mm Btg $ 77.60
13 Besi beton 36mm Btg
14 Harga per kg besi beton ulir Kg
15 Bronjong 1x1x2m Buah $ 35.00
16 Kawat Beton Kg $ 2.10
17 Kawat Ikat Bronjong Kg $ 2.00
18 Bronjong biasa Lbr $ 28.00
19 Kawat Ikat Bronjong Macceferry (25 kg) Kg $ 2.00
20 Geotextile M2 $ 2.00
21 Kawat Duri BTO - 65 / 50 cm Roll $ 28.20
22 Kawat Duri BTO - 65 / 90 cm Roll $ 35.00
23 Wiremesh (BRC) M2 $ 1.80
24 Kawat Berduri Roll $ 23.00
Profil H-Beam 12 meter
1 100x100x6x8 Btg
2 125x125x5x7 Btg
3 125x125x6.5x9 Btg
4 150x150x7x10 Btg $ 231.00
5 150x75x7x12 Btg $ 190.50
6 250x125x6x9x12 Btg
7 200x100x5x7x12 Btg $ 240.50
8 250x125x6x9x12 Btg $ 385.00
9 200x200x8x12 Btg
10 250x250x9x14 Btg $ 529.50
11 300x300x10x15 Btg
12 400x200 Btg $ 750.00
13 250x350x12x19 Btg
14 400x400x13x21 Btg
Profil WF (Wide Flange) 12 meter
1 WF 100x50x5x7 Btg $ 95.50
2 WF 125x60x6x8 Btg
3 WF 148x100x6x9 Btg
4 WF 150x75x5x7 Btg $ 115.50
5 WF 175x90x5x8 Btg
6 WF 197x99x4.5x7 Btg
7 WF 200x100x5.5x8 Btg $ 171.00
8 WF 200x100x5.5x8 Btg
9 WF 248x124x5x8 Btg
10 WF 250x125x6x9 Btg $ 235.50
11 WF 298x149x6x8 Btg
12 WF 300x150x6.5x9 Btg $ 450.50
13 WF 346x174x6x9 Btg
14 WF 350x175x7x11 Btg
15 WF 396X199X7x11 Btg
16 WF 400x200x8x13 Btg
17 WF 446x199x8x12 Btg
18 WF 450x200x9x14 Btg
19 WF 500x200x10x16 Btg
20 WF 588x300x10x16 Btg
21 WF 600x200x11x17 Btg
22 WF 700x300x12x24 Btg
23 WF 800x300x14x26 Btg
Profil C 6 meter
1 50x40x0.5 m' $ 5.00
2 75x40x0.8 m' $ 4.40
3 75x45x15x1.6 Btg
4 75x45x15x2.3 Btg
5 100x50x20x1.6 Btg
6 100x50x20x2.3 Btg $ 25.50
7 100x50x20x3.2 Btg
8 125x50x20x2.3 Btg
9 125x50x20x3.2 Btg
10 150x50x20x2.3 Btg $ 35.50
11 150x50x20x3.2 Btg
12 150x60x20x2.3 Btg
13 150x65x20x3.2 Btg
14 200x75x20x3.2 Btg
15 Canal C 75.35.15.1.5 Btg $ 21.00
16 Steel Light Canal C 75x35x1mm m' $ 3.50
17 Steel Light Canal C 45x35x1mm m' $ 1.50
18 Light Steel Profile m' $ 4.50
19 Screw Ls $ 0.50
20 Dynabolt Ls $ 1.20

Besi Siku 5.8 Meter


1 20x20x3 Btg $ 6.30
2 25x25x3 Btg $ 7.20
3 25x25x5 Btg $ 7.30
4 30x30x3 Btg $ 11.00
5 40x40x3 Btg $ 19.00
6 40x40x4 Btg $ 22.50
7 50x50x5 Btg $ 30.50
8 50x50x6 Btg $ 25.50
9 60x60x5 Btg $ 37.50
10 60x60x6 Btg $ 37.50
11 65x65x6 Btg $ 45.05
12 70x70x8 Btg $ 45.00
13 75x75x6 Btg $ 47.00
14 80x80x6 Btg $ 61.50
15 80x80x6 Btg
16 90x90x6 Btg
17 90x90x7 Btg
18 100x100x10 Btg $ 95.00
19 100x100x7 Btg $ 87.60
20 120x120x10 Btg
21 120x120x8 Btg
22 120x120x11 Btg
23 130x130x12 Btg
24 130x130x9 Btg
25 150x150x12 Btg
26 150x150x15 Btg
27 150x150x16 Btg
28 175x175x12 Btg
28 175x175x19 Btg
29 200x200x15 Btg
30 200x200x20 Btg
31 250x250x25 Btg
32 250x250x35 Btg
Besi Kotak (Hollow) 5.8 Meter
1 12x12x0.9 Btg
2 15x15x0.9 Btg
3 20x20x0.9 Btg $ 9.80
4 25x25x1 Btg $ 13.30
5 30x30x1 Btg $ 16.50
6 40x40x1.2 Btg $ 15.50
7 40x40x1.5 m'
8 50x80x2.3 Btg $ 55.50
9 12x27x0.9 Btg
10 15x30x0.9 Btg
11 20x40x1 Btg $ 20.50
12 20x40x1.5 m'
13 25x50x1.4 Btg
14 20x60x1.4 Btg
15 50x50x1.6 Btg $ 23.85
16 50x50x2.3 Btg
17 60x30x2.3 Btg $ 36.50
18 60x60x3.2 Btg $ 37.00
19 75x45x3.1 Btg
20 75x75x2 Btg $ 54.50
21 75x75x3.2 Btg $ 50.50
22 50x100x3.2 Btg $ 60.50
23 Steel truss Box 60x10x1.5mmx6000mm Kg $ 1.10
24 Steel Purlin 50x20x10x1.5x6000mm Kg $ 1.10
25 Self Drilling Screws 12-14x20mm Kg $ 1.50
26 RHS 100.50.5 Btg $ 60.00
27 Besi Hollow Zincromate 4/3 Btg $ 9.50
28 Besi Hollow Zincromate 4/4 Btg $ 12.50
29 Kawat Las Kg $ 3.00

Besi Bulat 6 Meter (Glavanized Pipe) & Fittings


1 Ø ½" Btg $ 15.35
2 Pipa Galvanize Ø ¾" Btg $ 19.00
3 Pipa Galvanize Ø 1" Btg $ 26.90
4 Pipa Galvanize Ø 1¼" Btg $ 35.65
5 Pipa Galvanize Ø 1½" Btg $ 43.50
6 Pipa Galvanize Ø 2" Btg $ 57.50
7 Pipa Galvanize Ø 3" Btg $ 74.00
8 Pipa Galvanize Ø 4" Btg $ 93.00
9 Pipa Galvanize Ø 6" Btg $ 130.00
9 DN 100mm Btg
10 DN 150mm Btg
11 DN 200mm Btg
12 DN 250mm Btg
13 DN 300mm Btg
14 Socket Ø ½" Bh $ 0.55
15 Socket Ø ¾" Bh $ 0.70
16 Socket 1" Bh $ 1.00
17 Socket Ø 1¼" Bh $ 1.65
18 Socket Ø 2" Bh $ 2.55
19 Socket Ø 3" Bh $ 6.50
20 Socket Ø 4" Bh $ 8.90
21 Knee/Elbow Ø ½" Bh $ 0.70
22 Knee/Elbow Ø ¾" Bh $ 1.00
23 Knee/Elbow 1" Bh $ 1.15
24 Knee/Elbow Ø 1¼" Bh $ 1.75
25 Knee/Elbow Ø 2" Bh $ 3.10
26 Knee/Elbow Ø 3" Bh $ 10.00
27 Knee/Elbow Ø 4" Bh $ 19.00
28 Tee Ø ½" Bh $ 0.95
29 Tee Ø ¾" Bh $ 1.10
30 Tee 1" Bh $ 1.50
31 Tee Ø 1¼" Bh $ 2.00
32 Tee Ø 2" Bh $ 3.85
33 Tee Ø 3" Bh $ 11.00
34 Tee Ø 4" Bh $ 16.46
35 Sock Drat Dalam (SDD) Ø ½" Bh $ 0.50
36 Sock Drat Dalam (SDD) Ø ¾" Bh $ 0.50
37 Sock Drat Dalam (SDD) 1" Bh $ 0.65
38 Sock Drat Luar (SDL) Ø ½" Bh $ 0.25
39 Sock Drat Luar (SDL) Ø ¾" Bh $ 0.30
40 Sock Drat Luar (SDL) 1" Bh $ 0.50
41 Sock Drat Luar (SDL) Ø 1¼" Bh $ 0.55
42 Sock Drat Luar (SDL) Ø 2" Bh $ 0.75
43 Knee Drat Dalam (SDD)/Faucet Elbow Ø ½" Bh
44 Knee Drat Dalam (SDD)/Faucet Elbow Ø ¾" Bh
45 Tee Drat Dalam (SDD)/Faucet Tee Ø ½" Bh
46 Tee Drat Dalam (SDD)/Faucet Tee Ø ¾" Bh
47 Vlok Sock (Reducing Socket ) Ø ¾" to Ø ½" Bh $ 0.95
48 Vlok Sock (Reducing Socket Ø 1" to Ø ¾" Bh $ 1.25
49 Vlok Sock (Reducing Socket Ø 2" to Ø 1" Bh $ 2.55
50 sealtape bh $ 0.35
Besi Plat
1 1.5mm Lbr $ 45.00
2 2mm Lbr $ 64.25
3 3mm Lbr $ 95.00
4 4mm Lbr $ 120.00
5 5mm Lbr $ 153.40
6 6mm Lbr $ 168.00
7 6.5mm Lbr
8 10mm Lbr $ 275.00
9 12mm Lbr $ 330.00
10 Besi strip tebal 5mm. kg $ 1.45
PAKU
1 Paku Tripleks Kg $ 2.10
2 Paku 2cm Kg $ 2.50
3 Paku 4cm Kg $ 2.00
4 Paku 5cm Kg $ 2.00
5 Paku 7cm Kg $ 2.00
6 Paku 10cm Kg $ 2.00
7 Paku 12cm Kg $ 2.00
8 Paku 15cm Kg $ 2.00
9 Paku 20cm Kg $ 2.50
10 Paku Seng Kg $ 2.50
11 Paku Seng ulir Kg $ 3.00
12 Paku 5 - 10 cm Kg $ 2.50
13 Paku pancing 60 x 230 Kg $ 2.50
14 Paku 5-7 cm Kg $ 1.85
BAUT, BESI STRIP & SKRUP
1 Paku Skrup Bh $ 0.25
2 Besi anker Bh
3 Skrup untuk atap Bh $ 0.10
4 Baut Ø 10mm Bh $ 0.50
5 Besi Strip 3cm x 5mm (6 meter) m' $ 1.20
6 Paku skrup 10 cm bh $ 0.30
7 Paku skrup 5 cm Kg $ 3.50
8 Besi profil Kg $ 2.30
9 Paku skrup 2 - 4 cm Bh $ 0.05
10 Besi Tralis m' $ 2.75

KAYU
1 Ijuk M3 $ 5.00
2 Dolken Btg $ 1.50
3 Kayu balok kelas I (4/6) M3 $ 500.00
4 Kayu balok kelas I (5/7) M 3
$ 500.00
5 Kayu balok kelas I (5/10) M 3
$ 500.00
6 Kayu balok kelas I (6/12) M 3
$ 410.00
7 Kayu balok kelas I (8/12) M 3
$ 410.00
8 Kayu balok kelas II (4/6) M 3
$ 380.00
9 Kayu balok kelas II (5/7) M 3
$ 340.00
10 Kayu balok kelas II (5/10) M 3
$ 393.00
11 Kayu balok kelas II (6/12) M 3
$ 430.00
12 Kayu balok kelas II (8/12) M3 $ 430.00
13 Kayu balok kelas III (4/6) M 3
$ 300.00
14 Kayu balok kelas III (5/7) M 3
$ 300.00
15 Kayu balok kelas III (5/10) M3 $ 300.00
16 Kayu balok kelas III (6/12) M 3
$ 300.00
17 Kayu balok kelas III (8/12) M 3
$ 300.00
18 Kayu papan kelas I (jati open) M2 $ 875.00
19 Kayu balok kelas I M 3
$ 410.00
20 Kayu balok kelas II M 3
$ 380.00
21 Kayu balok kelas III M 3
$ 300.00
22 Kayu papan kelas I M3 $ 697.00
23 Kayu papan kelas II M 3
$ 400.00
24 Kayu papan kelas III M3 $ 300.00
25 Kayu Profil 3/4 M $ 1.75
26 Lantai kayu (Gym Floor) M2 $ 50.00
27 Papan nama proyek Bh $ 65.00
28 Kaso 5/7 Btg $ 4.50
29 Kaso-kaso (5x7)cm M3 $ 393.00
30 Reng (2x3)cm M 3
$ 393.00
31 Perancah kayu M 3
$ 300.00
TRIPLEKS & GYPSUM BOARD
1 Tripleks 4mm Lbr $ 7.36
2 Tripleks 6mm Lbr $ 7.47
3 Tripleks 9mm Lbr $ 12.77
4 Tripleks 12mm Lbr $ 16.79
5 Tripleks 15mm Lbr $ 21.94
6 Tripleks 16mm Lbr $ 22.00
7 Tripleks 18mm Lbr $ 23.43
8 Tripleks 20mm Lbr $ 32.00
9 Gypsum Board 6mm Lbr $ 10.73
10 Gypsum Board 9mm Lbr $ 12.00
11 Gypsum Board 12mm Lbr $ 24.00
12 List Gypsum profil C - 7 m' $ 2.50
13 Tepung Gypsum Kg $ 0.60
14 List Kayu profil C-7 m' $ 1.75
15 Asbes Semen M2 $ 4.00
16 Lem Kayu/Vinyl Kg $ 4.00
17 Egg Foun Sheet $ 11.50
18 Calsiboard 9 mm Lbr $ 32.00
19 Plywood 9 mm Lbr $ 12.50
20 Plywood 4 mm Lbr $ 8.00

KERAMIK
1 Keramik 20 x 20 Dos $ 7.00
2 Keramik 30 x 30 Dos $ 7.50
3 Keramik 40 x 40 Dos $ 8.50
4 Keramik 60 x 60 Dos $ 25.00
5 Keramik 10 x 25 Dos $ 6.55
6 Keramik 20 x 25 Dos $ 6.50
7 Keramik 20 x 40 Dos $ 8.50
8 Keramik 30 x 60 Dos $ 29.00
9 Keramik 10 x 10 Dos $ 7.00
10 Keramik 10 x 20 Dos $ 7.00
11 Keramik 10 x 29 Dos $ 7.00
12 Plint 15 x 20 Buah $ 0.38
13 Granit/Marmer 20x20 Dos $ 11.00
14 Granit/Marmer 30x30 Bh $ 2.50
15 Granit/Marmer 40x40 Bh $ 4.50
16 Granit/Marmer 60x40 Dos $ 28.00
17 Granit Essenza 30x60 Dos $ 55.00
18 Granit Essenza 60x60 Dos $ 55.00
19 Karpet M² $ 30.00
20 Ubin abu-abu 20 x 20 cm Bh $ 0.35
21 Plint ubin Bh $ 0.30
22 Lantai kayu (gym floor) M² $ 50.00
23 Lem Lantai Kayu Kg $ 12.50
24 Karpet M² $ 24.00
25 Under layer Lantai kayu M² $ 5.00
26 Batu koral sikat Kg $ 0.90
27 Batu alam M² $ 30.00
29 Keramik Batu Paras Bh $ 30.00

CAT
1 Cat kayu kaleng $ 5.50
2 Cat besi kaleng $ 5.50
3 Cat tembok Dulux Kg $ 4.92
4 Cat tembok Vinilex Kg $ 1.92
5 Cat dasar Kg $ 0.80
6 Cat Penutup Kg $ 2.00
9 Cat tembok Watershield Setara Jotun Kg $ 10.00
10 Cat tembok interior (Acrilic emulsion) Kg $ 5.00
11 Waterproofing (Liquid/coating) Kg $ 5.00
12 Water proofing (Bitumen) Kg $ 5.50
13 Cat meni kayu Kg $ 2.60
14 Cat meni besi Kg $ 2.75
15 Dempul Kg $ 2.00
16 Kuas roll Bh $ 2.50
17 Kuas cat Bh $ 1.50
18 Minyak Cat Kg $ 1.00
19 Politur/Vernis Ltr $ 6.50
20 Plamir kayu kg $ 3.60
21 Plamir tembok kg $ 1.00
22 Minyak Bekisting Ltr $ 3.00
23 Lem Kayu Kg $ 4.00
24 Amplas Lbr $ 0.45
PIPA PVC 4 Meter & Fittings
1 PVC Ø ½" Btg $ 3.00
2 PVC Ø ¾" Btg $ 3.10
3 PVC Ø 1" Btg $ 5.00
4 PVC Ø 1¼" Btg $ 6.60
5 PVC Ø 1½" Btg $ 6.00
6 PVC Ø 2" Btg $ 8.50
7 PVC Ø 3" Btg $ 16.00
8 PVC Ø 4" Btg $ 23.00
9 PVC Ø 5" Btg $ 33.75
10 PVC Ø 6" Btg $ 47.33
9 Socket Ø ½" Bh $ 0.31
10 Socket Ø ¾" Bh $ 0.35
11 Socket 1" Bh $ 0.50
12 Socket Ø 1¼" Bh $ 0.60
13 Socket Ø 1½" Bh $ 0.70
14 Socket Ø 2" Bh $ 0.70
15 Socket Ø 3" Bh $ 1.20
16 Socket Ø 4" Bh $ 1.75
17 Knee/Elbow Ø ½" Bh $ 0.35
18 Knee/Elbow Ø ¾" Bh $ 0.50
19 Knee/Elbow 1" Bh $ 0.50
20 Knee/Elbow Ø 1¼" Bh $ 0.60
21 Knee/Elbow Ø 1½" Bh $ 0.60
22 Knee/Elbow Ø 2" Bh $ 1.00
23 Knee/Elbow Ø 3" Bh $ 1.50
24 Knee/Elbow Ø 4" Bh $ 2.69
25 Tee Ø ½" Bh $ 0.40
26 Tee Ø ¾" Bh $ 0.45
27 Tee 1" Bh $ 0.55
28 Tee Ø 1¼" Bh $ 0.80
29 Tee Ø 1½" Bh $ 0.70
30 Tee Ø 2" Bh $ 0.80
31 Tee Ø 3" Bh $ 1.40
32 Tee Ø 4" Bh $ 2.50
33 Sock Drat Dalam (SDD) Ø ½" Bh $ 0.40
34 Sock Drat Dalam (SDD) Ø ¾" Bh $ 0.41
35 Sock Drat Dalam (SDD) 1" Bh $ 0.50
36 Sock Drat Luar (SDL) Ø ½" Bh $ 0.30
37 Sock Drat Luar (SDL) Ø ¾" Bh $ 0.36
38 Sock Drat Luar (SDL) 1" Bh $ 0.50
39 Sock Drat Luar (SDL) Ø 1¼" Bh $ 0.65
40 Sock Drat Luar (SDL) Ø 2" Bh $ 0.80
41 Knee Drat Dalam (SDD)/Faucet Elbow Ø ½" Bh $ 0.45
42 Knee Drat Dalam (SDD)/Faucet Elbow Ø ¾" Bh $ 0.55
43 Tee Drat Dalam (SDD)/Faucet Tee Ø ½" Bh
44 Tee Drat Dalam (SDD)/Faucet Tee Ø ¾" Bh $ 1.20
45 Vlok Sock (Reducing Socket ) Ø ¾" to Ø ½" Bh $ 0.50
46 Vlok Sock (Reducing Socket Ø 1" to Ø ¾" Bh $ 0.74
47 Vlok Sock (Reducing Socket Ø 2" to Ø 1" Bh $ 1.25
PENUTUP DINDING
1 Batako 40x20x10 Bh $ 0.55
2 Batako 40x20x10 Coloured Bh $ 0.95
3 Batako 20x20x10 Bh $ 0.40
4 Half Full Block 19x19x19 Bh $ 0.86
5 Full Block 39x19x19 Bh $ 1.65
6 Hollow Block 39x14x19 Bh $ 1.50
7 Hollow Block 40x15x20 Bh $ 1.55
8 Half Hollow Block 19x14x19 Bh $ 0.79
9 Bata merah 5 x 11 x 22 cm Bh $ 0.66
10 Porselin 11 x 11 cm Bh $ 0.30
11 Porselin 20 x 20 cm Bh $ 6.50
12 Keramik artistik 10 x 20 cm Bh $ 0.35
13 Batu bata Bh $ 0.80
14 Loster X 20x20cm Bh $ 0.90
15 Loster Ruby 20x20cm Bh $ 0.90
16 Loster Rose 20x20cm Bh $ 1.00
17 Loster Matahari 20x28cm Bh $ 1.00
18 Loster Angle 20x20cm Bh $ 1.00
19 Loster Diamond New 20x20cm Bh $ 0.90
20 Loster segi 1 20x20cm Bh $ 0.90
21 Loster segi 2 20x20cm Bh $ 0.90
22 Loster Sunflower 20x20cm Bh $ 0.80
23 Loster Tulip 20x20cm Bh $ 0.90
24 Loster Sunflower 20x20cm (Kaca) Bh $ 5.00
25 Loster Tulip 20x20cm (Kaca) Bh $ 5.00
26 Loster Coco New 20x20cm Bh $ 0.90
27 Loster Benz 20x20cm Bh $ 0.90
PENUTUP LANTAI (LANDSCAPING)
1 Unipave 22x10x6 Natural Bh $ 0.28
2 Unipave 22x10x8 Natural Bh $ 0.31
3 Top Cover 30x20x6 Natural Bh $ 0.33
4 Top Cover 30x20x8 Natural Bh $ 0.42
5 Hexagon 10x6 Natural Bh $ 0.32
6 Paving Stone 20x10x6 Natural Bh $ 0.28
7 Paving Stone 20x10x8 Natural Bh $ 0.31
8 Kerb Stone 60x35x16 Natural Bh $ 6.25
9 Kerb Stone 40x10x20 Natural Bh $ 2.35
10 Grass Block 54x36 Natural Bh $ 6.50
11 Footstone 23x19x6 Natural Bh $ 0.38
12 Footstone 25x20x6 Natural Bh $ 0.41
13 Triangular Hexstone 10x3x8 Natural Bh $ 0.39
14 Unipave 22x10x6 Coloured Bh $ 0.39
15 Unipave 22x10x8 Coloured Bh $ 0.43
16 Top Cover 30x20x6 Coloured Bh $ 0.89
17 Top Cover 30x20x8 Coloured Bh $ 1.00
18 Hexagon 10x6 Coloured Bh $ 0.53
19 Paving Stone 20x10x6 Coloured Bh $ 0.39
20 Paving Stone 20x10x8 Coloured Bh $ 0.43
21 Footstone 23x19x6 Coloured Bh $ 0.57
22 Footstone 25x20x6 Coloured Bh $ 0.59
23 Triangular Hexstone 10x3x8 Coloured Bh $ 0.59
24 Bunga natural Bh $ 0.30
25 Bunga coloured Bh $ 0.54
26 H block natural Bh $ 2.20
27 H block natural Bh $ 4.20
PENUTUP ATAP
1 Seng BJLS 0.20mm Lbr $ 4.05
2 Seng BJLS 0.30mm Lbr $ 5.50
3 Seng Plat BJLS 0.30mm bubungan M¹ $ 2.70
4 Seng Plat M¹ $ 6.00
5 Seng BJLS 0.42mm Colorbond M' $ 7.50
6 Seng Plat BJLS 0.42mm bubungan M¹ $ 12.25
7 Seng Plat BJLS 0.42mm Talang M¹ $ 5.00
8 Talang PVC 4" M¹ $ 14.50
9 Seng Genteng M²
10 Genteng plentong Bh $ 0.50
11 Bubungan plentong Bh $ 1.50
12 Bubungan Seng genteng M¹
13 Talang Seng genteng M¹
14 Asbes gelombang Lbr $ 6.00
15 Genteng sirap Lbr $ 2.00
16 Alang-alang Lbr $ 3.00
17 Tali Pengikat Roll $ 3.00
18 Aluminium foil "Wofen double side laminated" Roll $ 73.50
19 Aluminium foil "Wofen double side laminated" M2 $ 1.23
PEKERJAAN SANITASI
1 Closet Jongkok Merk INA Bh $ 14.50
2 Closet Duduk Merk INA Bh $ 155.00
3 Wastafel Merk INA Set $ 70.00
4 Closet Jongkok Merk TOTO Bh $ 45.00
5 Closet Jongkok Bh $ 45.00
6 Closet Duduk Merk TOTO CW630 PJ Bh $ 575.00
7 Closet Duduk Bh $ 355.00
8 Closet Duduk Bh $ 355.00
9 Wastafel Lengkap Bh $ 221.00
10 Wastafel Bh $ 221.00
11 Wastafel Merk TOTO L237V3 Bh $ 208.00
12 Bathtub ex Toto FB 170080N Bh $ 225.00
13 Kran air panas dan dingin ex Toto TX 467 SF Bh $ 300.00
14 Bak Cuci stainless steel Bh $ 55.00
15 Water Drine + Accessories Bh $ 15.00
16 Floor Drain ex Toto TX 1 BV1 Bh $ 52.50
17 Floor Drain ex Toto TX 1 AV2 Bh $ 42.25
18 Tissue/Papper Holder ex. Toto AW 360 J Bh $ 50.50
19 Tissue/Papper Holder ex. Toto S 20 Bh $ 36.40
20 Shower Fixed ex. Toto TX 465 SEN Bh $ 126.50
21 Shower Fixed ex. Toto TX 438 SE Bh $ 53.50
22 Tempat Handuk ex. Toto TX 701 AE Bh $ 102.50
23 Tempat Handuk ex. Toto TX 702 ARR Bh $ 51.50
24 Zinc basin untuk dapur Bh $ 78.00
25 Wall Faucet Bh $ 7.75
26 Floor Drain Bh $ 11.00
27 Tissue Holder TS 116R Bh $ 38.97
28 Tissue Holder Bh $ 9.00
29 Kran air biasa Bh $ 5.00
30 Jet Shower Bh $ 17.50
31 Bak mandi fiber glass 220 Ltr Bh $ 225.00
32 Bak mandi fiber glass Bh $ 125.00
33 Bak mandi keramik Bh $ 310.00
34 Urinoir INA Bh $ 114.00
35 Urinoir Lengkap Bh $ 225.00
36 Seal tape Bh $ 0.60
PEKERJAAN PINTU & JENDELA
1 Kusen Pintu + Ventilasi 2x0.7x0.03 Bh $ 77.27
2 Kusen Pintu + Ventilasi 2x0.8x0.03 Bh $ 81.82
3 Kusen Pintu + Ventilasi 2x0.9x0.03 Bh $ 85.45
4 Pintu Panel 2x0.7x0.03 K.M. Aluminium Bh $ 17.00
5 Pintu Panel 2x0.7x0.03 Kayu Bh $ 45.00
6 Pintu Panel 2x0.8x0.03 Bh $ 120.00
7 Pintu Panel 2x0.9x0.03 Aluminium Bh $ 55.00
8 Pintu Panel 2x0.9x0.03 Kayu Bh $ 275.00
9 Kusen Jendela + Ventilasi 1x0.6x0.03 Bh $ 52.73
10 Kusen Jendela + Ventilasi 1.2x0.6x0.03 Bh $ 56.36
11 Kusen Jendela + Ventilasi 1.5x0.6x0.03 Bh $ 61.82
12 Jendela kaca, rangka kayu 1x0.6x0.03 Bh $ 81.82
13 Jendela kaca, rangka kayu 1.2x0.6x0.03 Bh $ 86.36
14 Jendela kaca, rangka kayu 1.5x0.6x0.03 Bh $ 46.36
15 Kusen Jendela NAKO 1.00m Bh $ 50.91
16 Kusen Jendela NAKO 1.20m Bh $ 61.82
17 Jendela NAKO 1.00m komplit Bh $ 81.82
18 Jendela NAKO 1.20m komplit Bh $ 90.91
19 Kusen Jendela kaca Mati M² $ 50.00
20 Jendela kaca Mati M² $ 45.45
21 Kaca 5mmn putih (1.22x1.53cm) M² $ 18.00
24 Kaca 6mm M² $ 9.00
25 Kaca 8mm M² $ 10.00
26 Rangka + kaca 5 mm M² $ 45.00

BAHAN KACA
1 Kaca Bening tebal 3mm M² $ 14.00
2 Kaca Bening tebal 5mm M² $ 16.00
3 Kaca Bening tebal 8mm M² $ 25.00
4 Kaca Bening tebal 10mm M² $ 35.00
5 Kaca Raybend tebal 3mm M² $ 12.00
6 Kaca Raybend tebal 5mm M² $ 16.00
7 Kaca Raybend tebal 8mm M² $ 22.00
8 Kaca Raybend tebal 10mm M² $ 36.00
9 Kaca Raybend tebal 12mm M² $ 45.00
AKSESORIS PEMASANGAN PINTU & JENDELA
1 Engsel Pintu 4" (kuningan modern 4x3) Bh $ 4.50
2 Engsel Jendela (RRT 2" Hinges) Bh $ 3.00
3 Grandel Pintu (Kuningan awa 3") Bh $ 1.75
4 Kait/Hak angin (Kuningan awa 8") set Bh $ 1.20
5 Kunci tanam pintu panel Bh $ 30.00
6 Skrup Kayu (Dry wall 6x1 @ 50 pcs) Bh $ 1.55
7 Lem Kayu (Rajawali, 1kg) Kg $ 4.65
8 Hak angin otomatis (Art flush tower) Bh
9 Kunci tanam biasa Bh $ 16.00
10 Kunci Slot Bh $ 28.00

KABEL, LAMPU & AKSESORIS LISTRIK


1 Kabel NYY 3x2.5mm M¹ $ 1.85
2 Kabel NYY 3x4mm M¹ $ 2.95
3 Pipa Installasi kabel Btg $ 1.30
4 Lampu 20 wat Bh $ 1.20
5 Lampu neon 2 x 38 wat Bh $ 9.50
6 Saklar Tunggal Bh $ 2.00
7 Saklar Ganda Bh $ 2.50
8 Saklar Triple Bh $ 2.90
9 Stop kontak Bh $ 2.00
10 Terminal T box Bh
ALAT BERAT
1 Concrete mixer/molen Jam $ 3.00
2 Bh
3 Bh
4 Bh
5 Bh
6 Bh
TIANG PAGAR
1 Kancil 37cm Bh $ 2.25
2 Lady 52cm Bh $ 2.60
3 Lotus 56cm Bh $ 2.75
4 Putri 60cm Bh $ 3.00
5 Orkid 61cm Bh $ 3.45
6 Crown 62cm Bh $ 3.00
7 Luis 63cm Bh $ 3.00
8 Oscar 64cm Bh $ 3.10
9 Suki 70cm Bh $ 3.25
10 Raja 90cm Bh $ 3.50

GORONG - GORONG
1 RCPC DIA 300mm 2 METER M $ 177.62
2 RCPC DIA 400mm 2 METER M $ 213.85
3 RCPC DIA 500mm 2 METER M $ 259.43
4 RCPC DIA 600mm 2 METER M $ 302.67
6 RCPC DIA 800mm M $ 213.04
7 RCPC DIA 800mm 2 METER M $ 370.46
8 RCPC DIA 900mm 2 METER M $ 425.00
9 RCPC DIA 1000mm M $ 262.05
10 RCPC DIA 1000mm 2 METER M $ 455.77
11 RCPC DIA 1200mm M $ 329.59
12 RCPC DIA 1200mm 2 METER M $ 572.63

SENG GENTENG BERWARNA (Lebar 0.82m)


1 PANJANG 5.6m Lbr $ 51.25
2 PANJANG 4.98m Lbr $ 45.55
3 PANJANG 2.5m Lbr $ 23.50
4 PANJANG 1.3m Lbr $ 12.06
5 PANJANG 0.71m Lbr $ 7.25
6 PANJANG 0.40m Lbr $ 5.25
7 Bubungan genteng Bulat/Barrel Ridge Capping 2.7 m Lbr $ 22.25
8 Bubungan persegi / valley ridge caping 2.2m Lbr $ 21.00
9 Taka Janela/Crimp Curve Zinc 1.2m Lbr $ 17.38

SENG GENTENG BERWARNA (Lebar 0.82m)


1 Tiang Concrete Listrik 9.00m Batang $ 450.00
2 Tiang Concrete Listrik 11.00m Batang $ 550.00
3 Tiang Concrete Listrik 12.00m Batang $ 620.00
DAFTAR UPAH TENAGA KERJA DISTRIK DILI
AGENCIA DESENVOLVIMENTO NACIONAL

NO URAIAN SATUAN HARGA (USD) Or/jam


1 Pekerja 0r/hr 5 $ 0.63
2 Tukang Or/hr 8 $ 1.00
3 Tukang batu Or/hr 8 $ 1.00
4 Tukang kayu Or/hr 8 $ 1.00
5 Tukang besi Or/hr 8 $ 1.00
6 Pemasang Atap Alang-Alang Or/hr 12 $ 1.50
7 Kepala Tukang Or/hr 10 $ 1.25
8 Mandor Or/hr 12 $ 1.50
9 Pekerja Penganyam Or/hr 5 $ 0.63
10 Pengayam Or/hr 8 $ 1.00
11 Mandor Penganyam Or/hr 12 $ 1.50
12 Pekerja Pengisi Or/hr 5 $ 0.63
13 Mandor Pengisi Or/hr 12 $ 1.50
14 Tukang Las Or/hr 8 $ 1.00
15 Tukang cat Or/hr 8 $ 1.00
REAL KOEFICIENT AND

1 M' Pagar sementara dari seng gelombang, tinggi 2m


Bahan Semen Portland Kg.
Bahan Seng gelombang 0.2 Lbr.
Bahan Pasir beton M³
Bahan Koral Beton M³
Bahan Kayu usuk 5/7 M³
Bahan Paku biasa 2"-5" Kg.
Tenaga Pekerja Oh
Kerja
Tenaga Tukang kayu Oh
Kerja
Tenaga Kepala tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
1 M' Pengukuran & pemasangan bouwplank.
Bahan Kayu usuk 5/7 M³
Bahan Paku biasa 2"-5" Kg.
Bahan Kayu papan 3/20 M³
Tenaga Pekerja Oh
Kerja
Tenaga Tukang kayu Oh
Kerja
Tenaga Kepala tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
1 M² Pembuatan gudang semen dan alat-alat.
Bahan Dolken kayu Ø 8-10/4m Btg.
Bahan Kayu M³
Bahan Paku biasa 2"-5" Kg.
Bahan Semen Portland Kg.
Bahan Pasir beton M³
Bahan Koral Beton M³
Bahan Seng gelombang BJLS 28 Lbr.
Tenaga Pekerja Oh
Kerja
Tenaga Tukang kayu Oh
Kerja
Tenaga Kepala tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
KEBUTUHAN UNIT
1M² Pembuatan rumah jaga/konstruksi kayu.
Bahan Dolken kayu Ø 8-10/4m Btg.
Bahan Kayu M³
Bahan Paku biasa 2"-5" Kg.
Bahan Seng gelombang BJLS 28 Lbr.
Tenaga Pekerja Oh
Kerja
Tenaga Tukang kayu Oh
Kerja
Tenaga Kepala tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
1 M² Membersihkan lapangan dan perataan.
Ten Kerja Pekerja Oh
Ten Kerja Mandor Oh
1 Buah Pemasangan papan nama proyek.
Bahan Papan nama proyek Bh
Bahan Usuk 5/7 kayu kelas II M³
Bahan Paku biasa 2"-5" Kg.
Ten Kerja Pekerja Oh
Ten Kerja Mandor Oh
1 M² Pembuatan bedeng buruh
Bahan Dolken kayu Ø 8-10/4m Btg.
Bahan Kayu M³
Bahan Paku biasa 2"-5" Kg.
Bahan Semen Portland Kg.
Bahan Pasir beton M³
Bahan Koral Beton M³
Bahan Seng gelombang BJLS 28 Lbr.
Bahan Plywood 4 mm Lbr.
Tenaga Pekerja Oh
Kerja
Tenaga Tukang kayu Oh
Kerja
Tenaga Kepala tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
KEBUTUHAN UNIT
1 buah pembuatan bak takaran (40x50x20) cm.
Bahan Kayu terentang M³
Bahan Paku biasa 2"-5" Kg.
Bahan Kaso 5/7 - 4m Btg.
Tenaga Tukang kayu Oh
Kerja
Tenaga Mandor Oh
Kerja
1M² Pembuatan jalan sementara
Bahan Batu belah 15/20 M³
Bahan Batu pecah 5/7 M³
Bahan Pasir pasang M³
Tenaga Pekerja Oh
Kerja
Tenaga Mandor Oh
Kerja
1 M³ Bongkaran beton bertulang.
Tenaga Pekerja Oh
Kerja
Tenaga Mandor Oh
Kerja
1 M³ Bongkaran dinding tembok bata merah.
Tenaga Pekerja Oh
Kerja
Tenaga Mandor Oh
Kerja
KEBUTUHAN UNIT
1 M³ Galian tanah biasa sedalam 1 meter.
Tenaga Pekerja Oh
Kerja
Tenaga Mandor Oh
Kerja
1 M³ Galian tanah biasa sedalam 2 meter.
Tenaga Pekerja Oh
Kerja
Tenaga Mandor Oh
Kerja
1 M³ Galian tanah biasa sedalam 3 meter.
Tenaga Pekerja Oh
Kerja
Tenaga Mandor Oh
Kerja
1 M³ Galian tanah keras sedalam 1 meter.
Tenaga Pekerja Oh
Kerja
Tenaga Mandor Oh
Kerja
1 M³ Galian tanah cadas sedalam 1 meter.
Tenaga Pekerja Oh
Kerja
Tenaga Mandor Oh
Kerja
1 M³ Galian tanah lumpur sedalam 1 meter.
Tenaga Pekerja Oh
Kerja
Tenaga Mandor Oh
Kerja
1 M2 Pekerjaan Stripping tebing setinggi 1 meter.
Tenaga Pekerja Oh
Kerja
Tenaga Mandor Oh
Kerja
1 M³ Membuang tanah sejauh 30 meter.
Tenaga Pekerja Oh
Kerja
Tenaga Mandor Oh
Kerja
Menimbun kembali 1 m3 galian
Tenaga Pekerja Oh
Kerja
Tenaga Mandor Oh
Kerja
1 M³ Pemadatan tanah (Per 20 Cm).
Tenaga Pekerja Oh
Kerja
Tenaga Mandor Oh
Kerja
KEBUTUHAN UNIT
1 M³ Timbunan pasir.
Bahan Pasir Urug M³
Tenaga Pekerja Hr.
Kerja
Tenaga Mandor Hr.
Kerja
1 M³ Pemasangan lapisan ijuk tebal 10 Cm
Bahan Ijuk M³
Tenaga Pekerja Oh
Kerja
Tenaga Mandor Oh
Kerja
1 M³ Penimbunan sirtu padat untuk peninggian lantai bangunan.
Bahan Sirtu M³
Tenaga Pekerja Oh
Kerja
Tenaga Mandor Oh
Kerja
KEBUTUHAN UNIT
1 M³ Pasang pondasi batu belah 1 Pc : 3 Ps
Bahan Batu belah 15/20 cm M³
Bahan Semen Portland Kg.
Bahan Pasir pasangan M³
Tenaga Pekerja Oh
Kerja
Tenaga Tukang Batu Oh
Kerja
Tenaga Kepala Tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
1 M³ Pasang pondasi batu belah 1 Pc :4 Ps
Bahan Batu belah 15/20 cm M³
Bahan Semen Portland Kg.
Bahan Pasir pasangan M³
Tenaga Pekerja Oh
Kerja
Tenaga Tukang Batu Oh
Kerja
Tenaga Kepala Tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
1 M³ Pasang pondasi batu belah 1 Pc : 5 Ps
Bahan Batu belah 15/20 cm M³
Bahan Semen Portland Kg.
Bahan Pasir pasangan M³
Tenaga Pekerja Oh
Kerja
Tenaga Tukang Batu Oh
Kerja
Tenaga Kepala Tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
KEBUTUHAN UNIT
1 M³ Pasang pondasi batu kosong
Bahan Batu belah 15/20 cm M³
Bahan Pasir urug M³
Tenaga Pekerja Oh
Kerja
Tenaga Tukang Batu Oh
Kerja
Tenaga Kepala Tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
1 M³ Pasangan pondasi sumuran Ф 1 m.
Bahan Batu belah 15/20 cm M³
Bahan Semen portland Kg
Bahan Pasir beton M³
Bahan Kerikil/koral M³
Tenaga Pekerja Oh
Kerja
Tenaga Tukang Batu Oh
Kerja
Tenaga Kepala Tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
KEBUTUHAN UNIT
Pembesian 10 kg dengan besi polos / ulir
Bahan Besi beton (polos/ulir) Kg.
Bahan Kawat Beton Kg.
Tenaga Pekerja Oh
Kerja
Tenaga Tukang besi Oh
Kerja
Tenaga Kepala Tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
1 M² Pasang bekisting untuk pondasi
Bahan Kayu klas III M³
Bahan Paku biasa 5' - 10' Kg.
Bahan Minyak bekisting Ltr
Tenaga Pekerja Oh
Kerja
Tenaga Tukang kayu Oh
Kerja
Tenaga Kepala Tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
1 M² Pasang bekisting untuk sloof
Bahan Plywood 9mm Lbr.
Bahan Kayu klas III M³
Bahan Paku biasa 5' - 10' Kg.
Bahan Minyak bekisting Ltr
Tenaga Pekerja Oh
Kerja
Tenaga Tukang kayu Oh
Kerja
Tenaga Kepala Tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
1 M² Pasang bekisting untuk kolom
Bahan Kayu klas III M³
Bahan Paku biasa 5' - 12' Kg.
Bahan Minyak bekisting Ltr
Bahan balok kayu klas II M³
Bahan Plywood tebal 9 mm Lbr.
Bahan Dolken kayu 8"-10"/4 m Btg.
Tenaga Pekerja Oh
Kerja
Tenaga Tukang kayu Oh
Kerja
Tenaga Kepala Tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
KEBUTUHAN UNIT
1 M² Pasang bekisting untuk balok
Bahan Kayu klas III M³
Bahan Paku biasa 5' - 12' Kg.
Bahan Minyak bekisting Ltr
Bahan balok kayu klas II M³
Bahan Plywood tebal 9 mm Lbr.
Bahan Dolken kayu 8"-10"/4 m Btg.
Tenaga Pekerja Oh
Kerja
Tenaga Tukang kayu Oh
Kerja
Tenaga Kepala Tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
1 M² Pasang bekisting untuk lantai
Bahan Kayu klas III M³
Bahan Paku biasa 5' - 12' Kg.
Bahan Minyak bekisting Ltr
Bahan balok kayu klas II M³
Bahan Plywood tebal 9 mm Lbr.
Bahan Dolken kayu 8"-10"/4 m Btg.
Tenaga Pekerja Oh
Kerja
Tenaga Tukang kayu Oh
Kerja
Tenaga Kepala Tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
1 M² Pasang bekisting untuk tangga
Bahan Kayu klas III M³
Bahan Paku biasa 5' - 12' Kg.
Bahan Minyak bekisting Ltr
Bahan balok kayu klas II M³
Bahan Plywood tebal 9 mm Lbr.
Bahan Dolken kayu 8"-10"/4 m Btg.
Tenaga Pekerja Oh
Kerja
Tenaga Tukang kayu Oh
Kerja
Tenaga Kepala Tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
KEBUTUHAN UNIT
1 M² Pasang jembatan untuk pengecoran beton
Bahan Kayu klas III (papan) M³
Bahan Paku biasa 5' - 12' Kg.
Bahan Dolken kayu 8"-10"/4 m Btg.
Tenaga Pekerja Oh
Kerja
Tenaga Tukang kayu Oh
Kerja
Tenaga Kepala Tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
1 M³ membuat pondasi beton bertulang K 175 , F'c =14.5 Mpa
(150
BahanKg besi + bekisting). Kayu klas III M³
Bahan Paku biasa 5' - 12' Kg.
Bahan Minyak bekisting Ltr
Bahan Besi beton polos Kg.
Bahan Kawat beton Kg.
Bahan Semen portland Kg.
Bahan Pasir beton M³
Bahan Koral beton M³
Bahan Pekerja Oh
Tenaga Tukang batu Oh
Kerja
Tenaga Tukang kayu Oh
Kerja
Tenaga Tukang besi Oh
Kerja
Tenaga Kepala tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
KEBUTUHAN UNIT
1 M³ membuat sloof beton bertulang K 175 , F'c =14.5 Mpa
(200
BahanKg besi + bekisting). Kayu klas III M³
Bahan Paku biasa 5' - 12' Kg.
Bahan Minyak bekisting Ltr
Bahan Besi beton polos Kg.
Bahan Kawat beton Kg.
Bahan Semen portland Kg.
Bahan Pasir beton M³
Bahan Koral beton M³
Tenaga Pekerja Oh
Kerja
Tenaga Tukang batu Oh
Kerja
Tenaga Tukang kayu Oh
Kerja
Tenaga Tukang besi Oh
Kerja
Tenaga Kepala tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
1 M³ membuat kolom beton bertulang K 175 , F'c =14.5 Mpa
(300
BahanKg besi + bekisting). Kayu klas III M³
Bahan Paku biasa 5' - 12' Kg.
Bahan Minyak bekisting Ltr
Bahan Besi beton polos Kg.
Bahan Kawat beton Kg.
Bahan Semen portland Kg.
Bahan Pasir beton M³
Bahan Koral beton M³
Bahan Kayu klas II balok M3
Bahan Plywood tebal 9 mm Lbr.
Bahan Dolken kayu 8"/4 m Btg.
Tenaga Pekerja Oh
Kerja
Tenaga Tukang batu Oh
Kerja
Tenaga Tukang kayu Oh
Kerja
Tenaga Tukang besi Oh
Kerja
Tenaga Kepala tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
KEBUTUHAN UNIT
1 M³ membuat balok beton bertulang K 175 , F'c =14.5 Mpa (200 Kg besi + bekisting).
Bahan Kayu klas III M³
Bahan Paku biasa 5' - 12' Kg.
Bahan Minyak bekisting Ltr
Bahan Besi beton polos Kg.
Bahan Kawat beton Kg.
Bahan Semen portland Kg.
Bahan Pasir beton M³
Bahan Koral beton M³
Bahan Kayu klas II balok M³
Bahan Plywood tebal 9 mm Lbr.
Bahan Dolken kayu 8"/4 m Btg.
Tenaga Pekerja Oh
Kerja
Tenaga Tukang batu Oh
Kerja
Tenaga Tukang kayu Oh
Kerja
Tenaga Tukang besi Oh
Kerja
Tenaga Kepala tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
1 M³ membuat plat beton bertulang K175, f*c 14.5 Mpa
(150
BahanKg besi + bekisting). Kayu klas III M³
Bahan Paku biasa 5' - 12' Kg.
Bahan Minyak bekisting Ltr
Bahan Besi beton polos Kg.
Bahan Kawat beton Kg.
Bahan Semen portland Kg.
Bahan Pasir beton M³
Bahan Koral beton M³
Bahan Kayu klas II balok M³
Bahan Plywood tebal 9 mm Lbr.
Bahan Dolken kayu 8"/4 m Btg.
Tenaga Pekerja Oh
Kerja
Tenaga Tukang batu Oh
Kerja
Tenaga Tukang kayu Oh
Kerja
Tenaga Tukang besi Oh
Kerja
Tenaga Kepala tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
KEBUTUHAN UNIT
1 M' membuat kolom praktis beton bertulang (11 x 11) cm.
Bahan Kayu klas III M³
Bahan Paku biasa 5' - 12' Kg.
Bahan Besi beton polos Kg.
Bahan Kawat beton Kg.
Bahan Semen portland Kg.
Bahan Pasir beton M³
Bahan Koral beton M³
Tenaga Pekerja Oh
Kerja
Tenaga Tukang batu Oh
Kerja
Tenaga Tukang kayu Oh
Kerja
Tenaga Tukang besi Oh
Kerja
Tenaga Kepala tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
1 M³ membuat beton mutu f*c = 7.4 Mpa ( K 100 )
Bahan Semen Porland Kg.
Bahan Batu koral Beton m3
Bahan Pasir beton m3
Tenaga Pekerja Oh
Kerja
Tenaga Tukang batu Oh
Kerja
Tenaga Kepala Tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
1 M³ membuat beton mutu f*c = 9.8 Mpa ( K 125 )
Bahan Semen Porland Kg.
Bahan Batu koral Beton m3
Bahan Pasir beton m3
Tenaga Pekerja Oh
Kerja
Tenaga Tukang batu Oh
Kerja
Tenaga Kepala Tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
KEBUTUHAN UNIT
1 M³ membuat beton mutu f*c = 12.2 Mpa ( K 150 )
Bahan Semen Porland Kg.
Bahan Batu koral Beton m3
Bahan Pasir beton m3
Tenaga Pekerja Oh
Kerja
Tenaga Tukang batu Oh
Kerja
Tenaga Kepala Tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
1 M³ membuat beton mutu f*c = 14.5 Mpa ( K 175 )
Bahan Semen Porland Kg.
Bahan Batu koral beton m3
Bahan Pasir beton m3
Tenaga Pekerja Oh
Kerja
Tenaga Tukang batu Oh
Kerja
Tenaga Kepala Tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
1 M³ membuat beton mutu f*c = 16.9 Mpa ( K 200 )
Bahan Semen Porland Kg.
Bahan Batu koral Beton m3
Bahan Pasir beton m3
Tenaga Pekerja Oh
Kerja
Tenaga Tukang batu Oh
Kerja
Tenaga Kepala Tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
1 M³ membuat beton mutu f*c = 19.3 Mpa ( K 225 )
Bahan Semen Porland Kg.
Bahan Batu koral Beton m3
Bahan Pasir beton m3
Tenaga Pekerja Oh
Kerja
Tenaga Tukang batu Oh
Kerja
Tenaga Kepala Tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
KEBUTUHAN UNIT
1 M³ membuat beton mutu f*c = 21.7 Mpa ( K 250 )
Bahan Semen Portland Kg.
Bahan Batu koral Beton m3
Bahan Pasir beton m3
Tenaga Pekerja Oh
Kerja
Tenaga Tukang batu Oh
Kerja
Tenaga Kepala Tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
1 M³ membuat beton mutu f*c = 24 Mpa ( K 275 )
Bahan Semen Porland Kg.
Bahan Batu koral Beton m3
Bahan Pasir beton m3
Tenaga Pekerja Oh
Kerja
Tenaga Tukang batu Oh
Kerja
Tenaga Kepala Tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
1 M³ membuat beton mutu f*c = 26.4 Mpa ( K 300 )
Bahan Semen Porland Kg.
Bahan Batu koral Beton m3
Bahan Pasir beton m3
Tenaga Pekerja Oh
Kerja
Tenaga Tukang batu Oh
Kerja
Tenaga Kepala Tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
1 M³ membuat beton mutu f*c = 31.2 Mpa ( K 350)
Bahan Semen Porland Kg.
Bahan Batu koral Beton m3
Bahan Pasir beton m3
Tenaga Pekerja Oh
Kerja
Tenaga Tukang batu Oh
Kerja
Tenaga Kepala Tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
KEBUTUHAN UNIT
1 M³ membuat sloof beton bertulang K 350 ,F*c =31.2 Mpa
(150
BahanKg besi + bekisting). Kayu klas III M³
Bahan Paku biasa 5' - 12' Kg.
Bahan Minyak bekisting Ltr.
Bahan Besi beton polos Kg.
Bahan Kawat beton Kg.
Bahan Semen portland Kg.
Bahan Pasir beton M³
Bahan Koral beton M³
Bahan Plywood tebal 9 mm Lbr
Tenaga Pekerja Oh
Kerja
Tenaga Tukang batu Oh
Kerja
Tenaga Tukang kayu Oh
Kerja
Tenaga Tukang besi Oh
Kerja
Tenaga Kepala tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
1 M³ membuat balok beton bertulang mutu K 350, f*c = 31.2 Mpa
(175Kg
Bahan besi + bekisting). Kayu klas III M³
Bahan Paku biasa 5' - 12' Kg.
Bahan Minyak bekisting Ltr
Bahan Besi beton polos Kg.
Bahan Kawat beton Kg.
Bahan Semen portland Kg.
Bahan Pasir beton M³
Bahan Koral beton M³
Bahan Kayu klas II balok M³
Bahan Plywood tebal 9 mm Lbr.
Bahan Dolken kayu 8"/4 m Btg.
Tenaga Pekerja Oh
Kerja
Tenaga Tukang batu Oh
Kerja
Tenaga Tukang kayu Oh
Kerja
Tenaga Tukang besi Oh
Kerja
Tenaga Kepala tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
KEBUTUHAN UNIT
1 M³ membuat balok beton bertulang mutu K 275, f*c 24 Mpa
(175Kg
Bahan besi + bekisting). Kayu klas III M³
Bahan Paku biasa 5' - 12' Kg.
Bahan Minyak bekisting Ltr
Bahan Besi beton polos Kg.
Bahan Kawat beton Kg.
Bahan Semen portland Kg.
Bahan Pasir beton M³
Bahan Koral beton M³
Bahan Kayu klas II balok M³
Bahan Plywood tebal 9 mm Lbr.
Bahan Dolken kayu 8"/4 m Btg.
Tenaga Pekerja Oh
Kerja
Tenaga Tukang batu Oh
Kerja
Tenaga Tukang kayu Oh
Kerja
Tenaga Tukang besi Oh
Kerja
Tenaga Kepala tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
KEBUTUHAN UNIT
1 kg Pekerjaan kuda-kuda baja (Truss Steel Works)
Bahan Steel truss Box Kg.
Bahan 60x10x1.5mmx600mm
Self Drilling Screws 12-14x20mm buah
Tenaga Pekerja oh
Kerja
Tenaga Tukang oh
Kerja
Tenaga Kepala Tukang oh
Kerja
Tenaga Mandor oh
Kerja
1 kg Purlin Steel Works
Bahan Steel Purlin 50x20x10x1.5x600mm Kg.
Bahan Self Drilling Screws 12-14x20mm buah
Tenaga Pekerja oh
Kerja
Tenaga Tukang oh
Kerja
Tenaga Kepala Tukang Oh
Kerja
Tenaga Mandor oh
Kerja
1 M Pekerjaan rangka atap
Bahan RHS 100.50.5 Btg
Bahan Kawat las Kg.
Tenaga Pekerja Oh
Kerja
Tenaga Tukang Las Oh
Kerja
Tenaga Kepala Tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
1 M Pasang Gording Canal C 75.45.15.1.6
Bahan Canal C 75.35.15.1.5 Btg
Bahan Kawat las Kg.
Tenaga Pekerja Oh
Kerja
Tenaga Tukang Las Oh
Kerja
Tenaga Kepala Tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
KEBUTUHAN UNIT
1 M² Baja Ringan
Bahan Light Steel Profile M
Bahan Screw Ls
Bahan Dynabolt Ls
Tenaga Pekerja Oh
Kerja
Tenaga Tukang Oh
Kerja
Tenaga Kepala Tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
1 M² Pasang atap seng gelombang
Bahan Seng gelombang Lbr.
Bahan Paku Seng Kg.
Tenaga Pekerja Oh
Kerja
Tenaga Tukang kayu Oh
Kerja
Tenaga Kepala tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
1 M' Pasang nok atap sirap
Bahan Seng plat 3" x 6" BJLS 28 Lbr.
Bahan Paku ½" - 1" Kg.
Bahan Paku 2" - 5" Kg.
Bahan Kayu papan 3 cm M³
Tenaga Pekerja Oh
Kerja
Tenaga Tukang kayu Oh
Kerja
Tenaga Kepala tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
1 M² Pasang atap genteng plentong besar
Bahan Genteng plentong Bh
Tenaga Pekerja Oh
Kerja
Tenaga Tukang kayu Oh
Kerja
Tenaga Kepala tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
KEBUTUHAN UNIT
1 M' Pasang bubungan plentong besar
Bahan Bubungan plentong Bh
Bahan Semen portland Kg.
Bahan Pasir pasang M³
Tenaga Pekerja Oh
Kerja
Tenaga Tukang kayu Oh
Kerja
Tenaga Kepala tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
1 M² Pasang atap asbes gelombang 1,80 x 0,92m x 5mm
Bahan Asbes gelombang Lbr.
Bahan Paku pancing 60 x 230 Kg.
Tenaga Pekerja Oh
Kerja
Tenaga Tukang kayu Oh
Kerja
Tenaga Kepala tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
1 M² Pasang atap sirap
Bahan Genteng sirap Bh
Bahan Paku biasa ½" - 1" Kg.
Tenaga Pekerja Oh
Kerja
Tenaga Tukang kayu Oh
Kerja
Tenaga Kepala tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
1 M² Pasang atap alang-alang
Bahan Alang-alang Lbr.
Bahan Tali Pengikat Kg.
Tenaga Pekerja Kg.
Kerja
Tenaga Mandor M³
Kerja
KEBUTUHAN UNIT
1 M² Pasangan Batako 40x20x10 cm, camp speci 1PC : 4Ps
Bahan Batako Bh.
Bahan Semen Portland Kg.
Bahan Pasir pasang M³
Tenaga Pekerja Oh
Kerja
Tenaga Tukang Batu Oh
Kerja
Tenaga Kepala Tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
1 M² Pasangan Paving block 25x20x6cm
Bahan Paving block Bh.
Bahan Semen Portland Kg.
Bahan Pasir pasang M³
Tenaga Pekerja Oh
Kerja
Tenaga Tukang Batu Oh
Kerja
Tenaga Kepala Tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
1 M² Pasangan Paving block 20x10x6 cm
Bahan Paving block Bh.
Bahan Semen Portland Kg.
Bahan Pasir pasang M³
Tenaga Pekerja Oh
Kerja
Tenaga Tukang Batu Oh
Kerja
Tenaga Kepala Tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
1 M³ Pasang Bronjong (2 x 1 x 1 m)
Bahan Batu kali M³
Bahan Bronjong Unit
Tenaga Pekerja Oh
Kerja
Tenaga Mandor Oh
Kerja
KEBUTUHAN UNIT
1 M² Plesteran 1 Pc : 3 Ps, tebal 15 mm
Bahan Semen Portland Kg.
Bahan Pasir pasang M³
Tenaga Pekerja Oh
Kerja
Tenaga Tukang Batu Oh
Kerja
Tenaga Kepala Tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
1 M² Plesteran 1 Pc : 4 Ps, tebal 15 mm
Bahan Semen Portland Kg.
Bahan Pasir pasang M³
Tenaga Pekerja Oh
Kerja
Tenaga Tukang Batu Oh
Kerja
Tenaga Kepala Tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
1 M² Plesteran 1 Pc : 2 Ps, tebal 20 mm
Bahan Semen Portland Kg.
Bahan Pasir pasangan M³
Tenaga Pekerja Oh
Kerja
Tenaga Tukang Batu Oh
Kerja
Tenaga Kepala Tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
1 M² Plesteran 1 Pc : 3 Ps, tebal 20 mm
Bahan Semen Portland Kg.
Bahan Pasir pasang M³
Tenaga Pekerja Oh
Kerja
Tenaga Tukang Batu Oh
Kerja
Tenaga Kepala Tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
1 M² Plesteran 1 Pc : 4 Ps, tebal 20 mm
Bahan Semen Portland Kg.
Bahan Pasir pasang M³
Tenaga Pekerja Oh
Kerja
Tenaga Tukang Batu Oh
Kerja
Tenaga Kepala Tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
KEBUTUHAN UNIT
1 M² Plesteran Ciprat, 1 Pc : 2 Ps
Bahan Semen Portland Kg.
Bahan Pasir pasang M³
Tenaga Pekerja Oh
Kerja
Tenaga Tukang Batu Oh
Kerja
Tenaga Kepala Tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
1 M² Plesteran 1 Pc : 5 Ps, tebal 15 mm
Bahan Semen Portland Kg.
Bahan Pasir pasang M³
Tenaga Pekerja Oh
Kerja
Tenaga Tukang Batu Oh
Kerja
Tenaga Kepala Tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
1 M² Plesteran 1 Pc : 5 Ps, tebal 20 mm
Bahan Semen Portland Kg.
Bahan Pasir pasang M³
Tenaga Pekerja Oh
Kerja
Tenaga Tukang Batu Oh
Kerja
Tenaga Kepala Tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
KEBUTUHAN UNIT
Memasang 1 m2 finishing siar pasangan dinding bata merah
Bahan Semen Portland Kg.
Tenaga Pekerja Oh
Kerja
Tenaga Tukang Batu Oh
Kerja
Tenaga Kepala Tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
Memasang 1 m2 finishing siar pasangan dinding conblock ekspose
Bahan Semen Portland Kg.
Tenaga Pekerja Oh
Kerja
Tenaga Tukang Batu Oh
Kerja
Tenaga Kepala Tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
Memasang 1 m2 finishing siar pasangan batu kali adukan 1 PC : 2 Ps
Bahan Semen Portland Kg.
Bahan Pasir pasang M³
Tenaga Pekerja Oh
Kerja
Tenaga Tukang Batu Oh
Kerja
Tenaga Kepala Tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
1 m2 Acian
Bahan Semen Portland Kg.
Tenaga Pekerja Oh
Kerja
Tenaga Tukang Batu Oh
Kerja
Tenaga Kepala Tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
KEBUTUHAN UNIT
Membuat dan memasang1 M³ kusen pintu dan jendela kayu kelas I
Bahan Balok kayu M³
Bahan Paku 10 cm Kg.
Bahan Lem kayu Kg.
Tenaga Pekerja Oh
Kerja
Tenaga Tukang Kayu Oh
Kerja
Tenaga Kepala Tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
Membuat dan memasang1 M³ kusen pintu dan jendela kayu kelas II/III
Bahan Balok kayu M³
Bahan Paku 10 cm Kg.
Bahan Lem kayu Kg.
Tenaga Pekerja Oh
Kerja
Tenaga Tukang Kayu Oh
Kerja
Tenaga Kepala Tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
Membuat dan memasang1 M² pintu klamp standar, Kayu kelas II
Bahan Papan kayu M³
Bahan Paku 5-7 cm Kg.
Tenaga Pekerja Oh
Kerja
Tenaga Tukang Kayu Oh
Kerja
Tenaga Kepala Tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
Membuat dan memasang1 M² Pintu klamp sederhana, Kayu kelas III
Bahan Papan kayu M³
Bahan Paku 5-7 cm Kg.
Tenaga Pekerja Oh
Kerja
Tenaga Tukang Kayu Oh
Kerja
Tenaga Kepala Tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
KEBUTUHAN UNIT
Membuat dan memasang1 M² daun pintu panel, kayu kelas I/II
Bahan Papan kayu M³
Bahan Lem kayu Kg.
Tenaga Pekerja Oh
Kerja
Tenaga Tukang Kayu Oh
Kerja
Tenaga Kepala Tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
Membuat dan memasang1 M² pintu dan jendela kaca, kayu kelas I/II
Bahan Papan kayu M³
Bahan Lem kayu Kg.
Tenaga Pekerja Oh
Kerja
Tenaga Tukang Kayu Oh
Kerja
Tenaga Kepala Tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
Membuat dan memasang1 M² pintu dan jendela jalusi, kayu kelas I/II
Bahan Papan kayu M³
Bahan Lem kayu Kg.
Tenaga Pekerja Oh
Kerja
Tenaga Tukang Kayu Oh
Kerja
Tenaga Kepala Tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
Membuat 1 M² daun pintu plywood rangkap,rangka tertutup kayu kelas II (lebar sampai 90 cm)
Bahan Papan kayu M³
Bahan Paku 1 - 2,5 cm Kg.
Bahan Lem kayu Kg.
Bahan Plywood 4 mm uk.90x220cm Lbr.
Tenaga Pekerja Oh
Kerja
Tenaga Tukang Kayu Oh
Kerja
Tenaga Kepala Tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
KEBUTUHAN UNIT
Membuat 1 M² daun pintu plywood rangkap, rangka expose kayu kelas I/II
Bahan Papan kayu M³
Bahan Paku 1 - 2,5 cm Kg.
Bahan Lem kayu Kg.
Bahan Plywood 4 mm uk.90x220cm Lbr.
Tenaga Pekerja Oh
Kerja
Tenaga Tukang Kayu Oh
Kerja
Tenaga Kepala Tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
Memasang 1 M² jalusi kusen, kayu kelas I/II
Bahan Papan kayu M³
Bahan Paku 1 - 2,5 cm Kg.
Tenaga Pekerja Oh
Kerja
Tenaga Tukang Kayu Oh
Kerja
Tenaga Kepala Tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
Memasang 1 M² teakwood rangkap, rangka expose kayu klas I
Bahan Papan kayu M³
Bahan Paku 1 - 2,5 cm Kg.
Bahan Lem kayu Kg.
Bahan Teakwood 4 mm uk.90x220cm Lbr.
Tenaga Pekerja Oh
Kerja
Tenaga Tukang Kayu Oh
Kerja
Tenaga Kepala Tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
Memasang 1 M³ Konstruksi kuda-kuda konvensional, kayu klas I, II dan III bentang 6 m'
Bahan Balok kayu M³
Bahan Besi strip tebal 5mm. Kg.
Bahan Paku 12 cm Kg.
Tenaga Pekerja Oh
Kerja
Tenaga Tukang Kayu Oh
Kerja
Tenaga Kepala Tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
KEBUTUHAN UNIT
Memasang 1 M³ Konstruksi kuda-kuda expose, kayu klas I
Bahan Balok kayu M³
Bahan Besi strip tebal 5mm. Kg.
Bahan Paku 12 cm Kg.
Tenaga Pekerja Oh
Kerja
Tenaga Tukang Kayu Oh
Kerja
Tenaga Kepala Tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
Memasang 1 M³ Konstruksi gording,kayu klas II
Bahan Balok kayu M³
Bahan Besi strip tebal 5mm. Kg.
Bahan Paku 12 cm Kg.
Tenaga Pekerja Oh
Kerja
Tenaga Tukang Kayu Oh
Kerja
Tenaga Kepala Tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
Memasang 1 M² rangka atap genteng keramik, kayu kelas II
Bahan Kaso-kaso (5x7)cm M³
Bahan Reng (2x3)cm m3
Bahan Paku 5 dan 10 cm Kg.
Tenaga Pekerja Oh
Kerja
Tenaga Tukang Kayu Oh
Kerja
Tenaga Kepala Tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
Memasang 1 M² rangka atap genteng beton, kayu kelas II
Bahan Kaso-kaso (5x7)cm M³
Bahan Reng (3x4)cm M³
Bahan Paku 5 dan 10 cm Kg.
Tenaga Pekerja Oh
Kerja
Tenaga Tukang Kayu Oh
Kerja
Tenaga Kepala Tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
KEBUTUHAN UNIT
Memasang 1 M² rangka atap sirap, kayu kelas II
Bahan Kayu klas II M³
Bahan Paku 5 sampai 10 cm Kg.
Tenaga Pekerja Oh
Kerja
Tenaga Tukang Kayu Oh
Kerja
Tenaga Kepala Tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
Memasang 1 M² rangka langit-langit, (50x100) cm kayu kelas II/III
Bahan Kaso-kaso (5x7)cm M³
Bahan Paku 7 dan 10 cm Kg.
Tenaga Pekerja Oh
Kerja
Tenaga Tukang Kayu Oh
Kerja
Tenaga Kepala Tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
Memasang 1 M² rangka langit-langit, (60x60) cm kayu kelas II/III
Bahan Kaso-kaso (5x7)cm M³
Bahan Paku 7 dan 10 cm Kg.
Tenaga Pekerja Oh
Kerja
Tenaga Tukang Kayu Oh
Kerja
Tenaga Kepala Tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
Memasang 1M' lisplank uk. 3x20 cm, kayu kelas I/II
Bahan Papan kayu M³
Bahan Paku 5 sampai 7 cm Kg.
Tenaga Pekerja Oh
Kerja
Tenaga Tukang Kayu Oh
Kerja
Tenaga Kepala Tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
Memasang 1M' lisplank uk. 3x30 cm, kayu kelas I/II
Bahan Papan kayu M³
Bahan Paku 5 sampai 7 cm Kg.
Tenaga Pekerja Oh
Kerja
Tenaga Tukang Kayu Oh
Kerja
Tenaga Kepala Tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
KEBUTUHAN UNIT
Memasang 1 M² rangka dinding pemisah, 60x120 cm, kayu kelas II/III
Bahan Balok kayu M³
Bahan Paku 5 sampai 7 cm Kg.
Tenaga Pekerja Oh
Kerja
Tenaga Tukang Kayu Oh
Kerja
Tenaga Kepala Tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
Memasang 1 M² dinding pemisah teakwood rangkap, kayu kelas II
Bahan Balok kayu 6/12 cm M³
Bahan Paku 5 dan 10 cm Kg.
Bahan Teakwood 4 mm uk.120x240cm Lbr.
Bahan Lem kayu Kg.
Tenaga Pekerja Oh
Kerja
Tenaga Tukang Kayu Oh
Kerja
Tenaga Kepala Tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
Memasang 1 M² dinding pemisah plywood rangkap, kayu kelas II
Bahan Balok kayu 6/12 cm M³
Bahan Paku 5 dan 10 cm Kg.
Bahan Plywood 4 mm uk.120x240cm Lbr.
Bahan Lem kayu Kg.
Tenaga Pekerja Oh
Kerja
Tenaga Tukang Kayu Oh
Kerja
Tenaga Kepala Tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
Memasang 1 M² dinding lambriziring papan kayu klas I
Bahan Papan kayu M³
Bahan Paku 5 dan 10 cm Kg.
Bahan Paku skrup 10 cm Kg.
Tenaga Pekerja Oh
Kerja
Tenaga Tukang Kayu Oh
Kerja
Tenaga Kepala Tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
KEBUTUHAN UNIT
Memasang M² dinding lambriziring plywood
Bahan Lambrizing plywood 4 mm ukuran Lbr.
Bahan 120x240
Paku 1 dan cm2.5 cm Kg.
Tenaga Pekerja Oh
Kerja
Tenaga Tukang Kayu Oh
Kerja
Tenaga Kepala Tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
KEBUTUHAN UNIT
1 M² pasang lantai ubin pc abu-abu 20 x20 cm
Bahan Ubin abu-abu 20 x 20 cm Bh
Bahan Semen portland Kg.
Bahan Pasir pasang M³
Bahan Colour cement Kg.
Tenaga Pekerja Oh
Kerja
Tenaga Tukang batu Oh
Kerja
Tenaga Kepala tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
1 M' pasang plint ubin pc abu-abu 15 x20 cm
Bahan Plint ubin Bh
Bahan Semen portland Kg.
Bahan Pasir pasang M³
Tenaga Pekerja Oh
Kerja
Tenaga Tukang batu Oh
Kerja
Tenaga Kepala tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
1 M² Pasang lantai kayu
Bahan Lantai kayu (gym floor) M²
Bahan Lem Kg.
Tenaga Pekerja Oh
Kerja
Tenaga Tukang kayu Oh
Kerja
Tenaga Kepala tukang kayu Oh
Kerja
Tenaga Mandor Oh
Kerja
1 M² Pasang lantai karpet
Bahan Karpet M²
Bahan Lem Kg.
Tenaga Pekerja Oh
Kerja
Tenaga Tukang Kayu Oh
Kerja
Tenaga Kepala tukang kayu Oh
Kerja
Tenaga Mandor Oh
Kerja
KEBUTUHAN UNIT
1 M² Pasang batu koral sikat campuran 1 : 2
Bahan Batu koral sikat Kg.
Bahan Semen portland Kg.
Bahan Pasir pasang M³
Tenaga Pekerja Oh
Kerja
Tenaga Tukang batu Oh
Kerja
Tenaga Kepala tukang batu Oh
Kerja
Tenaga Mandor Oh
Kerja
Memasang 1 m plint kayu kelas II ukuran (2 x 10) cm
Bahan Papan kayu klas II M³
Bahan Paku skrup 5 cm Kg.
Tenaga Pekerja Oh
Kerja
Tenaga Tukang batu Oh
Kerja
Tenaga Kepala tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
Memasang 1 m2 lantai keramik ukuran 30 x 30 cm
Bahan Keramik Bh
Bahan Semen portland Kg.
Bahan Pasir pasang M³
Bahan Semen warna Kg.
Tenaga Pekerja Oh
Kerja
Tenaga Tukang batu Oh
Kerja
Tenaga Kepala tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
Memasang 1 m2 lantai keramik ukuran 40 x 40 cm
Bahan Keramik Bh
Bahan Semen portland Kg.
Bahan Pasir pasang M³
Bahan Semen warna Kg.
Tenaga Pekerja Oh
Kerja
Tenaga Tukang batu Oh
Kerja
Tenaga Kepala tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
KEBUTUHAN UNIT
Memasang 1 m2 lantai keramik ukuran 60 x 60 cm
Bahan Keramik Bh
Bahan Semen portland Kg.
Bahan Pasir pasang M³
Bahan Semen warna Kg.
Tenaga Pekerja Oh
Kerja
Tenaga Tukang batu Oh
Kerja
Tenaga Kepala tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
Memasang 1 m2 batu alam
Bahan Batu alam M²
Bahan Semen portland Kg.
Bahan Pasir pasang M³
Tenaga Pekerja Oh
Kerja
Tenaga Tukang batu Oh
Kerja
Tenaga Kepala tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
KEBUTUHAN UNIT
Memasang 1 M² langit-langit asbes semen 4/5/6mm
Bahan Plat asbes M²
Bahan Paku biasa ½" - 1" Kg.
Tenaga Pekerja Oh
Kerja
Tenaga Tukang kayu Oh
Kerja
Tenaga Kepala tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
Memasang 1 M² langit-langit tripleks
Bahan Tripleks Lbr.
Bahan Paku biasa ½" - 1" Kg.
Tenaga Pekerja Oh
Kerja
Tenaga Tukang kayu Oh
Kerja
Tenaga Kepala tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
Memasang 1 M² langit-langit lambriziring kayu 9cm
Bahan Kayu papan M³
Bahan Paku biasa ½" - 1" Kg.
Tenaga Pekerja Oh
Kerja
Tenaga Tukang kayu Oh
Kerja
Tenaga Kepala tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
Memasang 1 M' list langit-langit kayu profil
Bahan Lis kayu profil M'
Bahan Paku lis Kg.
Tenaga Pekerja Oh
Kerja
Tenaga Tukang kayu Oh
Kerja
Tenaga Kepala tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
Memasang 1 M² langit-langit gypsum board ukuran (1200x2400x9)mm
Bahan Gypsum board Lbr.
Bahan Paku skrup Kg.
Tenaga Pekerja Oh
Kerja
Tenaga Tukang kayu Oh
Kerja
Tenaga Kepala tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
KEBUTUHAN UNIT
Memasang 1 kg besi profil
Bahan Besi profil Kg
Bahan Meni Besi kg
Tenaga Pekerja Oh
Kerja
Tenaga Tukang besi Oh
Kerja
Tenaga Kepala tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
Memasang 1 m2 jendela nako & tralis
Bahan Rangka + kaca 5 mm M2
Bahan Paku skrup 1 cm – 2,5 cm Bh
Bahan Besi strip M'
Tenaga Pekerja Oh
Kerja
Tenaga Tukang besi Oh
Kerja
Tenaga Kepala tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
Memasang 1 m talang datar/ jurai seng bjls 28 lebar 90 cm
Bahan Seng plat M'
Bahan Paku 1 cm – 2,5 cm kg
Bahan Papan kayu klas II atau III M3
Tenaga Pekerja Oh
Kerja
Tenaga Tukang besi Oh
Kerja
Tenaga Kepala tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
Memasang 1 m talang ½ lingkaran D-15 cm, seng plat bjls 30
Bahan Seng plat M'
Bahan Paku 1 cm – 2,5 cm kg
Bahan Papan kayu klas II atau III M3
Tenaga Pekerja Oh
Kerja
Tenaga Tukang besi Oh
Kerja
Tenaga Kepala tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
KEBUTUHAN UNIT
1 Bh. pasang kunci tanam biasa
Bahan Kunci tanam biasa Bh
Tenaga Pekerja Oh
Kerja
Tenaga Tukang besi Oh
Kerja
Tenaga Kepala tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
1 Bh. pasang engsel pintu
Bahan Engsel pintu Bh
Tenaga Pekerja Oh
Kerja
Tenaga Tukang besi Oh
Kerja
Tenaga Kepala tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
1 Bh. pasang engsel jendela kupu-kupu
Bahan Engsel jendela Bh
Tenaga Pekerja Oh
Kerja
Tenaga Tukang besi Oh
Kerja
Tenaga Kepala tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
1 Bh. pasang kait angin
Bahan Kait angin Bh
Tenaga Pekerja Oh
Kerja
Tenaga Tukang besi Oh
Kerja
Tenaga Kepala tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
1 Bh. pasang kunci slot
Bahan Kunci slot Bh
Tenaga Pekerja Oh
Kerja
Tenaga Tukang besi Oh
Kerja
Tenaga Kepala tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
1 M² pasang kaca, tebal 3 - 5 mm
Bahan Kaca Bh
Tenaga Pekerja Oh
Kerja
Tenaga Tukang besi Oh
Kerja
Tenaga Kepala tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
KEBUTUHAN UNIT
Memasang 1 buah kloset duduk/monoblok lengkap
Bahan Kloset duduk lengkap Bh.
Tenaga Pekerja Oh
Kerja
Tenaga Tukang batu Oh
Kerja
Tenaga Kepala tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
Memasang 1 buah kloset jongkok porselen
Bahan Kloset jongkok porselen Bh.
Bahan Semen portland Kg.
Bahan Pasir pasang M³
Tenaga Pekerja Oh
Kerja
Tenaga Tukang batu Oh
Kerja
Tenaga Kepala tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
Memasang 1 buah urinoir
Bahan Urinoir lengkap Bh.
Tenaga Pekerja Oh
Kerja
Tenaga Tukang batu Oh
Kerja
Tenaga Kepala tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
Memasang 1 buah wastafel
Bahan Wastafel lengkap Bh.
Tenaga Pekerja Oh
Kerja
Tenaga Tukang batu Oh
Kerja
Tenaga Kepala tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
KEBUTUHAN UNIT
Memasang 1 buah bak mandi Fibreglass, volume 220 ltr
Bahan Bak fibreglass 220 ltr lengkap Bh.
Tenaga Pekerja Oh
Kerja
Tenaga Tukang batu Oh
Kerja
Tenaga Kepala tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
Pasang 1 bh bak kontrol pasangan batu bata 30 x 30/T35 cm
Bahan Batu bata Bh
Bahan Semen portland Kg.
Bahan Pasir pasang M³
Bahan Koral beton M³
Bahan Besi beton Kg.
Bahan Pasir beton M³
Tenaga Pekerja Oh
Kerja
Tenaga Tukang batu Oh
Kerja
Tenaga Kepala tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
Memasang 1 M' pipa galvanis Ø ½" - 1"
Bahan Pipa galvanis M'
Bahan Asesories (% dari harga pipa) %
Tenaga Pekerja Oh
Kerja
Tenaga Tukang batu Oh
Kerja
Tenaga Kepala tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
Memasang 1 M' pipa galvanis Ø 1½" - 3"
Bahan Pipa galvanis M'
Asesories (% dari harga pipa) %
Tenaga Pekerja Oh
Kerja
Tenaga Tukang batu Oh
Kerja
Tenaga Kepala tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
KEBUTUHAN UNIT
Memasang 1 M' pipa PVC tipe AW Ø ½" - 1½"
Bahan Pipa PVC M'
Bahan Asesories (% dari harga pipa) %
Tenaga Pekerja Oh
Kerja
Tenaga Tukang batu Oh
Kerja
Tenaga Kepala tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
KEBUTUHAN UNIT
Memasang 1 M' pipa PVC tipe AW Ø 2"
Bahan Pipa PVC M'
Bahan Asesories (% dari harga pipa) %
Tenaga Pekerja Oh
Kerja
Tenaga Tukang batu Oh
Kerja
Tenaga Kepala tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
Memasang 1 M' pipa PVC tipe AW Ø 3"-4"
Bahan Pipa PVC M'
Tenaga Pekerja Oh
Kerja
Tenaga Tukang batu Oh
Kerja
Tenaga Kepala tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
Memasang 1 buah kran Ø ½" atau ¾"
Bahan Kran air Bh
Bahan Seal tape Bh
Tenaga Pekerja Oh
Kerja
Tenaga Tukang batu Oh
Kerja
Tenaga Kepala tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
KEBUTUHAN UNIT
1 M² pengecatan bidang kayu baru (1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup).
Bahan Cat meni Kg.
Bahan Dempul/plamir Kg.
Bahan Cat dasar Kg.
Bahan Cat penutup 2 x Kg.
Bahan Kuas bh
Tenaga Pekerja Oh
Kerja
Tenaga Tukang cat Oh
Kerja
Tenaga Kepala tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
1 M² pengecatan bidang kayu dengan vernis
Bahan Vernis Kg.
Bahan Dempul/plamir Kg.
Bahan Amplas Lbr.
Bahan Kuas Bh.
Tenaga Pekerja Oh
Kerja
Tenaga Tukang cat Oh
Kerja
Tenaga Kepala tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
1 M² pengecatan tembok baru (1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup).
Bahan Plamir Kg.
Bahan Cat dasar Kg.
Bahan Cat penutup 2 x Kg.
Bahan Kuas bh
Tenaga Pekerja Oh
Kerja
Tenaga Tukang cat Oh
Kerja
Tenaga Kepala tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
KEBUTUHAN UNIT
1 M² pengecatan tembok lama (1 lapis cat dasar, 2 lapis cat penutup).
Bahan Cat dasar Kg.
Bahan Cat penutup 2 x Kg.
Bahan Kuas bh
Tenaga Pekerja Oh
Kerja
Tenaga Tukang cat Oh
Kerja
Tenaga Kepala tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
1 M² pengecatan permukaan baja dengan meni besi
Bahan Meni besi/cat besi Kg.
Bahan Minyak cat ltr
Bahan Kuas Bh.
Tenaga Pekerja Oh
Kerja
Tenaga Tukang cat Oh
Kerja
Tenaga Kepala tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
1 M² pengecatan permukaan baja, 1 lapis dengan meni besi dan perancah.
Bahan Meni Besi Kg.
Bahan Kuas Bh.
Bahan Perancah kayu M³
Tenaga Pekerja Oh
Kerja
Tenaga Tukang cat Oh
Kerja
Tenaga Kepala tukang Oh
Kerja
Tenaga Mandor Oh
Kerja
2.5000
1.2158
0.005
0.009
0.041
0.0829
0.2495
0.2858
0.02
0.02

0.0177
0.02
0.007
0.1
0.1
0.01
0.005

1.7
0.2074
0.3
10.5
0.03
0.05
1.5306
1
2
0.2
0.05
KOEFISIEN

3.05
0.2807
0.7117
1.709
1.0167
1.525
0.1527
0.051
0.1
0.05

1
0.0235
0.1665
0.2503
0.0443

1.25
0.186
0.3
18
0.03
0.05
1.5401
0.5883
1
2
0.2
0.05
KOEFISIEN

0.037
0.082
1.025
0.3075
0.002

0.15
0.09
0.01
1
0.05

6.667
0.333

6.667
0.033
KOEFISIEN

0.67
0.032
0.75
0.047

0.89
0.0685

0.95
0.053

1.5
0.06

0.9163
0.07

0.423
0.026

0.33
0.0126

0.2142
0.0143

0.5
0.05
KOEFISIEN

1.2
0.3023
0.0127

2.7577
0.15
0.015

1.2
0.3046
0.0379
KOEFISIEN

1.149
202
0.485
1.5
0.6
0.0905
0.0973

1.2
163
0.5348
1.8313
0.8404
0.0991
0.075

1.2
136
0.544
1.7141
0.713
0.1095
0.1919
KOEFISIEN

1.2
0.3033
0.78
0.39
0.0579
0.0579

0.45
213.4
0.3837
0.567
2.2353
0.458
0.0457
0.09
KOEFISIEN

10.5
0.15
0.0949
0.0757
0.0109
0.0223
0.0329
0.1586
0.0168
0.52
0.26
0.026
0.026

0.35
0.045
0.3
0.0256
0.52
0.26
0.026
0.026

0.04
0.4
0.0555
0.015
0.35
2
0.66
0.33
0.033
0.033
KOEFISIEN

0.04
0.4
0.0536
0.036
0.35
2
0.66
0.33
0.033
0.033

0.04
0.4
0.0536
0.036
0.35
2
0.66
0.33
0.033
0.033

0.03
0.4
0.15
0.0183
0.3455
2
0.66
0.33
0.033
0.0161
KOEFISIEN

0.026
0.6
0.5
0.15
0.05
0.0051
0.008

0.2
1.5
0.0667
150
2.25
323
0.52
0.78
4.2108
0.3093
1.0842
1.05
0.245
0.1922
KOEFISIEN

0.27
2
0.1
200
3
323
0.52
0.78
4.9152
0.3093
1.56
1.4
0.327
0.2013

0.4
4
2
300
4.5
323
0.52
0.78
0.15
3.5
16
7.175
0.3093
2.792
2.1
0.4883
0.2747
KOEFISIEN

0.3200
3.2000
2
200
3
323
0.52
0.78
0.15
3.5
16
7.175
0.3093
1.65
1.4
0.4883
0.2747

0.135
1.3497
0.675
157.5
2.25
323
0.52
0.78
0.0505
2.181
16
6.769
0.3093
1.3
1.05
0.265
0.265
KOEFISIEN

0.0025
0.0452
3
0.45
4.175
0.0063
0.0093
0.1588
0.0473
0.0113
0.0118
0.0108
0.01

254
0.8197
0.62
1.65
0.289
0.029
0.02
284.55
0.8273
0.6175
1.682
0.2805
0.028
0.02
KOEFISIEN

315.7
0.818
0.5845
1.6915
0.282
0.0285
0.02

323
0.78
0.52
1.65
0.2675
0.0267
0.02

325
0.81
0.54
1.65
0.275
0.038
0.03

377.02
0.82
0.5
1.6694
0.305
0.0456
0.04
KOEFISIEN

384
0.7368
0.4697
1.65
0.275
0.0458
0.04

412
0.78
0.556
1.682
0.3125
0.05
0.05

413
0.7206
0.4769
1.65
0.275
0.0459
0.04

464.35
0.78
0.4867
2.1
0.35
0.0717
0.07
KOEFISIEN

0.277
2.05
0.615
150
2.25
464.35
0.4867
0.78
2.916
4.346
0.282
1.3325
1.0765
0.27
0.2
0.328
3.28
1.64
175
2.625
464.35
0.4867
0.78
0.15
4
16
5.4325
0.3415
1.65
1.4
0.333
0.3
KOEFISIEN

0.328
3.28
1.64
175
2.625
412
0.556
0.78
0.14
4
16
5.4325
0.3415
1.65
1.4
0.333
0.3
KOEFISIEN

1.0250
1.0250
0.041
0.02
0.01
0.01
1.0250
1.025
0.0205
0.0105
0.0011
0.0005

0.205
0.0105
0.0615
0.0615
0.006
0.003

0.205
0.0105
0.0585
0.03
0.006
0.003
KOEFISIEN

4.56
1
1
0.077
0.154
0.0155
0.004

0.7
0.02
0.1409
0.1256
0.051
0.0067

0.4
0.06
0.05
0.006
0.125
0.25
0.042
0.0063

23.077
0.15
0.0656
0.007
0.007
KOEFISIEN

4.4351
8
0.032
0.4
0.2
0.02
0.002

0.7577
0.12
0.14
0.067
0.007
0.007

61
0.2033
0.1687
0.2543
0.0253
0.008

6.6625
0.5125
0.205
0.0105
KOEFISIEN

12.5
12
0.038
0.3518
0.1131
0.0193
0.0288
20.6
8.32
0.062
0.321
0.437
0.022
0.0175

51.5
8.32
0.062
0.321
0.437
0.022
0.0175

1.1
0.5
0.6667
0.024
KOEFISIEN

7.0521
0.02
0.2559
0.15
0.0167
0.0167

6.24
0.0214
0.2559
0.15
0.0167
0.0167

12.75
0.027
0.35
0.15
0.0202
0.0273

10.35
0.031
0.35
0.15
0.0202
0.0273

8.32
0.032
0.35
0.15
0.0202
0.0273
KOEFISIEN

5.608
0.011
0.2559
0.127
0.013
0.015

4.7751
0.022
0.2559
0.15
0.0167
0.0167

6.449
0.023
0.35
0.15
0.0202
0.0273
KOEFISIEN

3.822
0.15
0.0731
0.0074
0.0069

1.64
0.072
0.036
0.004
0.004

6.34
0.012
0.3
0.15
0.015
0.027

3.4988
0.1753
0.1057
0.0146
0.0146
KOEFISIEN

1.108
1.0031
1
6.938
20.814
2.1521
0.4283

1.108
1.0031
1
6
18
2
0.389

0.04
0.475
0.5725
1.5508
0.1551
0.0956

0.04
0.475
0.5725
1.5508
0.1551
0.0956
KOEFISIEN

0.04
0.5
1
2.5543
0.2556
0.05

0.024
0.1593
0.8
2.1006
0.2043
0.04

0.0385
0.5
1
3
0.3
0.05

0.025
0.03
0.5
1
0.6359
2.0127
0.2
0.0546
KOEFISIEN

0.026
0.03
0.5
1
0.6651
2.1006
0.2043
0.056

0.06
0.15
0.5743
2
0.2
0.0764

0.0217
0.03
0.3
1
0.6366
2.0434
0.2043
0.056

1.1
15
3.446
4.4054
10.154
1.0154
0.2
KOEFISIEN

1.115
15
2.426
4.7508
20.1
2.01
0.2375

1.1
15
3
2.4
7.2
0.72
0.12

0.014
0.0038
0.25
0.1
0.1
0.01
0.005
0.014
0.007
0.25
0.1
0.1
0.01
0.005
KOEFISIEN

0.169
0.205
0.123
0.123
0.0123
0.006

0.015
0.2
0.15
0.3
0.03
0.075

0.0163
0.2543
0.2033
0.305
0.0305
0.075

0.01
0.0759
0.1194
0.239
0.0239
0.005

0.011
0.0759
0.1194
0.239
0.0239
0.005
KOEFISIEN
0.0283
0.1527
0.1527
0.4577
0.0473
0.008

0.0275
0.15
0.8451
0.45
0.1436
0.4307
0.0431
0.0077

0.028
0.144
0.8451
0.45
0.1914
0.5742
0.0574
0.0096

0.007
0.1025
0.1538
0.615
1.845
0.1845
0.0308
KOEFISIEN

0.4100
0.0515
0.0255
0.077
0.0077
0.001
KOEFISIEN

25.3588
10.4
0.045
0.3467
0.3228
0.1966
0.0197
0.0197

6.1554
1.2724
0.0033
0.09
0.09
0.009
0.0045

1.1177
0.61
0.7
0.356
0.0407
0.0407

1.05
0.35
0.171
0.127
0.0127
0.0091
KOEFISIEN

10
3.895
0.0665
0.5125
0.205
0.0205
0.0205

0.0023
0.05
0.12
0.12
0.012
0.006
11.87
8
0.045
1.5
0.7
0.35
0.035
0.035

6.625
8
0.045
0.94
0.7
0.35
0.035
0.035
KOEFISIEN

3
8
0.045
0.9321
0.7
0.35
0.035
0.035

1.1
11.5453
0.0193
2.336
0.3047
0.0117
0.0138
KOEFISIEN

1.1
0.01
0.03
0.07
0.007
0.04

0.375
0.03
0.1
0.1
0.01
0.005

0.0155
0.0105
0.82
0.82
0.082
0.041

1.05
0.0329
0.05
0.05
0.005
0.003

0.3646
0.11
0.228
0.4158
0.0416
0.014
KOEFISIEN

1.1
0.071
0.06
0.06
0.006
0.0023

1.1
10
7
0.2
0.2
0.02
0.001

1.05
0.015
0.019
0.231
0.4
0.04
0.01

1.05
0.01
0.0125
0.15
0.3
0.03
0.008
KOEFISIEN

1
0.01
0.5
0.01
0.005

1
0.015
0.15
0.015
0.001

1
0.01
0.1
0.01
0.001

1
0.015
0.15
0.015
0.001

1
0.0098
0.0683
0.0068
0.001
1.1
0.015
0.15
0.015
0.001
KOEFISIEN

1
1.4501
1.2366
0.1236
0.16

1
6.1
0.0103
1
1.525
1.5
0.1627

1
1
1
0.1
0.1

1
1.2
1.2366
0.1236
0.1
KOEFISIEN

1
1.9474
2.7
0.54
0.1189

53
44
0.07
0.07
1.415
0.06
3.2
1.015
0.1015
0.016

1.2
35
0.054
0.09
0.009
0.027

1.2
35
0.108
0.18
0.018
0.0054
KOEFISIEN

1.2
35
0.036
0.0706
0.0075
0.0043
KOEFISIEN

1.2
35
0.045
0.075
0.009
0.0025

1.2
0.081
0.1879
0.0189
0.007

1
0.0245
0.01
0.1
0.01
0.005
KOEFISIEN

0.185
0.138
0.17
0.273
0.0294
0.0847
0.089
0.0139
0.0051

0.293
0.0934
0.8924
0.0294
0.0539
0.0806
0.0129
0.0046

0.1154
0.092
0.26
0.0294
0.0362
0.063
0.0064
0.0064
KOEFISIEN

0.12
0.1839
0.0294
0.0361
0.042
0.0051
0.0037

0.123
0.0136
0.0227
0.0636
0.2
0.0204
0.0114

0.1
0.01
0.002
0.25
0.225
0.023
0.008
1.1.Analisa Harga Satuan Mobilisasi

No. URAIAN

A. Sewa Tanah

PERALATAN
B.
Periksa lembar 1.1-1.2

C. FASILITAS KONTRAKTOR
1 Base Camp
2 Kantor
3 Barak
4 Bengkel
5 Gudang, dan lain-lain
6 Pagar kaleng setingi 2 m Periksa lembar 1.3

D. FASILITAS LABORATORIUM
1 Ruang Laboratorium (sesuai Gambar)

2 Soil and Agregate Testing


Compaction Test
CBR Test
Specific Gravity
Atterberg Limits
Grain Size Analysis
Field Density Test by Sand Cone Methode
Moisture Content
Abrasion of Aggregate by Los Angeles Machine

3 Bitumino Testing
Marshall Asphalt Test
Extraction Test, Centrifuge/Refflux Method
Specific Gravity for Coarse Aggregate
Specific Gravity for Fine Aggregate
Mix Air Viod Content (Accurate Method)
Core Drill
Metal Thermometer
Accessories and Tolls
Penetration Test
Softening Point
Refusal Density Compactor

4 Concrete Testing
Slump Cone
Cylinder/Cube Mould for Compressive Strength
Beam Mould for Flexural Strength (RIGID)
Crushing Machine

5 Pendukung (Periksa Fasilitas Laboratorium)

6 Operasional (Periksa Fasilitas Laboratorium)

E. MOBILISASI LAINNYA
E.I. PEKERJAAN DARURAT
1 Perkuatan Jembatan Lama
2 Pemeliharaan Jalan Kerja / Samping
3 ......................
4 ......................
5 ......................
6 ......................

E.II. LAIN-LAIN
1 Komunikasi Lapangan Lengkap
2 ......................
3 ......................
4 ......................
5 ......................
6 ......................

F. DEMOBILISASI

Total Biaya Mobilisasi

Catatan : Jumlah yang tercantum pada masing-masing item mobilisasi di atas sudah termasu
serta seluruh pajak dan bea , dan pengeluaran lainnya.
1.2.Analisa Harga Satuan Mobilisasi Untuk Alat Berat

No. JENIS ALAT

B. PERALATAN

1 Dump-Truck 5.5 TON


2 Dum truck truck 10 ton
3 Water tangker 5000 liter
4 Escavator volvo EC 200D
5 Whell loader L956F
6 Bulldozer
7 Motor Grader
8 Vibration roller
9 Three axle tamdem roller
10 Tamdem roller RS8200
11 Pneumatic tyre rollers
12 Diesel generator (generator set)
13 Air compressor
14 Aspalt sprayer
15 Aspalt finisher
16 Aspalt mixing plant
17 Concrete mixing plant (concrete batching plan)
18 Stone Crusher

Total untuk Item B pada Lembar 1

1.3.Analisa pagar kaleng setingi 2m

Project Name:
District:
Sub district:
Location :
Work Item: Pembersihan lapangan
No Description Unit Task Rate

A LABOUR
Su
B TOOLS/EQUIPMENT
1 Hand Tool (5% of item A) %

Su
C MATERIAL
Unit Quantity

Su

D SUM OF LABOUR,EQUIPMENTS AND MATERIAL (A+B+C)


Notes :
1. Task rate is based on Ajencio desemvolvimento standart.
2. Unit cost for skill labour , unskilled labour and semi skilled labour based on the government rate
3. Unit cost of equipment's are based on hiring rate per hour/per day
4. All cost belong to all of expenditures of related tax, and other cost to complete the work item
nalisa Harga Satuan Mobilisasi

HARGA JUMLAH
IAN SATUAN VOL. SATUAN HARGA
($US) ($US)

M2 20,000 0.25 5,000

M2 150 50,000 7,500,000


M2 60 75,000 4,500,000
M2 60 45,000 2,700,000
M2 100 25,000 2,500,000
M2 100 25,000 2,500,000
m' 565 0 0

M2 108 55,000 5,940,000

Set 1 15,000,000 15,000,000


Set 1 20,000,000 20,000,000
Set 1 5,000,000 5,000,000
Set 1 5,000,000 5,000,000
Set 1 12,500,000 12,500,000
Set 2 6,500,000 13,000,000
Set 2 6,000,000 12,000,000
Bln 2 5,000,000 10,000,000

Set 1 20,000,000 20,000,000


Set 1 9,000,000 9,000,000
Set 1 9,000,000 9,000,000
Set 1 9,000,000 9,000,000
Set 1 15,000,000 15,000,000
Set 1 15,000,000 15,000,000
Set 1 1,000,000 1,000,000
Set 1 5,000,000 5,000,000
Bln 6 1,000,000 6,000,000
Set 1 6,000,000 6,000,000
Set 1 15,000,000 15,000,000

Set 1 500,000 500,000


Set 1 10,000,000 10,000,000
Set 1 10,000,000 10,000,000
Set 1 50,000,000 50,000,000

LS 1 100,000,000 100,000,000
LS 1 100,000,000 100,000,000
.... 0
.... 0
.... 0
.... 0

Set 1 5,000,000 5,000,000


.... 0 0 0
.... 0 0 0
.... 0 0 0
.... 0 0 0
.... 0 0 0

LS 1 0 0

503,645,000

asing item mobilisasi di atas sudah termasuk over-head dan laba


eluaran lainnya.
arga Satuan Mobilisasi Untuk Alat Berat

KODE HARGA JUMLAH


ALAT SATUAN VOL. SATUAN HARGA
(Rp.) (Rp.)

E42 Unit
E44 Unit
E86 Unit
E10 Unit
E82 Unit
E7 Unit
E61 Unit
E17 Unit
E14 Unit
E69 Unit
E71 Unit
E36 Unit
E30 Unit
E3 Unit
E2 Unit
E1 Unit
Unit
E21 Unit

m B pada Lembar 1 0

setingi 2m

Works Item No.

1.3

n
Unit Unit - 1 M'
Productivity
Price (US$) Amount
(US$)
Sub Total

Sub Total

Rate

Sub Total
Summary bahan baku ke quary

No Kode Daftar harga Units Unit Price Jarak dari quary (km)
1 M1 Pasir pasang m3 $ 3.52 0.1
2 M2 Pasir beton m3 $ 5.48 2
3 M3 Batu kali m3 2
4 M4 Batu belah m3 3
5 M5 Gravel m3 0.1
6 M6 Sirtu m3 0.1
7 M7 Pasir Urug m3 0.1
8 M8 Tanah Timbun m3 1.5
10 M10 Aspalt 60/70 penetration ton 95
11 M11 Portland cement kg $ 0.18 95
12 M12 Agregat kasar m3 0.1
13 M13 Agregad halus m3 0.1
14 m14 Batu m3 1.5

ANALISA HARGA SATUAN DASAR MATERIAL


Jenis : Pasir
Lokasi : Quary
Tujuan : Base Camp

No Uraian Kode Koefisien

I Asumsi
Menggunakan alat berat (Mekanik)
Kondisi jalan sedang / baik
Jarak Quary ke loksasi proyek L 0.10
Harga satuan pasir di quary $ M01 1.00
Harga satuan dasar excavator $ E10 1.00
Harga satuan dasar Dump truck $ E08 1.00

II Urutan kerja
Pasir digali dengan excavator
Excavator memuat pasir ke dalam truck
Dump Truck mengangkut pasir ke proyek

III Perhitungan
EXCAVATOR (E10)
Kapasitas Bucket V 1
Kapasitas Bucket V 1.00
Faktor Bucket Fb 1.00
Faktor efisiensi alat Fa 0.83
waktu siklus Ts1
-Menggali memuat T1 0.30
-Lain-lain T2 0.30
TS1 0.60
Kap. Prod/jam =
V x Fb x Fa x 60
Q1 83.00
TS1
Biaya Excavator/m3 = ( 1 : Q1 ) x Rp E10 $US 0.7470

DUMP TRUCK (E08)


Kapasitas bak V 3.00
Faktor efisiensi alat Fa 0.83
Kecepatan Rata-rata bermuatan V1 20.00
Kecepatan Rata-rata kosong V2 40.00
Waktu siklus Ts2
- waktu tempuh isi = (L/V1)x 60 T1 0.30
- waktu tempuh kosong=(L/V2)x 60 T2 0.15
-muat = (V/Q1)x60 T3 2.17
-Lain-lain T4 1.00
Ts2 3.62

Kapasitas produksi / perjam =


V*Fax60
Ts2 Q2 41.29

Biaya Dump Truck / M3 = (1:Q2)xRpE08 $US 0.78

IV Harga satuan Dasar Bahan di lokasi proyek


Harga satuan Dasar Pasir =
( $ M01 + $1 +$2) M01 3.52

ANALISA HARGA SATUAN DASAR MATERIAL


Jenis : Pasir Beton
Lokasi : Quary
Tujuan : Base Camp

No Uraian Kode Koefisien

I Asumsi
Menggunakan alat berat (Mekanik)
Kondisi jalan sedang / baik
Jarak Quary ke loksasi proyek L 2.00
Harga satuan pasir di quary $ M01 1.00
Harga satuan dasar excavator $ E10 1.00
Harga satuan dasar Dump truck $ E08 1.00

II Urutan kerja
Pasir digali dengan excavator
Excavator memuat pasir ke dalam truck
Dump Truck mengangkut pasir ke proyek

III Perhitungan
EXCAVATOR (E10)
Kapasitas Bucket V
Kapasitas Bucket V 1.00
Faktor Bucket Fb 1.00
Faktor efisiensi alat Fa 0.83
waktu siklus Ts1
-Menggali memuat T1 0.30
-Lain-lain T2 0.30
TS1 0.60
Kap. Prod/jam =
V x Fb x Fa x 60
Q1 83.00
Q1 83.00
TS1

Biaya Excavator/m3 = ( 1 : Q1 ) x Rp E10 $US 0.75

DUMP TRUCK (E08)


Kapasitas bak V 6.00
Faktor efisiensi alat Fa 0.83
Kecepatan Rata-rata bermuatan V1 20.00
Kecepatan Rata-rata kosong V2 40.00
Waktu siklus Ts2
- waktu tempuh isi = (L/V1)x 60 T1 6.00
- waktu tempuh kosong=(L/V2)x 60 T2 3.00
-muat = (V/Q1)x60 T3 4.34
-Lain-lain T4 1.00
Ts2 14.34

Kapasitas produksi / perjam =


V*Fax60
Ts2 Q2 20.84

Biaya Dump Truck / M3 = (1:Q2)xRpE08 $US 2.74

IV Harga satuan Dasar Bahan di lokasi proyek


Harga satuan Dasar Pasir =
( $ M01 + $1 +$2) M01 5.48

ANALISA HARGA SATUAN DASAR


Jenis : Batu Kali
Lokasi : Quary
Tujuan : Base Camp
No Uraian Kode Koefisien

I Asumsi
Menggunakan alat berat (Mekanik)
Kondisi jalan sedang / baik
Jarak Quary ke loksasi proyek L
Harga satuan Bt. Kali di quary Rp M01 1.00
Harga satuan dasar excavator Rp E10 1.00
Harga satuan dasar Dump truck Rp E08 1.00
II Urutan kerja
Batu kali digali dengan excavator
Excavator memuat Batu kali ke dalam truck
Dump Truck mengangkut Batu kali ke proyek
III Perhitungan
EXCAVATOR (E10)
Kapasitas Bucket V
Kapasitas Bucket V 1.00
Faktor Bucket Fb 0.75
Faktor efisiensi alat Fa 0.83
waktu siklus Ts1
-Menggali memuat T1 0.75
-Lain-lain T2 0.50
TS1 1.25
Kap. Prod/jam =
V x Fb x Fa x 60
Q1 29.88
TS1

Biaya Excavator/m3 = ( 1 : Q1 ) x Rp E10 $US -

DUMP TRUCK (E08)


Kapasitas bak V 4.00
Faktor efisiensi alat Fa 0.83
Kecepatan Rata-rata bermuatan V1 40.00
Kecepatan Rata-rata kosong V2 50.00
Waktu siklus Ts2
- waktu tempuh isi = (L/V1)x 60 T1 -
- waktu tempuh kosong=(L/V2)x 60 T2 -
-muat = (V/Q1)x60 T3 8.03
-Lain-lain T4 1.00
Ts2 9.03

Kapasitas produksi / perjam =


V*Fax60
Ts2 Q2 22.05

Biaya Dump Truck / M3 = (1:Q2)xRpE08 $US -

IV Harga satuan Dasar Bahan di lokasi proyek


Harga satuan Dasar Pasir =
( $ M01 + $1 +$2) M02 -

ANALISA HARGA SATUAN DASAR


Jenis : Batu Belah
Lokasi : Quary
Tujuan : Lokasi Pekerjaan

No Uraian Kode Koefisien


I Asumsi
Menggunakan alat berat (Mekanik)
Kondisi jalan sedang / baik
Jarak Quary ke loksasi proyek L
Harga satuan Batu belah di quary Rp M06 1.00
Harga satuan dasar excavator Rp E10 1.00
Harga satuan dasar Dump truck Rp E06 1.00
Harga satuan dasar Whell Loader Rp E15 1.00
Harga satuan Upah Pekerja Rp L01 1.00
II Urutan kerja
1 Batu Kali digali dengan excavator
2 Batu Kali di belah oleh pekerja
3 whell Loader memuat batu belah ke dalam truck
4 Dump Truck mengangkut Batu belah ke proyek

III Perhitungan
EXCAVATOR (E10)
Kapasitas Bucket V
Kapasitas Bucket V 0.50
Faktor Bucket Fb 0.75
Faktor efisiensi alat Fa 0.83
waktu siklus Ts1
-Menggali memuat T1 0.75
-Lain-lain T2 0.50
TS1 1.25
Kap. Prod/jam =
V x Fb x Fa x 60
Q1 14.94
TS1

Biaya Excavator/m3 = ( 1 : Q1 ) x Rp E10 Rp1 -


Wheel Loader (E10)
Kapasitas backet V 1.50
Faktor backet Fb 0.75
Faktor evisiensi alat Fa 0.83
Waktu siklus Ts1
-Menggali memuat T1 0.75
-lain-lain T2 0.50
Ts2 1.25
Kap. Prod/jam =
V x Fb x Fa x 60
Q2 44.82
TS1
Biaya Excavator / M3 = (1 : Q1)x Rp E15 Rp1 -

DUMP TRUCK (E08)


Kapasitas bak V 4.00
Faktor efisiensi alat Fa 0.83
Kecepatan Rata-rata bermuatan V1 40.00
Kecepatan Rata-rata kosong V2 50.00
Waktu siklus Ts2
- waktu tempuh isi = (L/V1)x 60 T1 -
- waktu tempuh kosong=(L/V2)x 60 T2 -
-muat = (V/Q1)x60 T3 5.35
-Lain-lain T4 1.00
Ts2 6.35

Kapasitas produksi / perjam =


V*Fax60
Q3 31.35
Ts2

Biaya Dump Truck / M3 = (1:Q3)xRpE08 Rp2 -

3.d PEKERJA
Produksi menentukan : Excavator Q1 14.94
Hasil galian batu / hari = Q1 x 7 jam Qt 104.58
Kebutuhan pekerja P 15

Biaya pekerja ./ M3 =
((7 jam x P):Qt) x RpL01 Rp4 -

IV Harga satuan Dasar Bahan di lokasi pekerjaan


Harga satuan Dasar Batu Belah =
( Rp M06 + Rp1 +Rp2 +Rp4) M06 -

ANALISA HARGA SATUAN DASAR


Jenis : Gravel
Lokasi : Quary
Tujuan : Base Camp

No Uraian Kode Koefisien

I Asumsi
Menggunakan alat berat (Mekanik)
Kondisi jalan sedang / baik
Jarak Quary ke loksasi proyek L
Harga satuan Gravel di quary Rp M7 1.00
Harga satuan dasar excavator Rp E10 1.00
Harga satuan dasar Dump truck Rp E08 1.00
II Urutan kerja
Gravel digali dengan excavator
Excavator memuat Gravel ke dalam truck
Dump Truck mengangkut Gravel ke proyek

III Perhitungan
EXCAVATOR (E10)
Kapasitas Bucket V
Kapasitas Bucket V 0.50
Faktor Bucket Fb 0.75
Faktor efisiensi alat Fa 0.83
waktu siklus Ts1
-Menggali memuat T1 0.75
-Lain-lain T2 0.50
TS1 1.25
Kap. Prod/jam =
V x Fb x Fa x 60
Q1 14.94
TS1

Biaya Excavator/m3 = ( 1 : Q1 ) x Rp E10 Rp1 -

DUMP TRUCK (E08)


Kapasitas bak V 15.00
Faktor efisiensi alat Fa 0.83
Kecepatan Rata-rata bermuatan V1 40.00
Kecepatan Rata-rata kosong V2 50.00
Waktu siklus Ts2
- waktu tempuh isi = (L/V1)x 60 T1 -
- waktu tempuh kosong=(L/V2)x 60 T2 -
-muat = (V/Q1)x60 T3 60.24
-Lain-lain T4 1.00
Ts2 61.24

Kapasitas produksi / perjam =


V*Fax60
Ts2 Q2 12.20

Biaya Dump Truck / M3 = (1:Q2)xRpE08 Rp2 -

IV Harga satuan Dasar Bahan di lokasi proyek


Harga satuan Dasar Pasir =
( Rp M07 + Rp1 +Rp2) M07 -

ANALISA HARGA SATUAN DASAR


Jenis : Sirtu
Lokasi : Quary
Tujuan : L:okasi Pekerjaan

No Uraian Kode Koefisien

I Asumsi
1 Menggunakan alat berat (Mekanik)
2 Kondisi jalan sedang / baik
3 Jarak Quary ke loksasi proyek L
4 Harga satuan Sirtu di quary Rp M16 1.00
5 Harga satuan dasar excavator Rp E10 1.00
6 Harga satuan dasar Dump truck Rp E08 1.00

II Urutan kerja
Sirtu digali dengan excavator
Excavator memuat Sirtu ke dalam truck
Dump Truck mengangkut Sirtu ke proyek

III Perhitungan
3a EXCAVATOR (E10)
Kapasitas Bucket V
Kapasitas Bucket V 0.50
Faktor Bucket Fb 0.90
Faktor efisiensi alat Fa 0.83
waktu siklus Ts1
-Menggali memuat T1 0.50
-Lain-lain T2 0.50
TS1 1.00
Kap. Prod/jam =
V x Fb x Fa x 60
Q1 22.41
TS1

Biaya Excavator/m3 = ( 1 : Q1 ) x Rp E10 Rp1 -

3.b DUMP TRUCK (E08)


Kapasitas bak V 4.00
Faktor efisiensi alat Fa 0.83
Kecepatan Rata-rata bermuatan V1 40.00
Kecepatan Rata-rata kosong V2 50.00
Waktu siklus Ts2
- waktu tempuh isi = (L/V1)x 60 T1 -
- waktu tempuh kosong=(L/V2)x 60 T2 -
-muat = (V/Q1)x60 T3 10.71
-Lain-lain T4 1.00
Ts2 11.71
Kapasitas produksi / perjam =
V*Fax60
Ts2 Q2 17.01

Biaya Dump Truck / M3 = (1:Q2)xRpE08 Rp2 -

IV Harga satuan Dasar Bahan di lokasi proyek


Harga satuan Dasar Pasir =
( Rp M07 + Rp1 +Rp2) M16 -

ANALISA HARGA SATUAN DASAR


Jenis : Pasir urug
Lokasi : Quary
Tujuan : L:okasi Pekerjaan

No Uraian Koefisien

I Asumsi
1 Menggunakan alat berat (Mekanik)
2 Kondisi jalan sedang / baik
3 Jarak Quary ke loksasi proyek L
4 Harga satuan Pasir urug di quary Rp M16 1.00
5 Harga satuan dasar excavator Rp E10 1.00
6 Harga satuan dasar Dump truck Rp E08 1.00

II Urutan kerja
1 Pasir urug digali dengan excavator
2 Excavator memuat Pasir urug ke dalam truck
3 Dump Truck mengangkut Pasir urug ke proyek
III Perhitungan
3a EXCAVATOR (E10)
Kapasitas Bucket V
Kapasitas Bucket V 0.50
Faktor Bucket Fb 0.90
Faktor efisiensi alat Fa 0.83
waktu siklus Ts1
-Menggali memuat T1 0.50
-Lain-lain T2 0.50
TS1 1.00
Kap. Prod/jam =
V x Fb x Fa x 60
Q1 22.41
TS1

Biaya Excavator/m3 = ( 1 : Q1 ) x Rp E10 Rp1 -

3.b DUMP TRUCK (E08)


Kapasitas bak V 4.00
Faktor efisiensi alat Fa 0.83
Kecepatan Rata-rata bermuatan V1 40.00
Kecepatan Rata-rata kosong V2 50.00
Waktu siklus Ts2
- waktu tempuh isi = (L/V1)x 60 T1 -
- waktu tempuh kosong=(L/V2)x 60 T2 -
-muat = (V/Q1)x60 T3 10.71
-Lain-lain T4 1.00
Ts2 11.71

Kapasitas produksi / perjam =


V*Fax60
Ts2 Q2 17.01
Biaya Dump Truck / M3 = (1:Q2)xRpE08 Rp2 -

IV Harga satuan Dasar Bahan di lokasi proyek


Harga satuan Dasar Pasir =
( Rp M07 + Rp1 +Rp2) M44 -

ANALISA HARGA SATUAN DASAR MATERIAL


Jenis : Tanah timbun
Lokasi : Quary
Tujuan : Base Camp

No Uraian Kode Koefisien

I Asumsi
Menggunakan alat berat (Mekanik)
Kondisi jalan sedang / baik
Jarak Quary ke loksasi proyek L
Harga satuan tanah timbun $ M01 1.00
Harga satuan dasar excavator $ E10 1.00
Harga satuan dasar Dump truck $ E08 1.00

II Urutan kerja
Pasir digali dengan excavator
Excavator memuat pasir ke dalam truck
Dump Truck mengangkut pasir ke proyek

III Perhitungan
EXCAVATOR (E10)
Kapasitas Bucket V
Kapasitas Bucket V 1.00
Faktor Bucket Fb 0.90
Faktor efisiensi alat Fa 0.83
waktu siklus Ts1
-Menggali memuat T1 0.19
-Lain-lain T2 0.19
TS1 0.38
Kap. Prod/jam =
V x Fb x Fa x 60
Q1 119.52
TS1

Biaya Excavator/m3 = ( 1 : Q1 ) x Rp E10 $US -

DUMP TRUCK (E08)


Kapasitas bak V 4.00
Faktor efisiensi alat Fa 0.83
Kecepatan Rata-rata bermuatan V1 40.00
Kecepatan Rata-rata kosong V2 50.00
Waktu siklus Ts2
- waktu tempuh isi = (L/V1)x 60 T1 -
- waktu tempuh kosong=(L/V2)x 60 T2 -
-muat = (V/Q1)x60 T3 2.01
-Lain-lain T4 1.00
Ts2 3.01

Kapasitas produksi / perjam =


V*Fax60
Ts2 Q2 66.22

Biaya Dump Truck / M3 = (1:Q2)xRpE08 $US -


IV Harga satuan Dasar Bahan di lokasi proyek
Harga satuan Dasar Pasir =
( $ M01 + $1 +$2) M01 -

Item Pembayaran : Agregat kasar dan halus


Jenis Pekerjaan : Pengadaan Agregat Kasar dan Halus
Satuan pembayaran : M3
No Uraian
I Asumsi
1 Bahan dasar (Batu + pasir) diterima dilokasi alat
Pemecah batu di base camp
2 Kegiatan dikakukan dilokasi base camp
3 Hasil produksi alat pemecah batu: - Agregat halus
- Agregat Kasar
4 Berat jenis bahan - Batu/Gravel
- Pasir
- Batu belah
5 Harga satuan bahan dasar - Batu / Gravel
- Pasir
6 Biaya operasi alat - Pemecah batu (stone Crusher)
- Whell Loader
7 Kapassitas Alat - Pemecah batu (stone Crusher)
- Whell Loader
8 Faktor efisiensi alt - Pemecah batu (stone Crusher)
- Whell Loader
9 Faktor kehilangan material
10 Harga satuan agregat kasar diambil sama dengan
harga satuan agregat produksi stone crusher
11 Agregat halus masih perlu dicampur dgn pasir

II METHODE PELAKSANAAN
1 Whell loader mengangkut gravel dari tumpukan dan
menuangkannya ke alat pemecah batu
Batu /gravel dipecah dengan alat pemecah batu shgg
menghasilkan agregat batu pecah

III PERITUNGAN
III.1 HARGA SATUAN AGREGAT PRODUKSI STONE CRUS
1.a Kerja stone crusher memecah batu/gravel
- waktu kerja stone crusher
- Produksi Stone crusher 1 jam = (Fa1xCp1):D3
- Kebutuhan batu/gravel 1 jam = (Fa1xCp1):D1

1.b Kerja whell loader melayani stone crusher


- Kapasitas angkut/rit = Fa2 x Cp2
- Waktu siklus (muat, Tuang, Tunggu) dll
- Waktu kerja whell loader memasok gravel
((Qg:Ka)xTs):60 Menit

1.c Biaya produksi batu pecah /M3


((Tst x Rp3)+(Tw x Rp4)):Qb

1.d Harga Satuan Batu pecah Produksi Stone Crusher/M3


= ((Qg:Qb)x Fh x Rp1)+Bp

III.2 HARGA SATUAN AGREGAT KASAR


Harga satuan agregat kasar diambil sama dengan
agregat batu pecah produksi stone crusher
Harga satuan agregat kasar / M3

III.3 HARGA SATUAN AGREGAT HALUIS


Dianggap agregat produksi ston crusher yang lolos
saringan # 4 (4,75mm) belum memenuhi spesifikasi
sehingga perlu di campur lagi dengan psir 10%
3.a Agregat Hasil stone crusher = 90% X Hsb
Pasir 10% X Rp2
Waktu pencampuran (Blending) dengan Whell Loader
Biaya Pencampuran = Tc X Rp4

Harga satuan Agregat Halus / M3


= HS1 + HS2+ HS3

Jumlah

ANALISA HARGA SATUAN DASAR


Jenis : Batu
Lokasi : Quary
Tujuan : Lokasi Pekerjaan

No Uraian Kode Koefisien

I Asumsi
Menggunakan alat berat (Mekanik)
Kondisi jalan sedang / baik
Jarak Quary ke loksasi proyek L
Harga satuan Batu belah di quary Rp M06 1.00
Harga satuan dasar excavator Rp E10 1.00
Harga satuan dasar Dump truck Rp E06 1.00
Harga satuan dasar Whell Loader Rp E15 1.00
Harga satuan Upah Pekerja Rp L01 1.00
II Urutan kerja
1 Batu Kali digali dengan excavator
2 Batu Kali di belah oleh pekerja
3 whell Loader memuat batu belah ke dalam truck
4 Dump Truck mengangkut Batu belah ke proyek

III Perhitungan
EXCAVATOR (E10)
Kapasitas Bucket V
Kapasitas Bucket V 1.00
Faktor Bucket Fb 0.75
Faktor efisiensi alat Fa 0.83
waktu siklus Ts1
-Menggali memuat T1 0.75
-Lain-lain T2 0.50
TS1 1.25
Kap. Prod/jam =
V x Fb x Fa x 60
Q1 29.88
TS1

Biaya Excavator/m3 = ( 1 : Q1 ) x Rp E10 Rp1 -

Wheel Loader (E10)


Kapasitas backet V 1.50
Faktor backet Fb 0.75
Faktor evisiensi alat Fa 0.83
Waktu siklus Ts1
-Menggali memuat T1 0.75
-lain-lain T2 0.50
Ts2 1.25
Kap. Prod/jam =
V x Fb x Fa x 60
Q2 44.82
TS1
Biaya Excavator / M3 = (1 : Q1)x Rp E15 Rp1 -

DUMP TRUCK (E08)


Kapasitas bak V 4.00
Faktor efisiensi alat Fa 0.83
Kecepatan Rata-rata bermuatan V1 40.00
Kecepatan Rata-rata kosong V2 50.00
Waktu siklus Ts2
- waktu tempuh isi = (L/V1)x 60 T1 -
- waktu tempuh kosong=(L/V2)x 60 T2 -
-muat = (V/Q1)x60 T3 5.35
-Lain-lain T4 1.00
Ts2 6.35

Kapasitas produksi / perjam =


V*Fax60
Q3 31.35
Ts2

Biaya Dump Truck / M3 = (1:Q3)xRpE08 Rp2 -

3.d PEKERJA
Produksi menentukan : Excavator Q1 29.88
Hasil galian batu / hari = Q1 x 7 jam Qt 209.16
Kebutuhan pekerja P 15
Biaya pekerja ./ M3 =
((7 jam x P):Qt) x RpL01 Rp4 -

IV Harga satuan Dasar Bahan di lokasi pekerjaan


Harga satuan Dasar Batu Belah =
( Rp M06 + Rp1 +Rp2 +Rp4) M06 -
Keterangan
diolah di base camp
dari quary ke base camp
dari quary ke base camp
dari quary ke base camp
diolah di base camp
diolah di base camp
diolah di base camp
dari quary ke base camp
Dili ke base camp
Dili ke base camp
diolah di base camp
diolah di base camp
dari quary ke base camp
Satuan Keterangan

Km
M3 2.00
Jam 62.00
Jam 32.02

M3
-
-

Menit
Menit

M3/Jam
M3

M3
-
Km/Jam
Km/Jam

Menit
Menit
Menit
Menit
Menit

M3/jam

M3

$US
Satuan Keterangan

Km
M3 2.00
Jam 61.94
Jam 57.00

M3
-
-

Menit
Menit

M3/Jam
M3/Jam

M3

M3
-
Km/Jam
Km/Jam

Menit
Menit
Menit
Menit
Menit

M3/jam

M3

$US
Satuan Keterangan

Km
M3
Jam
Jam

M3
-
-

Menit
Menit

M3/Jam

M3/Jam
M3
-
Km/Jam
Km/Jam

Menit
Menit
Menit
Menit
Menit

M3/jam

$US

$US

Satuan Keterangan
Km
M3
Jam
Jam
Jam
Jam

M3
-
-

Menit
Menit

M3/Jam

M3/Jam
M3
-
-

Menit
Menit
Menit

M3/Jam

M3

M3
-
Km/Jam
Km/Jam

Menit
Menit
Menit
Menit
Menit

M3/jam

$US
M3/jam
M3/ 7 jam
Org

$US

$US

Satuan Keterangan

Km
M3
Jam
Jam
M3
-
-

Menit
Menit

M3/Jam

M3/Jam

M3
-
Km/Jam
Km/Jam

Menit
Menit
Menit
Menit
Menit

M3/jam

US$

US$

Satuan Keterangan

Km
M3
Jam
Jam
M3
-
-

Menit
Menit

M3/Jam

M3/Jam

M3
-
Km/Jam
Km/Jam

Menit
Menit
Menit
Menit
Menit
M3/jam

US$

US$

Satuan Keterangan

Km
M3
Jam
Jam
M3
-
-

Menit
Menit

M3/Jam

M3/Jam

M3
-
Km/Jam
Km/Jam

Menit
Menit
Menit
Menit
Menit

M3/jam
US$

US$

Satuan Keterangan

Km
M3
Jam
Jam
M3
-
-

Menit
Menit

M3/Jam

M3

M3
-
Km/Jam
Km/Jam

Menit
Menit
Menit
Menit
Menit

M3/jam

M3
$US

Kode Koefisien Satuan Keterangan

H 20 %
K 80 %
D1 1.8 Ton/M3
D2 1.67 Ton/M3
D3 1.8 Ton/M3
Rp1 - Rp/M3
Rp2 5.48 Rp/M3
Rp3 Rp/M3
Rp4 Rp/M3
CP1 Ton/Jam
CP2 M3 Kap. Bucket
Fa1 0.7 -
Fa2 0.83 -
Fh 1.1 -
TSt 1.00 Jam
Qb - M3/Jam
Qg - M3/Jam

Ka - M3
Ts 2.00 Menit

TW #DIV/0! Jam

Bp #DIV/0! US/M3

HSb #DIV/0! US/M3


Hsak #DIV/0! US
PPN 10% #DIV/0! US
HSak #DIV/0! US

HS1 #DIV/0!
HS2 #DIV/0!
TC 0.033
HS3 -

Hsah #DIV/0! US
PPN 10% #DIV/0! US
HSAH #DIV/0! US

Satuan Keterangan
Km
M3
Jam
Jam
Jam
Jam

M3
-
-

Menit
Menit

M3/Jam

M3/Jam

M3
-
-
Menit
Menit
Menit

M3/Jam

M3

M3
-
Km/Jam
Km/Jam

Menit
Menit
Menit
Menit
Menit

M3/jam

$US

M3/jam
M3/ 7 jam
Org
$US

$US
Analisa Harga Satuan Pekerjaan Tanah Biasa

ITEM PEMBAYARAN NO. : ……..


JENIS PEKERJAAN : Pekerjaan Galian Tanah Biasa
SATUAN PEMBAYARAN : m3

NO. URAIAN KODE KOEFISIEN SATUAN KETERANGAN

I. ASUMSI
1. Kondisi jalan : sedang
2. Menggunakan alat secara mekanis
3. Lokasi sepanjang jalan
4. Jam kerja efektif per hari Ew 7 Jam
5. Faktor pengembangan bahan Lf 1.2 -
6. Berat volume tanah (lepas) Vd 1.6 Ton/m3
7. Jarak lokasi ke pembuangan L 3.75 km

II. URUTAN KERJA


1. Tanah yang dipotong umumnya berada di sisi jalan;
2. Penggalian dilakukan dengan menggunakan
excavator;
3. Loader menuangkan material hasil galian ke dalam
dump truck;
4. Dump truck membuang material hasil galian ke luar
lokasi jalan sejauh L = 1 km.

III. PEMAKAIAN ALAT DAN TENAGA

1. ALAT
a. Hydraulic Excavator 0.90 cu.m. E54 * Kond. kerja : Sedang
Kapasitas bucket Vb 0.90 m3 ** Kond operasi :

Faktor efisiensi alat * Ef 0.75 - Agak sulit (Tanah

Faktor Bucket ** Bf 0.95 - biasa berbatu)

Faktor konversi kedalaman = 3 m / 6.37 m = 0.47 Cf 1.30 - Maksimum 6.37 m

[ 40-75% dan kondisi dumping : Agak sulit ]


Waktu Siklus, Ct :
-Menggali, memuat T1 0.32 Menit Hasil uji
-Lain-lain (waktu tunda, dll) T2 0.10 Menit Hasil uji
Jumlah Ct1 0.42 Menit

Vb x Bf x Ef x 60
Kapasitas Produksi /Jam = Q1 58.72 m3
Ct1 x Cf x Lf
Koefisien Alat / m3 = 1/Q1 0.0170 Jam

NO. URAIAN KODE KOEFISIEN SATUAN KETERANGAN

b. Dump Truck 5.5 Ton E42 * Kond. kerja : Sedang


Kapasitas bak Vt 5.50 Ton
Faktor efisiensi alat * Ef 0.80 -
Kecepatan rata-rata bermuatan s1 20.00 km/Jam
Kecepatan rata-rata kosong s2 40.00 km/Jam
Waktu Siklus, Ct :
-Muat = (Vt x 60) /(Vd x Q1) T1 3.51 Menit
-Waktu tempuh isi = (L / s1) x 60 T2 11.25 Menit
-Waktu tempuh kosong = (L / s2) x 60 T3 5.63 Menit
-Lain-lain T4 2.00 Menit Hasil uji
Jumlah Ct2 22.39 Menit

Vt x Ef x 60
Kapasitas Produksi /Jam = Q2 7.37 m3
Ct2 x Vd
Koefisien alat/m3 = 1/Q2 0.1357 Jam

2. TENAGA
Produksi menentukan : Excavator Q1 58.72 m3/Jam
Produksi galian/hari = Ew x Q1 = 7 x Q1 Qt 411.06 m3
Kebutuhan tenaga :
-Pekerja UL 2.00 Orang
-Mandor FO 1.00 Orang
Koefisien tenaga/m3 :
-Pekerja = (Ew x UL) / Qt L1 0.0341 Jam
-Mandor = (Ew x FO) / Qt L4 0.0170 Jam
FORMULIR STANDAR
Analisa MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : ……..


JENIS PEKERJAAN : Pekerjaan Galian Tanah Biasa
SATUAN PEMBAYARAN : m3

HARGA JUMLAH
NO. KOMPONEN SATUAN KOEFISIEN SATUAN HARGA
($) ($)

A. Tenaga
Pekerja Jam 0.0341 0.71 0.02
Mandor Jam 0.0170 1.71 0.03
Jumlah harga tenaga 0.05

B. Bahan - - - -
Jumlah harga bahan 0.00

C. Peralatan
Hydraulic Excavator 0.90 cu.m. Jam 0.0170 75.00 1.28
Dump Truck 5.5 Ton Jam 0.1357 15.00 2.04
Jumlah harga peralatan 3.31
D. Harga Satuan Pekerjaan (A+B+C) 3.37

Note :
1 Satuan untuk Tenaga Kerja dan Peralatan berdasarkan Jam kerja operasi, untuk bahan-bahan
berdasarkan volume dan/atau berat.
2 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
3 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk
pajak yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa Harga Satuan Pekerjaan Galian Untuk Drainase & Saluran Air

ITEM PEMBAYARAN NO. : ....


JENIS PEKERJAAN : Galian Utk Drainase & Saluran Air
SATUAN PEMBAYARAN : m3

NO. URAIAN KODE KOEFISIEN SATUAN KETERANGAN

I. ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi Jalan : sedang / baik
4 Jam kerja efektif per-hari Ew 7.00 Jam
5 Faktor pengembangan bahan Lf 1.20 -
6. Berat volume tanah (lepas) Vd 1.6 Ton/m3

II. URUTAN KERJA


1 Penggalian dilakukan dengan menggunakan Excavator
2 Selanjutnya Excavator menuangkan material hasil
galian kedalam Dump Truck
3 Dump Truck membuang material hasil galian keluar
lokasi jalan sejauh L; L 3.00 km
4 Sekelompok pekerja akan merapikan hasil galian

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA

1. BAHAN
Tidak ada bahan yang diperlukan
2. ALAT
a. Hydraulic Excavator 0.90 cu.m. E54 * Kond. kerja : Sedang

Kapasitas bucket Vb 0.90 m3 ** Kond operasi :

Faktor efisiensi alat * Ef 0.75 - Agak sulit (Tanah

Faktor Bucket ** Bf 0.95 - biasa berbatu)

Waktu siklus, Ct Menit


- Menggali / memuat T1 0.500 Menit
- Lain-lain T2 0.200 Menit
Ct1 0.700 Menit

Kap. Prod. / jam = Vb x Bf x Ef x 60 Q1 45.80 m3 / Jam


Ct1 x Lf
Koefisien A = 1 / Q1 - 0.0218 Jam

NO. URAIAN KODE KOEFISIEN SATUAN KETERANGAN

b. Dump Truck 5.5 Ton E42 * Kond. kerja : Sedang


Kapasitas bak Vt 5.50 Ton
Faktor efisiensi alat * Ef 0.80 -
Kecepatan rata-rata bermuatan s1 20.00 km/Jam
Kecepatan rata-rata kosong s2 40.00 km/Jam
Waktu siklus, Ct :
- Waktu tempuh isi = (L / s1) x 60 T1 9.00 menit
- Waktu tempuh kosong = (L / s2) x 60 T2 4.50 menit
- Muat = (Vt / Q1) x 60 T3 7.20 menit
- Lain-lain T4 0.50 menit
Ct2 21.20 menit

Vt x Ef x 60 Q2 7.78 m3 / Jam
Kapasitas Produksi / Jam =
Vd x Ct2

Koefisien A = 1 / Q2 0.1285 Jam

d. Alat Bantu
Diperlukan alat-alat bantu kecil Lump Sump
- Sekop
- Keranjang + Sapu

3. TENAGA
Produksi menentukan : EXCAVATOR Q1 45.80 m3/Jam
Produksi Galian / hari = Ew x Q1 Qt 320.63 m3
Kebutuhan tenaga :
- Pekerja UL 4.00 Orang
- Mandor FO 1.00 Orang

Koefisien tenaga / m3 :
- Pekerja = (Ew x UL) / Qt L1 0.0873 Jam
- Mandor = (Ew x FO) / Qt L4 0.0218 Jam
FORMULIR STANDAR
Analisa MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : ……..


JENIS PEKERJAAN : Galian Utk Drainase, Saluran Air & SMRW
SATUAN PEMBAYARAN : m3

HARGA JUMLAH
NO. KOMPONEN SATUAN KOEFISIEN SATUAN HARGA
($) ($)

A. Tenaga
Pekerja Jam 0.0873 0.71 $ 0.06
Mandor Jam 0.0218 1.71 $ 0.04
Jumlah harga tenaga $ 0.10

B. Bahan - - - -
Jumlah harga bahan $ -

C. Peralatan
Hydraulic Excavator 0.90 cu.m. Jam 0.0218 62.00 $ 1.35
Dump Truck 5.5 Ton Jam 0.1285 32.02 $ 4.12
Alat Bantu LS 1 0.12 $ 0.12
Jumlah harga peralatan $ 5.59
D. Harga Satuan Pekerjaan (A+B+C) $ 5.69

Note :
1 Satuan untuk Tenaga Kerja dan Peralatan berdasarkan Jam kerja operasi, untuk bahan-bahan
berdasarkan volume dan/atau berat.
2 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
3 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk
pajak yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa Harga Satuan Pekerjaan Galian Struktur dengan kedalaman 0 – 2 meter

Lokasi : di sekitar jembatan


Alat yang dipergunakan Excavator dan Buldozer.

ITEM PEMBAYARAN NO. : ……..


JENIS PEKERJAAN : Galian Struktur dengan kedalaman 0 – 2 meter
SATUAN PEMBAYARAN : m3

NO. URAIAN KODE KOEFISIEN SATUAN KETERANGAN

I. ASUMSI
1. Pekerjaan dilakukan secara mekanis
2. Kondisi jalan : baik
3. Jam kerja efektif per hari Ew 7 Jam
4. Faktor pengembangan bahan Lf 1.2 -
5. Penimbunan kembali (backfill) untuk struktur Fb 50 %/m3

II. URUTAN KERJA


1. Tanah yang digali/dipotong berada di sekitar lokasi
2. Penggalian dilakukan dengan alat Excavator
3. Buldozer mengangkut/menggusur hasil galian ke tempat
pembuangan di sekitar lokasi pekerjaan sejauh L=100m
4. Bahan pengaman tebing galian dari bahan kayu.

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA


1. BAHAN
Urugan pilihan (untuk backfill) = Fb x 1 m3 M17 0.5 m3

2. ALAT
a. Hydraulic Excavator 0.90 cu.m. E54 * Kond. kerja : Sedang

Kapasitas bucket Vb 0.90 m3 ** Kond operasi :

Faktor efisiensi alat * Ef 0.75 - Agak sulit (Tanah

Faktor Bucket ** Bf 0.95 - biasa berbatu)

Faktor konversi kedalaman = 2 m / 6.37 m (< 40%) dan Cf 0.90


kondisi dumping normal
Waktu siklus, Ct :
-Menggali, memuat, lain-lain (standar) T1 0.40 Menit Hasil uji
-Lain-Lain T2 0.20 Menit Hasil uji
Jumlah Ct1 0.60 Menit

Kapasitas Vb x Bf x Ef x 60
Produksi Q1 59.38 m3
/Jam = Ct1 x Cf x Lf
Koefisien alat / m3 = 1 / Q1 0.0168 Jam

NO. URAIAN KODE KOEFISIEN SATUAN KETERANGAN

b. Buldozer 215 hp E12 * Kond. kerja : Sedang


Faktor pisau (blade) Kf 0.70 -
Faktor efisiensi alat * Ef 0.75 -
Kecepatan maju (mengupas) Sp 3.00 km/Jam
Kecepatan mundur Sr 5.00 km/Jam
Lebar Blade Bw 3.00 m
Tinggi blade Bh 1.20 m
Jarak penggusuran L 100.00 m
Volume 1 kali gusur = Bh^2 x Bw x Kf V 3.02 m3
Waktu siklus, Ct
-Waktu gusur = (L x 60) / (Sp x 1000) T1 2.00 Menit
-Waktu kembali = (L x 60) / (Sr x 1000) T2 1.20 Menit
-Waktu lain-lain T3 0.05 Menit Hasil uji
Ct2 3.25 Menit

Kapasitas V x Ef x 60
Produksi Q2 34.89 m3
/Jam = Ct2 x Lf
Koefisien alat / m3 = 1 / Q2 0.0287 Jam

3. TENAGA
Produksi menentukan : Excavator Q1 59.38 m3/Jam
Produksi galian/hari = Ew x Q1 Qt 415.63 m3
Kebutuhan tenaga
-Pekerja UL 4 Orang
-Mandor FO 1 Orang

Koefisien tenaga / m3
-Pekerja = (Ew x UL) / Qt L1 0.0674 Jam
-Mandor = (Ew x FO) / Qt L4 0.0168 Jam
FORMULIR STANDAR
Analisa MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : ……..


JENIS PEKERJAAN : Galian Struktur dengan kedalaman 0 – 2 meter
SATUAN PEMBAYARAN : m3

HARGA JUMLAH
NO. KOMPONEN SATUAN KOEFISIEN SATUAN HARGA
($) ($)

A. Tenaga
Pekerja Jam 0.0674 0.71 0.05
Mandor Jam 0.0168 1.71 0.03
Jumlah harga tenaga 0.08

B. Bahan
Urugan pilihan (untuk backfill) m3 0.5 0.00 0.00
Jumlah harga bahan 0.00

C. Peralatan
Hydraulic Excavator 0.90 cu.m. Jam 0.0168 75.00 1.26
Bulldozer, 140 HP Jam 0.0287 62.00 1.78
Jumlah harga peralatan 3.04
D. Harga Satuan Pekerjaan (A+B+C) 3.12

Note :
1 Satuan untuk Tenaga Kerja dan Peralatan berdasarkan Jam kerja operasi, untuk bahan-bahan
berdasarkan volume dan/atau berat.
2 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
3 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk
pajak yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa Harga Satuan Pekerjaan Galian Untuk Drainase & Saluran Air

ITEM PEMBAYARAN NO. : ....


JENIS PEKERJAAN : Galian Utk Perletakan Bronjong
SATUAN PEMBAYARAN : m3

NO. URAIAN KODE KOEFISIEN SATUAN KETERANGAN

I. ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi Jalan : sedang / baik
4 Jam kerja efektif per-hari Ew 7.00 Jam
5 Faktor pengembangan bahan Lf 1.40 -
6. Berat volume tanah (lepas) Vd 1.6 Ton/m3

II. URUTAN KERJA


1 Penggalian dilakukan dengan menggunakan Excavator
2 Selanjutnya Excavator menuangkan material hasil
galian kedalam Dump Truck
3 Dump Truck membuang material hasil galian keluar
lokasi jalan sejauh L; L 1.00 km
4 Sekelompok pekerja akan merapikan hasil galian

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA

1. BAHAN
Tidak ada bahan yang diperlukan
2. ALAT
a. Hydraulic Excavator 0.90 cu.m. E54 * Kond. kerja : Sedang

Kapasitas bucket Vb 0.90 m3 ** Kond operasi :

Faktor efisiensi alat * Ef 0.75 - Agak sulit (Tanah

Faktor Bucket ** Bf 0.8 - biasa berbatu)

Faktor konversi kedalaman = 2 m / 6.37 m (< 40%) dan Cf 1.10


kondisi dumping normal
Waktu siklus, Ct
- Menggali / memuat T1 0.400 Menit
- Lain-lain T2 0.200 Menit
Ct1 0.600 Menit

Kap. Prod. / jam = Vb x Bf x Ef x 60 Q1 35.06 m3 / Jam


Ct1 x Cf x Lf
Koefisien A = 1 / Q1 - 0.0285 Jam

NO. URAIAN KODE KOEFISIEN SATUAN KETERANGAN

b. Dump Truck 5.5 Ton E42 * Kond. kerja : Sedang


Kapasitas bak Vt 5.50 Ton
Faktor efisiensi alat * Ef 0.80 -
Kecepatan rata-rata bermuatan s1 20.00 km/Jam
Kecepatan rata-rata kosong s2 40.00 km/Jam
Waktu siklus, Ct :
- Waktu tempuh isi = (L / s1) x 60 T1 3.00 menit
- Waktu tempuh kosong = (L / s2) x 60 T2 1.50 menit
- Muat = (Vt / Q1) x 60 T3 9.41 menit
- Lain-lain T4 2.00 menit
Ct2 15.91 menit

Vt x Ef x 60 Q2 10.37 m3 / Jam
Kapasitas Produksi / Jam =
Vd x Ct2

Koefisien A = 1 / Q2 0.0964 Jam

d. Alat Bantu
Diperlukan alat-alat bantu kecil Lump Sump
- Sekop
- Keranjang + Sapu

3. TENAGA
Produksi menentukan : EXCAVATOR Q1 35.06 m3/Jam
Produksi Galian / hari = Ew x Q1 Qt 245.45 m3
Kebutuhan tenaga :
- Pekerja UL 4.00 Orang
- Mandor FO 1.00 Orang

Koefisien tenaga / m3 :
- Pekerja = (Ew x UL) / Qt L1 0.1141 Jam
- Mandor = (Ew x FO) / Qt L4 0.0285 Jam
FORMULIR STANDAR
Analisa MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : ……..


JENIS PEKERJAAN : Galian Utk Perletakan Bronjong
SATUAN PEMBAYARAN : m3

HARGA JUMLAH
NO. KOMPONEN SATUAN KOEFISIEN SATUAN HARGA
($) ($)

A. Tenaga
Pekerja Jam 0.1141 0.71 0.08
Mandor Jam 0.0285 1.71 0.05
Jumlah harga tenaga 0.13

B. Bahan - - - -
Jumlah harga bahan 0.00

C. Peralatan
Hydraulic Excavator 0.90 cu.m. Jam 0.0285 75.00 2.14
Dump Truck 5.5 Ton Jam 0.0964 15.00 1.45
Alat Bantu LS 1 0.1 0.10
Jumlah harga peralatan 3.69
D. Harga Satuan Pekerjaan (A+B+C) 3.82
Note :
1 Satuan untuk Tenaga Kerja dan Peralatan berdasarkan Jam kerja operasi, untuk bahan-bahan
berdasarkan volume dan/atau berat.
2 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
3 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk
pajak yang dibayar dari kontrak) dan biaya-biaya lainnya.
Contoh Analisa Harga Satuan Pekerjaan Galian Batu

ITEM PEMBAYARAN NO. : ....


JENIS PEKERJAAN : Galian Batu (Rock Excavation)
SATUAN PEMBAYARAN : m3

NO. URAIAN KODE KOEFISIEN SATUAN KETERANGAN

I. ASUMSI
1 Pekerjaan dilakukan secara mekanis
2 Kondisi jalan : Baik
3 Lokasi : sepanjang jalan
4 Jam kerja efektif per hari Ew 7 Jam
5 Faktor pengembangan bahan Lf 1.2 -
6 Berat volume material (lepas) Vd 1.8 Ton/m3
7 Jarak lokasi ke pembuangan L 5 km

II. URUTAN KERJA


1 Batu yang digali/dipotong umumnya berada disisi jalan
Penggalian dilakukan dengan excavator, breaker kadang
2 membantu pada kondisi batu cadas
Pengumpulan Hasil Galiandilakukan dengan Hydraulic Excavator.
3 Hasil galian dimuat dalam truck dengan Loader.
4 Dump Truck membuang material hasil galian keluar
lokasi jalan sejauh (L) km.

III. PEMAKAIAN ALAT DAN TENAGA


1 ALAT
a. Hydraulic Excavator with breacker E..
Produksi / Jam Q1 10.00 m3
Koefisien Alat / m3 = 1/Q1 0.1000 Jam

b. Hydraulic Excavator 0.90 cu.m. E.. * Kond. Operasi :

Kapasitas bucket Vb 0.90 m3 SEDANG

Faktor efisiensi alat * Ef 0.75 - **Kond. lap. : SULIT

Faktor Bucket ** Bf 0.85 - (batu pecah)

Faktor konversi kedalaman = 3 m / 6.37 m = 0.47 Cf 1.10 - Maksimum 6.37 m

[ 40-75% dan kondisi dumping : Agak sulit ]


Waktu Siklus, Ct :
-Menggali/mengumpulkan batu T1 1.00 Menit
-Lain-lain (waktu tunda, dll) T2 0.50 Menit
Jumlah Ct1 1.50 Menit

Vb x Bf x Ef x 60
Kapasitas Produksi /Jam = Q2 17.39 m3
Ct1 x Cf x Lf
Koefisien Alat / m3 = 1/Q2 0.0575 Jam

NO. URAIAN KODE KOEFISIEN SATUAN KETERANGAN

c. Wheel Loader, 1.8 m3 E82 * Kond. Opr : SEDANG

Kapasitas bucket Vb 1.80 m3 Pemelh. Mesin :

Faktor efisiensi alat * Ef 0.65 - SEDANG

Faktor bucket ** Bf 0.85 - ** Kondisi dumping :

Waktu siklus, Ct SEDANG


-Menggali, memuat T1 1.00 Menit
-Lain-lain T2 0.50 Menit
Jumlah Ct1 1.50 Menit
(Vb x Bf x Ef x 60)
Kapasitas Produksi / Jam = Q3 33.15 m3
(Ct1 x Lf)
Koefisien alat/m3 = 1 / Q3 0.0302 Jam

d. Dump Truck 12 Ton


Kapasitas bak Vt 12.00 Ton
Faktor efisiensi alat Ef 0.80 -
Kecepatan rata-rata bermuatan s1 20.00 km/Jam
Kecepatan rata-rata kosong s2 30.00 km/Jam
Waktu Siklus, Ct :
-Muat = (Vt x 60)/(Vd x Q3) T1 12.07 Menit
-Waktu tempuh isi = (L/s1) x 60 T2 15.00 Menit
-Waktu tempuh kosong = (L/s2) x 60 T3 10.00 Menit
-Lain-lain T4 2.00 Menit
Ct4 39.07 Menit
Vt x Ef x 60
Kapasitas Produksi / Jam : Q4 8.1912 m3/Jam
Vd x Ct2
Koefisien Alat/m3 = 1 / Q4 0.1221 Jam

2 TENAGA
Produksi menentukan : Excavator with Breacker Q1 10.00 m3/Jam
Produksi galian/hari = Ew x Q1 Qt 70.00 m3

Kebutuhan tenaga :
-Pekerja UL 8.00 Orang
-Mandor FO 1.00 Orang

Koefisien tenaga/m3 :
-Pekerja = (Ew x UL) / Qt L1 0.8000 Jam
-Mandor = (Ew x FO) / Qt L4 0.1000 Jam
FORMULIR STANDAR
ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : ……..


JENIS PEKERJAAN : Galian Batu (Rock Excavation)
SATUAN PEMBAYARAN : m3

HARGA JUMLAH
NO. KOMPONEN SATUAN KOEFISIEN SATUAN HARGA
($) ($)

A. Tenaga
Mandor Jam 0.1000 1.71 0.17
Pekerja Jam 0.8000 0.71 0.57
Jumlah harga tenaga 0.74

B. Bahan - - - -

Jumlah harga bahan 0.00

C. Peralatan
Hydraulic Excavator with breacker Jam 0.0250 100.00 2.50
Hydraulic Excavator 0.90 cu.m. Jam 0.0575 75.00 4.31
Wheel loader 1.8 m3 Jam 0.0302 0.00 0.00
Dump Truck 12 Ton Jam 0.1221 35.00 4.27

Jumlah harga peralatan 11.09


D. Harga Satuan Pekerjaan (A+B+C) 11.83

Note :
1 Satuan untuk Tenaga Kerja dan Peralatan berdasarkan Jam kerja operasi, untuk bahan-bahan
berdasarkan volume dan/atau berat.
2 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
3 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk
pajak yang dibayar dari kontrak) dan biaya-biaya lainnya.

NOTE : Pada galian bukit digunakan Wheel Loader untuk memuat ke dalam Dump Truck.
Pada galian datar digunakan Excavator untuk memuat ke dalam Dump Truck.
Analisa Harga Satuan Pekerjaan Timbunan Tanah Biasa

ITEM PEMBAYARAN NO. : ……..


JENIS PEKERJAAN : Pekerjaan Timbunan Material Pilihan (Sirtu)
SATUAN PEMBAYARAN : m3

NO. URAIAN KODE KOEFISIEN SATUAN

I. ASUMSI
1. Pekerjaan dilakukan secara mekanis
2. Kondisi jalan : sedang
3. Jam kerja efektif per hari Ew 7 Jam
4. Faktor pengembangan bahan Lf 1.2 -
6. Berat volume tanah (lepas) Vd 1.6 Ton/m3
6. Tebal hamparan padat t 0.2 m
7. Jarak quarry ke lokasi pekerjaan / lapangan L 7.5 km

II. URUTAN KERJA


1. Excavator Menggali & memuat material ke dalam dump truck
2. Dump Truck mengangkut material dari quarry ke lokasi
pekerjaan sejauh L.
3. Material diratakan dengan menggunakan motor grader
4. Material dipadatkan dengan menggunakan vibrator roller
5. Selama pemadatan sekelompok pekerja akan merapikan
tepi hamparan dan level permukaan menggunakan alat
alat bantu.

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA


1. BAHAN
Material timbunan = 1 x Lf M16 1.2 m3

2. ALAT
a. Hydraulic Excavator 0.90 cu.m. E82
Kapasitas bucket Vb 0.90 m3
Faktor efisiensi alat * Ef 0.75 -
Faktor bucket ** Bf 1.00 -
Waktu siklus, Ct
-Menggali, memuat T1 1.00 Menit
-Lain-lain T2 1.00 Menit
Jumlah Ct1 2.00 Menit
Kapasitas Produksi / (Vb x Bf x Ef x 60)
Q1 16.88 m3
Jam = (Ct1 x Lf)
Koefisien alat/m3 = 1 / Q1 0.0593 Jam
NO. URAIAN KODE KOEFISIEN SATUAN

b. Dump Truck 5.5 Ton E42


Kapasitas bak Vt 5.50 Ton
Faktor efisiensi alat * Ef 0.83 -
Kecepatan rata-rata bermuatan s1 20.00 km/Jam
Kecepatan rata-rata kosong s2 40.00 km/Jam
Waktu Siklus, Ct :
-Waktu tempuh isi = (L/s1) x 60 T1 22.50 Menit
-Waktu tempuh kosong = (L/s2) x 60 T2 11.25 Menit
-Lain-lain T3 5.00 Menit
Jumlah Ct2 38.75 Menit

Kapasitas Produksi / Vt x Ef x 60
Q2 4.42 m3
Jam = Ct2 x Vd
Koefisien alat / m3 = 1 / Q2 0.2264 Jam

c. Motor Grader >125 hp E61


Panjang hamparan Ly 50.00 m
Lebar efektif kerja Blade Bw 2.40 m

Faktor efisiensi alat * Ef 0.80 -

Kecepatan rata-rata alat Sa 2.00 km/Jam


Jumlah lintasan n1 6.00 Lintasan
Waktu Siklus, Ct :
-Perataan 1 kali Ly x 60
T1 1.50 Menit
lintasan = Sa x 1000
-Lain-lain T2 0.30 Menit
Jumlah Ct3 1.80 Menit

Kapasitas Produksi / Ly x Bw x t x Ef x 60
Q3 183.96 m3
Jam = Ct3 x n1
Koefisien alat / m3 = 1 / Q3 0.0054 Jam

d. Vibratory Drum Roller 3-5 Ton E73


Kecepatan rata-rata Sa 4.00 km/Jam
Lebar efektif pemadatan cw 1.20 m
Jumlah lintasan n1 8.00 kali
Faktor efisiensi alat * Ef 0.75 -

Kapasitas Sa x 1000 x cw x t x Ef
Produksi / Q4 90.00 m3
n1
Jam =
Koefisien alat / m3 = 1 / Q4 0.0111 Jam

NO. URAIAN KODE KOEFISIEN SATUAN

e. Water Tank Truck with Pump 5000 liter E86

Volume tangki air Vw 5.00 m3


Kebutuhan air/m3 material padat Wr 0.07 m3
Mengisi tangki/Jam n2 4.00 kali
Faktor efisiensi alat * Ef 0.83 -

Kapasitas Produksi / Vw x n2 x Ef
Q5 237.14 m3
Jam = Wr
Koefisien alat / m3 = 1 / Q5 0.0042 Jam

f. Alat bantu
Sekop = 3 buah

3. TENAGA

Produksi menentukan : Motor Grader Q3 183.96 m3 / Jam


Produksi timbunan / hari = Ew x Q3 Qt 1287.75 m3
Kebutuhan tenaga : - Pekerja UL 10 Orang
- Mandor FO 1 Orang

Koefisien Tenaga / m2
- Pekerja = (Ew x UL) / Qt L1 0.0621 Jam
- Mandor = (Ew x FO) / Qt L4 0.0062 Jam
FORMULIR STANDAR
Analisa MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : ……..


JENIS PEKERJAAN : Pekerjaan Timbunan Material Pilihan (Sirtu)
SATUAN PEMBAYARAN : m3

HARGA
NO. KOMPONEN SATUAN KOEFISIEN SATUAN
($)

A. Tenaga
Pekerja Jam 0.0621 0.71
Mandor Jam 0.0062 1.71
Jumlah harga tenaga

B. Bahan
Bahan Timbunan Sirtu m3 1.2000 7.84
Jumlah harga bahan

C. Peralatan
Hydraulic Excavator 0.90 cu.m. Jam 0.0593 75.00
Dump Truck 5.5 Ton Jam 0.2264 15.00
Motor Grader >125 hp Jam 0.0054 90.00
Vibratory Drum Roller 3-5 Ton Jam 0.0111 60.00
Water Tank Truck with Pump 5000 liter Jam 0.0042 25.00
Alat Bantu LS 0.0000
Jumlah harga peralatan
D. Harga Satuan Pekerjaan (A+B+C)
Note :
1 Satuan untuk Tenaga Kerja dan Peralatan berdasarkan Jam kerja operasi, untuk bahan-bahan
berdasarkan volume dan/atau berat.
2 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
3 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk
pajak yang dibayar dari kontrak) dan biaya-biaya lainnya.
KETERANGAN

Borrow pit

* Kond. kerja : Sedang

Pemelh. Mesin :

Agak sulit

** Kondisi dumping :

Mudah
Hasil uji
Hasil uji
KETERANGAN

* Kond. kerja : Sedang

Kurang baik

Hasil uji

Perbaikan jalan, perataan

Perbaikan jalan,
perataan

Hasil uji

* Kond. Operasi :

Sedang

Pemelh. mesin :

Sedang
Baik

KETERANGAN

* Kond. Operasi :

Sedang

Pemelh. mesin :

Sedang

Baik

Lump sum
JUMLAH
HARGA
($)

0.04
0.01
0.06

9.41
9.41

0.49
0.67
0.11
0.00
1.26
10.72
tidak termasuk

Potrebbero piacerti anche