Sei sulla pagina 1di 4

ASPHALTIC SURFACING OF CUCERD WORKSHOP

ITEM DESCRIPTION QTY UNIT RATE AMOUNT


ROAD AND CAR PARK
A Excavate top soil average 150mm 1609 m2 120.00 193,080.00
deep and cart away

B Provide, spread and compact 241 m3 6,200.00 1,494,200.00


laterite material to serves as stone
base material to serve as base
course 0.15m thick

D Provide and spray prime coat MC-1 1609 m2 220.00 353,980.00


cut back bitumen at the rate of
1litre/M2

E 50mm thick Asphatic wearing 1609 m2 3,000.00 4,827,000.00


course laid to all necessary falls and
cross as specified and directed on
site

PRECAST CONCRETE KERBS


G Precast concrete kerbs in foundation 444 m 1,350.00 599,400.00
bedded and jointed with cement
mortar (1:3) including excavations,
blinding and all necessary backings
and haunchings

CARRIED TO SUMMARY 7,467,660.00


ASPHALTIC SURFACING OF CUCERD WORKSHOP

ITEM DESCRIPTION QTY UNIT RATE AMOUNT


WALK WAY
A Excavate trench maximum depth 57 M3 400.00 22,800.00
not exceeding 1.0m starting at
formation level

B Remove surplus excavated materials 29 M3 300.00 8,700.00


from site
C Laterite fillings to make up levels 52 M3 1,600.00 83,200.00

not exceeding 200mm thick

including spreading and compacting

LEVEL AND COMPACT


D Level and compact bottom of 127 M2 40.00 5,080.00
excavation to receive concrete.

CONCRETE WORK
E Plain In-Situ Concrete base (1:3:6- 14 M3 19,500.00 273,000.00
38mm aggregate) in trenches laid
on earth

BLOCKWORK
F 225mm sandcrete hollow blockwall 127 M2 2,900.00 368,300.00

filled solid with weak concrete

G Concrete 1:2:4-19mm aggregates in 64 M3 23,500.00 1,504,000.00


walkway pavement filled into
formwork (measured separately)
and well packed around
reinforcement

H BRC mesh Fabric reinforcement 365 M2 550.00 200,750.00

lapped at joints and intersection


J Forwork to edges of concrete 41 M2 1,100.00 45,100.00
pavement 125mm high
ASPHALTIC SURFACING OF CUCERD WORKSHOP

CARRIED TO SUMMARY 2,510,930.00

SUMMARY

PRELIMINARIES 700,000.00

ROAD, CARPARK AND KERBS 7,467,660.00

WALK WAY 2,510,930.00

CONTIGENCY 1,200,000.00

GRAND TOTAL 11,878,590.00


ASPHALTIC SURFACING OF CUCERD WORKSHOP

TO GRAND TOTAL 28,632,755.00

Potrebbero piacerti anche