PROJECT IMPLEMENTATION, MONITORING AND EVALUATION SYSTEM
THE TRADITIONAL ORGANIZATION We will refer here to the normal organization as line or functional. Staff departments are part of the normal organization and can be viewed as functional or line. Although many have attacked current hierarchical line organizations as bureaucratic and unable to accomplish goals efficiently, the traditional structure has lasted a long time—for several reasons. First, the line or functional organization represents stability for employees. It is a home. There are existing relationships and controls within departments. A standard organization has an existing vertical communications system already in place. Communications channels are established and tested. There is better technical control in line organizations. People who have hard to- find skills can be used on many different activities. Line organizations are set up to handle routine and recurring tasks. Mass production is an example. For these reasons, many companies have attempted to undertake projects within current organizations. FAILURE OF LINE ORGANIZATIONS IN PROJECTS Most of the times line organization fails to support the projects undertaken by the company due to the following reasons 1. Lack of Focus and Attention 2. Inability to Cope with Different Project Characteristics 3. Feelings of Being Used and Exploited 4. Lack of Project Experience Matrix organization is hence focused to be the most suitable structure for projects management MATRIX MANAGEMENT A matrix organization appears as a table of row and columns: line departments are rows; projects are columns. People in the organization belong to a row or line organization. When they are required on a project, they move to that column. We could create an artificial column called unassigned for people who are waiting for an assignment or have just completed the assignment. Companies that carry out government and private projects have sometimes organized themselves into matrix organizations. Advantages 1. Very good for project-oriented companies 2. Ensures that people on projects are utilized (as otherwise they are returned to the pool) 3. Project manager tends to be powerful in getting resources 4. Accountability and tracking of projects improved 5. Possibility that people who move between projects can build skills 6. Provides formal structure for projects of medium to large size 7. Ability to track what people are working on in projects Disadvantages 1. Good people will be in heavy demand for projects; others, who are not so good, will sit in the unassigned pool. 2. Difficult to assign control between project and line management. 3. Line managers tend to be weak. 4. Projects with long lives tend to be confused with line organizations. 5. Difficult to share resources between projects 6. More difficult to have lessons and skills cross projects—less chance for organization history 7. Project prospers and traditional organization suffers 8. More difficult to anticipate resource needs and to staff for requirements 9. More difficult to address small projects Project Planning Project planning and a project monitoring includes Project planning o Definition of work requirements o Definition of quantity and quality of work o Definition of resources needed Project monitoring o Tracking progress o Comparing actual outcome to predicted outcome o Analyzing impact o Making adjustments Some of the main benefits that are associated with a fully integrated project planning and control system are: o Estimating: the estimate forms the basis of the project plan. If you cannot estimate and measure it, how can you manage it? The performance of the current project will form the estimating data base for future projects. o CPM: the Critical Path Method calculates the activities start and finish dates, together with the critical activities which determine the duration of the project- delaying a critical activity will delay the project o Project Integration: Co-ordinates and integrates the contribution of all the project participants o Reporting Interfaces: The planning and control system’s data base can be structured around the work breakdown structure (WBS) for project reporting and around the organization breakdown structure (OBS) for corporate reporting. Without integrated system the two reporting requirements would have to be processed separately. o Response Time: Timely response on project performance is essential for effective project control. The project planning and control system can adjust the content and frequency of the feedback to address the needs of the project, while the corporate systems may be less flexible. o Trends: Projects are best controlled by monitoring the progress trends of time, cost and performance. This information may not be available to the project manager if the trend parameters are derived from a number of different functional sources o Data Capture: If the project progress reporting is based on information supplied by the functional departments, the project manager cannot control the accuracy of this information. The problem here is that it may only become obvious towards the end of the project, that the reporting is inaccurate, by which time it may be too late to bring the project back on course in order to meet the project’s objectives. o Single Point of responsibility: With the project manager responsible for the complete project, this should limit scope overlap and scope under lap. o Procedures: The planning and control system enables the project manager to develop procedures and work instructions which are tailored to the specific needs of the project. o Clients: the project manager is the project’s single point of responsibility and the company’s representative to the client. During meetings with the client the planning and control system will provide information about every aspect of the project
Project Planning Process
Most of the projects of low complexity will bias the ratio of planning: action heavily towards the action. As complexity increases, so does the necessity for a formalized plan. This is both a systematic analysis of the project.
Work Breakdown Structure (WBS)
The breaking down of large activities into comprehensible or manageable units is a
fundamental part of project management. WBS is also known as 'chunking' or 'unbundling'. This is attractive as it gives people responsibility for a manageable part of the project. WBS also facilitates financial control activities, as individual parts can have their consumption of resources tracked. The sensitivity of such control is preferable to keeping track of a single large activity. The role of WBS is to create a linked, hierarchical series of activities which are independent units but at the same time still part of the whole. The hierarchical structure can be represented using the input, output, constraints and mechanisms
Project Monitoring and control
The basis of project monitoring systems is to track actual progress against planned progress at any given time. This covers financial progress (monitoring of actual expenditure against budgeting expenditure) as well as the progress of project activities. Monitoring systems should be considered alongside the implementation plan because it is the targets set out in this plan which forms the targets for monitoring. The whole system is therefore often referred to as an “integrated planning, implementation and monitoring system” (IPIMS). Monitoring systems should: At all times be concerned with future progress. Be simple and cost effective. Be able to detect deviations quickly and accurately. Be verifiable. When designing a monitoring system, the project formulation should keep the following points in mind: Identify key personnel or informants for the monitoring information. These could include line mangers, accountants, contractors and suppliers etc. Indicate frequency of data/information collection time. Remember that data is only effective once it has been processed. Identify responsibilities for data processing. Assign also responsibilities to act on the result of these data. Try to attain the right combination of speed and accuracy. Sometimes a trade-off has to be made between the two, with information that is extremely accurate leading to delays in taking effective remedial action. Make sure that the monitoring system only intends to processes that data which is necessary. Monitoring information increases workload so it is important that only the most essential data is requested for processing. Monitoring systems in themselves are ineffective unless they are linked to an effective control system which will allow the manger to take swift and effective action to remedy any deviations from the implementation plan. Systems concerned with implementation measure the project’s effectiveness in converting inputs to outputs; while monitoring systems concerned with operations measure the project’s effectiveness in converting outputs into immediate and wider objectives. Information acquired through monitoring systems can be divided into three categories: Monitoring of physical progress Monitoring of financial progress Monitoring the quality of project outputs. MONITORING PHYSICAL PROGRESS: The primary purpose of physical progress monitoring is to ensure whether project activities are on schedule. This can be achieved through milestone (target) monitoring and time chart monitoring. Milestone monitoring involves the use of project milestones which were identified as part of the project implementation plan. The actual date on which these milestones were reached can be entered in table form or on the Gantt chart. Milestone monitoring provides a retrospective record of project progress, but it is unable to provide us with information about activities which are still in progress. Time chart monitoring is a method which is used to anticipate whether or not milestones will be reached on schedule. When dealing with physical progress of an activity there are three possible scenarios: Activity outputs can be quantified as a single number. This is relatively simple to monitor. for example, if the activity was to print a certain number of textbooks then both the physical target and progress to date can be expressed in terms of this single number (for example, 250 books printed out of a target of 1000). Activity outputs can be measured and valued. This is the case with the construction of buildings and roads. progress towards meeting physical targets should be expressed as: When dealing with direct labor the planners must be careful not to equate the value of the work done with financial spending. The planners should devise methods to measure actual physical progress. Activity outputs cannot be directly valued. This is the case in activities such as training or in supply-only contracts. These activities should use milestones to mark the beginning and end of each separate activity phase. if this is not possible, physical progress can be expressed as: Time spent to date X 100(%) Total time to complete This can be problematic because the time taken may not bear any relation to the actual amount of physical progress towards activity completion. Once physical progress has been monitored for all ongoing activities, it is possible to plot this information against the implantation plan in the form of a bar chart. MONITORING FINANCIAL PROGRESS: This involves comparing actual expenditure against the financial plan (budget) produced as part of the implementation plan. The project must therefore have a cost reporting system in place to enable a comparison of actual and predicted costs. It is unwise to rely on existing accounting systems to provide this information as these systems are liable to be slow and to categorize expenditure using different methods to those desired by the project manger. As many authors note “public sector mangers will need to take particular care that they keep a measure of overall spending of the project against overall budget……managers are not able to spend above each year’s authorized budget, so that cost over-runs are met by delaying implementation, or reducing the scope of the project to compensate.” Once the manger has access to accurate cost data, it is possible to utilize this information in the process of project cost control. Using the following relationship can do this: Cost of work to date = Cost of work remaining Value of work to date Value of work remaining The information gained through this calculation can then be entered in tabular form. MONITORING THE QUALITY OF PROJECT OUTPUTS: This involves ensuring that outputs are delivered according to specification. This is normally done through a system of direct inspection and supervision. A formal agreement between the implementing agency and the project owner that project outputs are satisfactory is known as ‘signing-off’. Each project will have its own quality assurance features in operation and it is important that the quality control aspect is not overlooked during project design. EVALUATION: Evaluation is the structured process by which a project activities and achievements are assessed and understood. It provides information for those who are involved in the project such as managers, promoters, funders and/or policy makers. Evaluation in addition to quantitative questions attempts to answer also qualitative questions. Evaluation could be ongoing (mid term), terminal or ex post. A good evaluation system in a project from the outset may assist the project implementers in identifying difficulties that hinder the progress as planned and avoid repeating mistakes in future endeavors. It is therefore, crucial to identify the main actors for the evaluation exercise during the project formulation. The preliminary function of evaluation after project completion is to use data on the performance of projects in such a way that new projects can learn from experience. PROJECT SUSTAINABILITY: A project is sustainable if its net benefits continue throughout the life of the project at a level sufficient to meet the predetermined objectives. Sustainability is, therefore, the ability of a project under consideration to continue operation or provision of services and/or production without interruptions for the period under design. It also includes the managerial and technical capacity and capability of the project personnel in the operation and running of the project to meeting its desired objectives. The aim of any development project is to meet its predetermined objectives/goals on sustainable basis. If the project formulators fail to consider what will happen upon completion of the project’s implementation phase, then however well implemented, the project is liable to encounter serious problems in providing the required services and/or production. Full coverage and exhaustive analysis of project aspects such as: demand/need, technical, environmental, social, institutional, financial, and economic analyses are critical for the sustainability of a project under consideration. Furthermore, risk, uncertainty and distributional analysis are vital to ensure the sustainability of a project. Project planning, therefore, should also need focus on project handover, operations, maintenance and termination arrangements so that implementation and operation phases are smooth and clear. To ensure that the transition between the project’s implementation and operation phase is as smooth as possible consider the following strategies in the formulation of the proposed project: Ensure that project handover, operation and termination arrangements are properly planned and responsibilities identified from the outset. Ensure that the handover operation and commissioning period is smooth in order to use newly created facilities and utilities to use them in the most efficient and effective manner. Ensure that project handover procedures have included acceptance tests, relevant safety and quality standards set by the project or responsible authority. Ensure that the process of project operation is properly monitored and changes to be achieved during operation are evaluated. Ensure that adequate maintenance facilities and operation arrangements are in place for the proposed technology or system of operation. Ensure that the institutional and financial arrangements for project operations should be clearly outlined at the project formulation stage. Ensure that adequate financial provision has been made for maintenance needs, which may arise during operations. Examine thoroughly that financing arrangements for future operation, especially with relation to the funding of recurrent costs. Ensure that the body responsible for project operations should have adequate organizational capacity in order that it will be able to sustain operations. Ensure that proper management information system is in place with practically applicable tools to successfully implement and operate a project. Ensure that the project’s technical design utilizes technology, which is easy to maintain within the environment in which it will operate. Summary of Project Analysis and Overall Decision Project Profile Project Title: _________________________________________________ Project Code: ________________________________________________ Specific area where project will be implemented: ____________________ Sector within which a project will be implemented: __________________ Responsible Authority: ________________________________________ Scheduled Start Date: _________________________________________ Scheduled completion Date:____________________________________ Total Budget: ________________________________________________ Sources and Terms of Project Financing: __________________________ Summary of Project Analysis: Issues of Project Preparation Good Satisfactory Unsatisfactory Comments Technical aspect Environmental aspect Social aspect Institutional aspect Financial aspect Economic aspect Sensitivity analysis and Risk Overall Decision: Accept Reject Redesign Comment (action to be taken/by whom)