Sei sulla pagina 1di 7

Supplement for Earthwork Quantities through Geopak

Proposed Project:

Roadway: FM 1607
County: Scurry
Range: Station 125+00 to 172+00
Proposed: Cut Section Station 140+00 to Station 151+50
Fill Section Station 151+50 to Station 172+00
Tie into existing grade @ Station 125+00 and Station 172+00

Geopak Data:
Chain: G
Profile: PROP2
DTM: 1607.TIN
General Project Information:
No superelevated surface.
Pavement Slope Constant ¼” per 1’ (2.08%)
22’ of pavement, 2~11’ lanes undivided
4” HMACP
6” New Flex Base
Rework Subgrade 6”

Governing Specifications:
Item 110 ~ Excavation
Payment by the Cubic Yard (CY)
Quantity of excavation is measured to the top of finished subgrade
Undercut (6” depth) is considered incidental to Item 110
Item 132 ~ Embankment
Payment by the Cubic Yard (CY)
Payment is for compacted volume
Item 247 ~ Flexible Base Material
Payment by the Cubic Yard (CY)
Payment is for compacted volume

Page 1 of 7
Supplement for Earthwork Quantities through Geopak (continued)

Files (Microstation and Geopak)


Initial Seed Files ~ Exsseed.dgn (for cross-section processing)
42022d.dgn (2d seed file relevant to this area of Texas as per NAD83)
42023d.dgn (3d seed file relevant to this area of Texas as per NAD83)
Survey Data ~ 1607_2d.dgn
1607_3d.dgn
Design Drafting/Cross-Section Preparation ~ Plan.dgn
Pattern File for Cross-Sections ~ Patt.dgn
Shape file ~ Shape.dgn
Existing XS ~ xs.dgn
Proposed XS ~ xsd.dgn
Geometry ~ job607.gpk
Mike607.imm ~ gpk backup
Input file design.inp (cross-section generation)
Shape File shape.inp (shape creation)
Earthwork Calculations Erthwrk.inp (earthwork calculations)
Earthwork Output erthwrk.log (earthwork run output)
pavement.x (criteria file)
slope.x (criteria file)

Patterns
Pattern Lines Define X-Sect Location, Orientation and Length
Level 4
Color 4
Style 4
Weight 4

Page 2 of 7
Supplement for Earthwork Quantities through Geopak (continued)

GPK File
job607.gpk Main gpk file
Backup file is ASCII text file
Name, mike607; “mike” any text here
“607” job number

Extension, imm; “i” for input


“mm” for user initials

Page 3 of 7
Supplement for Earthwork Quantities through Geopak (continued)

X-Sect Files
Existing Cross Section File, xs.dgn (and xsd.dgn)
Cross-section Cell
Level 63
Elevation Reference for Each X-Sect
Coordinate Reference in relation to Station

Design file, xsd.dgn must duplicate original ground file xs.dgn and both must exist to
create sections.

Natural Ground Line


Level 55
Color 5
Style 5
Weight 2

Variable definitions
Total pavement depth = 4”
Define”pavement”0.33
Define”base”0.50

File element definitions


Define_dgn "BASELINE"\
dgn = baseline.dgn
lv=3
co=5

Any reference to “baseline” in the criteria file will point to elements on level 3 and color
5.

Page 4 of 7
Supplement for Earthwork Quantities through Geopak (continued)

Earthwork Steps

After initial geometrics and project setup,


1) Define Project
a) Extent of Work
b) Method of Payment
2) Existing Ground Sections
3) Proposed Ground Sections
4) Define earthwork limits in earthwork.inp
5) Run earthwork.inp and generate earthwork.log

Page 5 of 7
Supplement for Earthwork Quantities through Geopak (continued)

Station 125+00 Existing Ground X-Section

Station 125+00 Proposed X-Section

Page 6 of 7
Supplement for Earthwork Quantities through Geopak (continued)

Station 125+00 with Earthwork Shapes

Earthwork Output Data

Final Tabulation
Excavation = 7102 CY
Embankment = 16928 CY

Page 7 of 7