15-Dec-10

MILESTONE
Contract Signed
3-Feb-12
Ground Breaking
December 2015
Project Hold
22-May-17
Project Restart
(Amend 10 Signed)
11-Oct-17
Kick of Meeting
29-Oct-17
Civil Activity Start
SUMMARY WORK PRIOR TO COMMISSIONING
PLTU MALINAU 2X3 MW

15-Jul-18
Mechanical Activity Start
2-Apr-19
BACKFEEDING

Remaining Due Date

Civil
1. MCC
- Installation 17-Mar-19 Remaining Due Date Remaining Due Date
- Wiring Cable 24-Mar-19 1. MPH building 14. Laboratory Building
2. UPS, Battery & Charger - Cladding & roofing of boiler house 19-Apr-19 - Architectural 8-Mar-19

- Shipment 3-Mar-19 - Brickwall Installation 13-Mar-19


15. Fire Figthing Building
- Installation 21-Mar-19 - Architectural 27-Mar-19 - Architectural 8-Mar-19

3. Transformer 2. Admin Building 16. Mosque


- Installation 23-Mar-19 - Architectural 17-Mar-19 - Cladding & Roofing 18-Mar-19
4. Cable System (Incl. Cable Tray) 3. WTP Building - Architectural 8-Apr-19
- Installation 1-Apr-19 - Architectural 1-Apr-19 17. Garage
4. Storage waterpond - Cladding & Roofing 1-Apr-19
- Waterproofing 15-Mar-19 - Concrete repair (Slab) 11-Mar-19
5. Clarifier - Architectural 8-Apr-19
- Waterproofing 22-Apr-19 18. Guard House
6. WWTP - Concrete work 25-Mar-19
- Chemical Coating 27-Mar-19 - Architectural 22-Apr-19
- Architectural 1-Apr-19 19. Site Drainage
7. CW Pump House - Concrete work 31-May-19
- Architectural 1-Apr-19 20. Parking Area
- Grouting of Pump Foundation 1-Mar-19 - Paving Block 22-Apr-19

8. Weight Bridge Building 21. Plant Road


- Building 15-Mar-19 - Soil Filling 18-May-19
- Architectural 22-Mar-19 - Aspalt Layer 20-Jun-19

9. Coal yard 22. Road Lighting


- Soil Filling & HDPE Layer 17-Feb-19 - Concrete Work 18-Mar-19

- Coal bed 24-Feb-19 23. Perimeter Fencing


10. Dry Coal Shed - Concrete Work 25-May-19

- Soil Filling & HDPE Layer 17-Feb-19 - Brickwall & Fencing 1-Jun-19

- Coal bed 24-Feb-19

11. Coal Run Of


- Concrete work 8-Mar-19

- Chemical Coating 4-Apr-19

12. Ash Yard & Settling Pond


- Soil Filling & HDPE Layer 8-Mar-19

- Concrete work 14-Mar-19

13. Workshop & Warehouse Building


- Cladding & Roofing 4-Mar-19

- Architecture 18-Mar-19
SSIONING

19-May-19
Erection Essentially Complete
29-May-19
Preliminary Inspection & Checkout and
Mechanical Electrical & Instrumentation Individual Test Period
Remaining Due Date Remaining Due Date
1. Boiler Island 13. Turbine & Generator
- Cashing of boiler Incl. Rockwool 19-Apr-19 - Installation 23-Apr-19 Remaining Due Date

- Chemical Pasivation 5-May-19


14. Condensor System 1. Test of Individual Equipment (If Possible)
- Individual test Chain Grate 4-May-19 - Installation 16-Apr-19 - Start Up of Misscellaneous Equipment 20-May-19

- Installation of Refractory 10-Apr-19 - Individual Test 23-May-19


15. Fuel System
- Installation of Insulation 1-Apr-19 - Installation of Pump & Dispenser 6-Apr-19 2. Start Boiler
- Boiler Drying 14-Apr-19 16. Emergency Genset - Boiler Washing 24-May-19
- Individual Test of Fan System 3-May-19 - Installation 12-Mar-19 - Auxilliary Interlock Protection Test 25-May-19
2. Water System 17. Cable System (Incl. Cable Tray) - Furnace Drying 14-Apr-19
- Installation of Ponton 17-Feb-19 - Installation 1-Apr-19 - Boiler Ignition Test (if Applicable) 23-May-19
- Installation of WTP System 8-Apr-19 18. Lighting System - Chemical Boiling 28-May-19
- Installation of WWTP System 8-Mar-19 - Installation 18-Mar-19 - Steam Blowing Pipe 29-May-19
3. Boiler Water System (External Pipe) 19. Lightning System - Boiler Safety Valve Adjustment & Boiler Main Protection Test 29-May-19
- Installation of Piping System 19-May-19 - Installation 18-Mar-19
4. Cooling Tower System 20. Instrumentation
- Finishing 19-May-19 - Field Instrument 1-May-19
5. Sampling Rack System - DCS System 1-May-19
- Installation 12-Mar-19 - Instrument cable system 26-Apr-19

6. Pump - Control system 1-May-19

- Installation 4-Apr-19 21. CCTV System


7. BOP Pipe - Installation 2-Mar-19

- Installation 9-Mar-19 22. Workshop Equipment


8. Pipe Rack - Installation 19-Mar-19

- Installation 7-Mar-19 23. Mobile Equipment


9. Spiral Pipe - On Site 20-Apr-19

- Installation 25-Mar-19 24. Laboratory Equipment


10. Steam System - On Site 20-Apr-19

- Boiler 24-Mar-19 25. Fire Fighting System


- Turbine 24-Mar-19 - On Site 28-Apr-19

11. Ducting 26. AC & Ventilation


- Boiler to ESP 1-Mar-19 - Installation 28-Apr-19

12. Coal Handling System 27. PABX (Communication System)


- Conveyor Drive system & Take up Device 30-Mar-19 - Installation 28-Apr-19

- Coal Crusher 30-Mar-19

- Coal Bunker 30-Mar-19

- Coal Hopper 30-Mar-19


18-Jun-19
Unit/Common System Test Period
20-Jun-19
Operational Readlines
Certificate Issued
Remaining Due Date 20-Jun-19
Final Acceptance
Certificate
1. Syncronization of Steam Turbine Generator
- Loading Test Include 10% Overspeed 1-Jun-19 Remaining Due Date
- Load Rejection Test from 50% to 100% MCR 1-Jun-19 1. Boiler Certificate 12-Jun-19
2. Inspection & Adjustment 2. Ash Yard Permit 3-May-19
- Shutdown 9-Jun-19 3. Jetty Operational Permit 12-Jun-19
3. Commecial Operation 4. Power Plant Operational Permit 20-Jun-19
- Guarantee Performance Test 18-Jun-19
- 30 Days Reliability Run Incl. 96 hours full load continuous