Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
MILESTONE
Contract Signed
3-Feb-12
Ground Breaking
December 2015
Project Hold
22-May-17
Project Restart
(Amend 10 Signed)
11-Oct-17
Kick of Meeting
29-Oct-17
Civil Activity Start
SUMMARY WORK PRIOR TO COMMISSIONING
PLTU MALINAU 2X3 MW
15-Jul-18
Mechanical Activity Start
2-Apr-19
BACKFEEDING
Civil
1. MCC
- Installation 17-Mar-19 Remaining Due Date Remaining Due Date
- Wiring Cable 24-Mar-19 1. MPH building 14. Laboratory Building
2. UPS, Battery & Charger - Cladding & roofing of boiler house 19-Apr-19 - Architectural 8-Mar-19
- Soil Filling & HDPE Layer 17-Feb-19 - Brickwall & Fencing 1-Jun-19
- Architecture 18-Mar-19
SSIONING
19-May-19
Erection Essentially Complete
29-May-19
Preliminary Inspection & Checkout and
Mechanical Electrical & Instrumentation Individual Test Period
Remaining Due Date Remaining Due Date
1. Boiler Island 13. Turbine & Generator
- Cashing of boiler Incl. Rockwool 19-Apr-19 - Installation 23-Apr-19 Remaining Due Date