Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
INSTITUTE OF TECHNOLOGY
SCHOOL OF CIVIL ENGINEERING
M.S.C in CONSTRUCTION TECHNOLOGY AND
MANAGEMENT
Course: Construction Contract & Law
Risk: it’s Regulation & Management under the MDB-FIDIC (2006) & the PPA
(2011) Conditions of Construction Contracts & the Applicable Laws: with
special emphasis to Construction Insurance Practice in Ethiopia
Submitted by:
Acknowledgements
First of all we would like to thank God for his guidance in all our way and our next deepest appreciation
goes to our instructor Mr. Zewudu Tefera (Engineering Contracts Lawyer) for his endless share of
academic knowledge and advice to perform our project study well.
Finally, we would like to thank all those who assisted us in providing the data and information
what we needed to accomplish our task successfully.
Abstract
Risks have a significant impact on a construction projects performance in terms of cost, time and
quality. As the size and complexity of the projects have increased, an ability to manage risks
throughout the construction process has become a central element preventing unwanted
consequences. Managing risks in construction projects has been recognized as a very important
management process in order to achieve the project objectives in terms of time, cost, quality,
safety and environmental sustainability. Poor contract management was found to be one of the
major causes of risk which has a high probability of occurrence and a high level of impact on
project objectives.
The main objective of this paper is to study the impact of risk management on construction
projects success with respect to insurance coverage specifically to contract condition that of
FIDIC Multi-lateral Development Bank and Federal Public Procurement Agency of Ethiopia.
Different literatures were assessed to show that risk management is a very important
management process that helps in making projects successful. Risk management is a process
which consists of identification of risks, assessment with qualitatively and quantitatively,
responses with a suitable method for handling risks, and then controls the risks by monitoring.
Contents
CHAPTER ONE ............................................................................................................................. 1
1 INTRODUCTION ................................................................................................................... 1
1.1 Background of the project ................................................................................................ 1
1.2 Objective of the study ...................................................................................................... 2
1.2.1 General objective ...................................................................................................... 2
1.2.2 Specific objective ...................................................................................................... 2
1.3 Significance of Study ....................................................................................................... 2
1.4 Scope of the research........................................................................................................ 2
1.5 Organization of the research ............................................................................................ 2
1.6 Research methodology ..................................................................................................... 3
CHAPTER TWO ............................................................................................................................ 4
2 LITERATURE REVIEW ........................................................................................................ 4
2.1 Risk Definition ................................................................................................................. 4
2.2 Construction ..................................................................................................................... 5
2.3 Construction Risk ............................................................................................................. 6
2.4 Insurance .......................................................................................................................... 8
2.4.1 Definition of Insurance ............................................................................................. 8
2.4.2 Principles of Insurance .............................................................................................. 9
2.4.3 The Insurability of Risks ......................................................................................... 11
2.4.4 The Uninsurablity of Risks ..................................................................................... 11
2.5 Construction Insurance ................................................................................................... 12
2.5.1 Type of Construction Insurances ............................................................................ 12
2.6 Risk management ........................................................................................................... 14
2.7 Contract and Risk Allocation ......................................................................................... 17
CHAPTER THREE ...................................................................................................................... 19
3 Risk In General ...................................................................................................................... 19
3.1 Risk Definition ............................................................................................................... 19
3.2 Scope of Risk in General ................................................................................................ 19
3.3 The Concept of Risk Management ................................................................................. 21
3.4 Process of Risk Management ......................................................................................... 21
3.4.1 Risk identification ................................................................................................... 21
3.4.2 Risk assessment ...................................................................................................... 22
List of Tables
Table 1 Risk assessments for health and safety risks ................................................................... 25
Table 2 Basic Contract Data of Kibremengest-Shakiso Project ................................................... 67
Table 3 the remaining work of the project .................................................................................... 68
Table 4 Comparative analysis of MDB FIDIC 2006 and FPPA 2011 with respect to risk and ... 72
List of figures
Figure 1 Risk Management Framework (Source: PMI PMBoK, 2013). ...................................... 14
Figure 2 Risk Ranking Matrix ...................................................................................................... 23
Figure 3 Risk Categorization Framework ..................................................................................... 43
CHAPTER ONE
1 INTRODUCTION
1.1 Background of the project
Among other things, it requires interpretation of and compliance with many laws, codes, and
regulations; gathering of considerable resources, including labor, equipment, and material; and
communications with and coordination among multiple parties, such as the owner, the design
professional, other contractors and subcontractors, and suppliers, all of whom may have differing
purposes and goals. In addition, many factors are unknown or unknowable at the start of any
project. Not surprisingly then, risks are an expected part of this process.
In theory, risk is usually defined as a positive or negative deviation of a variable from its
expected value. Risk arises when uncertainty has the potential to affect objectives. In order to
turn risks into chances, the business owner must first know his / her risk sufficiently well. Risk
management constitutes a strategy to avoid losses and use available chances or rather chances
potentially arising from risks. The strategy demands from the person taking action a precise
consideration and assessment of the situation and the scenarios probably occurring in the future.
On this basis, decisions are made in the hope of having eliminated all risks and used all chances.
This means recognizing potential risks and circumventing a threat by averting, evading or
reducing their negative effects.
There are many typical construction risks that might impact a contractor’s success on a project.
These risks could be attributed to a number of reasons, which include the nature of the
construction process, the complexity and time-consuming design and construction activities, and
the involvement of a multitude of people from different organizations with different skills and
interests. Hence, a great deal of effort is required to co-ordinate the wide range of activities that
are undertaken.
Risks might show up due to different factors during the execution of the construction project,
some of the factors are Payment delays, Funding problem for projects, Accidents/safety,
Defective design, Inaccurate schedule ,Poor performance of subcontractors ,Exchange rate
fluctuation and inflation, Improper scope of work definition in a contract, Poor quality of
materials and equipment Shortage/delay of material supply.
The second chapter presents literature review with general descriptions of by different
scholars on concept of risk, risk management, risk in construction and insurance.
The third chapter discusses about risk in general
The fourth chapter discusses about construction risk in various projects phases and its
management
The fifth chapter contains risk management in Ethiopian building construction contracts.
The sixth chapter discuss about construction insurance practice in Ethiopia.
The seventh chapter contains the role of professional engineers on Construction risks.
The eighth chapter contains case study related to the research.
The ninth chapter is Comparative Table & Analysis of risks of contractors and employers
based on MDB-FIDIC-2006 & PPA-2011; and the applicable laws.
The tenth and last chapter is about conclusion and recommendation of the study.
CHAPTER TWO
2 LITERATURE REVIEW
This chapter presents the findings from different reviewed literatures on the subjects of risk
management. This includes a generic definition of risk, risks management and their method.
The risk facing any project depends on the type and methods of construction, the stage of
construction, the type of contract and delivery system and project type and complexity etc.
similarly the risk management technique that should be applied also depends on the above
factors. Hence, the literature review tried to highlight these issues in relation to risk with the
main focus being on management of construction risk starting from the contractual stage.
2.1 Risk Definition
Before discussing about risk management it would be better to understand what the terminology
‘risk’ means. Etymologically, the origin of the English word ‘risk’; or ‘risque’ in French; and
‘rischio’ in Italian is uncertain. In Arabic, there is even confusion as to its real meaning—since
some say it simply means ‘danger’—(‘Khattar’ in Arabic), others refer to ‘Rizkk’, which
signifies what destiny bestows in the future for someone, positive or negative, good or bad;
whereas others use it wrongly to mean ‘Gharar’, a forbidden transaction under Islamic law. Of
course, the latter version cannot be right because if it were so, then a construction contract,
which is known to be exposed to a large number of risks, would not be permitted under Islamic
law. This simply does not make any sense nor can it be right. The Latin word ‘resecum’ meaning
‘danger’ or ‘rock’ may throw some light on the origin of the word ‘risk’, but the Chinese ‘wejji’
with the characters representing ‘opportunity’ and ‘danger’, is more illustrative of the concept of
risk as it applies to the construction industry( Nael G.Bunni. 2003).
Different literatures, professionals and standards define risk in their own way. But most of them
confirm that the view towards risk is most of the time negative. For Nael G.Bunni the risk can be
represented by the following mathematical expression:
Risk=Event × Probability of Occurrence, where the event is measured in terms of its intensity.
Bowen (2005) stated that despite the largely negative connotation of risk that prevails today, it
has to be conceded that one person's risk may be another's opportunity to profit. PMBOK
(Project Management Body of Knowledge) guide fifth edition also describes risk as an uncertain
event or condition that, if it occurs, has a positive or negative effect on a project’s objective. In
theory, risk is usually defined as a positive or negative deviation of a variable from its expected
value. In general parlance, risk is understood only as a loss. The definition of risk in the
meantime not least takes into account the chances.
Regardless of the continuing debate among risk management practitioners about the definition of
risk; there exist several attempts from different professional bodies and standard institutions to
propose a definition of risk that capture broad acceptance. However there is no one official
definition for risk. But it was discovered most standards use the word risk in its negative sense to
mean, chance of bad consequences, or exposure to mischance and some standards like the UK
define risk as an uncertain event or set of circumstances which, should it occur, will have an
effect on achievement of objectives.
Since the effect is not specified it could mean either negative or positive and taking this into
consideration risk has been defined by PMBoK, (2008), stated above.
2.2 Construction
A construction in simple words is a process of constructing something by human for one purpose
or another. It may be a road, bridge, a dam, a private residence, an airport, a commercial
building, etc. According to Wikipedia, construction is a process that consists of the building or
assembling of infrastructure. Construction is the recruitment and utilization of capital,
specialized personnel, materials, and equipment on a specific site in accordance with drawings,
specifications, and contract documents prepared to serve the purposes of a client. According to
Moavenzdadeh F. (1976), construction contributes to the economic development of any country
by satisfying some of the basic objectives of development including output generation,
employment creation and income generation and re distribution; it also plays a major role in
satisfying basic physical and social needs, including the production of shelter, infrastructure and
consumer goods.
A project is a temporary endeavor undertaken to create a unique product, service or result
(Project Management institute, 2008). According to Hillson D., (2009), all projects are risky and
there are three separate reasons for that. The first reason is that all projects share common
characteristics which inevitably introduce uncertainty. Some of this common characteristics are
projects are unique, complex, involve assumptions and constraints, performed by people and
involve change from a known present to an unknown future. The second reason is that all
projects are undertaken to achieve some specific objectives. The final reason is that all projects
are affected by the external environment they exist in.
Inflation
Local taxes
According to Martin Schieg (2006) in projects, in particular the following risks occur, which are
broken down according to risk types:
Quality risks
o Defect in interim results
o Lacking application of project methods
o Too few controls / tests
Personnel risks
o Lack of skills
o Disagreements in the team
Cost risks
o Planning changes
o Complicated project conditions
o Customer fails to pay
Set date / deadline risks
o No handover in good time
o The project end is delayed
Risks of strategic decisions
o Failure to recognize chances
o Lack of ability to consistently use chances
External risks
o Natural occurrences
o Political changes
o Changes in society
o A shift in the market / new markets
o Legal developments
o Shifts in sectorial trends
o Technological changes
IMCA risk guideline groups risks into the following main areas of risk in construction contracts
which are briefly discussed below;
Contractual risk: is risk which result from not clearly defining the responsibilities and duties
of the contracting parties. The contract clauses should be clear and easily understood by
everyone involved
Performance risk: is a risk due to clearly undefined scope and nature of work. The contractor
is expected to perform the work with some standard including safety. Different situations that
could hinder performance should be included in the contract. Incomplete information at the time
of bid can negatively affect the performance of the contractor.
Financial/Economical risk: are risks that are a result of not understanding the terms of
payment, performance bond, bank guarantee etc. The payment terms should reflect the progress
of the work and the parties should have the required financial backing from a reliable source.
Political risk: are risks that are especially significant when the construction is on a host
government’s site/country. The host country might interfere in the bidding and construction
process by changing laws and standards. The contractor needs a secure environment for
performing the construction and should be clearly stated in the bid as well as the contract
document.
Technical risk: this risk arises from lack of understanding of the system and the technology
that would be utilized at the time of bid and during construction.
Geographical risk: arise as a result of the location of the site. The location of the site is very
important and should be selected very carefully because it can lead to additional risks like
political risk. The stability, material supply interruptions, mobility and access should all be
considered during bid and contract agreement.
Operator risk: are due to the operators influence on the bid, contract, supervision, and
approval etc…the operator should have the required insurance coverage which should be clearly
stated in the contract document, for example, so that claims would lead to payment instead of
dispute. Underperformance of the operator should not affect the work of the contractor; therefore
there should be clear statements in the contract specifying the operator’s obligations and the
consequences to the contractor.
2.4 Insurance
C.Insurable interests: A fundamental requirement of insurance law is that the insured must
have an insurable interest in the subject matter of the insurance. An insurable interest is an
interest which is recognized and enforceable at law and it may be legal or equitable, a proprietary
right or a contractual right. An insurable interest is not required under general contract law, but it
is necessary under insurance contracts (Gould, 2003).
D.Subrogation: Subrogation is the complimentary principle of indemnity. The principle of
subrogation provides the insurer with two benefits (Gould, 2003):
• To stand in the shoes of the insured and avail himself of all the rights and remedies available to
the insured against the third parties and the action by the insurer is brought in the insured’s name
and the third party can raise any defenses which would have been available against the insured;
and
• To recover from the insured any benefit received by the insured from third parties which
reduces the loss covered by the insurance.
Article 683(1) of the Commercial code of Ethiopia (Code C., 1960) indicates the right of
subrogation of the insurer as: the insurer who has paid the agreed compensation shall substitute
himself to the extent of the amount paid by him for the beneficiary for the purpose of claiming
against third parties who caused the damage.
E.Contribution: If an insured subject matter is covered against a peril for the benefit of an
insured party by more than one policy, and if that peril eventuates into a loss, the insured cannot
recover from more than one insurer.
In that event, an insurer, having paid a claim, can seek a contribution from other insurers liable
for the same loss to contribute towards the payment made (Bunni, 2003). The right of
contribution under the Ethiopian case is specified under Article 681of the Commercial code of
Ethiopia.
i. Proximate cause: The principle of proximate cause is implied into contracts of insurance and
requires the insured to show that the loss was caused by an insured peril. Proximate cause means
the effect of the common, dominant or real cause of the loss and will be a question of facts in
each case. The principle may of course be modified or even excluded by the contract (Gould,
2003).
ii. Warranties: A warranty is a term of the insurance policy which if broken entitles the insurer to
terminate the contract from the time of the breach regardless of whether the breach is material. In
the law of insurance the term “warranty” is therefore used in a similar sense to that more readily
associated in general contract law with the term “condition”. Breach of a warranty justifies the
injured party’s refusal to further performance (Gould, 2003).
iii. Fortuity: The principle of fortuity is fundamental to the basic concept of insurance and the grant
of coverage.
Insurance responds to risk, rather than losses that were planned, intended or anticipated by the
insured (Karen, 2011). The term “fortuitous” means accidental, unintentional or unexpected.
Article 663(3) of the Commercial code of Ethiopia confirms that intentional damages are not
covered in insurance policy as: Notwithstanding any provision to the contrary, risks arising out
of the intentional default of the beneficiary shall not be covered by the insurance.
so when dealing with this issue because, otherwise, it could result in a dispute if repair to a
resultant damage is costly.
3) Political risks and risks on an international scale: War is a good example of these risks that
are normally uninsurable. The reason is that the principle of the contribution of many for the
benefit of an individual suffering loss breaks down in such a situation, unless governmental
institutions carry out the insurance.
4) Causation: To prove the cause of any damage on a project is to establish the responsibility
and liability for it and to establish whether or not the damage is covered through the provisions
of the insurance contract. If such a cause cannot be proven for any particular risk, the risk
becomes uninsurable.
• Compulsory (Liability) Motor Insurance; (in case of car accident or collision on road);
• Employer’s Liability Insurance; (to compensate the employer in case of the worker’s
negligence who injures third party); see also Article 2130 of the Civil Code;
• Professional Liability Insurance/Professional Indemnity Insurance ;( in case of Engineer’s or
Architect’s liability towards its client); and
• Workmen’s Compensation Policy; (to cover the liability of the employer to the worker as per
the Labor Law.
Risk
identification
Risk
Risk
monitoring
classification
and control
The International Organization for Standardization (ISO) in ISO 31000 identifies the following
principles of risk management:
Risk management should:
Create value
Be an integral part of organizational processes
Be part of decision-making
Explicitly address uncertainty
Be systematic and structured
Be based on the best available information
Be tailored
Take into account human factors
Be transparent and inclusive
Be dynamic, iterative and responsive to change
Be capable of continual improvement and enhancement.
Nael G.Bunni defined risk management is therefore concerned with the mitigation of those risks
deriving from unavoidable hazards through the optimum specification of warning and safety
devices; and risk control procedures, such as contingency plans and emergency actions.
If a decision is made to accept a risk, a further decision must be made on whether the risk should
be retained or whether it should be shared and if so with whom. Before such decisions can be
made, it is necessary to go through a systematic process, which involves the analysis of the
possible hazards to which the project may be exposed and the evaluation of their intensity,
frequency and return period.
According to Partnership Victoria guidance material (2001), risk management is used to identify,
prevent, contain and mitigate risks in order to achieve project objectives. It further explains risk
management as ongoing process throughout the project containing the following five steps.
Risk identification- The process of identifying all the risks relevant to the project;
Risk assessment- Determining the likelihood of identified risks materializing and the
magnitude of their consequences if they do materialize;
Risk allocation- Allocating responsibility for dealing with the consequences of each risk to one
of the parties to the contract, or agreeing to deal with the risk through a specified mechanism
which may involve sharing the risk;
Risk mitigation- Attempting to reduce the likelihood of the risk occurring and the degree of its
consequences for the risk-taker; and
Monitoring and review- Monitoring and reviewing identified risks and assessing, allocating,
mitigating and monitoring new risks as the project develops and its environment changes. This
process continues during the life of the contract.
According to Kajsa Simu, (2006), much of what is practiced is based on intuition or personal
judgment. The action taken to control the risks that are analyzed earlier are called risk responses.
Responses is often graded in four levels, namely risk retention, risk reduction, risk transfer and
risk avoidance.
Risk retention concerns accepting the presence of risk and still conducting business as usual. The
reasons for retaining the risk could be that the estimated probability, consequence or the
combination of the two is low and at an acceptable level.
Risk reduction is about decreasing the probability, the consequences or a combination thereof for
a risk to breakout. This could be done in several ways, of which sharing with other parties or
taking some action where the probabilities or consequences become reduced is common. There
could also be involvement of a third party as an extra assurance and quality control of projects to
ensure that nothing is forgotten or overlooked. A common way to reduce risks at construction
sites is through work planning. The work plans consist of timetables and allocation of resources
such as staff and equipment.
Transferring the risk to another party is a fairly common way to deal with risks in the
construction sector. It is transferred from the client to the contractor through the agreements in
the contract, or from the contractor to the sub-contractor. Another way to transfer the risk is to
have insurance, which is a way to transfer the uncertain cost for a potential loss to a certain cost
of money for the premium.
Risk avoidance is about refusing to accept a risk. This is either done by simply refusing a
project that is too risky to begin with or by writing exceptional clauses in the tender.
(IMCA, 2006) defines Risk management as the process by which the likelihood of risk occurring
or its impact on a project is reduced. Similarly it explains that the risk management function
contains the following five steps.
i. Identify the potential sources of risk on the project.
ii. Determine their individual impact and select those with a significant impact for full
analysis.
iii. Assess the overall impact of significant risk.
iv. Determine how the likelihood or impact of risk can be reduced.
v. Develop and implement a plan for controlling the risks and achieving the reductions.
According to (Bryan) several principles are often employed in the analysis of and management
of risk. A party to a contract should generally bear a risk where:
the risk is within the party’s control;
The party can transfer the risk (for example, by insurance), and it is most economically
Beneficial to deal with the risk in this fashion;
The preponderant economic benefit of controlling the risk lies with the party in question;
To place the risk upon the party in question is in the interests of efficiency, including
Planning, incentive and innovative efficiency;
If the risk occurs, the loss falls on the party in the first instance, and it is not practical or there is
no reason under the above principles to cause expense and uncertainty by attempting to transfer
the loss to another. Risk tends to be allocated on the basis of commercial and negotiating
strength (Bryan). Although not always the best way to proceed, the stronger party will often
allocate risk that it does not want to bear to the weaker party. This scenario does not necessarily
provide the most effective and efficient risk management process. Improperly-allocated risks will
have an impact on the entire project and may affect the stronger party as well as the weaker.
Allocation of risk to the party best able to manage it efficiently, inexpensively and easily will
generally result in a more successful and profitable project and will benefit all of the parties
concerned.
CHAPTER THREE
3 Risk In General
3.1 Risk Definition
Risk is defined as a combination of the probability, or frequency, of occurrence of a defined
hazard and the magnitude of the consequences of the occurrence. Hazard is a situation that could
occur during the life time of a product, system or plant that has the potential for human injury,
damage to property, damage to the environment, or economic loss (Zewdu).
According to (Heinz) Risk is unavoidable and present in every human situation. It is present in
daily lives, public and private sector organizations. Depending on the context (insurance,
stakeholder, technical causes), there are many accepted definitions of risk in use. The common
concept in all definitions is uncertainty of outcomes. Where they differ is in how they
characterize outcomes. Some describe risk as having only adverse consequences, while others
are neutral. One description of risk is the following: risk refers to the uncertainty that surrounds
future events and outcomes. It is the expression of the likelihood and impact of an event with the
potential to influence the achievement of an organization's objectives. The phrase "the expression
of the likelihood and impact of an event" implies that, as a minimum, some form of quantitative
or qualitative analysis is required for making decisions concerning major risks or threats to the
achievement of an organization's objectives.
Fit for purpose, in the sense of it meeting design, construction and performance criteria.
But there are risks of contractor that limit to accomplish the above obligations; some of them
according to MDB FIDIC are;
Sub Clause 18.2 works under construction and contractor’s equipment;
Sub Clause 18.3, the property of the employer, employer’s personnel, and the property of
third parties.
Sub Clause 18.4 contractor’s personnel; On the other hand, the contractors’ key concerns are
generally:
To be paid in accordance with the terms of the contract including any additional amounts
owing because of variation, etc;
To achieve its aimed for margin;
To complete in accordance with its programmers;
To have had the contract fairly administered;
To have avoided liability to third parties or the principal, e.g. liquidated damages, etc.
According to MDB FIDIC some of employer’s risks that limit contractors to accomplish the
above obligations are;
Sub Clause 17.3: The risks referred to in Sub-Clause 17.4 [Consequences of Employers Risks]
below, insofar as they directly affect the execution of the Works in the Country, are:
(a) War, hostilities (whether war be declared or not), invasion, act of foreign enemies,
(b) Rebellion, terrorism, sabotage by persons other than the contractor’s personnel, revolution,
insurrection, military or usurped power, or civil war, within the country,
(c) Riot, commotion or disorder within the country by persons other than the contractor’s
personnel,
(d) Munitions of war, explosive materials, ionizing radiation or contamination by radioactivity,
within the country, except as may be attributable to the contractor’s use of such munitions,
explosives, radiation or radio-activity,
(e) Pressure waves caused by aircraft or other aerial devices travelling at sonic or supersonic
speeds,
(f) Use or occupation by the employer of any part of the permanent works, except as may be
specified in the contract,
(g) Design of any part of the works by the employer’s personnel or by others for whom the
employer is responsible, and
(h) Any operation of the forces of nature which is unforeseeable or against which an experienced
contractor could not reasonably have been expected to have taken adequate preventive
precautions.
A financier of the project will have other key areas of risk which differ again, although there may
be varying degrees of overlap. Completion risk, being the risk that the project will not be
completed or not completed on time or at the anticipated cost translates into the risk for the
financier that insufficient cash flow will be generated such that it may trigger default under the
particular or a broader funding facility.
The risk map illustrates the risk profile of an enterprise. It is referred to as risk landscape, risk
map or risk matrix. In a risk map it can be read with what priority the risks should be
approached. In this, the risks that cannot be borne, which could endanger the continued existence
of the enterprise, are prioritized. The risk classification in a risk matrix thus enables a
differentiated consideration of two classification criteria: probability of occurrence and expected
value.
A risk ranking matrix, as shown in the figure below, can be used for categorizing the risk as
minor, moderate or major and decide on the action to be taken. Minor risks can be accepted,
moderate risks need some management measures and for major risks with high probability of
occurrence and high impact a serious risk action schedule needs to be devised to manage the risk.
If the risk is too big, the party might decide to walk away from the project instead of assuming it.
The relative significance of each risk should then be characterized and prioritized, and placed in
one of the following two risk categories:
1. Insignificant risks: risks that are broadly regarded as not posing a significant danger to
human health or environment;
2. Significant risks, risks that must be reduced to insignificant through implementation of
risk reducing measures in order to gain project approval, or to meet anticipated conditions for
site closure.
sector has different alternative to a wide range of insurance products covering project risks such
as owner's liability, some force majeure events, owner's risks (to the asset), business interruption,
some legislative and government policy risks relating to the convertibility of local currency, and
change of law events etc.
Risk assessments for health and safety risks might follow these steps:
Table 1 Risk assessments for health and safety risks
3.Evaluate the risks arising from the hazard High risk of collapse
4.Determine the control measures or Risk Use steel trench drag box
Mitigation required
5.Evaluate the remaining risks & any risks caused Risk of crushing/injury from excavator
by the control measures bucket. Risk of falling materials.
6.Record the findings of the risk assessment Fill in risk assessment sheet
7.Make contingency plans for the residual risks Prepare safety method statement based on
risk assessment.
Supervisor to give task talk. Permit to work
required.
Banks man working with excavator.
CHAPTER FOUR
other hand lead to a low quality of final product and increased overall cost. Being behind
schedule generates greater costs for both investors and contractors due to non-compliance with
contracted works (Gould and Joyce, 2002). And thus it is important to keep a balance in the
concept of time-cost-quality tradeoff, which more widely is becoming an important issue for the
construction sector (Zhang and Xing, 2010).
2) External risks
New stakeholders emerge and request changes
Public objections
Laws and local standards change
Tax change
3) Environmental risks
Environmental analysis incomplete
New alternatives required to avoid, mitigate or minimize environmental impact
4) Organizational risks
Inexperienced workforce and staff turnover
Delayed deliveries
Lack of protection on a construction site
7) Construction risks
Building cost overruns
Technology changes
The above view of risk assessment and allocation can be broken down into three questions:
1. Who can manage the risk most cheaply, efficiently and easily?
2. Who benefits most from its management?
3. Who has the greatest incentive to manage it? (Bryan S. Shapiro, QC)
Anita F. Baker puts six key risk allocation and management concepts that should be considered
at the project contract formation stage. Let see through this
1) Allocate risk to the party best situated to control the risk. At the outset of each project, an
owner and a contractor should anticipate and evaluate potential risks to project success and,
where applicable, assign responsibility for those risks to the party or parties best situated to
control them. For example, a contractor should assign the owner responsibility for design
errors because the owner typically holds the design services contracts and is in a better
position to work with the project designed to minimize the risk of those errors. From the
owner’s perspective, the contractor should undertake primary responsibility for bodily
injuries or property damage arising out of the contractor’s operations, since the contractor is
in the better position to minimize those risks by maintaining a safe jobsite.
2) Allocate risk through indemnity provisions. Contract indemnity provisions generally
require one party to pay for losses incurred by the other party as a result of claims made by
third parties. A construction contract indemnity provision typically requires the contractor to
indemnify the owner against claims for bodily injury or property damage arising out of the
negligent performance of work by the contractor or its subcontractors. Conversely, the owner
typically is called on to indemnify the contractor against claims or losses arising from the
existence of hazardous substances at the project site, at least to the extent that the contractor
does not have any control over those substances.
3) Use insurance to support indemnity provisions. Contract provisions requiring insurance
coverage provide assurance that each party can satisfy its indemnity obligations. Drafting
effective insurance coverage requirements in contracts first requires properly identifying the
risk obligations assumed by each project participant, and then ensuring each party has the
right insurance to cover those obligations.
For example, owners must require their contractors to secure commercial general liability,
automobile liability and worker's compensation/employers liability coverage. These obligations
should flow down to subcontractors. Commercial general liability insurance generally covers
bodily injury and property damage resulting from contractor or subcontractor negligence.
However, owners and contractors should bear in mind that liability policies typically do not
cover the contractor for defective work, which is instead subject to the contractor’s warranty.
Similarly, liability policies typically do not cover project improvements or construction materials
for damage due to unknown site conditions, natural disasters and similar risks. Those damages
are covered by a “builder’s risk” policy, which is usually required to be obtained by the owner.
CONSTRUCTION CONTRACT AND LAW Page 30
Risk: it’s Regulation & Management under the MDB-FIDIC (2006) & the PPA (2011) 2018 GC
Conditions of Construction Contracts & the Applicable Laws: with special emphasis to
Construction Insurance Practice in Ethiopia
Contracts with design professionals, such as architects, engineers, and contractors performing
design-build functions, must also require professional liability insurance to cover errors and
omissions in providing design or other professional services. Because professional liability
policies typically cover claims made on all of a particular design professional’s projects during a
given policy period, the aggregate limit of coverage must be sufficiently high to protect the
owner with respect to the owner’s specific project. An owner can accomplish this by requiring
project-specific coverage or excess limits applicable to professional liability. For larger projects,
the owner may also consider obtaining owner’s protective professional liability coverage to
indemnify the owner directly for losses arising from the design professional’s negligence.
4) Require additional insured status and evidence of insurance. Owners and contractors
should always require lower tier contractors or subcontractors to add the owner and
contractor as additional insured. A central reason for additional insured status is the insurer’s
primary duty to defend claims made against the additional insured. Additional insured status
is obtained by endorsement; thus, the applicable endorsement should be broad enough to
cover ongoing and completed operations on a primary and non-contributory basis.
Project participants must confirm that contractual insurance requirements, including proper
coverage, policy limits, and additional insured status, have been obtained and properly
documented. Project participants should never rely solely upon certificates of insurance to
confirm insurance requirements. Most certificates of insurance are issued by the broker, rather
than by the insurer, and are not contractually binding. Accordingly, the insurance provisions of a
project contract should mandate delivery of copies of policy declarations pages and all applicable
endorsements.
5) Include waivers of subrogation. Where applicable, contracts should include waivers of
subrogation to ensure that project risks are transferred in the manner intended by the project
participants. Subrogation allows an insurer to stand in the position of its insured to recover
amounts paid on behalf of the insured for damages for which another party may be liable.
Project participants intentionally shift risk through a variety of contract provisions. Allowing
an insurer to recover amounts paid on behalf of a contract participant to whom that risk was
shifted through indemnification or other means may undermine the parties’ intentions. A
waiver of subrogation precludes the insurer from seeking reimbursement for amounts paid on
claims, and thus prevents an insurer from passing assigned risk back to the other project
participants. In other words, a waiver of subrogation ensures that transferred project risk
stays with the insurers as contemplated by the project participants.
6) Review documents with appropriate consultants. Construction projects typically require
multiple contracts, which need to be consistent and complementary. For example, project
lender and owner requirements for payment timing and conditions should flow down through
all project contracts. Dispute resolution provisions should be consistent throughout the
project contracts to assure that all parties to a dispute are involved in the same proceeding at
CONSTRUCTION CONTRACT AND LAW Page 31
Risk: it’s Regulation & Management under the MDB-FIDIC (2006) & the PPA (2011) 2018 GC
Conditions of Construction Contracts & the Applicable Laws: with special emphasis to
Construction Insurance Practice in Ethiopia
the same time and are subject to the same dispute resolution rules. In addition, many standard
construction contracts utilize insurance terms that are inconsistent with current insurance
industry offerings, usages and customs. To minimize issues arising out of conflicting,
inconsistent or antiquated terms in the various project contracts, the project participants
should rely on experienced counsel and trusted insurance consultants familiar with current
industry forms and practices. In short, careful contract preparation and review are essential to
proper risk management for a construction project, and the ultimate goal of project success.
4.5.2.4 Lack of knowledge, inadequate checking and work carried out in haste
Although a professional may be qualified and experienced to carry out the design of a certain
project, he may still lack knowledge of a particular aspect of the design. The problem is that if he
does not realize his limitation, he may proceed without executing his duties properly. This
occurred in the case of a firm of consulting engineers commissioned to design a steam power
station for which the various pieces of equipment were ordered directly from the manufacturers
who supplied, independently of each other, in accordance with the specification. Due to
economic restraints or shortage of time, this type of risk increases, reaching unacceptable levels
and situations, this may produce problems later during construction. The level of this type of risk
also increases if economic restraints or shortage of time exist (MDB FIDIC 2006 clause 3.1).
Civil Code Art. 2636 states that:
2636 Required care and responsibility.
(1) Whosever hires out his work shall undertake to carry it out in the best interest of his client,
conscientiously and in conformity with the practiced rules of his profession.
(2)He shall not be liable to his client, unless he commits an error, having regard to the rules of
his profession.
(3) The error may consist in an omission or an act detrimental to his client.
Accordingly, they were held liable. The techniques and materials are used for the design phase is
must be proved.
MDB FIDIC (2006) Sub Clause 7.1 states that;
The Contractor shall carry out the manufacture of Plant, the production and manufacture of
Materials, and all other execution of the Works:
(a) in the manner (if any) specified in the Contract,
(b) in a proper workmanlike and careful manner, in accordance with recognized good
practice, and
(c) with properly equipped facilities and non-hazardous Materials, except as otherwise
specified in the Contract.
PPA (2011) Sub Clause 8.2 also states
The Engineer shall be entitled, either by himself or his agent, to inspect, examine, measure and
test the components, materials and workmanship, and check the progress of preparation,
fabrication or manufacture of anything being prepared, fabricated or manufactured for delivery
under the contract in order to establish whether the components, materials and workmanship are
of the requisite quality and quantity. This shall take place at the place of manufacture,
fabrication, preparation or on the site or at such other places as may be specified in the contract.
4.5.4.6 Risks associated with wear and tear during the project’s designed life span
The life span of materials and components incorporated in construction projects is limited and
inversely proportional to the deterioration, wear and tear which takes place usually for many
reasons; some are natural and others are artificial. To increase the life span, one must reduce the
deterioration, wear and tear and increase the durability of the various elements. Such a result
could only be achieved by a strict program of inspection and maintenance.
According to MDB FIDIC 2006 Sub Clause 7.3 (b) during production, manufacture and
construction (at the Site and elsewhere), be entitled to examine, inspect, measure and test the
materials and workmanship, and to check the progress of manufacture of Plant and production
and manufacture of Materials.
According to PPA (2011) Sub Clause 81.2 The Engineer shall be entitled, either by himself or
his agent, to inspect, examine, measure and test the components, materials and workmanship,
and check the progress of preparation, fabrication or manufacture of anything being prepared,
fabricated or manufactured for delivery under the contract in order to establish whether the
components, materials and workmanship are of the requisite quality and quantity. This shall take
place at the place of manufacture, fabrication, preparation or on the site or at such other places as
may be specified in the contract.
4.6 The effects of construction risk on the project & on the contracting
parties
An effect of the construction risk may include;
4.6.1 Quality
Risks, such as human mistakes, like wrong material selection by supervisors, workers’
misinterpretation of how to properly complete a specific task or lack of carefulness, can lead to
decrease quality levels. The casting of a concrete wall can be taken as an example, there is a need
to carefully, slowly and continuously vibrate the concrete mixture as it is poured. The lack of
seriousness or workers’ poor experience while performing this task can result in dramatic effects,
noticeable only after removing the frameworks. Because the mixture is not homogenous, there is
more gravel at the bottom of the wall and sand with water at the top, leading to an inappropriate
wall surface appearance and decreased mechanical properties, which means poor quality of the
work performed. Now, if the same level of carefulness is kept for all the exterior walls of the
building and the concrete needs to be visible for architectural purposes, the whole project quality
is going to suffer.
MDB FIDIC (2006) Sub Clause 4.9 states Quality Assurance as “The Contractor shall institute a
quality assurance system to demonstrate compliance with the requirements of the Contract. The
system shall be in accordance with the details stated in the Contract. The Engineer shall be
entitled to audit any aspect of the system.
Details of all procedures and compliance documents shall be submitted to the Engineer for
information before each design and execution stage is commenced. When any document of a
technical nature is issued to the Engineer, evidence of the prior approval by the Contractor
himself shall be apparent on the document itself.
Compliance with the quality assurance system shall not relieve the Contractor of any of his
duties, obligations or responsibilities under the Contract.”
4.6.2 Cost
Moreover, another very common issue is the budget overrun: there is a difference between the initial
cost of a project and the final one.
According to MDB FIDIC (2006) Sub Clause 11.2:- Cost of Remedying Defects
All work referred to in sub-paragraph (b) of Sub-Clause 11.1 [Completion of Outstanding Work
and Remedying Defects] shall be executed at the risk and cost of the Contractor, if and to the
extent that the work is attributable to:
(a) any design for which the Contractor is responsible,
(b) Plant, Materials or workmanship not being in accordance with the Contract, or
(c) failure by the Contractor to comply with any other obligation.
If and to the extent that such work is attributable to any other cause, the Contractor shall be
notified promptly by (or on behalf of) the Employer, and Sub-Clause 13.3 [Variation Procedure ]
shall apply.
4.6.3 Time
The most well-known risk, being a threat, in the construction field is related to planning overrun: the
agreed time of the contract is exceeded during the construction process. Time related problems on
construction projects seem to be very common in Ethiopia.
According to MDB FIDIC (2006) Sub Clause 8.7: Delay Damages
If the Contractor fails to comply with Sub-Clause 8.2 [Time for Completion], the Contractor
shall subject to notice under Sub-Clause 2.5 [Employer’s Claims] pay delay damages to the
Employer for this default. These delay damages shall be the sum stated in the Contract Data,
which shall be paid for every day which shall elapse between the relevant Time for Completion
and the date stated in the Taking-Over Certificate. However, the total amount due under this
Sub-Clause shall not exceed the maximum amount of delay damages (if any) stated in the
Contract Data.
These delay damages shall be the only damages due from the Contractor for such default, other
than in the event of termination under Sub-Clause 15.2 [Termination by Employer] prior to
completion of the Works. These damages shall not relieve the Contractor from his obligation to
complete the Works, or from any other duties, obligations or responsibilities which he may have
under the Contract.
PPA (2011) Sub Clause 27.1 also states:
Except as provided under GCC Clause 18, if the Contractor fails to carry out any or all of the
Works within the period specified in the Contract, the Public Body may without prejudice to all
its other remedies under the Contract, deduct from the Contract Price, as liquidated damages the
following:
(a) A penalty of 0.1% or 1/1000 of the value of undelivered Service for each day of delay until
actual delivery or performance,
(b) The cumulative penalty to be paid by the Contractor shall not exceed 10% of the contract
price.
4.6.4 Safety
This is or should be the main concern of all managers on a construction site. Due to the number
of equipment, tools, machines and engines use, an accident can easily and quickly happen and
could lead to injuries, absenteeism or even death.
4.6.5 Performance
According to MDB FIDIC (2006) Sub Clause 7.5: Rejection
If, as a result of an examination, inspection, measurement or testing, any Plant, Materials or
workmanship is found to be defective or otherwise not in accordance with the Contract, the
Engineer may reject the Plant, Materials or workmanship by giving notice to the Contractor, with
reasons. The Contractor shall then promptly make good the defect and ensure that the rejected
item complies with the Contract.
If the Engineer requires this Plant, Materials or workmanship to be retested, the tests shall be
repeated under the same terms and conditions. If the rejection and retesting cause the Employer
to incur additional costs, the Contractor shall subject to Sub Clause 2.5 [Employer’s Claims] pay
these costs to the Employer.
According to PPA Sub Clause 82.1:
Components and materials which are not of the specified quality shall be rejected. A special
mark may be applied to the rejected components or materials.
This shall not be such as to alter them or affect their commercial value. Rejected components and
materials shall be removed by the Contractor from the site within a period which the Engineer
shall specify, failing which they shall be removed by the Engineer as of right at the expense and
risk of the Contractor. Any work incorporating rejected components or materials shall be
rejected.
Project Risks
Climatic
War, Hostilities Inflation Employer's
Conditions
Shortage of
Geological Riot, Civil
Material, Contractor's
Conditions Disorder, etc
Equipment
To go with the above risk categorization framework, discussions of the risk allocations are made
in the same order as listed in the framework.
“n”, expressed in the relevant currency of payment, each of which is applicable to the relevant
tabulated cost element on the date 49 days prior to the last day of the period (to which the
particular Payment Certificate relates); and
“Lo”, “Eo”, “Mo”, … are the base cost indices or reference prices, expressed in the relevant
currency of payment, each of which is applicable to the relevant tabulated cost element on the Base
Date.
Shortage of labour, materials and equipment is also dealt with under the FIDIC Form to some
extent; if such shortage is reasonably unforeseeable, the Contractor is entitled to an EOT under
Sub-clause 8.4. However, under Sub-clauses- 4.1 and 6.1, it is the Contractor's obligation to
"provide all Contractor's personnel, Goods..." and the Contractor shall "make arrangements for
the engagement of all staff and labour... and for their payment...". It can be inferred from such
provisions that the Contractor shall bear all the consequences of the risks of unavailability of the
required personnel, materials and equipment, except for allowed EOT in case of unforeseeable
shortage. Legal risks refer to the changes in legislation or introduction of new laws after the Base
Date of the contract. It is provided that in Sub Clause 13.7 Adjustments for Changes in
Legislation that the Contractor is entitled to an EOT and additional cost caused as a result of the
changes in the laws. Therefore, under FIDIC Form, such legal change risks are basically retained
by the Employer.
However, PPA-2011 form of contract does not embrace price adjustment provision for
fluctuation of prices and cost changes by the market unless such costs such as rates of wages,
other emoluments and expenses are increased or decreased by any Act, Statute, Decree,
Regulation and the like after the date of bid pricing. This means that the risk of inflation is not
shared by the parties where the contractor is to carry the risk and the contractor should forecast
and add a contingency for this work.
b. Market according to MDB FIDIC 2006 sub clause 13.8 ,cost risk
c. Government according to MDB FIDIC 2006 sub clause 13.7 cost and time
extension
d. Third party
According to MDB FIDIC 2006 sub clause 2.1 Right of Access to the Site
The Employer shall give the Contractor right of access to and possession of, all parts of the Site
within the time (or times) stated in the Contract Data. The right and possession may not be
exclusive to the Contractor. If, under the Contract, the Employer is required to give (to the
Contractor) possession of any foundation, structure, plant or means of access, the Employer shall
do so in the time and manner stated in the Specification. However, the Employer may withhold
any such right or possession until the Performance Security has been received.
If no such time is stated in the Contract Data, the Employer shall give the Contractor right of
access to, and possession of, the Site within such times as required to enable the Contractor to
proceed without disruption in accordance with the programme submitted under Sub-Clause 8.3
[Programme].
If the Contractor suffers delay and/or incurs Cost as a result of a failure by the Employer to give
any such right or possession within such time, the Contractor shall give notice to the Engineer
and shall be entitled subject to Sub-Clause 20.1 [Contractor’s Claims] to:
(a) An extension of time for any such delay, if completion is or will be delayed, under Sub-
Clause 8.4 [Extension of Time for Completion], and
(b) Payment of any such Cost plus profit, which shall be included in the Contract Price.
After receiving this notice, the Engineer shall proceed in accordance with Sub-Clause 3.5
[Determinations] to agree or determine these matters.
However, if and to the extent that the Employer’s failure was caused by any error or delay by the
Contractor, including an error in, or delay in the submission of, any of the Contractor’s
Documents, the Contractor shall not be entitled to such extension of time, Cost or profit.
In this clause we have seen how the risks identified and allocated due to the right of access to the
site and possession for the contractor by the employer. The employers delayed due to give right
of access to the site the contractors have the right to entitled cost or profit sub clause 1.9b. The
engineer determines this matter. The delay is happen by the contractors it is the risk for himself,
his does not asked any cost or profit. FPPA 2011 sub clause 31.1- 31.4 access to site.
According to MDB FIDIC 2006 sub clause 4.7 setting out
The Contractor shall set out the Works in relation to original points, lines and levels of reference
specified in the Contract or notified by the Engineer. The Contractor shall be responsible for the
correct positioning of all parts of the Works, and shall rectify any error in the positions, levels,
dimensions or alignment of the Works.
The Employer shall be responsible for any errors in these specified or notified items of reference,
but the Contractor shall use reasonable efforts to verify their accuracy before they are used.
If the Contractor suffers delay and/or incurs Cost from executing work which was necessitated
by an error in these items of reference, and an experienced contractor could not reasonably have
discovered such error and avoided this delay and/or Cost, the Contractor shall give notice to the
Engineer and shall be entitled subject to Sub Clause 20.1 [Contractor’s Claims] to:
(a) an extension of time for any such delay, if completion is or will be delayed, under Sub-
Clause 8.4 [Extension of Time for Completion], and
(b) Payment of any such Cost plus profit, which shall be included in the Contract Price.
After receiving this notice, the Engineer shall proceed in accordance with Sub-Clause 3.5
[Determinations] to agree or determine (i) whether and (if so) to what extent the error could not
reasonably have been discovered, and (ii) the matters described in sub-paragraphs (a) and (b)
above related to this extent.
This clause stated that how risk is identified and allocated based due to setting out, if the risk or
error is happened due to in the notified items of reference, it will be responsible for the employer
so the contractors have a right to ask any entitlement for the delayed project. If the risks happen
due to contractors in order to put the point on the appropriate position or alignment’s, it is the
responsibility of the contractors. According to FPPA 2011 sub clause 49.2 If, at any time during
the execution of the Works, any error appears in the position, levels, dimensions or alignment of
any part of the Works, the Contractor, shall, if the Engineer so requires, at the Contractor's cost,
rectify such error to the satisfaction of the Engineer, unless such error is based on incorrect data
supplied by the Engineer, in which case the Public Body shall be responsible for the cost of
rectification.
According to MDB FIDIC 2006 sub clause 8.7
If the Contractor fails to comply with Sub-Clause 8.2 [Time for Completion], the Contractor
shall subject to notice under Sub-Clause 2.5 [Employer’s Claims] pay delay damages to the
Employer for this default. These delay damages shall be the sum stated in the Contract Data,
which shall be paid for every day which shall elapse between the relevant Time for Completion
and the date stated in the Taking-Over Certificate. However, the total amount due under this
Sub-Clause shall not exceed the maximum amount of delay damages (if any) stated in the
Contract Data.
These delay damages shall be the only damages due from the Contractor for such default, other
than in the event of termination under Sub-Clause 15.2 [Termination by Employer] prior to
completion of the Works. These damages shall not relieve the Contractor from his obligation to
complete the Works, or from any other duties, obligations or responsibilities which he may have
under the Contract.
In this Sub-Clause, “physical conditions” means natural physical conditions and manmade and
other physical obstructions and pollutants, which the Contractor encounters at the Site when
executing the Works, including sub-surface and hydrological conditions but excluding climatic
conditions.
If the Contractor encounters adverse physical conditions which he considers to have been
Unforeseeable, the Contractor shall give notice to the Engineer as soon as practicable.
This notice shall describe the physical conditions, so that they can be inspected by the Engineer,
and shall set out the reasons why the Contractor considers them to be Unforeseeable. The
Contractor shall continue executing the Works, using such proper and reasonable measures as are
appropriate for the physical conditions, and shall comply with any instructions which the
Engineer may give. If an instruction constitutes a Variation, Clause 13 [Variations and
Adjustments] shall apply.
If and to the extent that the Contractor encounters physical conditions which are Unforeseeable,
gives such a notice, and suffers delay and/or incurs Cost due to these conditions, the Contractor
shall be entitled subject to notice under Sub-Clause 20.1 [Contractor’s Claims] to:
(a) an extension of time for any such delay, if completion is or will be delayed, under Sub-
Clause 8.4 [Extension of Time for Completion], and
(b) Payment of any such Cost, which shall be included in the Contract Price.
According to MDB FIDIC sub clause 4.10 site data:
The Employer shall have made available to the Contractor for his information, prior to the Base
Date, all relevant data in the Employer’s possession on sub-surface and hydrological conditions
at the Site, including environmental aspects. The Employer shall similarly make available to the
Contractor all such data which come into the Employer’s possession after the Base Date. The
Contractor shall be responsible for interpreting all such data.
To the extent which was practicable (taking account of cost and time), the Contractor shall be
deemed to have obtained all necessary information as to risks, contingencies and other
circumstances which may influence or affect the Tender or Works. To the same extent, the
Contractor shall be deemed to have inspected and examined the Site, its surroundings, the above
data and other available information, and to have been satisfied before submitting the Tender as
to all relevant matters, including (without limitation):
(a) The form and nature of the Site, including sub-surface conditions,
(b) The hydrological and climatic conditions,
(c) The extent and nature of the work and Goods necessary for the execution and completion of
the Works and the remedying of any defects,
(d) The Laws, procedures and labor practices of the Country, and
(e) The Contractor’s requirements for access, accommodation, facilities, personnel, power,
transport, water and other services.
According to sub clause 8.4 Extension of Time for Completion:
The Contractor shall be entitled subject to Sub-Clause 20.1 [Contractor’s Claims] to an extension
of the Time for Completion if and to the extent that completion for the purposes of Sub-Clause
10.1 [Taking-Over of the Works and Sections] is or will be delayed by any of the following
causes:
(a) a Variation (unless an adjustment to the Time for Completion has been agreed under Sub-
Clause 13.3 [Variation Procedure]) or other substantial change in the quantity of an item of work
included in the Contract,
(b) a cause of delay giving an entitlement to extension of time under a Sub-Clause of these
Conditions,
(c) exceptionally adverse climatic conditions,
(d) Unforeseeable shortages in the availability of personnel or Goods caused by epidemic or
governmental actions, or
(e) Any delay, impediment or prevention caused by or attributable to the Employer, the
Employer’s Personnel, or the Employer’s other contractors.
If the Contractor considers himself to be entitled to an extension of the Time for Completion, the
Contractor shall give notice to the Engineer in accordance with Sub Clause 20.1 [Contractor’s
Claims]. When determining each extension of time under Sub-Clause 20.1, the Engineer shall
review previous determinations and may increase, but shall not decrease, the total extension of
time.
III. Incentive principles
According to MDB FIDIC 2006 sub clause 4.24 fossils;
All fossils, coins, articles of value or antiquity, and structures and other remains or items of
geological or archaeological interest found on the Site shall be placed under the care and
authority of the Employer. The Contractor shall take reasonable precautions to prevent
Contractor’s Personnel or other persons from removing or damaging any of these findings.
The Contractor shall, upon discovery of any such finding, promptly give notice to the Engineer,
who shall issue instructions for dealing with it. If the Contractor suffers delay and/or incurs Cost
from complying with the instructions, the Contractor shall give a further notice to the Engineer
and shall be entitled subject to Sub-Clause 20.1 [Contractor’s Claims] to:
(a) An extension of time for any such delay, if completion is or will be delayed, under Sub-
Clause 8.4 [Extension of Time for Completion], and
(b) Payment of any such Cost, which shall be included in the Contract Price. Is not profit After
receiving this further notice, the Engineer shall proceed in accordance with Sub Clause 3.5
[Determinations] to agree or determine these matters.
According to MDB FIDIC 2006 sub clause 4.12 (b) payment of any such Cost, which shall
be included in the Contract Price, is not profit
According to MDB FIDIC 2006 sub clause 4.7(b) 2.1(b) and 1.9(b); Payment of any such
Cost plus profit, which shall be included in the Contract Price, The contractors get profit
According MDB FIDIC 2006 clauses 1.9 The Contractor shall give notice to the Engineer
whenever the Works are likely to be delayed or disrupted if any necessary drawing or instruction
is not issued to the Contractor within a particular time, which shall be reasonable. The notice
shall include details of the necessary drawing or instruction, details of why and by when it
should be issued, and the nature and amount of the delay or disruption likely to be suffered if it is
late.
III. Inadequate site supervision
IV. Lack of communication. According to MDB FIDIC 2006 sub clause 1.3
IV. Programming the work
4.7.6.2 Construction phase risks allocated to the contractor;
I. Mechanical and electrical breakdown
Site operations are becoming more dependent on plant and equipment, the breakdown of which
forms a major risk element. According to MDB FIDIC 2006 sub clause 4.1, The Contractor shall
provide the Plant and Contractor’s Documents specified in the Contract, and all Contractor’s
Personnel, Goods, consumables and other things and services, whether of a temporary or
permanent nature, required in and for this design, execution, completion and remedying of
defects.
II. Defective workmanship and material
According to MDB FIDIC 2006 7.4 Except as otherwise specified in the Contract, the Contractor
shall provide all apparatus, assistance, documents and other information, electricity, equipment,
fuel, consumables, instruments, labor, materials, and suitably qualified and experienced staff, as
are necessary to carry out the specified tests efficiently. The Contractor shall agree, with the
Engineer, the time and place for the specified testing of any Plant, Materials and other parts of
the Works to minimize defective workmanship and materials.
Technical complexity and innovation in design requiring new methods of construction and/or
erection.
When traditional materials or methods are used in construction, the familiarity of those involved
with the design or the work itself may permit an occasional ambiguity in the drawings or
specifications without them being misinterpreted. It may even provide correction of a mistake.
However, in a novel or relatively new design, material or construction method, what is needed is
precise and thorough communication between the designer, manufacturer or contractor, as the
case may be, and others involved in the construction process.
According to FPPA 2011 sub clause 42.1The Contractor shall prepare, at its own expense, all
design and construction drawings and other documents and objects necessary for the proper
execution of the Contract, and in particular drawings and design calculations and the
reinforcement drawings for reinforced concrete structures. The Contractor shall submit, in
triplicate, construction, design and reinforcement drawings, design calculations and any other
documents or objects it is to provide for the Engineer‟s approval at least one month before
commencing construction of the works in question.
Human error .according to MDB FIDIC 2006 sub clause 4.12 and FPPA sub clause 44.1
Negligence and lack of care According to [MDB FIDIC 2006] clause 3.1 and According
civil code art 2031
CHAPTER FIVE
should cover the damage. As mentioned earlier insurance is one way of dealing with risk but the
amount of damage the risk may cause to the project should be assessed and the exact amount
known to have an equivalent insurance cover. In simple terms the insurance should cover every
cost that arises because of the manifestation of the risk and its consequences.
The general conditions of contract, 2006, prepared by the Public Procurement Agency (PPA) of
Ethiopia also have different clauses that deal with the general risks common to most projects.
Clause 20: states that “the consultant should have an insurance coverage against risks specified
in the special conditions of contract”. This implies that the risks which are believed to have an
effect on the execution of the project should be clearly identified and dealt with in the specific
conditions of the contract by providing enough insurance coverage. The article further discusses
that a consultant needs to have professional indemnity insurance before award of any contract.
This is one way of dealing with risk by making sure the consultant is covered for any fault that
might occur during the design and supervision of the project.
The general conditions of contract by the ministry of works and urban development (MoWUD),
identifies some special risks which the contractor is not liable for. Some of these special risks are
war hostilities, invasion, act of foreign enemies; contamination by radio-active components,
pressure wave caused by aircraft or other aerial devices; riot, commotion, or disorder, unless
solely restricted to employees of the contractor or his sub-contractor and arising from the
conduct of the works; rebellions, revolution, military or usurped power, or civil war. This general
condition of contract further states in the following statement that the contractor should be
provided with payment to rectify any damage or destruction caused by the special risk and to
replace any material or property needed to complete the project.
If the works or any materials on the site or any property of the contractor used or intended to be
used for the purpose of the works, sustain destruction or damage by reason of any of the said
special risks, the contractor shall be entitled to payments in accordance with the contract for any
permanent work duly executed and for materials so destroyed or damaged and, so far as may be
required by the Engineer or as may be necessary for the completion of the works.
As mentioned above, the standard contract documents used in Ethiopian building construction
industries deal with some risks which are common in all building construction projects. And in
most cases, only the risks which are included in these standard documents are included in the
contracts. But in addition to that, it is recommended that risks that are unique and specific to any
particular project be identified and included in the particular conditions of the contract so that
they can easily be managed if and when they occur.
concept of risk management. This shows that most of the parties involved in Ethiopian building
construction projects, 97%, know about the concept of risk management, the next question tried
to assess how they became aware and if they are confident enough to implement their knowledge
into action. Most of the respondents who answered yes to the above question became aware of
the principle of risk management through study and training. Figure 4.1 shows 70.8% of the
parties became aware of the principles of risk management through study and 26.2 % became
aware through training. But when the respondents were asked to evaluate their knowledge of risk
management principles, most of them answered as medium or fair This result shows out of those
who claim to have knowledge of risk management, most of them are not fully confident enough
to rate their knowledge as high. This implies that a lot needs to be done in increasing awareness
and making the parties involved in the Ethiopian building construction projects confident enough
to implement their knowledge of risk management to increase the efficiency and effectiveness of
their projects. From the above result it can be observed that only a small number of parties
involved in the Ethiopian building projects evaluated their knowledge on principles of risk
management as high. And from this and other researches shows the parties knowledge about the
principle of risk management is not enough to implement its applications in their building
construction projects.
CHAPTER SIX
CHAPTER SEVEN
The factors that give rise to risk are interdependent and cannot be examined in isolation. It is
vital in managing risk to be aware of this interdependency, and rather than dealing with risks
one-by-one as they arise, use approaches that deal with whole systems. This requires engineers
to:
• look beyond purely technical considerations, to address non-technical factors and include
human, organizational and cultural perspectives
• make risk assessment and management an integral part of all engineering activity and decision
making
• adopt a conservative decision making approach that is proportionate to the risk especially
where a novel process is employed
• aim to quantify the risks with as much precision as is relevant, sufficient and can be supported
by the evidence
• be responsive to changes in the operating environment
• look for connections, patterns and relationships between risks and opportunities
• consider the role that ergonomics can play in mitigating the risk of human error
• bear in mind that risk assessment should be used as an aid to professional judgment and not as a
substitute for it
• be aware that developing over-elaborate procedures can lead to poor compliance and
undermine the wider safety culture
Comply with legislation and codes, but be prepared to seek further improvements
Regulations and codes are generic. They can only deal with anticipated events, and cannot
predict every possible situation.
Engineers should take a measured, yet challenging approach to potential risks, whether or not
regulations apply. Engineers should:
• act in accordance with codes of conduct
• know about and comply with the law in countries where they are operating or where their
products will be used
• recognize and understand the intent behind standards and codes, and understand when their
limits are being approached
• comply with current relevant legal requirements governing engineering risk issues
• seek advice where necessary
• recognize the social, political and economic implications in the risk assessment and
acknowledge them publicly
• explain the quantitative aspects of risk with clarity and supporting evidence
• be honest and clear about uncertainties, and be prepared to challenge mis-representations
Negotiating, and
Revising contracts.
Most risks are arising from contract documents due to different cases such as the interpretation
and/ or application of any part of the contract documents and at any time during the execution of
the contract. If the contract documents are ambiguous, unplanned and conflicting this will most
certainly lead to disputes. Contract clauses, which unrealistically and unfairly shift project risk to
parties who are not prepared or not able to assume such risk.
Therefore the engineer should work hard during contract administration stage to avoid the above
risk causes.
Art. 1678 of Civil Code says that No valid contract shall exist unless:
(a) The parties are capable of contracting and give their consent sustainable at law;
(b) The object of the contract is sufficiently defined and is possible and lawful;
(c) The contract is made in the form prescribed by law, if any.
The engineer should also understand the law of contract and administer contracts by considering
every rules and regulations that are present in the general and special conditions of contract and
also clarify for the parties that are engaged in the contract.
He/she shall check the contract document;
All the clauses are clear and understand by the parties;
Allocation of risks equally for the parties;
Making elaborations of statements of contract document to parties;
And finally interpretation of contract agreements during the execution of project.
the Engineer's representative be empowered to relieve the Contractor of his obligations under the
contract or – except where express instructions to that effect are given in the SCC – order works
resulting in an extension of the period of performance or additional costs to be paid by the Public
Body or introduce variants in the nature or scale of the works (FPPA 2011
Sub clause 12.4).
The quality of site supervision has a major influence on the overall performance and efficiency
of construction projects. Inadequate supervision is believed to be one of the major causes of
rework. Therefore, experienced and well-trained supervisors have an important role in
minimizing the amount of risk due to construction defects.
Poor supervision results in defective construction which not only contributes to the final cost of
the product but also to the cost of maintenance, which can be substantial. Defective construction
may lead to the complete failure of a structure.
Authenticate daily work records of materials, labour and plant.
MDB FIDIC sub-clause 3.1. Except as otherwise stated in these Conditions:
(c) Any approval, check, certificate, consent, examination, inspection, instruction, notice,
proposal, request, test, or similar act by the Engineer (including absence of disapproval) shall not
relieve the Contractor from any responsibility he has under the Contract, including responsibility
for errors, omissions, discrepancies and non-compliances.
Examine and adjust priced bill of quantities.
All prices shall be firm unless the Contractor has provided claim for price adjustment. The
Contractor may invoke this provision at any time during the Contract by notice in writing to
the Engineer (FPPA 2011 Sub clause 62.3).
Prepare valuations: - FPPA 2011 Sub clause 63.1
iii) The Engineer shall determine by measurement the actual quantities of the works executed by
the Contractor, and these shall be paid for in accordance with GCC Clause 64 [Interim Payment].
Unless otherwise provided in the SCC no additions shall be made to the items in the bill of
quantities except as a result of a modification in accordance with GCC Clause 15 [Modifications
by Change Orders] or another provision of the Contract entitling the Contractor to additional
payment;
iv) The Engineer shall, when he requires any parts of the works to be measured, give reasonable
notice to the Contractor to attend, or to send a qualified agent to represent him. The Contractor or
his agent shall assist the Engineer in making such measurements and shall furnish all particulars
required by the Engineer. Should the Contractor not attend, or omit to send such agent, the
measurement made by the Engineer or approved by him shall be binding on the Contractor;
Issue interim certificates and variation orders and expedite payments.
According to MDB FIDIC 2006 Sub clause 14.6 No amount will be certified or paid until the
Employer has received and approved the Performance Security. Thereafter, the Engineer shall,
within 28 days after receiving a Statement and supporting documents, deliver to the Employer
and to the Contractor an Interim Payment Certificate which shall state the amount which the
Engineer fairly determines to be due, with all supporting particulars for any reduction or
withholding made by the Engineer on the Statement if any.
However, prior to issuing the Taking-Over Certificate for the Works, the Engineer shall not be
bound to issue an Interim Payment Certificate in an amount which would (after retention and
other deductions) be less than the minimum amount of Interim Payment Certificates (if any)
stated in the Contract Data. In this event, the Engineer shall give notice to the Contractor
accordingly.
An Interim Payment Certificate shall not be withheld for any other reason, although:
(a) If anything supplied or work done by the Contractor is not in accordance with the Contract,
the cost of rectification or replacement may be withheld until rectification or replacement has
been completed; and/or
(b) If the Contractor was or is failing to perform any work or obligation in accordance with the
Contract, and had been so notified by the Engineer, the value of this work or obligation may be
withheld until the work or obligation has been performed.
The Engineer may in any Payment Certificate make any correction or modification that should
properly be made to any previous Payment Certificate. A Payment Certificate shall not be
deemed to indicate the Engineer’s acceptance, approval, consent or satisfaction.
In case of variations; MDB FIDIC Sub clause 13.1
Variations may be initiated by the Engineer at any time prior to issuing the Taking-Over
Certificate for the Works, either by an instruction or by a request for the Contractor to submit a
proposal.
Each Variation may include:
a. Changes to the quantities of any item of work included in the Contract (however, such changes
do not necessarily constitute a Variation),
b. Changes to the quality and other characteristics of any item of work,
c. Changes to the levels, positions and/or dimensions of any part of the Works,
d. Omission of any work unless it is to be carried out by others,
e. any additional work, Plant, Materials or services necessary for the Permanent Works,
including any associated Tests on Completion, boreholes and other testing and exploratory work,
or
f. Changes to the sequence or timing of the execution of the Works.
Therefore the key roles of the engineer in construction risk management are
Give a detailed written instruction to the contractor about the methods and procedures of
construction processes
Carefully inspect the project weather it is constructed with in the standards and
specifications written in the contract document.
By prepare a risk management plan during the design phase of the project.
By accurately measuring executed works in order to prepare payment certificates.
Preparing clear contract document.
By preparing price adjustments during variations of work
CHAPTER EIGHT
8 Case Study
8.1 General
These portions of the paper cover a case study of the construction works of Kibermingest shakiso
road project. The agreement made between Ethiopia construction Work Corporation and
Ethiopian road authority on June 2016.
The employer, Ethiopian Road Authority, covenant to pay the contractor, Ethiopia construction
Work Corporation, in consideration of the execution and completion of the works and remedying
of defect there in ETB 149,525,402.49.
About eight years ago a contractor named Flint Stone Construction was starting build the said
project. After executing some percent of the work his contract has terminated. And then after, the
Employer made another agreement with ECWC for 8 month contract period. This case study
focused only the ECWC and ERA contract agreement.
Amount withheld for late submission of ETB 10,000 per calendar date of delay
program
Cash of flow estimate Within 42 day of receipt of the letter of
acceptance
Amount of liquidated damages 0.1% of the value of remaining per day
Limit of liquidated damage 10%of final contract price
Defect of liability period 365 days from the issue of taking over
certificate
Minimum amount of interim payment ETB 2,500,000
certificate
%of retention 5%of interim payment certificate, up to a
maximum of 5% of final contract price.
Maximum amount of advance payment 20% of contract amount less day work,
provisional sums and contingency.
Start repayment of advance payment After certification of 30% contract price, less
provisional sums, day work contingency and
VAT
Monthly recovery of advance payment 40%of amount of monthly interim payment
certificate
and extension of project time, which gives rise to dissatisfaction to all the parties involved and
nowadays it’s becoming a major obstruction for their development for developing countries
like Ethiopia. The major problem of the said project is also time overrun beyond the date th at
the parties have agreed upon for the delivery of the project.
Heavy rainfall often leads to complete suspension of highway construction due to saturated and
unworkable soil conditions. Therefore, quantifying the impact of rainfall on the productivity of
highway construction is essential in preparing realistic schedules and cost estimates for the
preconstruction stage and in analyzing weather-related claims for the post construction stage.
Since K/mengist-Shakiso has uneven and heavy rainfall through all season, it affects the progress
of the work.
The main reason the contractor fall to risk is material that is fog spray not found in the market of
Ethiopia and cannot be easily import because of shortage of supply from abroad and the
contractor need minimum amount of material that is only enough to this project which is
174,098.84 lit. This material expired with in short period of time with maximum 6 month of life
time so the importer not interested to deliver.
Due to the fact that, contractor wrote letter and asked willingness of the Engineer to finish DBST
with out of fog spray or with another type of fog spray which is 30% anionic spray grade
bitumen, found from local private contractor called Gemshu Beyene PLC.
Unfortunately, the Engineer did not accept the idea and tell to do based on the contract
document, which is a 30% cationic spray grade, and obeying contract agreement.
In another case, the contractor has produced a surface aggregate at Gidabo( around Dilla) and
when he tries to haul the material the society and the regional administration form a controversy
with contractor and prohibit him due to regional natural resource case. Even though, the
contractor has paid for the right of way for that site.
3. Other factors
Other factors like Infective project planning, scheduling or resource management low
productivity of labour/inadequate experienced labour, insufficient data collection and survey
before design, bureaucracy (Excessively complicated administrative procedure), regular
interference, poor communication and coordinate on with other parties, slowness in decision
making, inflexibility (rigidity) of consultant, in accurate site inspection and conflicts puts their
own marks on the delay of the project.
CHAPTER NINE
Table 4 Comparative analysis of MDB FIDIC 2006 and FPPA 2011 with respect to risk and
delay damages (if any) stated (b) The cumulative penalty to be paid by the
in the Contract Data Contractor shall not exceed 10% of the
contract price.
Adjustments for Changes in Legislation Change in Laws and Regulations
13.7 16
The Contract Price shall be adjusted to take account of Unless otherwise expressly agreed in the SCC,
any increase or decrease in Cost resulting from a change 16.1 price and completion date are not adjusted after
in the Laws of the Country (including the introduction of the deadline of submission.
new Laws and the repeal or modification of existing
Laws) or in the judicial or official governmental
interpretation of such Laws, made after the Base Date,
which affect the Contractor in the performance of
obligations under the Contract.
Adjustments for Changes in Cost Price adjustment
13.8 62
In this Sub-Clause, “table of adjustment data” means the Adjustments of contract prices shall be allowed
completed table of adjustment data for local and foreign 62.1 after twelve (12) months from the effective
currencies included in the Schedules. If there is no such date of the Contract where it is verified that the
table of adjustment data, this Sub-Clause shall not apply. performance of the contract requires more than
18 months.
Indemnities Indemnification and Limitation of
17.1 39
The Contractor and employer shall indemnify from all Liability
claims, damages, losses and expenses (including legal 39.1 At its own expense, the Contractor shall
fees and expenses bodily injury, sickness, disease or indemnify, protect and defend, the Public
death, of any person whatsoever arising Body, its agents and employees, from and
out of damage to or loss of any property, real or personal. against all actions, claims, losses or damage
arising from any act or omission by the
Contractor.
Contractor’s Care of the Work General obligations
17.2 34
The Contractor shall take full responsibility for the care The Contractor shall take full responsibility for
of the Works and Goods from the Commencement Date 34.2 the adequacy, stability and safety of all
until the Taking-Over Certificate is issued operations and methods of construction under
the Contract.
Insurance for Works and Contractor’s Insurance to be Taken Out by the
18.2 40
Equipment Contractor
The insuring Party shall insure the Works, Plant, 40.1 The Contractor shall provide, in the joint
Materials and Contractor’s Documents for not less than names of the Public Body and the Contractor,
the full reinstatement cost including the costs of insurance cover against loss or damage for
demolition, removal of debris and professional fees and which he is liable under the contract in the
profit. amounts and deductibles stated in the SCC.
Insurance against Injury to Persons and Such insurance shall, unless the SCC provide
18.3
Damage to Property otherwise, cover:
The insuring Party shall insure against each Party’s a. Any damage or loss of Works, together with
liability for any loss, damage, death or bodily injury Materials and Plant.
which may occur to any physical property. b. An additional sum of 15% of such
Insurance for Contractor’s Personnel replacement cost.
18.4
The Contractor shall effect and maintain insurance c. The Contractor's Equipment and other things
against liability for claims, damages, losses and expenses brought onto the Site by the Contractor, for a
(including legal fees and expenses) arising from injury, sum sufficient to provide their replacement at
sickness, disease or death of any person employed by the the Site.
Contractor or any other of the Contractor’s Personnel
Force Majeure Force Majeure
19.1 18
may include, but is not limited to, exceptional events or For the purposes of the Contract, “Force
circumstances of the kind listed below; war, hostilities, Majeure “shall mean an event or events which
invasion, act of foreign enemies, rebellion, terrorism, are beyond the reasonable control of a
sabotage, revolution, insurrection, military power, or Contractor, and which makes a Contractor’s
civil war, riot, commotion, disorder, strike, munitions of performance of its obligations hereunder
war, explosive materials, ionizing, except as may be impossible in the circumstances, and includes:
attributable to the Contractor’s use of such munitions, An official prohibition preventing the
explosives, radiation or radio-activity, and Natural performance of a contract, A natural
catastrophes. catastrophe, International or civil war, or Other
instances of Force Majeure.
Employer’s Risks
17.3
The risks they directly affect the execution of the Works
in the Country, are:
war, hostilities
rebellion, terrorism,
riot,
munitions of war,
pressure waves,
use or occupation by the Employer of any part of the
Permanent Works, except as may be specified in the
Contract,
Design of any part of the Works by the Employer’s
Personnel or by others for whom the Employer is
responsible and
Consequences of Employer’s Risks
17.4
If and to the extent that any of the risks listed in Sub-
Clause 17.3 above results in loss or damage to the
Works, Goods or Contractor’s Documents, the
Contractor shall promptly give notice to the Engineer and
shall rectify this loss or damage to the extent required by
the Engineer.
Use of Employer’s Accommodation/Facilities Fraud and Corruption
17.7 5
The Contractor shall take full responsibility for the care It is the Government of the Federal Democratic
of the Employer-provided accommodation and facilities, 5.1 Republic of Ethiopia’s policy to require that
if any, as detailed in the Specification, If any loss or Public Body, as well as bidders/suppliers, to
damage happens to any of the above items while the observe the highest standards of ethics during
Contractor is responsible for their care arising from any the procurement and the execution of contracts.
cause whatsoever other than those for which the That Public Bodies shall include in bidding
Employer is liable, the Contractor shall, at his own cost, documents, provisions against corrupt practices
rectify the loss or damage to the satisfaction of the
Engineer.
Rejection Rejection
7.5 82
If, as a result of an examination, inspection, measurement Components and materials which are not of the
or testing, any Plant, Materials or workmanship is found 82.1 specified quality shall be rejected. A special
to be defective or otherwise not in accordance with the mark may be applied to the rejected
Contract, the Engineer may reject the Plant, Materials or components or materials. This shall not be such
workmanship by giving notice to the Contractor, with as to alter them or affect their commercial
reasons. The Contractor shall then promptly make good value. Rejected components and materials shall
the defect and ensure that the rejected item complies with be removed by the Contractor from the site
the Contract. within a period which the Engineer shall
specify, failing which they shall be removed by
the Engineer as of right at the expense and risk
of the Contractor. Any work incorporating
rejected components or materials shall be
rejected.
CHAPTER TEN
10.2 Recommendation
The most effective key risk factors which have a significant effect on construction projects scope
are identified and classified through a comprehensive literature survey. Our case study have
shown poor identification of risk can leads to delay of construction work which is result of
improper risk management plan and process.
Risk is perceived as a negative term, even though in theory it can have two dimensions.
Professionals in the construction industries are using techniques described in the literature
concerning RM, but are not aware of it. Risks are being managed every day in the industry, As
also other researchers confirmed, the knowledge of risk and risk management is close to zero,
even though the concept of risk management is becoming more popular in the construction sector
technique that should be applied within an industry to achieve the goals of the industry are not
effectively applied. Hence, it is necessary to spread awareness and create interest amongst people
to use risk management techniques in the industries.
Reference
1. Abebe Dinku, Insurance Requirements and Practices of Ethiopia’s Construction
Sector, Journal of EAEA, VoL 17, Department of Civil Engineering Addis Ababa
University, 2000
2. Addis Mesfin, A Study on Construction Contract Risk Management Practice in
Ethiopian Building Construction Projects, MSc. thesis, Faculty of Technology, Addis
Ababa University,2014
3. An IMCA Discussion Document, Identifying and Assessing Risk in Construction
Contracts, July, 2006
4. Bryan S. Shapiro, Transferring Risks in Construction Contracts, Shapiro Hankison &
Knutson Law Corporation
5. Civil Code of Ethiopia, 1960
6. Commercial Code of Ethiopia,1960
7. Getachew Yilma Debela, Construction Risk Management through Insurance in the
Ethiopian Federal Road Projects, Civil and Environmental Research, Vol.10, No.1,
2018
8. Guidance on Risk for the Engineering Profession, Engineering Council,2011
9. Nadeem Ehsan et al, Risk Management in construction industry,2010
10. Nael G.Bunni, Risk and Insurance In Construction, Second Edition, New York, 2003.
11. Martin Schieg, Risk management in construction project management, Journal of
Business Economics and Management, October 2011.
12. Partnership Victoria guidance material, Risk Allocation and Contractual Issues, a guide,
2001.
13. Project Management Institute. 2008, A guide to the project management body of
knowledge (PMBoK ), fourth edition, USA.
14. Public Procurement Agency (PPA), standard conditions of contract, Ethiopia, 2006.
15. The ministry of works and urban development, General conditions of contract for
construction of civil work projects, Ethiopia, December 1994.
16. Thomas PIALLES, Study of the Coherences and Dependencies between Quality and
Risk Management, within the Construction Industry, A thesis submitted in partial
fulfilment of the requirements for the degree of Master in Construction Research,
Technology and Management in Europe,Sep,2017
17. ZHANG Shuibo, ZHANG Le, GAO Risk Allocations in Construction Contracts, A
Comparison of China's Standard Form of Construction Contract and FIDIC Conditions
of Contract for Construction, Yuan,School of Management, Tianjin
University,People's Republic of China