06/25/2019 1
EQUIPMENT : FEED SURGE DRUM REV 0
PRPD 0
0
CHKD 0
INDEX
APPD 0
1 COVER PAGE 1
2 INDEX 2
4 RECORDS OF REVISION 3
6 DESIGN DATA 6
8 LOADINGS (UG-22) 8
9 EVALUATION OF MATERIALS 9
06/25/2019 2
EQUIPMENT : FEED SURGE DRUM REV 0
PRPD 0
0
CHKD 0
RECORDS AND SUMMARY OF REVISION
APPD 0
RECORDS OF REVISION :
PRPD CHKD. APPD.
REV DATE PAGES DESCRIPTION
BY BY BY
0 FIRST ISSUE
SUMMARY OF REVISION :
REV
DATE REVISION DETAILS PAGE NO.
NO.
0 ISSUED FOR REVIEW
06/25/2019 3
EQUIPMENT : FEED SURGE DRUM REV 0
PRPD 0
0
APPLICABLE STANDARDS, REFERENCES CHKD 0
AND CONVERSION FACTORS APPD 0
1 ft3 = 0.02831685 m3
PRESSURE
06/25/2019 4
06/25/2019 5
EQUIPMENT : FEED SURGE DRUM REV 0
PRPD 0
0
CHKD 0
DESIGN DATA
APPD 0
CONFIGURATION - HORIZONTAL
ASME SEC. VIII DIV. 1
DESIGN CODE -
EDITION 2017
ASME CERIFICATION MARK - -
INTERNAL DESIGN PRESSURE MPa(g) 1.379 [200 PSI]
EXTERNAL DESIGN PRESSURE bar(g) 0.1035
DESIGN TEMPERATURE FOR
°C 260 [500 °F]
INTERNAL PRESSURE DESIGN
DESIGN TEMPERATURE FOR
°C 260 [500 °F]
EXTERNAL PRESSURE DESIGN
INNER DIAMETER mm 2134 [7 FT]
T.L. TO.TL. LENGTH mm 4268 [14 FT]
M.D.M.T °C 0
CORROSION ALLOWANCE mm 3 INTERNAL
RADIOGRAPHY (SHELL/ D'END) - FULL/SEAMLESS RT1( UG-116)
FOR SHELL 1/1
JOINT EFFICIENCY (LONG/CIRC SEAM)
FOR D'END 1/1
INTERNAL OPERATING PRESSURE bar(g) 3.448 [50 PSI]
EXTERNAL OPERATING PRESSURE MPa(g) N.A.
OPERATING TEMPERATURE °C 142.78 [289 °F]
FLUID - NAPTHA NONLETHAL
DENSITY kg/m3 694
SEISMIC CODE - UBC
WIND CODE - UBC
PWHT - YES - DUE TO PROCESS SEE NOTE 2
IMPACT TESTING - EXEMPT SEE NOTE 3
NOTES:
1) As per endnote 36 of UG-99(b) & as defined in Appendix 3, MAWP is considered same as Design
Pressure as calculations are not made to determine MAWP. e.g. MAWP = Design Press.
2) Exempted As per UW-2,UCS-56,UCS-68
3) As per UG-20(f),UCS-66(c) and note (c) OF Fig UCS-66.
06/25/2019 6
EQUIPMENT : FEED SURGE DRUM REV 0
PRPD 0
0
RT REQUIREMENTS AND JOINT EFFICIENCY CHKD 0
AS PER UW-11, UW-12 APPD 0
1 LETHAL SERVICE NO
CONCLUSION:
2) RT IS CONSIDERED AS FOLLOWS:
06/25/2019 7
EQUIPMENT : FEED SURGE DRUM REV 0
PRPD 0
0
LOADINGS CHKD 0
AS PER UG-22 APPD 0
APPLICABLE
CLAUSE DESCRIPTION APPLICABLE
INTERNAL DESIGN PRESSURE YES
UG-22(a)
EXTERNAL DESIGN PRESSURE YES
UG-22(b) WEIGHT OF CONTENT & STATIC HEAD YES
UG-22(c) SUPER IMPOSED STATIC REACTIONS FROM WEIGHT OF ATTACHED EQUIPMENT NO
ATTACHMENT OF INTERNALS YES
UG-22(d)
VESSEL SUPPORT YES
CYCLIC & DYNAMIC REACTIONS NO
UG-22( e)
MECHANICAL LOADING NO
WIND LOAD YES
UG-22(f)
SEISMIC LOAD YES
UG-22(g) IMPACT REACTIONS (DUE TO FLUID SHOCK) NO
UG-22(h) TEMPERATURE GRADIENT AND DIFFERNTIAL NO
UG-22(i) ABNORMAL PRESSURE (CAUSED BY DEFLAGRATION) NO
UG-22(j) TEST PRESSURE AND COINCIDENT STATIC LOAD ACTING DURING TEST YES
06/25/2019 8
EQUIPMENT : FEED SURGE DRUM REV 0
PRPD 0
0
EVALUATION OF MATERIALS CHKD 0
APPD 0
MATERIAL P. NO. TEMPERATURE ALL. STRESS (2) RATIO
DESCRIPTION SPECIFICATION GR. NO. DESIGN PERMITTED S Sa Sa/S
°C °C Mpa Mpa 3)
1
SHELL SA-516 GR 60 300 538 118 118 1
1
1
DISHED END SA-516 GR 60 300 538 118 118 1
1
1
PADS SA-516 GR 60 300 538 136 138 1.015
2
NOZZLE FLANGES/ 1
SA-105 300 538 129 138 1.070
COUPLINGS 2
1
SUPPORTS SA-36 300 538 114 114 -
1
1
PIPE SA-106 GR B 300 538 118 118 1
1
BOLTING FOR SA 193 GR B7 1
300 538 172 172 -
FLANGES SA 194 GR 2H 1
NOTES:-
1) P NO. & GROUP NO. ARE FROM ASME BOILER & PRESSURE VESSEL CODE, SEC II PART D, ED-2017
2) S = ALLOWABLE STRESS AT DESIGN TEMPERATURE
Sa = ALLOWABLE STRESS AT AMBIENT TEMPERATURE
06/25/2019 9
EQUIPMENT : FEED SURGE DRUM REV 0
PRPD 0
0
FLANGE RATING CHECK CHKD 0
UG 44, ASME B16.5 APPD 0
FLANGE RATING CHECK:
AS PER UG 44, FLANGES AS PER ASME B16.5 ARE ACCEPTABLE
DESCRIPTION UNIT VALUE
STANDARD FOR FLANGES - ASME B16.5
SELECTED RATING - CL.300
MATERIAL - SA 105
MATERIAL GROUP - 1.1
DESIGN TEMPERATURE °C 260
ALLOWABLE PRESSURE FOR SELECTED RATING AT 300°C bar g 119.5
Mpa g 11.95
DESIGN PRESSURE INCLUSIVE OF STATIC HEAD(MAX.) Mpa g 8.4
CONCLUSION 11.95>8.4
SAFE
06/25/2019 10
EQUIPMENT : FEED SURGE DRUM REV
PRPD
0
POST FORMING HEAT TREATMENT CHKD
UCS-79, UG-79 APPD
POST FORMING HEAT TREATMENT
AS PER UCS-79(d), AFTER COLD FORMING, HEAT TREATMENT IS REQUIRED WHEN
THE RESULTING EXTREME FIBER ELONGATION IS MORE THAN 5% AND ANY OF
FOLLOWING CONDITION EXIST :
CONCLUSION:
POST FORMING HEAT TREATMENT IS NOT REQUIRED AS FIBRE ELONGATION IS EXCEEDING FOR
SHELL AND DISHED END.
06/25/2019 11
0
0
0
0
APPLICABLE
NO
NO
NO
NO
NO
N IS EXCEEDING FOR
06/25/2019 12
EQUIPMENT : FEED SURGE DRUM REV 0
PRPD 0
0
PWHT REQUIREMENT CHKD 0
UW-2, UCS-56, UCS-68 APPD 0
POST WELD HEAT TREATMENT IS REQUIRED WHEN ANY OF FOLLOWING CONDITION EXIST:
06/25/2019 13
EQUIPMENT : FEED SURGE DRUM REV 0
PRPD 0
0
IMPACT TEST CHKD 0
UG-20(f), UCS-66 APPD 0
AS PER UG-20(f), IMPACT TESING AS PER UG-84 IS NOT REQUIRED FOR PRESSURE VESSEL MATERIALS
WHICH SATISFY ALL OF THE FOLLOWING:
CONDITION
SR NO. CONDITION
SATISFIED
CONCLUSION:
IMPACT TEST IS NOT REQUIRED.
06/25/2019 15
EQUIPMENT : FEED SURGE DRUM REV 0
PRPD 0
0
REQUIREMENT FOR INSPECTION OPENING CHKD 0
UG-46 APPD 0
1. AS PER UG-46(a), ALL PRESSURE VESSELS FOR USE WITH COMPRESSED AIR AND
THOSE SUBJECT TO INTERNAL CORROSION OR HAVING PARTS SUBJECT TO EROSION
OR MECHANICAL ABRASION (SEE UG-25) EXCEPT AS PERMITTED OTHERWISE IN THIS
PARAGRAPH, SHALL BE PROVIDED WITH SUITABLE MANHOLE, HANDHOLE, OR OTHER
INSPECTION OPENINGS FOR EXAMINATION AND CLEANING.
2. AS PER UG-46(d), VESSELS 300 mm OR LESS IN INSIDE DIAMETER , OPENINGS FOR INSPECTION
ONLY BE OMITTED IF THERE ARE ATLEAST TWO REMOVABLE PIPE CONNECTIONS NOT
LESS THAN DN 20
CONCLUSION :
PROVIDED 24" OF MANWAY ON SHELL AS INSPECTION OPENING.
06/25/2019 16
S FOR INSPECTION
06/25/2019 17
EQUIPMENT : FEED SURGE DRUM REV 0
PRPD 0
0
REQUIREMENT FOR DRAIN CHKD 0
UG-25 APPD 0
CONCLUSION :
ONE DRAIN NOZZLE (DN 50) IS PROVIDED AT SUMP D'END.
06/25/2019 18
EQUIPMENT : FEED SURGE DRUM REV 0
PRPD 0
0
LIFTING LUG DESIGN CHKD 0
APPD 0
Description Symbol Unit Value
Empty weight of equipment We N 6513.84
Shock factor Sf - 2
Erection weight for design Wer N 13027.68
Number of lifting lugs N - 2
Sling angle with horizontal θ degree 90
Load along sling line = (Wer/sinθ)/N F N 6513.84
Width of lifting lug at hole centre b mm 80
Width of lifting lug at base b1 mm 80
Thickness of lifting lug t mm 20
Hole diameter d mm 34
Hole location from base of lug L mm 65
Pad length Lp mm 0
Pad width Wp mm 0
Pad thickness Tp mm 0
Pad to dish end fillet weld size Fp mm 16
Lifting lug to pad weld length = 2*(b1+t) Lpl mm 0
Lifting lug to pad weld size Fpl mm 0
Material - - SA 516 GR 70
06/25/2019 19
EQUIPMENT : FEED SURGE DRUM REV 0
PRPD 0
0
FLANGE CHECK FOR NOZZLE LOAD CHKD 0
CODE CASE 2901 APPD 0
FLANGE RATING CHECK:
AS PER UG 44, FLANGES AS PER ASME B16.5 ARE ACCEPTABLE
DESCRIPTION SYMBOL UNIT VALUE
NOZZLE MARK - - N1,N2
SIZE - - DN 150
FLANGE CLASS - - 300
DESIGN PRESSURE INCLUDING STATIC HEAD PD MPa g 8.4
DESIGN TEMPERATURE T °C 300
FLANGE PRESSURE RATING AT TEMPERATURE PR MPa g 11.95
MOMENT FACTOR FROM TABLE 1 FM - 0.5
LONGITUDINALBENDING MOMENT ML N-M 5370
CIRCUMFERENTIAL BENDING MOMENT MC N-M 6985
ME=SQRT( N-M
EXTRERNAL MOMENT ML2+Mc2) 8810.6256872029
EXTERNAL TENSILE AXIAL FORCE FE N 8025
GASKET O.D. Go MM 368.3
GASKET I.D. Gi MM 323.9
GASKET LOAD REACTION DIAMETER G MM 351.5
TOTAL EQUIVALENT MOMENT M1 N-M 152253.160995247
=16*ME + 4*FE*G/1000
PERMISSIBLE MOMENT M2 N-M 1298884.75789744
= π*G3*((PR-PD) + (FM*PR))/1000
CHECK WHETHER M1≤M2 - YES
CONCLUSION - SAFE
06/25/2019 20