Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Abstract—Overhead distribution systems may experience analyze the operation of a protection scheme for an actual
faults involving more than one feeder. During simultaneous fault involving two feeders of the Oaxaca Uno Substation
faults, the transformer low-voltage-side overcurrent relay located in Oaxaca de Juárez, Oaxaca, Mexico.
measures a current greater than the current measured by faulted
feeder relays. Therefore, the transformer relay may trip faster
than faulted feeder relays. Transformer relay misoperation II. SIMULTANEOUS FAULTS
affects service availability in circuits not involved with the fault. The need to improve service availability has increased the
In this paper, we describe the causes of simultaneous faults on complexity of distribution network topology. Disconnect
distribution feeders and discuss overcurrent protection
switches allow transferring loads to alternate sources under
coordination problems caused by these faults. We then propose
low-cost protection schemes using multifunction relays with emergency conditions. Limitations on the rights of way make
communications and logic programming abilities. We summarize it necessary to use multicircuit overhead lines or single-circuit
the operation experience of 19 simultaneous fault protection lines that run close to each other. As a result, simultaneous
schemes installed in several substations of two Comisión Federal faults involving more than one circuit are becoming quite
de Electricidad (CFE) distribution divisions in Mexico. Finally, common. Typical causes of simultaneous faults include:
we analyze the operation of a protection scheme for an actual
simultaneous fault.
• Multicircuit lines or lines sharing the same right of
way
I. INTRODUCTION • Switching operations
• Thunderstorms
In radial distribution substations, feeder relays typically
Fig. 1 shows a distribution system with four feeders and
include instantaneous and inverse-time overcurrent elements.
normally open (NO) disconnect switches between adjacent
The transformer low-voltage-side relay provides backup for
feeders.
feeder faults and typically includes inverse-time overcurrent
elements. Utilities normally use automatic reclosing of B1
Feeder 1
overhead feeder breakers. The transformer low-voltage-side T
B3 S23 (NO)
relay to trip only the faulted feeder. However, for Feeder 3
T
simultaneous feeder faults, the current measured by the
S3 (NC)
transformer relay is greater than the current measured by each
T
B4 S34 (NO)
faulted feeder relay. The transformer relay may operate faster Feeder 4
T
than the faulted feeder relay and undesirably trip the
S4 (NC)
transformer low-voltage-side breaker. Transformer breaker
misoperation affects service to the loads of healthy feeders. Fig. 1. Operation of tie disconnect switches may cause simultaneous faults
Given the growing incidence of simultaneous faults, in distribution systems.
Comisión Federal de Electricidad (CFE), the Mexican national
Under normal conditions, the system shown in Fig. 1
electric utility, decided to apply simultaneous fault protection
operates radially. For a permanent fault on Feeder 2 between
schemes in distribution substations several years ago. For
Breaker B2 and the normally closed (NC) Disconnect
example, the CFE Southeastern Distribution Division has
Switch S2, Breaker B2 trips and recloses to lockout. Operation
18 schemes in operation, and the CFE Jalisco Distribution
personnel open Disconnect Switch S2 to isolate the fault and
Division recently commissioned one scheme.
then close either Disconnect Switch S12 or Disconnect Switch
In this paper, we discuss the overcurrent protection
S23 to restore service to the Feeder 2 load connected beyond
coordination problems caused by simultaneous faults. We
Disconnect Switch S2. When remote access to motor-operated
describe two types of simultaneous fault protection schemes
disconnect (MOD) switches is available, the system operator
for distribution substations and summarize the operation
can send control commands to MOD switches from the
experience of the schemes installed in several substations of
distribution system dispatch center, in which case, service
the CFE distribution divisions mentioned above. Finally, we
Fig. 2. For a feeder fault, the transformer relay and faulted feeder relay
measure practically the same current.
Receive
Copper
first feeder relay issues a reclosing-blocking signal to the
Relay Output Relay Logic second feeder relay to prevent reclosing of the second feeder
Contact Input
breaker onto a fault.
Relay 1 Relay 2 The simultaneous fault protection scheme clears faults in
(a) 3 to 6 cycles plus the breaker operating time. The fault-
clearing time is comparable to instantaneous tripping, even for
faults that fall out of the reach of the feeder relay
instantaneous overcurrent elements. In addition, this logic
discriminates between single and simultaneous faults and
TMB1A RMB1A issues an alarm for simultaneous faults (not shown in Fig. 8).
Transmit
Receive
Copper
or The alarm helps operation personnel to quickly and safely
Relay Relay
Transmitted Bit Optical Received Bit restore service to the loads.
Fiber
The logic of the distributed scheme using hardwired
Relay 1 Relay 2
connections is similar to the logic shown in Fig. 8. This
(b)
scheme requires wiring the output contact of each feeder relay
Fig. 7. Two methods of communication between the devices include to the logic inputs of all other feeder relays. The resulting
(a) wiring a relay output contact to a logic input of another device and (b) scheme is more complex and less reliable than the scheme in
direct digital communication between the devices over copper wire or fiber-
optic cable. Fig. 8. In addition, the relays cannot supervise the condition of
the copper wires.
Fig. 8 depicts the logic diagram of a distributed scheme for The distributed simultaneous fault protection scheme is
four feeders using direct digital communication. Feeder relays easy to apply as an enhancement to existing installations.
communicate via copper wires or fiber-optic cable in a looped When existing relays have logic programming abilities,
scheme, and each feeder relay communicates with two implementing the scheme requires only wiring and relay
adjacent feeder relays. The scheme uses phase (51P) and programming.
ground (51G) instantaneous overcurrent elements (fault
A B C D
RMB1A
RMB2A
RMB3A
RMB4A
Phase
Fault 51P Reclose
79RI
Detector Initiate
1 TPU
SV1 SV1T
Ground TDO
Fault 51G 2 To Tripping
TR
Detector Logic
TMB1A
TMB2A
TMB3A
TMB4A
Feeder 1 Relay
RMB1A
RMB2A
RMB3A
RMB4A
Phase
Fault 51P Reclose
79RI
Detector Initiate
1 TPU
SV1 SV1T
Ground TDO
Fault 51G 2 To Tripping
TR
Detector Logic
TMB1A
TMB2A
TMB3A
TMB4A
Feeder 2 Relay
RMB1A
RMB2A
RMB3A
RMB4A
Phase
Fault 51P Reclose
79RI
Detector Initiate
1 TPU
SV1 SV1T
Ground TDO
Fault 51G 2 To Tripping
TR
Detector Logic
TMB1A
TMB2A
TMB3A
TMB4A
Feeder 3 Relay
RMB1A
RMB2A
RMB3A
RMB4A
Phase
Fault 51P Reclose
79RI
Detector Initiate
TPU
1 SV1 SV1T
Ground TDO
Fault 51G 2
TR
To Tripping
Detector Logic
TMB1A
TMB2A
TMB3A
TMB4A
Feeder 4 Relay
A B C D
Fig. 8. Logic diagram of a distributed simultaneous fault protection scheme using direct digital relay-to-relay communication.
Phase
Fault 51P Timer 1 Reclose
79RI
Detector Initiate
TPU
TMB1A R1P1 SV1 SV1T T1P1 RMB1A
1
Ground TDO
Fault 51G 1 To Tripping
TR
Detector Logic
Phase
Fault 51P Timer 2 Reclose
79RI
Detector Initiate
TPU
TMB1A R1P2 SV2 SV2T T1P2 RMB1A
2
Ground TDO
Fault 51G 2 To Tripping
TR
Detector Logic
Phase
Timer 3
Fault 51P 79RI Reclose
Detector Initiate
TPU
TMB1A R1P3 SV3 SV3T T1P3 RMB1A
3
Ground TDO
Fault 51G 3 To Tripping
TR
Detector Logic
Phase
Timer 4 Reclose
Fault 51P 79RI
Detector Initiate
TPU
TMB1A R1P4 SV4 SV4T T1P4 RMB1A
4
Ground TDO
Fault 51G 4 To Tripping
TR
Detector Logic
Fig. 9. Logic diagram of a centralized simultaneous fault protection scheme using direct digital communication between the devices.
Fig. 9 depicts the logic diagram of a centralized scheme for The centralized simultaneous fault protection scheme
four feeders using direct digital communication between the concentrates all fault information in one device. This device
devices. Feeder relays communicate radially with the may provide sequential event reporting, which facilitates fault
transformer relay or logic processor via copper wires or fiber- analysis. When the scheme uses a logic processor, the
optic cables. For a simultaneous fault involving Feeder 1 and processor can provide additional functions, such as fast bus
Feeder 2 (see Fig. 4), the fault detectors 51P and/or 51G and tripping, breaker failure protection, and automatic restoration
the OR gate of these relays assert. Each relay transmits bit of unfaulted transformers [1].
TMB1A to the transformer relay or logic processor, where
received bits R1P1 and R1P2 assert. As a result, OR Gate 1, V. FIELD OPERATION EXPERIENCE
OR Gate 2, AND Gate 1, and AND Gate 2 assert in the Table I summarizes the simultaneous fault protection
transformer relay or logic processor. After a security delay, schemes operating in the CFE Southeastern Distribution
Timer 1 asserts bit SV1T, and Timer 2 asserts bit SV2T. The Division and the CFE Jalisco Distribution Division. The first
transformer relay or logic processor then transmits bit T1P1 to scheme was commissioned in 2003.
the Feeder 1 relay and bit T1P2 to the Feeder 2 relay to initiate
TABLE I
tripping and sequential reclosing of the faulted feeder SIMULTANEOUS FAULT PROTECTION SCHEMES
breakers. OPERATING IN TWO CFE DISTRIBUTION DIVISIONS
The logic of a centralized scheme using hardwired
Southeastern Jalisco
connections is similar to the scheme shown in Fig. 9. Scheme Type Distribution Distribution Total
However, the scheme is more complex and less reliable, Division Division
because two copper wires run between each feeder relay and
Distributed 17 0 17
the transformer relay or logic processor. In addition, the relays
cannot supervise the condition of the copper wires. Centralized 1 1 2
Total 18 1 19
Fig. 10. Simplified one-line diagram of the Oaxaca Uno Substation.
These schemes have operated correctly for all distribution feeders OAX-4010 and OAX-4020. The fault
46 simultaneous faults that have occurred on feeders of both current contributions were 2,001 A on the OAX-4010 feeder
distribution divisions. The causes of the faults are as follows: and 823 A on the OAX-4020 feeder. The prefault demands
• Faults in double-circuit lines: 20 were 5.9 MVA on the OAX-4010 feeder, 6.8 MVA on the
• Thunderstorms: 19 OAX-4020 feeder, and 28.9 MVA on the transformer.
• Faults during circuit-looped operation: 7 From the sequential event report of the OAX-4010 feeder
No scheme misoperations have occurred for faults relay (see Fig. 11), we conclude the following:
involving only one feeder, cold load pickup conditions, or • The phase fault detector 51P operated at
other abnormal conditions. 20:29:16.918 hours.
• The feeder relay transmitted fault detection
VI. EXAMPLE OF SCHEME OPERATION FOR AN ACTUAL FAULT information (bit TMB1A asserted) to the logic
processor at 20:29:16.918 hours.
A. Scheme Operation Analysis
• The feeder relay received a tripping command (bit
The Oaxaca Uno Substation (see Fig. 10), located in the RMB1A asserted) from the logic processor at
city of Oaxaca de Juárez, state of Oaxaca, Mexico, has a 20:29:17.051 hours.
12/16/20 MVA, 115/13.8 kV transformer and an
• The feeder relay sent a trip signal to the breaker (bit
18/24/30 MVA, 115/13.8 kV transformer. Each transformer
TRIP asserted) at 20:29:17.055 hours.
feeds four radial feeders. This substation has a centralized
• The breaker opened (bit 52A deasserted) at
simultaneous fault protection scheme using a protection
20:29:17.130 hours. Breaker operating time is
processor and direct digital communication between the
75 milliseconds (4.5 cycles).
devices.
The sequential event report of the OAX-4020 feeder relay
During a severe thunderstorm on May 18, 2009, a
is almost identical to the report shown in Fig. 11.
temporary phase-to-phase simultaneous fault occurred on
• Declared a simultaneous fault involving the
OAX-4020 feeder (bit SV6 asserted) at
20:29:16.953 hours.
• Sent a tripping signal to the OAX-4010 feeder relay
(bit T1P1 asserted) at 20:29:17.053 hours when the
timer expired (bit SV5T asserted). Timer pickup
setting is 100 milliseconds (6 cycles).
• Sent a tripping signal to the OAX-4020 feeder relay
(bit T1P2 asserted) at 20:29:17.053 hours when the
timer expired (bit SV6T asserted). Timer pickup
setting is 100 milliseconds (6 cycles).
20100120 • TP6414