Max 2x+3y
Subject to
x+ y ≤ 5
x+2y ≤ 7
x ≥ 0, y integer.
Submit the Excel file with the solution. Do make sure that Solver boxes are complete.
Solution:
X=3
Y=2
Solution:
‘Variables:
1
A = quantity to be produced in United States plant to be supplied to North America
B = quantity to be produced in United States plant to be supplied to Europe
C = quantity to be produced in Germany plant to be supplied to North America
D = quantity to be produced in Germany plant to be supplied to Europe
Objective function:
Min 600A + 1300B + 1300C + 600D + 10000A + 10000B + 7530C + 7530 D
Constraints:
A 0
B 185
C 270
D 15
b)
If we remove the limits on the production in the plant, we get the following linear
programming equation:
‘Variables:
Objective function:
Min 600A + 1300B + 1300C + 600D + 10000A + 10000B + 7530C + 7530 D
Constraints:
2
A+B >= 92.5
C+D >= 237.5
A+B <= 185
C+D <= 475
A 32.5
B 0.0
C 237.5
D 0.0
c)
Scenario 1:
On adding 10 ton capacity to United States plant, we get the following solution:
A 0
B 195
C 270
D 5.0
Scenario 2:
A 0
B 185
C 270
D 15.0
The value of the objective function is : $,4596,550
In this case, the cost is same as the scenario where no capacity was increased.
3
d)
Sunchem can introduce the exchange rates as a part of the constraint itself with equality to
ensure that changes are recorded, and the cost is minimized.