Incident – STO Dates

Planned Order 1408250052, created by MRP, for material 56445198 to be supplied to plant UST4
from plant UXHN with a Delivery Date of 01/31/2020.

Purchase Requisition 529377219 created from Planned Order 1408250052

Shipping Condition UL defaulted on Purchase Requisition 529377219 based on the entry in table
YMM1_SCOC_DEF
Purchase Order 4942742405 created from Purchase Requisition 529377219

Shipping Condition UL came from Purchase Requisition 529377219 and Route USAU94 defaulted
on Purchase Order 4942742405 based on the entry in YRDSDV1_SGB_03 - Route Determination
According to the Transit Time of 12 days on Route USAU94 and the Factory Calendar of VC on the
Shipping Point and a Delivery Date of 01/31/2020

The issue is that the following dates on the Delivery Schedule tab are incorrect:
Date field Current, Incorrect Values Values should be
Mat. Staging Date 01/30/2020 01/16/2020
Committed Date 01/30/2020 01/16/2020
Transptn Plang Date 01/31/2020 01/17/2020
Loadg Date 01/31/2020 01/17/2020
Goods Issue 01/31/2020 01/17/2020
This causes issues in the supplying plant:

With Material Planning, as the demand (ConRel) is shown on 01/30/2020, instead of 01/16/2020

With Shipment Scheduling, as the Goods Issue Date is shown as 01/31/2020, instead of 01/17/2020

The issue is not unique to this material or transportation lane, as it exists with all stock transport
purchase orders where YMM1_SCOC_DEF is used to determine the Shipping Condition on the
stock transport purchase requisition.