Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Credential Exposure
PERSONNEL
Tony Bird from Fyfe Pty Ltd is a principal process engineer with over ten years of
experience in hazardous area classifications of new and existing projects. His experience in
the development of retrospective hazardous area classifications includes Palm Valley gas
plant, Torrens Island power station, Pelican Point power station and numerous Santos
facilities.
His experience covers oil and gas pipeline and facility projects during all stages of design
from concept, feasibility, and FEED through to detailed design. He also has experience in
procurement, construction supervision, commissioning and operations support of pipeline
facilities.
Tony’s responsibilities for this project included the examination of site, confirmation of
installed equipment, and development of hazardous area classification and hazardous area
mapping drawings.
Neville Green from Sitzler Pty Ltd is an electrical engineer with over ten years of
experience in the design, construction, commissioning and inspection of installation in
hazardous environment in the oil and gas industry. Neville has the following competencies
in accordance to AS/NZS 4761(Refer attachments):
UTE NES 010 A Report on integrity of explosion protected equipment in hazardous areas
UTE NES 107 Install explosion-protected equipment and wiring systems (Ex)
UTE NES 707 Design electrical installations in hazardous areas (Ex)
Neville’s role was to perform close inspection of all electrical equipment in accordance to
AS/NZS 60079 series on site to verify installation. His role was also to review inspection
sheets and provide recommendations for remedial actions to ensure compliance.
David Bourke from Fyfe Pty Ltd is the surveyor who completed three dimensional (3D)
scanning and photography of the facilities. The 3D images were used by Fyfe drafters to
update site arrangement drawings. The 3D scan data is retained by Fyfe for future use if
required by APA Group.
METHODOLOGY
The Hazardous Area Verification Dossier is produced to ensure that the installation
complies with the appropriate certification documents as well as with AS/NZS 2381.1 and
any other relevant part of the AS/NZS 2381 and AS/NZS 60079 series. In addition
equipment and installations where hazardous areas exist are required to comply with the
applicable regulations of the applicable Australian State or Territory. It should be borne in
mind that an installation can come under the jurisdiction of several authorities with different
areas of responsibility, e.g. mining, electrical safety, handling and transport of flammable
materials and occupational health and safety.
APA GROUP – AMADEUS BASIN TO DARWIN PIPELINE
KATHERINE METER STATION HAZARDOUS AREA DOSSIER
This dossier has been prepared in accordance with the following codes and standards:
• Dossiers AS 2381.1:2005 - Electrical equipment for explosive gas atmospheres -
Selection, installation and maintenance Part 1: General requirements
• Hazardous area AS/NZS 60079.10.1:2009 - Explosive atmospheres: Classification of
areas - Explosive gas atmospheres (IEC 60079-10-1, Ed. 1.0 (2008) MOD) (2009)
• AS/NZS 60079.17:2009 : Explosive atmospheres - Electrical installations inspection
and maintenance (IEC 60079-17, Ed.4.0 (2007) MOD)
Note that a Hazardous Area Verification Dossier is a living document and should be
updated by APA and / or its contractors. Any modifications to electrical equipment, including
removing an instrument cover should be recorded and stored within the Dossier. Changes
to the operation or equipment installed within the station will require a review of the
hazardous area classification and may require revision of the classification, hazardous area
mapping drawings, hazardous area equipment lists and associated certificates of
conformity. An extract from AS 2381.1 (2005) is included to provide guidance to APA.
Previously AS / NZS Ex and FLP have been recognised certification standards for
equipment in hazardous areas and may have been applicable at the time of construction /
installation. Equipment that was identified as having any of the certification to show
conformity to the above standards was deemed to be acceptable. Where no certification
was available or certification was available to standards not recognised in Australia, a
conformity assessment document (CAD) is required. The CAD shall be completed by a
suitably qualified organisation and the associated residual risk shall be accepted by the
head of APA. For new installations, equipment with the correct certificates of conformity
should be used unless no item exists and then a CAD should be produced. No information
on the date of installation/ of equipment purchase/manufacturer has been provided of the
site. Therefore no checking has been undertaken to determine the currency of the
certificate at the time of installation.
DISCLAIMER
Opportunities for improvements (OFI) are provided for items associated with
hazardous area and general engineering. The scope of work for the project was to
identify hazardous area and provide visual inspection of the equipment. The visual
inspection did not include opening of equipment and the OFIs are limited to the level of
inspection. General engineering OFIs are non-exhaustive and require APA to confirm
the OFI and the recommendation.
APA GROUP – AMADEUS BASIN TO DARWIN PIPELINE
KATHERINE METER STATION HAZARDOUS AREA DOSSIER
It is necessary to ensure that any installation complies with the appropriate certification
documents as well as with this Standard and any other requirements specific to the
plant on which the installation takes place.
To achieve this result, a verification dossier shall be prepared for every plant and shall
be either kept on the premises or stored in another location in which case a document
shall be left on the premises indicating who the owner or owners are and where that
information is kept, so that when required, copies may be obtained. This dossier
should contain the information detailed in the appropriate Parts of this series of
Standards for the types of protection concerned.
a) Where applicable a statement of the identity of the person(s) having legal ownership
of the installation or parts thereof and where the verification dossier is located.
b) The classification of hazardous areas and the Standards used for the classification.
c) Equipment group and temperature class.
d) Installation instructions.
e) Documentation/certification for electrical equipment, including those items with
special conditions, for example, equipment with certificate numbers that have the
suffix ‘X’.
f) Descriptive system document for the intrinsically safe system.
g) Documentation relating to the suitability of the equipment for the area and
environment to which it will be exposed, e.g. T rating, Ex rating, IP rating, corrosion
resistance.
h) Documentation certifying that the equipment is rated for the voltages and frequency
applied during normal operation.
i) Manufacturer’s/qualified person’s declaration, e.g. tradesperson’s documentation
and inspector’s inspection reports.
j) Records sufficient to enable the explosion-protected equipment to be maintained in
accordance with its type of protection (for example, list and location of equipment,
spares, technical information).
k) Records covering any maintenance, overhaul and repair of the equipment.
l) Records of selection criteria for cable entry systems for compliance with the
requirements for the particular explosion technique.
m) Drawings and schedules relating to circuit identification (see Clause 3.8.16).
n) In New Zealand, the Hazardous Area Statement of Periodic Verification on
completion of a periodic inspection. (Refer to Appendix B).
APA GROUP – AMADEUS BASIN TO DARWIN PIPELINE
KATHERINE METER STATION HAZARDOUS AREA DOSSIER
It shall be the responsibility of the person(s) having legal ownership of the installation
or parts thereof to ensure that the relevant information is produced but the preparation
of the document may be delegated to expert bodies/organizations. The dossier may be
kept as hard copy or in electronic form.
Table of Contents
1 Site Information
2 Hazardous Area Classification Report
3 Observation For Improvement (OFI)
4 Hazardous Area Mapping Drawings
5 Hazardous Area Equipment Register and Certificates of Conformity
6 Datasheets and Electrical Drawings
7 Calculations
8 Manufacturer’s Data Report (MDR) and Installation, Operating and Maintenance
(IOM) Manual
9 Maintenance Register
10 Inspection Register
11 Overhaul, Repair, Modification and Replacement Register
12 Schedule of Equipment and Conditions Requiring Compliance Status Attention
Revision History:
1 Site Information
An inspection on the Katherine meter station site was performed on 10th September 2011
by Tony Bird, a principal process engineer from Fyfe, Neville Green, an electrical engineer
from Sitzler and David Bourke a surveyor from Fyfe.
The Katherine Meter/Regulating Station includes two filter separator, two water bath
heaters, a slop tank, a main line valve, control valves, pressure relief valves and the related
pipe work and valving.
The inlet to the station is DN 100 and consists of a buried station limit valve (MLV 11) with
above ground actuator, maintenance ports and cavity bleed. A scraper receiver vessel is
installed in parallel to MLV 11. The scraper vessel is fitted with local vent, PSV, pressure
indicator and associated pipe work and valving. The closure on the vessel is a blind flange.
The following instrumentation is installed at the inlet; pressure indicator, a pressure
transmitter and a temperature indicator.
The gas then passes through two parallel filter separators. Upstream of both filter
separators are temperature control valves that reduce the pressure to 4,400 kPag / 16°C
[based on operating conditions at the site visit]. The temperature control valves are
provided with cascade control for pressure and temperature. One valve is fitted with a
pneumatic controller to continue supply during outage of the electronic control system. The
filter separators are fitted with differential pressure transmitter, pressure indicator, high
liquid level switches and high-high liquid level switches. The liquids are drained manually to
an elevated slops tank. The slop tank is fitted with a liquid level glass and a hose to allow
emptying. Gas from filter separators is then heated by indirect fired water bath heaters up to
approximately 60 °C. The water bath heaters are operated as duty - standby, with the
standby heater remaining "hot" to allow quick change over of the that is controlled by
actuated valves on the inlet to each heater.
The heated gases from heaters pass through two parallel regulator / meter runs. The
regulator / meter runs are operated in duty - standby and each contains active - monitor
pressure regulators. The meter skids are provided with two actuated valves that close on
high pressure downstream of the regulators. Additional high pressure switches at the
station outlet provide a station ESD. Further over pressure protection is provided by a PSV
at the station outlet. A meter is provided in each run. The meters are orifice meters with
upstream flow conditioners, temperature transmitters, pressure transmitters and high and
low range differential pressure transmitters. Each run is provided with a local blowdown
point, pressure indicators and valving.
The station outlet is provided with a temperature indicator, temperature transmitter and low
temperature switches. There is also provision for the installation of a future gas sampler.
The connection to the Katherine power generation site is DN 100.
Instrument gas is conditioned locally for each actuated valve and temperature control valve.
Gas is conditioned at each water bath heater to provide fuel gas for the pilot and main
burners. The fuel gas conditioning trains comprise of pre-heat coil, strainer, primary
APA GROUP – AMADEUS BASIN TO DARWIN PIPELINE
KATHERINE METER STATION HAZARDOUS AREA DOSSIER
pressure regulating valve, actuated ESD valves, secondary pressure regulating valve,
meter and temperature control valve.
The gas released in emergency directs to the vent stack that discharges to atmosphere and
the liquid removed from the gas flows to the slop tank. The maximum PSV set point is
3,200 kPag and the temperature limit is set at 60 °C in the station.
A control system provides control and telemetry for the various process measurement
parameters. The control system provides flow control and high pressure automatic
shutdown functionality and allows remote operator shutdown. The control system is
powered by single phase 230 VAC power supply, with back up batteries.
APA GROUP – AMADEUS BASIN TO DARWIN PIPELINE
KATHERINE METER STATION HAZARDOUS AREA DOSSIER
The site arrangement drawings and P&IDs for Katherine meter station can be found
overleaf.
This section contains the hazardous area classification report written for the Amadeus
Basin to Darwin pipeline facilities.
AMADEUS BASIN TO DARWIN PIPELINE
HAZARDOUS AREA CLASSIFICATION
TABLE OF CONTENTS
2.1 INTRODUCTION ................................................................................................... 3
2.1.1 Objective......................................................................................................... 3
2.1.2 Scope of Stations ........................................................................................... 4
2.1.3 Exclusions ...................................................................................................... 5
2.1.4 Revision History.............................................................................................. 5
2.1.4.1 Revision A ............................................................................................. 5
2.1.4.2 Revision B ............................................................................................. 5
2.1.4.3 Revision C ............................................................................................. 5
2.1.4.4 Revision D ............................................................................................. 6
2.1.4.5 Revision E ............................................................................................. 6
2.1.4.6 Revision 0 ............................................................................................. 6
2.2 Methodology ........................................................................................................ 7
2.3 References ........................................................................................................... 8
2.3.1 Australian Standards ...................................................................................... 8
2.3.2 International Standards .................................................................................. 8
2.4 Process Description and Operations ................................................................ 9
2.4.1 Process Description........................................................................................ 9
2.4.1.1 Overview ............................................................................................... 9
2.4.1.2 Mereenie ............................................................................................... 9
2.4.1.3 Palm Valley ......................................................................................... 10
2.4.1.4 Palm Valley Alice Springs ................................................................... 10
2.4.1.5 Tylers Pass ......................................................................................... 11
2.4.1.6 Tennant Creek Metering Station ......................................................... 12
2.4.1.7 Elliott Meter Station ............................................................................. 13
2.4.1.8 Daly Waters Scraper and Meter Station .............................................. 13
2.4.1.9 Katherine Offtake ................................................................................ 14
2.4.1.10 Katherine Meter / Regulating Station .................................................. 14
2.4.1.11 Pine Creek .......................................................................................... 15
2.4.1.12 Darwin City Gate ................................................................................. 16
2.4.1.13 Channel Island .................................................................................... 17
2.4.1.14 Scraper Stations .................................................................................. 18
2.4.1.15 Ban Ban Springs Scraper Station ....................................................... 18
2.4.1.16 Warrego Scraper Station ..................................................................... 19
2.4.1.17 Mainline Valves ................................................................................... 19
2.4.1.18 Bachelor Mainline Valve ...................................................................... 20
2.4.2 Operating Conditions .................................................................................... 20
2.4.3 Ventilation ..................................................................................................... 20
2.5 Properties of Hazardous Materials .................................................................. 21
2.5.1 Gases Handled ............................................................................................. 21
2.5.2 Liquids Handled ............................................................................................ 23
2.5.2.1 Filter Separator Drains ........................................................................ 23
2.5.2.2 Odorant ............................................................................................... 23
2.6 EQUIPMENT SELECTION.................................................................................. 24
2.7 CLASSIFICATION .............................................................................................. 25
2.7.1 Piping ........................................................................................................... 25
2.7.1.1 Process Piping .................................................................................... 25
2.7.1.2 Instrument Gas Piping ......................................................................... 25
2.7.1.3 Fuel Gas Piping ................................................................................... 26
2.7.1.4 Control Valves ..................................................................................... 26
2.7.1.5 Pressure Relief and Safety Relief Valves ........................................... 26
2.7.1.6 Mainline Valves ................................................................................... 27
Page 1
APA GROUP – AMADEUS BASIN TO DARWIN PIPELINE
HAZARDOUS AREA CLASSIFICATION
Revision History:
Page 2
APA GROUP – AMADEUS BASIN TO DARWIN PIPELINE
HAZARDOUS AREA CLASSIFICATION
2.1 INTRODUCTION
2.1.1 OBJECTIVE
The hazardous area classification covers the above ground gas regulating and metering
stations, scraper stations and mainline valves in the Northern Territory Gas Network.
The pipeline and facilities were originally constructed in 1985 with the additional facilities
added to supply new users and supply points. No hazardous area documentation was
completed at the time of the construction as there were no Australian Standards for
hazardous area classification in 1985. The selection, installation and maintenance of
electrical equipment were covered by AS 1076 series (1977).
This report documents the results of a Hazardous Area Classification undertaken for the
facilities mentioned in Section 2.4.
The interpretation and application of this classification should take into account that
Hazardous Area Classifications are inherently “imprecise” and involve assumption based
estimates, code interpretation and engineering judgement.
Page 3
APA GROUP – AMADEUS BASIN TO DARWIN PIPELINE
HAZARDOUS AREA CLASSIFICATION
Page 4
APA GROUP – AMADEUS BASIN TO DARWIN PIPELINE
HAZARDOUS AREA CLASSIFICATION
2.1.3 EXCLUSIONS
The following stations are excluded from this hazardous area classification
• Alice Springs facilities (owned and operated by Envestra),
• McArthur River Mine pipeline lateral facilities,
• Warrego compression facilities (scraper facilities are included),
• Tenant Creek offtake,
• Helling scraper station training pipework,
• Cosmo Howley facilities,
• Mt Todd facilities,
• Weddell facilities,
• Mataranka meter station.
The hazardous area classification does not consider the hazardous area associated with
equipment not included in the pipeline licence, e.g. gas plants at Mereenie and Palm
Valley, and the gas reticulation facilities at Darwin.
2.1.4.2 Revision B
Further inspection of sites was undertaken in August 2011 and the hazardous area
classification updated to incorporate sources of hazardous release from the equipment at
these sites. The additional sites inspected were:
• Mereenie Station
• Palm Valley Meter Station
• Palm Valley Interconnect / Alice Springs Meter Station
• Tylers Pass Station
• Tanami Road Scraper Station
• Aileron Valve Site
• Ti Tree Scraper Station
2.1.4.3 Revision C
The hazardous area classification updated to incorporate comments and recommendations
from APA.
Page 5
APA GROUP – AMADEUS BASIN TO DARWIN PIPELINE
HAZARDOUS AREA CLASSIFICATION
2.1.4.4 Revision D
Further inspection of sites was undertaken in September 2011 and the hazardous area
classification updated to incorporate sources of hazardous release from the equipment at
these sites. The additional sites inspected were:
• Katherine Meter Station
• Mataranka Scraper Station
• Ban Ban Springs Scraper Station
• Batchelor Valve Site
• Berry Springs Valve Site
In addition there were some revisions to site descriptions for the stations included at
revision to ensure consistency.
2.1.4.5 Revision E
Further inspection of sites was undertaken in October 2011 and the hazardous area
classification updated to incorporate sources of hazardous release from the equipment at
these sites. The additional sites inspected were:
• Wauchope Scraper Station
• Tennant Creek Meter Station
• Warrego Springs Scraper Station
• Renner Springs Scraper Station
• Elliott Meter Stations
• Newcastle Waters Scraper Station
• Daly Waters Meter Station
2.1.4.6 Revision 0
• Original Issue for use.
Page 6
APA GROUP – AMADEUS BASIN TO DARWIN PIPELINE
HAZARDOUS AREA CLASSIFICATION
2.2 METHODOLOGY
This Hazardous Area Classification has been carried out in accordance with the “source-
by-source” guidance taken from AS/NZS 60079.10.1 (Standards Association of Australia
and New Zealand), in association with IP Code Part 15 (Institute of Petroleum – UK) and
API RP 505 (American Petroleum Institute – USA).
The potential leaks that can be anticipated in both normal and abnormal operations have
been considered, such as the failure of a valve gland and the partial failure of a gasket
flange. The application of explosion proof (Ex) equipment will make sure that ignition does
not take place. The classification does not allow for catastrophic failure of pipework or
equipment where the associated mechanical effects are almost certain to cause ignition.
The extent of Zone 0, 1 and 2 areas has been identified by investigating each relevant
source or type of source.
Due to the imprecision inherent in hazardous area classification, the designation of small
non-hazardous area within larger hazard areas has been avoided.
Natural boundaries have been used to define zone limits where reasonably practical. In
some cases, where believed adequate, this has reduced the assigned area to some extent.
In other cases, where there is no economic disadvantage, the zone areas have been
extended to simplify their arrangement.
The equipment and pipework in the stations are installed in open outdoor (all sides of the
compounds are open and the stations are not installed in natural depressions), therefore
they are considered adequately ventilated. This classification assumes that all stations on
the ADP covered by this report are well maintained at all times.
Page 7
APA GROUP – AMADEUS BASIN TO DARWIN PIPELINE
HAZARDOUS AREA CLASSIFICATION
2.3 REFERENCES
2.3.1 AUSTRALIAN STANDARDS
Page 8
APA GROUP – AMADEUS BASIN TO DARWIN PIPELINE
HAZARDOUS AREA CLASSIFICATION
2.4.1.1 Overview
The Amadeus Darwin Pipeline (ADP) was constructed to deliver gas from the Palm Valley
and Mereenie gas plants in the south of the Northern Territory to Darwin in the north of the
territory. Several offtakes have been added to supply users along the length of the pipeline.
The pipeline is approximately 1,513 km long.
Currently, the majority of the gas is supplied to the ADP from Wadeye via the Bonaparte
pipeline. The Bonaparte pipeline connects in to the ADP at Ban Ban Springs.
Typically drains and vents in the facilities are fitted with plugs or caps and therefore are not
a source of release during normal operation. Drains are operated only when then the
pipeline is depressured and do not require further consideration, vent points marked with
BD on the P&IDs are assumed to be operated during routine operation and maintenance of
the station and require consideration as a source of release.
2.4.1.2 Mereenie
Gas to the Mereenie station comes from the Santos operated Mereenie gas plant. Currently
there is no contract for the supply of gas from Mereenie, however the station remains
pressurised and can be returned to operation if required.
The station consists of DN 200 above ground connection to the Mereenie gas plant. Close
to the connection point are temperature and pressure transmitters and high temperature
and pressure trips and a station limit valve (SLV). The SLV is pneumatically actuated from
instrument gas conditioned locally. The instrument gas system is provided with a local PSV
that vents to atmosphere.
The gas then passes to two parallel filter separators. The filter separators are horizontal
and fitted with quick opening closures to allow removal of the filter elements. The filter
separators have been swapped with the filters originally installed at Palm Valley and this
required some pipework modifications. The liquids removed from the gas are collected in a
drain boot underneath the filter separator. The liquids are drained back to the Mereenie
production facility. The filter separators are fitted with the following instrumentation;
pressure indicator, differential pressure transmitter, level glasses, high level switches and a
PSV.
From each filter separator the gas flows to a meter run. The flow meters are orifice meters
that are fitted with flow conditioners, pressure transmitter, a low range and a high range
differential pressure transmitter and a temperature transmitter. A blowdown point is
provided on each meter run that can blow down the meter run and filter separator.
The pipework downstream of each meter run joins to a common line. There is a DN 20
blowdown point and an insertion sample probe installed to provide gas samples for the gas
chromatograph and dew point analyser.
The gas then passes underground through a manual station limit valve to the Mereenie to
Tylers Pass pipeline. There is a scraper launcher installed with quick opening closure,
pressure indicator, blow down vent and associated valving for the launching of pigs.
Page 9
APA GROUP – AMADEUS BASIN TO DARWIN PIPELINE
HAZARDOUS AREA CLASSIFICATION
Page 10
APA GROUP – AMADEUS BASIN TO DARWIN PIPELINE
HAZARDOUS AREA CLASSIFICATION
The line from the Palm Valley gas plant is DN 100 which increases to DN 200. The gas
then passes to a restriction orifice (RO). Upstream of the RO is the DN 50 kicker line
connection to the scraper launcher. Downstream of the RO is the connection from the ADP.
Next there is a station limit valve (SLV) that isolates Palm Valley to Alice Springs pipeline
from both gas feeds. The SLV is pneumatically actuated from instrument gas conditioned
locally and closes when a low pressure is sensed in the pipeline.
The scraper launcher is fitted with a quick opening closure, a pressure indicator, pressure
relief valve and valves to allow operation.
Parallel to the scraper launcher is a wall. The wall is 1.8 m away from the centre line of the
scraper launcher. The impact of the wall on the hazardous zones will be to extend the size
of the hazardous area zone (refer section 2.7.12).
Page 11
APA GROUP – AMADEUS BASIN TO DARWIN PIPELINE
HAZARDOUS AREA CLASSIFICATION
Page 12
APA GROUP – AMADEUS BASIN TO DARWIN PIPELINE
HAZARDOUS AREA CLASSIFICATION
Page 13
APA GROUP – AMADEUS BASIN TO DARWIN PIPELINE
HAZARDOUS AREA CLASSIFICATION
The actuated valve is gas over oil actuated. Downstream of the actuated valve are two dry
gas filters. Each dry gas filter is fitted with a differential pressure transmitter, manual vent
and a drain. The gas from each filter passes to a meter run that comprises of a flow
conditioner, orifice plate and thermowells. One of the meter runs is not fitted with
instruments. The other is fitted with pressure transmitter, differential pressure transmitter
and temperature transmitter.
Page 14
APA GROUP – AMADEUS BASIN TO DARWIN PIPELINE
HAZARDOUS AREA CLASSIFICATION
The station outlet is provided with a temperature indicator, temperature transmitter and low
temperature switches. There is also provision for the installation of a future gas sampler.
The connection to the Katherine power generation site is DN 100.
Instrument gas is conditioned locally for each actuated valve and temperature control valve.
Gas is conditioned at each water bath heater to provide fuel gas for the pilot and main
burners. The fuel gas conditioning trains comprise of pre-heat coil, strainer, primary
pressure regulating valve, actuated ESD valves, secondary pressure regulating valve,
meter and temperature control valve.
The gas released in emergency directs to the vent stack that discharges to atmosphere and
the liquid removed from the gas flows to the slop tank. The maximum PSV set point is
3,200 kPag and the temperature limit is set at 60 °C in the station.
A control system provides control and telemetry for the various process measurement
parameters. The control system provides flow control and high pressure automatic
shutdown functionality and allows remote operator shutdown. The control system is
powered by single phase 230 VAC power supply, with back up batteries.
Page 15
APA GROUP – AMADEUS BASIN TO DARWIN PIPELINE
HAZARDOUS AREA CLASSIFICATION
gasket. A spare flange is provided at the connection point for a future connection to the
Pine Creek power generation site, the flange is fitted with a blind flange, insulation gasket
and a surge arrestor.
Liquids collected from the dry filter, filter separator and knock out pots is sent to an
elevated slops tank. The slops tank is fitted with a safety relief valve (SRV, pressure
vacuum vent valve, flame arrestor, pressure indicator, high liquid level switch and hose for
emptying.
Vents and PSV discharges from the dry filter, filter separator and knock out pots and vents
from instrument manifolds and pneumatic controllers are sent to a local vent stack. The
vent stack is fitted with a flame arrestor.
Instrument gas is conditioned centrally for the site from a connection from the outlet knock
out pot.
Gas is conditioned at each water bath heater to provide fuel gas for the pilot and main
burners. The fuel gas conditioning trains comprise of pre-heat coil, strainer, primary
pressure regulating valve, actuated ESD valves, secondary pressure regulating valve,
meter and temperature control valve. A control system provides control and telemetry for
the various process measurement parameters. The control system provides flow control
and high pressure automatic shutdown functionality and allows remote operator shutdown.
The control system is powered by single phase 230 VAC power supply, with back up
batteries.
Page 16
APA GROUP – AMADEUS BASIN TO DARWIN PIPELINE
HAZARDOUS AREA CLASSIFICATION
temperature and level control valves are pneumatically controlled and actuated. Local
instrument gas conditioning skid is provided with PSV to provide over pressure protection.
Common line of the outlet from the filter separators is installed with temperature indicators,
temperature transmitter, pressure indicators, and pressure transmitters. The connection
point for the gas chromatograph and dew point analyser has been installed to this section
of pipework to allow analysis of the gas. The gas chromatograph and dew point analyser
are installed in a shelter adjacent to the filter skid. The chromatograph receives a sample of
the transmission gas at a pressure of approximately 140 kPag from an insertion regulator
installed in the pipe. The carrier and calibration gases are stored in gas bottles and
regulated for use at 140 kPag. The chromatograph vents gas to exhaust vents above the
analyser shelter roof. The mainline then passes through a mainline valve. Downstream of
the mainline valve is installed with pressure indicator and transmitter before the pipeline
directed to Channel Island meter station.
A separate offtake to TPOTS passes gas to a DN 50 pressure regulation and metering
skid. The skid has duty and standby arrangement with each containing active and monitor
pressure regulators and turbine meters. A high pressure trip is provided that closes an
actuated valve at the inlet. The meter runs, with one serving as duty run and other as
standby run. The gas is then directed to Berrimah Road.
A control system provides measurement and telemetry for the various process instruments.
The control system allows remote operator shutdown. The control system is powered by
single phase 230 VAC power supply, with back up batteries.
Page 17
APA GROUP – AMADEUS BASIN TO DARWIN PIPELINE
HAZARDOUS AREA CLASSIFICATION
1 regulation, filter and metering runs is fitted with low pressure switch and high pressure
switches that all initiate an ESD, and a pressure transmitter, pressure indicator,
temperature transmitter, temperature indicator, low temperature switch connection for
future gas analysis and an isolation valve.
The Unit 7 filter, regulation and metering run comprises of two parallel runs each consisting
of filter separator, pressure regulators, metering and associated instrumentation and
valving. There is an actuated valve at the inlet before a split to two filters. The filters are
fitted with pressure indicator and differential pressure transmitter. Downstream of each filter
is an actuated valve. The valves are normally open and are closed on signal from the
control system or high pressure downstream of the pressure regulators. Metering is
provided by a Coriolis meter and a AVT turbine meter. The primary duty meter is the
Coriolis meter, but the turbine meter can be operated in series or parallel. Both meters are
provided with temperature and pressure correction. Downstream of the meters the
combined outlet has a PSV, local manual vent, temperature transmitter and pressure
transmitter.
Instrument gas is conditioned locally for each actuated valve.
A control system provides measurement and telemetry for the various process instruments.
The control system allows remote operator shutdown. The control system is powered by
single phase 230 VAC power supply, with back up batteries.
Page 18
APA GROUP – AMADEUS BASIN TO DARWIN PIPELINE
HAZARDOUS AREA CLASSIFICATION
At the Helling scraper station there are pipework and vents that are used for training The
training pipework is not connected to the station pipework during normal operation of the
pipeline and the training pipework is unpressurised. No records have been provided for the
training pipework and it is not included in the hazardous area classification.
Page 19
APA GROUP – AMADEUS BASIN TO DARWIN PIPELINE
HAZARDOUS AREA CLASSIFICATION
2.4.3 VENTILATION
Each of the sites is in the open air and is considered to have good ventilation. Some
equipment is installed in open-sided shelters. These are not considered to have any impact
on ventilation.
Page 20
APA GROUP – AMADEUS BASIN TO DARWIN PIPELINE
HAZARDOUS AREA CLASSIFICATION
Page 21
APA GROUP – AMADEUS BASIN TO DARWIN PIPELINE
HAZARDOUS AREA CLASSIFICATION
The chromatograph used for gas composition analysis requires carrier and calibration
gases. The carrier gas (helium) is not flammable, while the calibration gas (mainly
methane) is classified as a Category G(i) fluid with similar compositions as process gas.
Page 22
APA GROUP – AMADEUS BASIN TO DARWIN PIPELINE
HAZARDOUS AREA CLASSIFICATION
2.5.2.2 Odorant
Odorant is injected into the pipeline at Tylers Pass. The odorant is SpotLeak 1005 and is a
flammable liquid. It consists of Thiophene, Propanethiol and methyl as per the product
specification. The odorant is classified as group IIA in accordance to AS/NZS 60079.20 and
category C fluid in accordance with IP15 Section 1 (Table 1.2 – fluid categories).
Page 23
APA GROUP – AMADEUS BASIN TO DARWIN PIPELINE
HAZARDOUS AREA CLASSIFICATION
Page 24
APA GROUP – AMADEUS BASIN TO DARWIN PIPELINE
HAZARDOUS AREA CLASSIFICATION
2.7 CLASSIFICATION
2.7.1 PIPING
Page 25
APA GROUP – AMADEUS BASIN TO DARWIN PIPELINE
HAZARDOUS AREA CLASSIFICATION
Page 26
APA GROUP – AMADEUS BASIN TO DARWIN PIPELINE
HAZARDOUS AREA CLASSIFICATION
of discharge from 1 m behind the points of discharge to a distance 8 m in front of the points
of discharge.
The seats on the PSVs and SRVs will be metal to metal and tight shut-off, which will
contribute to a small leakage at the vent tips during the normal operation. In line with the
specification described in IP15 Section 5.4.4.5, a Zone 2 area of nominal 1 m radius should
be placed around the end of the discharge point to account for any small leakages. It is
recommended to upgrade the Secondary grade of release to a Primary grade of release
accounting for the presence of the flammable material in the normal operating. Hence, an
additional Zone 1 area with a nominal hazard radius of 1 m is claimed around the PSV and
SRV discharge points to account for the minor leak through the valve seats.
The hazard zones of the PSVs and RSVs are considered to be the same due to lack of the
discharge rates, which actually affect the extending zone of hazardous area.
The hazard zones adopted for the PSVs and RSVs are summarised below:
Zone 1 1 m radius from the vent tips
Zone 2 6 m laterally, 8 m above and 1 m below the discharge points
Page 27
APA GROUP – AMADEUS BASIN TO DARWIN PIPELINE
HAZARDOUS AREA CLASSIFICATION
Page 28
APA GROUP – AMADEUS BASIN TO DARWIN PIPELINE
HAZARDOUS AREA CLASSIFICATION
undertake plume analysis based on the blowdown conditions. An estimate of the extent of
the plume from previous experience for pipeline blowdown vents is a cylinder with a radius
of 15 m and a length of 30 m extending in the direction of the discharge and 1 m below the
discharge point to account for the localised turbulence at the vent tip. Pipeline blowdowns
are a done infrequently and therefore a Secondary release that results in a Zone 2
hazardous area. The discharge is vertically upwards and therefore no ground effect would
occur.
During normal operation a quick opening closure in the closed position is considered to
provide similar containment as a pipe flange or fitting. Therefore the associated release
would be Secondary providing a Zone 2 hazardous area of 2 m as per AS/NZS 60079.10.1
Clause ZA.6.4.2.4.
Zone 2 A cylinder of radius 15 m extending 30 m vertically upwards and 1 m
downwards from the point of discharge
HOLD The exact shape of the hazardous area zone should be determined using
plume dispersion modelling based on the blowdown operation and
conditions.
Page 29
APA GROUP – AMADEUS BASIN TO DARWIN PIPELINE
HAZARDOUS AREA CLASSIFICATION
Page 30
APA GROUP – AMADEUS BASIN TO DARWIN PIPELINE
HAZARDOUS AREA CLASSIFICATION
Page 31
APA GROUP – AMADEUS BASIN TO DARWIN PIPELINE
HAZARDOUS AREA CLASSIFICATION
The heater compartment is not considered to be gas tight and an additional hazardous area
zone is claimed that will surround the heater compartment. The release will be a primary
grade of release. The heater has good ventilation and a Zone 1 hazardous area is claimed.
The released gas will be fuel gas and will be close to atmospheric pressure. In accordance
with section 2.7.1.3 the extent of the hazardous area will be 0.5 m from the outside of the
box.
The hazard zone adopted for the catalytic heater is summarised below:
Zone 0 Inside the heater compartment
Zone 1 0.5 m from the edges of the heater box
Zone 2 2 m radius from the high pressure gas connections of the vessel
Page 32
APA GROUP – AMADEUS BASIN TO DARWIN PIPELINE
HAZARDOUS AREA CLASSIFICATION
radius is declared from the vent tips in accordance with AS/NZS 60079.10.1 Clause
ZA.6.6.2.8 for the low velocity vents in adequately ventilated area.
In addition, a larger region that represents infrequent higher gas quantities may exist
surrounded the Zone 1 area due to the failure of pressure regulator or PSV. It results a
Secondary grade of release and an additional Zone 2 area with 1 m radius is considered
around the vents in accordance with AS/NZS 60079.10.1 Clause ZA.6.6.2.8.
The pressure relief valve will be activated in emergency. To simplify the hazardous area
arrangement, it is treated the same as a vent as described above.
The hazard zones adopted for the chromatograph system are summarised below:
Zone 1 0.5 m radius from the vent tips
Zone 2 0.5 m radius around the gas chromatograph system, excluding the cylinders
1.0 m radius around the vent tips
Page 33
APA GROUP – AMADEUS BASIN TO DARWIN PIPELINE
HAZARDOUS AREA CLASSIFICATION
The hazard zone adopted for the water dew point analyser / gas sampler is summarised
below:
Zone 1 0.5 m radius from the vent tips
Inside the sampler box
Zone 2 0.5 m radius around the water dew point analyser system
1.0 m radius around the vent tips
Page 34
APA GROUP – AMADEUS BASIN TO DARWIN PIPELINE
HAZARDOUS AREA CLASSIFICATION
Page 35
APA GROUP – AMADEUS BASIN TO DARWIN PIPELINE
HAZARDOUS AREA CLASSIFICATION
R1
R2
1.0 m
Page 36
APA GROUP – AMADEUS BASIN TO DARWIN PIPELINE
HAZARDOUS AREA CLASSIFICATION
Source of release
Page 37
APA GROUP – AMADEUS BASIN TO DARWIN PIPELINE
HAZARDOUS AREA CLASSIFICATION
Page 38
Part I – Sheet 1 of 1 Revision: 0
Date: 24/11/2011
Odorant
AS/NZS
(tetrahydrothiophene 0.939 (liquid)
Liquid 3 C 82 - -8 1.1* 12.1* 224 T3* IIA 60079.20
and 3.06 (vapour)
MSDS
tertiary butyl mercaptan)
† † † † † † † AS/NZS
Condensate Liquid 3 C 69 - 2.97 -21 1.0 8.4 233 T3 IIA
60079.20
* Values obtained for Tetrahydrothiophene
†
Based on Hexane
Part II – Sheet 1 of 4 Revision: 0
Date: 24/11/2011
Process Equipment Item Operating Description of Source Of Release Distance From Source To Equipment
Flammable Conditions Flammable Group and
Ventilation Section
Material Pressure and Material Boundary Boundary Boundary of Temperature
No. Description Location Temperature Containment Description Grade* Class
of Zone 0 of Zone 1 Zone 2
1 2 3 4 5 6 7 8 9 10 11 12 13 14
Closed system
< 9,650 kPag Flanges, joints, 2 m radius from
Process Vap. Cat with flanges, Natural
1 valve seals, S N/A N/A the edge of IIA, T1 2.7.1.1
piping “G(i)” < 60 °C piping joints and (open air)
drains and vents piping routes
valves
Closed system
< 770 kPag Flanges, joints, 1 m radius from
Instrument Vap. Cat with flanges, Natural
2 valve seals, S N/A N/A the edge of IIA, T1 2.7.1.2
gas piping “G(i)” < 60 °C piping joints and (open air)
drains and vents piping routes
valves
Closed system
< 700 kPag Flanges, joints, 0.5 m radius
Fuel gas Vap. Cat with flanges, Natural
3 valve seals, S N/A N/A from the edge of IIA, T1 2.7.1.3
piping “G(i)” < 60 °C piping joints and (open air)
drains and vents piping routes
valves
Amadeus
Basin to 0.5 m radius
Darwin Valves with 1 m radius
< 9,650 kPag Valve glands, around
Control Pipeline Vap. Cat packed gland / Natural around control
4 positioners and C&P&S N/A control valve IIA, T1 2.7.1.4
valves surface “G(i)” < 60 °C positioner / (open air) valve positioners
connections positioners
facilities exhaust and exhausts;
and exhaust
Pressure 6 m laterally,
< 9,650 kPag Valves and piping 1 m radius
relief and Vap. Cat Natural Pipe vent to 8 m above and 1
5 discharging C&P N/A from vent IIA, T1 2.7.1.5
safety relief “G(i)” < 60 °C (open air) atmosphere m below
vertically upwards tips
valves discharge points
Closed system Within
Mainline Vap. Cat < 9,650 kPag with flanges, Natural Connections and solenoid
6 S N/A As Piping IIA, T1 2.7.1.6
valves “G(i)” < 60 °C piping joints and (open air) valve seals valve
valves enclosure
6 m laterally,
< 9,650 kPag Valves and piping
Local Vent Vap. Cat Natural Pipe vent to 8 m above and 1
7 discharging S N/A N/A IIA, T1 2.7.1.7
Points “G(i)” < 60 °C (open air) atmosphere m below
vertically upwards
discharge points
* C – Continuous; S – Secondary; P – Primary
Part II – Sheet 2 of 4 Revision: 0
Date: 24/11/2011
Process Equipment Item Operating Description Source Of Release Distance From Source To Equipment
Conditions of
Flammable Group and
Pressure Flammable Ventilation Section
Material Boundary of Boundary Temperature
No. Description Location and Material Description Grade* Boundary of Zone 2
Zone 0 of Zone 1 Class
Temperature Containment
1 2 3 4 5 6 7 8 9 10 11 12 13 14
Date: 24/11/2011
Operating
Process Equipment Item Description of Source Of Release Distance From Source To Equipment
Conditions
Flammable Flammable Group and
Pressure Ventilation Section
Material Material Boundary of Boundary Boundary of Temperature
No. Description Location and Description Grade*
Containment Zone 0 of Zone 1 Zone 2 Class
Temperature
1 2 3 4 5 6 7 8 9 10 11 12 13 14
Date: 24/11/2011
Operating
Process Equipment Item Description of Source Of Release Distance From Source To Equipment
Conditions
Flammable Flammable Group and
Pressure Ventilation Section
No Material Material Boundary of Boundary Boundary of Temperature
Description Location and Description Grade*
. Containment Zone 0 of Zone 1 Zone 2 Class
Temperature
1 2 3 4 5 6 7 8 9 10 11 12 13 14
Flanges,
Closed system
Odorant < 9,650 kPag joints, valve 1.5 m in all
Vap. Cat with flanges, Natural
19 injection system seals, S N/A N/A directions down IIA, T3 2.7.10.1
“C” < 60 °C piping joints (open air)
pipework drains and to ground level
and valves
vents
Shelter
15 kPag 1.5 m in all
Vap. Cat Enclosed with open Connection
S N/A N/A directions down IIA, T3 2.7.10.2
“C” < 60 °C vessel sides s
to ground level
(open air)
Tylers Radius of
Within cylindrical
Pass Blanket gas Pipe vent to 1.5 m in all
Odorant P volume below
odorant vent atmosphere directions
20 injection system Zone 1
injection from vent tip
storage tanks
station
Pressure relief
valve and
Radius of 1.5 m
piping Pipe vent to
S N/A in all directions
discharging atmosphere
from vent tip
vertically
upwards
Pneumatic Shelter
Odorant < 400 kPag Piping
Vap. Cat pump with open
21 injection system connections C N/A N/A Radius of 0.5 m IIA, T1 2.7.10.3
“G(i)” < 60 °C instrument gas sides
pumps and vents
exhaust (open air)
Amadeus 2.5 m laterally
Flanges,
Basin to Closed system and extending to
< 9,650 kPag joints, valve
Darwin Vap. Cat with flanges, Natural 1 m above grade
22 Ground effect seals, S N/A N/A N/A 2.7.12
Pipeline “G(i)” < 60 °C piping joints (open air) for all process
drains and
surface and valves piping less than
vents
facilities 2 m above grade
* C – Continuous; S – Secondary; P – Primary
APA GROUP – AMADEUS BASIN TO DARWIN PIPELINE
HAZARDOUS AREA CLASSIFICATION
Page 44
APA GROUP – AMADEUS BASIN TO DARWIN PIPELINE
KATHERINE METER STATION HAZARDOUS AREA DOSSIER
KK0005-OFI-16
No cable support Provide cable support
Temperature
Transmitter/Element Damaged outer blue sheath
Replace blue sheathing
KK0005-TT/TE-22 of cabling
Replace blue cable sheath,
verify exposed armour and Replace blue sheathing
KK0005-OFI-17 rectify if required
Pressure Transmitter
Provide cable support Provide cable support
KK0005-PT-24
Replace damaged black
Replace damaged plug
plug
Fit the cable with a blue
KK0005-OFI-18 Blue sheath and cabling
sheath and provide cable
Temperature support required
support
Transmitter/Element
TE22A housing is loose at Tighten housing at
KK0005-TT/TE-22A
thermowell stem thermowell stem
Damaged blank plug Replace blanking plug
KK0005-OFI-19
Pressure Transmitter Fit the cable with a blue
Blue sheath and cabling
sheath and provide cable
KK0005-PT-24A support required
support
APA GROUP – AMADEUS BASIN TO DARWIN PIPELINE
KATHERINE METER STATION HAZARDOUS AREA DOSSIER
Additional Information
The slops tank receives liquids collected from the filter separators the tank is
elevated to allow emptying under gravity for disposal. At the time of the site visit the
tank was approximately 20% full. The liquids could be condensate, compressor oil or
water and therefore the tank should be designed as a storage tank for flammable
liquids which is covered by Australian standards AS 1940 “The storage and handling
of flammable and combustible liquids” and AS 1692 “Steel tanks for flammable and
combustible liquids”. Additionally there is an access ladder to the top of the tank that
should comply with AS 1657 “Fixed platforms, walkways, stairways and ladders -
Design, construction and installation”. Some deficiencies identified in the tank
arrangement include:
APA GROUP – AMADEUS BASIN TO DARWIN PIPELINE
KATHERINE METER STATION HAZARDOUS AREA DOSSIER
The tank should be replaced with a properly designed tank that meets the
requirements of the Australian standard and environmental (EPA) requirements.
The requirement for an elevated tank should be evaluated. Fyfe’s recommendation
would be to install a double skinned fibreglass tank at grade. The tank should include
an orifice on the inlet line from the filter vessels (the location would be dependent on
the pressure rating of the line), flame arrestor and explosion hatch. The vents should
be sized in accordance with AS 1940 and API 2000 “Venting atmospheric and low-
pressure storage tanks: non-refrigerated and refrigerated”.
APA should consider the addition of an orifice in the liquid drain line to minimise the
gas flow rate if the control valve fails open. Calculations should be performed on the
maximum gas rate through the level control valves and the associated capacity of
the vent points. It is recommended that plume dispersion is performed on the vent
point of the tank to determine the extent of the hazardous area.
The integrity of the underground drain pipe work between the filter vessels and the
slops tank should be investigated.
The generation of static in the emptying connection should conform to velocity
requirements in AS/NZS 1020 “The control of undesirable static electricity”. It is
recommended that the hose is replaced with one with an integral earth.
PSVs are provided on the fuel gas conditioning lines for the indirect fired heaters.
The PSVs are Fisher / Farris PSVs that are constructed from brass and the
discharge point is approximately 500 mm from grade. The integrity of brass in a fire
is questionable and carbon steel is preferable. Any personnel working on the
platform above the discharge point would be exposed to the gas. It is recommended
that a carbon steel PSV steel is installed with a discharge point 2,400 mm above the
platform, above head height. The new PSV should comply with AS 1271 “Safety
valves, other valves, liquid level gauges, and other fittings for boilers and unfired
pressure vessels”.
No
su
Fyfe has utilised the services of Daryl McCormick and Gail Courtney of Corrosion
Control Engineering in the past to provide solutions for insulation gaskets and surge
arrestors. The contact details are as below:
This section contains the hazardous area equipment register and associated certificates of
conformity.
Color Code Notes:
The equipment label was illegible at site and information is based on similar equipment.
The equipment label was illegible at site.
The equipment certification is not Australian and not available
Katherine Meter Station
Hazardous Area Equipment Register
Doc No.: 18756-5-70-002
Rev: 0
Date: 01-Nov-2011
1 of 6
Color Code Notes:
The equipment label was illegible at site and information is based on similar equipment.
The equipment label was illegible at site.
The equipment certification is not Australian and not available
Katherine Meter Station
Hazardous Area Equipment Register
Doc No.: 18756-5-70-002
Rev: 0
Date: 01-Nov-2011
KK0005-SVO-39 KK0005-7004-1 Upstream of Regulators Solenoid Valve (Open) ASCO/SAE FA80 163 / FNJ1 FA320A20 / - KK 0005-5001 2 IIA T1 Flame Prep IIB T6 FLP 693
KK0005-SVC-41 KK0005-7004-1 Regulator-1 Solenoid Valve / Junction Box ASCO/SAE FA80163 / FNJ1 S39791-4 / - KK 0005-5001 2 IIA T1 ? / IIB Class I & 11 DIV 1&2 FLP 693
KK0005-ZSC-41 KK0005-7004-1 Regulator-1 Valve Limit Switch (Closed) Bettis IR 042 AFC KK 0005-5001 2 IIA T1
KK0005-ZSO-41 KK0005-7004-1 Regulator-1 Valve Limit Switch (Open) Bettis IR 042 AFC KK 0005-5001 2 IIA T1
KK0005-PSL-44 KK0005-7004-1 Regulator-1 Low Pressure Switch Ashcroft 3424B XJL 72842 KK 0005-5001 2 IIA T1
KK0005-ISB JB3 KK0005-7004-1 Meter Run 1 Junction Box KK 0005-5001 2 IIA T1 Ex i Ex 8331290
KK0005-FT-48 KK0005-7004-1 Meter Run No.1 Flow Transmitter Rosemount 30S1PD2A22A1AM517L404 0459792 KK 0005-5001 2 IIA T1 Ex ia IIC T6 AUS Ex 1249x
KK0005-FT-48A KK0005-7004-1 Meter Run No.1 Flow Transmitter Rosemount 3051PD2A22A1AM517L404 0459793 KK 0005-5001 2 IIA T1 Ex ia IIC T6 AUS Ex 1249x
KK0005-PT-48 KK0005-7004-1 Meter Run No.1 Pressure Transmitter Rosemount 3051PG5A22A1AM517L404 0459807 KK 0005-5001 2 IIA T1 AUS Ex 1249x?
KK0005-TIT-48 KK0005-7004-1 Meter Run No.1 Temperature Indicator Transmitter Rosemount 3144PD2A1L7M5 F5 01170769 KK 0005-5001 2 IIA T1 Ex ia IIC T6 (50 deg C) 02. 3794X
KK0005-ZSO-51 KK0005-7004-1 Meter Run No.2 Valve Limit Switch (Open) Bettis TR 022 AFC KK 0005-5001 2 IIA T1 Ex d IIB T6 Ex 95
KK0005-ZSC-51 KK0005-7004-1 Meter Run No.2 Valve Limit Switch (Closed) Bettis TR 022 AFC KK 0005-5001 2 IIA T1 Ex d IIB T6 Ex 95
KK0005-SVC-51 KK0005-7004-1 Meter Run No.2 Solenoid Valve / Junction Box ASCO/SAE FA80163 / FNJ1 S39791-4 / - KK 0005-5001 2 IIA T1 CL I, II DIV I, II IIB T6 (JB) FLP 693 (JB)
KK0005 PSL 54
KK0005-PSL-54 KK0005 7004 1
KK0005-7004-1 Meter R
Run
n No
No.2
2 Lo Pressure
Low Press re S
Switch
itch Ashcroft KK 0005-5001 2 IIA T1
KK0005-IS JB 4 KK0005-7004-1 Meter Run No.2 Junction Box KK 0005-5001 2 IIA T1 Ex 8331290
KK0005-PT-58 KK0005-7004-1 Meter Run No.2 Pressure Transmitter Rosemount 3051 PTG4A2B29BK7M5T9P9040855 O2O43197 KK 0005-5001 2 IIA T1 Ex ia IIC T5 (40 deg C) AUS Ex 1249x
KK0005-FT-58A KK0005-7004-1 Meter Run No.2 Flow Transmitter Rosemount 3051PD2A22A1AM517L404 0459791 KK 0005-5001 2 IIA T1 Ex ia IIC T6 AUS Ex 1249x
KK0005-FT-58 KK0005-7004-1 Meter Run No.2 Flow Transmitter Rosemount 3051PD2A22A1AM5I7L404 0459790 KK 0005-5001 2 IIA T1 Ex ia IIC T6 AUS Ex 1249x
KK0005-TIT-58 KK0005-7004-1 Meter Run No.2 Temperature Indicator Transmitter Rosemount 3144PD2A117M5F5 01170777 KK 0005-5001 2 IIA T1 Ex ia IIC T6 (50 deg C) Aus Ex 02.3794X
KK0005-TSL-67 KK0005-7004-1 Downstream of Meter Runs / station outlet Low Temperature Switch UE E117 2BSB S061 KK 0005-5001 2 IIA T1 CL2 DIV II Gr G UL 796A / LR7814
KK0005-PSL-68 KK0005-7004-1 Downstream of Meter Runs Low Pressure Switch Ashcroft KK 0005-5001 2 IIA T1 N/A (Instrinsic Safe)
KK0005-PT-71 KK0005-7004-1 Downstream of Meter Runs Pressure Transmitter Rosemount 3051TG4A2B21BB4M5T1 RS0686957 KK 0005-5001 2 IIA T1 AUS Ex 1249x?
KK0005-TE-66 KK0005-7004-1 Downstream of Meter Runs Temperature Element/Transmitter KK 0005-5001 2 IIA T1
KK0005-PSL-72 KK0005-7004-1 Downstream of Meter Runs Low Pressure Switch Allen Bradley 836 T-T256J KK 0005-5001 2 IIA T1 IEC 337-1
KK0005-PSH-69A KK0005-7004-1 Downstream of Meter Runs High Pressure Switch Allen Bradley 836T-T256J KK 0005-5001 2 IIA T1 IEC 377-1
KK0005-PSH-69B KK0005-7004-1 Downstream of Meter Runs High Pressure Switch Allen Bradley 836T-T256J KK 0005-5001 2 IIA T1 IEC 337-1
2 of 6
Color Code Notes:
The equipment label was illegible at site and information is based on similar equipment.
The equipment label was illegible at site.
The equipment certification is not Australian and not available
Katherine Meter Station
Hazardous Area Equipment Register
Doc No.: 18756-5-70-002
Rev: 0
Date: 01-Nov-2011
3 of 6
Color Code Notes:
The equipment label was illegible at site and information is based on similar equipment.
The equipment label was illegible at site.
The equipment certification is not Australian and not available
Katherine Meter Station
Hazardous Area Equipment Register
Doc No.: 18756-5-70-002
Rev: 0
Date: 01-Nov-2011
4 of 6
Color Code Notes:
The equipment label was illegible at site and information is based on similar equipment.
The equipment label was illegible at site.
The equipment certification is not Australian and not available
Katherine Meter Station
Hazardous Area Equipment Register
Doc No.: 18756-5-70-002
Rev: 0
Date: 01-Nov-2011
5 of 6
Color Code Notes:
The equipment label was illegible at site and information is based on similar equipment.
The equipment label was illegible at site.
The equipment certification is not Australian and not available
Katherine Meter Station
Hazardous Area Equipment Register
Doc No.: 18756-5-70-002
Rev: 0
Date: 01-Nov-2011
6 of 6
"1""' .,
STANDARDS ASSOCIA TJONOF AUSTAAL;JA
Incorpofated by Royal Charter
follo'liing itel:15:
Certificate Holder
( i) (a) "Fisher" Electronic Transmitters,
Fla~.r C..lrlla Pty UMit.d
'1':rpes 2340sB al:ld 2341; 10Z Hlaull Street
(b) "Fi.sher" Electronic Transducers, Wet~er111PIR NSW 2164
Telepllan.1021 604 0333; Telex 74780
Types 5463 and 546~-4i
Manufacturer
(c) "Fisher'l Electronic Positione~.
T:lpe 35~GS; Refer Schedule 1
Australian Standard(s)
Re - ar '- -
.:. 1'0:?
~~--~,;,"~" :t.
This certificate SliFet'sedes the info!':!iation
SAA File Reference
gi'len in Gert.ifi-;ate ~Io Ex .:;4,
dated 1173-G5-2.5.
p/3: 32F11/:-1107
Effective Date
Date or Issue
" .~ ~ )1; 1 ":I
I ,,'., ) .~ -,0 7
-,
rh,S :.:c,,'..en! S:-all ".)t :Je .~p/.',:,"C~., '!..:~PI .n 1,,11
rh.S :'!..".o;a:e S ~Ol :rJ~~.~.10:e In,j '~fT\a.~s...e ::r,:::~'.. ;, ',,~
S.I.-:.I.:S -'...;'=J!.;... " .1-;:.J J J'.': "'..5( ::~ .~!-,--?: 'c:"e
...~~~
.\ J ...n r.r~~,
.~~ -.-' " ,~~,~
-~ ' ~ ~~
O.(~c:.;';.:.-.Ac~;".,si~~p~o~ais
51.3(",:jdr.::s ASSOC.dIICn Of -\:..Slral,a
Incorporated by Royal Charter
S~DULE 1-
(iv) The barriers, types 128 and 128H, must be installed inside
a safe area in accordance with the requirel::ents of SAA
Certificate Nos INS 61 and Ex 84 respectively;
;~~t'i
ST ANDARDS ASSQCIAT'ON Q~F AUSTRALIA
Incor:poratedbyRoyalChar:ter
STANDARDS ...OUSE, 80 ARTHUR, STREET. NORTH SYDNEY, N.S.W.
IIFox
b
oro
II
t
Types 2AI-I3V-AGA and 3A2-I3D CS-E/AGB-A;
(iii) Tt\e barriers, Types 128, 128H, -187 and 187H, must be
installed inside a safe area inaccorda.nce with
. the
require~ents ofSAA Certificate Nos. INS 61, Ex-84,
Ex 29 and Ex ~9. respectivelyj
."~:
(v} The .abov~ gr:par.at!lS m!l5t be installed in a'7"cordance :;;i~-
with the Orawing rlo. 2B10306 Rev. A, and t.he m~uract~er:~~;',~~"
ln5tr..1ction manl.lal t Fot'm 1?83 May 1982 ~d"Form " ,'c~,
.Y)771'..~ 4 ' , ,:. c , ;~,
--.:... 1.,7? -.',., c ,~ v ,- "'c ,
St andards A$$OC;~~~h'O'~i.I'$'tt:ah.
STANDARDS ASSOCIATION OF AU$TRAllA
'"" IncorporltedbyRoyafCharter
., , "
STANDARDS HOUSE. 80 ARTHUR STREET, NORTH SYDNEY; N.S.W.
)
(v) The above apparatus must be installed in accordance with
the Drawing rlo. 2810306 Rev. At and the manufacturer's
in.struction :::an:Jalt Form 1783 May 1982 and Form Y27714-G8
1972.
(iii) The barriers, Types 128, 128H. 187 and 187H. must be
installed inside a safe area in accordance with the
requirements ofSAA Gertificate Nos. INS 6i, Ex 8!+,
Ex 29 and Ex 29 respectively;
Group or oF mH
Barrier
)
2AD-V2I-AGA .. 1-30 4 .2
2AO-V3L-AGB 130 4 .2
2AT-SBU-AGA 130 .4 .2
2AO-VAI-AGA 130 4 .2
IIC 2AI-I2V-AGA 130 3 .7
2AI-I3V,.AGA 130 3 .7
3A2-I2D CS-E/AGA-A 100 10.5
3A2-13D CS-E/AGA-A 95 12
3A2-D31 CS-E/AGB-A 220 6
The values for Groups IIB and lIA are 3 times and 8 times the values
) for Group IIC respectively.
~
Sr'ANDARDS ASSOClA TION OFAUSTRALIA
DrawingNo{s)
This certifies that the equipment described hereunder has been examined and tested in acco!dance wJththerequirements of
the Australian standilrd(s) speciffedhereii1.and such equipment has been foundJo comply with these re(julr~ents. -
Thiscc~llicate may be withdrawn alaily tIme it in the 9plnionofSAA6ommitteeP/3;Certffication of Electric81Equipm"ent
for Hazardous Locations. therelevanl standard has been altered or revised ioa degree that the equipment1si1Qlol}ger
considered suiiable forinstallationinthe hazardous localionstated. or if the certificate holder has breached any of the terms
or conditIons underwt\ich this cert!liCate was issued.
Hazardous Location
Class r Zone a
Ex 1a IIC !4
This supplementary certificate ~elates to the
following item~:
-
(aj The equipment previously certified under
SAA Certificate No~ Ex 64 and Ex 64-1,
which may be used in conjunction with
alternative barrier devices, as detailed
in Schedule 1.
Fistler Controls
Marshalltown
IOWA USA.
Dra~1ng N9 ( s ) .
Test Report No(s)
!2810306 RevS; ,281 0307 R~y B and
SCC TR NO: 59957
'ZB10308'Rev B
)
Australian Standard(s)
AS 1829-1981
J-:~;;
Date of issue
1984-11-12
-. ;J.~.
(111 Any SAA certified barrier, category (Ex ia), Group IIC, incorporating
) active components which affec;t the output characteristics, having
the rollowing nominal parame/ters ;
(b) TraQ~du<;ers rypes 54§S and 546S-G-4 an(j Position~r !ype 3590S.
~
(i) Barrier. Type S;AA Certifl~ate No
v
MTL 122 E~ 410
MTL 722 Ex562
MTL T28 Ex 5f12 ",
,,;
CCitegory (Ex ia) .U1'OUp IIC, havin.g the fo:llOwing QOmlnal p~raine:ter$::
,~,,'
This document shelf not be reproducEid except in full.
":\i;
This certificeteis not transfer:ab~.andremainstheproperty ot the
Standards Association 01 AuStralIa and (TIust be returned to the
Association 'rrtheeVent at It being r8iiok'ed~ "
';':;
;;l'
"
STANDARDS ASSOCLATlQN OF AUSTRALLA
or
(iii Any SAA certified barrier, category (Ex ia}, Group IIC,
incorporating active components which affect the output
characteristics, having the following nominal parameters:
)
Output voltage not greater than 32V
Output curr~nt not greater than 100 mA
~
=>3 o
z~ N
~ C
e
£,.
.. .
~ :I:
.~,
~ Z 'i:~
-..a:...
1 -18;i
..~2
%
..
~
a:
~UJ
~~
<l- I..
..
a) 0
..
..
~
..
~
~
.tI. j ~.
0- I
0 O
UJI:l:
~ 0: 0:: ~I j ::
i:i:UJ
O O 0
i=cr ID aI G)
a: a: x x i ~
...
0 ~ 0 ~ ~!r~~~ v.
~~ LL I!. u. ~~i~~~~
..z«z~z~ --a "' "'
~
~ z
0
MI...8:I:o...
u
o -c ~ Q.u~o ... 0\17
a:~-.. z
QIJ"I -~~co~-
a:Z ~ .~~~~~ 8~
~o -Q
~ 1- UJ
~ > 1-
Zu oa:S
00 a:UJ""
Z-' a.OC:X:
a.a:U
1 a~~
I @~,
+ >z I
OW..,
a:~1O
11.::> ~
V) Q.a:X
<~W lJJ
::>V) (/1 1-
Oz Z
a:-
00 < 1:
<'4 V)
.J
NU
<0 ..., ";'
I ~ -.~
:I:~ In O V) c
O UJ
ootx:VJ .ocrV) ~ ~ ~
...,000 ~o.o
In ..., 111 ~
In 111 ~ ~- ~
~~~ 5z
~~o n~
~ < »:1:
/T1 ~»
O -N
0»
Z~
V)o
°
' c:...;:~~~ .8 c
~
!iO>~»
...m»» ~ !!I m
~
~~ o>n~~~6 UI
~O%nmm Z UI
~r>oID... > O "" " a>n
k
-~ ~ :t :t
. mml:~c- r ...
~ -i -i O ;g o >m
, r-
"'
>ZpZ»Z
~G)~m»ii
tt I
m -1 ~
r-: ~ ~ , , x x x :t):t)
-I c~~»~% I c. °z> I r 00 (1) ~-I
» c
"'~ r , ~
~
UI
m
~
m t ~ ~ 0
~ !
r ~"tJ
r
O
.n
o ~I ~
0
;%)
0 ~
ii'i'Ti
~ii'i
o
.!
z . O
!!
...It
% m
n
.» ~
{./\
~ - ~
0 e I m
O
;;
.. ::c
~ c
{./\ N 1..1 N N N N
~ -1 "I! ~ QI ~ ))0 ))0 })0 ~
~ ~ ~ ~ ~ ~ N O ~ 0 ~
~ (J) ,~ 1\1 I .. , ,
,. ~ 0 , 0 < U! < <
,. m
"' 0 -1.t'
O ~ D I 1..1 ))0 (D (..I N
,. C ...
.. (") ~ I . -<~
" -. ~ ]00
o i» N n ))0 > ~m
z ~ ~ I In C> C") O
m
C> ;X)
z ! r I -
.. >
m r ..m
I Ii ""'"-
,.
(")
-i i ~
rT1 aJ
O .
»
f .»
(")
Er-8 ,; ~ ~- (")
0
..;Xz ~ z
0 ! VI
.-4 ~
~ :x :t ~
j~~ (!
* ~ I ~ (/) ...
-t N N r-) ~Z
i~ ~
<0' i 1..1 <» N
0 zC
O () , O c. 0 0
a , 0
O O O 8 ~'"'l
-1 , I
r-
:r: I \1, '- - - - - - --
2
m --:-
~ rn
0 (J) ~~~ m m /T1 rI1 /TI m )(VI
» '\)",111 )( x X )( )( )(
-" - (""»>
" ~ N
~
QIO~ ""
~ -..) " -..I rn»
~ .
-nrz w~' ID
-0-1 " -4
~
U'l°:u
I-U-
~
(11 Z ::t I I
D ~ > VI
:Uv)U'l I -- ("')
~
..
~
~nn
z
c '\) '\! , , I.N N t-.} ..\ ~ Zr
om
"T1
-<Ipo I' I ~
~
-U(11r -t
(11:::{r c
~I po~ ~
& W-I .~
(T1 I-
a. 'U' oV) ~
I
w ~ po .c.ri I i
VI
-I
a .i 1"1
"'..1 °<:Il z
~ ~I
U'l5m {./\ ! m 1 m m m m m m ~.
-t
-1 ;u ~
~ ~ ~
t... ;I X
Lo. ~ ~.
X x x x x )( n o~
T t.. (.. ~. '-. '-. '-. w.
~ c.. L
~ ' p ~ p
~ o I
:j
SI
A n ~ ~ p t;" 1"1
~ I
C)
o I.. 0
z
{./\ ~
~ I
m
-I
:I:
m
r
O
O
~
~ ~
V}
~
~
m
m
o
o
z
z
m
n
-.
IT1
O
:..
n
n
O
~
z
C>
'-4
O
-.
;I:
IT1
~
:u
~
m
:u
~
z
c
-n
~
c
':t)
IT1
:u
vi
z
(/)
~
:u
c
n
~
6
z
V}
~
Certificate of Conformity: IECEx CSA 05.0005 Page 1 of 4
IECEx Certificate
of Conformity
INTERNATIONAL ELECTROTECHNICAL COMMISSION
IEC Certification Scheme for Explosive Atmospheres
for rules and details of the IECEx Scheme visit www.iecex.com
Type of Protection: Ex i; Ex n
Signature:
(for printed version)
Date:
IECEx Certificate
of Conformity
Certificate No.: IECEx CSA 05.0005
Page 2 of 4
Manufacturing location(s):
Yokogawa Electric
Corporation
155 Takamuro-cho, Kofu-shi
Yamanashi-ken, 400-8558
Japan
This certificate is issued as verification that a sample(s), representative of production, was assessed and tested and
found to comply with the IEC Standard list below and that the manufacturer's quality system, relating to the Ex products
covered by this certificate, was assessed and found to comply with the IECEx Quality system requirements. This
certificate is granted subject to the conditions as set out in IECEx Scheme Rules, IECEx 02 and Operational Documents
as amended.
STANDARDS:
The electrical apparatus and any acceptable variations to it specified in the schedule of this certificate and the identified
documents, was found to comply with the following standards:
IEC 60079-0 : 2000 Electrical apparatus for explosive gas atmospheres - Part 0: General requirements
Edition: 3.1
IEC 60079-11 : 1999 Electrical apparatus for explosive gas atmospheres - Part 11: Intrinsic safety 'i'
Edition: 4
IEC 60079-15 : 2001 Electrical apparatus for explosive gas atmospheres - Part 15: Type of protection 'n'
Edition: 2
http://iecex.iec.ch/iecex/iecexweb.nsf/CoCHistory/IECEx%20CSA%2005.00056 22/09/2011
Certificate of Conformity: IECEx CSA 05.0005 Page 2 of 4
This Certificate does not indicate compliance with electrical safety and performance requirements other than those
expressly included in the Standards listed above.
http://iecex.iec.ch/iecex/iecexweb.nsf/CoCHistory/IECEx%20CSA%2005.00056 22/09/2011
Certificate of Conformity: IECEx CSA 05.0005 Page 3 of 4
IECEx Certificate
of Conformity
Certificate No.: IECEx CSA 05.0005
Page 3 of 4
Schedule
EQUIPMENT:
Equipment and systems covered by this certificate are as follows:
The EJX series are two wire electronic transmitters which convert differential pressure, gauge pressure or absolute
pressure into a 4 to 20mA dc output signal with a possibility for digital communication.
The EJX series transmitter consists of a field wiring compartment, an electronic amplifier in an aluminum alloy housing
and pressure sensor assembly.
CONDITIONS OF CERTIFICATION: NO
IECEx Certificate
of Conformity
Certificate No.: IECEx CSA 05.0005
Page 4 of 4
http://iecex.iec.ch/iecex/iecexweb.nsf/CoCHistory/IECEx%20CSA%2005.00056 22/09/2011
Certificate of Conformity: IECEx CSA 05.0005 Page 4 of 4
http://iecex.iec.ch/iecex/iecexweb.nsf/CoCHistory/IECEx%20CSA%2005.00056 22/09/2011
-'t)
!..
~; '1',\ 1',11) A It D S 1\ s s tJ t: I A 1.1CJr~ U l~ J\ U ~ II< A L I/~
;heat of )ilolJl 2 INCOBPI1RAT"1>
DY ROYAl. c;.'AATUtl
."'rl\ N I)A I' OS ~OUSE .rJO AI~THUI{ STR:~E.r. NORTH SVnNEY NRW
No. N 6?3
Jh,~ G'rti(;e, Ihot the flomoproof enc!o$uro de$cribo(1 t1areunder hol been ExAMINEO G'1d TEsreo
or,d h.,s be~n found to comply with tfle roquiremonts f,~r a fl~meproof enctolure in ~C:l;ord.snce wIth
AS C98- ~IQ",oproof Enclosufe. "f FIAt;tr~1 Equipmenl. Including Amendm8nt No.15) ..
ThIs Cerlir;"ol.. ot"'"I;,,~ vI.ly 'v II,~ nal"at'.'.!.uf rb6Iuf.. vr III. ~~I,;r-,,"b,\1 JoJ.!/:LaJ ',UIC;" dIlIJ
do$$ not purport. nor is it intended to certify complionc:e wi~ the rCIi.v~nt vl.ctr;c:~1 Jnrefy req\Jir.m~nt. of
the SAA Wirillg Rules, AS CCI Ports I mnd , 1,
A.PPUCANT:
Saf. Applfance and EquIpment Go. P{Y. L~d..
Z6-28 Kert Road,
M,\5COT N. $.';; .2060
MA~aUPACTUnrJ=-:
Hetalcraft Engil1e,rfng Co. Pty.Ltd..
26M1IJ Kert Road,
I1ASCOT. N.S.W, 2060
t4~ ">"H
Choirma"
.",-(~:~-~:M~ of Gommitto. EL/~9
"
.~MAQI(S;
C,\$-T fLl!!t~!N l~t'l!1b~~~
spindle.
Cat, Ilo.F~ILI1, Pilot Lamp $tatlarl -Qne bare and spigot Joints,
Four i in, Or 1 in, conduit ontrie4
16 T.p.I. Iwo indica1or lamp
Inspectllln ,'indoYIs.
Cat, No.FNP11., Push Blltton Station -One bore and spigot joint,
Four i In. or I In. conduit en'trles
16 f,P,I. T.o operatIng rods,
;Y, 8 ~
Cheirmsn
",.".,r:zf:"~~c.~..o'..C)'mmitt~. m/29
",
t;L/~9
o.,t. }.6.74
~ Q,!flt:e
236 SIo:J$$I!;.
S,t!"oot
S)'1:1ne}'NSW 200() Austt8lia
i'o~tm -Addtt'$~
GPO Box 5420
3}-dt1C)'NSW m1 Au~tr"li"
PhQn~ (61 *2) B2:06 6060
"
f ax" ( 1-"") ,,"',~
,", ""L
"""' I
I{) F~ruarv 2()O3
~
f~il D~~~ai~9'DbaLwm
tr~lnll'l!14':iaI-global.
com
~ ,~I~~I,c;om
O R t'
e : ." US t7 "S4?V
A
United Electrie Control"", (AuSl) Pty Ltd , ur .J::x' ,.."'
~
w
I
~
,\v...~.;,;.'1t
" 0-.l"'-vI:W
n...~,.f r-j-..,.,t",~ t .~I B ~!(~'
.~,
~ "" .-i. cu.~.
p1..iltnC,'i:.l-
} '}"~ .C61 A
2 8 .'.'J'i:.1}..'
AShburton Vicrori~ 3147
l1 r~ 1 ') 0., .)6 ":03 .'
I.ax- Vl~~ I>~( u .t.
En1():il :nQeLbakt.~sai-'.)obal.com
., !iJ
DCM Sir~
1 am ple.ascdto inft..nn y~)l1that your rt'quest tor ZLt-urlhe:re~teT,si()ll()f the expiry date for the
a~)\i.e Certificate (tfCot\forJnitl' is gr:aJ)tedOr} the basis tllat 81'\1'1.'
ARS has contlzmed that an
application fur re\;.alidation of the appararus has been submittt:Ll JUld that th'Ccontract js beiilg
f]nalisC(,1.
1 confirm that thc cxpiry <ls~ ftlr thc AUS E.~ C(.'rf;ifJcatt ot" C~)fit{)mtjly No. 542X is nov.' 31 Jul}r
:lOO3.
Yours sJficerely,
--.A.""" #~ /
~Z~~~
.~~.
Noel Bakcr
Project Coordinator
Elettr(ltvchnQlo v
A d"i'oisOODi SAJ Global limited Otf!K:eStltroughoutAJ.Jsu~lia and ii) New zealand, North .M"I@rki\, Indon(~ ~l10::1lndi"
ABiN &1 OSQ &11 642
Assurance Services
Head Office
286 Sussex Street
Sydney NSW 2000 Australia
Postal Address
GPO Box 5420
Sydney NSW 2001 Australia
Phone (61-2) 82066060
Fax (61-2) 82066061
30 October 2002
Email assurance@sai-global.com
training@sai-global.com
Web www.sai-global.com
United Electric Controls (Aust) Pty Ltd Our Ref: AUS Ex 542)\
615 Warrigal Road Contact: N.Bake1
Ashburton Victoria 3147 Phone: 61-2 8206 6614
Fax. 61-2 8206 6032
Email :noel.baker@sai -globa1.corn
Attention: Mr. Peter Edgar
Dear Sir,
I am pleased to inform you that your request for an extension of the expiry date for the above
Certificate of Conformity is granted on the basis that SIMT ARS confirmed that an application for
revalidation of the apparatus has been submitted.
I confinn that the expiry date for the AUS Ex Certificate of Confonnity No. 542X is now 31
January 2003.
Yours sincerely,
-i, (i":
-., ---
iS
~/~~~ ~~~,
Noel Baker
Project Coordinator
~!!ctrotechnolo2Y
A division of SAI Global Limited Offices throughout Australia and in New Zealand, North America, Indonesia and India
ABN 67050611 642
A.lrhizti~tet'ed~(-; Stilllijards ."U$tT[jlia (i!,Jjilit~i'A:ssuriJJnce ,S,~rviccs
T'/pe of Pro!ecbon and MaskJng Code: Ex d llC 1'6 LPMI (~Ia!i~ I Zonc 1
AUS Ex 542X
1551j\,,\,1~,.;
.j
M f"')i/.' 1 "f. .7...
Surl:lar:ls.\"l';\rltli?i (,~U"J,rt.~.""1jf';;).:l!~rli~5 F'tylimioo.:; A:(:,:4 050(111M:
AdminihtL"'Tcdb}';Standatds J'\LI,~tr;;Jli{~
Quality ,.\~5Uran,(;. ScnrjC(~5
Equipment
The 120 Serle!i Flameproof Temperature and Pressure Sw[t(:hos are housed In dle-c8st enclosures
manufactured from American Die,Casting Irtstltute Aluminium Ailov fl360 8"d incorporete a threaded cover
wl1h a 1hreaded conduit entry on the b8Se, The 9ncLQisures are fitt9d w1th It limit $wtt~h which r$ operat:ed
hy means of balLQiwS by external pres$ure for pre$sure switches and a capillary expansion tube for the
1emperature swltC:heg. This sup pj em e.ntary certificate includes mo<Jifi4)d eovQr ltnd sealing arrM1gement:3, tor
modeLs 4!5 Li$tod in Appcn<lix A. The part;iGIJIBrmQdels as listed in Table 1 be1ow have a different internal
switchJsensor .
Drawings:
D 7
$l;lJldilrll\. ...':lllrillia QUilli~ .""",ur1lnC\: S~r.ic,~ Ic'I;lJig,l,ri,j .\,f:' G\?~'~j ! ~, 1'"r~'l,l(
j\dnlinL~ct.cdbr"Stalldards .~ustralia (~uality .~ssurance ,I)erv'ices
: Ex 542X
.,tijdcndumtn l-:i::ftifiart~ Xo ,,."""'..".,.,',
Js.aue: 4
C
fl '~I! ". '
~ , .xr~5 ID C ,.~ ~-- .'.'
lliKI1 lA n~.
C'-6llZl)-I fc ~.,. ..'1"' r 11;{1~11)~
J'.Re~n/2
.11.
"..
[..d:lifi 1 Qf ~
Conditions of Certification:
Only !lpproved fl~meproof thre!lded !ld!lptora are to be \J~ed with the NPT threaded entry
lsS1~nib:t':
STAN:DARDS AUSTRAliA
rJ 5 7
'~
StaR~ A1IstraliuQualil} McUtU!\i:1:.~r'o'i~!i"t}. 2.imilcd ,...';;.N"i:\:I) (,II (,*;:
J\dminist~Trob}c;Stand[1I'ds AustriUi(1 Qua;lity 1\$5Ura",C Servi ,e"5
; Ex 542X
AJd;en{jufi; trt {~"jfiG4'ltJi: Nct...
I$$U~: 4
Addjtional1nformation
Appendix A
IW uiaJ .."",
.~,. J.~
""'.J...uI , 3 ,...-.-", ~' I , ~" .~2".2,t
::", "'- , -~ ,,~ -u, ' 3n
*'.1 *:0"'t !i] , * ] , * ". ..fi fi .."I.'.
i"'.,i'..~,
. fi ' ~
"...",...,.,.""',,"","ll...,,'"..,;',..,-..'.;'
". 1 '~
566, 5~'J, tiU, "16, "HI), 7{11, 'J{l2" 'J{l3..7U4. 7US' 7t16"
.5"', ..~I .~~ .~, ..;..., :."Ir.
"a, ..; ,,~ .',..
"., ..,
~-1... ~. S ...~:)A,
., ""A ~;1~.
147, IS7, SJ47~, ~L57B, ~7, ~. 37, J8, ~V),4~~, 4~,
4S1,5S9
LaIItjJtr rtmtattf cu,(r 5$J. 5$4. 555. 011. 014, 7tll, 7{J2, 7U3, 7{14, 7U5. H7.
SI,J1D. SHtlD, SI561~. SI~~B
u i '".'.. J
" , , n,
r.. ".~".. .".
" ., ;"", .n, ""'.'"
4 ".'
"' ."
L"f.
."'-. ,.
"121 T1"(j SPOT; TII!JI e\LfnIul rerereDCCdiub, ;tJlIl 1~6, 134.1,(4, 1%, 156, IfJ4, .,- .'..4
",... ". ..."
.r~ c...
'
l c.."
1..-'
A. fI ...'I..'
,-"',-,J.-,
'.J l.
,
fI
,.-""'
~r,
tafUptr r~Sc~tau. t(l'f~r; dual ~ifth ocpararinll M !II' Sr!6... Stl4... S144D,S14fiD. 553. 5S;t.555.'11. 'l~. 7(jl. 7(j~. 7(j3. 7t14.'7{15.147:
L'JJOO% ul r.&rlg( ~15f,K,Sl'.H SI4'n. t51. SI~m, 451i.451. 55~
1~:sIl!t'd &.1':
StA N
" DA RDS
' AUS~ T 1\1'\ LIA n A
a
6 7
Pili!"
Stwd:lrds A!;;Sjro'ifiJ. ~J1Jiitl ASSU:-dlt<£S\.r.i<l~ rl'r urflil;lxi A,l:~,;..; (}5(1!i) ) ~
,-\dmirrl$lereclii»'; Stanl;';ctrd!; A lic~lraliaQualitJ.Assurtln(:e ,Services
"""J
J=..tl1 b \.. v .
~A N UM!
nA RDS AJ
USTRA' U A'
\:J IM: ." M " .
fj
7 1
'ilpf: oi
~1"It.i"f\i, .\II$rr;l!fd UI:..IJi'l:'f A~1;IJr;jnc: Sfr'.lcn PtyLimil-:d A.C.N. OSfloJ 1 &11
Administeredby; Standards Australia Quality Assurance Se"ices
Issued~
STANDARDS AUSTRAUA 5
"- A t aI. Q aJ 't "- ,,-.:- 0... U mi t -.J '
rJ Page I of
s--..n
d aru. usr la U Iy'.'.surm,c"", t$.., ="- C .. N 050 611642
This certificate is granted subject to the conditions as set ()ut in Standards Australia Miscellaneous Publication MP 69 and the
Procedures(Doc Q7134) of the scheme.
The electrical equipment and any acceptablevariation to it specifiedin the scheduleto this certificate and the identified documentS,
wasfound to comply with the follcwingstandards:
This certificate does not ensure compJiancewith eJectrical safety and performance requirements other than those included
in the standard.rJistedabove.
The equipment listed has successfully met the examination and test requiremetlts as recorded in
9 July 1999
Date of is5ue
This certificate is not transferable and remains the property of Standards Australia Quality Assurance ServJ'cesand must be returned in the event of
its being revoked or not renewed.
STAN[lA.RDS AUSTRALIA
fj Page 2 of ~...
Standards Australia Quality A\.~urance ServicesPty Umitw A.CN. OSO611 642
Administered
by: Standards Australia Quality Assurance Services
Equipment:
The 120 Series Flameproof Temperature and Pressure Switches are housed in die-cast ajuminium
enclosures and Incorporate a threaded cover with a threaded conduit entIY in the base. The enclosures
are fitted with a limit switch which is operated by means of beliows by external pressure for pressure
switches and a capillalY expansion tube for the temperature switches. The range Is listed In Tables 2
and 3.
This supplementary certificate covers the additional models to the pressure switch range as listed In
Table 1.
Tabte 1: Addition of Modets
; "
ENCLOSURE TYPE MD'S ,0, EL;
DESCRJPTION
NON-VENTED VeNTED
J120 .On9 SPOT; internal adjustment S126B,S134B, 50, 51.52.53, 54.55, S50B, S51B. S52B, S53B. S54B. S55B.171.172.173,
with Internal scale S137B,S144B, 174.471.472,473, 474, 183,184,185,186.188,189,483,484,485.486.488,
S152B,S156B, 489,190.191.192,193.194,490,491, 492, 493, 494,270, 274,356,358.361,
J120K -On9 SPOT; Internal set point S164B, 126 134, 376, 520.521,522.523.524,525.530.531,532,533,534,535. 560,561.562,
adjustment, no dial 137, 144,152, 563.564,565,566,567.612.616,680,701,702,703.704,705, 706,450,451,
156, 164. 452.453, 454,540,541, 542, 543.544, 54S,546.547, 548, 550,551, S52, 553,
554. 555, 147. 157. S147B. S157B. 367. 36. 37, 38, 39,455.456, 457. 559
H1Z1 -One SPOT; top external reference 126,134, 137, 210, 274.358, 361, 376.450, 452.453, 454.550, 552, 553,554, 555, 612, 614,
dIal and tamper resistant cover 144, 146, 156, 701, 702, 703, 704, 705, 147, 51478,157, 51578, 456, 457, 559
164, S126B,
H1Z1K -One SPOT; external reference S134B,S137B,
dial and tamper resistant cov.r S144B, S146B,
S156B,S164B
H122 -Two SPDT; top external reference 126, 134, 144, 270, 274, 358, 361, 376, 450, 452,453.454, 550, 552, 553, 554, 555, 612, 614,
dials and tamper re$istant cover; dual 146, 156,164. 701, 702, 703, 704, 705,147, 51478,157, 51578, 456, 457, 559
switch separation of up to 100% of range 81268.81348.
81448, 81468,
H122K -Two SPDT; extemat reference 8156B,S164B
dials and tamper resistant cover
STANDARDS AUSTRAUA
~ 5
Pagt 3 of
Standards Australia QualityAMUranct' 5crvkcs Pty Limited A.c.N, 050 611 642
Administered
by: Standards Australia Quality Assurance Services
Issue; 5
Date of Issue; 9 July 1999
8121 -One SPOT: Imme~lon stem; external calibrated dial and 119.120.121
tamper resistant cover
E121 -One SPOT; bulb and capIllary; external calibrated dial and 2BSA. 2BSB. 385, 4BS, SBS, 885. M9BB
tamper rasistant cover
E122 -Two SPOT; bulb and capIllary; external calibrated dial and
tamper raslstant cover
F120 -One SPOT; bulb and capillary; no reference scale; Internal 1BS. 2BS. 3BS. 4BS. SBS. 6BS. 7BS. BBS. M9B
set point adjustment
Issued by:
STANDARDS AUSTRAUA
~ '.g~ 4 ut .6
Standards Australia Quality A"uran(t St"rvi,ts Pty Limittd A.CN. 050 611 642
Administeredby-. Standards Australia Quality Assurance Services
issue; 5
Drawings:
The following drawings are associated with the additional models to the range:
Conditions of Certification:
Separately certified flameproof threaded adaptors shall be used with the NPT threaded entry.
Issuedby;
STANDARDS AUSTRAliA
~ 'age 5 of 5
Standards Au$tralia Quality A$6Uran.:e Servi.:es Pty Limited A.C.N. 050 611 642
FW0001 (826x1165x16M jpeg)
FW0002 (826x1165x16M jpeg)
FW0003 (826x1165x16M jpeg)
r~
." .h~. STANDARDS ASSO~IATION IOF AUSTRALIA
Incorporated by Royal Crarter
STANDARDS HOUSE, 80 ARTHUR STREET.I NORTH SYDNEY, N.S.W
This certifies that the equipment described hereunder has been examined and tested in accordance with the requirements
of the Australian standard(s) specified herein, and such equipment has geen round to comply with these requirements.
This certificate may be withdrawn at any time if in the opinion of SAA Committee P/3, Certification of Electrical Equipment
for Hazardous Locations, the relevant standard has been altered or revised to a degree that the equipment is no longer
considered suitable for installation in the hazardous location stated, or if th,e certificate holder has breached any of the terms
or conditions under which this certiricate was issued.
Certificate Holder
I
United Electric Controls
I (Au.st) Pty Ltd
IManufacturer
Drawing No(s)
Unlted~Electric Controls Co
Refer Schedule 2 83 School Street
Watertown
MASSACHUSETTS USA
test'Report No(s)
ILOndonderry Centre
Remarks
~ffective Date
1984-10-29
d>ateof Issue
1!984- i 0-30
SCHEDULE ,
(a)
(b)
Each control may be provided with one ormor of the following options:
2.
3.
I
E6296-185 Iss~e c
E6296-186 Issltle c
E6296-187 IsslJJe B
E12259 Issue A
E12260 Isstie
I
A
E12261 Iss~e A
E12262 Issl.!e B
E12263 Issye B
E12264 Issl\e B
E12265 Issue A
E12266 Issule A
E12267 Issu1ie A
E12198 Issu~ A
E12200 Issue A
D6201-167 Issue B
D6201-20J Issub A
D6201-204 Issu~ A
I
UEA-1200G Orig:J.nal
UEA-1200L Revi$ion 2
C<lfn1JJnuarlOfl
0( ~tdtlcate No: F.x 542-1
83 Murphy Streeti
IC 31'! 1 c ;:I c
iICu~ ","\VlND
, ,
V , c'
for the 120 series ran e of Preasu~~a11d 're, ,e~ature contrDla la hereby
extended to inelOOe 1ttOOi£1c.ationa as detailed in the followin~ scheCIuJ.e.
-
o";.,~.;1,,l,Q
y...I~...U.. v
,..."..f
tT""~,,.J.
t-
,0:
i """'
vu
...
v
.f w"..dif
n...
i ...
,",a
ti o .,
,no
.~.
3. R~moV'al 0£ all unuaed BE!COnd adjuBtment ~ba,ft hol.e from type Hl,21 cO'ntr'ol
enclosu"t'es.
~!~~!~~
Page 1 of 2 ~
Kx: 54:2-1
Conlinuation 01 Certlflcare No:
Certlf1e.&tlofi Conditions
Pa3e. of ~
Certificate of Compliance
This is to certify that Standards Australia C~rtificate NO5 Ex 542 and Ex 542-1
issued to;
~~~~PV~~
DescriDtion of modi!ica.tions:
PreSBUre controls
(fiOnavented) J120, .JllOK, H121. a122 i5eries: 126. 137, 144. 134.
152. 1561 164. S126+ S1371 S14f4, S134. S152. S156.
S;164. SU~5. S1375. 514"~. S134B. SI~2B. S1555+ 8164B.
45() 4S 1 .1,~!) '". A ~~
"+..;j.
qcc
.. 4
Pressure controls
(vented) .J120, J120K, H121, "122. H121K, H122K series: 270. 274.
358. 361~ 316. 550~ S:Sl~ 552; 553. 554. 555+ 612~ 614.
455t 456, 45if 5~9, 7()l. 7()2, 703, 7G4, 705t 19a, 191.
192, 193. 194, 147, S147, S147B, 157, S157, S157i. 36,
37. 38. 39. 40. 183, 184, 185, 186. 188. 189, 612. 616~
1!.0 1!., I!.i'J "' J "'J. "'"'
'J,..c,o, ,..'...~';;J
Page 10£ 2
Thi! ~~rti~~~ i. ""t jr1J"J.",,~;. ti~ ..-01 lIS tile pr~ cf SlaBdo7Jrdj;
"'-'s1rnli(l "lId "'1'.~ ;.,~ r-'1.i~ j" II,. w-.J 0! fU bel lIe rD'~ c.r nl)! r.Be~
---~~ I ~~-~.-~~
Q UAUT
. y ASS Ucf]; A h.. Ir
i.tV'\I~ E
SERVICES r; I
Stondard~ A1J5tro lia !
~dQrd$ A\Jllr- O\Iclily Assuronc~ Soer.,ice~Ply l!M~ A.CN, 050 611 olt2
Ex 542-%
Drawin21i-1
T~~-f\e1)ort No.
.
NET 92}024 to AS 2:180.1-1989 and AS 2380.1-1991
Page 2 of 2
1/',
i
rill. o;crtif,:o!e 11 not 1rQn:!f.!Q~~~n!f!lepr'O~ of Sro...dord! IJ~.-oII" (',..;I ""..~ b..1,.!1J'"~" ir, IJ.~ w."", ,:1 i", b..i"f{J '*..t "' I.cl ,*..*..,..;j
QUAurv ASSLRArt-K:E
~dard~
SERVICESfj
Stond(jrds Ausfrolio
No. N 6?3
Jh,~ G'rti(;e, Ihot the flomoproof enc!o$uro de$cribo(1 t1areunder hol been ExAMINEO G'1d TEsreo
or,d h.,s be~n found to comply with tfle roquiremonts f,~r a fl~meproof enctolure in ~C:l;ord.snce wIth
AS C98- ~IQ",oproof Enclosufe. "f FIAt;tr~1 Equipmenl. Including Amendm8nt No.15) ..
ThIs Cerlir;"ol.. ot"'"I;,,~ vI.ly 'v II,~ nal"at'.'.!.uf rb6Iuf.. vr III. ~~I,;r-,,"b,\1 JoJ.!/:LaJ ',UIC;" dIlIJ
do$$ not purport. nor is it intended to certify complionc:e wi~ the rCIi.v~nt vl.ctr;c:~1 Jnrefy req\Jir.m~nt. of
the SAA Wirillg Rules, AS CCI Ports I mnd , 1,
A.PPUCANT:
Saf. Applfance and EquIpment Go. P{Y. L~d..
Z6-28 Kert Road,
M,\5COT N. $.';; .2060
MA~aUPACTUnrJ=-:
Hetalcraft Engil1e,rfng Co. Pty.Ltd..
26M1IJ Kert Road,
I1ASCOT. N.S.W, 2060
t4~ ">"H
Choirma"
.",-(~:~-~:M~ of Gommitto. EL/~9
"
.~MAQI(S;
C,\$-T fLl!!t~!N l~t'l!1b~~~
spindle.
Cat, Ilo.F~ILI1, Pilot Lamp $tatlarl -Qne bare and spigot Joints,
Four i in, Or 1 in, conduit ontrie4
16 T.p.I. Iwo indica1or lamp
Inspectllln ,'indoYIs.
Cat, No.FNP11., Push Blltton Station -One bore and spigot joint,
Four i In. or I In. conduit en'trles
16 f,P,I. T.o operatIng rods,
;Y, 8 ~
Cheirmsn
",.".,r:zf:"~~c.~..o'..C)'mmitt~. m/29
",
t;L/~9
o.,t. }.6.74
APA GROUP – AMADEUS BASIN TO DARWIN PIPELINE
KATHERINE METER STATION HAZARDOUS AREA DOSSIER
7 Calculations
Hazardous Area:
H. A. Report: Area Class:
H. A. Drawing No.: Gas Group:
Temperature Class:
Repeater Power Supply / Barrier Sensor
Cable Screens shall be
connected to
intrinsically safe earth
at the Intrinsically Cable 1
I.S. Earth
Safe Barrier end.
D1
Tag: Max Voltage Um: V
Type of instrument: O/C Voltage Uo: V
Manufacturer: S/C Current Io: mA
Model Number: Power Po: mW
Serial No: Allowable Cap. Co: uF
Certificate Number: Allowable Ind. Lo: mH
Certifying Authority: L/Ro: uH/Ohm
Protection Type:
Cables:
Cable 1: Cable 2: Total Cable:
Tag: Tag:
Capacitance: uF/m Capacitance: uF/m Capacitance: uF
Inductance: mH/m Inductance: mH/m Inductance: mH
L/RC: mH/Ohm L/RC: mH/Ohm Max L/Rc mH/Ohm
Length(D1): m Length(D2): m
Checks: PASS/FAIL/NA
1 Uo <= Ui <=
2 Io <= Ii <=
3 Po <= Pi <=
Notes:
1- Calculation is based on AS.NZS 2381.1:2005, AS2381.7-1989 & AS/NZS 60079.25:2004 for a single power supply loop in an intrinsically safe system.
2‐ The I.S. Barrier is an integral part of the discrete input wireless transmitter.
3‐ The above calculation, check and conclusion are also applicable to wireless transmitter LSL and LSLL level switch I.S.
circuits used for pump 1161C/D, 1162C/D, 1163C/D and 1164C/D sealoil pots.
4‐ The level switch in this I.S. Circuit is classified as simple device.
APA GROUP – AMADEUS BASIN TO DARWIN PIPELINE
KATHERINE METER STATION HAZARDOUS AREA DOSSIER
9 Maintenance Register
Site:
HAD 1.9
1 of 3 Rev 0
MAINTENANCE
REGISTER
Site:
HAD 1.9
2 of 3 Rev 0
MAINTENANCE
REGISTER
Site:
HAD 1.9
3 of 3 Rev 0
APA GROUP – AMADEUS BASIN TO DARWIN PIPELINE
KATHERINE METER STATION HAZARDOUS AREA DOSSIER
10 Inspection Register
Close visual inspection to confirm equipment installations was performed by Neville Green,
an electrical engineer from Sitzler during a site visit on 5th September 2011.
This Section contains the inspection sheets. The Section also contains sample inspection
sheet(s) for future inspection.
Documentation in relation to this section is to be maintained by APA Group.
Hazardous Area Check Sheet
Flameproof Ex d
TAG/IDENTIFICATION DESCRIPTION
Area Classification ‐ Zone 0 1 2 Non Hazardous ‐ Group I IIA IIB IIC ‐ Temp T1 T2 T3 T4 T5 T6
Record Name Plate Details Record other nameplate information that may
Manufacturer KW FLC be relevant
Serial No. Volts RPM
Model
Certificate No. T IP
Certifying authority
Inspection Type Performed (I=Initial, P=Periodic, S=Sample) I P S
Inspection Grade Performed (D=Detailed, C=Close, V=Visual) D C V Detailed requires de‐energization
Equipment Y=OK, N=Not Acceptable, N/A=Not Applicable, N/C=Not Checked Inspect
Remarks
Grade
Equipment is Australian or IEC Certified Y N N/A N/C DCV
EX markings are suitable for the area Y N N/A N/C DCV
Equipment is clearly marked and has appropriate tag/identification details Y N N/A N/C DCV
Enclosure is not damaged and maintains its flameproof characteristics Y N N/A N/C DCV
Locking sealing, fastening devices are of type certified by manufacturer Y N N/A N/C DCV
Locking sealing, fastening devices operate correctly and are tight Y N N/A N/C DC
Bolts, bungs, plugs/blank plates installed and tight Y N N/A N/C DCV
Sealing gaskets and components in acceptable condition Y N N/A N/C DCV
Flange faces are clean and undamaged Y N N/A N/C D
Flange gap dimensions are less than________________ mm Y N N/A N/C DC
No unauthorised modifications (Y= OK) Y N N/A N/C DCV
Equipment is clear of obstructions (minimum dimensions 40mm) Y N N/A N/C DCV
No chafing parts that may cause local hot spots (motor fans) (Y=OK) Y N N/A N/C D
Guards are correctly fitted Y N N/A N/C D
Lamp rating, type and position are correct Y N N/A N/C D
Notes:
Inspected:_______________________________ Date:___________________ Checked:_______________________________ Date:_________________
'Uncontrolled' Form HAD 2.3 Rev_0
INSPECTION CHECK SHEET
Increased Safety Ex e
TAG/IDENTIFICATION DESCRIPTION
Area Classification ‐ Zone 0 1 2 Non Hazardous ‐ Group I IIA IIB IIC ‐ Temp T1 T2 T3 T4 T5 T6
Record Name Plate Details Record other nameplate information that may
Manufacturer KW FLC be relevant
Serial No. Volts RPM
Model
Certificate No. T IP
Certifying authority
Inspection type performed (I=Initial, P=Periodic, S=Sample) I P S
Inspection Grade Performed (D=Detailed, C=Close, V=Visual) D C V Detailed requires de‐energization
Equipment Y=OK, N=Not Acceptable, N/A=Not Applicable, N/C=Not Checked Inspect
Remarks
Grade
Equipment is Australian or IEC Certified Y N N/A N/C DCV
EX markings are suitable for the area Y N N/A N/C DCV
Equipment is clearly marked and has appropriate tag/identification details Y N N/A N/C DCV
Enclosure is not damaged and maintains its weatherproofing (min IP54) Y N N/A N/C DCV
Enclosure gaskets are in a satisfactory condition Y N N/A N/C D
Bolts, bungs, plugs/blank plates installed and tight Y N N/A N/C DCV
Terminals are sized correctly for the rating Y N N/A N/C D
Conductors > 0.5mm2 for multistranded and 1mm2 for single strand Y N N/A N/C D
No chafing parts that may cause local hot spots (motor fans) (Y=OK) Y N N/A N/C D
Guards are correctly fitted Y N N/A N/C D
No unautorised modifications (Y=OK) Y N N/A N/C DCV
Lamp rating, type and position are correct Y N N/A N/C D
Notes:
Inspected:_______________________________ Date:___________________ Checked:_______________________________ Date:__________________
'Uncontrolled' Form HAD 2.2 Rev_0
INSPECTION CHECK SHEET
Intrinsically Safe Ex i
TAG/IDENTIFICATION DESCRIPTION
Area Classification ‐ Zone 0 1 2 20 21 22 Non Hazardous ‐ Group I IIA IIB IIC ‐ Temp T1 T2 T3 T4 T5 T6
Record Name Plate Details Record other nameplate information that may be
Manufacturer Vin Chin relevant
Serial No. Lin Lin
Model
Certificate no. T IP
Certifying authority
Inspection Type Performed (I=Initial, P=Periodic, S=Sample) I P S
Inspection Grade Performed (D=Detailed, C=Close, V=Visual) D C V Detailed requires de‐energization
Equipment Y=OK, N=Not Acceptable, N/A=Not Applicable, N/C=Not Checked Inspect
Remarks
Grade
Equipment is Australian or IEC Certified Y N N/A N/C DCV
EX markings are suitable for the area Y N N/A N/C DCV
Equipment is clearly marked and has appropriate tag/identification details Y N N/A N/C DCV
Enclosure is not damaged and maintains its weatherproofing Y N N/A N/C DCV
Terminations are tight Y N N/A N/C DC
All unused conductors terminated Y N N/A N/C DC
Bolts, bungs, plugs/blank plates installed and tight Y N N/A N/C DCV
Fuses and lamps are correct rating Y N N/A N/C DCV
No unautorised modifications (Y=OK) Y N N/A N/C DCV
Notes:
Inspected:_______________________________ Date:___________________ Checked:_______________________________ Date:__________________
'Uncontrolled' Form HAD 2.1 Rev_0
APA GROUP – AMADEUS BASIN TO DARWIN PIPELINE
KATHERINE METER STATION HAZARDOUS AREA DOSSIER
General
Tag no.: Site:
P&ID: Area Classification:
Equipment Details
Equipment type: Gas group (IIA/B/C):
Manufacturer: Temp class (T1-T6):
Model no.: Certificate no.:
Serial no.: Test authority:
Competent Operator
Name: Identification no.:
Company: Company registration:
Condition
Condition upon receipt:
Old repair label details:
Reported Fault (if any):
Action
Repair action:…………………………………………………………………………………………
…………………………………………………………………………………………………………
…………………………………………………………………………………………………………
…………………………………………………………………………………………………………
…………………………………………………………………………………………………………
…………………………………………………………………………………………………………
Remarks:………………………………………………………………………………………………
…………………………………………………………………………………………………………
…………………………………………………………………………………………………………
…………………………………………………………………………………………………………
…………………………………………………………………………………………………………
…………………………………………………………………………………………………………
…………………………………………………………………………………………………………
Sign:………………………………… Date:….../……./…………
Based on AS/NZS 3800:2005 Form HAD 1.1
“Uncontrolled” Rev_0
REPAIR AND EXAMINATION REPORT FOR
INCREASED SAFETY ENCLOSURES (EX ‘e’)
General
Tag no.: Site:
P&ID: Area Classification:
Equipment Details
Equipment type: Gas group (IIA/B/C):
Manufacturer: Temp class (T1-T6):
Model no.: Certificate no.:
Serial no.: Test authority:
Competent Operator
Name: Identification no:
Company: Company Registration:
Enclosure Condition
Old repair label no.:
External surface cleaned for inspection - Yes / No
Covers and fasteners: Base of enclosure:
Threaded holes: External corrosion:
Surface coating: Gland entries and glands:
General external condition:
Enclosure dismantled: Degree of protection: IP
Internal Condition - Dust/Liquids: Corrosion: Heat:
Missing parts:
Cables and terminations: Terminal blocks:
Earth terminals: Insulation:
Windows and seals: Actuators and seals:
Ex ‘de’ parts: Meters:
Lamps: Transformers:
Switches: Others:
Relays: Interlocks:
Luminaire: Lamp power (W):
Transparent part: Lampholders:
Ballasts: Capacitors: Batteries:
Action
Repair
……………………………………………………………………………………………………………………
Remarks:…………………………………………………………………………………………………………
……………………………………………………………………………………………………………………
Sign:………………………………… Date:….../……./…………
Based on AS/NZS 3800:2005 Form HAD 1.2
“Uncontrolled” Rev_0
REPAIR AND EXAMINATION REPORT FOR
ELECTRICAL EQUIPMENT INSTALLED WITHIN
FLAMEPROOF ENCLOSURE (EX‘d’)
General
Tag no.: Site:
P&ID: Area Classification:
Equipment Details
Equipment type: Gas group (IIA/B/C):
Manufacturer: Temp class (T1-T6):
Model no.: Certificate no.:
Serial no.: Test authority:
Operator
Name: Identification no.:
Company: Company registration:
Equipment Condition Checklist
Item Description of check No work Repaired Replaced
(a) Isolator mechanism and switch operation i d (R)
(b) Earthing device and operation
(c) All auxiliary mechanisms, trip bars, latching
arrangements, etc.
(d) All locking devices, function and operation
(e) All parts for mechanical condition
(f) All insulation checked – no heat, cracks, etc.
(g) Phase barriers fitted correctly and functional
(h) Oil levels and/or gas pressure
(i) Gas pressure-sensing devices
(J) All wiring and terminations
(k) Earth continuity; phase/earth fault lock units
(l) Overcurrent, overload and earth-fault devices
(m) Earth-fault trip devices
(n) Timing devices
(o) Temperature-sensing devices
(p) Transformer connections, bolts, tapes. bracing,
insulators and fittings, etc.
(q) Installation
(r) Machine cables and glands
Based on AS/NZS 3800:2005 Form HAD 1.4
“Uncontrolled” Rev_0
REPAIR AND EXAMINATION REPORT FOR
ELECTRICAL EQUIPMENT INSTALLED WITHIN
FLAMEPROOF ENCLOSURE (EX‘d’)
Assembled unit tested for insulation resistance with: V megohmmeter, and power frequency
tested on the following circuits:
Certification no(s).………………………………………………………………………………….…..
……………………………………………………………………………………………………………
Remarks:………………………………………………………………………………………………
……………………………………………………………………………………………………………
……………………………………………………………………………………………………………
……………………………………………………………………………………………………………
……………………………………………………………………………………………………………
………………………………………………………………………………………………………….
Sign:………………………………… Date:….../……./…………
Based on AS/NZS 3800:2005 Form HAD 1.4
“Uncontrolled” Rev_0
REPAIR AND EXAMINATION REPORT FOR
FLAMEPROOF ENCLOSURE (EX‘d’)
General
Tag no.: Site:
P&ID: Area Classification:
Equipment Details
Equipment type: Gas group (IIA/B/C):
Manufacturer: Temp class (T1-T6):
Model no.: Certificate no.:
Serial no.: Test authority:
Operator
Name: Identification no.:
Company: Company registration:
Equipment Condition Checklist
Item Description of check Remarks
(a) Check of external and internal damage
(b) Dimensional check
(c) Corrosion on flamepaths
(d) Result of static pressure test
(e) Check of flanged joint surfaces
(f) Check of all threaded holes
(g) Check of all windows and lenses
(h) Check of breathers
(i) Check of all bolt holes, studs, screws,
(J) Check of all gland entries and fixing
(k) h l
Check of all cables glands
(l) Check of all handhole and inspection
(m) Check of all mechanical interlocks
(n) Check of all flamepath gaps
Main control panel
1. Max. out of plane of box flanges:……………………………………………………………
2. Max. out of plane of cover:……………………………………………………………………
3. Max. flameproof gap when bolted up:………………………………………………………
4. Max. diametral clearance of spindles:………………………………………………………
5. Max. diametral clearance of gland to gland apertures:……………………………………
6. Static pressure test – pressure:……………………………………………………………
7. Water jacket – pressure test:………………………………Capacity:……………………
Certification drawing no(s).:…………………………………………………………………………
Remarks:………………………………………………………………………………………………
……………………………………………………………………………………………………………
…………………………………………………………………………………………………………
Sign:………………………………… Date:….../……./…………
Based on AS/NZS 3800:2005 Form HAD 1.3
“Uncontrolled” Rev_0
APA GROUP – AMADEUS BASIN TO DARWIN PIPELINE
KATHERINE METER STATION HAZARDOUS AREA DOSSIER