Índice

1. DATOS GENERALES DEL PROYECTO........................................................3


1.1 GENERALIDADES.................................................................................................... 3
1.2 ETAPA DE INVERSION............................................................................................. 4
1.3 RESPONSABLES DE OBRA.......................................................................................4
2. DESCRIPCION DEL PROYECTO................................................................5
2.1 Antecedentes......................................................................................................... 5
2.2 Objetivos del Proyecto............................................................................................ 5
2.3 Metas del proyecto................................................................................................. 5
2.4 Marco Legal............................................................................................................ 6
2.5 Ubicación:.............................................................................................................. 6
2.6 Presupuesto:.......................................................................................................... 7
2.7 Plazo De Ejecución................................................................................................. 7
2.8 Cronograma Programado de Ejecución Física (Según Plan de Trabajo 2018)..........7
3. EVALUACION DEL ESTADO SITUACIONAL ACTUAL....................................8
A. DOCUMENTOS TECNICOS.......................................................................................8
3.1 Expediente Técnico................................................................................................ 8
3.2 Acta de Entrega de Terreno....................................................................................8
3.3 Actas de Inicio de Obra.......................................................................................... 8
3.4 Cuadernos de obra................................................................................................. 8
3.5 Pruebas De Control De Calidad..............................................................................8
3.6 Planes de Trabajo................................................................................................... 9
3.7 Plan de Seguridad y Salud en el Trabajo.................................................................9
3.8 Informes Mensuales............................................................................................... 9
3.9 Expediente de Ampliaciones de Plazo....................................................................9
3.10.................Expediente de Modificaciones Presupuestales (Adicionales y Deductivos)
9
3.11........................................................................................................ Consultas al Proyectista
9
3.12..................................................................... Hoja de Control de Cambios Físicos en Obra
9
3.13............................................................................. Modificaciones al Presupuesto Analítico
9
3.14................................................... Cronogramas Acelerados de Reprogramación de Obra
9
3.15.......................................................................................................... Informes Situacionales
9
B. ACERVO DOCUMENTARIO.......................................................................................9
3.16....................................................................................... Documentos emitidos y recibidos
10
3.17............................................................. Conformidades de pago por Servicios Prestados
11
3.18................................................................................................................. Tareos del Personal
11
3.19................................................................. Documentos de Designación de Responsables
11
Gerencia de Ingeniería y Obras

C. AVANCE FISICO Y FINANCIERO..............................................................................11


3.20............................................................................................................. Replanteo De Campo
11
3.21................................................................................................... Resumen de Avance Físico
15
3.22............................................................................... Gasto a Nivel de Recursos Empleados
15
a) Total gastos por recursos empleados...................................................................15
3.23............................. Gasto Financiero de Obra (Según Reporte Siaf – Nivel de Pagados)
15
a) Gasto Financiero de obra Acumulado según las especificas.................................15
3.24 Comparativo Entre Avance Físico Vs Avance Programado del Plan de Trabajo 2018
16
3.25................Comparativo Entre Avance Físico y Gasto a Nivel de Recursos Empleados
16
D. MODIFICACIONES PRESUPUESTALES....................................................................16
3.26............................................................................................................... Deductivos de Obra
16
3.27............................................................................................................... Adicionales de Obra
16
E. MODIFICACIONES AL PLAZO DE EJECUCION.........................................................17
3.28........................................................................................................... Ampliaciones de Plazo
17
3.29.................................................................................................... Plazo Actualizado de Obra
17
3.30....................................................................................................... Plazo Ejecutado de Obra
17
3.31.................................................................................................. Saldo de Plazo por ejecutar
17
F. MODIFICACIONES AL CRONOGRAMA DE EJECUCION.............................................17
3.1 Cronogramas Acelerados de Reprogramación de Obra........................................17
G. ALMACEN DE OBRA.............................................................................................. 17
3.2 Reporte de bienes y materiales Adquiridos..........................................................17
3.3 Inventario Actual de existencias en el Almacén de Obra......................................17
3.4 Tarjetas de Control Visible (Kardex)......................................................................17
3.5 Reporte Total de Bienes existentes.......................................................................18
H. LIMITACIONES Y OBSERVACIONES........................................................................18
I. PANEL FOTOGRAFICO...........................................................................................19
4. CONCLUSIONES...................................................................................19
5. RECOMENDACIONES............................................................................21
6. ANEXOS.............................................................................................. 21

Informe Situacional 2019 de la Obra: “MEJORAMIENTO DE SERVICIO DE TRANSITABILIDAD PEATONAL Y VEHICULAR DE LA


ASOCIACIÓN DE VIVIENDA URB. VILLA MARÍA DEL TRIUNFO DE LA JUNTA VECINAL JESÚS MARÍA DE LA CIUDAD DE TACNA,
DISTRITO TACNA, PROVINCIA TACNA – TACNA

” Pág. 2
Gerencia de Ingeniería y Obras

INFORME SITUACIONAL DE OBRA


(Al 02 de Enero 2019)
1. DATOS GENERALES DEL PROYECTO
1.1 GENERALIDADES

Obra: MEJORAMIENTO DE SERVICIO DE TRANSITABILIDAD PEATONAL Y VEHICULAR DE LA ASOCIACIÓN


DE VIVIENDA URB. VILLA MARÍA DEL TRIUNFO DE LA JUNTA VECINAL JESÚS MARÍA DE LA
CIUDAD DE TACNA, DISTRITO TACNA, PROVINCIA TACNA – TACNA

Entidad Ejecutora : Municipalidad Provincial De Tacna


Unidad Orgánica Ejecutora : Gerencia de Ingeniería y Obras

Función : Transporte
Programa : Transporte Urbano
Subprograma : Vías Urbanas
Código SNIP : 309903

Meta Sigam : CD 200620 (2018)


GG 200621(2018)

Modalidad de Ejecución : Ejecución Presupuestaria Directa

Localización de la Obra :
Provincia : TACNA
Distrito : TACNA
Sector : URB. VILLA MARÍA DEL TRIUNFO DE LA JUNTA VECINAL JESÚS
MARÍA DE LA CIUDAD DE TACNA

Fuente de Financiamiento : Canon Sobrecanon y Regalías Mineras

Pptto Perfil (PIP Viable) : S/ 1’134,142.55 Soles


Pptto Exp Téc. Aprobado : S/ 1’193,454.62 Soles
% Incidencia Respecto al Perfil : + 5.2 % (según Formato Snip 15)

Informe Situacional 2019 de la Obra: “MEJORAMIENTO DE SERVICIO DE TRANSITABILIDAD PEATONAL Y VEHICULAR DE LA


ASOCIACIÓN DE VIVIENDA URB. VILLA MARÍA DEL TRIUNFO DE LA JUNTA VECINAL JESÚS MARÍA DE LA CIUDAD DE TACNA,
DISTRITO TACNA, PROVINCIA TACNA – TACNA

” Pág. 3
Gerencia de Ingeniería y Obras

Resolución Aprob. Exp. Técnico: Resol. De Alcaldía N°1339-2018


Fecha de Aprob. del Exp. Téc. : 04 de Octubre de 2018

Presupuesto Costo de Obra : S/ 1, 080,105.19 Soles (CD+GG)


Plazo de Ejecución : 105 días calendarios (Expediente Técnico)

Plazo de Ejecutado : 43 días calendarios al 31/12/2018


Fecha Inicio de Obra : 19 de Noviembre de 2018
Fecha de Fin de obra : 03 de marzo de 2018

1.2 ETAPA DE INVERSION


a. Avance físico: En base a la verificación y replanteo de campo

Valorización Física Acumulada (CD) : S/ 419, 610.69 Soles


Valorización Física Acumulada (GG) : S/ 62, 941.60 Soles
Valorización Física Acumulada (CD+GG): S/ 482,552.29 Soles
Porcentaje Acumulado : 44.68 %

Saldo por Valorizar (CD+GG) : S/ 597,552.89 Soles


Porcentaje por Valorizar : 55.32 %
OBS: Actualmente el informe mensual del mes de noviembre del 2018 se encuentra observado,
por parte del inspector de la obra. Así mismo se indica que no se tiene el
informe mensual del mes de diciembre del 2018

b. Gasto Financiero de Uso de Recursos en Obra: Comprende el uso de Recurso netamente empleados en
la ejecución de las partidas ejecutadas en campo.

Valorización Acumulada : S/ 568, 362.17 Soles


Porcentaje Acumulado : 52.62 %

El monto acumulado se la obtenido del procesamiento del reporte de adquisiciones –año 2018
en comparación con las conformidades emitidas del acervo documentario y saldos del Control
Visible de Almacén (Kardex), los saldos de materiales recibidas en el documento de la
transferencia.

c. Gasto Financiero Total: En base al reporte Siaf y Sigan del área de presupuesto a nivel de fase
devengado

Gasto Financiero Año 2018 (CD+GG) : S/ 603,846.84 Soles


Porcentaje Acumulado : 55.91 %

Saldo Financiero (CD+GG) : S/ 476, 258.35 Soles


Porcentaje por Utilizar : 44.09 %

1.3 RESPONSABLES DE OBRA

Periodo
Nº Residentes de Obra Documento que Designa
Desde hasta
1° Ing.Andres Eduardo del R.G.M 203-2018 10/10/2018 31/12/2018

Informe Situacional 2019 de la Obra: “MEJORAMIENTO DE SERVICIO DE TRANSITABILIDAD PEATONAL Y VEHICULAR DE LA


ASOCIACIÓN DE VIVIENDA URB. VILLA MARÍA DEL TRIUNFO DE LA JUNTA VECINAL JESÚS MARÍA DE LA CIUDAD DE TACNA,
DISTRITO TACNA, PROVINCIA TACNA – TACNA

” Pág. 4
Gerencia de Ingeniería y Obras

Campo Vera

Periodo
Nº Inspectores de Obra Documento que Designa
Desde hasta
1° Ing. Hernan Paul Ventura R.G.M. 204-2018 16/10/2018 31/12/2018
Cabana

Gerencia de Ingeniería y Obras: Ing. Oscar Cañari Cañari


Sub Gerencia de Supervisión : Ing. Henry Cañari Cañari

2. DESCRIPCION DEL PROYECTO


2.1 Antecedentes
 La Municipalidad Provincial de Tacna, ha considerado dentro de su programa de inversiones
para el presente año, la ejecución de la obra “MEJORAMIENTO DEL SERVICIO DE
TRANSITABILIDAD PEATONAL Y VEHICULAR DE LA ASOCIACIÓN DE VIVIENDA URB. VILLA MARÍA
DEL TRIUNFO DE LA JUNTA VECINAL JESÚS MARÍA DE LA CIUDAD DE TACNA, DISTRITO TACNA,
PROVINCIA TACNA – TACNA”, con Código SNIP: 309903, fue evaluado y declarado viable con
INFORME TÉCNICO Nº 008–2016-HVTM–SGPI–GM-MPT, el 20 de SETIEMBRE del 2016, con un
monto total de S/. 1’134,142.55 soles.

 Con INFORME Nº 196-2016-SGPI-GM/MPT de fecha 28 de Setiembre de 2016, se comunica a la


Gerencia Municipal que el PIP: “MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD
PEATONAL Y VEHICULAR DE LA ASOCIACIÓN DE VIVIENDA URB. VILLA MARÍA DEL TRIUNFO DE
LA JUNTA VECINAL JESÚS MARÍA DE LA CIUDAD DE TACNA, DISTRITO TACNA, PROVINCIA TACNA
– TACNA”, con Código SNIP Nº 309903, ha sido declarado VIABLE mediante el INFORME
TÉCNICO Nº 008–2016-HVTM–SGPI–GM-MPT

 El presente Expediente Técnico se rige por la Directiva Nº 003-2018-MPT-GPPyCT “Normas para


la distribución y Uso de Costos Indirectos en el Presupuesto de los Proyectos de Inversión y
Mantenimiento de Infraestructura pública en la modalidad de ejecución presupuestaria Directa
de la Municipalidad Provincial de Tacna”.

 En tal sentido mediante MEMORANDO Nº 003-2018-UGEI-GIO/MPT/TACNA, se pidió la


elaboración del Expediente Técnico.

 Por lo tanto, el Equipo Técnico de la Unidad de Gestión de Estudios de Inversión elaboró el


Presente Expediente Técnico.
2.2 Objetivos del Proyecto
 A fin de solucionar el problema central

“INADECUADAS CONDICIONES DE TRANSITABILIDAD PEATONAL Y VEHICULAR EN LAS CALLES


DE LA URBANIZACION VILLA MARÍA DEL TRIUNFO DE LA JUNTA VECINAL JESUS MARIA”

 Se ha planteado el objetivo principal:

” ADECUADAS CONDICIONES DE TRANSITABILIDAD PEATONAL Y VEHICULAR EN LAS CALLES DE


LA URBANIZACION VILLA MARIA DEL TRIUNFO DE LA JUNTA VECINAL JESUS MARIA”

2.3 Metas del proyecto

Informe Situacional 2019 de la Obra: “MEJORAMIENTO DE SERVICIO DE TRANSITABILIDAD PEATONAL Y VEHICULAR DE LA


ASOCIACIÓN DE VIVIENDA URB. VILLA MARÍA DEL TRIUNFO DE LA JUNTA VECINAL JESÚS MARÍA DE LA CIUDAD DE TACNA,
DISTRITO TACNA, PROVINCIA TACNA – TACNA

” Pág. 5
Gerencia de Ingeniería y Obras

El proyecto: “MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD PEATONAL Y VEHICULAR DE LA


ASOCIACIÓN DE VIVIENDA URB. VILLA MARÍA DEL TRIUNFO DE LA JUNTA VECINAL JESÚS MARÍA DE LA
CIUDAD DE TACNA, DISTRITO TACNA, PROVINCIA TACNA – TACNA”, contiene las siguientes
componentes:

COMPONENTE 01 INFRAESTRUCTURA VIAL

 Comprende la realización de las siguientes metas:


 PISTA DE PAVIMENTO FLEXIBLE CON CARPETA ASFÁLTICA E=2'' EN FRIO 1432.19 m2
 BERMA DE PAVIMENTO FLEXIBLE CON CARPETA ASFÁLTICA E=2'' EN FRIO 1729.64 m2

COMPONENTE 02 INFRAESTRUCTURA PEATONAL

 Comprende la realización de las siguientes metas:


 VEREDA DE PIEDRA LAVADA Y CEMENTO PULIDO S/DISEÑO F'C=175 KG/CM2 E=4" 2083.17 m2
 VEREDA DE PIEDRA LAVADA COLOREADA Y CEMENTO PULIDO S/DISEÑO F'C=175 KG/CM2 E=4"
175.44 m2
 MARTILLO DE PIEDRA LAVADA Y CEMENTO PULIDO S/DISEÑO F'C=175 KG/CM2 E=4" 553.22 m2
 RAMPA ACABADO SEMIPULIDO Y BRUÑADO CONCRETO F'C=175 KG/CM2 S=30% 76.56 m2
 RETIRO Y REPOSICION DE CAJA Y TAPA DE AGUA EXISTENTES 22.00 UND
 RETIRO Y REPOSICION DE CAJAS Y TAPA DE REGISTRO DE DESAGUE EXISTENTES 40.00 UND

COMPONENTE 03 SEÑALIZACIÓN Y OBRAS COMPLEMENTARIAS

 Comprende la realización de las siguientes metas:


 PINTADO LINEAL INTERMITENTE CENTRAL E=0.10M 228.00 ML
 PINTADO LINEAL CONTINUO LATERAL E=0.10M 1,963.40 ML
 PINTADO DE BORDE DE VEREDAS CON PINTURA TRAFICO COLOR AMARILLO 108.94 M2
 PINTADO DE BORDE DE VEREDAS CON PINTURA TRAFICO COLOR AZUL 92.29 M2
 PINTADO DE SEÑALIZACION EN EL PAVIMENTO 454.25 M2
 SUMINISTRO E INSTALACION DE SEÑALIZACION VERTICAL 28.00 UND
 SUMINISTRO E INSTALACION DE BOLARDOS 16.00 UND
 CONSTRUCCION DE JARDINERAS SEGÚN DISEÑO 42.00 UND
 SUMINISTRO E INSTALACION DE BASURERO SEGÚN DISEÑO 03.00 UND
 REUBICACION DE POSTES EXISTENTES 13.00 UND

COMPONENTE 04 MITIGACION DE IMPACTO AMBIENTAL

 Comprende la realización de las siguientes metas:


 RIEGO EN LA ZONA DE TRABAJO 6,055.94 M2
 ACONDICIONAMIENTO DE MATERIAL EXCEDENTE EN BOTADERO 3,267.17 M2
2.4 Marco Legal
- Ley Nº 27783 – Ley de Bases de Descentralización.
- DECRETO LEGISLATIVO Nº 1252 SISTEMA NACIONAL DE PROGRAMACION MULTIANUAL Y
GESTION DE INVERSIONES
- Ley N° 27972 – Ley Orgánica de Municipalidades.
- Plan de Desarrollo Urbano 2015 – 2025
- Plan Director de la Ciudad de Tacna 2015 – 2025
- Ley de contrataciones del estado
- Ley Nº 29783, Ley de Seguridad y Salud en el Trabajo
- RNE (Reglamento Nacional de Edificaciones)
- Otras Normas aplicables al tipo de obra.

Informe Situacional 2019 de la Obra: “MEJORAMIENTO DE SERVICIO DE TRANSITABILIDAD PEATONAL Y VEHICULAR DE LA


ASOCIACIÓN DE VIVIENDA URB. VILLA MARÍA DEL TRIUNFO DE LA JUNTA VECINAL JESÚS MARÍA DE LA CIUDAD DE TACNA,
DISTRITO TACNA, PROVINCIA TACNA – TACNA

” Pág. 6
Gerencia de Ingeniería y Obras

- Manual de Carreteras, Especificaciones Técnicas Generales para Construcción EG-2013

2.5 Ubicación:
Región : Tacna
Provincia : Tacna
Distrito : Tacna
Sector : Asoc. De Viv. Urb. Villa María del triunfo de la Junta vecinal Jesús
María

2.6 Presupuesto:
El presupuesto total del proyecto está distribuido de la siguiente forma:

2.7 Plazo De Ejecución


El expediente técnico aprobado mediante RGM 1339-2018 indica un plazo de ejecución de 105 días
calendario, dándose por iniciada la obra el 19 de Noviembre del 2018 según el asiento N°01 del
residente de obra del folio 05 del cuaderno de obra.
2.8 Cronograma Programado de Ejecución Física (Según Plan de Trabajo 2018)
El cronograma de ejecución líneas abajo corresponde al cronograma programado del plan de trabajo 2018
del mes de noviembre al mes de diciembre del 2018, que incluye el costo directo más gastos generales.X

Informe Situacional 2019 de la Obra: “MEJORAMIENTO DE SERVICIO DE TRANSITABILIDAD PEATONAL Y VEHICULAR DE LA


ASOCIACIÓN DE VIVIENDA URB. VILLA MARÍA DEL TRIUNFO DE LA JUNTA VECINAL JESÚS MARÍA DE LA CIUDAD DE TACNA,
DISTRITO TACNA, PROVINCIA TACNA – TACNA

” Pág. 7
Gerencia de Ingeniería y Obras

OBS: Según avance fisico programado del plan del 2018 v/s ejecutado al 31/12/2018, se puede observar en la
curva “S” que la ejecucion fisica de la obra se encuentra Retrasada a un 30.17 %

3. EVALUACION DEL ESTADO SITUACIONAL ACTUAL


A. DOCUMENTOS TECNICOS
3.1 Expediente Técnico
“No hubo hallazgo”
3.2 Acta de Entrega de Terreno
“No hubo hallazgo”
3.3 Actas de Inicio de Obra
“No hubo hallazgo”
3.4 Cuadernos de obra
Se tiene cuaderno de obra Tomo I, el cual se encuentra incompleto el llenado de los asientos
respectivos del residente e inspector de obra según el detalle que se indica:
 Los folios 02, 03 se encuentra en hojas vacías, en la cual falta el pegado de las actas de
entrega de terreno y acta de reinicio de obra, la cual no se ubica en ningún acervo
documentario existente.
 Falta firma del inspector de obra los siguientes folios: 16 ,
18,20,21,22,24,26,27,29,30,31,33,34,35,36,38,39,,40,41,42,,44,45,,46,47,,49,50,51,53,5
4,56,57,59,60,61,62,63.
 Falta firma del residente de obra en folio 21.
 No existe escrito en número de asientos en diferentes fechas del cuaderno de obra en
los folios 33,35,42,44,46,47,49,50,51,53,54,56,57,59,60,61, las cuales deben son
necesarios para continuación correlativa de números de asiento.
3.5 Pruebas De Control De Calidad
“No hubo hallazgo en el acervo documentario existente”

3.6 Planes de Trabajo


Resolución de Monto
Año Documento de Presentación Residente Observación
Aprobación (Soles)

Informe Situacional 2019 de la Obra: “MEJORAMIENTO DE SERVICIO DE TRANSITABILIDAD PEATONAL Y VEHICULAR DE LA


ASOCIACIÓN DE VIVIENDA URB. VILLA MARÍA DEL TRIUNFO DE LA JUNTA VECINAL JESÚS MARÍA DE LA CIUDAD DE TACNA,
DISTRITO TACNA, PROVINCIA TACNA – TACNA

” Pág. 8
Gerencia de Ingeniería y Obras

No hubo
InformeNª 1601-2018- hallazgo de la
Ing. Andres
SGSLP-GM/MPT. resolución de
2018 782,377.06 Eduardo Campo File original
(Conformidad del Plan de aprobación del
Vera
Trabajo 2018) plan de trabajo
2018

3.7 Plan de Seguridad y Salud en el Trabajo


Se tiene el plan de seguridad, sin los documentos de aprobación de parte del área de la
supervisión de la entidad y área de seguridad salud de la misma. Así mismo se indica que no
tiene firmado por el responsable los siguientes: Planos de ubicación y localización, matriz de
identificación, de peligros y evaluación de riesgos, plano de seguridad (protección colectivas),
plano de matriz de riesgo y plano de evaluación en caso de accidente.

3.8 Informes Mensuales


Se indica que no tiene aprobado el informe mensual del mes de noviembre del 2018, la cual se
encuentra en el área de supervisión de la entidad, según la documentación existe en el acervo
documentario el residente anterior remetió mediante informe N°032-2018-AEDCV-
MSTPVAVUVMT-GIO-MPT, con fecha 17 de diciembre del 2018.Asi mismo falta elaborar y
presentar el informe mensual del mes de Diciembre del 2018, según la directiva se debió
presentarse en los 5 días hábiles del presentes mes, la cual es responsabilidad del residente
saliente.

3.9 Expediente de Ampliaciones de Plazo


“No presenta, según verificación en el banco de proyectos a la fecha 08/01/2019”

3.10 Expediente de Modificaciones Presupuestales (Adicionales y Deductivos)


No registra Modificaciones Presupuestales (Adicionales y Deductivos) según verificación del formato
Snip16 en el banco de proyectos (Fecha de verificación 08/01/2019)

3.11 Consultas al Proyectista


No hubo hallazgo en el acervo documentario existente.

3.12 Hoja de Control de Cambios Físicos en Obra


No hubo hallazgo en el acervo documentario existente.

3.13 Modificaciones al Presupuesto Analítico

Año Documento Ref. Residente Asunto


Informe N°014-2018-
Ing.Andres Eduardo
2018 AEDCV-MSTPVAVUVMT- Modificación presupuestal analítico
Campo vera
GIO-MPT
3.14 Cronogramas Acelerados de Reprogramación de Obra
No hubo hallazgo en el acervo documentario existente.

3.15 Informes Situacionales


No hubo hallazgo en el acervo documentario existente.

B. ACERVO DOCUMENTARIO
3.16 Documentos emitidos y recibidos

Informe Situacional 2019 de la Obra: “MEJORAMIENTO DE SERVICIO DE TRANSITABILIDAD PEATONAL Y VEHICULAR DE LA


ASOCIACIÓN DE VIVIENDA URB. VILLA MARÍA DEL TRIUNFO DE LA JUNTA VECINAL JESÚS MARÍA DE LA CIUDAD DE TACNA,
DISTRITO TACNA, PROVINCIA TACNA – TACNA

” Pág. 9
Gerencia de Ingeniería y Obras

3.17 Conformidades de pago por Servicios Prestados

Informe Situacional 2019 de la Obra: “MEJORAMIENTO DE SERVICIO DE TRANSITABILIDAD PEATONAL Y VEHICULAR DE LA


ASOCIACIÓN DE VIVIENDA URB. VILLA MARÍA DEL TRIUNFO DE LA JUNTA VECINAL JESÚS MARÍA DE LA CIUDAD DE TACNA,
DISTRITO TACNA, PROVINCIA TACNA – TACNA

” Pág. 10
Gerencia de Ingeniería y Obras

Los informes de conformidades emitidas que se encuentran en el acervo documentario están


incompletos.

3.18 Tareos del Personal


No hubo hallazgo en el acervo documentario existente.

3.19 Documentos de Designación de Responsables


Existen resoluciones de asignación del residente e inspector de obra en copia simple

C. AVANCE FISICO Y FINANCIERO


3.20 Replanteo De Campo
Sea a realizado el procesamiento del resumen de metrados del cuaderno de obra del
asiento N°14 del residente de obra para determinar el avance físico del mes de
Noviembre y del Folio 62 al 63 para el mes de Diciembre del 2018,con los cuales se
obtiene los siguientes avances físicos acumulados indicadas líneas abajo. Así mismo
queda pendiente realizar la verificación y mediciones, replanteo de campo para
constatar los trabajos realmente ejecutados durante el periodo de ejecución del año
2018.

METRADOS EJECUTADOS AL 31 DE DICIEMBRE DEL 2018


AVANCE
PRESUPUESTO APROBADO SALDO
ACUMULADO
UND
ITEM
. PRECI
O PRESUPUE VALORIZ VALORIZ
METR. METR. % METR. %
UNIT. STO S/. ADO S/. ADO S/.
S/.

01 INFRAESTRUCTURA VIAL

01.01 OBRAS PROVISIONALES

CARTEL DE IDENTIFICACION DE OBRA 3.60x2.40 CON 1, 100.00


01.01.01 und
GIGANTOGRAFIA 639.75 %
1.00 1,639.75 1,639.75 1.00
8 10, 100.00
01.01.02 ALMACEN OFICINA Y CASETA DE GUARDIANIA m2
0.00 092.80 %
80.00 126.16 10,092.80
2 1, 100.00
01.01.03 VESTUARIO Y COMEDOR PARA EL PERSONAL m2
0.00 933.20 %
20.00 96.66 1,933.20
1 62.50
01.01.04 ALQUILER BAÑO PORTATIL INCL MANTENIMIENTO mes 37.50%
,236.25 %
4.00 494.50 1,978.00 1.50 741.75 2.50
62.50
01.01.05 SUMINISTRO PROVISIONAL DE AGUA POTABLE mes 37.50%
%
4.00 350.00 1,400.00 1.50 525.00 2.50 875.00
62.50
01.01.06 SUMINISTRO PROVISIONAL DE ENERGIA ELECTRICA mes 37.50%
%
4.00 350.00 1,400.00 1.50 525.00 2.50 875.00

MOVILIZACION Y DESMOVILIZACION DE MAQUINARIAS, EQUIPOS Y 50.00


01.01.07 glb 50.00%
HERRAMIENTAS PARA OBRA %
1.00 1,416.00 1,416.00 0.50 708.00 0.50 708.00

01.02 SEGURIDAD Y SALUD


- - -

ELABORACIÓN, IMPLEMENTACIÓN Y ADMINISTRACIÓN DEL PLAN DE 3, 100.00


01.02.01 glb
SEGURIDAD Y SALUD EN EL TRABAJO 000.00 %
1.00 3,000.00 3,000.00 1.00 -

5 28, 100.00
01.02.02 EQUIPOS DE PROTECCIÓN INDIVIDUAL und 0.00%
0.00 225.00 %
50.00 564.50 28,225.00 - -
1, 100.00
01.02.03 EQUIPOS DE PROTECCIÓN COLECTIVA glb 0.00%
797.50 %
1.00 1,797.50 1,797.50 1.00 - -
2, 100.00
01.02.04 SEÑALIZACIÓN TEMPORAL DE SEGURIDAD glb
161.00 %
1.00 2,161.00 2,161.00 1.00 -
2, 100.00
01.02.05 CAPACITACION SOBRE SALUD Y SEGURIDAD glb
000.00 %
1.00 2,000.00 2,000.00 1.00 -
100.00
01.02.06 RECURSOS DE RESPUESTA DE EMERGENCIA glb
%
1.00 680.00 680.00 1.00 680.00 -
2, 100.00
01.02.07 AGUA DE MESA PARA CONSUMO HUMANO glb 0.00%
000.00 %
1.00 2,000.00 2,000.00 1.00 - -
SERVICIO DE REVISION MEDICA P/PERSONAL OBRERO Y TECNICO 1 4, 3 8 64.00
01.02.08 und 36.00%
DE OBRA 8.00 860.00 2.00 ,640.00 %
50.00 270.00 13,500.00

Informe Situacional 2019 de la Obra: “MEJORAMIENTO DE SERVICIO DE TRANSITABILIDAD PEATONAL Y VEHICULAR DE LA


ASOCIACIÓN DE VIVIENDA URB. VILLA MARÍA DEL TRIUNFO DE LA JUNTA VECINAL JESÚS MARÍA DE LA CIUDAD DE TACNA,
DISTRITO TACNA, PROVINCIA TACNA – TACNA

” Pág. 11
Gerencia de Ingeniería y Obras

01.03 PISTA
- - -

01.03.01 TRABAJOS PRELIMINARES


- - -
1,43 2 100.0
01.03.01.01 TRAZO DE NIVELES Y REPLANTEO m2
2.19 ,205.57 0%
1,432.19 1.54 2,205.57 - -
1,43 1 100.0
01.03.01.02 CONTROL TOPOGRAFICO m2
2.19 ,131.43 0%
1,432.19 0.79 1,131.43 - -
1,43 100.0
01.03.01.03 LIMPIEZA PERMANENTE DURANTE OBRA m2
2.19 0%
1,432.19 0.15 214.83 - - 214.83

01.03.02 DEMOLICIONES
- - -
1 100.0
01.03.02.01 DEMOLICION DE VEREDA DE CONCRETO C/EQUIPO E=0.10M m2
5.31 0%
15.31 14.89 227.97 - - 227.97
3 100.0
01.03.02.02 DEMOLICION DE BERMA DE CONCRETO CON EQUIPO E=0.15M m2
4.10 0%
34.10 17.38 592.66 - - 592.66
DEMOLICION DE BERMA DE ADOGRASS DE CONCRETO CON 100.0
01.03.02.03 m2
EQUIPO 0%
4.35 13.03 56.68 - - 4.35 56.68
2 100.0
01.03.02.04 DEMOLICION DE PAVIMENTO RIGIDO CON EQUIPO E=0.20M m2
1.60 0%
21.60 21.94 473.90 - - 473.90
10 1 100.0
01.03.02.05 DEMOLICION DE PAVIMENTO FLEXIBLE CON EQUIPO E=0.05M m2
8.78 ,259.67 0%
108.78 11.58 1,259.67 - -
1 100.0
01.03.02.06 DEMOLICION DE TAPA DE CONCRETO C/EQUIPO E=0.125M m2
8.21 0%
18.21 14.89 271.15 - - 271.15
DEMOLICION DE SARDINEL PERALTADO INCL CIMENTACION 100.0
01.03.02.07 m3
C/EQUIPO 0%
4.10 208.51 854.89 - - 4.10 854.89
1 100.0
01.03.02.08 REMOCIÓN DE AREAS VERDES m2
0.73 0%
10.73 1.20 12.88 - - 12.88
3 100.0
01.03.02.09 ACARREO DE MATERIAL EXCEDENTE HASTA 30M m3
8.04 0%
38.04 23.08 877.96 - - 877.96
3 100.0
01.03.02.10 ELIMINACION DE MATERIAL EXCEDENTE C/MAQUINARIA m3
8.04 0%
38.04 11.16 424.53 - - 424.53

01.03.03 MOVIMIENTOS DE TIERRA


- - -
1,18 9 100.0
01.03.03.01 CORTE DE TERRENO CON MAQUINARIA MATERIAL SUELTO m3
3.98 ,957.27 0%
1,183.98 8.41 9,957.27 - -
1,43 3 100.0
01.03.03.02 PERFILADO Y COMPACTADO DE SUBRASANTE m2
2.19 ,437.26 0%
1,432.19 2.40 3,437.26 - -
1,43 16 100.0
01.03.03.03 SUB BASE GRANULAR E=0.20M C/MAQUINARIA m2
2.19 ,255.36 0%
1,432.19 11.35 16,255.36 - -
1,43 16 100.0
01.03.03.04 BASE GRANULAR E=0.20M C/MAQUINARIA m2
2.19 ,899.84 0%
1,432.19 11.80 16,899.84 - -
1,53 8 100.0
01.03.03.05 ACARREO DE MATERIAL EXCEDENTE CON MAQUINARIA m3
9.18 ,326.96 0%
1,539.18 5.41 8,326.96 - -
1,53 17 100.0
01.03.03.06 ELIMINACION DE MATERIAL EXCEDENTE m3
9.18 ,177.25 0%
1,539.18 11.16 17,177.25 - -

01.03.04 PISTA PAVIMENTO FLEXIBLE


- - -
1,43 8 100.0
01.03.04.01 IMPRIMACION CON ASFALTO DILUIDO m2
2.19 ,736.36 0%
1,432.19 6.10 8,736.36 - -
1,43 42 100.0
01.03.04.02 CARPETA ASFALTICA E=2" EN FRIO m2
2.19 ,894.09 0%
1,432.19 29.95 42,894.09 - -

01.03.05 VARIOS COMPLEMENTARIOS


- - -
1 100.0
01.03.05.01 NIVELACION DE BUZONES und
,035.06 0%
3.00 345.02 1,035.06 - - 3.00

01.04 BERMAS
- - -

01.04.01 TRABAJOS PRELIMINARES


- - -
1,73 2 100.0
01.04.01.01 TRAZO DE NIVELES Y REPLANTEO m2
5.35 ,672.44 0%
1,735.35 1.54 2,672.44 - -
1,73 1 100.0
01.04.01.02 CONTROL TOPOGRAFICO m2
5.35 ,370.93 0%
1,735.35 0.79 1,370.93 - -
1,73 100.0
01.04.01.03 LIMPIEZA PERMANENTE DURANTE OBRA m2
5.35 0%
1,735.35 0.15 260.30 - - 260.30

01.04.02 DEMOLICIONES
- - -
16 2, 100.00
01.04.02.01 DEMOLICION DE VEREDA DE CONCRETO C/EQUIPO E=0.10M m2
6.84 484.25 %
166.84 14.89 2,484.25 -
29 5, 100.00
01.04.02.02 DEMOLICION DE BERMA DE CONCRETO CON EQUIPO E=0.15M m2
1.09 059.14 %
291.09 17.38 5,059.14 -
15 1 100.0
01.04.02.03 DEMOLICION DE BERMA CON IMPRIMANTE CON EQUIPO E=0.10M m2
4.81 ,614.67 0%
154.81 10.43 1,614.67 - -
DEMOLICION DE BERMA DE ADOGRASS DE CONCRETO CON 1 100.00
01.04.02.04 m2
EQUIPO 2.71 %
12.71 13.03 165.61 165.61 -
100.0
01.04.02.05 DEMOLICION DE PAVIMENTO FLEXIBLE CON EQUIPO E=0.05M m2
0%
3.22 11.58 37.29 - - 3.22 37.29

Informe Situacional 2019 de la Obra: “MEJORAMIENTO DE SERVICIO DE TRANSITABILIDAD PEATONAL Y VEHICULAR DE LA


ASOCIACIÓN DE VIVIENDA URB. VILLA MARÍA DEL TRIUNFO DE LA JUNTA VECINAL JESÚS MARÍA DE LA CIUDAD DE TACNA,
DISTRITO TACNA, PROVINCIA TACNA – TACNA

” Pág. 12
Gerencia de Ingeniería y Obras

DEMOLICION DE SARDINEL PERALTADO INCL CIMENTACION 100.00


01.04.02.06 m3
C/EQUIPO %
2.53 208.51 527.53 2.53 527.53 -
4 100.00
01.04.02.07 REMOCIÓN DE AREAS VERDES m2
2.51 %
42.51 1.20 51.01 51.01 -
10 2, 2 17.72
01.04.02.08 ACARREO DE MATERIAL EXCEDENTE HASTA 30M m3 82.28%
8.98 515.26 3.47 %
132.45 23.08 3,056.95 541.69
10 1, 2 17.72
01.04.02.09 ELIMINACION DE MATERIAL EXCEDENTE C/MAQUINARIA m3 82.28%
8.98 216.22 3.47 %
132.45 11.16 1,478.14 261.93

01.04.03 MOVIMIENTOS DE TIERRA


- - -
100.0
01.04.03.01 CORTE DE TERRENO MANUAL m3
0%
2.28 35.72 81.44 - - 2.28 81.44
23 1 100.0
01.04.03.02 CORTE DE TERRENO CON MAQUINARIA MATERIAL SUELTO m3
7.61 ,998.30 0%
237.61 8.41 1,998.30 - -
1,73 4 100.0
01.04.03.03 PERFILADO Y COMPACTADO DE SUBRASANTE m2
5.35 ,164.84 0%
1,735.35 2.40 4,164.84 - -
1,73 20 100.0
01.04.03.04 BASE GRANULAR E=0.20M C/MAQUINARIA m2
5.35 ,477.13 0%
1,735.35 11.80 20,477.13 - -
31 1 100.0
01.04.03.05 ACARREO DE MATERIAL EXCEDENTE CON MAQUINARIA m3
1.87 ,687.22 0%
311.87 5.41 1,687.22 - -
31 3 100.0
01.04.03.06 ELIMINACION DE MATERIAL EXCEDENTE m3
1.87 ,480.47 0%
311.87 11.16 3,480.47 - -

01.04.04 BERMA DE PAVIMENTO FLEXIBLE


- - -
1,72 10 100.0
01.04.04.01 IMPRIMACION CON ASFALTO DILUIDO m2
9.64 ,550.80 0%
1,729.64 6.10 10,550.80 - -
1,72 51 100.0
01.04.04.02 CARPETA ASFALTICA E=2" EN FRIO m2
9.64 ,802.72 0%
1,729.64 29.95 51,802.72 - -

01.04.05 BERMA DE CONCRETO


- - -
100.0
01.04.05.01 BERMA DE CONCRETO F'C=175 KG/CM2 m3
0%
1.14 406.51 463.42 - - 1.14 463.42

02 INFRAESTRUCTURA PEATONAL
- - -

02.01 TRABAJOS PRELIMINARES


- - -
2,88 4, 100.00
02.01.01 TRAZO DE NIVELES Y REPLANTEO m2
8.40 448.14 %
2,888.40 1.54 4,448.14 -
2,88 2, 100.00
02.01.02 CONTROL TOPOGRAFICO m2
8.40 281.84 %
2,888.40 0.79 2,281.84 -
1,18 1,70 59.05
02.01.03 LIMPIEZA PERMANENTE DURANTE OBRA m2 40.95%
2.80 5.60 %
2,888.40 0.15 433.26 177.42 255.84

02.02 DEMOLICIONES
- - - -
1,32 19, 100.00
02.02.01 DEMOLICION DE VEREDA DE CONCRETO C/EQUIPO E=0.10M m2
9.10 790.30 %
1,329.10 14.89 19,790.30 - -
7 1, 100.00
02.02.02 DEMOLICION DE BERMA DE CONCRETO CON EQUIPO E=0.15M m2
7.19 341.56 %
77.19 17.38 1,341.56 - -
4 100.00
02.02.03 DEMOLICION DE BERMA CON IMPRIMANTE CON EQUIPO E=0.10M m2
3.61 %
43.61 10.43 454.85 454.85 - -
2 100.00
02.02.04 DEMOLICION DE BERMA DE ADOGRASS DE CONCRETO CON EQUIPO m2
6.80 %
26.80 13.03 349.20 349.20 - -
10 1, 16 1 60.38
02.02.05 DEMOLICION DE PAVIMENTO FLEXIBLE CON EQUIPO E=0.05M m2 39.62%
8.17 252.61 4.87 ,909.19 %
273.04 11.58 3,161.80
100.00
02.02.06 DEMOLICION DE PAVIMENTO RIGIDO CON EQUIPO E=0.20M m2 0.00%
%
4.00 21.94 87.76 4.00 87.76 - -
3 100.0
02.02.07 DEMOLICION DE TAPA DE CONCRETO C/EQUIPO E=0.125M m2
1.78 0%
31.78 14.89 473.20 - - 473.20
DEMOLICION DE SARDINEL PERALTADO INCL CIMENTACION 100.00
02.02.08 m3
C/EQUIPO %
0.55 208.51 114.68 0.55 114.68 -
100.0
02.02.09 DEMOLICIÓN DE MURO DE ADOBE EN FORMA MANUAL m2
0%
0.98 27.86 27.30 - - 0.98 27.30
100.06
02.02.10 REMOCIÓN DE AREAS VERDES m2
%
5.88 1.20 7.06 5.88 7.06 -
16 3, 9 2 37.97
02.02.11 ACARREO DE MATERIAL EXCEDENTE HASTA 30M m3 62.03%
1.95 737.85 9.12 ,287.64 %
261.07 23.08 6,025.50
16 1, 9 1 37.97
02.02.12 ELIMINACION DE MATERIAL EXCEDENTE C/MAQUINARIA m3 62.03%
1.95 807.38 9.12 ,106.16 %
261.07 11.16 2,913.54

02.03 MOVIMIENTOS DE TIERRA


- - -
42 15, 13 4 24.74
02.03.01 CORTE DE TERRENO MANUAL m3 75.26%
4.41 159.93 9.54 ,984.37 %
563.95 35.72 20,144.29
1,99 8, 82 3 29.29
02.03.02 NIVELACION Y COMPACTADO DE SUB RASANTE CON EQUIPO m2 70.71%
3.72 353.69 6.04 ,461.11 %
2,819.76 4.19 11,814.79
12 4, 3 1 23.29
02.03.03 EXCAVACIÓN DE ZANJA MANUAL P/SARDINEL SUMERGIDO m3 76.71%
1.20 694.03 6.80 ,425.31 %
158.00 38.73 6,119.34
1,99 25, 82 10 29.29
02.03.04 TERRAPLEN PARA VEREDAS E=0.10 M m2 70.71%
3.72 579.43 6.04 ,598.09 %
2,819.76 12.83 36,177.52

Informe Situacional 2019 de la Obra: “MEJORAMIENTO DE SERVICIO DE TRANSITABILIDAD PEATONAL Y VEHICULAR DE LA


ASOCIACIÓN DE VIVIENDA URB. VILLA MARÍA DEL TRIUNFO DE LA JUNTA VECINAL JESÚS MARÍA DE LA CIUDAD DE TACNA,
DISTRITO TACNA, PROVINCIA TACNA – TACNA

” Pág. 13
Gerencia de Ingeniería y Obras

70 16, 22 5 24.43
02.03.05 ACARREO DE MATERIAL EXCEDENTE HASTA 30M m3 75.57%
9.29 370.34 9.25 ,291.16 %
938.54 23.08 21,661.50
70 7, 22 2 24.43
02.03.06 ELIMINACION DE MATERIAL EXCEDENTE m3 75.57%
9.29 915.64 9.25 ,558.46 %
938.54 11.16 10,474.11

02.04 OBRAS DE CONCRETO SIMPLE


- - -
11 47, 4 16 25.58
02.04.01 SARDINEL SUMERGIDO: CONCRETO F'C=175 KG/CM2 m3 74.42%
7.17 632.00 0.27 ,368.93 %
157.44 406.51 64,000.93
55 39, 27 19 33.11
02.04.02 ENCOFRADO Y DESENCOFRADO CARAVISTA m2 66.89%
0.66 097.19 2.56 ,351.43 %
823.22 71.00 58,448.62
VEREDA DE PIEDRA LAVADA Y CEMENTO PULIDO S/DISEÑO F'C=175 1,49 104, 59 41 28.42
02.04.03 m2 71.58%
KG/CM2 E=4" 1.13 125.35 2.04 ,342.41 %
2,083.17 69.83 145,467.76
VEREDA DE PIEDRA LAVADA COLOREADA Y CEMENTO PULIDO 17 13 100.0
02.04.04 m2 0.00%
S/DISEÑO F'C=175 KG/CM2 E=4" 5.44 ,393.09 0%
175.44 76.34 13,393.09 - -
MARTILLO DE PIEDRA LAVADA Y CEMENTO PULIDO S/DISEÑO 15 11, 39 27 71.13
02.04.05 m2 28.87%
F'C=175 KG/CM2 E=4" 9.69 151.37 3.53 ,479.98 %
553.22 69.83 38,631.35
RAMPA ACABADO SEMIPULIDO Y BRUÑADO CONCRETO F'C=175 7 5 98.28
02.04.06 m2 1.72%
KG/CM2 S=30% 5.24 ,187.80 %
76.56 68.95 5,278.81 1.32 91.01

02.05 VARIOS
- - -
95 7 100.0
02.05.01 JUNTAS DE DILATACION DE 1" RELLENAS CON MEZCLA ASFALTICA m
0.73 ,891.06 0%
950.73 8.30 7,891.06 - -
1,84 5, 1,04 3 36.27
02.05.02 CURADO DE CONCRETO CON ADITIVO m2 63.73%
0.84 430.47 7.56 ,090.31 %
2,888.40 2.95 8,520.78
REUBICACION Y REPOSICION DE CAJA Y TAPA DE AGUA 2 2, 100.00
02.05.03 und 0.00%
EXISTENTES 2.00 194.28 %
22.00 99.74 2,194.28 - -
REUBICACION Y/O REPOSICION DE CAJA Y TAPA DE REGISTRO DE 4 5, 100.00
02.05.04 und 0.00%
DESAGUE EXISTENTES 0.00 424.00 %
40.00 135.60 5,424.00 - -

03 SEÑALIZACION Y OBRAS COMPLEMENTARIAS


- - -

03.01 SEÑALIZACION VEHICULAR


- - -

03.01.01 SEÑALIZACION HORIZONTAL


- - -
22 1 100.0
03.01.01.01 PINTADO LINEAL INTERMITENTE CENTRAL E=0.10M. m
8.00 ,010.04 0%
228.00 4.43 1,010.04 - -
1,96 8 100.0
03.01.01.02 PINTADO LINEAL CONTINUO LATERAL E=0.10M. m
3.40 ,697.86 0%
1,963.40 4.43 8,697.86 - -
PINTADO DE BORDE DE VEREDAS CON PINTURA TRAFICO COLOR 10 1 100.0
03.01.01.03 m2
AMARILLO 8.94 ,966.37 0%
108.94 18.05 1,966.37 - -
PINTADO DE BORDE DE VEREDAS CON PINTURA TRAFICO COLOR 9 1 100.0
03.01.01.04 m2
AZUL 2.29 ,665.83 0%
92.29 18.05 1,665.83 - -
45 15 100.0
03.01.01.05 PINTADO DE SEÑALIZACION EN EL PAVIMENTO m2
4.25 ,603.49 0%
454.25 34.35 15,603.49 - -

03.01.02 SEÑALIZACION VERTICAL


- - -
100.0
03.01.02.01 RETIRO DESEÑALIZACION VERTICAL EXISTENTE und
0%
9.00 73.23 659.07 - - 9.00 659.07
100.0
03.01.02.02 REUBICACION DE LETRERO EXISTENTE und
0%
1.00 146.45 146.45 - - 1.00 146.45
100.0
03.01.02.03 EXCAVACION DE ZANJA MANUAL EN TERRENO NORMAL m3
0%
4.69 38.73 181.64 - - 4.69 181.64
100.0
03.01.02.04 ACARREO DE MATERIAL EXCEDENTE HASTA 30M m3
0%
6.09 23.08 140.56 - - 6.09 140.56
100.0
03.01.02.05 ELIMINACION DE MATERIAL EXCEDENTE m3
0%
6.09 11.16 67.96 - - 6.09 67.96
2 15 100.0
03.01.02.06 SUMINISTRO E INSTALACION DE SEÑALIZACION VERTICAL und
8.00 ,028.72 0%
28.00 536.74 15,028.72 - -
1 4 100.0
03.01.02.07 SUMINISTRO E INSTALACION DE BOLARDOS und
6.00 ,219.84 0%
16.00 263.74 4,219.84 - -

03.02 OBRAS COMPLEMENTARIAS


- - -

03.02.01 JARDINERAS Y SARDINELES


- - -

03.02.01.01 DEMOLICIONES Y DESMONTAJES


- - -

DEMOLICION DE SARDINEL PERALTADO INCL CIMENTACION 100.0


m3
03.02.01.01.0 C/EQUIPO 0%
0.98 208.51 204.34 - - 0.98 204.34
1

100.0
RETIRO DE ARBOLES EXISTENTES und
03.02.01.01.0 0%
2.00 26.50 53.00 - - 2.00 53.00
2

100.0
ACARREO DE MATERIAL EXCEDENTE HASTA 30M m3
03.02.01.01.0 0%
1.27 23.08 29.31 - - 1.27 29.31
3

100.0
ELIMINACION DE MATERIAL EXCEDENTE m3
03.02.01.01.0 0%
1.27 11.16 14.17 - - 1.27 14.17
4

03.02.01.02 MOVIMIENTO DE TIERRAS


- - -

Informe Situacional 2019 de la Obra: “MEJORAMIENTO DE SERVICIO DE TRANSITABILIDAD PEATONAL Y VEHICULAR DE LA


ASOCIACIÓN DE VIVIENDA URB. VILLA MARÍA DEL TRIUNFO DE LA JUNTA VECINAL JESÚS MARÍA DE LA CIUDAD DE TACNA,
DISTRITO TACNA, PROVINCIA TACNA – TACNA

” Pág. 14
Gerencia de Ingeniería y Obras

2 1 100.0
EXCAVACIÓN DE ZANJA MANUAL P/SARDINEL SUMERGIDO m3
03.02.01.02.0 9.75 ,152.22 0%
29.75 38.73 1,152.22 - -
1

3 100.0
ACARREO DE MATERIAL EXCEDENTE HASTA 30M m3
03.02.01.02.0 8.67 0%
38.67 23.08 892.50 - - 892.50
2

3 100.0
ELIMINACION DE MATERIAL EXCEDENTE m3
03.02.01.02.0 8.67 0%
38.67 11.16 431.56 - - 431.56
3

03.02.01.03 OBRAS DE CONCRETO


- - -

1 6 100.0
SARDINEL CONCRETO F'C=175 KG/CM2 m3
03.02.01.03.0 6.12 ,552.94 0%
16.12 406.51 6,552.94 - -
1

18 13 100.0
SARDINEL ENCOFRADO Y DESENCOFRADO CARAVISTA m2
03.02.01.03.0 3.56 ,032.76 0%
183.56 71.00 13,032.76 - -
2

57 3 100.0
SARDINEL ACERO DE REFUERZO FY=4200 KG/CM2 GRADO 60 kg
03.02.01.03.0 3.22 ,187.10 0%
573.22 5.56 3,187.10 - -
3

03.02.01.04 VARIOS
- - -

21 100.0
CURADO DE CONCRETO CON ADITIVO m2
03.02.01.04.0 2.49 0%
212.49 2.95 626.85 - - 626.85
1

11 100.0
SOLAQUEADO DE JARDINERAS m2
03.02.01.04.0 6.42 0%
116.42 5.85 681.06 - - 681.06
2

9 1 100.0
IMPERMEAB. DE CONCRETO CON ASFALTO LIQUIDO m2
03.02.01.04.0 6.08 ,120.29 0%
96.08 11.66 1,120.29 - -
3

11 1 100.0
PINTADO C/PINTURA ESMALTE EN JARDINERAS m2
03.02.01.04.0 6.42 ,897.65 0%
116.42 16.30 1,897.65 - -
4

03.02.01.05 AREAS VERDES


- - -

16 100.0
MULLIDO DE CAMPO m2
03.02.01.05.0 4.22 0%
164.22 2.92 479.52 - - 479.52
1

16 6 100.0
SUM. E INSTALACION DE TIERRA DE CHACRA H=50CM m2
03.02.01.05.0 4.22 ,572.08 0%
164.22 40.02 6,572.08 - -
2

16 4 100.0
SUM. E INSTALACION DE CESPED m2
03.02.01.05.0 4.22 ,598.16 0%
164.22 28.00 4,598.16 - -
3

2 1 100.0
SUM. Y PLANTADO DE ARBOL TIPO MOLLE HAWAIANO und
03.02.01.05.0 9.00 ,481.03 0%
29.00 51.07 1,481.03 - -
4

03.02.02 MOBILIARIO
- - -
100.0
03.02.02.01 RETIRO DE BASUREROS EXISTENTES und
0%
3.00 66.26 198.78 - - 3.00 198.78
2 100.0
03.02.02.02 SUMINISTRO E INSTALACION DE BASURERO SEGÚN DISEÑO und
,250.00 0%
3.00 750.00 2,250.00 - - 3.00

03.02.03 REUBICACION DE POSTES


- - -
1 13, 100.00
03.02.03.01 REUBICACION DE POSTES EXISTENTES und 0.00%
3.00 364.00 %
13.00 1,028.00 13,364.00 - -

04 MITIGACION DE IMPACTO AMBIENTAL


- - -
2,88 1, 3,16 1 52.30
04.01 RIEGO EN ZONA DE TRABAJO m2 47.70%
8.40 559.74 7.54 ,710.47 %
6,055.94 0.54 3,270.21
87 2, 2,39 7 73.33
04.02 ACONDICIONAMIENTO DE MATERIAL EXCEDENTE EN BOTADEROS m3 26.67%
1.24 709.55 5.93 ,451.35 %
3,267.17 3.11 10,160.90
419,61 519,6
COSTO DIRECTO
0.69 11.21
939,221.90
62,94 77,9
GASTOS GENERALES (15%)
1.60 41.68
140,883.29

482,55 597,55
PRESUPUESTO TOTAL DE LA OBRA
1,080,105. 2.29 2.89
19

PORCENTAJE % 100.00% 44.68% 55.32%

3.21 Resumen de Avance Físico


La valorización física acumulada de avance de obra, fue determinada a partir del resumen de
metrados de cada mes (Noviembre y Diciembre) del cuaderno de obra, la verificación de

Informe Situacional 2019 de la Obra: “MEJORAMIENTO DE SERVICIO DE TRANSITABILIDAD PEATONAL Y VEHICULAR DE LA


ASOCIACIÓN DE VIVIENDA URB. VILLA MARÍA DEL TRIUNFO DE LA JUNTA VECINAL JESÚS MARÍA DE LA CIUDAD DE TACNA,
DISTRITO TACNA, PROVINCIA TACNA – TACNA

” Pág. 15
Gerencia de Ingeniería y Obras

campo y replanteo de trabajos realizados queda pendiente. Alcanzando un total acumulado


según se muestra en el siguiente cuadro:

3.22 Gasto a Nivel de Recursos Empleados


Montos en moneda nacional (Soles) gastados desde el inicio de obra el 19 de Noviembre del
2018 hasta el 31 de diciembre del 2018 fecha en la que fue paralizada la obra por cambio de
gestión municipal debido a las elecciones municipales y regionales del año 2018.
a) Total gastos por recursos empleados

Fuente: Según los saldo del control visible de almacén (kardex) v/s reporte de adquisiciones del año 2018. Así mismo en
cuando a la valorización de maquinaria pesada y liviana de horas efectivas trabajadas, se ha realizado el procesamiento
del cuaderno de obra, del cual se determinó que no existe registrado en el cuaderno de obra, el alquiler del uso de la
camioneta, más si existe informe de conformidad de la misma.

3.23 Gasto Financiero de Obra (Según Reporte Siaf – Nivel de Devengado)


Montos en moneda nacional (Soles) por periodos de ejecución de acuerdo a los reportes Siaf a
nivel de devengado.

a) Gasto Financiero de obra Acumulado según las especificas

Informe Situacional 2019 de la Obra: “MEJORAMIENTO DE SERVICIO DE TRANSITABILIDAD PEATONAL Y VEHICULAR DE LA


ASOCIACIÓN DE VIVIENDA URB. VILLA MARÍA DEL TRIUNFO DE LA JUNTA VECINAL JESÚS MARÍA DE LA CIUDAD DE TACNA,
DISTRITO TACNA, PROVINCIA TACNA – TACNA

” Pág. 16
Gerencia de Ingeniería y Obras

Fuente: Reporte de sistema Siaf (Devengado Vs Marco Presupuestal -2018)

3.24 Comparativo Entre Avance Físico Vs Avance Programado del Plan de Trabajo 2018
El avance programado acumulado para a presenta tabla considera la programación
acumulada hasta el 31 de diciembre del 2018 y su ejecución física acumulada de
acuerdo al plan de trabajo aprobado 2018.

Se aprecia un desfase de -208,467.14 soles, reflejados en un -30.17 % de retraso


respecto a lo programado correspondientes al periodo de ejecución del año 2018.
3.25 Comparativo Entre Avance Físico y Gasto a Nivel de Recursos Empleados

Se aprecia un desbalance financiero de -85, 809.88 soles, reflejados en un -12.42 % de


perdida.
D. MODIFICACIONES PRESUPUESTALES
3.26 Deductivos de Obra
“No se tiene modificaciones”

3.27 Adicionales de Obra


“No se tiene modificaciones”

E. MODIFICACIONES AL PLAZO DE EJECUCION

Informe Situacional 2019 de la Obra: “MEJORAMIENTO DE SERVICIO DE TRANSITABILIDAD PEATONAL Y VEHICULAR DE LA


ASOCIACIÓN DE VIVIENDA URB. VILLA MARÍA DEL TRIUNFO DE LA JUNTA VECINAL JESÚS MARÍA DE LA CIUDAD DE TACNA,
DISTRITO TACNA, PROVINCIA TACNA – TACNA

” Pág. 17
Gerencia de Ingeniería y Obras

Para verificar si se registran modificaciones al plazo de ejecución se realizó una búsqueda


en el banco de proyectos mediante código SNIP 309903 correspondiente a la obra.
3.28 Ampliaciones de Plazo
“No presenta según verificación en el banco de proyectos a la fecha 02/01/2019”

3.29 Plazo Actualizado de Obra


Debido a que no se registra modificaciones al plazo de ejecución, El plazo actualizado
de la obra continúa con 105 días calendarios
3.30 Plazo Ejecutado de Obra

Fecha de Inicio Fecha Fin Días Calen. Documento Ref.


19/11/2018 03/03/2019 105 Cuaderno de Obra y resolución del expediente técnico

3.31 Saldo de Plazo por ejecutar


El saldo del plazo por ejecutar se contempla en días calendarios

Plazo aprobado Plazo Ejecutado Saldo de plazo por ejecutar


105 43 62

F. MODIFICACIONES AL CRONOGRAMA DE EJECUCION


3.1 Cronogramas Acelerados de Reprogramación de Obra
“No hubo hallazgo en el acervo documentario”

G. ALMACEN DE OBRA

3.2 Reporte de bienes y materiales Adquiridos


“Según Documentos de la Transferencia -Anexo N°6.2”

3.3 Inventario Actual de existencias en el Almacén de Obra


“Según Documentos de la Transferencia- Anexo N°6.2”

3.4 Tarjetas de Control Visible (Kardex)


 No se tiene el kardex visible de Gasolina 90 Oct. y Bloqueador
 Según las Observaciones Adicionales del residente de obra, adjuntadas en el documento de
la trasferencia aclara lo siguiente :

 Según la orden de compra N°3479 (petróleo) total de compra 170 galones,


quedando un saldo de 80 por atender por parte del proveedor (Estación de
servicio centenario).

 El saldo de combustible (gasolina 90 oct.) de 80 galones, queda custodiado en


el grifo de la municipalidad provincial de Tacna.

3.5 Reporte Total de Bienes existentes

“Según Documentos de la Transferencia- Anexo N°6.2”

Informe Situacional 2019 de la Obra: “MEJORAMIENTO DE SERVICIO DE TRANSITABILIDAD PEATONAL Y VEHICULAR DE LA


ASOCIACIÓN DE VIVIENDA URB. VILLA MARÍA DEL TRIUNFO DE LA JUNTA VECINAL JESÚS MARÍA DE LA CIUDAD DE TACNA,
DISTRITO TACNA, PROVINCIA TACNA – TACNA

” Pág. 18
Gerencia de Ingeniería y Obras

H. LIMITACIONES Y OBSERVACIONES
 Documentación Técnica
La documentación técnica entregada en la transferencia, se encuentra incompleto ya que no existe
el expediente técnico Original y los planos del expediente técnico para la ejecución de la obra,
asimismo falta los informes mensuales del mes de Noviembre y Diciembre del 2018, no existe
informe de control de calidad, el cuaderno de obra Tomo I se encuentra Incompleto, la cual limita la
claridad del manejo administrativo y control de obra.
 Acervo Documentario
El acervo documentario entregada en la trasferencia se encuentra desordenado e incompleto en
cuando a los informes faltan INFORMES N°38.N°36,N°33,N°28,N°25,N°19,N°18,N°17,N°16,N°12 ,
por lo cual no se puede tener claro el manejo de la documentación y seguimiento de la obra.

 Avance físico
 La valorización física acumulada de avance de obra, fue determinada a partir del resumen de
metrados de cada mes (Noviembre y Diciembre) del cuaderno de obra, la verificación de campo
y replanteo de trabajos realizados queda pendiente. Alcanzando un total acumulado según se
muestra en el siguiente cuadro:

Resumen de Valorización Física Acumulada

 Gasto a Nivel de Recursos Empleados

Este reporte incluye las compras y servicios generados gastados desde el inicio de obra el 19 de
Noviembre del 2018 hasta el 31 de diciembre del 2018 fecha en la que fue paralizada la obra por
cambio de gestión municipal debido a las elecciones municipales y regionales del año 2018

Resumen de Gasto a Nivel de Recursos Empleados

Informe Situacional 2019 de la Obra: “MEJORAMIENTO DE SERVICIO DE TRANSITABILIDAD PEATONAL Y VEHICULAR DE LA


ASOCIACIÓN DE VIVIENDA URB. VILLA MARÍA DEL TRIUNFO DE LA JUNTA VECINAL JESÚS MARÍA DE LA CIUDAD DE TACNA,
DISTRITO TACNA, PROVINCIA TACNA – TACNA

” Pág. 19
Gerencia de Ingeniería y Obras

 Gasto Financiero (Reportes Siaf)

Este reporte incluye las compras y servicios generados mediante cuadros de necesidades.
 El avance financiero acumulado de obra (CD+GG) a nivel devengado al año 2018 es de S/.
603,846.84 que representa un porcentaje de 55.91 %, teniendo como saldo financiero de S/.
476,258.35 que representa un porcentaje de 44.09 %. Estos gastos fueron realizados en el año
2018.

 Otros
 El residente saliente realizo el pedido de la compra de mezcla de asfalto en frio,
según cuadro de necesidad N°5163 con fecha 17/10/2018 por un monto de
S/74,700.00 la cual es un proceso de contratación que requiere un promedio de
40 días calendarios para la firma de contrato, dicha compra no procedió.
Para el año 2019 es necesario realizar nuevamente el pedido y la compra del
dicho insumo, para el asfaltado de las calles y bermas programadas en el
expediente técnico, el proceso de selección el cual incrementara el plazo
de ejecución física de la obra (requerida ampliación de plazo), ya que se
debió realizarse la compra en el año 2018 para no afectar el plazo físico de la
obra.

I. PANEL FOTOGRAFICO
“Ver Anexo Nº 6.1”
4. CONCLUSIONES

 Mediante Memorándum R.G.M 203-2018, con fecha 10 de Octubre del 2018 se designa como
residente de la obra “MEJORAMIENTO DE SERVICIO DE TRANSITABILIDAD PEATONAL Y
VEHICULAR DE LA ASOCIACIÓN DE VIVIENDA URB. VILLA MARÍA DEL TRIUNFO DE LA JUNTA
VECINAL JESÚS MARÍA DE LA CIUDAD DE TACNA, DISTRITO TACNA, PROVINCIA TACNA – TACNA”
al Ing. Andres Eduardo del Campo Vera
 Asimismo, se indica que esta residencia no se responsabiliza de las acciones ocurridas antes de la
designación de mi persona como residente de la obra descrita, para el cual se elabora el
presente estado situacional de la obra a la actualidad.

Informe Situacional 2019 de la Obra: “MEJORAMIENTO DE SERVICIO DE TRANSITABILIDAD PEATONAL Y VEHICULAR DE LA


ASOCIACIÓN DE VIVIENDA URB. VILLA MARÍA DEL TRIUNFO DE LA JUNTA VECINAL JESÚS MARÍA DE LA CIUDAD DE TACNA,
DISTRITO TACNA, PROVINCIA TACNA – TACNA

” Pág. 20
Gerencia de Ingeniería y Obras

 El inicio de obra se dio el 19/11/2018 con un plazo de ejecución de 105 días calendarios, con un
plazo ejecutado de 43 días calendarios, plazo por ejecutar de 62 días calendarios, Debiéndose
culminar la obra el 03 de Marzo del 2019.
 A la fecha la obra no presenta modificaciones presupuestales ni ampliación de plazo.
 No se tiene las guías de salida de materiales y bienes de almacén central.
 El avance físico acumulado determinado a partir del resúmenes de asentadas en el cuaderno de
obra Tomo I, que corresponden a la ejecución física desarrollada el año 2018 (CD+GG) tiene una
valorización de S/482,552.29, que representa un porcentaje de 44.68%, teniendo un saldo físico
de S/. 597,552.89 que representa un porcentaje de 55.32%. faltante por ejecutar.
 El avance de Gasto Financiero acumulado de obra (CD+GG) a nivel Devengado al año 2018 es de
S/. 603,846.84 que representa un porcentaje de 55.91 %, teniendo como saldo financiero de S/.
476,258.35 que representa un porcentaje de 44.09 %. Estos gastos fueron realizados en el año
2018.

 No se cuenta con la totalidad de la documentación técnica y acervo documentario para


determinar con precisión el manejo y control de obra por lo cual se ha elaborado el presente
informe en base a un cruce de información entre los documentos encontrados en obra y el área
de contabilidad, para lo cual esta residencia realiza la consolidación y comparación de los saldos
de materiales encontrados en obra y el control visible del almacenen de la obra (Kardex) e
informe de conformidades vs total de bienes y materiales adquiridos por la obra (reporte Siaf.),
llegando así a determinar los recursos realmente empleados.
 El avance financiero acumulado de obra (CD+GG) a nivel recursos utilizados al diciembre del
2018 es de S/. 568,362.17 que representa un porcentaje de 52.62 %, teniendo como saldo
financiero de recursos es de S/. 511,743.02 que representa un porcentaje de 47.38 %. Estos
recursos fueron empleados en el año 2018.

 Del Comparativo entre avance físico vs gasto a nivel recursos utilizados, se puede apreciar que
existe mayor uso de recursos que el avance físico acumulado, se puede indicar que existe una
pérdida de S/. -85,809.88 que representa un porcentaje de -12.42% de desbalance financiero.

 Se aprecia un desfase de -208,467.14 soles, reflejados en un -30.17 % de retraso respecto a lo


programado correspondientes al periodo de ejecución del año 2018.

Informe Situacional 2019 de la Obra: “MEJORAMIENTO DE SERVICIO DE TRANSITABILIDAD PEATONAL Y VEHICULAR DE LA


ASOCIACIÓN DE VIVIENDA URB. VILLA MARÍA DEL TRIUNFO DE LA JUNTA VECINAL JESÚS MARÍA DE LA CIUDAD DE TACNA,
DISTRITO TACNA, PROVINCIA TACNA – TACNA

” Pág. 21
Gerencia de Ingeniería y Obras

5. RECOMENDACIONES
 Se recomienda notificar y requerir al Ing. Andres Eduardo del Campo Vera, para la entrega de las
actas de entrega de terreno y acta de inicio de obra que no se encuentra pegado en el cuaderno
de obra.

 Al no encontrarse una buena relación entre el saldo físico y financiero, esta residencia solicita
opinión técnica del área de supervisión a fin tomar acciones respecto a las pérdidas económicas.

 Se recomiendas realizar la asignación presupuestal del año fiscal 2019 de manera oportuna ,
para realizar el pedido de la compra de mezcla de asfalto en frio, ya que es un proceso de
selección el cual afectara en el plazo de ejecución física de la obra (requerida ampliación de
plazo),
6. ANEXOS

6.1 Panel Fotográfico.


6.2 Copia Simple de la documentación de la transferencia.
6.3 Reporte de sistema Siaf (Devengado Vs Marco Presupuestal -2018)

Informe Situacional 2019 de la Obra: “MEJORAMIENTO DE SERVICIO DE TRANSITABILIDAD PEATONAL Y VEHICULAR DE LA


ASOCIACIÓN DE VIVIENDA URB. VILLA MARÍA DEL TRIUNFO DE LA JUNTA VECINAL JESÚS MARÍA DE LA CIUDAD DE TACNA,
DISTRITO TACNA, PROVINCIA TACNA – TACNA

” Pág. 22