Daily Labour Report

Site : Ansal Town Date :


Sr. No Work Description Maison Labour Blacksmith Shuttering Others
Fitter Helper Carpenter Helper
1 steel cutting for retaining wall vertical 1 1
2 column placing on foundation 2 2
3 Basement raft binding 2 2
4 column plumb 1
5 column vertical & ring shifting 0 3
6 cover block fixing & cleaning 2
7
8

Total 1 2 5 8 0 0 0
Today's Plan as per schedule : Pouring of foundation
Today Running Activity : column placing on Raft area & Isolated footing
Remarks : Casting of Isolated footings & Basement raft will be start tomorrow from 11 am.
6/9/2019
Total
Manpower

2
4
4
1
3
2
0
0
0
0
0
0
0
0
0
0
0
0
16