Sl.No Site Name Tower Qty Coils Supply Status Chiller Commissioning Status.

Tower B
1.290 TR 2 1)Coils delivered and replaced for all the three chillers. 1)290 & 204 TR both chillers commissioning has been completed.
2.204 TR 1

1 RMZ Infinity Tower D


1
1.204 TR 1
1)204 tr chiller coils has been delivered and replaced. 1.204 tr ideal gas charge has been done, gas topup need to be done.
2.290 TR 2. 290 tr chiller coils yet to received. 2. Pending due to non availability of coils.
1
Tower E 1)Circuit coils reveived and replaced the same, circuit 2 coils pending. 1. Circuit 1 commissioning has been done, circuit 2 work pending due to non
1. 290 TR availability of coils.

Tower 1B
1.204 TR 2 1. 1B coils delivered. 1.Chiller 1 coil replaced, commissioning under progress. Chiller 2 need to start
2 RMZ Ecospace
2
Tower 1A 1.Chiller 1 coils received and chiller 2 coils pendinng 2.Chiller 1 coil replacement under progress , chiller 2 need to start.
1.290 TR
Tower 1A 2 1)Chiller1 coils received and replaced 1) Chiller 1 commissioning has been done. Chiller 2 pending.
1.204 TR 2)Chiller 2 - 3nos RH coils pending.

Tower 1B 2 1)Both chiller coils are received , and replaced in Chiller1, chiller 2 need start. 2)Chiller 1 commissioning has been done. Chiller 2 need to start.
1.204 TR
2
Tower 2A 1)Both chiller coils are received , and replaced in Chiller1 both circuits and in chiller 3)Chiller 1 both circuits and chiller 2 circuit has been commissioned. Chiller 2
1.290 TR 2 circuit 2 also completed, chiller 2 circuit 1 need start the coil replacement circuit 1 need to start.
3 RMZ NXT

Tower 2B 2
1.204 TR 1)Chiller 1 coils received and replaced. chiller 2 coils are pending 4)Chiller 1 commissioning has been completed, and chiller 2 pending due to
non availability of coils.
Tower 2C 2
1.204 TR 1)Both chiller coils are received, and chiller 1 coils replaced. chiller 2 work pending. 5)Chiller 1 commisisoning completed, chiller 2 need to start.

Tower B 3 1)All the three chiller circuits 2 coils receieved and replaced. Circuit 1 coils pending 1)All the three chillers circuit 2 has been commissioned and circuit 1 pending
1.247 TR for all the three chillers. due to non availability of coils.

2
Tower D 2)Both chiller coils are delivered and replaced. 2) Both chillers commissioning has been completed.
4 RMZ Centennial
1.290 TR

2
Tower C 3)Both chillers coils delivered. Chiller 1 circuit 2 and chiller 2 circuit 2 coils 3) Chiller 1 circuit 2 commissioning has been completed, rest of the circuits
1.247 TR replaced. coils to be replaced and commissioning to be done.