PROJECT : CONSTRUCTION OF NOLCOM COMMAND CENTER BUILDING

LOCATION: CAMP S. AQUINO, TARLAC CITY


SUBJECT : WEEKLY REPORT

DATE ACTIVITIES REMARKS

April 2-7, 2018 1. Courtesy call to Nolcom official in preparation for


mobilization on the proposed construction of Nolcom 100%
Command Center
2. Mobilization of key personnel, procurement of materials 100%
3. Staking, layout of the proposed 50%
building and fencing
4. Construction of temporary 25%
facilities and barracks

April 9-14, 2018 1. Continue const. of temporary facilities 50%


2. Procurement of materials 10%
3. Changed site layout so as not to hit the power lines 50%

April 16-21, 2018 1. Continue staking and layout of the proposed building 100%
2. Continue construction of temporary facilities 100%
3. Procurement of materials 12%
4. Excavation of foundation footings 5%

April 23-28, 2018 1. Cutting of occupied trees inside proposed building 85%
2. Procurement of equipment and materials 15%
3. Excavation works 7.5%

April 30-May 05, 1. Procurement of equipment and materials


2018
20%
2. Fabrication and installation of reinforcing steel for footings
5%
and columns
3. Mobilization and use of backhoe for excavation works 15%
May 07 – May 12, 1. Procurement of equipment and materials
2018
22%
2. Excavation of foundation footings (Communication Center) 70%
3. Excavation of footings (powerhouse) 66%
4. Installation of Temporary Perimeter Fence 10%
5. Realignment of the existing pipeline crossing the
20%
communication center building
6. Fabrication of Steel Reinforcements 7%
May 13-May 19, 1. Procurement of equipment and materials
2018
35%
2. Excavation of foundation footings (Communication Center) 85%
3. Excavation of footings (powerhouse) 75%
4. Installation of Temporary Perimeter Fence 100%
5. Realignment of the existing pipeline crossing the
100%
communication center building
6. Fabrication and installation of reinforcing steel for footings 8%
and columns
7. Construction of Field Office 40%
May 20 – May 1. Procurement of equipment and materials
40%
26, 2018
2. Excavation of foundation footings (Communication center) 95%
3. Excavation of footings (powerhouse) 75%
4. Fabrication and installation of RSB for footings and columns 40%
5. Formworks for footings 40%
6. Construction of Field office 85%
May 27 – June 1. Procurement of equipment and materials
45%
02, 2018
2. Excavation of foundation footings (Communication center) 100%
3. Fabrication and installation of RSB for footings and columns 76%
4. Formworks for footings 50%
5. Construction of Field office 95%
6. Fabrication and installation of shear wall rebars 20%
7. Excavation of tower footings 100%
8. Excavation of perimeter fence footings 50%
June 03 – June 1. Procurement of equipment and materials
41%
09, 2018
2. Excavation of foundation footings (Communication center) 100%
3. Fabrication and installation of RSB for footings and columns 85%
4. Formworks for footings 65%
5. Fabrication and installation of shear wall rebars 50%
6. Excavation of perimeter fence footings 60%
7. Concrete pouring at comm center building footings 20%
8. Installation of forms for shear wall 15%
June 10 – 16, 1. Procurement of equipment and materials
50%
2018
2. Fabrication and installation of RSB for footings and columns 100%
3. Formworks for footings 100%
4. Fabrication and installation of shear wall rebars 85%
5. Concrete pouring at comm center building footings 90%
June 17-23, 1. Procurement of equipment and materials
55%
2018
2. Fabrication and installation of RSB for Genset rom footings. 100%
3. Fabrication and installation of shear wall rebars 85%
4. Concrete pouring at comm center building footings 100%
5. Installation of footing rebars for perimeter fence 15%
June 24 – June 1. Procurement of equipment and materials
60%
30, 2018
2. Fabrication and installation of RSB for Genset Room columns 100%
3. Concrete Pouring at the columnfooting and wall footing of
100%
Genset Room
4. Concrete Pouring at the columns of Genset room 100%
5. Installation of footing rebars for perimeter fence footings 40%
6. Concrete pouring at the Perimeter fence footings 40%
7. Fabrication and installation of tie beam rebars 20%
July 01 – 07, 1. Procurement of equipment and materials
65%
2018
2. Concrete pouring at comm. Center building shearwall 35%
3. Concrete Pouring at comm. Center tie beams 50%
4. Concrete pouring at coom. Center interior columns 33%
5. CHB laying at Perimter fence 20%
6. CHB laying at GenSet Room Wall 20%
7. Installation of forms at Shearwall 60%
July 08 – 14, 1. Procurement of equipment and materials
70%
2018
2. Concrete pouring at tie beams 90%
3. Concrete pouring at shearwall 48%
4. Concrete pouring at building columns 77%
5. CHB laying at perimeter fence 20%
July 15 – 21, 1. Procurementvof equipment and materials
72%
2018
2. Concrete pouring at shearwall 54%
3. Concrete pouring at comm. tower footings 96%
July 22 – 28, 1. Procurement of equipment and materials
72%
2018
2. Concrete Pouring at shearwall 69%
3. Formworks at shearwall 65%
4. Masonry Works at Perimeter Fence 40%
July 29 – Aug. 1. Procurement of equipment and materials
73%
04, 2018
2. Concrete pouring at shearwall 78%
3. Formworks at shearwall 85%
4. Masonry works at Perimeter Fence 45%
Aug. 05 – Aug 1. Procurement of equipment and materials
73%
11, 2018
2. Concrete pouring at shearwall 83%
3. Masonry Works at Perimeter Fence 45%
4. Backfilling Works at Comm. center building 10%
Aug. 12 – Aug. 1. Procurement of materials and equipments.
73%
18, 2018
2. Concrete pouring at shearwall 100%
3. Backfilling works at comm. center building 20%
Aug. 19 – Aug. 1. Procurement of equipment and materials
74%
25, 2018
2. Backfilling Works at Comm. Center building 30%
3. Masonry Works (plastering) at the shearwall exterior 90%
Aug. 26 – Sep. 1. Procurement of equipment and materials
75%
01, 2-18
2. Backfilling works inside the Comm. Center building 35%
3. Sanitary Works inside the building 10%
Sep. 02 – Sep. 1. Procurement of Equipment and materials
75%
08, 2018
2. Backfilling works inside Comm. center building 45%
3. Plastering of Perimeter fence 50%
Sep. 09 – Sep. 1. Fabrication and installation of rebars for communication
45%
15, 2018 center roof beams
2. Backfilling works inside the comm. center building 70%
3. Formworks for comm. center roof beams 10%
Sep. 16 – Sep. 1. Gravel Bedding inside the comm. center building
90%
22, 2018
2. Backfilling works inside the comm. center building 95%
3. Formworks for comm. center building roof beams and roof
15%
slab
4. Installation of rebars for comm. center building roof beams 100%
Sep. 23 – Sep. 1. Formworks for roof slab and roof beams (CNCB)
95%
30, 2018
Sep. 30 – Oct. 1. Formworks on cantilever beams and slab on CNCB
45%
06, 2018
Oct. 07 – 1. Formworks on cantilever beams and slab on CNCB
90%
Oct.13, 2018
2. Excavation works for CNCB septic tank 70%
Oct. 14 – Oct. 1. Fabrication and installation of rebars for roof slab, and
95%
20, 2018 cantilever beams on Comm. Center Building
2. Fabrication and installation of forms for comm. center
90%
building parapet wall.
3. Installation of shoring for roof slab and cantilever beams 90%
Oct. 21 – Oct. 1. Rebar works for roof slab, beams on Comm. Center building
100%
27, 2018
2. Formworks on roof slab. Beams, parapet on Comm. center
100%
building
3. Shoring works on comm. center building 100%
Oct. 28 – Nov. 1. Concrete pouring on Comm, Center roof slab
100%
03, 2018
2. Formworks on roof slab. Beams, parapet on Comm. center
95%
building
Nov. 11 – Nov. 1. Removal of forms for roof slab and beams at Communication
100%
17, 2018 Center Building
2. Concrete pouring at shear wall on main entrance 90%
3. Plastering works on parapet wall at communication center
75%
building
Nov. 18 – Nov. 1. Concrete pouring at shear wall on main entrance
100%
24, 2018
2. Concrete pouring on pedestal of communication tower 100%
3. Masonry works inside communication center building 10%
Nov. 25 – Dec. 1. Masonry works inside the building
20%
01, 2018
2. Fabrication of gusset plates for tower 60%
Dec. 02 – Dec. 1. Masonry Works inside the building
40%
08, 2018
2. Fabrication of gusset plates for tower 90%
3. Construction of CNCB septic tank 60%
4. Concrete pouring at Genset room beams 100%
Dec. 09 – Dec. 1. Fabrication of gusset plate for tower
100%
15, 2018
2. Masonry works inside the building 50%
3. Construction of CNCB septic tank 85%