STRUCTURAL QUANTITIES

Clearing and Grubbing


Length Width Area Unit
10.5 7.75 81.375 m²
81.375 m²

Soil Poisoning
for Footing
Item Quantity Area Area total
F1 12 10.56 126.72

for Wall Footing


Item Length Width Area total
WF1 31 0.4 12.4
WF2 19.87 0.5 9.935

for Tie Beam


TB 52.55 0.3 15.765

for Slab
Length Width Area
10.35 6.65 68.8275

Soil Poisoning 217.8825

Gravel Bedding
for Footing
Item Quantity Area Thickness
F1 12 1.44 0.1

for Wall Footing


Item Length Width Thickness
WF1 31 0.4 0.1
WF2 19.87 0.48 0.1
for Tie Beam
TB 52.55 0.3 0.1

for Slab
Length Width Thickness
10.35 6.65 0.15

Soil Poisoning

Excavation
for Footing
Item Quantity Area D
F1 12 1.44 1.3

for Wall Footing


Item Length Area Volume
WF1 31 0.4 12.4
WF2 19.87 0.09 0
for Tie Beam
TB 52.55 0.105 0
Excavation 34.864

Backfill and Compaction


for Footing
Item Quantity VolumeExc VolumeF&C
F1 12 1.872 0.522
WF1 31 0.4 0.2
TB 52.55 0.105 0.105
Slab 1 0.3 68.8275

Backfill and Compaction


Ordinary Backfill
Imported Backfill

Concreting
for Footing
Item Quantity Area t
F1 12 1.44 0.3
Total

for Wall Footing


Item Length Area Volume
WF1 31 0.08 2.48
WF2 19.87 0.09 1.7883
Total 4.2683

for Tie Beam 52.55 0.06 3.153

for Column
Item Quantity Area Length
C1 12 0.09 4.4
Total

for Beam
Item Area Length Volume
B1 0.08 57.65 4.612
IB 0.03 23.9 0.717
Total 5.329

for Slab/Pantry Concrete


Area Thickness Volume
68.8275 0.1 6.95025

for Roof Deck


Volume 1 Volume 2 VolumeTotal
6.55025 2.0685 13.549192125

Reinforcement
for Footing
Item Quantity No. of Bars Length per bar
F1 12 12 1.41

Weight for Footing 16mm Ø bar


GI Tie Wire
F1 12 36 0.25

Weight for GI Tie Wire Footing

for Wall Footing


Item Length No. of 6m bars Lengthper bar
Horizontal Bars
WF1 93 16.32 6
WF2 79.48 14.24 6
for 12mmØ bars
Item Length No. of stirrups Lengthperstirrup
WF1 31 78.5 0.4
WF2 19.87 51 1.35

10mm Ø bar
Weight for Wall Footing
GI Tie Wire No. of Ties No. of stirrups Lengthpertie
3 78.5 0.25
4 51 0.25

Weight for GI Tie Wire Wall Footing

for Tie Beam Length No. of Bars L total


TB (Horizontal Bars) 52.55 4 210.2
for 16mmØ bars 332.116
Stirrups
@3.85 3 15 45
3 28 84
3 19 57
2 16 32
2 24 48
Total 266
for 10mmØ bars 164.122
Weight for Tie Beam 496.238

Weight for GI Tie Wire 408


7.6981132075

for Column
Item Quantity Qty. Vert. bars Lengthperbar
C1 12 4 4.4
16mm Ø bar
Item Length No. of stirrups Lengthperstirrup
C1stirrup 4.4 408 1.048
10mm Ø bar
Weight for Column
GI Tie Wire No. of Ties No. of stirrups Lengthpertie
4 408 0.25
Weight for GI Tie Wire Column

for Beam
Item No. of Bars Length Lengthtotal
B1 6 57.65 345.9
IB 4 23.9 95.6
441.5
16mm Ø bar 697.57
Stirrups Length No. of stirrups Lengthperstirrup
B1
2.5 15 1.2
4.15 23 1.2
3.1 18 1.2
4.9 27 1.2
1.85 12 1.2
IB 3.1 18 0.7
4.9 27 0.7
1.85 12 0.7
0.7 6 0.7

10mm Ø bar
Weight for Beam
GI Tie Wire No. of Ties No. of stirrups Lengthpertie
6 95 0.3
7 45 1.3
Weight for GI Tie Wire Beam

for Slab/Pantry
Slab L No. of bars Lengthperbar
along 10.35m 10.35 27 6.95
along 6.5m 6.5 18 10.65
Weight for Slab 10mm
Stirrups 486 0.25

for Suspended Slab/Roof Deck


Item L No. of Bars Lengthperbar
S1
.7x3.1 area
Bottom Short Span 3.1 20 0.7
Bottom Longspan 0.7 4 3.1
Top Short Span 2.077 10 0.7
Top Longspan 0.469 2 3.1
.7x4.9 area
Bottom Short Span 4.9 32 0.7
Bottom Longspan 0.7 4 4.9
Top Short Span 3.283 16 0.7
Top Longspan 0.469 2 4.9
.7x1.85
Bottom Short Span 1.85 12 0.7
Bottom Longspan 0.7 4 1.85
Top Short Span 1.2395 6 0.7
Top Longspan 0.469 2 4.9
S2
4.15x3.1area
Bottom Short Span 4.15 17 3.1
Bottom Longspan 3.1 10 4.15
Top Short Span 4.15 10 3.1
Top Longspan 3.1 5 4.15
4.15x4.9area
Bottom Short Span 4.9 20 4.15
Bottom Longspan 4.15 13 4.9
Top Short Span 4.9 12 4.15
Top Longspan 4.15 6 4.9
4.15x1.85area
Bottom Short Span 4.15 17 1.85
Bottom Longspan 1.85 6 4.15
Top Short Span 4.15 10 1.85
Top Longspan 1.85 3 4.15
2.5x3.1area
Bottom Short Span 3.1 12 2.5
Bottom Longspan 2.5 8 3.1
Top Short Span 3.1 7 2.5
Top Longspan 2.5 4 3.1
2.5x4.9area
Bottom Short Span 4.9 20 2.5
Bottom Longspan 2.5 8 4.9
Top Short Span 4.9 12 2.5
Top Longspan 2.5 4 4.9
2.5x1.85area
Bottom Short Span 2.5 10 1.85
Bottom Longspan 1.85 6 2.5
Top Short Span 2.5 6 1.85
Top Longspan 1.85 3 2.5

12mm Ø bar
for Stirrups
Masonry Works
150mm CHB
Item Length Height Areatotal
Wall 31 3.9 120.9
Parapet 33 1.2 39.6
Less Doors and/windows
Item Area Areatotal
D3 1 1.68 1.68
W1 1 7.2 7.2
W2 2 3.15 6.3
W3 2 1.05 2.1
W4 3 0.2 0.6
W5 3 0.2 0.6
18.48
CHB 150mm 142.02

Item Length Height Areatotal


for 100mm CHB 26.69 3 80.07
Column Casing (Front) 1 7.105 7.105
87.175
Less Doors and/windows
D1 1 3.15 3.15
D2 1 1.68 1.68
D4 1 1.47 1.47
D5 2 1.47 2.94
D6 1 1.68 1.68
D7 2 1.47 2.94
13.86
CHB 100mm 73.315

Tiling Works
Floor Tiles

Item Length Width Areatotal


Floor Tiles (Ceramic Unglazed) 1.08 2.4 2.592

Ceramic Tiles 6.65 10.35 68.8275


Less 1.2 2.5 -3
0.63 3.85 -2.4255
2.65 2.35 -6.2275
Vynil Tiles Total 57.1745

Wall Tiles/Counter 2.4 6.96 16.704


1.25 0.6 0.6
Less Doors and Windows 2 1.47 -2.94
1 0.2 -0.2
Wall Tiles/Counter Ceramic Glazed Total 14.164
Painting

Exterior and Exterior 413.966


Ceiling 67.275
Marine Plywood on Metal Furring(Optional)

Floor Toppings

Roof Deck 68.8275 65.5025 0.025

GI Sheet Plain

Area/Painting 35 1.2 42
Unit

Unit

Unit

Volume Unit
1.728 m³

Volume Unit
1.24 m³
0.95376 m³

1.5765 m³

Volume Unit
10.324125 m³

14.245885 m³

Volume Unit
22.464 m³

Unit


Volume Unit
16.2 m³
6.2 m³
0 m³
20.64825

43.04825 m³
33.1208 m³
10.4238225 m³
Volume Unit
5.184 m³
5.184 m³

Unit


Volume Unit
4.752 m³

Unit


Unit

Unit

Length Unit
203.04 m

203.04 m
320.8032 kgs

108 m

108 m
2.0377358491 kgs

L total Unit
m
97.89 m
85.46 m
183.36 m
163.1878211658 kgs
L total Unit
31.40 m
68.85 m
100.25
61.85 kgs
225.04 kgs
L total Unit
58.875 m
51 m
109.875 m
2.0731132075 kgs

Unit
m
kgs

m
m
m
m
m
m
kgs
kgs

kgs

Length Unit
211.2 m
333.696 kgs
L total Unit
427.584 m
263.819328 kgs
597.515328 kgs
L total Unit
408 m
7.6981132075 kgs

Unit
m
m
m
kgs
L total Unit

72 m
110.4 m
64.8 m
97.2 m
43.2 m
25.2 m
37.8 m
16.8 m
25.2 m
492.6 m
303.9342 kgs
1001.5042 kgs
L total Unit
171 m
409.5 m
10.9528301887 kgs

L total Unit
187.65 m
200.7 m
239.61195 kgs
121.5 m
2.2924528302 kgs

L total Unit

28 m
24.8 m
14 m
12.4 m

44.8 m
39.2 m
22.4 m
19.6 m

16.8 m
14.8 m
8.4 m
19.6 m
264.8

52.7 m
41.5 m
31 m
20.75 m
83 m
63.7 m
49.8 m
29.4 m

31.45 m
24.9 m
18.5 m
12.45 m

30 m
24.8 m
17.5 m
12.4 m

50 m
39.2 m
30 m
19.6 m

18.5 m
15 m
11.1 m
7.5 m
1264.35 m
1125.2715 kgs

56.263575 kgs
Unit







Unit









Unit











112.7093329688 m³
134.33


COMMUNITY FACILITIES
COMPACT
Bill of Quantities

Item Quantity Unit


Clearing and Grubbing 81.375 m²
Soil Poisoning 217.8825 m²
Gravel Bedding 14.245885 m³
Excavation 34.864 m³
Backfill and Compaction 33.1208 m³
Imported Backfill 10.4238225 m³
Concreting
Footing 5.184 m³
Wall Footing Column 4.2683 m³
Tie Beam 3.153 m³
Column 4.752 m³
Beam 5.329 m³
Roof Deck 13.549192125 m³
Slab 6.95025 m³
Reinforced Concrete
Footing 320.8032 kgs
Wall Footing 225.04 kgs
Tie Beam 496.238 kgs
Column 597.515328 kgs
Beam 1001.5042 kgs
Slab 239.61195 kgs
Suspended Slab 1125.2715 kgs
Masonry Works
150 mm thick CHB exterior wall) 142.02 m²
100 mm thick CHB (interior wall) 73.315 m²
Painting
Exterior and Exterior 413.966 m²
Ceiling Painting
Roof Deck (Interior Ceiling) 67.275 m²
MR Gypsum Board (optional) 3 m²
Tiling Works
Ceramic Unglazed Tiles 2.592 m²
Ceramic Tiles 57.1745
Ceramic Glazed Tiles 14.164 m²
Floor Topping 25mm 134.33 m²
Ceiling MR Gypsum Board (optional) 3 m²
GI Sheet Cladding 42 m²
Doors
2.1 x 0.9 Single Swing Aluminum Powder Coated Door W/ 1/4" Thk. Tinted Glass 1 sets
2.1 x 0.8 Hollow Core Flush Door W/ 2"X5" Wood Door Jamb Painted Finish 1 sets
2.1 x 0.8 Single Swing Door W/ Sched. 40 Steel Sheets W/ 2"X5" Steel Jamb 1 sets
2.1 x 0.7 Hollow Core Flush Door W/ 2"X5" Wood Door Jamb Painted Finish 1 sets
2.1 X 0.7 PVC Door With Louvers 2 sets
2.1 X 0.7 Hollow Core Flush Door W/ 2"X5" Wood Door Jamb Painted Finish 1 sets
2.1 x 0.7 Steel Door W/ Round Bar and Lockset 2 sets
0.7 x 0.7 Steel Roofdeck Hatch W/ Lockset 1 sets
Windows sets
2.4 x 3.0 Frameless Glass Window W/ Top & Bottom Aluminum Powder Coated Glass Holder
1 sets
W/ 1/4" Thk. Tinted Glass
1.5 X 2.1 Sliding Window Aluminum Powder Coated On 1/4" Thk. Tinted Glass W/ Fixed
2 sets
Transom
1.5 X 0.7 Sliding Window Aluminum Powder Coated On 1/4" Thk. Tinted Glass W/ Fixed
2 sets
Transom
0.4 X 0.5 Sliding Window Aluminum Powder Coated On 1/4" Thk. Tinted Glass 3 sets
0.4 X 0.5 Steel Fixed Window 2cm Ø Round Bar W/ 7cm Ø Spacing O.C. 3 sets
Office of the President
NATIONAL HOUSING AUTHORITY
Elliptical Road, Quezon City

APPROVED COST ESTIMATES


STANDARD COMMUNITY POLICE ACTION BUILDING
NHA Various Projects

MARK-UPS
ITEM DIRECT UNIT ESTIMATED
DESCRIPTION QUANTITY UNIT
NO. COST DIRECT COST OCM PROFIT

(1) (2) (3) (4) (4') (5) (6) (7)


I. GENERAL REQUIREMENT
1.1 Mobilization and Demobilization 1.00 lot 8,090.00 8,090.00
TEMFACIL ( Including electrical and water
1.2 1.00 lot 30,000.00 30,000.00 10%
consumption)
Personal Protective Equipment (NHA staff,
1.3 1.00 lot 19,200.00 19,200.00 10%
workers & contractor)
Sub-Total 57,290.00

II. CONSTRUCTION OF TRAINING AREA


A. EARTHWORKS
a.1 Clearing and Grubbing 81.38 sq.m 12.79 1,040.79 12% 124.89 10%
a.2 Excavation 34.86 cu.m 579.78 20,213.45 12% 2,425.61 10%
a.3
Gravel Bedding (Supply, Place and Compact) 14.25 cu.m 965.14 13,749.27 12% 1,649.91 10%
a.4 Backfill and Compact Trenches with Excavated 33.12 cu.m 784.92 25,997.18 12% 3,119.66 10%
Materials
a.5 Soil Poisoning 217.88 sq.m 129.95 28,313.83 12% 3,397.66 10%
a.6 Imported Earthfill 10.42 cu.m 909.14 9,476.71 12% 1,137.21 10%

Page 19 of 123
STANDARD COMMUNITY POLICE ACTION BUILDING
NHA Various Projects

Sub-Total 98,791.23
B. STRUCTURAL WORKS
b.1 Concreting Including Formworks
b.1.1 Column Footing 5.18 cu.m 4,090.48 21,205.05 12% 2,544.61 10%
b.1.2 Wall Footing 4.27 cu.m 4,090.48 17,459.40 12% 2,095.13 10%
b.1.3 Tie Beam 3.15 cu.m 7,252.45 22,866.98 12% 2,744.04 10%
b.1.4 Slab on Fill 6.95 cu.m 4,090.48 28,429.86 12% 3,411.58 10%
b.1.5 Columns 4.75 cu.m 8,991.19 42,726.13 12% 5,127.14 10%
b.1.6 Beams 5.33 cu.m 10,961.38 58,413.19 12% 7,009.58 10%
b.1.7 Suspended Slab/Roof Deck 13.55 cu.m 9,587.20 129,898.81 12% 15,587.86 10%
b.2 Reinforcing Steel Bar
b.2.1 Column Footing 320.80 kgs 42.93 13,772.08 12% 1,652.65 10%
b.2.2 Wall Footing 225.04 kgs 42.93 9,661.06 12% 1,159.33 10%
b.2.3 Tie Beam 496.24 kgs 42.93 21,303.50 12% 2,556.42 10%
b.2.4 Slab on Fill 239.61 kgs 42.93 10,286.54 12% 1,234.38 10%
b.2.5 Columns 597.52 kgs 42.93 25,651.33 12% 3,078.16 10%
b.2.6 Beams 1,001.50 kgs 42.93 42,994.58 12% 5,159.35 10%
b.2.7 Suspended Slab 1,125.27 kgs 42.93 48,307.91 12% 5,796.95 10%
b.3 Masonry Works
b.3.1 4" CHB Wall incl. Plastering 73.32 sq.m 939.81 68,902.17 12% 8,268.26 10%
b.3.2 6" CHB Wall incl. Plastering 142.02 sq.m 1,044.43 148,329.95 12% 17,799.59 10%
Sub-Total 710,208.54

Page 20 of 123
STANDARD COMMUNITY POLICE ACTION BUILDING
NHA Various Projects

C. ARCHITECTURAL WORKS
c.1 Tiling Works
c.1.1 20cmx20cm Ceramic Unglazed Tiles 2.59 sq.m 1,383.56 3,586.18 12% 430.34 10%
c.1.2 20cmx20cm Ceramic Glazed Tiles 14.16 sq.m 1,154.74 16,355.77 12% 1,962.69 10%
c.1.3 60cmx60cm Ceramic Unglazed Tiles 57.17 sq.m 1,383.56 79,104.20 12% 9,492.50 10%
c.2 Ceiling Finishes
c.2.1 MR Gypsum Board on light metal framing 3.00 sq.m 1,044.26 3,132.78 12% 375.93 10%
c.3 Floor Topping 25mm 134.33 sq.m 159.81 21,466.98 12% 2,576.04 10%
c.4 Doors
2.1 x 0.9 Single Swing Aluminum Powder
c.4.1 Coated Door W/ 1/4" Thk. Tinted Glass 1.00 set/s 21,204.56 21,204.56 12% 2,544.55 10%
2.1 x 0.8 Hollow Core Flush Door W/ 2"X5"
c.4.2 Wood 1.00 set/s 3,721.45 3,721.45 12% 446.57 10%
Door Jamb Painted Finish
2.1 x 0.8 Single Swing Door W/ Sched. 40
c.4.3 Steel 1.00 set/s 13,340.54 13,340.54 12% 1,600.86 10%
Sheets W/ 2"X5" Steel Jamb
2.1 x 0.7 Hollow Core Flush Door W/ 2"X5"
c.4.4 Wood 1.00 set/s 3,534.55 3,534.55 12% 424.15 10%
Door Jamb Painted Finish
c.4.5 2.1 X 0.7 PVC Door With Louvers 2.00 set/s 3,281.65 6,563.30 12% 787.60 10%
2.1 X 0.8 Hollow Core Flush Door W/ 2"X5"
c.4.6 Wood 1.00 set/s 3,721.45 3,721.45 12% 446.57 10%
Door Jamb Painted Finish
2.1 x 0.7 Steel Door W/ Round Bar and
c.4.7 Lockset 2.00 set/s 3,789.85 7,579.69 12% 909.56 10%

c.4.8 0.7 x 0.7 Steel Roofdeck Hatch W/ Lockset 1.00 set/s 1,209.61 1,209.61 12% 145.15 10%
c.5 Windows
2.4 x 3.0 Frameless Glass Window W/ Top &
c.5.1 Bottom Aluminum Powder Coated Glass 1.00 set/s 73,668.65 73,668.65 12% 8,840.24 10%
Holder W/ 1/4" Thk. Tinted Glass

Page 21 of 123
STANDARD COMMUNITY POLICE ACTION BUILDING
NHA Various Projects

1.5 X 2.1 Sliding Window Aluminum Powder


c.5.2 Coated On 1/4" Thk. Tinted Glass W/ Fixed 2.00 set/s 32,419.40 64,838.81 12% 7,780.66 10%
Transom
1.5 X 0.7 Sliding Window Aluminum Powder
c.5.3 Coated On 1/4" Thk. Tinted Glass W/ Fixed 2.00 set/s 11,030.90 22,061.81 12% 2,647.42 10%
Transom
0.4 X 0.5 Sliding Window Aluminum Powder
c.5.4 Coated 3.00 set/s 2,475.50 7,426.51 12% 891.18 10%
On 1/4" Thk. Tinted Glass
0.4 X 0.5 Steel Fixed Window 2cm Ø Round Bar
c.5.5 3.00 set/s 373.73 1,121.19 12% 134.54 10%
W/ 7cm Ø Spacing O.C.
c.6 Painting
c.6.1 Interior and Exterior 413.97 sq.m 291.91 120,840.82 12% 14,500.90 10%
c.6.2 Ceiling 70.28 sq.m 291.91 20,513.98 12% 2,461.68 10%
c.7 Waterproofing 65.50 sq.m 246.56 16,150.28 12% 1,938.03 10%
Sub-Total 511,143.11
D. PLUMBING
d.1 Sanitary Sewer Line
d.1.1 100mm dia PVC Pipes 55.30 lm 302.77 16,743.42 12% 2,009.21 10%
d.1.2 75mm dia PVC Pipes 59.00 lm 191.34 11,289.04 12% 1,354.68 10%
d.1.3 50mm dia PVC Pipes 22.00 lm 102.63 2,257.78 12% 270.93 10%
d.1.3 25mm dia PVC Pipes 13.75 lm 57.75 794.01 12% 95.28 10%
d.2 Water line
d.2.1 20mm dia PVC Pipes 13.75 lm 216.99 2,983.57 12% 358.03 10%
d.3 Catch Basin 9.00 set/s 1,402.01 12,618.05 12% 1,514.17 10%
d.4 Septic Tank (Conventional) 1.00 units 36,193.35 36,193.35 12% 4,343.20 10%
d.5 Plumbing Fixtures
d.5.1 Water Closet (Elongated) inc. Fittings 3.00 set/s 4,799.40 14,398.19 12% 1,727.78 10%
d.5.2 Lavatory including Fittings 1.00 set/s 6,799.40 6,799.40 12% 815.93 10%

Page 22 of 123
STANDARD COMMUNITY POLICE ACTION BUILDING
NHA Various Projects

d.5.3 Faucet 3.00 set/s 214.90 644.70 12% 77.36 10%


d.5.4 Floor Drain 12.00 set/s 339.88 4,078.55 12% 489.43 10%
d.5.5 Soap Holder 3.00 set/s 1,439.80 4,319.40 12% 518.33 10%
d.5.6 Tissue Holder 3.00 set/s 359.80 1,079.40 12% 129.53 10%
d.5.7 Kitchen Sink 1.00 set/s 5,299.40 5,299.40 12% 635.93 10%
d.5.8 Grease Trap 1.00 set/s 3,649.70 3,649.70 12% 437.96 10%
Sub-Total 119,498.23
E. ELECTRICAL WORKS
e.1 Roughing-in
Supply of materials, labor, equipment and
tools needed for the installation of electrical
roughing -in circuit breaker, panel boards, 1.00 lot 12,366.00 12,366.00 12% 1,483.92 10%
switches, outlets, fixtures, and other
incidentals necessary as specified/shown in
plans.
e.2 Wires and Cables
Supply of materials, labor, equipment and
tools needed for the installation of conduits,
wirings, utlity boxes, junction boxes and other 1.00 lot 11,910.04 11,910.04 12% 1,429.20 10%
incidentals necessary as specified/shown in
plans.
e.3 Wiring Devices and Lighting Fixtures

Supply of materials, labor, equipment and


tools needed for the installation of electrical
fixtures, outlets, switches, and panel boards, 1.00 lot 12,966.75 12,966.75 12% 1,556.01 10%
lighting fixtures and other incidentals
necessary as specified/shown in plans.

e.4 Panel Board, CB, Nema Enclosure

Page 23 of 123
STANDARD COMMUNITY POLICE ACTION BUILDING
NHA Various Projects

Supply of materials, labor, equipment and


tools needed for the installation of lighting 1.00 lot 22,950.00 22,950.00 12% 2,754.00 10%
fixtures and other incidentals necessary as
specified/shown in plans.
e.5 Miscellaneous Items 1.00 lot 6,561.00 6,561.00 12% 787.32 10%
Sub-Total 66,753.79
GRAND TOTAL 1,506,394.90

Prepared by: Reviewed by: Recommendin

MARY JOY P. MORAN JOVITA G. PANOPIO MA. BENITA O


Supervising Engineer A, CDU-HTDO Division Manager, CDU-HTDO Department Ma

Page 24 of 123
t
HORITY
City

TIMATES
E ACTION BUILDING
ects

MARK-UPS TOTAL
VAT INDIRECT TOTAL COST UNIT COST
PROFIT OCM +PROFIT COST
(8) (9) (10) (11)
(7)
(6) + (7) [(5) + (8)]5% (8) + (9) (5) + (10)

8,090.00 8,090.00

3,000.00 10% 3,000.00 5% 1,650.00 4,650.00 34,650.00 34,650.00

1,920.00 10% 1,920.00 5% 1,056.00 2,976.00 22,176.00 22,176.00


64,916.00

104.08 22% 228.97 5% 63.49 292.46 1,333.25 16.38


2,021.35 22% 4,446.96 5% 1,233.02 5,679.98 25,893.43 742.70
1,374.93 22% 3,024.84 5% 838.71 3,863.54 17,612.81 1,236.34

2,599.72 22% 5,719.38 0% 1,585.83 7,305.21 33,302.39 1,005.48


2,831.38 22% 6,229.04 5% 1,727.14 7,956.19 36,270.02 166.47
947.67 22% 2,084.88 5% 578.08 2,662.96 12,139.67 1,164.61

Page 25 of 123
E ACTION BUILDING
ects

126,551.57

2,120.51 22% 4,665.11 5% 1,293.51 5,958.62 27,163.67 5,239.91


1,745.94 22% 3,841.07 5% 1,065.02 4,906.09 22,365.49 5,239.91
2,286.70 22% 5,030.74 5% 1,394.89 6,425.62 29,292.60 9,290.39
2,842.99 22% 6,254.57 5% 1,734.22 7,988.79 36,418.65 5,239.91
4,272.61 22% 9,399.75 5% 2,606.29 12,006.04 54,732.17 11,517.71
5,841.32 22% 12,850.90 5% 3,563.20 16,414.11 74,827.30 14,041.53
12,989.88 22% 28,577.74 5% 7,923.83 36,501.57 166,400.38 12,281.20

1,377.21 22% 3,029.86 5% 840.10 3,869.95 17,642.03 54.99


966.11 22% 2,125.43 5% 589.32 2,714.76 12,375.82 54.99
2,130.35 22% 4,686.77 5% 1,299.51 5,986.28 27,289.78 54.99
1,028.65 22% 2,263.04 5% 627.48 2,890.52 13,177.06 54.99
2,565.13 22% 5,643.29 5% 1,564.73 7,208.02 32,859.35 54.99
4,299.46 22% 9,458.81 5% 2,622.67 12,081.48 55,076.06 54.99
4,830.79 22% 10,627.74 5% 2,946.78 13,574.52 61,882.43 54.99

6,890.22 22% 15,158.48 5% 4,203.03 19,361.51 88,263.68 1,203.90


14,833.00 22% 32,632.59 5% 9,048.13 41,680.72 190,010.67 1,337.91
909,777.14

Page 26 of 123
E ACTION BUILDING
ects

358.62 22% 788.96 5% 218.76 1,007.72 4,593.90 1,772.34


1,635.58 22% 3,598.27 5% 997.70 4,595.97 20,951.74 1,479.22
7,910.42 22% 17,402.92 5% 4,825.36 22,228.28 101,332.48 1,772.34

313.28 22% 689.21 5% 191.10 880.31 4,013.09 1,337.70


2,146.70 22% 4,722.74 5% 1,309.49 6,032.22 27,499.20 204.71

2,120.46 22% 4,665.00 5% 1,293.48 5,958.48 27,163.04 27,163.04

372.15 22% 818.72 5% 227.01 1,045.73 4,767.18 4,767.18

1,334.05 22% 2,934.92 5% 813.77 3,748.69 17,089.23 17,089.23

353.46 22% 777.60 5% 215.61 993.21 4,527.76 4,527.76


656.33 22% 1,443.93 5% 400.36 1,844.29 8,407.59 4,203.79

372.15 22% 818.72 5% 227.01 1,045.73 4,767.18 4,767.18

757.97 22% 1,667.53 5% 462.36 2,129.89 9,709.58 4,854.79

120.96 22% 266.11 5% 73.79 339.90 1,549.51 1,549.51

7,366.87 22% 16,207.10 5% 4,493.79 20,700.89 94,369.54 94,369.54

Page 27 of 123
E ACTION BUILDING
ects

6,483.88 22% 14,264.54 5% 3,955.17 18,219.71 83,058.52 41,529.26

2,206.18 22% 4,853.60 5% 1,345.77 6,199.37 28,261.18 14,130.59

742.65 22% 1,633.83 5% 453.02 2,086.85 9,513.36 3,171.12

112.12 22% 246.66 5% 68.39 315.05 1,436.24 478.75

12,084.08 22% 26,584.98 5% 7,371.29 33,956.27 154,797.09 373.94


2,051.40 22% 4,513.08 5% 1,251.35 5,764.43 26,278.41 373.94
1,615.03 22% 3,553.06 5% 985.17 4,538.23 20,688.51 315.84
654,774.32

1,674.34 22% 3,683.55 5% 1,021.35 4,704.90 21,448.32 387.85


1,128.90 22% 2,483.59 5% 688.63 3,172.22 14,461.26 245.11
225.78 22% 496.71 5% 137.72 634.44 2,892.22 131.46
79.40 22% 174.68 5% 48.43 223.12 1,017.13 73.97

298.36 22% 656.39 5% 182.00 838.38 3,821.95 277.96


1,261.81 22% 2,775.97 5% 769.70 3,545.67 16,163.72 1,795.97
3,619.34 22% 7,962.54 5% 2,207.79 10,170.33 46,363.68 46,363.68

1,439.82 22% 3,167.60 5% 878.29 4,045.89 18,444.07 6,148.02


679.94 22% 1,495.87 5% 414.76 1,910.63 8,710.02 8,710.02

Page 28 of 123
E ACTION BUILDING
ects

64.47 22% 141.83 5% 39.33 181.16 825.86 275.29


407.85 22% 897.28 5% 248.79 1,146.07 5,224.62 435.38
431.94 22% 950.27 5% 263.48 1,213.75 5,533.14 1,844.38
107.94 22% 237.47 5% 65.84 303.31 1,382.70 460.90
529.94 22% 1,165.87 5% 323.26 1,489.13 6,788.52 6,788.52
364.97 22% 802.93 5% 222.63 1,025.56 4,675.26 4,675.26
157,752.50

1,236.60 22% 2,720.52 5% 754.33 3,474.85 15,840.85 15,840.85

1,191.00 22% 2,620.21 5% 726.51 3,346.72 15,256.76 15,256.76

1,296.68 22% 2,852.69 5% 790.97 3,643.66 16,610.41 16,610.41

Page 29 of 123
E ACTION BUILDING
ects

2,295.00 22% 5,049.00 5% 1,399.95 6,448.95 29,398.95 29,398.95

656.10 22% 1,443.42 5% 400.22 1,843.64 8,404.64 8,404.64


85,511.60
1,999,283.13

Recommending Approval: Approved by:

MA. BENITA O. REGALA MARCELINO P. ESCALADA JR.


Department Manager, HTDO General Manager

Page 30 of 123
Office of the President
NATIONAL HOUSING AUTHORITY
Elliptical Road, Quezon City Period Hig

PROJECT : STANDARD COMMUNITY POLICE ACTION BUILDING TOTAL NO


LOCATION: NHA VARIOUS PROJECTS

ITEM Weight
NO. DESCRIPTION QUANTITY UNIT Cost 1
1
I. GENERAL REQUIREMENT
1.1 Mobilization 1.00 lot ###
8,090.00 0.40%
1.1' Demobilization 1.00 lot
TEMFACIL ( Including electrical and water
1.2 1.00 lot 34,650.00 1.73%
consumption) ###
1.3 Personal Protective Equipment (NHA staff, 1.00 lot 22,176.00 1.11%
workers & contractor) ###
Sub-Total 64,916.00
II. CONSTRUCTION OF COMPACT
A. EARTHWORKS
a.1 Clearing and Grubbing 81.38 sq.m 1,333.25 0.07% 0
a.2 Excavation 34.86 cu.m 25,893.43 1.30%
a.3 Gravel Bedding (Supply, Place and Compact) 14.25 cu.m 17,612.81 0.88%
a.4 Backfill and Compact Trenches with Excavated 33.12 cu.m 33,302.39 1.67%
Materials
a.5 Soil Poisoning 217.88 sq.m 36,270.02 1.81%
a.6 Imported Earthfill 10.42 cu.m 12,139.67 0.61%
Sub-Total 126,551.57
B. STRUCTURAL WORKS
a.1 Concreting Including Formworks
a.1.1 Column Footing 5.18 cu.m 27,163.67 1.36%
b.1.2 Wall Footing 4.27 cu.m 22,365.49 1.12%
b.1.3 Tie Beam 3.15 cu.m 29,292.60 1.47%
b.1.4 Slab on Fill 6.95 cu.m 36,418.65 1.82%
b.1.5 Column 4.75 cu.m 54,732.17 2.74%
b.1.6 Beam 5.33 cu.m 74,827.30 3.74%
b.1.7 Suspended Slab/ Roofdeck 13.55 cu.m 166,400.38 8.32%
b.2 Reinforcing Steel Bar
b.2.1 Column Footing 320.80 kgs 17,642.03 0.88%
b.2.2 Wall Footing 225.04 kgs 12,375.82 0.62%
b.2.3 Tie Beam 496.24 kgs 27,289.78 1.36%
b.2.4 Slab on Fill 239.61 kgs 13,177.06 0.66%
b.2.5 Column 597.52 kgs 32,859.35 1.64%
b.2.6 Beam 1,001.50 kgs 55,076.06 2.75%
b.2.7 Suspended Slab/ Roofdeck 1,125.27 kgs 61,882.43 3.10%
b.3 Masonry Works
b.3.1 4" CHB Wall incl. Plastering 73.32 sq.m 88,263.68 4.41%
b.3.2 6" CHB Wall incl. Plastering 142.02 sq.m 190,010.67 9.50%
Sub-Total 909,777.14
C. ARCHITECTURAL WORKS
c.1 Tiling Works
c.1.1 20cmx20cm Ceramic Unglazed Tiles 2.59 sq.m 4,593.90 0.23%
c.1.2 20cmx20cm Ceramic Glazed Tiles 14.16 sq.m 20,951.74 1.05%
c.1.3 60cmx60cm Ceramic Unglazed Tiles 57.17 sq.m 101,332.48 5.07%
c.2 Ceiling Finishes

c.2.1 MR Gypsum Board on light metal framing 3.00 sq.m 4,013.09 0.20%

c.3 Floor Toppings (25mm) 134.33 sq.m 27,499.20 1.38%


c.4 Doors

2.1 x 0.9 Single Swing Aluminum Powder Coated


c.4.1 Door 1.00 set/s 27,163.04 1.36%
W/ 1/4" Thk. Tinted Glass

2.1 x 0.8 Hollow Core Flush Door W/ 2"X5" Wood


c.4.2 Door 1.00 set/s 4,767.18 0.24%
Jamb Painted Finish
2.1 x 0.8 Single Swing Door W/ Sched. 40 Steel
c.4.3 Sheets 1.00 set/s 17,089.23 0.85%
W/ 2"X5" Steel Jamb
2.1 x 0.7 Hollow Core Flush Door W/ 2"X5" Wood
c.4.4 Door 1.00 set/s 4,527.76 0.23%
Jamb Painted Finish
c.4.5 2.1 X 0.7 PVC Door With Louvers 2.00 set/s 8,407.59 0.42%
2.1 X 0.8 Hollow Core Flush Door W/ 2"X5" Wood
c.4.6 Door Jamb Painted Finish 1.00 set/s 4,767.18 0.24%

c.4.7 2.1 x 0.7 Steel Door W/ Round Bar and Lockset 2.00 set/s 9,709.58 0.49%

c.4.8 0.7 x 0.7 Steel Roofdeck Hatch W/ Lockset 1.00 set/s 1,549.51 0.08%

c.5 Windows

2.4 x 3.0 Frameless Glass Window W/ Top &


c.5.1 Bottom Aluminum Powder Coated Glass Holder 1.00 set/s 94,369.54 4.72%
W/ 1/4" Thk. Tinted Glass

1.5 X 2.1 Sliding Window Aluminum Powder


c.5.2 Coated On 1/4" Thk. Tinted Glass W/ Fixed 2.00 set/s 83,058.52 4.15%
Transom

1.5 X 0.7 Sliding Window Aluminum Powder


c.5.3 Coated On 1/4" Thk. Tinted Glass W/ Fixed 2.00 set/s 28,261.18 1.41%
Transom

0.4 X 0.5 Sliding Window Aluminum Powder


c.5.4 Coated 3.00 set/s 9,513.36 0.48%
On 1/4" Thk. Tinted Glass

0.4 X 0.5 Steel Fixed Window 2cm Ø Round Bar


c.5.5 W/ 3.00 set/s 1,436.24 0.07%
7cm Ø Spacing O.C.
c.6 Painting
c.6.1 Interior and Exterior 413.97 sq.m 154,797.09 7.74%
c.6.2 Ceiling 70.28 sq.m 26,278.41 1.31%
c.7 Waterproofing 65.50 sq.m 20,688.51 1.03%
Sub-Total 654,774.32
D PLUMBING WORKS
d.1 Sanitary Sewer Line
d.1.1 100mm dia PVC Pipes 55.30 lm 21,448.32 1.07%
d.1.2 75mm dia PVC Pipes 59.00 lm 14,461.26 0.72%
d.1.3 50mm dia PVC Pipes 22.00 lm 2,892.22 0.14%
d.1.3 25mm dia PVC Pipes 13.75 lm 1,017.13 0.05%
d.2 Water line
d.2.1 20mm dia PVC Pipes 13.75 lm 3,821.95 0.19%
d.3 Catch Basin 9.00 set/s 16,163.72 0.81%
d.4 Septic Tank (Conventional) 1.00 units 46,363.68 2.32%
d.5 Plumbing Fixtures
d.5.1 Water Closet (Elongated) inc. Fittings 3.00 set/s 18,444.07 0.92%
d.5.2 Lavatory including Fittings 1.00 set/s 8,710.02 0.44%
d.5.3 Faucet 3.00 set/s 825.86 0.04%
d.5.4 Floor Drain 12.00 set/s 5,224.62 0.26%
d.5.5 Soap Holder 3.00 set/s 5,533.14 0.28%
d.5.6 Tissue Holder 3.00 set/s 1,382.70 0.07%
d.5.7 Kitchen Sink 1.00 set/s 6,788.52 0.34%
d.5.8 Grease Trap 1.00 set/s 4,675.26 0.23%
Sub-Total 157,752.50
E ELECTRICAL WORKS
e.1 Roughing-in 1.00 lot 15,840.85 0.79%
e.2 Wires and Cables 1.00 lot 15,256.76 0.76%
e.3 Wiring Devices and Lighting Fixtures 1.00 lot 16,610.41 0.83%
e.4 Panel Board, CB, Nema Enclosure 1.00 lot 29,398.95 1.47%
e.5 Miscellaneous Items 1.00 lot 8,404.64 0.42%
Sub-Total 85,511.60
TOTAL 1,999,283.13 100.00%

Weekly Accomplishment , %
CASH FLOW Accumulated Weekly Accomplishments, %
Weekly Accomplishment , P
Accumulated Weekly Accomplishments, P

Prepared by: Reviewed by:


ANTONIO T. SALAZAR JR. JOVITA G. PA
Supervising Engineer A, CDU-HTDO Division Mana
Period Highlight: 1 Plan Actual % Complete Actual (beyond plan)

TOTAL NO. OF DAYS: 115 calendar days

Week 1 Week 2 Week 3 Week 4


2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

############### ###

############### ################## ################## ##################

0 0 0 0 0 0
0 0

0 0 0 0 0 0 0
0 0

0 0
0
0

0 0
0
0 0

0
Week 1 Week 2 Week 3 Week 4
2.53% 3.49% 6.96% 1.71%
2.53% 6.02% 12.98% 14.70%
50,607.73 69,843.37 139,107.96 34,286.87
50,607.73 120,451.09 259,559.06 293,845.93

Recommending Approval:
MA. BENITA O. REGALA
Department Manager, HTDO
nd plan) % Complete (beyond plan)

Week 5 Week 6 Week 7


29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49
25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42

################## ################## ##################

0 0 0 0
0 0 0 0
0 0

0 0 0
0 0 0 0
0 0 0
0 0 0

Week 5 Week 6 Week 7


3.40% 4.72% 11.73%
18.10% 22.81% 34.55%
67,978.26 94,311.33 234,580.73
361,824.19 456,135.53 690,716.26

Approved:
MARCELINO P. ESCALADA JR.
General Manager
Week 8 Week 9 Week 10 Week 11
50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76
43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66

################## ################## ################## ##################

0 0

0 0 0

0
0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0

0 0 0 0 0

0 0

0 0
0

0 0 0

Week 8 Week 9 Week 10 Week 11


7.09% 3.92% 3.26% 7.58%
41.64% 45.56% 48.81% 56.39%
141,776.80 78,288.88 65,093.79 151,446.92
832,493.06 910,781.94 975,875.74 1,127,322.66
Week 12 Week 13 Week 14 Week 15
77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103
67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89

################## ################## ################## ###############


0 0 0 0 0

0
0 0 0 0
0 0 0 0 0 0 0

0
0 0 0 0 0
0 0 0 0 0 0 0 0 0 0

######### ###############
0 0 0 0 0 0 0 0 0 0 0 0
0 0

0 0 0 0 0 0
0 0 0 0 0

0 0 0 0 0
0 0 0 0 0
###
###

Week 12 Week 13 Week 14 Week 15


6.64% 10.91% 16.57% 8.16%
63.03% 73.94% 90.52% 98.68%
51,446.92 132,832.71 218,168.94 331,381.05 163,218.
27,322.66 1,260,155.37 1,478,324.31 1,809,705.36 1,972,923.
5 Week 16 Week 17
104 105 106 107 108 109 110 111 112 113 114 115 116 117 118 119###
90 91 92 93 94 95 96 97 98 99 100 101 102

############### #########

### ###
### ###
5 Week 16 Week 17
1.24% 0.08%
% 99.92% 100.00%
163,218.45 24,741.32 1,618.00
1,972,923.81 1,997,665.13 1,999,283.13
OFFICE OF THE PRESIDENT
NATIONAL HOUSING AUTHORITY
Elliptical Road, Diliman, Quezon City

DETAILED ESTIMATES
STANDARD COMMUNITY POLICE ACTION BUILDING
National Capital Region Rates
Item of Work : EARTHWORKS
Item No. : Clearing and Grubbing
ITEM
DESCRIPTION QUANTITY
NO.
A. MATERIAL COST QUANTITY
None

B. LABOR COST QUANTITY


Foreman 1.00
Labor 2.00

EQUIPMENT COST QUANTITY


C. None -

TOTAL DIRECT COST


UNIT COST

Item of Work : EARTHWORKS


Item No. : Excavation
ITEM
DESCRIPTION QUANTITY
NO.
A. MATERIAL COST QUANTITY
None

B. LABOR COST QUANTITY


Foreman 1.00
Labor 10.00

EQUIPMENT COST QUANTITY


C. None -

TOTAL DIRECT COST


UNIT COST

Page 52 of 123
DETAILED ESTIMATES
STANDARD COMMUNITY POLICE ACTION BUILDING

Item of Work : EARTHWORKS


Item No. : Gravel Bedding (Supply, Place and Compact)
ITEM
DESCRIPTION QUANTITY
NO.
A. MATERIAL COST
Gravel G3/4 100.00

B. LABOR COST QUANTITY


Foreman 1.00
Labor 10.00

EQUIPMENT COST QUANTITY


C. Vibratory Plate Compactor 1.00

TOTAL DIRECT COST


UNIT COST

Page 53 of 123
DETAILED ESTIMATES
STANDARD COMMUNITY POLICE ACTION BUILDING

Item of Work : EARTHWORKS


Item No. : Backfill and Compact Trenches with Excavated Materials
ITEM
DESCRIPTION QUANTITY
NO.
A. MATERIAL COST
None -

B. LABOR COST QUANTITY


Foreman 1.00
Labor 10.00

EQUIPMENT COST QUANTITY


C. Vibratory Plate Compactor 1.00

TOTAL DIRECT COST


UNIT COST

Item of Work : EARTHWORKS


Item No. : Soil Poisoning
ITEM
DESCRIPTION QUANTITY
NO.
A. MATERIAL COST
Soil Poisoning 33.33

B. LABOR COST QUANTITY


Foreman 1.00
Skilled 2.00

EQUIPMENT COST QUANTITY


C. None -

TOTAL DIRECT COST


UNIT COST

Item of Work : EARTHWORKS


Item No. : Imported Earthfill
ITEM
DESCRIPTION QUANTITY
NO.
A. MATERIAL COST
Earthfill Materials 100.00

B. LABOR COST QUANTITY

Page 54 of 123
DETAILED ESTIMATES
STANDARD COMMUNITY POLICE ACTION BUILDING

Foreman 1.00
Labor 10.00

EQUIPMENT COST QUANTITY


C. Vibratory Plate Compactor 1.00

TOTAL DIRECT COST


UNIT COST

Item of Work : STRUCTURAL WORKS


Item No. : Concreting Including Formworks/Slab on Fill
ITEM
DESCRIPTION QUANTITY
NO.
A. MATERIAL COST
Ready Mix Concrete 3000psi @28days 10.00

B. LABOR COST QUANTITY


Foreman 1.00
Skilled 5.00
Labor 5.00

EQUIPMENT COST QUANTITY


C. Concrete Vibrator 1.00

TOTAL DIRECT COST


UNIT COST

Page 55 of 123
DETAILED ESTIMATES
STANDARD COMMUNITY POLICE ACTION BUILDING

Item of Work : STRUCTURAL WORKS


Item No. : Concreting Including Formworks
Column Footing, Wall Footing
ITEM
DESCRIPTION QUANTITY
NO.
A. MATERIAL COST
Ready Mix Concrete 3000psi @28days 10.00

B. LABOR COST QUANTITY


Foreman 1.00
Skilled 5.00
Labor 5.00

EQUIPMENT COST QUANTITY


C. Concrete Vibrator 1.00

TOTAL DIRECT COST


UNIT COST

Item of Work : STRUCTURAL


Item No. : Concreting Including Formworks
Tie Beams
ITEM
DESCRIPTION QUANTITY
NO.
A. MATERIAL COST
Ready Mix Concrete 3000psi @28days 10.00
Formworks
Coco Lumber 2"x2" 742.00
Ordinary Plywood (0.0125mx1.2x2.44m) 35.00
Miscellaneous 1.00

B. LABOR COST QUANTITY


Foreman 1.00
Skilled 5.00
Labor 5.00

EQUIPMENT COST QUANTITY


C. Concrete Vibrator 1.00

TOTAL DIRECT COST


UNIT COST

Page 56 of 123
DETAILED ESTIMATES
STANDARD COMMUNITY POLICE ACTION BUILDING

Item of Work : STRUCTURAL WORKS


Item No. : Concreting Including Formworks
Column
ITEM
DESCRIPTION QUANTITY
NO.
A. MATERIAL COST
Ready Mix Concrete 3000psi @28days 10.00
Formworks
Coco Lumber 2"x2" 834.75
Ordinary Plywood (0.0125mx1.2x2.44m) 39.00
Miscellaneous 1.00

B. LABOR COST QUANTITY


Foreman 1.00
Skilled 5.00
Labor 5.00

EQUIPMENT COST QUANTITY


C. Concrete Vibrator 1.00

TOTAL DIRECT COST


UNIT COST

Page 57 of 123
DETAILED ESTIMATES
STANDARD COMMUNITY POLICE ACTION BUILDING

Item of Work : STRUCTURAL


Item No. : Concreting Including Formworks
Beams
ITEM
DESCRIPTION QUANTITY
NO.
A. MATERIAL COST
Ready Mix Concrete 3000psi @28days 10.00
Formworks
Coco Lumber 2"x2" 1,298.50
Ordinary Plywood (0.0125mx1.2x2.44m) 60.76
Miscellaneous 1.00

B. LABOR COST QUANTITY


Foreman 1.00
Skilled 5.00
Labor 5.00

EQUIPMENT COST QUANTITY


C. Concrete Vibrator 1.00

TOTAL DIRECT COST


UNIT COST

Item of Work : STRUCTURAL


Item No. : Concreting Including Formworks
Suspended Slab
ITEM
DESCRIPTION QUANTITY
NO.
A. MATERIAL COST
Ready Mix Concrete 3000psi @28days 10.00
Formworks
Coco Lumber 2"x2" 1,168.65
Ordinary Plywood (0.0125mx1.2x2.44m) 39.00
Miscellaneous 1.00

B. LABOR COST QUANTITY


Foreman 1.00
Skilled 5.00
Labor 5.00

EQUIPMENT COST QUANTITY

Page 58 of 123
DETAILED ESTIMATES
STANDARD COMMUNITY POLICE ACTION BUILDING

C. Concrete Vibrator 1.00

TOTAL DIRECT COST


UNIT COST

Item of Work : STRUCTURAL


Item No. : Reinforcing Steel Bar
ITEM
DESCRIPTION QUANTITY
NO.

A. MATERIAL COST
Reinforcing Steel Bar Grade 40 1,000.00
GI Tie Wire #16 50.00

B. LABOR COST QUANTITY


Skilled 2.00
Labor 2.00

EQUIPMENT COST QUANTITY


C. None -

TOTAL DIRECT COST


UNIT COST

Page 59 of 123
DETAILED ESTIMATES
STANDARD COMMUNITY POLICE ACTION BUILDING

Item of Work : STRUCTURAL


Item No. : Masonry Works
4" CHB Wall incl. Plastering
ITEM
DESCRIPTION QUANTITY
NO.
A. MATERIAL COST
CHB ordinary (101mmx293mmx406mm) 1,250.00
Cement 110.10
Sand 36.38
10mm dia bar 15.67

B. LABOR COST QUANTITY


Foreman 1.00
Skilled 2.00
Labor 2.00

EQUIPMENT COST QUANTITY


C. None -

TOTAL DIRECT COST


UNIT COST

Item of Work : STRUCTURAL


Item No. : Masonry Works
6" CHB Wall incl. Plastering
ITEM
DESCRIPTION QUANTITY
NO.
A. MATERIAL COST
CHB ordinary (150mmx293mmx406mm) 1,250.00
Cement 110.10
Sand 36.38
10mm dia bar 15.67

B. LABOR COST QUANTITY


Foreman 1.00
Skilled 2.00
Labor 2.00

EQUIPMENT COST QUANTITY


C. None -

TOTAL DIRECT COST

Page 60 of 123
DETAILED ESTIMATES
STANDARD COMMUNITY POLICE ACTION BUILDING

UNIT COST

Item of Work : ARCHITECTURAL WORKS


Item No. : Floor Finishes
Floor Toppings
ITEM
DESCRIPTION QUANTITY
NO.
A. MATERIAL COST
Cement 7.20
Sand 0.40

B. LABOR COST QUANTITY


Foreman 1.00
Skilled 5.00
Labor 5.00

EQUIPMENT COST QUANTITY


C. None -

TOTAL DIRECT COST


UNIT COST

Page 61 of 123
DETAILED ESTIMATES
STANDARD COMMUNITY POLICE ACTION BUILDING

Item of Work : ARCHITECTURAL WORKS


Item No. : Floor Finishes
Floor Tiles - Ceramic Unglazed Tiles
ITEM
DESCRIPTION QUANTITY
NO.
A. MATERIAL COST
30x30cm Ceramic Unglazed tiles 100.00
Tile adhessive 7.60
Tile Grout 100.00

B. LABOR COST QUANTITY


Foreman 1.00
Skilled 2.00
Labor 2.00

EQUIPMENT COST QUANTITY


C. None -

TOTAL DIRECT COST


UNIT COST

Item of Work : ARCHITECTURAL WORKS


Item No. : Wall Finishes
Wall Tiles - Ceramic Glazed Tiles
ITEM
DESCRIPTION QUANTITY
NO.
A. MATERIAL COST
30cmx30cm Ceramic Glazed tiles 100.00
Tile adhessive 7.60
Tile Grout 100.00

B. LABOR COST QUANTITY


Foreman 1.00
Skilled 2.00
Labor 2.00

EQUIPMENT COST QUANTITY


C. None -

TOTAL DIRECT COST


UNIT COST

Page 62 of 123
DETAILED ESTIMATES
STANDARD COMMUNITY POLICE ACTION BUILDING

Item of Work : ARCHITECTURAL WORKS


Item No. : Ceiling Works
Moisture Resistant Gypsum Board on Light Framing System
ITEM
DESCRIPTION QUANTITY
NO.

A. MATERIAL COST
Wall Angle (25mmx25mm) Ga. 24 28.00
Metal Furring (19 mm x 50mm x 5M) Ga. 24 75.00
Carrying Channel (12mm x 38mmx5m) Ga. 22 15.00
Hanger 30.00
Moisture Resistant Gypsum Board 12mm 36.00
Miscellaneous 1.00

B. LABOR COST QUANTITY


Foreman 1.00
Skilled 2.00
Labor 2.00

EQUIPMENT COST QUANTITY


C. None -

TOTAL DIRECT COST


UNIT COST

Page 63 of 123
DETAILED ESTIMATES
STANDARD COMMUNITY POLICE ACTION BUILDING

Item of Work : ARCHITECTURAL WORKS


Item No. : Painting Works
Interior, Exterior and Ceiling
ITEM
DESCRIPTION QUANTITY
NO.
A. MATERIAL COST
Latex Paint 80.00
Skimcoat 100.00
Miscellaneous and Consumables 1.00

B. LABOR COST QUANTITY


Foreman 1.00
Skilled 4.00
Labor 4.00

C. EQUIPMENT COST QUANTITY


None -

D. TOTAL DIRECT COST


UNIT COST

Item of Work : ARCHITECTURAL WORKS


Item No. : Doors
2.1 x 0.9 Single Swing Aluminum Powder Coated Door with 1/4" thick Tinted Glass
ITEM
DESCRIPTION QUANTITY
NO.
A. MATERIAL COST
2.1 x 0.9 Single Swing Aluminum Powder Coated
1.89
Door with 1/4" thick Tinted Glass
Glass 1.47
Door Hinges 3.00
Lockset 1.00
Steel Jambs 20.00
Miscellaneous

B. LABOR COST QUANTITY


Skilled 1.00
Labor 1.00

C. EQUIPMENT COST QUANTITY


None -

Page 64 of 123
DETAILED ESTIMATES
STANDARD COMMUNITY POLICE ACTION BUILDING

D. TOTAL DIRECT COST


UNIT COST

Item of Work : ARCHITECTURAL WORKS


Item No. : Doors
2.1 x 0.8 Single Swing Door W/ 2"X5" Steel Jamb
ITEM
DESCRIPTION QUANTITY
NO.
A. MATERIAL COST
2.5mm Steel Sheet 131.71
Door Hinges 3.00
Lockset 1.00
Steel Jambs 20.00
Miscellaneous

B. LABOR COST QUANTITY


Skilled 1.00
Labor 1.00

C. EQUIPMENT COST QUANTITY


None -

D. TOTAL DIRECT COST


UNIT COST

Page 65 of 123
DETAILED ESTIMATES
STANDARD COMMUNITY POLICE ACTION BUILDING

Item of Work : ARCHITECTURAL WORKS


Item No. : Door
0.8mx2.1m Flush Door Hollow Core Type
ITEM
DESCRIPTION QUANTITY
NO.
A. MATERIAL COST
0.8mx2.1m Flush Door Hollow Core Type 7.00
Door Hinges 21.00
Door Knob and Lockset 7.00
Door Jambs 34.30

B. LABOR COST QUANTITY


Skilled 1.00
Labor 1.00

C. EQUIPMENT COST QUANTITY


None -

D. TOTAL DIRECT COST


UNIT COST

Item of Work : ARCHITECTURAL WORKS


Item No. : Door
0.7mx2.1m Flush Door Hollow Core Type
ITEM
DESCRIPTION QUANTITY
NO.
A. MATERIAL COST
0.7mx2.1m Flush Door Hollow Core Type 7.00
Door Hinges 21.00
Door Knob and Lockset 7.00
Door Jambs 34.30

B. LABOR COST QUANTITY


Skilled 1.00
Labor 1.00

C. EQUIPMENT COST QUANTITY


None -

Page 66 of 123
DETAILED ESTIMATES
STANDARD COMMUNITY POLICE ACTION BUILDING

D. TOTAL DIRECT COST


UNIT COST

Item of Work : ARCHITECTURAL WORKS


Item No. : Door
2.1 x 0.7 FPVC Type Door
ITEM
DESCRIPTION QUANTITY
NO.
A. MATERIAL COST
2.1 x 0.7 FPVC Type Door 8.00
Door Hinges 24.00
Door Knob and Lockset 8.00

B. LABOR COST QUANTITY


Skilled 1.00
Labor 1.00

C. EQUIPMENT COST QUANTITY


None -

D. TOTAL DIRECT COST


UNIT COST

Page 67 of 123
DETAILED ESTIMATES
STANDARD COMMUNITY POLICE ACTION BUILDING

Item of Work : ARCHITECTURAL WORKS


Item No. : Doors
2.1 x 0.7 Steel Door W/ Round Bar and Lockset
ITEM
DESCRIPTION QUANTITY
NO.
A. MATERIAL COST
Steel 2.5 mm 115.25
Round Bar (10mm) 11.28
Door Hinges 12.00
Door Knob and Lockset 4.00
Door Jambs 19.60
Miscellaneous

B. LABOR COST QUANTITY


Skilled 1.00
Labor 1.00

C. EQUIPMENT COST QUANTITY


None -

D. TOTAL DIRECT COST


UNIT COST

Item of Work : ARCHITECTURAL WORKS


Item No. : Doors
0.7 x 0.7 Steel Roofdeck Hatch W/ Lockset
ITEM
DESCRIPTION QUANTITY
NO.
A. MATERIAL COST
Steel 2.5mm 38.42
Door Hinges 8.00
Lockset 4.00
Miscellaneous

B. LABOR COST QUANTITY


Skilled 1.00
Labor 1.00

C. EQUIPMENT COST QUANTITY


None -

Page 68 of 123
DETAILED ESTIMATES
STANDARD COMMUNITY POLICE ACTION BUILDING

D. TOTAL DIRECT COST


UNIT COST

Item of Work : ARCHITECTURAL WORKS


Item No. : Windows
2.4 x 3.0 Frameless Glass Window W/ Top & Bottom Aluminum Powder Coated Glass Holder W/ 1/4"
ITEM
DESCRIPTION QUANTITY
NO.
A. MATERIAL COST
2.4 x 3.0 Frameless Glass Window W/ Top & Bottom
Aluminum Powder Coated Glass Holder W/ 1/4" Thk. 7.20
Tinted Glass

B. LABOR COST QUANTITY


Skilled 1.00
Labor 1.00

C. EQUIPMENT COST QUANTITY


None -

D. TOTAL DIRECT COST


UNIT COST

Page 69 of 123
DETAILED ESTIMATES
STANDARD COMMUNITY POLICE ACTION BUILDING

Item of Work : ARCHITECTURAL WORKS


Item No. : Windows
1.5 X 2.1 Sliding Window Aluminum Powder Coated On 1/4" Thk. Tinted Glass W/ Fixed Transom
ITEM
DESCRIPTION QUANTITY
NO.
A. MATERIAL COST
1.5 X 2.1 Sliding Window Aluminum Powder Coated
3.15
On 1/4" Thk. Tinted Glass W/ Fixed Transom

B. LABOR COST QUANTITY


Skilled 1.00
Labor 1.00

C. EQUIPMENT COST QUANTITY


None -

D. TOTAL DIRECT COST


UNIT COST

Item of Work : ARCHITECTURAL WORKS


Item No. : Windows
1.5 X 0.7 Sliding Window Aluminum Powder Coated On 1/4" Thk. Tinted Glass W/ Fixed Transom
ITEM
DESCRIPTION QUANTITY
NO.
A. MATERIAL COST
1.5 X 0.7 Sliding Window Aluminum Powder Coated
1.05
On 1/4" Thk. Tinted Glass W/ Fixed Transom
Miscellaneous

B. LABOR COST QUANTITY


Skilled 1.00
Labor 1.00

C. EQUIPMENT COST QUANTITY


None -

D. TOTAL DIRECT COST


UNIT COST

Page 70 of 123
DETAILED ESTIMATES
STANDARD COMMUNITY POLICE ACTION BUILDING

Item of Work : ARCHITECTURAL WORKS


Item No. : Windows
0.4 X 0.5 Sliding Window Aluminum Powder Coated On 1/4" Thk. Tinted Glass
ITEM
DESCRIPTION QUANTITY
NO.
A. MATERIAL COST
0.4 X 0.5 Sliding Window Aluminum Powder Coated
0.20
On 1/4" Thk. Tinted Glass
Miscellaneous

B. LABOR COST QUANTITY


Skilled 1.00
Labor 1.00

C. EQUIPMENT COST QUANTITY


None -

D. TOTAL DIRECT COST


UNIT COST

Page 71 of 123
DETAILED ESTIMATES
STANDARD COMMUNITY POLICE ACTION BUILDING

Item of Work : ARCHITECTURAL WORKS


Item No. : Windows
0.4 X 0.5 Steel Fixed Window 2cm Ø Round Bar W/ 7cm Ø Spacing O.C.
ITEM
DESCRIPTION QUANTITY
NO.
A. MATERIAL COST
0.4 X 0.5 Steel Fixed Window 2cm Ø Round Bar W/
23.71
7cm Ø Spacing O.C.
Miscellaneous

B. LABOR COST QUANTITY


Skilled 1.00
Labor 1.00

C. EQUIPMENT COST QUANTITY


None -

D. TOTAL DIRECT COST


UNIT COST

Item of Work : ARCHITECTURAL WORKS


Item No. : Finishing Works
Water Proofing
ITEM
DESCRIPTION QUANTITY
NO.
A. MATERIAL COST
Waterproofing Material 11.00
Cement 4.00

B. LABOR COST QUANTITY


Skilled worker 2.00
Laborer 2.00

C. EQUIPMENT COST QUANTITY


None -

D. TOTAL DIRECT COST


UNIT COST

Page 72 of 123
DETAILED ESTIMATES
STANDARD COMMUNITY POLICE ACTION BUILDING

Item of Work : PLUMBING WORKS


Item No. : Sanitary Sewer Line
100mm dia Storm Drainage Pipe
ITEM
DESCRIPTION QUANTITY
NO.
A. MATERIAL COST
100mm Ø PVC Waste & storm drainage Pipe 34.00
Fittings 5%
Miscellanious 5%

B. LABOR COST QUANTITY


Plumber 1.00
Labor 3.00

EQUIPMENT COST QUANTITY


C. None -

TOTAL DIRECT COST


UNIT COST

Page 73 of 123
DETAILED ESTIMATES
STANDARD COMMUNITY POLICE ACTION BUILDING

Item of Work : PLUMBING WORKS


Item No. : Sanitary Sewer Line
75mm dia Storm Drainage Pipe
ITEM
DESCRIPTION QUANTITY
NO.

A. MATERIAL COST
75mm Ø PVC storm drainage Pipe 34.00
Fittings 5%
Miscellanious 5%

B. LABOR COST QUANTITY


Plumber 1.00
Labor 1.00

EQUIPMENT COST QUANTITY


C. None -

TOTAL DIRECT COST


UNIT COST

Item of Work : PLUMBING WORKS


Item No. : Sanitary Sewer Line
50mm dia Vent & Storm Drainage Pipe
ITEM
DESCRIPTION QUANTITY
NO.
A. MATERIAL COST
50mm Ø PVC Waste, Vent & storm drainage Pipe 34.00
Fittings 5%
Miscellanious 5%

B. LABOR COST QUANTITY


Plumber 1.00
Labor 1.00

EQUIPMENT COST QUANTITY


C. None -

TOTAL DIRECT COST


UNIT COST

Page 74 of 123
DETAILED ESTIMATES
STANDARD COMMUNITY POLICE ACTION BUILDING

Item of Work : PLUMBING WORKS


Item No. : Sanitary Sewer Line
25mm dia Vent & Storm Drainage Pipe
ITEM
DESCRIPTION QUANTITY
NO.
A. MATERIAL COST
25mm dia Vent & Storm Drainage Pipe 34.00
Fittings 5%
Miscellanious 5%

B. LABOR COST QUANTITY


Plumber 1.00
Labor 1.00

EQUIPMENT COST QUANTITY


C. None -

TOTAL DIRECT COST


UNIT COST

Page 75 of 123
DETAILED ESTIMATES
STANDARD COMMUNITY POLICE ACTION BUILDING

Item of Work : PLUMBING WORKS


Item No. : Water Line
20mm uPVC dia Water Line Pipe
ITEM
DESCRIPTION QUANTITY
NO.
A. MATERIAL COST
20mm Ø uPVC Water line Pipe 34.00
Water Meter 1.00
Gate Valve 1.00
Check Valve 1.00
Fittings 5%
Miscellanious 5%

B. LABOR COST QUANTITY


Plumber 1.00
Labor 3.00

EQUIPMENT COST QUANTITY


C. None -

TOTAL DIRECT COST


UNIT COST

Item of Work : PLUMBING WORKS


Item No. : Catch Basin
ITEM
DESCRIPTION QUANTITY
NO.
A. MATERIAL COST
Cement 6.00
Sand 0.34
10mm dia. RSB 36.00
12mm RSB 36.00
Plywood 6.00
Lumber 42.00
GI Tie Wire 5.14
38mmx3mm Flat bar 5.00

B. LABOR COST QUANTITY


Plumber 1.00
Labor 4.00

EQUIPMENT COST QUANTITY


C. None -

Page 76 of 123
DETAILED ESTIMATES
STANDARD COMMUNITY POLICE ACTION BUILDING

TOTAL DIRECT COST


UNIT COST

Item of Work : PLUMBING WORKS


Item No. : Conventional Type Septic Tank
ITEM
DESCRIPTION QUANTITY
NO.
A. MATERIAL COST
Gravel 0.86
Sand 2.12
Cement 42.00
12mm Ø RSB 67.00
10mm Ø RSB 41.03
GI Tie Wire No. 16 4.30
150mm CHB (Load Bearing) 213.00

B. LABOR COST QUANTITY


Plumber 2.00
Labor 4.00

EQUIPMENT COST QUANTITY


C. None -

TOTAL DIRECT COST


UNIT COST

Page 77 of 123
DETAILED ESTIMATES
STANDARD COMMUNITY POLICE ACTION BUILDING

Item of Work : PLUMBING WORKS


Item No. : Plumbing Fixtures
Water Closet (elongated) inc. fittings
ITEM
DESCRIPTION QUANTITY
NO.
A. MATERIAL COST
Water Closet 1.00

B. LABOR COST QUANTITY


-
Labor 1.00

EQUIPMENT COST QUANTITY


C. None -

TOTAL DIRECT COST


UNIT COST

Item of Work : PLUMBING WORKS


Item No. : Plumbing Fixtures
Lavatory Including Fittings
ITEM
DESCRIPTION QUANTITY
NO.
A. MATERIAL COST
Lavatory including fittings 1.00

B. LABOR COST QUANTITY


Plumber -
Labor 1.00

EQUIPMENT COST QUANTITY

C. None -

TOTAL DIRECT COST


UNIT COST

Page 78 of 123
DETAILED ESTIMATES
STANDARD COMMUNITY POLICE ACTION BUILDING

Item of Work : PLUMBING WORKS


Item No. : Plumbing Fixtures
Faucet Brass type
ITEM
DESCRIPTION QUANTITY
NO.
A. MATERIAL COST
Faucet 3.00

B. LABOR COST QUANTITY


Plumber -
Labor 1.00

EQUIPMENT COST QUANTITY


C. None -

TOTAL DIRECT COST


UNIT COST

Page 79 of 123
DETAILED ESTIMATES
STANDARD COMMUNITY POLICE ACTION BUILDING

Item of Work : PLUMBING WORKS


Item No. : Plumbing Fixtures
Floor Drain
ITEM
DESCRIPTION QUANTITY
NO.
A. MATERIAL COST
Floor Drain 5.00

B. LABOR COST QUANTITY


Plumber -
Labor 1.00

EQUIPMENT COST QUANTITY


C. None -

TOTAL DIRECT COST


UNIT COST

Item of Work : PLUMBING WORKS


Item No. : Plumbing Fixtures
Soap Holder
ITEM
DESCRIPTION QUANTITY
NO.
A. MATERIAL COST
Soap Holder 3.00

B. LABOR COST QUANTITY


Plumber -
Labor 1.00

EQUIPMENT COST QUANTITY


C. None -

TOTAL DIRECT COST


UNIT COST
Item of Work : PLUMBING WORKS
Item No. : Plumbing Fixtures
Tissue Holder
ITEM
DESCRIPTION QUANTITY
NO.
A. MATERIAL COST
Tissue Holder 3.00

Page 80 of 123
DETAILED ESTIMATES
STANDARD COMMUNITY POLICE ACTION BUILDING

B. LABOR COST QUANTITY


Plumber -
Labor 1.00

EQUIPMENT COST QUANTITY


C. None -

TOTAL DIRECT COST


UNIT COST

Page 81 of 123
DETAILED ESTIMATES
STANDARD COMMUNITY POLICE ACTION BUILDING

Item of Work : PLUMBING WORKS


Item No. : Plumbing Fixtures
Kitchen Sink
ITEM
DESCRIPTION QUANTITY
NO.
A. MATERIAL COST
Kitchen Sink 1.00

B. LABOR COST QUANTITY


Plumber -
Labor 1.00

EQUIPMENT COST QUANTITY


C. None -

TOTAL DIRECT COST


UNIT COST

Item of Work : PLUMBING WORKS


Item No. : Plumbing Fixtures
4 Gallon Per Munite Grease Trap
ITEM
DESCRIPTION QUANTITY
NO.
A. MATERIAL COST
Grease Trap 4GPM 1.00

B. LABOR COST QUANTITY


Plumber -
Labor 1.00

EQUIPMENT COST QUANTITY


C. None -

TOTAL DIRECT COST


UNIT COST

Item of Work : ELECTRICAL WORKS


Item No. : Roughing-ins

Page 82 of 123
DETAILED ESTIMATES
STANDARD COMMUNITY POLICE ACTION BUILDING

ITEM
DESCRIPTION QUANTITY
NO.
A. MATERIAL COST
20mmØ x 3m PVC Pipe 40.00
20mmØ PVC Adaptor 64.00
20mmØ PVC Locknut 64.00
25mmØ x 3m RSC Pipe 5.00
25mmØ x 8cm RSC Nipple 1.00
25mmØ RSC Elbow 2.00
25mmØ RSC Locknut and Bushing 4.00
25mmØ RSC Entrance Cap 1.00
25mmØ RSC C-Clamp 6.00
2" x 4" Utility Box 20.00
4" x 4" Junction Box with Cover 12.00
3/4"Ø Flexible Metallic Conduit 12.00

B. LABOR COST QUANTITY


35% of Material Cost

EQUIPMENT COST QUANTITY


C. None -

TOTAL DIRECT COST


UNIT COST

Page 83 of 123
DETAILED ESTIMATES
STANDARD COMMUNITY POLICE ACTION BUILDING

Item of Work : ELECTRICAL WORKS


Item No. : Wires
ITEM
DESCRIPTION QUANTITY
NO.
A. MATERIAL COST
2.0mm² THHN Copper Wire 1.00
3.5mm² THHN Copper Wire 95.00
5.5mm² THHN Copper Wire 40.00
8.0mm² THHN Copper Wire 30.00
2.0mm² TW Copper Wire 60.00

B. LABOR COST QUANTITY


35% of Material Cost

EQUIPMENT COST QUANTITY


C. None -

TOTAL DIRECT COST


UNIT COST

Item of Work : ELECTRICAL WORKS


Item No. : Wiring Devices and Lighting Fixtures
ITEM
DESCRIPTION QUANTITY
NO.
A. MATERIAL COST
Duplex C.O. with Ground 13.00
ACU Outlet (30AT, 2P) 2.00
6"Ø Keyless Receptacle with 18W CFL 12.00
Single Pole Switch with Plate and Cover 2.00
Two Pole Switch with Plate and Cover 2.00
Three Pole Switch with Plate and Cover 1.00

B. LABOR COST QUANTITY


35% of Material Cost

EQUIPMENT COST QUANTITY


C. None -

TOTAL DIRECT COST


UNIT COST

Item of Work : ELECTRICAL WORKS

Page 84 of 123
DETAILED ESTIMATES
STANDARD COMMUNITY POLICE ACTION BUILDING

Item No. : Panel Board


ITEM
DESCRIPTION QUANTITY
NO.
A. MATERIAL COST
LPP 1.00
Main: 60AT 2P 18 KAIC @ 240 V
Branches: 2 - 30AT 2P Bolt-on
2 - 20AT 2P Bolt-on
2 - 15AT 2P Bolt-on
Enclosure: NEMA 1
MCB 1.00
Main: 60AT 2P 18 KAIC @ 240 V
Enclosure: NEMA 3R

B. LABOR COST QUANTITY


35% of Material Cost

EQUIPMENT COST QUANTITY


C. None -

TOTAL DIRECT COST


UNIT COST

Page 85 of 123
DETAILED ESTIMATES
STANDARD COMMUNITY POLICE ACTION BUILDING

Item of Work : ELECTRICAL WORKS


Item No. : Miscellaneous and Consumables
ITEM
DESCRIPTION QUANTITY
NO.
A. MATERIAL COST
400cc PVC Solvent Cement 1.00
Hacksaw Blade 2.00
Electrical Tape 4.00
Rubber Tape 1.00
G.I. Tie Wire 2.00
Copper Clod Grounding Rod 16mmØ x 3000mm 1.00
Epoxy Primer 1.00
Paint Thinner 1.00
Paint Brush 2" 1.00

B. LABOR COST QUANTITY


35% of Material Cost

EQUIPMENT COST QUANTITY


C. None -

TOTAL DIRECT COST


UNIT COST

Prepared by:

LAWRENCE S. LAZARO
Sr. Engineer A, CDU-HTDO

ANTONIO T. SALAZAR JR.


Supervising Engineer A, CDU-HTDO

Reviewed and Submitted by:

Page 86 of 123
DETAILED ESTIMATES
STANDARD COMMUNITY POLICE ACTION BUILDING

JOVITA G. PANOPIO
Division Manager, CDU-HTDO

Recommending Approval:

MA. BENITA O. REGALA


Department Manager, HTDO

Approved by:

MARCELINO P. ESCALADA JR.


General Manager

Page 87 of 123
THE PRESIDENT
USING AUTHORITY
Diliman, Quezon City

D ESTIMATES
Y POLICE ACTION BUILDING

Area: 100.00 sq.m

UNIT DIRECT UNIT COST AMOUNT

Sub-Total P
NO. OF DAYS COST PER DAY
0.63 833.03 524.81
0.63 598.79 754.48
Sub-Total P 1,279.28
NO. OF DAYS COST PER DAY
- -
Sub-Total `

1,279.28
12.79

Volume: 100.00 cu.m

UNIT DIRECT UNIT COST AMOUNT

Sub-Total P
NO. OF DAYS COST PER DAY
8.50 833.03 7,080.76
8.50 598.79 50,897.15
Sub-Total P 57,977.91
NO. OF DAYS COST PER DAY
- -
Sub-Total P

57,977.91
579.78

Page 88 of 123
D ESTIMATES
Y POLICE ACTION BUILDING

Volume: 100.00 cu.m

UNIT DIRECT UNIT COST AMOUNT

cu.m 436.00 43,600.00


Sub-Total P 43,600.00
NO. OF DAYS COST PER DAY
6.25 833.03 5,206.44
6.25 598.79 37,424.38
Sub-Total P 42,630.81
NO. OF HOURS COST PER HOUR
9.17 1,121.36 10,282.87
Sub-Total P 10,282.87

96,513.68
965.14

Page 89 of 123
D ESTIMATES
Y POLICE ACTION BUILDING

Volume: 100.00 cu.m

UNIT DIRECT UNIT COST AMOUNT

- - 0.00
Sub-Total P 0.00
NO. OF DAYS COST PER DAY
10.00 833.03 8,330.30
10.00 598.79 59,879.00
Sub-Total P 68,209.30
NO. OF HOURS COST PER HOUR
9.17 1,121.36 10,282.87
Sub-Total P 10,282.87
78,492.17
784.92

Area: 100.00 sq.m

UNIT DIRECT UNIT COST AMOUNT

liters 320.00 10,666.67


Sub-Total P 10,666.67
NO. OF DAYS COST PER DAY
1.00 833.03 833.03
1.00 747.82 1,495.64
Sub-Total P 2,328.67
NO. OF HOURS COST PER HOUR
- - 0.00
Sub-Total P 0.00

12,995.34
129.95

Volume: 100.00 cu.m

UNIT DIRECT UNIT COST AMOUNT

cu.m 380.00 38,000.00


Sub-Total P 38,000.00
NO. OF DAYS COST PER DAY

Page 90 of 123
D ESTIMATES
Y POLICE ACTION BUILDING

6.25 833.03 5,206.44


6.25 598.79 37,424.38
Sub-Total P 42,630.81
NO. OF HOURS COST PER HOUR
9.17 1,121.36 10,282.87
Sub-Total P 10,282.87

90,913.68
909.14

Volume: 10.00 cu.m

UNIT DIRECT UNIT COST AMOUNT

cu.m 3,405.00 34,050.00


Sub-Total P 34,050.00
NO. OF DAYS COST PER DAY
0.88 833.03 733.07
0.88 747.82 3,290.41
0.88 598.79 2,634.68
Sub-Total P 6,658.15
NO. OF HOURS COST PER HOUR
0.88 223.50 196.68
Sub-Total P 196.68

40,904.83
4,090.48

Page 91 of 123
D ESTIMATES
Y POLICE ACTION BUILDING

Volume: 10.00 cu.m

UNIT DIRECT UNIT COST AMOUNT

cu.m 3,405.00 34,050.00


Sub-Total P 34,050.00
NO. OF DAYS COST PER DAY
0.88 833.03 733.07
0.88 747.82 3,290.41
0.88 598.79 2,634.68
Sub-Total P 6,658.15
NO. OF HOURS COST PER HOUR
0.88 223.50 196.68
Sub-Total P 196.68
40,904.83
4,090.48

Volume: 10.00 cu.m

UNIT DIRECT UNIT COST AMOUNT

cu.m 3,405.00 34,050.00

bd.ft 17.00 12,614.00


Sheets 500.00 17,500.00
lot 1,505.70 1,505.70
Sub-Total P 65,669.70
NO. OF DAYS COST PER DAY
0.88 833.03 733.07
0.88 747.82 3,290.41
0.88 598.79 2,634.68
Sub-Total P 6,658.15
NO. OF DAYS COST PER DAY
0.88 223.50 196.68
Sub-Total P 196.68

72,524.53
7,252.45

Page 92 of 123
D ESTIMATES
Y POLICE ACTION BUILDING

Volume: 10.00 cu.m

UNIT DIRECT UNIT COST AMOUNT

cu.m 3,405.00 34,050.00

bd.ft 17.00 14,190.75


Sheets 500.00 19,500.00
lot 1,684.54 1,684.54
Sub-Total P 69,425.29
NO. OF DAYS COST PER DAY
2.63 833.03 2,190.87
2.63 747.82 9,833.83
2.63 598.79 7,874.09
Sub-Total P 19,898.79
NO. OF DAYS COST PER DAY
2.63 223.50 587.81
Sub-Total P 587.81

89,911.88
8,991.19

Page 93 of 123
D ESTIMATES
Y POLICE ACTION BUILDING

Volume: 10.00 cu.m

UNIT DIRECT UNIT COST AMOUNT

cu.m 3,405.00 34,050.00

bd.ft 17.00 22,074.50


Sheets 500.00 30,380.00
lot 2,622.73 2,622.73
Sub-Total P 89,127.23
NO. OF DAYS COST PER DAY
2.63 833.03 2,190.87
2.63 747.82 9,833.83
2.63 598.79 7,874.09
Sub-Total P 19,898.79
NO. OF DAYS COST PER DAY
2.63 223.50 587.81
Sub-Total P 587.81

109,613.82
10,961.38

Volume: 10.00 cu.m

UNIT DIRECT UNIT COST AMOUNT

cu.m 3,405.00 34,050.00

bd.ft 17.00 19,867.05


Sheets 500.00 19,500.00
lot 1,968.35 1,968.35
Sub-Total P 75,385.40
NO. OF DAYS COST PER DAY
2.63 833.03 2,190.87
2.63 747.82 9,833.83
2.63 598.79 7,874.09
Sub-Total P 19,898.79
NO. OF DAYS COST PER DAY

Page 94 of 123
D ESTIMATES
Y POLICE ACTION BUILDING

2.63 223.50 587.81


Sub-Total P 587.81

95,872.00
9,587.20

Weight: 1,000.00 kg

UNIT DIRECT UNIT COST AMOUNT

kg 31.00 31,000.00
kg 70.00 3,500.00
Sub-Total P 34,500.00
NO. OF DAYS COST PER DAY
3.13 747.82 4,681.35
3.13 598.79 3,748.43
Sub-Total P 8,429.78
NO. OF DAYS COST PER DAY
- - 0.00
Sub-Total P 0.00
42,929.78
42.93

Page 95 of 123
D ESTIMATES
Y POLICE ACTION BUILDING

Area: 100.00 sq.m

UNIT DIRECT UNIT COST AMOUNT

pcs 9.00 11,250.00


bags 215.00 23,671.50
cu.m 700.00 25,466.00
kg 33.00 517.11
Sub-Total P 60,904.61
NO. OF DAYS COST PER DAY
9.38 833.03 7,813.82
9.38 747.82 14,029.10
9.38 598.79 11,233.30
Sub-Total P 33,076.23
NO. OF DAYS COST PER DAY
- - 0.00
Sub-Total P 0.00
93,980.84
939.81

Area: 100.00 sq.m

UNIT DIRECT UNIT COST AMOUNT

pcs 15.00 18,750.00


bags 215.00 23,671.50
cu.m 700.00 25,466.00
kg 33.00 517.11
Sub-Total P 68,404.61
NO. OF DAYS COST PER DAY
10.22 833.03 8,513.57
10.22 747.82 15,285.44
10.22 598.79 12,239.27
Sub-Total P 36,038.28
NO. OF DAYS COST PER DAY
- - 0.00
Sub-Total P 0.00

104,442.89

Page 96 of 123
D ESTIMATES
Y POLICE ACTION BUILDING

1,044.43

Area: 1,000.00 sq.m

UNIT DIRECT UNIT COST AMOUNT

bags 215.00 1,548.00


cu.m 700.00 280.00
Sub-Total P 1,828.00
NO. OF DAYS COST PER DAY
20.88 833.03 17,393.67
20.88 747.82 78,072.41
20.88 598.79 62,513.68
Sub-Total P 157,979.75
NO. OF DAYS COST PER DAY
- - 0.00
Sub-Total P 0.00

159,807.75
159.81

Page 97 of 123
D ESTIMATES
Y POLICE ACTION BUILDING

Area: 100.00 sq.m

UNIT DIRECT UNIT COST AMOUNT

sq.m 850.00 85,000.00


bags 90.00 684.00
kg 47.50 4,750.00
Sub-Total P 90,434.00
NO. OF DAYS COST PER DAY
13.59 833.03 11,320.88
13.59 747.82 20,325.75
13.59 598.79 16,275.11
Sub-Total P 47,921.74
NO. OF DAYS COST PER DAY
- - 0.00
Sub-Total P 0.00
138,355.74
1,383.56

Area: 100.00 sq.m

UNIT DIRECT UNIT COST AMOUNT

sq.m 740.00 74,000.00


bags 480.00 3,648.00
kg 47.50 4,750.00
Sub-Total P 82,398.00
NO. OF DAYS COST PER DAY
9.38 833.03 7,813.82
9.38 747.82 14,029.10
9.38 598.79 11,233.30
Sub-Total P 33,076.23
NO. OF DAYS COST PER DAY
- - 0.00
Sub-Total P 0.00
115,474.23
1,154.74

Page 98 of 123
D ESTIMATES
Y POLICE ACTION BUILDING

Area: 100.00 sq.m

UNIT DIRECT UNIT COST AMOUNT

pcs 87.00 2,436.00


pcs 357.00 26,775.00
pcs 283.00 4,245.00
lm 30.00 900.00
sheets 450.00 16,200.00
lot 2,527.80 2,527.80
Sub-Total P 53,083.80
NO. OF DAYS COST PER DAY
14.56 833.03 12,128.92
14.56 747.82 21,776.52
14.56 598.79 17,436.76
Sub-Total P 51,342.20
NO. OF DAYS COST PER DAY
- - 0.00
Sub-Total P 0.00

104,426.00
1,044.26

Page 99 of 123
D ESTIMATES
Y POLICE ACTION BUILDING

Area: 1,000.00 sq.m

UNIT DIRECT UNIT COST AMOUNT

gal 480.00 38,400.00


pails 1,600.00 160,000.00
lot 9,920.00 9,920.00
Sub-Total P 208,320.00
NO. OF DAYS COST PER DAY
13.44 833.03 11,195.92
13.44 747.82 40,202.80
13.44 598.79 32,190.95
Sub-Total P 83,589.68
NO. OF DAYS COST PER DAY
- - 0.00
Sub-Total P 0.00
291,909.68
291.91

Qty: 1.00 set

with 1/4" thick Tinted Glass

UNIT DIRECT UNIT COST AMOUNT

sq.m 6,500.00 12,285.00


sq.m 450.00 661.50
sets 320.00 960.00
sets 250.00 250.00
ln.m 285.00 5,700.00
674.75
Sub-Total P 20,531.25
NO. OF DAYS COST PER DAY
0.50 747.82 373.91
0.50 598.79 299.40
Sub-Total P 673.31
NO. OF DAYS COST PER DAY
- - 0.00
Sub-Total P 0.00

Page 100 of 123


D ESTIMATES
Y POLICE ACTION BUILDING

21,204.56
21,204.56

Qty: 1.00 set

UNIT DIRECT UNIT COST AMOUNT

kgs 47.00 6,190.46


sets 65.00 195.00
sets 250.00 250.00
ln.m 285.00 5,700.00
331.77
Sub-Total P 12,667.24
NO. OF DAYS COST PER DAY
0.50 747.82 373.91
0.50 598.79 299.40
P 673.31
NO. OF DAYS COST PER DAY
- - 0.00
Sub-Total P 0.00
13,340.54
13,340.54

Page 101 of 123


D ESTIMATES
Y POLICE ACTION BUILDING

Qty: 7.00 Sets

UNIT DIRECT UNIT COST AMOUNT

sets 1,495.20 10,466.40


sets 65.00 1,365.00
sets 250.00 1,750.00
lm 285.00 9,775.50
Sub-Total P 23,356.90
NO. OF DAYS COST PER DAY
2.00 747.82 1,495.64
2.00 598.79 1,197.58
Sub-Total P 2,693.22
NO. OF DAYS COST PER DAY
- - 0.00
Sub-Total P 0.00

26,050.12
3,721.45

Qty: 7.00 Sets

UNIT DIRECT UNIT COST AMOUNT

sets 1,308.30 9,158.10


sets 65.00 1,365.00
sets 250.00 1,750.00
lm 285.00 9,775.50
Sub-Total P 22,048.60
NO. OF DAYS COST PER DAY
2.00 747.82 1,495.64
2.00 598.79 1,197.58
Sub-Total P 2,693.22
NO. OF DAYS COST PER DAY
- - 0.00
Sub-Total P 0.00

Page 102 of 123


D ESTIMATES
Y POLICE ACTION BUILDING

24,741.82
3,534.55

Qty: 8.00 Sets

UNIT DIRECT UNIT COST AMOUNT

sets 2,500.00 20,000.00


sets 65.00 1,560.00
sets 250.00 2,000.00
Sub-Total P 23,560.00
NO. OF DAYS COST PER DAY
2.00 747.82 1,495.64
2.00 598.79 1,197.58
Sub-Total P 2,693.22
NO. OF DAYS COST PER DAY
- - 0.00
Sub-Total P 0.00

26,253.22
3,281.65

Page 103 of 123


D ESTIMATES
Y POLICE ACTION BUILDING

Qty: 4.00 sets

2.5mm steel door

UNIT DIRECT UNIT COST AMOUNT

kgs 47.00 5,416.66


kgs 33.00 372.37
sets 65.00 780.00
sets 250.00 1,000.00
ln.m 285.00 5,586.00
657.75
Sub-Total P 13,812.78
NO. OF DAYS COST PER DAY
1.00 747.82 747.82
1.00 598.79 598.79
Sub-Total P 1,346.61
NO. OF DAYS COST PER DAY
- - 0.00
Sub-Total P 0.00

15,159.39
3,789.85

Qty: 4.00 sets

UNIT DIRECT UNIT COST AMOUNT

kgs 47.00 1,805.55


sets 65.00 520.00
sets 250.00 1,000.00
166.28
Sub-Total P 3,491.83
NO. OF DAYS COST PER DAY
1.00 747.82 747.82
1.00 598.79 598.79
Sub-Total P 1,346.61
NO. OF DAYS COST PER DAY
- - 0.00
Sub-Total P 0.00

Page 104 of 123


D ESTIMATES
Y POLICE ACTION BUILDING

4,838.44
1,209.61

Qty: 1.00 sets

uminum Powder Coated Glass Holder W/ 1/4" Thk. Tinted Glass

UNIT DIRECT UNIT COST AMOUNT

sq.m 10,185.00 73,332.00

Sub-Total P 73,332.00
NO. OF DAYS COST PER DAY
0.25 747.82 186.96
0.25 598.79 149.70
Sub-Total P 336.65
NO. OF DAYS COST PER DAY
- - 0.00
Sub-Total P 0.00

73,668.65
73,668.65

Page 105 of 123


D ESTIMATES
Y POLICE ACTION BUILDING

Qty: 1.00 set

n 1/4" Thk. Tinted Glass W/ Fixed Transom

UNIT DIRECT UNIT COST AMOUNT

sq.m 10,185.00 32,082.75

Sub-Total P 32,082.75
NO. OF DAYS COST PER DAY
0.25 747.82 186.96
0.25 598.79 149.70
Sub-Total P 336.65
NO. OF DAYS COST PER DAY
- - 0.00
Sub-Total P 0.00

32,419.40
32,419.40

Qty: 1.00 set

n 1/4" Thk. Tinted Glass W/ Fixed Transom

UNIT DIRECT UNIT COST AMOUNT

sq.m 10,185.00 10,694.25

Sub-Total P 10,694.25
NO. OF DAYS COST PER DAY
0.25 747.82 186.96
0.25 598.79 149.70
Sub-Total P 336.65
NO. OF DAYS COST PER DAY
- - 0.00
Sub-Total P 0.00

11,030.90
11,030.90

Page 106 of 123


D ESTIMATES
Y POLICE ACTION BUILDING

Qty: 1.00 set

n 1/4" Thk. Tinted Glass

UNIT DIRECT UNIT COST AMOUNT

sq.m 10,185.00 2,037.00

101.85
Sub-Total P 2,138.85
NO. OF DAYS COST PER DAY
0.25 747.82 186.96
0.25 598.79 149.70
Sub-Total P 336.65
NO. OF DAYS COST PER DAY
- - 0.00
Sub-Total P 0.00

2,475.50
2,475.50

Page 107 of 123


D ESTIMATES
Y POLICE ACTION BUILDING

Qty: 4.00 sets

m Ø Spacing O.C.

UNIT DIRECT UNIT COST AMOUNT

kgs 33.00 782.50

39.12
Sub-Total P 821.62
NO. OF DAYS COST PER DAY
0.50 747.82 373.91
0.50 598.79 299.40
Sub-Total P 673.31
NO. OF DAYS COST PER DAY
- - 0.00
Sub-Total P 0.00

1,494.93
373.73

Area: 65.50 sq.m.

UNIT DIRECT UNIT COST AMOUNT

gallons 650.00 7,150.00


kgs 230.00 920.00
Sub-Total P 8,070.00
NO. OF DAYS COST PER DAY
3.00 747.82 4,486.92
3.00 598.79 3,592.74
P 8,079.66
NO. OF DAYS COST PER DAY
- - 0.00
Sub-Total P 0.00

16,149.66
246.56

Page 108 of 123


D ESTIMATES
Y POLICE ACTION BUILDING

Qty. 100.00 lm

UNIT DIRECT UNIT COST AMOUNT

pcs 715.00 24,310.00


1,215.50
1,215.50
Sub-Total P 26,741.00
NO. OF DAYS COST PER DAY
1.39 747.82 1,039.47
1.39 598.79 2,496.95
Sub-Total P 3,536.42
NO. OF DAYS COST PER DAY
- - 0.00
Sub-Total P 0.00
30,277.42
302.77

Page 109 of 123


D ESTIMATES
Y POLICE ACTION BUILDING

Qty. 100.00 lm

UNIT DIRECT UNIT COST AMOUNT

pcs 490.00 16,660.00


833.00
833.00
Sub-Total P 18,326.00
NO. OF DAYS COST PER DAY
0.60 747.82 448.69
0.60 598.79 359.27
Sub-Total P 807.97
NO. OF DAYS COST PER DAY
- - 0.00
Sub-Total P 0.00
19,133.97
191.34

Qty. 100.00 lm

UNIT DIRECT UNIT COST AMOUNT

pcs 260.00 8,840.00


442.00
442.00
Sub-Total P 9,724.00
NO. OF DAYS COST PER DAY
0.40 747.82 299.13
0.40 598.79 239.52
Sub-Total P 538.64
NO. OF DAYS COST PER DAY
- - 0.00
Sub-Total P 0.00

10,262.64
102.63

Page 110 of 123


D ESTIMATES
Y POLICE ACTION BUILDING

Qty. 100.00 lm

UNIT DIRECT UNIT COST AMOUNT

pcs 140.00 4,760.00


238.00
238.00
Sub-Total P 5,236.00
NO. OF DAYS COST PER DAY
0.40 747.82 299.13
0.40 598.79 239.52
Sub-Total P 538.64
NO. OF DAYS COST PER DAY
- - 0.00
Sub-Total P 0.00

5,774.64
57.75

Page 111 of 123


D ESTIMATES
Y POLICE ACTION BUILDING

Qty. 100.00 lm

UNIT DIRECT UNIT COST AMOUNT

pcs 490.00 16,660.00


unit 1,600.00 1,600.00
unit 387.00 387.00
unit 368.00 368.00
833.00
833.00
Sub-Total P 20,681.00
NO. OF DAYS COST PER DAY
0.40 747.82 299.13
0.40 598.79 718.55
Sub-Total P 1,017.68
NO. OF DAYS COST PER DAY
- - 0.00
Sub-Total P 0.00
21,698.68
216.99

Qty. 15.00 sets

UNIT DIRECT UNIT COST AMOUNT

bags 215.00 1,290.00


cu.m 700.00 238.00
kgs 33.00 1,188.00
kgs 33.00 1,188.00
pcs 500.00 3,000.00
bdft 50.00 2,100.00
kgs 70.00 359.80
pcs 118.00 590.00
Sub-Total P 9,953.80
NO. OF DAYS COST PER DAY
2.00 747.82 1,495.64
4.00 598.79 9,580.64
Sub-Total P 11,076.28
NO. OF DAYS COST PER DAY
- - 0.00

Page 112 of 123


D ESTIMATES
Y POLICE ACTION BUILDING

Sub-Total P 0.00
21,030.08
1,402.01

Qty. 1.00 unit

UNIT DIRECT UNIT COST AMOUNT

cum 800.00 688.00


cum 650.00 1,378.00
bags 230.00 9,660.00
kgs 33.00 2,211.00
kgs 33.00 1,353.99
kgs 70.00 301.00
pcs 20.00 4260
Sub-Total P 19,851.99
NO. OF DAYS COST PER DAY
4.20 747.82 6,281.69
4.20 598.79 10,059.67
Sub-Total P 16,341.36
NO. OF DAYS COST PER DAY
- - 0.00
Sub-Total P 0.00
36,193.35
36,193.35

Page 113 of 123


D ESTIMATES
Y POLICE ACTION BUILDING

Qty. 1.00 set

UNIT DIRECT UNIT COST AMOUNT

sets 4,500.00 4,500.00

Sub-Total P 4,500.00
NO. OF DAYS COST PER DAY
- - 0.00
0.50 598.79 299.40
Sub-Total P 299.40

NO. OF DAYS COST PER DAY


- - 0.00
Sub-Total P 0.00
4,799.40
4,799.40

Qty. 1.00 set

UNIT DIRECT UNIT COST AMOUNT

set 6,500.00 6,500.00

Sub-Total P 6,500.00
NO. OF DAYS COST PER DAY
- - 0.00
0.50 598.79 299.40
Sub-Total P 299.40
NO. OF DAYS COST PER DAY

- - 0.00
Sub-Total P 0.00

6,799.395
6,799.40

Page 114 of 123


D ESTIMATES
Y POLICE ACTION BUILDING

Qty. 3.00 set

UNIT DIRECT UNIT COST AMOUNT

pcs 165.00 495.00


Sub-Total P 495.00
NO. OF DAYS COST PER DAY
- - 0.00
0.25 598.79 149.70
Sub-Total P 149.70
NO. OF DAYS COST PER DAY
- - 0.00
Sub-Total P 0.00

644.70
214.90

Page 115 of 123


D ESTIMATES
Y POLICE ACTION BUILDING

Qty. 5.00 set

UNIT DIRECT UNIT COST AMOUNT

pcs 280.00 1,400.00


Sub-Total P 1,400.00
NO. OF DAYS COST PER DAY
- - 0.00
0.50 598.79 299.40
Sub-Total P 299.40
NO. OF DAYS COST PER DAY
- - 0.00
Sub-Total P 0.00
1,699.40
339.88

Qty. 3.00 set

UNIT DIRECT UNIT COST AMOUNT

pcs 1,340.00 4,020.00


Sub-Total P 4,020.00
NO. OF DAYS COST PER DAY
- - 0.00
0.50 598.79 299.40
Sub-Total P 299.40
NO. OF DAYS COST PER DAY
- - 0.00
Sub-Total P 0.00
4,319.40
1,439.80
Qty. 3.00 set

UNIT DIRECT UNIT COST AMOUNT

pcs 260.00 780

Page 116 of 123


D ESTIMATES
Y POLICE ACTION BUILDING

Sub-Total P 780.00
NO. OF DAYS COST PER DAY
- - 0.00
0.50 598.79 299.40
Sub-Total P 299.40
NO. OF DAYS COST PER DAY
- - 0.00
Sub-Total P 0.00

1,079.40
359.80

Page 117 of 123


D ESTIMATES
Y POLICE ACTION BUILDING

Qty. 1.00 set

UNIT DIRECT UNIT COST AMOUNT

sets 5,000.00 5,000.00

Sub-Total P 5,000.00
NO. OF DAYS COST PER DAY
- - 0.00
0.50 598.79 299.40
Sub-Total P 299.40
NO. OF DAYS COST PER DAY
- - 0.00
Sub-Total P 0.00

5,299.40
5,299.40

Qty. 1.00 set

UNIT DIRECT UNIT COST AMOUNT

sets 3,500.00 3,500.00


Sub-Total P 3,500.00
NO. OF DAYS COST PER DAY
- - 0.00
0.25 598.79 149.70
Sub-Total P 149.70
NO. OF DAYS COST PER DAY
- - 0.00
Sub-Total P 0.00
3,649.70
3,649.70

Qty. 1.00 lot 〖��〗 ^2

Page 118 of 123


D ESTIMATES
Y POLICE ACTION BUILDING

UNIT DIRECT UNIT COST AMOUNT

pcs 80.00 3,200.00


pcs 5.00 320.00
pcs 5.00 320.00
pcs 420.00 2,100.00
pcs 50.00 50.00
pcs 20.00 40.00
pcs 20.00 80.00
pcs 450.00 450.00
pcs 150.00 900.00
pcs 40.00 800.00
pcs 50.00 600.00
m 25.00 300.00
Sub-Total P 9,160.00
NO. OF DAYS COST PER DAY
3,206.00
Sub-Total P 3,206.00
NO. OF DAYS COST PER DAY
- - 0.00
Sub-Total P 0.00
12,366.00
12,366.00

Page 119 of 123


D ESTIMATES
Y POLICE ACTION BUILDING

Qty. 1.00 lot

UNIT DIRECT UNIT COST AMOUNT

rolls 2,731.00 2,731.00


m 23.67 2,248.65
m 35.00 1,400.00
m 45.00 1,350.00
m 18.21 1,092.60
Sub-Total P 8,822.25
NO. OF DAYS COST PER DAY
3,087.79
Sub-Total P 3,087.79
NO. OF DAYS COST PER DAY
- - 0.00
Sub-Total P 0.00
11,910.04
11,910.04

Qty. 1.00 lot

UNIT DIRECT UNIT COST AMOUNT

pcs 335.00 4,355.00


pcs 350.00 700.00
pcs 300.00 3,600.00
pcs 140.00 280.00
pcs 200.00 400.00
270.00 270.00
Sub-Total P 9,605.00
NO. OF DAYS COST PER DAY
3,361.75
Sub-Total P 3,361.75
NO. OF DAYS COST PER DAY
- - 0.00
Sub-Total P 0.00
12,966.75
12,966.75

Qty. 1.00 lot

Page 120 of 123


D ESTIMATES
Y POLICE ACTION BUILDING

UNIT DIRECT UNIT COST AMOUNT

assy 12,000.00 12,000.00

assy 5,000.00 5,000.00

Sub-Total P 17,000.00
NO. OF DAYS COST PER DAY
5,950.00
Sub-Total P 5,950.00
NO. OF DAYS COST PER DAY
- - 0.00
Sub-Total P 0.00
22,950.00
22,950.00

Page 121 of 123


D ESTIMATES
Y POLICE ACTION BUILDING

Qty. 1.00 lot

UNIT DIRECT UNIT COST AMOUNT

cans 230.00 230.00


pcs 60.00 120.00
rolls 35.00 140.00
rolls 190.00 190.00
kgs 65.00 130.00
pcs 3,000.00 3,000.00
lt 450.00 450.00
lt 300.00 300.00
pcs 300.00 300.00
Sub-Total P 4,860.00
NO. OF DAYS COST PER DAY
1,701.00
Sub-Total P 1,701.00
NO. OF DAYS COST PER DAY
- - 0.00
Sub-Total P 0.00
6,561.00
6,561.00

MARY JOY P. MORAN


Supervising Engineer A, CDU-HTDO

BILL ANTHONY A. SIRIBAN


Senior Engineer A, CDU-HTDO

and Submitted by:

Page 122 of 123


D ESTIMATES
Y POLICE ACTION BUILDING

G. PANOPIO
nager, CDU-HTDO

nding Approval:

TA O. REGALA
t Manager, HTDO

roved by:

P. ESCALADA JR.
eral Manager

Page 123 of 123