2018
Progress %
Recovery Plan
Discipline Wt% Cumm. Last Week This Week Cumm. To Date
Forcast Actual Variance Forcast Actual Variance Forcast Actual Variance Recovery Actual Variance
H I J=I-H D F G=F-D H I J=I-H H I J=I-H
General 6.89 6.89 6.89 6.89 6.89 6.89
Geotech Survey 0.41 100.00 100.00 0.00 0.00 0.00 0.00 100.00 100.00 0.00 100.00 100.00 0.00
Construction Subcontracting 1.31 100.00 100.00 0.00 0.00 0.00 0.00 100.00 100.00 0.00 100.00 100.00 0.00
Camp 2.85 100.00 100.00 0.00 0.00 0.00 0.00 100.00 100.00 0.00 100.00 100.00 0.00
Temporary Facilities 2.32 100.00 100.00 0.00 0.00 0.00 0.00 100.00 100.00 0.00 100.00 100.00 0.00
Total General % 6.9 100.00 100.00 0.00 0.00 0.00 0.00 100.00 100.00 0.00 100.00 100.00 0.00
Discipline 90.02 89.99 90.44 90.40 92.83 90.40
Civil 17.94 99.68 99.69 0.01 0.01 0.01 0.00 99.69 99.69 0.00 100.00 99.69 -0.31
Building 5.25 100.00 100.00 0.00 0.00 0.00 0.00 100.00 100.00 0.00 100.00 100.00 0.00
Steel Structure 7.74 100.00 100.00 0.00 0.00 0.00 0.00 100.00 100.00 0.00 100.00 100.00 0.00
UG Piping 1.71 100.00 100.00 0.00 0.00 0.00 0.00 100.00 100.00 0.00 100.00 100.00 0.00
AG Piping 39.26 96.17 96.38 0.21 0.15 0.15 0.00 96.53 96.53 0.00 99.96 96.53 -3.43
Mechanical 4.18 100.00 99.92 -0.08 0.04 0.03 -0.01 99.96 99.95 -0.01 100.00 99.95 -0.05
Electrical 6.14 98.51 98.27 -0.25 0.00 0.00 0.00 98.27 98.27 0.00 99.51 98.27 -1.24
Instrumentation&Control 7.25 95.01 95.03 0.02 0.69 0.71 0.02 95.72 95.74 0.02 99.66 95.74 -3.92
Pre-commissioning 3.64 77.46 73.55 -3.91 3.62 2.57 -1.05 77.17 76.12 -1.05 94.52 76.12 -18.40
Total Discipline % 93.10 96.96 96.88 -0.08 0.26 0.22 -0.04 97.14 97.10 -0.04 99.71 97.10 -2.61
Overall Construction % 100 97.16 97.09 -0.07 0.24 0.20 -0.04 97.33 97.29 -0.04 99.73 97.29 -2.43
Construction Status as of:10,Mar. 2017
Progress %