No.
"SELECCIÓN" Código Descripción Unid. Costo 1
EQ. Y HERRAMIENTA BAI0001 COMPACTADOR BAILARINA HR $0.00 2
EQ. Y HERRAMIENTA EAN0001 ANDAMIO METALICO DE 2 X 2 PZA $0.00 3
EQ. Y HERRAMIENTA EQGA003 REVOLVEDORA MIPSA-KOHLER 1 SACO HR $6.62 4
MAAR0016 ARMADURA SOLDADA CASTILLO ARMEX 15X15-4 MT $4.20
MATERIALES 5
MAAR0017 ARMADURA SOLDADA CASTILLO ARMEX 15X20-4 MT $4.43
MATERIALES
MATERIALES MAGU0010 AGUA M3 $2.21
MATERIALES MALA0180 ALAMBRE RECOCIDO No. 18 KG $2.52
MATERIALES MALA0190 ALAMBRON LISO DEL No.2, DIAM. 1/4"(6MM.) TON $2,000.00 *
MARM0018 ARMADURA SOLDADA CASTILLO ARMEX 15X25-4 MT $4.65
MATERIALES
MATERIALES MBAR0009 VARILLA No.2.5 (5/16") FY=4200KG/CM2. TON $1,250.10
MATERIALES MCEM0010 MORTERO HIDRAULICO TON $245.46
MATERIALES MCEM0050 CALHIDRA TON $241.82
MATERIALES MCEM0060 CEMENTO GRIS EN SACOS TON $350.00
MATERIALES MCLA0021 CLAVO DE 2 1/2" A 3 1/2" KG $2.87
MATERIALES MCOM0010 DIESEL LT $0.78
MATERIALES MDUE0001 DUELA 3/4" X 4" X 8´ PT $3.90
MATERIALES MEZ0002 MORTERO MORTERO - ARENA PROPORCION 1:5 M3 $339.18
MATERIALES MEZ0005 MORTERO CEMENTO-ARENA 1:6 M3 $165.89
MATERIALES MEZ0011 MEZCLA MORTERO-ARENA 1:5 M3 $355.96
MATERIALES MHIL0001 HILO DE PLAST.P/TRAZO EN CARRETE CAL.10 ML $0.00
MIMP0001 IMPERMEABILIZANTE AISLAFLEX 5 A, MARCA LT $0.00
MATERIALES PASA.
MJUNT0001 JUNTEADOR GRIS CON ARENA MARCA SACO $37.39
MATERIALES PERDURA STONE, SACO DE 10 K
MATERIALES MMAD0044 MADERA PINO DE 3a.EN TABLON DE 11/2"X12" PT $2.86
MATERIALES MMAD0045 MADERA PINO DE 3a. EN BARROTE DE 2"X4" PT $2.86
MATERIALES MMAD0047 MADERA PINO DE 3a. EN POLÍN DE 4"X4" REG PT $2.86
MATERIALES MMAD0049 MADERA DUELA DE PINO DE 1a. EN CONTACTO PT $0.00
MMAL0050 MALLA ELECTROSOLDADATECNOMALLA 6X6- M2 $3.32
MATERIALES 10/10
MMAL0080 MALLA ELECTROSOLDADA TECNOMALLA 6X6-6/6 M2 $5.96
MATERIALES
MMAL0090 MALLA ELECTROSOLDADA TECNOMALLA 6X6-8/8 M2 $4.43
MATERIALES
MMEM0001 MEMBRANA DE FIBRA DE POLIESTER#5 PARA M2 $0.00
MATERIALES IMPERMEABILIZACIÓN
MATERIALES MMOR0060 MORTERO TOLTECA TON $1,043.47
MANO DE OBRA. MOMM01 PEON JOR $217.50
MANO DE OBRA. MOMM30 OFICIAL ALBANIL JOR $362.50
MANO DE OBRA. MOMM32 OFICIAL PINTOR JOR $290.00
MATERIALES MPET0040 ARENA P/CONCRETOS M3 $45.46
MATERIALES MPET0170 GRAVA P/CONCRETOS 3/4" M3 $45.46
MATERIALES MPGP0001 PEGAPISO GRIS MARCA PERDURA STONE SACO $40.87
MATERIALES MPIN0001 PINTURA ESMALTE CUB $1,089.56
MATERIALES MPIN0060 PINTURA COLOR BLANCA BERLINTE CUB $668.69
MATERIALES MPIN0069 SELLADOR VINILICO LT $473.91
MATERIALES MPIS0240 PISO VITROMEX BCO. 2 AMERICAS 33X33 CM M2 $96.52
MATERIALES MRES0051 YESO DE RESANADOR KG $0.00
MATERIALES MSEL0001 SELLADOR PASA AISLAFLEX SELLO LT $0.00
MATERIALES MTAB0070 TABIQUE COMUN BARRO R.R. DE 7X14X28 CM. MILL $1,800.00
MATERIALES MTAB0090 TABICON DE CEMENTO VIBRO BLOCK MILL $1,280.10
MATERIALES MVAR0009 7X14X28CM
VARILLA No.3 (3/8") FY=4200 KG/CM2. TON $1,409.09
MATERIALES MVAR0012 VARILLA No.4 (1/2") FY=4200 KG/CM2 TON $1,595.00
MATERIALES MVAR0013 VARILLA No.5 (5/8") FY=4200 KG/CM2. TON $1,413.63
MATERIALES MVAR0014 VARILLA No.6 (3/4") FY=4200 KG/CM2. TON $1,404.54
MATERIALES MVAR0015 VARILLA No.8 (1") FY=4200 KG/CM2. TON $1,395.45
MATERIALES MVAR0016 VARILLA No.10(11/4") FY=4200KG/CM2. TON $1,395.45
MATERIALES MVAR0017 VARILLA NO.12(11/2") FY=4200KG/CM2. TON $1,395.45
MATERIALES PUR0001 PUERTA METALICA 0.70 X 2.10 PZA $0.00
EQ. Y HERRAMIENTA VAGA001 VIBRADOR PARA CONCRETO DYNAPAC INC.OP. HR $0.00
LISTA DE ELEMENTO CONST.
TIPO
MATERIALES
MANO DE OBRA.
EQ. Y HERRAMIENTA
SUBCONTRATOS
* Al seleccionar la celda de
"SELECCIÓN" B5, Se muestra la
cejilla del FILTRO, para verificar el
tipo de elemento constructivo.
CATÁLOGO DE CONCEPTOS CON RENDIMIENTO POR ETAPA
DEMOLICIONES
DEM0001 DEM. CIMIENTOS DE PIEDRA. DEMOLICIONM3 CUADRILLA 001 (1 PEON) 1.50 M3/JOR
DEM0002 DEM. CIM. CONC. ARM. S/REC. ACERO. DEMOLICIONM3 CUADRILLA 001 (1 PEON) 0.60 M3/JOR
DEM0004 DEM. MUROS DE ADOBE Y TEPETATE DEMOLICIONM3 CUADRILLA 001 (1 PEON) 5.50 M3/JOR
DEM0009 DEM. MURO TAB/BLOCK 14 CM. SIN/REC. DEMOLICIONM2 CUADRILLA 001 (1 PEON) 12.50 M2/JOR
DEM0010 DEM. MURO TAB/BLOCK 14 CM. CON/REC. DEMOLICIONM2 CUADRILLA 001 (1 PEON) 6.50 M2/JOR
DEM0014 DEM. CONC. ARMADO EN ESTRUCTURA. DEMOLICIONM3 CUADRILLA 001 (1 PEON) 0.65 M3/JOR
DEM0020 DEM. PISO CONC. SIMPLE 8-10 CM. ESP. DEMOLICIONM2 CUADRILLA 001 (1 PEON) 16.67 M2/JOR
DEM0022 DEM. PISO CONC. ARMADO 8-10 CM. ESP. DEMOLICIONUnidad CUADRILLA 001 (1 PEON) 7.52 Unidad/JOR
DEM0028 DEM. APLANADOS MURO/PLAFÓN 2.5 CM. ESP. DEMOLICIONM2 CUADRILLA 001 (1 PEON) 25.00 M2/JOR
DEM0029 DEM. FALSO PLAFÓN DE YESO. DEMOLICIONM2 CUADRILLA 001 (1 PEON) 19.00 M2/JOR
DEM0043 DEM. CONC. ASFÁLTICO 5-7 CM. ESP. DEMOLICIONM2 CUADRILLA 001 (1 PEON) 22.22 M2/JOR
PRELIMINARES
LTZ0001 LIMPIEZA DEL TERRENO A MANO. LIMPIEZA DE M2 CUADRILLA 001 (1 PEON) 27.03 M2/JOR
EXC0001 EXCAV. MANUAL CEPAS SUELO TIPO II EXCAVACIÓNM3 CUADRILLA 001 (1 PEON) 2.78 M3/JOR
LTZ0005 TRAZO Y NIVELACIÓN MANUAL TRAZO Y NI M2 CUADRILLA 040 100.00 M2/JOR
(1ALBANIL+1PEON)
CIMENTACIÓN
CIM0001 CIM. MANPOSTERIA 60,30 X 80 CM. MORT.1:5 CIMENTACION
M3 CUADRILLA 040 2.75 M3/JOR
RELL01CC RELLENO CIM. COMP. BAILARINA 90% RELLENO ENM3 (1ALBANIL+1PEON)
CUADRILLA 001 (1 PEON) 4.35 M3/JOR
RELL01CM RELLENO CIM. COMP. MANUAL RELLENO DEM3 CUADRILLA 001 (1 PEON) 4.35 M3/JOR
CASTILLOS Y COLUMNAS
CAST001V CASTILLO 15X15 , FC=150, 4 VARS. #3, 2 C CASTILLO COM CUADRILLA 040 10.84 M/JOR
CAST002V CASTILLO 15X15 , FC=200, 4 VARS. #3, 2 C CASTILLO COM (1ALBANIL+1PEON)
CUADRILLA 040 10.84 M/JOR
CAST003V CASTILLO 15X15 , FC=250, 4 VARS. #3, 2 C CASTILLO COM (1ALBANIL+1PEON)
CUADRILLA 040 10.84 M/JOR
CAST004V CASTILLO 15X20 , FC=150, 4 VARS. #3, 2 C CASTILLO COM (1ALBANIL+1PEON)
CUADRILLA 040 9.79 M/JOR
CAST005V CASTILLO 15X20 , FC=200, 4 VARS. #3, 2 C CASTILLO COM (1ALBANIL+1PEON)
CUADRILLA 040 9.79 M/JOR
CAST010V CASTILLO CON SECCION DE 15X30 CM DE CONC CASTILLO COM (1ALBANIL+1PEON)
CUADRILLA 040 9.64 M/JOR
CAST006V CASTILLO 15X20, FC=250, 4 VARS. #3, 2 C CASTILLO COM (1ALBANIL+1PEON)
CUADRILLA 040 9.79 M/JOR
CAST007V CASTILLO 20X20 , FC=150, 4 VARS. #3, 2 C CASTILLO COM (1ALBANIL+1PEON)
CUADRILLA 040 8.74 M/JOR
CAST008V CASTILLO 20X20 , FC=200, 4 VARS. #3, 2 C CASTILLO COM (1ALBANIL+1PEON)
CUADRILLA 040 8.74 M/JOR
CAST009V CASTILLO 20X20, FC=250, 4 VARS. #3, 2 C CASTILLO COM (1ALBANIL+1PEON)
CUADRILLA 040 8.74 M/JOR
(1ALBANIL+1PEON)
CONTRATRABES, TRABES Y CADENAS.
DALA001A DALA 15X15 , FC=150, ARMEX 15X15-4, 2 C DALA CON S M CUADRILLA 040 12.76 M/JOR
DALA002A DALA 15X15 , FC=200, ARMEX 15X15-4, 2 C DALA CON S M (1ALBANIL+1PEON)
CUADRILLA 040 12.76 M/JOR
DALA003A DALA 15X15 , FC=250, ARMEX 15X15-4, 2 C DALA CON S M (1ALBANIL+1PEON)
CUADRILLA 040 12.76 M/JOR
DALA004A DALA 15X20, FC=150, ARMEX 15X20-4, 2 C DALA CON S M (1ALBANIL+1PEON)
CUADRILLA 040 12.12 M/JOR
DALA005A DALA 15X20, FC=200, ARMEX 15X20-4, 2 C DALA CON S M (1ALBANIL+1PEON)
CUADRILLA 040 12.12 M/JOR
DALA006A DALA 15X20, FC=250, ARMEX 15X20-4, 2 C DALA CON S M (1ALBANIL+1PEON)
CUADRILLA 040 12.12 M/JOR
DALA007A DALA 20X20, FC=150, ARMEX 15X20-4, 2 C DALA CON S M (1ALBANIL+1PEON)
CUADRILLA 040 11.48 M/JOR
DALA008A DALA 20X20, FC=200, ARMEX 15X20-4, 2 C DALA CON S M (1ALBANIL+1PEON)
CUADRILLA 040 11.48 M/JOR
DALA009A DALA 20X20, FC=250, ARMEX 15X20-4, 2 C DALA CON S M (1ALBANIL+1PEON)
CUADRILLA 040 11.48 M/JOR
(1ALBANIL+1PEON)
FIRMES
PLA05-100 PLANTILLA CONC. SIMPLE F`C =100 KG/CM2 PLANTILLA DM2 CUADRILLA 040 20.00 M2/JOR
PIS05-100 FIRME 5 CM, FC 100, RN, AGR. 3/4". FIRME DE COM2 (1ALBANIL+1PEON)
CUADRILLA 040 15.00 M2/JOR
PIS05-150 FIRME 5 CM, FC 150, RN, AGR. 3/4". FIRME DE COM2 (1ALBANIL+1PEON)
CUADRILLA 040 15.00 M2/JOR
PIS08-150 FIRME 8 CM, FC 150, RN, AGR. 3/4". FIRME DE COM2 (1ALBANIL+1PEON)
CUADRILLA 040 15.00 M2/JOR
PIS08-200 FIRME 8 CM, FC 200, RN, AGR. 3/4". FIRME DE COM2 (1ALBANIL+1PEON)
CUADRILLA 040 15.00 M2/JOR
PIS10-150 FIRME 10 CM, FC 150, RN, AGR. 3/4". FIRME DE COM2 (1ALBANIL+1PEON)
CUADRILLA 040 15.00 M2/JOR
PIS10-200 FIRME 10 CM, FC 200, RN, AGR. 3/4". FIRME DE COM2 (1ALBANIL+1PEON)
CUADRILLA 040 15.00 M2/JOR
PIS15-150 FIRME 15 CM, FC 150, RN, AGR. 3/4". FIRME DE COM2 (1ALBANIL+1PEON)
CUADRILLA 040 12.00 M2/JOR
PIS15-200 FIRME 15 CM, FC 200, RN, AGR. 3/4". FIRME DE COM2 (1ALBANIL+1PEON)
CUADRILLA 040 12.00 M2/JOR
(1ALBANIL+1PEON)
MUROS
MURLAD7 MURO TRR, 7 CM, MOR 1:5, JUNTA 1.5, AC. MURO DE TAB
M2 CUADRILLA 040 12.00 M2/JOR
MURLAD14 MURO TRR, 14 CM, MOR 1:5, JUNTA 1.5, AC. MURO DE TAB
M2 (1ALBANIL+1PEON)
CUADRILLA 040 10.00 M2/JOR
MURLAD28 MURO TRR, 28 CM, MOR 1:5, JUNTA 1.5, AC. MURO DE TAB
M2 (1ALBANIL+1PEON)
CUADRILLA 040 6.49 M2/JOR
MURTAB10 MURO TAB, 10 CM, MOR 1:5, JUNTA 1.5, AC. MURO DE TAB
M2 (1ALBANIL+1PEON)
CUADRILLA 040 10.00 M2/JOR
MURTAB14 MURO TAB, 14 CM, MOR 1:5, JUNTA 1.5, AC. MURO DE TAB
M2 (1ALBANIL+1PEON)
CUADRILLA 040 10.00 M2/JOR
MURTAB28 MURO TAB, 28 CM, MOR 1:5, JUNTA 1.5, AC. MURO DE TAB
M2 (1ALBANIL+1PEON)
CUADRILLA 040 10.00 M2/JOR
MURPRET15 MUR. PRETIL PERIM. 7X14X28, 15 CM. MURO DE PRM (1ALBANIL+1PEON)
CUADRILLA 040 5.00 M/JOR
(1ALBANIL+1PEON)
MUROS ESPECIALES
MURTABI1 MURO LAMBRÍN DE TABLAROCA TIPO INTERIOR M2
MURTABE1 MURO LAMBRÍN DE TABLAROCA TIPO INTEMPERI M2
MURTABI2 MURO DE TABLAROCA A 2 CARAS TIPO INTERIO M2
MURTABE2 MURO DE TABLAROCA A 2 CARAS TIPO INTEMPE M2
MURMIXID MURO MIXTO TABLAROCA TIPO INTERIOR - DUR M2
MURMIXED MURO MIXTO TABLAROCA TIPO INTEMPERIE - D M2
MURMIXIE MURO DE TABLAROCA TIPO INTERIOR - INTEM M2
MURDUR2 MURO A 2 CARAS DE DUROK. M2
PLATAB001 PLAFÓN DE TABLAROCA M2
PLAPOLI001 PLAFÓN DE POLIESTIRENO DE 1" DE ESP. CON M2
DETTAB001 FABRICACIÓN DE DETALLES DE TABLAROCA (EN M2
DETTAB002 FABRICACIÓN DE BOQUILLAS. ML
MDURINT MURO LAMBRIN DE DUROK M2
ENTREPISOS Y CUBIERTAS
LOSA10-200 LOSA TECHO 10 CM, VAR. #3, FC=200 LOSA DE 10 M2
LOSA10-250 LOSA TECHO 10 CM, VAR. #3, FC=250 LOSA DE 10 M2
HERRERÍA Y CANCELERÍA
PTA0001 SUMINISTRO Y COLOCACIÓN DE PUERTA DE 0.7 SUMINISTROPZA CUADRILLA 040 2.50 PZA/JOR
VENT0001 SUMINISTRO Y COLOCACIÓN DE VENTANA METÁL SUMINISTROPZA (1ALBANIL+1PEON)
CUADRILLA 040 2.50 PZA/JOR
(1ALBANIL+1PEON)
ACABADOS
PIS0080 PISO DE CERÁMICA VITROMEX 33X33 CM. SUMINISTROM2 CUADRILLA 040 12.00 M2/JOR
PIN0001 PINTURA VINILICA EN MUROS Y PLAFONES SUMINISTROM2 (1ALBANIL+1PEON)
CUADRILLA 060 (1 PINTOR) 20.00 M2/JOR
PIN0002 SUMINISTRO Y APLICACIÓN DE PINTURA ESMAL SUMINISTROM2 CUADRILLA 060 (1 PINTOR) 21.45 M2/JOR
IMP0001 IMPERMEABILIZACIÓN DE LOSA DE AZOTEA SUMINISTROM2 CUADRILLA 040 30.00 M2/JOR
APL0025 EMBOQ. REPELLADO C/CEMENTO Y ARENA 1:6 EMBOQUILLAM (1ALBANIL+1PEON)
CUADRILLA 040 26.71 M/JOR
APL0022 APLANADO PLAFONES C/MORTERO Y ARENA 1:5 APLANADO EM2 (1ALBANIL+1PEON)
CUADRILLA 040 9.00 M2/JOR
PSO0001 ACABADO ESCOBILLADO INTEGAL PSO CONC. ACABADO ESM2 (1ALBANIL+1PEON)
CUADRILLA 040 45.45 M2/JOR
PSO0002 ACABADO PULIDO INTEGRAL PISO CONC. ACABADO PUM2 (1ALBANIL+1PEON)
CUADRILLA 040 30.00 M2/JOR
(1ALBANIL+1PEON)
FABRICACION DE MEZCLAS, MORTEROS Y CONCR
MEZ0003 MORTERO CEMENTO-ARENA 1:4 M3
MEZ0004 MORTERO CEMENTO-ARENA 1:5 M3
MEZ0005 MORTERO CEMENTO-ARENA 1:6 M3
MEZ0006 MORTERO CEMENTO-ARENA 1:7 M3
MEZ0007 MORTERO CEMENTO-ARENA 1:8 M3
MEZ0009 MEZCLA MORTERO-ARENA 1:3 M3
MEZ0010 MEZCLA MORTERO-ARENA 1:4 M3
MEZ0011 MEZCLA MORTERO-ARENA 1:5 M3
MEZ0012 MEZCLA MORTERO-ARENA 1:6 M3
MEZ0013 MEZCLA MORTERO-ARENA 1:7 M3
MEZ0014 MEZCLA MORTERO-ARENA 1:8 M3
FCO100M CONC. FC=100, RN, AGR MAX. 3/4", MANUAL. CONCRETO F'M3 CUADRILLA 001 (1 PEON) 1.59 M3/JOR
FCO100R CONC. FC=100, RN, AGR MAX. 3/4", REVOLV. CONCRETO F'M3 CUADRILLA 005 (5 PEONES) 15.02 M3/JOR
FCO150M CONC. FC=150, RN, AGR MAX. 3/4", MANUAL. CONCRETO FM3 CUADRILLA 001 (1 PEON) 1.59 M3/JOR
FCO150R CONC. FC=150, RN, AGR MAX. 3/4", REVOLV. CONCRETO FM3 CUADRILLA 005 (5 PEONES) 15.02 M3/JOR
FCO200M CONC. FC=200, RN, AGR MAX. 3/4", MANUAL. CONCRETO FM3 CUADRILLA 001 (1 PEON) 1.59 M3/JOR
FCO200R CONC. FC=200, RN, AGR MAX. 3/4", REVOLV. CONCRETO FM3 CUADRILLA 005 (5 PEONES) 15.02 M3/JOR
FCO250M CONC. FC=250, RN, AGR MAX. 3/4", MANUAL. CONCRETO FM3 CUADRILLA 001 (1 PEON) 1.50 M3/JOR
FCO250R CONC. FC=250, RN, AGR MAX. 3/4", REVOLV. CONCRETO FM3 CUADRILLA 005 (5 PEONES) 15.00 M3/JOR
ACARREOS
ACR0009 ACARREO CARR. SACOS: CEM. MORT. CAL. ACARREO ENM3 CUADRILLA 001 (1 PEON) 13.33 M3/JOR
ACR0012 ACARREO CARR. AGREGADOS MORT. CONCRETOS. ACARREO ENM3 CUADRILLA 001 (1 PEON) 5.25 M3/JOR
ACR0013 ACARREO CARR. PIEDRA BRAZA. ACARREO ENM3 CUADRILLA 001 (1 PEON) 5.50 M3/JOR
ACR0037 ACARREO A MANO MADERA P/CIMBRA. ACARREO A MIL CUADRILLA 001 (1 PEON) ### MIL/JOR
ACR0082A ACARREO EN CAM. A PRIM. KM. VOL. MED. M3
CIMBRAS
CFZAP CIMB./DESCIM, ACAB. COMÚN FRONTERAS/ZAP. CIMBRA Y D M2 CUADRILLA 040 7.97 M2/JOR
CDADO CIMB./DESCIM, ACAB. COMÚN CONTRATRABES CIMBRA Y D M2 (1ALBANIL+1PEON)
CUADRILLA 040 7.97 M2/JOR
(1ALBANIL+1PEON)
CCADE CIMB./DESCIM, ACAB. COMÚN CADENAS. CIMBRA Y D M2 CUADRILLA 040 14.01 M2/JOR
CCAST CIMB./DESCIM, ACAB. COMÚN CASTILLOS. CIMBRA Y D M2 (1ALBANIL+1PEON)
CUADRILLA 040 14.01 M2/JOR
CCOL30X30 CIMB./DESCIM, ACAB. COMÚN COLUMNAS 30X30 CIMBRA Y DEM2 (1ALBANIL+1PEON)
CUADRILLA 040 6.95 M2/JOR
CCOL50X50 CIMB./DESCIM, ACAB. COMÚN COLUMNAS 50X50 CIMBRA Y DEM2 (1ALBANIL+1PEON)
CUADRILLA 040 6.65 M2/JOR
(1ALBANIL+1PEON)
VACIADOS
VDACAS150 VAC. DALA Y CAST, FC=150, RN. AGR. 3/4" VACIADO DE M3 CUADRILLA 040 1.33 M3/JOR
VDACAS200 VAC. DALA Y CAST, FC=200, RN. AGR. 3/4" VACIADO DE M3 (1ALBANIL+1PEON)
CUADRILLA 040 1.33 M3/JOR
VDACAS250 VAC. DALA Y CAST, FC=250, RN. AGR. 3/4" VACIADO DE M3 (1ALBANIL+1PEON)
CUADRILLA 040 1.33 M3/JOR
VCL200 VAC. COLUMNAS P.B, FC=200, RN, AGR 3/4" VACIADO DE M3 (1ALBANIL+1PEON)
CUADRILLA 040 2.50 M3/JOR
VCL250 VAC. COLUMNAS P.B, FC=250, RN, AGR 3/4" VACIADO DE M3 (1ALBANIL+1PEON)
CUADRILLA 040 2.50 M3/JOR
VZTL150 VAC. ZAP. CIM, FC=150, RN. AGR. 3/4" VACIADO DE M3 (1ALBANIL+1PEON)
CUADRILLA 040 3.24 M3/JOR
VZTL200 VAC. ZAP. CIM, FC=200, RN. AGR. 3/4" VACIADO DE M3 (1ALBANIL+1PEON)
CUADRILLA 040 3.24 M3/JOR
VZTL250 VAC. ZAP. CIM, FC=250, RN. AGR. 3/4" VACIADO DE M3 (1ALBANIL+1PEON)
CUADRILLA 040 3.24 M3/JOR
VCOL150 VAC, COLUMAS S/E, FC=150, RN, AGR. 3/4" VACIADO DE M3 (1ALBANIL+1PEON)
CUADRILLA 040 3.10 M3/JOR
VCOL200 VAC, COLUMAS S/E, FC=200, RN, AGR. 3/4" VACIADO DE M3 (1ALBANIL+1PEON)
CUADRILLA 040 3.10 M3/JOR
VCOL250 VAC, COLUMAS S/E, FC=250, RN, AGR. 3/4" VACIADO DE M3 (1ALBANIL+1PEON)
CUADRILLA 040 3.10 M3/JOR
VTRABE200 VAC. TRABES S/E, FC=200, RN, AGR.3/4" VACIADO DE M3 (1ALBANIL+1PEON)
CUADRILLA 040 3.10 M3/JOR
VTRABE250 VAC. TRABES S/E, FC=250, RN, AGR.3/4" VACIADO DE M3 (1ALBANIL+1PEON)
CUADRILLA 040 3.10 M3/JOR
VLOSA150 VAC.. LOSAS S/E, FC=150, RN, AGR.3/4" VACIADO DE M3 (1ALBANIL+1PEON)
CUADRILLA 040 2.50 M3/JOR
VLOSA200 VAC.. LOSAS S/E, FC=200, RN, AGR.3/4" VACIADO DE M3 (1ALBANIL+1PEON)
CUADRILLA 040 2.50 M3/JOR
VLOSA250 VAC., LOSAS ,S/E, F´C=250, RN. AGR.3/4" VACIADO DE M3 (1ALBANIL+1PEON)
CUADRILLA 040 2.50 M3/JOR
VCIM100R VAC.. CIMENTACIÓN, FC=100, RN, AGR.3/4" VACIADO DE M3 (1ALBANIL+1PEON)
CUADRILLA 040 3.24 M3/JOR
VCIM150R VAC.. CIMENTACIÓN, FC=150, RN, AGR.3/4" VACIADO DE M3 (1ALBANIL+1PEON)
CUADRILLA 040 3.24 M3/JOR
VCIM200R VAC.. CIMENTACIÓN, FC=200, RN, AGR.3/4" VACIADO DE M3 (1ALBANIL+1PEON)
CUADRILLA 040 3.24 M3/JOR
VCIM250R VAC.. CIMENTACIÓN, FC=250, RN, AGR.3/4" VACIADO DE M3 (1ALBANIL+1PEON)
CUADRILLA 040 3.24 M3/JOR
(1ALBANIL+1PEON)
Tarjetas de análisis de precios unitarios de Básicos
* BÁSICOS Lista de elementos que componen la BASE de datos que intervienen generalmente en un Análisis de PU.
* Como se muestra en la mayor parte de las tarjetas, la mano de obra es de Albañil y peón. Esto es, porque en obra pequeña,
son ellos los que realizan la mayor parte de los trabajos. Pero para obra grande, es necesario desglosar la mano de obra, con
las categorías referentes a cada trabajo. En mi caso, estoy tomando la mano de obra de una obra común.
FCO100R CONCRETO F'C=100 KG/CM2, RESISTENCIA NORMAL, AGR.MAX. 3/4, FABRICADO EN OBRA M3
EN REVOLVEDORA DE 1 SACO; ACARREO MATERIAL PRIMERA ESTACION 20.00 M.
FCO150M CONCRETO F'C=150 KG/CM2, RESISTENCIA NORMAL, AGR.MAX. 3/4, FABRICADO EN OBRA M3
POR MEDIOS MANUALES; ACARREO MATERIAL PRIMERA ESTACION 20.00 M.
FCO150R CONCRETO F'C=150 KG/CM2, RESISTENCIA NORMAL, AGR.MAX. 3/4, FABRICADO EN OBRA M3
EN REVOLVEDORA DE 1 SACO; ACARREO MATERIAL PRIMERA ESTACION 20.00 M.
FCO200M CONCRETO F'C=200 KG/CM2, RESISTENCIA NORMAL, AGR.MAX. 3/4, FABRICADO EN OBRA M3
POR MEDIOS MANUALES; ACARREO MATERIAL PRIMERA ESTACION 20.00 M.
FCO200R CONCRETO F'C=200 KG/CM2, RESISTENCIA NORMAL, AGR.MAX. 3/4, FABRICADO EN OBRA M3
EN REVOLVEDORA DE 1 SACO; ACARREO MATERIAL PRIMERA ESTACION 20.00 M.
FCO250M CONCRETO F'C=250 KG/CM2, RESISTENCIA NORMAL, AGR.MAX. 3/4, FABRICADO EN OBRA M3
POR MEDIOS MANUALES; ACARREO MATERIAL PRIMERA ESTACION 20.00 M.
FCO250R CONCRETO F'C=250 KG/CM2, RESISTENCIA NORMAL, AGR.MAX. 3/4, FABRICADO EN OBRA M3
EN REVOLVEDORA DE 1 SACO; ACARREO MATERIAL PRIMERA ESTACION 20.00 M.
AREF2 HABILITADO Y ARMADO DE ACERO DE REFUERZO EN ESTRUCTURA, FY=3000 KG/CM2, No. 2 TON
DIAMETRO 1/4" (ALAMBRÓN), SIN INCLUIR TRASLAPES; ACARREO MATERIAL PRIMERA
ESTACION = 20.00 M
AREF2 HABILITADO Y ARMADO DE ACERO DE REFUERZO EN ESTRUCTURA, FY=3000 KG/CM2, No. 2 TON
DIAMETRO 1/4" (ALAMBRÓN), SIN INCLUIR TRASLAPES; ACARREO MATERIAL PRIMERA
ESTACION = 20.00 M
AREF3 HABILITADO Y ARMADO DE ACERO DE REFUERZO EN ESTRUCTURA, FY=4200 KG/CM2, No.3 TON
DIAMETRO 3/8", SIN INCLUIR GANCHOS, TRASLAMPES NI ANCLAJES,ACARREO MATERIAL
PRIMERA ESTACION =20.00 M
AREF5 HABILITADO Y ARMADO DE ACERO DE REFUERZO EN ESTRUCTURA, FY=4200 KG/CM2, No.5 TON
DIAMETRO 5/8", SIN INCLUIR GANCHOS, TRASLAMPES NI ANCLAJES,ACARREO MATERIAL
PRIMERA ESTACION =20.00 M
AREF6 HABILITADO Y ARMADO DE ACERO DE REFUERZO EN ESTRUCTURA, FY=4200 KG/CM2, No.6 TON
DIAMETRO 3/4", SIN INCLUIR GANCHOS, TRASLAMPES NI ANCLAJES,ACARREO MATERIAL
PRIMERA ESTACION =20.00 M
Subtotal: MATERIALES
Subtotal: MANO DE OBRA $3.76
Costo directo $6.69
INDIRECTO $0.00
UTILIDADES $0.00
COSTO TOTAL $6.69
Subtotal: MATERIALES
Subtotal: MANO DE OBRA $4.77
Costo directo $5.46
INDIRECTO $10.23
UTILIDADES $1.02
COSTO TOTAL $1.02
Subtotal: MATERIALES
Subtotal: MANO DE OBRA $5.03
Costo directo $5.46
INDIRECTO $0.00
UTILIDADES $0.00
COSTO TOTAL $5.46
CCAST CIMBRA Y DESCIMBRA ACABADO COMÚN EN CASTILLOS DE SECCIÓN MAYOR A 0.020 M2, M2
INCLUYE: MATERIALES Y MANO DE OBRA.
DEM0001 DEMOLICION A MANO DE CIMIENTOS DE PIEDRA BRASA, SIN INCLUIR ACARREOS, HASTA m3
1.50 M DE PROFUNDIDAD.
Código Concepto Unidad Rend. Cantidad Costo Importe
MANO DE OBRA
CUAD001 CUADRILLA 001 (1 PEON) JOR 1.50 0.666667 $245.78 $163.85
DEM0029 DEMOLICION A MANO DE FALSO PLAFON DE YESO, SIN INCLUIR ACARREOS, HASTA 2.50 M2
M DE ALTURA.
LTZ0001 LIMPIEZA DEL TERRENO PLANO A MANO, INCLUYE: APILE DEL MATERIAL EN EL LUGAR Y M2
ACARREO DEL MISMO A 1a. ESTACIÓN DE 20 M.
EXC0001 EXCAVACIÓN A MANO DE CEPAS PARA CIMENTACIÓN, EN SUELO TIPO II, HASTA UNA M3
ALTURA DE CEPA DE 2.00 M. NO INCLUYE ACARREO.
LTZ0005 TRAZO Y NIVELACIÓN POR MEDIOS MANUALES DEL TERRENO PLANO, PARA DESPLANTE M2
DE ESTRUCTURAS, ESTABLECIENDO EJES AUXILIARES, PASOS Y REFERENCIAS.
INCLUYE:MATERIALES Y MANO DE OBRA.
CAST001V CASTILLO CON SECCION DE 15X15 CM DE CONCRETO F'C=150 KG/CM2, R. N. AGR. MAX. M
3/4, REFORZADO CON 4 VARILLAS DE 3/8" DIAM. Y ESTRIBOS DE 1/4" DIAM. A CADA 20
CM, CON CIMBRA COMÚN 2 CARAS.
AREF2 HABILITADO Y ARMADO DE ACERO DE REFUERZO EN TON 0.00 0.001000 ### $8.78
ESTRUCTURA, FY=3000 KG/CM2, No. 2 DIAMETRO 1/4"
(ALAMBRÓN), SIN INCLUIR TRASLAPES; ACARREO
MATERIAL PRIMERA ESTACION = 20.00 M
CCAST CIMBRA Y DESCIMBRA ACABADO COMÚN EN CASTILLOS M2 0.00 0.300000 $65.92 $19.78
DE SECCIÓN MAYOR A 0.020 M2, INCLUYE: MATERIALES
Y MANO DE OBRA.
VDACAS150 VACIADO DE CONCRETO HECHO EN OBRA CON M3 0.00 0.022500 $759.21 $17.08
REVOLVEDORA 1 SACO, EN DALAS Y CASTILLOS DE
SECCIÓN >0.02 M2, F´C=150 KG/CM2, RESISTENCIA
NORMAL, TAMAÑO MÁXIMO DE AGREGADO 20 MM. (3/4"),
INCLUYE: VIBRADO, CURADO, ACARREO A UNA 1a.
ESTACIÓN A 20 M. MATERIALES Y
CAST002V CASTILLO CON SECCION DE 15X15 CM DE CONCRETO F'C=200 KG/CM2, R. N. AGR. MAX. M
3/4, REFORZADO CON 4 VARILLAS DE 3/8" DIAM. Y ESTRIBOS DE 1/4" DIAM. A CADA 20
CM, CON CIMBRA COMÚN 2 CARAS.
AREF2 HABILITADO Y ARMADO DE ACERO DE REFUERZO EN TON 0.00 0.001000 ### $8.78
ESTRUCTURA, FY=3000 KG/CM2, No. 2 DIAMETRO 1/4"
(ALAMBRÓN), SIN INCLUIR TRASLAPES; ACARREO
MATERIAL PRIMERA ESTACION = 20.00 M
CCAST CIMBRA Y DESCIMBRA ACABADO COMÚN EN CASTILLOS M2 0.00 0.300000 $65.92 $19.78
DE SECCIÓN MAYOR A 0.020 M2, INCLUYE: MATERIALES
Y MANO DE OBRA.
VDACAS200 VACIADO DE CONCRETO HECHO EN OBRA CON M3 0.00 0.022500 $773.81 $17.41
REVOLVEDORA 1 SACO, EN DALAS Y CASTILLOS DE
SECCIÓN >0.02 M2, F´C=200 KG/CM2, RESISTENCIA
NORMAL, TAMAÑO MÁXIMO DE AGREGADO 20 MM. (3/4"),
INCLUYE: VIBRADO, CURADO, ACARREO A UNA 1a.
ESTACIÓN A 20 M. MATERIALES Y
CAST003V CASTILLO CON SECCION DE 15X15 CM DE CONCRETO F'C=250 KG/CM2, R. N. AGR. MAX. M
3/4, REFORZADO CON 4 VARILLAS DE 3/8" DIAM. Y ESTRIBOS DE 1/4" DIAM. A CADA 20
CM, CON CIMBRA COMÚN 2 CARAS.
AREF2 HABILITADO Y ARMADO DE ACERO DE REFUERZO EN TON 0.00 0.001000 ### $8.78
ESTRUCTURA, FY=3000 KG/CM2, No. 2 DIAMETRO 1/4"
(ALAMBRÓN), SIN INCLUIR TRASLAPES; ACARREO
MATERIAL PRIMERA ESTACION = 20.00 M
CCAST CIMBRA Y DESCIMBRA ACABADO COMÚN EN CASTILLOS M2 0.00 0.300000 $65.92 $19.78
DE SECCIÓN MAYOR A 0.020 M2, INCLUYE: MATERIALES
Y MANO DE OBRA.
VDACAS250 VACIADO DE CONCRETO HECHO EN OBRA CON M3 0.00 0.022500 $773.81 $17.41
REVOLVEDORA 1 SACO, EN DALAS Y CASTILLOS DE
SECCIÓN >0.02 M2, F´C=250 KG/CM2, RESISTENCIA
NORMAL, TAMAÑO MÁXIMO DE AGREGADO 20 MM. (3/4"),
INCLUYE: VIBRADO, CURADO, ACARREO A UNA 1a.
ESTACIÓN A 20 M. MATERIALES Y
CAST004V CASTILLO CON SECCION DE 15X20 CM DE CONCRETO F'C=150 KG/CM2, R. N. AGR. MAX. M
3/4, REFORZADO CON 4 VARILLAS DE 3/8" DIAM. Y ESTRIBOS DE 1/4" DIAM. A CADA 20
CM, CON CIMBRA COMÚN 2 CARAS.
MATERIALES
MALA0180 ALAMBRE RECOCIDO No. 18 KG 0.00 0.130000 $2.52 $0.33
MANO DE OBRA
CUAD040 CUADRILLA 040 (1ALBANIL+1PEON) JOR 9.79 0.102145 $655.40 $66.95
SUBCONTRATOS
EAN0001 ANDAMIO METALICO DE 2 X 2 PZA 0.00 0.102145 $0.00 $0.00
BASICOS
AREF3 HABILITADO Y ARMADO DE ACERO DE REFUERZO EN TON 0.00 0.002520 ### $15.82
ESTRUCTURA, FY=4200 KG/CM2, No.3, DIAMETRO 3/8",
SIN INCLUIR GANCHOS, TRASLAPES NI ANCLAJES,
ACARREO MATERIAL PRIMERA ESTACION = 20.00 M
AREF2 HABILITADO Y ARMADO DE ACERO DE REFUERZO EN TON 0.00 0.001680 ### $14.76
ESTRUCTURA, FY=3000 KG/CM2, No. 2 DIAMETRO 1/4"
(ALAMBRÓN), SIN INCLUIR TRASLAPES; ACARREO
MATERIAL PRIMERA ESTACION = 20.00 M
CCAST CIMBRA Y DESCIMBRA ACABADO COMÚN EN CASTILLOS M2 0.00 0.350000 $65.92 $23.07
DE SECCIÓN MAYOR A 0.020 M2, INCLUYE: MATERIALES
Y MANO DE OBRA.
VDACAS150 VACIADO DE CONCRETO HECHO EN OBRA CON M3 0.00 0.030000 $759.21 $22.78
REVOLVEDORA 1 SACO, EN DALAS Y CASTILLOS DE
SECCIÓN >0.02 M2, F´C=150 KG/CM2, RESISTENCIA
NORMAL, TAMAÑO MÁXIMO DE AGREGADO 20 MM. (3/4"),
INCLUYE: VIBRADO, CURADO, ACARREO A UNA 1a.
ESTACIÓN A 20 M. MATERIALES Y
AREF2 HABILITADO Y ARMADO DE ACERO DE REFUERZO EN TON 0.00 0.001680 ### $14.76
ESTRUCTURA, FY=3000 KG/CM2, No. 2 DIAMETRO 1/4"
(ALAMBRÓN), SIN INCLUIR TRASLAPES; ACARREO
MATERIAL PRIMERA ESTACION = 20.00 M
CCAST CIMBRA Y DESCIMBRA ACABADO COMÚN EN CASTILLOS M2 0.00 0.350000 $65.92 $23.07
DE SECCIÓN MAYOR A 0.020 M2, INCLUYE: MATERIALES
Y MANO DE OBRA.
VDACAS200 VACIADO DE CONCRETO HECHO EN OBRA CON M3 0.00 0.030000 $773.81 $23.21
REVOLVEDORA 1 SACO, EN DALAS Y CASTILLOS DE
SECCIÓN >0.02 M2, F´C=200 KG/CM2, RESISTENCIA
NORMAL, TAMAÑO MÁXIMO DE AGREGADO 20 MM. (3/4"),
INCLUYE: VIBRADO, CURADO, ACARREO A UNA 1a.
ESTACIÓN A 20 M. MATERIALES Y
CAST010V CASTILLO CON SECCION DE 15X30 CM DE CONCRETO F'C=200 KG/CM2, R. N. AGR. MAX. M
3/4, REFORZADO CON 4 VARILLAS DE 3/8" DIAM. Y ESTRIBOS DE 1/4" DIAM. A CADA 20
CM, CON CIMBRA COMÚN 2 CARAS.
CSAT006V CASTILLO CON SECCION DE 15X20 CM DE CONCRETO F'C=250 KG/CM2, R. N. AGR. MAX. M
3/4, REFORZADO CON 4 VARILLAS DE 3/8" DIAM. Y ESTRIBOS DE 1/4" DIAM. A CADA 20
CM, CON CIMBRA COMÚN 2 CARAS.
AREF2 HABILITADO Y ARMADO DE ACERO DE REFUERZO EN TON 0.00 0.001680 ### $14.76
ESTRUCTURA, FY=3000 KG/CM2, No. 2 DIAMETRO 1/4"
(ALAMBRÓN), SIN INCLUIR TRASLAPES; ACARREO
MATERIAL PRIMERA ESTACION = 20.00 M
CCAST CIMBRA Y DESCIMBRA ACABADO COMÚN EN CASTILLOS M2 0.00 0.350000 $65.92 $23.07
DE SECCIÓN MAYOR A 0.020 M2, INCLUYE: MATERIALES
Y MANO DE OBRA.
VDACAS250 VACIADO DE CONCRETO HECHO EN OBRA CON M3 0.00 0.030000 $773.81 $23.21
REVOLVEDORA 1 SACO, EN DALAS Y CASTILLOS DE
SECCIÓN >0.02 M2, F´C=250 KG/CM2, RESISTENCIA
NORMAL, TAMAÑO MÁXIMO DE AGREGADO 20 MM. (3/4"),
INCLUYE: VIBRADO, CURADO, ACARREO A UNA 1a.
ESTACIÓN A 20 M. MATERIALES Y
CAST007V CASTILLO CON SECCION DE 20X20 CM DE CONCRETO F'C=150 KG/CM2, R. N. AGR. MAX. M
3/4, REFORZADO CON 4 VARILLAS DE 3/8" DIAM. Y ESTRIBOS DE 1/4" DIAM. A CADA 20
CM, CON CIMBRA COMÚN 2 CARAS.
AREF2 HABILITADO Y ARMADO DE ACERO DE REFUERZO EN TON 0.00 0.001800 ### $15.81
ESTRUCTURA, FY=3000 KG/CM2, No. 2 DIAMETRO 1/4"
(ALAMBRÓN), SIN INCLUIR TRASLAPES; ACARREO
MATERIAL PRIMERA ESTACION = 20.00 M
CCAST CIMBRA Y DESCIMBRA ACABADO COMÚN EN CASTILLOS M2 0.00 0.400000 $65.92 $26.37
DE SECCIÓN MAYOR A 0.020 M2, INCLUYE: MATERIALES
Y MANO DE OBRA.
VDACAS150 VACIADO DE CONCRETO HECHO EN OBRA CON M3 0.00 0.040000 $759.21 $30.37
REVOLVEDORA 1 SACO, EN DALAS Y CASTILLOS DE
SECCIÓN >0.02 M2, F´C=150 KG/CM2, RESISTENCIA
NORMAL, TAMAÑO MÁXIMO DE AGREGADO 20 MM. (3/4"),
INCLUYE: VIBRADO, CURADO, ACARREO A UNA 1a.
ESTACIÓN A 20 M. MATERIALES Y
CAST008V CASTILLO CON SECCION DE 20X20 CM DE CONCRETO F'C=200 KG/CM2, R. N. AGR. MAX. M
3/4, REFORZADO CON 4 VARILLAS DE 3/8" DIAM. Y ESTRIBOS DE 1/4" DIAM. A CADA 20
CM, CON CIMBRA COMÚN 2 CARAS.
AREF2 HABILITADO Y ARMADO DE ACERO DE REFUERZO EN TON 0.00 0.001800 ### $15.81
ESTRUCTURA, FY=3000 KG/CM2, No. 2 DIAMETRO 1/4"
(ALAMBRÓN), SIN INCLUIR TRASLAPES; ACARREO
MATERIAL PRIMERA ESTACION = 20.00 M
CCAST CIMBRA Y DESCIMBRA ACABADO COMÚN EN CASTILLOS M2 0.00 0.400000 $65.92 $26.37
DE SECCIÓN MAYOR A 0.020 M2, INCLUYE: MATERIALES
Y MANO DE OBRA.
VDACAS200 VACIADO DE CONCRETO HECHO EN OBRA CON M3 0.00 0.040000 $773.81 $30.95
REVOLVEDORA 1 SACO, EN DALAS Y CASTILLOS DE
SECCIÓN >0.02 M2, F´C=200 KG/CM2, RESISTENCIA
NORMAL, TAMAÑO MÁXIMO DE AGREGADO 20 MM. (3/4"),
INCLUYE: VIBRADO, CURADO, ACARREO A UNA 1a.
ESTACIÓN A 20 M. MATERIALES Y
CAST009V CASTILLO CON SECCION DE 20X20 CM DE CONCRETO F'C=250 KG/CM2, R. N. AGR. MAX. M
3/4, REFORZADO CON 4 VARILLAS DE 3/8" DIAM. Y ESTRIBOS DE 1/4" DIAM. A CADA 20
CM, CON CIMBRA COMÚN 2 CARAS.
AREF2 HABILITADO Y ARMADO DE ACERO DE REFUERZO EN TON 0.00 0.001800 ### $15.81
ESTRUCTURA, FY=3000 KG/CM2, No. 2 DIAMETRO 1/4"
(ALAMBRÓN), SIN INCLUIR TRASLAPES; ACARREO
MATERIAL PRIMERA ESTACION = 20.00 M
CCAST CIMBRA Y DESCIMBRA ACABADO COMÚN EN CASTILLOS M2 0.00 0.400000 $65.92 $26.37
DE SECCIÓN MAYOR A 0.020 M2, INCLUYE: MATERIALES
Y MANO DE OBRA.
VDACAS250 VACIADO DE CONCRETO HECHO EN OBRA CON M3 0.00 0.040000 $773.81 $30.95
REVOLVEDORA 1 SACO, EN DALAS Y CASTILLOS DE
SECCIÓN >0.02 M2, F´C=250 KG/CM2, RESISTENCIA
NORMAL, TAMAÑO MÁXIMO DE AGREGADO 20 MM. (3/4"),
INCLUYE: VIBRADO, CURADO, ACARREO A UNA 1a.
ESTACIÓN A 20 M. MATERIALES Y
DALA001A DALA CON SECCION DE 15X15 CM DE CONCRETO F'C=150 KG/CM2, R. N. AGR. MAX. 3/4" M
REFORZADA CON ARMADURA ELECTROSOLDADA ARMEX 15X15-4, CON CIMBRA COMÚN
2 CARAS.
DALA002A DALA CON SECCION DE 15X15 CM DE CONCRETO F'C=200 KG/CM2, R. N. AGR. MAX. 3/4" M
REFORZADA CON ARMADURA ELECTROSOLDADA ARMEX 15X15-4, CON CIMBRA COMÚN
2 CARAS.
DALA003A DALA CON SECCION DE 15X15 CM DE CONCRETO F'C=250 KG/CM2, R. N. AGR. MAX. 3/4" M
REFORZADA CON ARMADURA ELECTROSOLDADA ARMEX 15X15-4, CON CIMBRA COMÚN
2 CARAS.
DALA004A DALA CON SECCION DE 15X20 CM DE CONCRETO F'C=150 KG/CM2, R. N. AGR. MAX. 3/4" M
REFORZADA CON ARMADURA ELECTROSOLDADA ARMEX 15X20-4, CON CIMBRA COMÚN
2 CARAS.
VDACAS150 VACIADO DE CONCRETO HECHO EN OBRA CON M3 0.00 0.030000 $759.21 $22.78
REVOLVEDORA 1 SACO, EN DALAS Y CASTILLOS DE
SECCIÓN >0.02 M2, F´C=150 KG/CM2, RESISTENCIA
NORMAL, TAMAÑO MÁXIMO DE AGREGADO 20 MM. (3/4"),
INCLUYE: VIBRADO, CURADO, ACARREO A UNA 1a.
ESTACIÓN A 20 M. MATERIALES Y
DALA005A DALA CON SECCION DE 15X20 CM DE CONCRETO F'C=200 KG/CM2, R. N. AGR. MAX. 3/4" M
REFORZADA CON ARMADURA ELECTROSOLDADA ARMEX 15X20-4, CON CIMBRA COMÚN
2 CARAS.
DALA006A DALA CON SECCION DE 15X20 CM DE CONCRETO F'C=250 KG/CM2, R. N. AGR. MAX. 3/4" M
REFORZADA CON ARMADURA ELECTROSOLDADA ARMEX 15X20-4, CON CIMBRA COMÚN
2 CARAS.
VDACAS250 VACIADO DE CONCRETO HECHO EN OBRA CON M3 0.00 0.030000 $773.81 $23.21
REVOLVEDORA 1 SACO, EN DALAS Y CASTILLOS DE
SECCIÓN >0.02 M2, F´C=250 KG/CM2, RESISTENCIA
NORMAL, TAMAÑO MÁXIMO DE AGREGADO 20 MM. (3/4"),
INCLUYE: VIBRADO, CURADO, ACARREO A UNA 1a.
ESTACIÓN A 20 M. MATERIALES Y
DALA007A DALA CON SECCION DE 20X20 CM DE CONCRETO F'C=150 KG/CM2, R. N. AGR. MAX. 3/4" M
REFORZADA CON ARMADURA ELECTROSOLDADA ARMEX 15X20-4, CON CIMBRA COMÚN
2 CARAS.
DALA008A DALA CON SECCION DE 20X20 CM DE CONCRETO F'C=200 KG/CM2, R. N. AGR. MAX. 3/4" M
REFORZADA CON ARMADURA ELECTROSOLDADA ARMEX 15X20-4, CON CIMBRA COMÚN
2 CARAS.
VDACAS200 VACIADO DE CONCRETO HECHO EN OBRA CON M3 0.00 0.040000 $773.81 $30.95
REVOLVEDORA 1 SACO, EN DALAS Y CASTILLOS DE
SECCIÓN >0.02 M2, F´C=200 KG/CM2, RESISTENCIA
NORMAL, TAMAÑO MÁXIMO DE AGREGADO 20 MM. (3/4"),
INCLUYE: VIBRADO, CURADO, ACARREO A UNA 1a.
ESTACIÓN A 20 M. MATERIALES Y
DALA009A DALA CON SECCION DE 20X20 CM DE CONCRETO F'C=250 KG/CM2, R. N. AGR. MAX. 3/4" M
REFORZADA CON ARMADURA ELECTROSOLDADA ARMEX 15X20-4, CON CIMBRA COMÚN
2 CARAS.
PLA05-100 PLANTILLA DE CONCRETO SIMPLE F`C =100 KG/CM2, RESISTENCIA NORMAL, DE 5 CM. M2
ESPESOR, AGREGADO MAXIMO 3/4" (20 MM.) INCLYE: MATERIALES Y MANO DE OBRA.
PIS05-100 FIRME DE CONCRETO SIMPLE F`C =100 KG/CM2, RESISTENCIA NORMAL, DE 5 CM. M2
ESPESOR, AGREGADO MAXIMO 3/4" (20 MM.) ACABADO ESCOBILLADO. INCLYE:
MATERIALES Y MANO DE OBRA.
FCO100R CONCRETO F'C=100 KG/CM2, RESISTENCIA NORMAL, M3 0.00 0.051500 $236.89 $12.20
AGR.MAX. 3/4, FABRICADO EN OBRA EN REVOLVEDORA
DE 1 SACO; ACARREO MATERIAL PRIMERA ESTACION
20.00 M.
PSO0001 ACABADO ESCOBILLADO INTEGAL PSO CONC. M2 0.00 1.000000 $14.98 $14.98
PIS05-150 FIRME DE CONCRETO SIMPLE F`C =150 KG/CM2, RESISTENCIA NORMAL, DE 5 CM. M2
ESPESOR, AGREGADO MAXIMO 3/4" (20 MM.) ACABADO ESCOBILLADO. INCLYE:
MATERIALES Y MANO DE OBRA.
FCO150R CONCRETO F´C=150 KG/CM2, RESISTENCIA NORMAL M3 0.00 0.051500 $254.12 $13.09
AGREGADO MAXIMO 3/4", FABRICADO EN OBRA CON
REVOLVEDORA DE 1 SACO, ACARREO DE MATERIALES A
1a ESTACION A 20 M.
PSO0001 ACABADO ESCOBILLADO INTEGAL PSO CONC. M2 0.00 1.000000 $14.98 $14.98
PIS08-150 FIRME DE CONCRETO SIMPLE F`C =150 KG/CM2, RESISTENCIA NORMAL, DE 8 CM. M2
ESPESOR, AGREGADO MAXIMO 3/4" (20 MM.) ACABADO ESCOBILLADO. INCLYE:
MATERIALES Y MANO DE OBRA.
FCO150R CONCRETO F´C=150 KG/CM2, RESISTENCIA NORMAL M3 0.00 0.082400 $254.12 $20.94
AGREGADO MAXIMO 3/4", FABRICADO EN OBRA CON
REVOLVEDORA DE 1 SACO, ACARREO DE MATERIALES A
1a ESTACION A 20 M.
PSO0001 ACABADO ESCOBILLADO INTEGAL PSO CONC. M2 0.00 1.000000 $14.98 $14.98
PIS08-200 FIRME DE CONCRETO SIMPLE F`C =200 KG/CM2, RESISTENCIA NORMAL, DE 8 CM. M2
ESPESOR, AGREGADO MAXIMO 3/4" (20 MM.) ACABADO ESCOBILLADO. INCLYE:
MATERIALES Y MANO DE OBRA.
FCO200R CONCRETO F'C=200 KG/CM2, RESISTENCIA NORMAL, M3 0.00 0.082400 $268.29 $22.11
AGREGADO MAXIMO 3/4", FABRICADO EN OBRA EN
REVOLVEDORA DE 1 SACO, ACARREO MATERIAL
PRIMERA ESTACION=20.00M
PSO0001 ACABADO ESCOBILLADO INTEGAL PSO CONC. M2 0.00 1.000000 $14.98 $14.98
Subtotal: MATERIALES $0.16
Subtotal: MANO DE OBRA $43.69
Subtotal: BASICOS $41.02
Costo directo $84.87
INDIRECTO $0.00
UTILIDADES $0.00
COSTO TOTAL $84.87
PIS10-150 FIRME DE CONCRETO SIMPLE F`C =150 KG/CM2, RESISTENCIA NORMAL, DE 10 CM. M2
ESPESOR, AGREGADO MAXIMO 3/4" (20 MM.) ACABADO ESCOBILLADO. INCLYE:
MATERIALES Y MANO DE OBRA.
FCO150R CONCRETO F´C=150 KG/CM2, RESISTENCIA NORMAL M3 0.00 0.103000 $254.12 $26.17
AGREGADO MAXIMO 3/4", FABRICADO EN OBRA CON
REVOLVEDORA DE 1 SACO, ACARREO DE MATERIALES A
1a ESTACION A 20 M.
PSO0001 ACABADO ESCOBILLADO INTEGAL PSO CONC. M2 0.00 1.000000 $14.98 $14.98
PIS10-200 FIRME DE CONCRETO SIMPLE F`C =200 KG/CM2, RESISTENCIA NORMAL, DE 10 CM. M2
ESPESOR, AGREGADO MAXIMO 3/4" (20 MM.) ACABADO ESCOBILLADO. INCLYE:
MATERIALES Y MANO DE OBRA.
FCO200R CONCRETO F'C=200 KG/CM2, RESISTENCIA NORMAL, M3 0.00 0.103000 $268.29 $27.63
AGREGADO MAXIMO 3/4", FABRICADO EN OBRA EN
REVOLVEDORA DE 1 SACO, ACARREO MATERIAL
PRIMERA ESTACION=20.00M
PSO0001 ACABADO ESCOBILLADO INTEGAL PSO CONC. M2 0.00 1.000000 $14.98 $14.98
Subtotal: MATERIALES $0.16
Subtotal: MANO DE OBRA $43.69
Subtotal: BASICOS $47.43
Costo directo $91.28
INDIRECTO $0.00
UTILIDADES $0.00
COSTO TOTAL $91.28
PIS15-150 FIRME DE CONCRETO SIMPLE F`C =150 KG/CM2, RESISTENCIA NORMAL, DE 15 CM. M2
ESPESOR, AGREGADO MAXIMO 3/4" (20 MM.) ACABADO ESCOBILLADO. INCLYE:
MATERIALES Y MANO DE OBRA.
FCO150R CONCRETO F´C=150 KG/CM2, RESISTENCIA NORMAL M3 0.00 0.153000 $254.12 $38.88
AGREGADO MAXIMO 3/4", FABRICADO EN OBRA CON
REVOLVEDORA DE 1 SACO, ACARREO DE MATERIALES A
1a ESTACION A 20 M.
PSO0001 ACABADO ESCOBILLADO INTEGAL PSO CONC. M2 0.00 1.000000 $14.98 $14.98
PIS15-200 FIRME DE CONCRETO SIMPLE F`C =200 KG/CM2, RESISTENCIA NORMAL, DE 15 CM. M2
ESPESOR, AGREGADO MAXIMO 3/4" (20 MM.) ACABADO ESCOBILLADO. INCLYE:
MATERIALES Y MANO DE OBRA.
FCO200R CONCRETO F'C=200 KG/CM2, RESISTENCIA NORMAL, M3 0.00 0.153000 $268.29 $41.05
AGREGADO MAXIMO 3/4", FABRICADO EN OBRA EN
REVOLVEDORA DE 1 SACO, ACARREO MATERIAL
PRIMERA ESTACION=20.00M
PSO0001 ACABADO ESCOBILLADO INTEGAL PSO CONC. M2 0.00 1.000000 $14.98 $14.98
MURLAD7 MURO DE TABIQUE ROJO RECOCIDO DE 7×14×28 CM. DE 7 CM. DE ESP. (CAPUCHINO), M2
ASENTADO CON MEZCLA MORTERO-ARENA 1:5, JUNTAS DE 1.5 CM. DE ESP. ACABADO
COMÚN HASTA UNA ALTURA DE 3.5 M.
MURLAD14 MURO DE TABIQUE ROJO RECOCIDO DE 7×14×28 CM. DE 14 CM. DE ESP. ASENTADO M2
CON MEZCLA MORTERO-ARENA 1:5, JUNTAS DE 1.5 CM. DE ESP. ACABADO COMÚN
HASTA UNA ALTURA DE 3.5 M.
MURLAD28 MURO DE TABIQUE ROJO RECOCIDO DE 7×14×28 CM. DE 28 CM. DE ESP. ASENTADO CON M2
MEZCLA MORTERO-ARENA 1:5, JUNTAS DE 1.5 CM. DE ESP. ACABADO COMÚN HASTA
UNA ALTURA DE 3.5 M.
LOSA10-200 LOSA DE 10 CM. DE PERALTE EN TECHO DE CUBIERTA, FABRICADA CON CONCRETO F`c M2
= 200 KG/CM2 AGREGADO MAXIMO 3/4" INCLUYE CIMBRA ,DESCIMBRA, KG. DE ACERO
DE REFUERZO X M3 DE CONCRETO, MATERIALES MANO DE OBRA Y EQUIPO
AREF3 HABILITADO Y ARMADO DE ACERO DE REFUERZO EN TON 0.00 0.022330 ### $140.20
ESTRUCTURA, FY=4200 KG/CM2, No.3, DIAMETRO 3/8",
SIN INCLUIR GANCHOS, TRASLAPES NI ANCLAJES,
ACARREO MATERIAL PRIMERA ESTACION = 20.00 M
CLOSA HAB. Y COL. DE CIMBRA CON TARIMAS DE DUELA PARA M2 0.00 1.000000 $62.40 $62.40
LOSA DE CONCRETO.
LOSA10-250 LOSA DE 10 CM. DE PERALTE EN TECHO DE CUBIERTA, FABRICADA CON CONCRETO F`c M2
= 250 KG/CM2 AGREGADO MAXIMO 3/4" INCLUYE CIMBRA ,DESCIMBRA, KG. DE ACERO
DE REFUERZO X M3 DE CONCRETO, MATERIALES MANO DE OBRA Y EQUIPO
CLOSA HAB. Y COL. DE CIMBRA CON TARIMAS DE DUELA PARA M2 0.00 1.000000 $62.40 $62.40
LOSA DE CONCRETO.
PTA0001 SUMINISTRO Y COLOCACIÓN DE PUERTA DE 0.70 X 2.10 M. INCLUYE: CHAPA MODELO 715 PZA
Y PINTURA BASE.
APL0022 APLANADO EN PLAFÓN DE LOSA, PULIDO A LLANA CON MEZCLA DE MORTERO Y ARENA M2
PROPORCION DE 1:5, DE 2.5 CM. DE ESPESOR PROMEDIO.
LC LL
MEDIDA ZAPATA 1.20 × 1.20 M LC = LADO CORTO FC = FACTOR DE CONTACTO
SECCIÓN CIMBRADA DE DADO 0.50 × 0.50 M LL = LADO LARGO FD = FACTOR DE DESPERDICIO
PT = PIE TABLÓN FU = FACTOR DE USOS
PERALTE DE ZAPATA 0.30 M
ALTURA DE DADO 0.80 M PZAS = CANT. DE PIEZAS UTILIZADAS DE ESA MADERA
ESP.Y ANCHO = ESPESOR Y ANCHO DE LA MADERA
FACTOR DE DESPERDICIO 20.00 % MTS. = LONGITUD O LARGO DE LA MADERA
PROFUNDIDAD DE ESTACA 0.15 M DATOS QUE SE PUEDEN PROPONER O DEJAR EN CERO
HOLGURA YUGO 1 EXTREMO 0.05 M
SEPARACIÓN YUGO 0.50
LC LL
CARAS CIMBRADAS DE ZAPATA 2 2
CARAS CIMBRADAS DE DADO 2 2
CONTRATRABE (DADO)
CONTACTO LADO CORTO DUELA 5 2 1 20 0.80 2
0.80 17.50 1.60 10.94 13.13 5 2.63 1.26
CONTACTO LADO LARGO DUELA 5 2 1 20 0.80 2
CANT. DE YUGOS EN DADO BARROTE 5 2 4 3 3.42 22.42 1.60 14.01 16.81 5 3.36 5.38
CÁLCULO DE PIE TABLÓN PARA CIMBRA DE UN CASTILLO, COLUMNA, TRABE, DALA O CADENA
ELEMENTO CONSTRUCTIVO 2
Elemento Horizontal
DIAS NO TRABAJADOS AL AÑO DÍAS PAGADOS AL AÑO PRESTACIONES DEL IMSS (%)
g) Domingos 52.00 Días Calendario 365.00 Enfermedad y maternidad
h)Días festivos por ley 7.00 b) Aguinaldo por Ley 20.00 Invalidéz y vida 2.375 %
i)Días por costumbre c)Prima Vacacional 33% por ley 3.00 Cesantía en edad avanzada y retiro 4.275 %
j)Días Sindicato d)Prima Dominical 0.25% por ley Riesgos de trabajo 7.590 %
k) Vacaciones 10.00 e)Horas extra al año (especifique) por ley en días Guarderías 1.000 %
l)Permisos y Enfermedad f)Prestaciones por Contrato de trabajo Pensionados 1.425 %
m)Condiciones Climatológicas g)Días por terminación de obra al año (CFE) 30 Prestaciones en dinero 0.950 %
n)Horas inactivas por arrastre
o)Días no trabajados por guardia TOTAL X1 (DIAS)= 418.00
TOTAL Y1 (DIAS)= 296.00 Factor para Salario Integrado X1/Y1 1.4122 Suma en % de prestaciones del IMSS 17.62 %
- - - - - - - - - - -
1 CABO 125.32 8.63 - 1.19 1.79 9.51 2.98 5.36 1.25 6.27 1.8289 229.20
2 ALBAÑIL 109.92 8.63 - 1.04 1.57 8.34 2.61 4.70 1.10 5.50 1.8425 202.53
3 CARPINTERO 109.92 8.63 - 1.04 1.57 8.34 2.61 4.70 1.10 5.50 1.8425 202.53
4 PINTOR 109.92 8.63 - 1.04 1.57 8.34 2.61 4.70 1.10 5.50 1.8425 202.53
5 PLOMERO 109.92 8.63 - 1.04 1.57 8.34 2.61 4.70 1.10 5.50 1.8425 202.53
6 ELECTRICISTA 109.92 8.63 - 1.04 1.57 8.34 2.61 4.70 1.10 5.50 1.8425 202.53
7 PEON 56.67 8.63 - 0.54 0.81 4.30 1.35 2.42 0.57 2.83 1.9467 110.32
8 AYUDANTE EN GRAL. 83.44 8.63 - 0.79 1.19 6.33 1.98 3.57 0.83 4.17 1.8777 156.68
9 HERRERO 109.92 8.63 - 1.04 1.57 8.34 2.61 4.70 1.10 5.50 1.8425 202.53
10 CHOFER 109.92 8.63 - 1.04 1.57 8.34 2.61 4.70 1.10 5.50 1.8425 202.53
- - - - - - - - - - -
- - - - - - - - - - -
- - - - - - - - - - -
PERSONAL TÉCNICO ADMINISTRATIVO - - - - - - - - - - -
A1 SECRETARIA - - - - - - - - - - -
A2 DIBUJANTE - - - - - - - - - - -
A3 BODEGUERO - - - - - - - - - - -
A4 SUPERVISOR - - - - - - - - - - -
A5 CONTADOR - - - - - - - - - - -
A6 ADMINISTRADOR - - - - - - - - - - -
A7 - - - - - - - - - - -
*Dererminación del FSR analizando la cuota fija por separado y calculando en porcentaje
SALARIO PRESTACIONES EN % SALARIO
No. CATEGORÍA DIARIO CUOTA IMSS INFONAVIT FSR INTEGRADO
NOMINAL FIJA
- - - - -
1 CABO 125.32 6.89 17.62 5.00 1.8289 229.20
2 ALBAÑIL 109.92 7.86 17.62 5.00 1.8425 202.53
3 CARPINTERO 109.92 7.86 17.62 5.00 1.8425 202.53
4 PINTOR 109.92 7.86 17.62 5.00 1.8425 202.53
5 PLOMERO 109.92 7.86 17.62 5.00 1.8425 202.53
6 ELECTRICISTA 109.92 7.86 17.62 5.00 1.8425 202.53
7 PEON 56.67 15.24 17.62 5.00 1.9467 110.32
8 AYUDANTE EN GRAL. 83.44 10.35 17.62 5.00 1.8777 156.68
9 HERRERO 109.92 7.86 17.62 5.00 1.8425 202.53
10 CHOFER 109.92 7.86 17.62 5.00 1.8425 202.53
- - - - -
- - - - -
- - - - -
PERSONAL TÉCNICO ADMINISTRATIVO - - - - -
A1 SECRETARIA - - - - -
A2 DIBUJANTE - - - - -
A3 BODEGUERO - - - - -
A4 SUPERVISOR - - - - -
A5 CONTADOR - - - - -
A6 ADMINISTRADOR - - - - -
A7 - - - - -
ANÁLISIS, CÁLCULO E INTEGRACIÓN DE LOS COSTOS HORARIOS ANIEXO 29
DE LA MAQUINARIA Y EQUIPO DE CONSTRUCCIÓN
I CARGOS FIJOS
I.1 Depreciación D= (Vm-Vr)/Ve = 4.93
I.2 Inversión Im= (Vm+Vr) i /2Hea = 49.28
I.3 Seguros Sm= (Vm+Vr) s /2Hea = 49.28
I.4 Mantenimiento Mn= Ko x D = 9.85
(1) SUMA CARGOS FIJOS = 113.34
II. CONSUMOS
II.1 Combustibles CO= Gh x Pc = 16.00
II.2 Otras fuentes de energía =
II.3 Lubricantes Lb= (Ah+Ga) x Pa = 1,200.00
II.4 Llantas N= Pn/Vn = 240.00
II.5 Piezas Especiales Ae= Ppe/Vpe 0.90
(2) SUMA CONSUMOS = 1,456.90
III. OPERACIÓN
CATEGORÍAS CANTIDAD SALARIO REAL IMPORTE
OPERADOR 001 1 $10.00 10
$0.00 0
$0.00 0
$0.00 0
$0.00 0
(Po)= $10.00
III.1 OPERACIÓN Po=Sr/Ht
(3) SUMA OPERACIÓN
(1)+(2)+(3)= 1,580.24
ANIEXO 29
PROGRAMA MONTOS MENSUALES DE UTILIZACIÓN DE PERSONAL TÉCNICO, ADMINISTRATIVO Y DE SERVICIOS ENCARGADOS DE LA DIRECCIÓN,
SUPERVISIÓN Y ADMINISTRACIÓN DE LOS TRAAJOS
* Aquí, se muestra un ejemplo sencillo y común del desglose y factor de Indirectos
MONTO DE LA OBRA ACTUAL (C. D.) $71,740.80 Título del periodo SEM1 SEM2
MONTO DE CONTRATOS VIGENTES (AÑO) $400,000.00 Año 2005 2005
PERIODICIDAD SEMANAL Días naturales 7 7 7 7 4
Fecha de Inicio: 6/1/2005 Días por periodo 7 7 7 7 7
Fecha de terminación: 6/20/2005 Factor 1.0000 1.0000 1.0000 1.0000 0.5714 0.0000 0.0000 0.0000 0.0000 0.0000
Duración en Dias: 20.00
MONTO DE LA OBRA ACTUAL (C. D.) $71,740.80 MONTO DE CONTRATOS VIGENTES (AÑO) ### PERIODICIDAD SEMANAL
III.- SERVICIOS
3.1 $ - $ -
3.2 $ - $ -
3.3 $ - $ -
EJEMPLO
PERSONAL ADMINISTRATIVO $ 83.00
Cant. Categoría Salario TOTAL
1 ADMINISTRADOR DE OBRA $ 35.00 $ 35.00
2 AUXILIAR CONTABLE $ 20.00 $ 40.00
1 auxiliar a $ 8.00 $ 8.00
TOTAL $ 83.00
UTILIDAD PROPUESTA POR EL LICITANTE
CARGOS ADICIONALES
F´C=100, (GUARNICIONES, BANQUETAS Y FIRMES.) 1 7.50 8.00 3.00 0.175 FC=100, RN., AGR. MAX. 20 MM.
F´C=150, (PISOS, CADENAS Y CASTILLOS.) 1 5.50 6.50 2.50 0.151 FC=150, RN., AGR. MAX. 20 MM.
F´C=200, (LOSAS, TRABES, ZAPATAS Y MUROS.) 1 4.00 6.00 2.00 0.133 FC=200, RN., AGR. MAX. 20 MM.
F´C=250, (COLUMNAS Y LOSAS ESPECIALES.) 1 3.50 5.00 1.75 0.120 FC=250, RN., AGR. MAX. 20 MM.
F´C=300, (CONCRETO DE ALTA RESISTENCIA) 1 2.50 4.50 1.25 0.103 FUENTE: BIMSA
% DESPERDICIO DURANTE LA FAB. Y COLOCACIÓN. 3% 10% 10% 30% 5% % DESPERDICIO DURANTE LA FAB. Y COLOCACIÓN.
No. Ø pulg. Ø mm. Kg/m. mm2 pulg. 2 No. Ø pulg. Ø mm. Kg/m. mm2 pulg. 2 (M2)
0.0143 ALAMBRE #18 7 (7/8") 22.2 3.034 387 0.6 TRR 7×14×28 CM. DE 7CM. ESP. (CAPUCHINO), MORTERO CON JUNTAS DE 1.5 CM
2.5 (1/4") 6.35 0.251 ALAMBRÓN 8 (1") 25.4 3.975 507 0.79 TRR 7×14×28 CM. DE 14CM. ESP. (A SOGA), MORTERO CON JUNTAS DE 1.5 CM.
3 (3/8") 9.5 0.557 71 0.11 9 (1 1/8") 28.6 5.033 642 0.99 TRR 7×14×28 CM. DE 28CM. ESP. (A TIZÓN), MORTERO CON JUNTAS DE 1.5 CM.
4 (1/2") 12.7 0.996 127 0.2 10 (1 1/4") 31.8 6.225 794 1.23 TABICÓN 10×14×28 CM. DE 10CM. ESP. (CAPUCHINO), MORT CON JUNTAS DE 1.5
5 (5/8") 15.9 1.56 199 0.31 11 (1 3/8") 34.9 7.503 957 1.48 TABICÓN 10×14×28 CM. DE 14CM. ESP. (A SOGA), MORT. CON JUNTAS DE 1.5 CM.
6 (3/4") 19.1 2.25 287 0.44 12 (1 1/2") 38.1 8.938 1140 1.77 TABICÓN 10×14×28 CM. DE 28CM. ESP. (A TIZÓN), MORT. CON JUNTAS DE 1.5 CM.
MORTERO - ARENA 1.:4 (PISOS Y FIRMES) 1 4.00 3.00 0.095 MORTERO - ARENA 1.:4
MORTERO - ARENA 1.:5 (APLANADOS: ENJARRE, SARPEO) 1 5.00 2.50 0.110 MORTERO - ARENA 1.:5
MORTERO - ARENA 1.:6 (PEGADO DE BLOQUES) 1 6.00 2.00 0.127 MORTERO - ARENA 1.:6
MORTERO - ARENA 1.:8 (CIMIENTOS DE MAMPOSTERÍA) 1 8.00 1.25 0.168 MORTERO - ARENA 1.:8
% DESPERDICIO DURANTE LA FABRICACIÓN Y COLOC. 3% 3% 10% 30% % DESPERDICIO DURANTE LA FABRICACIÓN Y COLOC.
GANCHOS Y DOBLECES (cm) EMPALME "e" (cm) DETALLE GANCHOS Y DOBLECES (cm) EMPALME "e" (cm)
(1/4") 4 9 3 7 40 25 60 40 b a (7/8") 14 30 9 13 90 70
NERVADURA
d c
F´C=150 F´C=200
135 100 b a
150 115
5
170 130
190 145
230 170 e