IMS POLICY Editorial
We are pleased to publish April- June, 2014 issue of Gammon Bulletin.

We take pleasure in presenting some of our recent significant achievements,


successes, learning and events from across the country to our Gammon
family, our esteemed customers and other beloved stake holders.

Santacruz- Chembur Link Road Flyover was opened to traffic on


18th April, 2014. Gammon is proud to be a part of this Project.
This double deck flyover - which is first of its kind in the country is
2.45 Km long (viaduct portion) and will ease traffic in this busy corridor to
a very large extent apart from reducing travel time by nearly 30 minutes.
This successful achievement is important especially because the project was
hindered by numerous obstacles and removal of theses hindrances called
for concerted efforts from all concerned including Gammon in the capacity
of a contractor. Various innovative and creative tailor- made solutions were
worked out for this Project which was to be executed in a highly congested
area under live busy rail traffic.

Second article in the Bulletin covers innovative method adopted by Gammon


to rectify the tilt of unprecedented magnitude in P3 and P4 wells of Passighat
Bridge. The magnitude of the tilt was as high as 1 in 2.3 and no conventional
method of tilt rectification would work for such a high magnitude of tilts and
accordingly an innovative method was developed to rectify the tilt.

The News Flash section of Bulletin flashes the news of completion of tallest
cooling tower at Nigrie (190.5 m tall) and 16 diaphragam panels of Intake
well at Patna done by innovative technique for the first time in the country.

In our quest to continually improve the Bulletin, we will be glad to receive


feedback and suggestions from our valued readers to make Gammon
Bulletin more and more interesting and informative for the readers.

Your feedback and suggestions may please be sent to


bulletin@gammonindia.com

CONTENTS

SCLR Double Deck Flyover 3 Works in Progress 16

Tilt Rectification for 9 News Flash 18


Pasighat Bridge

Team Management Skills 11 Company News 19

For Private Circulation Only Cover Photo: Santacruz - Chembur Double Deck Flyover

GAMMON BULLETIN 2
LINKING SANTACRUZ & CHEMBUR - INDIA’S FIRST
DOUBLE DECK FLYOVER AT MUMBAI
Out of total land for construction, so as per Railway requirement in spite
47% land belongs to Indian Railways of permanent liner we had to drive 35
and 26% belongs to MHADA. As per m sheet Pile at a distance of 2.4 m from
Railway norms before work in their area face of the track involving a depth up
commences, each drawing & design to 5m to prevent possible caving due
needed to be approved by Railway. to constant moving loads of trains
Amitesh Ranjan For execution also their permission running at the frequency of every four
Dy. Gen. Manager and approval is required. Initially as minutes. It was done in five hours of one
per GAD the ROW was 30m but the night shift. The entire works from sheet
1. Introduction:- same was revised to 45.7m in year piling to substructure were completed
2007. There were several and frequent in 110 days without any need to obtain
The ambitious Project of construction changes made in GAD to meet the shut down from Railway.
of double deck Flyover was requirements of Railway authorities.
It could be done safely only due to our
conceptualized and conceived by Finally ninth revision of GAD with
proper coordination and meticulous
MMRDA to provide connectivity from composite super structure over Railway
micro planning for all resources. The
Eastern Suburbs to Western Suburban track was approved after vigorous
various stages of P5A foundation
of Mumbai. Funded by the World follow up and coordination of all the
construction are pictorially shown
Bank, the Project is implemented by agencies involved in the Project.
below:
MSRDC on behalf of MMRDA (Govt. of
To provide this connectivity from east
Maharashtra). Gammon India Limited
to west, the herculean task was to
has had the distinct honour to execute
cross the two extremely busy Railway
this Project as a Main Contractor.
Tracks of Mumbai suburban local
The total length for this East – West lines (central and harbour) which
connectivity of SCLR is 6.45 Km. Out was a challenging job. The same was
of which main viaduct part of SCLR complicated further, as the layout has
section – II (2.45 Km), double decker to pass through number of hutments
flyover (0.69 Km) with additional cross (approx. 3500nos.), Mosques, Temple
arm of 0.9 Km was in Gammon scope. and 16 (G+4) MHADA buildings. It
was extremely difficult to shift so
2. Challenges of acquiring many families and holy structures. But
hindrance free ROW: MMRDA was determined to do this and
after vigorous efforts of several years
When awarded, the project site was full successfully shifted all the structures
of Hindrances. Effective and constant and made the land available for
coordination with all Stakeholders construction of flyover.
was done relentlessly by MMRDA,
proactively supported by Gammon, 3. Construction of
to remove physical hindrances and Foundation:-
have the ground cleared to commence
execution of the works. The Foundation of the Bridge mainly
Challenge Particulars Remarks consisted of Pile Foundation for all the
piers except one Open Foundation at
Initially planned
ROW ROW of 30m A1 Abutment. Bored cast in situ Piles
Formalized in 2007
Availability was revised to of 1200 mm dia were designed for
45.7m
Minimum Load Carrying Capacity of
Composite Nine revisions took
GAD
Super Structure place to meet the
3000 KN at Founding Level. Pile was
Drawings
especially in
scheme approval requirements and socketed upto a length of 4.85m (3.6
by Railway specifications of
Railway Zone
Authorities Railways.
m in Soft/Weathered rock and 1.25m in
Hard Rock)
Railway Two Railway Central Railway line
Crossings Lines (8Tracks) and Harbour line
Out of total 1420 nos. piles, 24nos piles
3500 hutments, of P5A foundation were very critical
Mosques,16 Nos
Rehabilitation (G+4) MHADA which was much closer to main rail
Buildings were track (i.e. just 3.3 m from track face).
restored
The piling has been done by Rotary Rig,

3 GAMMON BULLETIN
4. Construction of Sub arrangement, Reinforcement fixing RHS Side (1P20-1P21) & at 1P20 Piercap
Structure: & Shuttering fixing/removing for the at LHS Side.
Middle Piercap due to restricted space
The pier caps of the Bridge Portion was 2. Supporting arrangement by cuplock
between two second level Piers.
flared Shape with varying dimensions. system was erected over the First Floor
Maximum Size of Piercap was 57.88m Piercap.
x 2.9m x 3.5m in nearby LT Terminus
station.
For Construction of Piercap, we have
to demolish the LTT Railway Shed for
supporting arrangement of Piercap.
This single pier cap is connecting 5
No’s of Pier. The pier cap is constructed
under heavy pedestrian & Traffic 3. Due to less space & safety Point of
movement. 5. Construction of Super view, supporting arrangement for 31m
structure: length of Box Girder was done with
inverted truss support & balance 18m
Whereas the Super Structure of this
Trestle Arrangement Support.
Viaduct Portion consisted of Box Girder
Constructed Cast in situ. The super
structure for Railway portion was cast
in Situ I Girder & Pre-Fabricated Steel
Girders with RCC slab.

5.1 Box Girder:-


Total 102 nos of Pre-stressed Box
Girders were cast, out of which 58Nos
Box Girders were at 1st level & 44 No’s
Box Girders were at 2nd level. The
Length of Box Girder varies from 21m
to 49m. The width of Box Girder varies As per approved Supporting
from 8.6m to 10.6m. Height of Box arrangement drawing, the erection of
Girder is 2.3m including 250mm thick Trestle & Inverted truss done by Crane
deck slab. The concreting of Box Girder and box girder cast in two stages.
was done in two stages. In first stage
web & soffit concrete & in second stage
Deck slab concrete done. Out of 102
No’s of Box Girder casting of 2nos of Box
Girder of 49m span Length over 18m
height from the Ground Level was very
critical because of heavy pedestrians
and traffic movement.

There were 5No’s of Piercap in single At Junction Area, first level super
Row that also within the distance of structure was with I Girders & second
50m Length. Two no’s of Piercap for level super structure was with 49 m Box
first level RHS & LHS side, two no’s of Girder. As the area near the LT Terminus
pier cap for second floor level RHS station having heavy movement of
& LHS Side and another one is in at vehicle & people, a pathway from Tilak
Middle location. The super structure Nagar Local station to LTT Station was
over the pier cap is connecting the planned. Firstly Pathway diversion was
Four no’s of Arm in one Location. As per done by the approval of Railway after
the site & Drawing condition we have that Box Girder activity was started. Due
5.2 I Girder:-
to cast Middle Piercap after completion to the availability of less working area,
of Two Nos of Second level Pier & more public movementetc. special Flyover consists of total 198 no’s of
Piercap. After completion of second composite supporting arrangements PSC I girder, out of these 140 no’s
level piercap within the available of Box Girder were planned & executed. girders were at junction. These Girders
restricted space we have to start Pier are over the existing road and way to
1. Supporting arrangement by trestles
work at Middle location. It is very Tilak Nagar local station & Kurla station
was erected over I Girder Deckslab at
difficult to accommodate Supporting from LTT station,where heavy traffic of

GAMMON BULLETIN 4
light vehicles and public movement Nallah. so we had to go for Inverted
was unavoidable. To add up these truss Supporting arrangement.
constraints, a 14m wide open drain is Inverted Truss was erected over the
crossing from one side and LTT station Nalla wall was acting as a ground
building at other side of fly over. So surface for Cuplock system erection.
working space was the major constraint We erected the Cuplock system over
to execute the work in this area. The Inverted truss at one location& cast
pircaps were designed in skew; as a two girders and side shift the same
result the length of girder varies from again side shift the total supporting
15.5m to 31.7m with different cross
sections in this area. The gap between
two adjacent span PSC girders were
only 100mm so we have to plan both in
proper sequence i. e. casting one span
girder with adjacent span stressing. In
this particular area (7000 sqm) we have
cast 140no’s PSC I girders at first level
and 10 no’s box girders at second level
in following sequence.
1. Cast RHS Side 1st Level I Girder &
RHS Side 2nd Level Box Girder. 5.3 Steel Girder:-
2. LHS Side 2nd Level Box Girder & In Railway area, there are total 80 no’s
after that LHS side1st Level I Girder. of steel Plate girders out of these 52no’s
are over Railway track. The maximum
3. Mid Span 1st Level I girders.
steel girder length was 51m with
Due to various length of I Girder & weight of 70 t.
the transverse distance between two,
Steel Girder execution involves
I-girder is more varying from one end
activities of Fabrication, Painting,
to another end. Due to this we were not
Transportation, Assembly & Erection.
able to complete the I Girder casting
by one time erection of supporting 5.3.1 Fabrication:-
arrangement for a single span. We
Fabrication of this steel Girder included
have to go for erecting of two or three
web plate,Top & Bottom flange of
supporting arrangement at the same
Built up I Section, End Cross Girders,
time for completion of I Girder in single arrangement over the truss for next Intermediate Cross Girders, Splice
span. two girders casting. Plate, Stiffners Plate, Bracings & Gusset
I Girder at middle Span for Plate etc. All structral steel conform to
connecting four arm at 1st Level. - FE410WB as per IS:2062 Grade-B.
Middle span I girders casting was Upon receipt at Fabrication yard, plates
started after completion of 2nd Level are stacked as per the Heat No.Proper
Box Girder at 2P19-2P21 (I Girder span Marking was done as per approved
is below that Box Girder span only) drawing. Material was cut to size by
as well as RHS & LHS Side I Girder & OXY-ACETYLENE Flame Cutting or
adjacent span I Girder also completed. Sawing. All Flame cut edges shall be
Hence there was space constraint from machined to clean, square & True edges.
all the three sides as well as there was Edge Preparation for welding shall be
no room for crane & Hydra Movement done by Machine controlled Flame
due to height restrictions. cutting with edges free from Burrs,
clean & Straight. welding is carried out
in accordance with approved welding
Procedure by RDSO. For welding Two
Flange Plates & Flange Plate with Web
Plate Submerged arc welding shall
At another span at P33-P34 where 14
be used as Per IS 4353-67.Minimum
Girders were to cast, Trestle erection for
Thickness of Fillet weld for Fabrication
I Girder Supporting was not feasible due
of Built up sections was varying from
to space constraints. The Span is over
6mm to 14mm. After completion of

5 GAMMON BULLETIN
welding the segments dimension shall
be checked as per approved drawings.
After fabrication of 5nos of segments
(no of segment vary based on span
length)trial assembly of Girder will
start.At the time of trial assembly
it is inspected by client & Railways
engineers jointly. After the approval
from both of them, it will go for Sand
Blasting & Metalizing or Painting work.

Method for Launching of Steel


5.3.3 Launching of Steel Girder: Girder at Central Line (Pier P4-P5A) :
We have taken Railway & CRS approval As per the Launching scheme we have
for two methods of Launching for to erect 3 Nos of Truss {Length35m
different spans: (Weight-34t),15.88m (Weight-13t), &
1. By 300 t Capacity single crane - For 18.04m (Weight-15 t)} over P4-P5A
all five spans. Span.So After completion of 14 nos
of Girder assembly one truss(Length
2. By Launching Truss and two 300t -18.04m) Erected over Piercap at P5A &
crane on both side – For launching of P6 for Trail Run of Steel Girder.
P4 – P5A (51m) span girder over main
line

Painting system is Epoxy based applied


in Five Coats (DFT=200 Microns) after
completion of Grit blasting work.

5.3.2 Assembly of Girder at Site:-


After reaching to site the Plate Girder
is stack on 500mm elevated ground
on wooden or concrete Block. During
the assembling approved nut & bolt
Purchased from approved RDSO
Vendor has been used. Bolts as
per IS:4000 & Nuts as per IS:6623 &
washers to conform IS:6649.
After Assembling of Girder the
Final dimensions were checked and
approved by Railway Engineer.

GAMMON BULLETIN 6
And one Trial Run of Steel Girder was By following this method all the 14
shown to Railway officers for Approval. nos of Girder has been launched &
After the Trail run Railway agreed to Transverse shifting of Girder Done.
give the main line block. After Completion of Launching, Truss
& Trestles are removed from that
As per Railway Requirement,
Locations.
Launching Activities of Steel Girder
including Temporary arrangement i.e
6. Challenges in the Project:
(Erection of Trestle & Placing 2nos of
Truss & Launching of 14nos of Girders The projects of this magnitude do
& Removing of 2 Nos of Truss & 1 nos of involve various challenges but in
Trestle will be complete within a time this project, the magnitude of the
Period of 13 Nights in2hr 30minutes challenges was abnormal and this
Shift /Night. Acutually we have coupled with heavy traffic, space
completed all Launching Activities restrictions etc made execution of this
within a time Period of 10 Nights in2.10 project quite challenging.
hr Shift/Night.
• Land availability for construction
and removal of physical hindrances
• Shifting of utilities with the
permission of various Government
department
• Number of revisions in GAD
• Approval of drawings from Railway
• Approval of Launching scheme
from CRS
• Obtaining shut downs from
Railways.
• Launching of Steel girders over
running track within block time
• Extra safety and stand by
arrangement to construct substructure
& super structure near the rail track
• Due to space restriction for
execution and critical design we have to
follow the sequances for construction

7. Safety Precautions:-
1. For Launching work responsibility
Chart Prepared for staff & PRW and
they were strictly working as per their
responsibility given in the chart.
2. Training conducted by Railway
Engineer to all the staff & Labours for
working in Railway Area
At a time we launched two steel 3. Animation made for launching
girders duly connecting with each Scheme & through that responsibility
other with cross diapraghms and for each task has been defined and
bracings. Longitudinal shifting done by awarded to individuals. Due to this
motorized trolley and after reaching its workers are having idea about the
position girders placed on pedestal by scheme of Launching & work as per the
using two cranes on either sides. scheme.

7 GAMMON BULLETIN
4. Not only for launching work, but also for work in Height for Box Girder & I Girder
work also Training was conducted for Labours. The Art of Photography
5. Safety Plan Prepared for Launching work. Similarly Crane Lifting Plan & Crane Just days after the Gammon’s
Safety Checklist were Prepared & followed the same as per the Approved Plan. SCLR flyover was thrown open
to public, the Photographer
Mr. Umesh Vaghela was in limelight.
His beautiful aerial photographs
of SCLR Flyover have gone viral,
and got high appreciation on
Social Networking sites. We wish
to give here an insight of the
technique used, difficultyand
thrills experienced while executing
the shoot of the structure before
accomplishing the final product
of these pictures, which had been
trending on social networking sites
and applications.
Clicking pictures capturing aerial
views is always an uphill task. Since
the area was an air funnel zone,
being close to the airport, we had
to seek permission from concerned
authorities before starting
shooting. After detailed study of
various locations on and around
site in several site visits, Mr. Vaghela
decided to shoot the picture from
the median of the upper deck of the
SCLR flyover which was providing
the best shot with the view of
the entire junction, including the
upper and lower deck, the arm of
the flyover that goes towards LTT
Terminus and Tilak Nagar.

8.Conclusion:-
The pictures were was taken
1. Inspite of several hindrances seriously affecting the smooth working at using a 12 megapixel, GoPro Hero
site, Gammon team has achived the success of completing this first double 3 + camera, mounted on a
dronewhich can be flown to the
decker flyover in India. height of 100 m. Its movements
2. Gammon team developed many innovative engineering solutions to can be tracked and angles can be
execute the work at different locations. By effective co-ordination and adjusted using a Wi-Fi connection.
For SCLR pictures drone was
vigorous follow up with clients and various authorities, hindrances were
released 70 m above the SCLR.
removed. By meticulous Planning & team work, Gammon has completed Once everything is in place, pictures
the prestigious project of MMRDA in extended duration of the Contract. are clicked using a remote control.
It is a dream project for Mumbikars and seen as a game changer for travel Without this equipment it wouldn’t
from eastern suburbs to western suburb. Its unique layout also enhances have been possible to take such
the beauty at ground as well as from aerial angle. beautiful photographs.

GAMMON BULLETIN 8
INNOVATIVE SCHEME FOR RECTIFICATION OF
UNPRECEDENTED TILTS FOR WELLS OF PASIGHAT BRIDGE
(Border Roads Organization) to have wells. The proposal of abandoning of
multi span bridge with cantilever super the wells is highly time consuming
structure. hence there was a need to work out a
solution for bringing the well back to
The bridge is 703 m. long having span
its normal position. The creativity of
configuration of 4 x 117m, 1 x 112m, 1 x
Gammon team of Engineers came into
R. RAGHAVAN 64m and 1 x 57m.
play and innovative tilt rectification
General Manager
4. THE WELLS scheme was worked out.
1. INTRODUCTION The wells P3 and P4 which were located
in the midstream of the river in a high
A large area of Arunachal Pradesh is velocity zone were designed to be
devoid of proper road communication installed in place by floating caisson.
system and hence is inaccessible. The actual river bed strata encountered
With a view to provide impetus to during the process was entirely
the economic growth of this region, different from what was envisaged in
Govt. of India decided to develop the tender based on pre-tender sub-
and improve road communication soil investigation. Densely compacted
in Arunachal Pradesh. Accordingly and vary large boulders were found
various plans were prepared including right from the upper level posing a real
extending NH37 in Assam. To translate threat for sinking efforts which proved
these plans, several formidable rivers to be an uphill task.
which come in the way are to be
bridged. The first major bridge is across 5. THE MISHAP
the river Siang to connect Pasighat on During the season of mishap, the river
south to Mebo on the north of the river. experienced prolonged period of
2. THE RIVER floods with discharge as high as 41000
cumec. During the flood, the river
The long Siangriver covering a distance carries lot of floating logs and boulders
of 1625 K.m., originates from Tibet and and water level remaining as high as
enters Indian Territory in high reaches at 162.5m, i.e. 9m. above designed
of Arunachal Pradesh. From there it LWL. The well P3 and P4 were exposed
travels another 226 K.m. and reaches to this unprecedented river floods
Pasighat. Beyond Pasighat it takes and remained submerged for over six
the name of Brahmaputra and joins months.
Lohitriver before it enters Bangla Desh
and finally is engulfed by the Bay of After floods resided to a level upto 6. THE INNOVATIVE
Bengal. which well was cast in previous RECTIFICATION SCHEME
season but when top of the well was
Siang river is known for its immensely After a prolonged and careful thought,
not visible, it was realized that due to
turbulent waters, unprecedented it was decided to pull the wells towards
prolonged floods and heavy discharge,
floods of high velocity and having downstream by means of 12/8mm
massive uneven bed scours must have
large catchment area which receives HT wires from either side of the bank
taken place which resulted in abnormal
heavy rainfall. A little rise in the with the help of Anchor blocks and
tilts. When floods resided further and
water level increases the velocity stressing the cables. Required forces
navigation around wells was possible,
considerably which makes navigation were worked out and suitable design of
the tilts were measured and found to be
in the river extremely difficult especially Anchor blocks was arrived. Besides the
having unprecedented in magnitude
maneuvering around well locations. system of pulling, it was also necessary
viz of the order of 1 in 2.34 and 1 in 6
The unhindered working season for to carry out and extensive grabbing
for wells P3 and P4 respectively. This
the river is hardly four months in a year of river bed on the downstream side
magnitude of tilt is highly abnormal
between December to March that too of half circle portion of tilted well
and possibility of rectifying these tilts
when winter season is at its peak. with 2nos. cranes so as to reduce the
by conventional sinking methods
surrounding earth pressure and allow
3. THE BRIDGE was ruled out. The options left were
the well to fall on the downstream side
to either nurse the tilted wells by
After examining several alternatives, by its own weight in a resistance free
rehabilitation by some special method
it was decided by the department manner as pulling continues.
or failing which abandoning the entire

9 GAMMON BULLETIN
Additional lifts of well staining were 7.2 Crushing of Pre stressing cones After grabbing for over 500 hours and
cast with a provision of embedding removal of soil on both inside as well
Initially concrete male and female
and locking pre- stressing cables at as outside of downstream portion
cones were used for stressing cables.
dead end at inner face of the well. of well and applying forces through
But these cones were getting crushed
This portion was strengthened with four cables on either side of jack with
because of enormous stresses
additional reinforcement and rich pressure upto 290 kg/cm2 in each
generated by repeated stressing,
concrete so as to serve as the anchor. cable, positive signs of movement were
locking and de-stressing of cables.
The laying of HT wires in the fast The operation involved number of de- observed.
flowing river was extremely difficult stressing operations as extension of When the well started moving in
task. To facilitate this six floating jacks at any given time was restricted to the required direction, operations of
bamboo made crafts were deployed only 300mm. Ultimately to overcome grabbing and stressing of cables were
along the line of alignment of well. this problem, steel male and female continued vigorously in a controlled
Additional precautions were taken to cones had to be provided. manner to maintain of the well which
avoid different or unequal sags and was checked regularly by theodolite
7.3 Difficult Soil strata
twisting of wires while laying. and leveling instruments. When well
Since sub-soil was consisting of was rectified to the level of I in 13
After laying of wire to the well location
densely compacted materials mixed tilt, monsoon was set and further
the dead end of wires were locked in
with heavy boulders and gravels, no rectification was suspended which
the well with Freyssinet anchorage
satisfactory materials were coming out restarted again after monsoon.It
system. After laying twelve wires in
during the grabbing inside the well. needed further 60 days of extensive
between well and anchor blocks, the
At the end of the day when work was efforts in the next season to bring the
wires were bundled to form a cables
stopped, sump was getting filled up well to its normal position.
and such four cables of twelve wires
with rolling boulders and gravels due
each were laid from well to both sides 9. CONCLUSION
to water current. To solve this problem
of end blocks garlanding the well.
extensive diving inside the dredge hole Successful rectification of massive tilt of
Two nos. of cranes were stationed on was restored for clearing the sump well P3 and P4 of Passighat Bridge are
barges face to face on either side of the area. Also minimum eighteen hours great examples of innovative approach
wall along the bridge alignment to carry of grabbing was done by each crane in the field of bridge engineering.
out grabbing. Simultaneously pulling every day and thereby reducing idle
of wells by stressing of cables from time during which sump was getting Rectifying tilt of this magnitude is in
both side end anchor blocks and very filled. itself a herculean task which coupled
extensive grabbing with two floating with other adverse factors (like
7.4 Extension of Well steining unpredictable weather, excessive rains,
cranes was carried out both from inside
and outside on downstream portion of It was realised that during the process heavy floods, tremendous velocity of
the well to bring the well to its normal of tilt rectification, the well may get river water, communication problem,
position. submerged as tilt rectification will extremely limited working season and
result in sinking of the well. Since the other limitations of remote location
7. PROBLEMS ENCOUNTERED erection of steining shuttering at well etc.) made this a great challenge for
AND THEIR SOLUTIONS location was not possible, the entire Gammon Engineers. The success in this
This scheme during its implementation steining shuttering in required shape mission inspite of all odds is a result of
encountered several problems, was erected outside the well and sheer determination and dedication of
solutions of which were worked out placed as a caisson on steining with the team of Gammon Engineers.
on-the-spot at field level by able team help of two cranes. All shuttering plates
of GAMMON Engineers. were provided with gasket and utmost
7.1 Uneven river bed profile care was taken to make shuttering
water-tight before it was put to use.
As the river bed profile along the axis
in between well and end anchor blocks 8. IMPLEMENTATION OF
were uneven and HT cables had to SCHEME
cross substantial length on dry river
The scheme was first implemented
bed with ups and downs, the cables
in well P3. Pulling of HT wire with
were touching dry bed at various
pre-calculated heavy forces and
locations creating friction and thereby
simultaneous grabbing with the help It is expected that documenting of
losing part of the stress. To avoid such
of two cranes was carried out. The this innovative success story and
losses, several propped supports were
cables were stressed using S7 hydraulic making it available for use by brother
given in dry bed at various locations to
jacks. The stress applied and developed engineers elsewhere will go a long
maintain the level of the cable profile
in each cable step by step was in the way in the history of innovative bridge
as desired.
increments of 25t pulling forces. engineering.

GAMMON BULLETIN 10
TEAM MANAGEMENT SKILLS
1. Introduction fabulous vision of the future, only to believe that most are happy and
fall flat on your face when it comes to willing to work, you’ll tend towards
You’ve just got a promotion or a new implementation. Theory Y. Make sure that you fully
job as a Manager. Congratulations! understand these theories – they will
What a challenge! Or, maybe you’ve 3. The Importance of fundamentally affect your success in
just been given the task of pulling Delegation motivating people.
a new team together. Either way,
The top priority for team managers Whatever approach you prefer to
whether your team exists already or
is delegation. No matter how skilled adopt, you also need to bear in mind
it’s your responsibility to create it, it
you are, there’s only so much that you that different people have different
is a challenging task. How will you
can achieve working on your own. needs when it comes to motivation.
go about this? What do you do first?
With a team behind you, you can Some individuals are highly self-
What do you do next?
achieve much more and that’s why motivated, while others will under-
This article looks at some of the key it’s so important that you delegate perform without managerial input.
things that team Managers need to do effectively! As a leader you need to manage them
if their team is to thrive and succeed. in either case. Also one particular
These range from choosing the right Successful delegation starts with approach of motivating a person may
people and deciding who does what, matching people and tasks, so you not work for the other person.
communicating with internal and first need to explain what your team’s
external people, developing and role and goals are. A good way of
doing this is to put together a team TWENTY YEARS DOWN
motivating people. It also covers
some of the most common pitfalls to charter which sets out the purpose THE MEMORY LANE !!!
be avoided. of the team and how it will work. Not - M U SHAH
only does this help you get your team A Civil Engineer’s wife awakes during
2. First Things First off to a great start, it can also be useful the night in a site colony and find that
for bringing the team back on track if her husband is not in bed with her. She
Before we go to the topic of it’s veering off course. goes downstairs to look for him. She
developing a team, it is necessary finds him sitting in the verandah with a
Only then will you be in a position cup of coffee in front of him. He appears
to understand the vital difference
to think about the skills, experience to be in deep thought, just staring at the
between management and sky. She watches as he wipes a tear from
leadership. and competencies within your team, his eye and takes a sip of his coffee.
and start matching people to tasks.
A good starting point is the quote of “What’s the matter, dear?” she asks.
This is basically a task allocation. In
Warren G Bennis: “Leaders are people “Why are you in verandah here at this
real world you never get a human time of night?”
who do the right things; managers resource perfectly matching your
are people who do things right.” The husband looks up sipping coffee,
requirements and it is challenging “Do you remember twenty years ago
Leadership involves creating a task to identify and manage the gaps when we were dating, and you were
compelling vision of the future, between team members’ skill sets and only sixteen?” he asks solemnly.
communicating that vision, and requirements. “Yes, I do,” she replies.
helping people understand and “Do you remember when your father
commit to it. Managers, on the other 4. Motivating Your Team caught us in the back seat of my jeep
hand, are responsible for ensuring …..?”
Another key duty you have as
that the vision is implemented a Manager is to motivate team “Yes, I remember,” says the wife, lowering
efficiently and successfully. members. herself into a chair beside him.
Of course, these two roles may The husband continues, “Do you
Popular Theory X and Theory remember when he shoved the shotgun
overlap and to be fully effective, you Y explains two very different on my forehead and said, ‘Either you
need to fulfill both roles. However, approaches to motivation, which marry my daughter, or I’ll send you to
the focus of this article is on the depend on the fundamental jail for 20 years ?”
specific skills and responsibilities of assumptions that you make about “I remember that, too,” she replies softly.
managers and on the tools available the people who work for you. If you He wipes another tear from his cheek
to them. After all, there’s no point believe that they’re intrinsically lazy, and says, “I would have gotten out
energizing people to work towards a you believe in Theory X, while if you today !!!”

11 GAMMON BULLETIN
5. Developing Your Team and communicating with people you’re approaching your boss for
outside your team. We’ll look at each advice, make sure you’ve thought
Teams are made up of individuals in turn. things through as far as you can.
who have different outlooks and Introduce the subject with a summary
abilities, and are at different stages 6.1 Communicating With People
of your thinking, and then say where
of their careers. Some may find that in Your Team you need help.
the tasks you’ve allocated to them As a team manager, you’re likely to
are challenging, and they may need Also, as a manager, part of your job is
be chairing regular sessions as well
support. Others may be “old hands” to look after your team and protect
as one-off meetings. Meeting of all
at what they’re doing, and may be it from unreasonable pressure. Learn
kinds, and regular ones in particular,
looking for opportunities to stretch skills like assertiveness and win-
are notorious for wasting people’s
their skills. Either way, it’s your win negotiation , so that you can
time, so it’s well worth mastering the
responsibility to develop all of your either turn work away, or negotiate
skill of running effective meetings .
people. additional resources.
Many meetings include brainstorming
Your skills in this aspect of Another part of your job is to manage
sessions. As a team manager, you’ll
management will define your long- the way that your team interacts
often have to facilitate these, so
term success as a Manager. If you can with other groups. Use stakeholder
you’ll need to be comfortable with
help team members to become better analysis to identify the groups that
doing this. There’s more to this than
at what they do, you’ll be a manager you need to deal with. Then talk to
simply coming up with creative ideas,
who people aspire to work for, and these people to find out what they
as you do when you’re just a regular
you’ll make a great contribution to want from you, and what they can do
participant in such a session. Make
your organization, too. to help you.
sure that you understand where they
The most effective way of developing can go wrong, and what you can do Apart from your own team or other
your people is to ensure that you give to avoid this. groups in your organization, you
regular feedback to members of need to communicate with external
Active listening is another important
your team. Many of us are nervous of world viz. Customer, Vendors and
skill for managers – and others –
giving feedback or feel shy in giving other Stakeholders.
to master. When you’re in charge,
the feedback, especially when it it can be easy to think that you 7. Managing Discipline
has to be negative. However, if you know what others are going to say,
give and receive feedback regularly, or that listening is less important, However much you hope that you
everyone’s performance will improve. because you’ve thought of a solution won’t have to do it, there comes a
You need to appreciate and beforehand anyway. time in most managers’ careers when
understand development needs of Don’t fall into this trap. Most good they have to discipline an employee.
individual team members, so that managers are active listeners: it helps Discipline may be subtly different
they can perform at their best. If you them detect problems early (while from basic feedback, because it
have to bring a substantial number they’re still easy to deal with), avoid doesn’t always relate specifically to
of new people into your team, it is a costly misunderstandings and build the employee’s work. You can give
great challenge. You need to learn the trust within their teams. feedback on their phone manner, for
art of forming, storming, norming example, but handling problems with
and performing to learn about the 6.2 Communicating With People timekeeping or personal grooming
stages you can expect your team to Outside Your Team can need a different approach.
go through. You can do a lot to help Your boss is probably the most
Obvious breaches of the law or of
your people through this process. important person you need to
company policy are easy to identify
communicate with. Take time to
6. Communicating and and deal with. But what of other
understand fully what your boss
Working With Your Team – and situations? On one hand you don’t
wants from you and your team – if
want to seem petty. On the other
With Others you know exactly what he likes, and
hand, you can’t let things go that
how he prefers this to be delivered,
Communication skills are essential for you’ll be better able to meet with his should be dealt with.
success in almost any role, but there approval. Use these rules-of-thumb to decide
are particular skills and techniques whether you need to take action.
that you’ll use more as a Manager Don’t be afraid to ask your boss to
coach or mentor you: you can usually If the answer to any is yes, then you
than you did as a regular worker. need to arrange a time to speak to
These fall under two categories: learn a lot from him, but he may not
be proactive about offering this. If the employee in private.
communicating with team members,

GAMMON BULLETIN 12
1. Does the issue affect the quality of 8. Traps to Avoid (whether internal or external) about
the employee’s deliverable to the client what they want from yourself and
(internal or external)? There are a number of common your team.
mistakes that new managers tend to
A Section In- Charge regularly comes make. Take care to avoid them! • Using your authority
to site late, although he stays at inappropriately – make sure that
Site till late evening. Customers are These are: everything you ask people to do is in
sometimes frustrated by not being • Thinking that you can rely on your the interests of the organization.
able to get through to him at the start existing job knowledge and technical Many of these points sound obvious,
of the day, particularly when he’s skills to succeed as a manager. It is however it’s incredibly easy to make
working on critical activities. essential that you take the time to these mistakes in the rush of everyday
develop good management and managerial life.
people skills as well – these can be
2. Does the issue adversely impact the more important than your technical 9. Conclusions
cohesiveness of the team? skills!
Individual Section In-charges tend When you move from being a worker
• Failing to consult regularly with to a line manager, you need to develop
to work on their own sub projects your boss, in a misguided attempt to
and meetings do take place a new set of skills, and make use of
show that you can cope on your own. new tools and techniques. These will
between them, so cohesiveness
is not impacted. However people • Approaching your boss without help you with the key management
are noticing his lack of punctuality, having thought a problem through, activities of organizing, motivating,
and other people’s timekeeping is and without having considered how developing and communicating with
beginning to slip. the problem could be solved. your team.
• Embarrassing your boss, or letting Above all, key thing is learn how
her get a nasty surprise. Follow the to delegate effectively. However,
3. Does the issue unnecessarily “no surprises” rule. also learn how to motivate
undermine the interests of other people, develop team members,
individuals in the team? • Doing anything that requires your
communicate effectively with people
boss to defend you to others. This can
The deputy of late comer Section In- inside and outside your team, and
cause your boss to “lose face” with his
charges is unhappy that he has to manage discipline effectively.
peers and superiors, and it makes it
field calls from clients and attend to And make sure that you avoid the
look as if his team is out of control.
them before he reaches the site and mistakes that many new managers
is unable to give a firm answer to the • Failing to talk to your customers
make!
question “When will he be in?”
In this situation, the manager decides
to speak to the latecomer because
of the impact on his co-worker.
They agree that coming in to work
late is not a problem (he has a long
commute, with heavy traffic en route)
but that he will commit to being in site
by 8.30 a.m. every day if not at 8.00 a.
m. to reduce the number of calls his
co-worker has to field, and also give
him a fixed time to give clients. He will
work late to make up time, and will
take on a task as per requirement.
When you are faced with a potential
discipline issue, take time to gather
information about the situation,
decide what you’re going to do, and
act. Discipline issues rarely go away
of their own accord, and they usually
get worse, often causing considerable
resentment amongst other team
members.

13 GAMMON BULLETIN
SERIOUSLY , LAUGHTER IS THE BEST MEDICINE
(LET US) MAKE(IT)UP !!!
- M. U. Shah

From my childhood days I hate different matter. Many women wear your eyesight is perfect. There’s
looking in the mirror. I don’t know thick makeup and even strange nothing wrong with your eyesight !!”
why but somehow I don’t like looking clothing to disguise the
Also women’s love for mirror and
looking in the mirror – may be in my perceived flaws and repeatedly seek
makeup is universal. Tracy Letts once
own esteem I don’t like my face or reassurance by looking in the mirror.
wrote “All women need makeup.
whatever but the fact remains that I But whatever the reason, it seems
Don’t let anybody tell you different.
don’t like to see in the mirror. I tend staring at our self in the mirror does
The only woman who was pretty
to agree with M.F. Moonzajer, when more psychological harm than good.
enough to go without makeup was
he wrote : “Stop looking in the mirror New research shows volunteers who
Elizabeth Taylor and she wore a ton.”
and forget how you look like; we are gazed at their reflections for up to
all special the way we are.” ten minutes at a time gradually Similarly Hannah Harrington wrote,
became more and more anxious and “All of them are the same type; girls
When my beard started growing I had
depressed about their looks - even if with over-processed hair and too
to compulsorily look in the mirror for
they were perfectly happy with them much makeup and way too much
shaving but then it was limited to
to start with. access to Daddy’s credit cards. Girls
this daily chore at 7 o’clock’ in the
who, if you took away the designer
morning ( in fact I was using stainless Passion for looking in the mirror exist
labels, hair dye and cover-up,
steel blade with brand name ‘Seven in whole spectrum of population of
wouldn’t be more than average-
o’clock’ which was popular in those ladies starting from Miss universe
looking, but with all that stuff look
days though because of aggressive kind of beauties on the upper side
too plastic to be pretty.”
marketing by Gillette, stainless of the range to even not-so-beautiful
steel blades have got practically kind of ladies on the other end Once I went to one of my close
eliminated). However the frequency of the spectrum. We can perhaps relatives’ place in Gujarat. They had
of this encounter with mirror was understand ladies on north of this a small house with only two rooms
limited to once in a day only. Since spectrum using mirrors but I am yet and out of these two rooms only one
then this daily routine continues to understand why those on south of of the rooms was having the facility
except that it does not happen this spectrum need mirror! Similarly of mirror. When my relative saw my
on Sundays unless some review this love for mirror has nothing to face unshaved till ten o’clock, he
meetings are scheduled in office on do with the age - irrespective of asked me why I have not finished
Sundays. age women love mirror with same shaving as yet though it is past
intensity though Balthasar Gracian, ten am. He asked whether I need
Once somebody asked me if I had an
writes in his book, ‘The Art of Worldly a shaving kit. I wanted to say that
option of getting fulfilled one and
Wisdom’ that “A beautiful woman mirror is not free but protocol of close
only one wish, what would I ask.
should break her mirror early” but family relation prevented me from
I replied, “ I wish I could avoid looking somehow many women do not agree giving this blunt answer. He had two
in the mirror for say six months !” with Gracian. young daughters who from seven
o’clock in the morning - the moment
Of course for this I will have to take A retired Civil Engineer and his wife
they got up, started queuing up in
six months leave from office because are getting ready for bed. The wife
front of mirror. If younger one takes
currently I don’t like my face myself is standing in front of a full length
more time, elder one will come and
but if I had to grow my beard for more mirror taking a hard look at herself.
push her and by the time they both
than six months, many people from
“You know, dear,” she says, “I look in partially finish their work, their mom
office will start agreeing with me !
the mirror and I see an old woman. My will come and replace them. Sitting
Contrary to this, ladies love face is all wrinkled, everything else is on sofa, with newspaper in my hand,
mirror- more than their respective either sagging or bloated. I’ve got fat I kept on watching these three ladies
boyfriend(s) or husband(s). Study legs, and my arms are all flabby.” struggling to get priority in front
shows that on an average, women of mirror. If one would try to stop
She turns to her husband and says,
stare in the mirror 38 times a day. the other in the middle , the other
“Tell me my dear, something positive
Some of them do it out of sheer would say, “ Hold on, it is my turn
to make me feel better about myself.”
vanity, others because they hate the now. I have not used mirror for even
way they look and want to try and The Engineer studies hard for a twelve minutes till now. When it was
change it. Of course whether they moment thinking about it and then your turn you used mirror for twenty
can change it or not is altogether a says in a soft, thoughtful voice, “Well, minutes. I am entitled to take twenty

GAMMON BULLETIN 14
minutes or being elder to you even The lady in a night dress (without environment or bearish environment,
more.” Seeing this I didn’t dare to use makeup) opened the door. the business of beauty products
mirror for shaving purpose. I thought grows alike.
He said, “ Sorry, madam, I think I am
if I start shaving and in the middle
on the wrong floor.” Once a Stock Market expert was
one out of three ladies gets an urge
asked by a television journalist as to
to look in the mirror on emergency His wife dragged him inside saying,
which scrip excites him the most. He
basis, forgetting अितिथ देवो भवः “Come in. I will show you the right
replied, “ Lovable Lingerie !” What he
culture of India, they may push me floor!”
really meant to convey was that this
away from the mirror, while shaving One gentleman who was unmarried scrip has given a fantastic return of
cream is still on my face, which will even at age of 35 years plus when over 50 % in one year. When many
put not only me but even host also in asked why he has not married as yet companies are struggling for survival,
an embarrassing position. I always try replied,” I am earning wages of Rs. 220 I don’t know why both the top line
to avoid conflict kind of situations- per day. If I marry, my wife’s lipstick and bottom line of business of
both in office and at home front and alone will cost Rs. 220. How can I lingerie is growing at such a fantastic
accordingly I decided to postpone survive?” rate! They say that though lingerie of
use of mirror till it became free but
Once I went to a restaurant in the latest fashion fetch fantastically high
that was not to happen and at lunch
afternoon. I heard a group of ladies price premium, cost of production of
time I had to go to a nearby saloon
chanting aloud: ‘Let us make it up! Let such so called expensive lingerie is
for a shave. The next day morning I
us make it up ………. !’ hardly anything which is the secret of
got up at 6-30 am, well before these
they generating huge profits.
three ladies get up, to use the mirror I asked one of the waiters as to what
before it is engaged. they are doing. The waiter replied, “ I agree with Mokokoma Mokhonoana
This is a kitty party of group of ladies. when he once said, “Primary purposes
Once one young Civil engineer took
They come here every Saturday.” of a mirror are twofold:
his girlfriend to an open air theater
for one programme. His girlfriend I said, “ That’s fine but what this loud (1) To help civilized men realize their
told him to bring some popcorns chanting is all about?”. imperfections and
from outside. He left for bringing (2) To help the imperfect hide their
popcorns. Meanwhile there was a He replied, “ They are saying ‘Let us
make it up’ i.e. whatever deficiencies imperfections.”
down pour of rain. When he returned
to his place, he asked the lady, “ Excuse are there in our beauty, let us make it Inspired by this beautiful quote
me madam, my GF was seating in this up (by makeup)!!!” when I became older, I started
seat, do you have any idea as to where That day I understood why Shahnaz using mirror for self-introspection. I
she has gone ?” What happened next Husain’s business is growing by leaps realized that mirror is the best tool for
can be understood without writing and bound when giant infrastructure self-introspection and accordingly
about it. In fact this was an eye- companies are de-growing at fast I installed a full size mirror in our
opener for him at the right time. He rates. I am a student of Stock Market house. I liked this idea and started
realized for the first time in his life and keep tracking growth stories using mirror more and more. Over a
the difference between girls with across sectors and across countries period the frequency increased to
and without makeup. Of course for and could trace back growth of all such an extent that my wife started
the purpose of ‘go’ or ‘no go’ kind of a companies but one company whose doubting me. It needed a lot of time
decision for marriage, he knew what phenomenal growth I was unable to explain to her that I am looking at
was more relevant. to explain through theory was the the mirror only for self-introspection
company in the business of beauty. and not for cosmetic purpose. I said
In marriage vows they say husband to her “You know that I have not
has to take an oath that he will love Corporatisation of beauty business
has converted this business to an used mirror for cosmatic purpose
her both in good times and bad even when I was young. What makes
times and that he will never leave enviable billion $ opportunity as a
result of which many board room you thing that at this age I could use
her deserted. May be we may have mirror for cosmatic purpose?”
to introduce an additional vow discussions started focusing on
that husband will love her in both diversification in this space rather We are so much obsessed by mirror
situations - with and without makeup. than continuing with debt-trapped for cosmetic purpose right from
infrastructure sector. Another beauty our childhood days that we need
One frequent traveler Civil Engineer of this beauty product business is decades of personal self-experience
returned from a tour but due to that it is seldom affected by cyclic to realize what Sophia Nam once
delayed flight it was past midnight ups and downs common for all other said, “The mirror is the worst judge of
when he reached his place. He sectors. Whether there is a bullish true beauty!”
pressed the doorbell of his flat.

15 GAMMON BULLETIN
WORKS IN PROGRESS

Pylon Fabrication shop in China for Signature Bridge Pylon base erection at Signature Bridge, Delhi

Elevated Water Tank at Patna, Bihar General Civil Works for 3 x 660 MW Power Plant at Sasan, MP

Pylon Pedastal Casting at Surat Cable Stay Bridge, Surat Sub-structure Works at Gangapath Elevated Road, Patna, Bihar
DISMANTLING & RECONSTRUCTION OF PIER (P-44) FOR M G SETU AT PATNA, BIHAR



P-44

P-43 SIDE P-45 SIDE

DISMANTLING WORK IN PROGRESS BY


DIAMOND WIRE CUTTING METHOD

Rapairs Works at Old Ganga Bridge, Patna, Bihar


31-05-2014 Flue Can Erection for Chimney, Sagardighi, West Bengal

GAMMON BULLETIN 16
A Million thanks to our
ESTEEMED CUSTOMERS

17 GAMMON BULLETIN
NEWS FLASH INSPIRING STORY OF THE PREGNANT DEER
1. Change in Skyline of Nigrie. In a forest, a pregnant deer is about The sequence of events that follows
to give birth to a baby deer. She finds are:
Gammon’s Project Team Successfully a remote grass field near a strong-
Completed the Shell for Second - While the hunter was about to
flowing river. She considers this to be
Natural Draught Cooling Tower release his arrow towards the deer,
a safe place and she plans to settle
(NDCT-2)at 2x 660 MW Ultra Mega one more severe lightning strikes &
down there to give a birth to a baby.
Power Project for Jaiprakash Power blinds the hunter. The arrow which
Ventures Ltd. at Nigrie, Madhya Even before she settles down, labour got released from the hunter’s bow
Pradesh with remarkable Quality, pain begins. Simultaneously all of a zips past the deer but strikes the
Safety &perfection in Shell Profile. sudden dark clouds gather in the sky hungry lion.
with thundering and lightening. In a
Standing tall at 190.5 m and - It starts to rain heavily & the forest
couple of minutes severe lightning
changing skyline of Nigrie, this is the fire is slowly doused by the rain.
accompanied by loud thundering
second tallest NDCT constructed by strikes the grounds which leads to a - The deer gives birth to a healthy
Gammon Team till date. forest fire. baby deer.
2. Completion of Diaphrgm Panels She looks to her left & sees a hunter In our life too, there are moments
for Intake Well at Patna. with his extended bow pointing at when we are confronted on all
her. To her right, she spots a hungry sides with difficulties, problems,
lion approaching her. Thus she is challenges, negative thoughts etc.
surrounded by a hunter on left, a lion and possibilities or opportunities
on right, fire on one side and flowing are not easily seen. However even
river on the other side. under such worst situations also
possibilities and opportunities do
exist. We, somehow need to look for
What can the pregnant deer do?
possibilities and opportunities even
She is in labour! in such extreme circumstances. We
will find that positivity is so powerful
What will happen?
that it overcomes our problems &
Will she survive? overwhelm us.
Will she give birth to a baby deer? Maybe we can learn from the deer.
Will the baby deer survive? The priority of the deer, at that given
moment, was simply to give birth to
Or will everything be burnt by the forest a baby. The rest was not in her hands
GIL Patna Water Supply site completed
the last and 16th panel of diaphragm
fire? & any action or reaction that changed
wall of Intake Well on 5th June, 2014. Or will she get drowned in flowing river? her focus would have possibly
resulted in death or disaster. A wrong
Well by diaphragm wall method has Or will she perish to the hunters’ arrow?
been done for the first time in the
move and in a fraction of second she
Country. GIL adopted this innovative or will she die a horrible death at the could have perished. But under the
technique instead of conventional hands of the hungry lion approaching guidance of almighty God, she rightly
method of casting well. Whereas her? focused on the most vital thing at
conventional method of laying kerb that point of time and completely
and casting lifts of staining one by one She just cannot escape anywhere as ignored rest of the things.
and simultaneously sinking the well is she is constrained by the fire on the
quite time consuming, this innovative one side & the flowing river on the Ask yourself, where is your focus?
method requires very short time for other & hunter on the left and lion on How strong is your positive approach?
construction. In major rivers like Ganges the right.
where working season is very limited, Where is your faith and hope?
the construction of well by conventional What she should do?
method could span two working seasons In the midst of any storm, do keep it
and between two seasons the well is Do you know what she did? on God always.
vulnerable to possible tilts during floods. She prays almighty God and He will never ever dissapoint you.
As against this construction of well up to
focuses on giving birth to a new life NEVER.
the level of island by diaphragm method
has taken about three months only
completely forgetting about what all
happening around her. Remember, GOD neither slumbers
resulting in substantial saving of time. nor sleeps...

GAMMON BULLETIN 18
COMPANY NEWS
World Health Day
WELCOME TO AWARDS As an initiative towards promoting Safety,
GAMMON FAMILY Health & Environment culture, Gammon
celebrated World Health Day on 7th April;
2014. Various health awareness events &
National Safety Awards camps were organized across various sites.
ASSISTANT VICE PRESIDENT
Aniruddha Deshpande As a part of Corporate initiatives towards
promoting Construction Safety culture
in the Organization, we participate &
GENERAL MANAGER nominate various Gammon Sites for
Safety Awards declared by National
PeushShanker
Safety Council every year. In year 2013
also Gammon actively participated for
Safety Awardsprogrammein a big way.
DEPUTY GENERAL MANAGER
KabiladossRajagopal With profound pleasure, we state that
the following Gammon Projects were
declared winners for prestigious “Safety
MANAGER Award” of Year 2013.

Abhijit Gupta Prashansa Patra Award


BhupatiBera 8611 Mumbai Port

Pranesh Ghosh Appreciation Certificates Issue No – 51 Health & Safety Department: Gammon House, Veer Savarkar Marg, Prabhadevi, Mumbai-400025,
ST 07/04/2014 +91-22-6111-4000/4146  +91-22-2430-0221/0529 corporatesafety@gammonindia.com
8707 Wazirabad Bridge
Health Check–up Camp
9012 RVNL Station Building
DEPUTY MANAGER As an initiative towards promoting Safety,
Mahendra Desai 8932 Runwal Elegant Building Health & Environment culture & create Health
awareness among the employees , Gammon,
Swaminathan Pichuiyer 8950 Lapanga Chimney
in association with Seven Hills Hospital,
8804/07 Krishnapatnam DCT Mumbai organized a Health Check Up Camp at
Rajiv Rishi Gammon House, Mumbai on 17th June 2014.
Rakesh Srivastava 8728 Guwahati WSP As many as 227 employees from Gammon HO
took the Benefit of the same.
SumanGusain 8949 JSW Civil Works, Bellary

SougataMitra 8802 Munger Bridge

Narayanamoorthy Panchaksharam 8847 Signature Bridge

Nikhil Dawda We wish to place on record our


appreciation to the entire Gammon
Anand Holkar team of the above projects for this
Sandeep Kumar remarkable distinction conferred on
the above Projects.
Blood Donation Camp
LECTURES EVENTS As an initiative towards CSR, Gammon,
DELIVERED in association with J J Hospital, Mumbai
CYCLOTHON organized a Blood Donation Camp at
Gammon House, Mumbai on 17th May 2014.
International Road Federation, (IRF), along As many as 65 employees from Gammon HO
Mr. Janardhanam Varatharajan with MoRT&H and Delhi Traffic Police donated Blood.
organized Cyclothon on 20th April 2014
Chief Safety Manager, CMRL Project,
in New Delhi. The Cyclothon was aimed
delivered a lecture on Safety on to highlight safety issues with respect to
invitation by the “American Society cyclists, who are among the most vulnerable
of Safety Engineers – Professional road users. The use of Cycles being a green
Development Conference (ASSE-PDC)” initiative needs to be encouraged in a big
at Chennai on 27th May 2014 way as a low cost environment friendly
option to negotiate short distances ranging
from 1 Km to 5 Km.

19 GAMMON BULLETIN
A CAPITAL EXCELLENCE
- THE Signature Bridge ACROSS YAMUNA AT DELHI

India’s First Cable Stay Bridge with an Inclined Steel Pylon


India’s first “Signature Bridge” being constructed by Gammon across Yamuna at
Wazirabad, promises to be a great tourist attraction of Delhi, the Capital of India. This cable-
stayed bridge will link NH-1at Wazirabadon Western bank and at Khajuri Khas on eastern
bank of the river Yamuna, connecting North Delhi with East Delhi.

With a length of about 575 m and a height of 175 m, the proposed Signature Bridge
would have a bow-shaped steel pylon in the middle. Two high towers will provide double
cable support in the inner periphery of the carriage way. The deck will be composite (steel
and concrete) while the pylon will be in steel.
Equipped with four lanes, this engineering masterpiece will have a1.2m wide central
verge, space for anchoring cables, maintenance walk way and crash barrier on either side
of the central verge. Once operational, the Signature Bridge will dramatically improve access
between North and West Delhi reducing present congestion and traffic jams and will become
the identity of Capital City – the way Taj Mahal is to Agra.

CLIENT: DELHI TOURISM & TRANSPORT DEVELOPMENT CORPORATION


CONTRACTOR: GAMMON INDIA LTD- C. CIDADE - TENSACCIAI JV
TM

DESIGN CONSULTANTS: SCHLAICH BERGERMANN & Partners, Germany


PROOF CONSULTANTS: M/s SYSTRA SA, France
Designed & Printed by

GAMMON INDIA LIMITED


GAMMON HOUSE, V. S. MARG, PRABHADEVI, MUMBAI 400025 INDIA
www.gammonindia.com, www.gammoninfra.com
EPC CIVIL| POWER T&D| POWER MANUFACTURING| PPP|REAL ESTATE
GAMMON BULLETIN 20