Task DURATION

(December 16,
2018 – March Week1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week10 Week 11 Week 12 Week 13 Week 14 Week 15
19, 2019)

Identification of the 4Days


project

Data gathering and 7 Days


Analysis

Proposals 4 Days

System Design 15 Days

Prototyping 22 days

Feasibility 7 Days

Programming 48 Days

Documentation 40 Days

Testing 8 Days

Project Developer System UI Database Techncal


Manager Designer Administration Writer
Requirements A R R R R
Gathering
Coding Design A R C I I

Coding Input A R C I I

Software A C R I I
Testing
Implementation A C R C C

Key:

R – Responsible for completing the task


A – Accountable for ensuring task completion
C – Consulted before any decisions are made
I – Informed of when an action/decision has been made
No. of Cost/Unit/Hr. Subtotals Level 1 % of Total
ITEMS Units/Hrs. Total
1. Support P7,580 100%

Internet 90 P60 P5,580

Electricity 20 P50 P1,000

Food 5 P200 P1,000

TOTAL PROJECT COST P7,580


ESTIAMTE

Name Role Quality Responsibility

Jhinecel Carballo Project Leader Quality coaching

Mrigold Platon Database Administrator Managing all ralated activities


about database
In charge of the quality of the
Leslie Tolentino System Designer project design

Ggerson Tamayo Software Developer Maintenance and testing of the


project
Ensures the complete project
Evenezer Abeles Technical Writer dcumentation

Tools Descriptions

Visual Studio 2015 is an integrated development environment from Microsoft. It is used to develop
Professional computer programs, as well as websites, web app web services and mobile apps.

Microsoft SQL Server is a relational database management system developed by Microsoft. As a


database server , it is a software product with the primary function of storin and
retrieving data as requested by other software application – which may run
either on the same computer or on another computer across a network
(including the Internet).
Risk Affects Description
An unauthorized personnel
Accidental Disclosure release the report that result
to leaking some important
information.
Acts of Nature The system may not be able
to use caused by
malfunctioning or damaged
it’s hardwares.
Electrical Distruption An interference that service
deny the user from its
activity.

System Configuration During the initial installation,


Error the software has incorrectly
configured damaged RAM,
that’swhy configuration error
occurs.

Potrebbero piacerti anche