Sei sulla pagina 1di 6

Form CETI-CC-MMXVIII

`
NEW CALUYA POWERPLANT Revision
COMISSIONING CHECKLIST Revision Date
Control No.

CLIENT DETAILS
Client Marcbilt Construction Inc. Date March 28, 2019
Address Caluya Island, Antique Sales Order No. SO2018-002

ACTIVITIES CONDITIONS TO MEET RESULT REMARKS


1. Voltage and Frequency Control
 Passed
Easygen is in Manual Mode. By  Failed
manually adjusting +/- voltage setpoint
1.1. Generator Manual Voltage
thru Easygen, the controller must react  Gen 1
Control
automatically to raise or lower the  Gen 2
voltage.  Gen 3
 Gen 4
 Passed
Easygen is in Auto Mode. The setpoint  Failed
will adjust automatically by the
1.2. Generator Automatic
controller and the voltage bias must be  Gen 1
Voltage Control
approximately 50% during no load  Gen 2
operation.  Gen 3
 Gen 4
 Passed
Easygen is in Manual Mode. By  Failed
manually adjusting +/- frequency
1.3. Generator Manual
setpoint thru Easygen, the controller  Gen 1
Frequency Control
must react automatically to raise or  Gen 2
lower the frequency.  Gen 3
 Gen 4

 Passed
Easygen is in Auto Mode. The setpoint  Failed
will adjust automatically by the
1.4. Generator Automatic
controller and the frequency bias must  Gen 1
Frequency Control
be approximately 50% during no load  Gen 2
operation.  Gen 3
 Gen 4
2. Validation of Parameter Readings
 Passed
Generator voltage must be reflected  Failed
on both Easygen and Digital Power
2.1. Generator Line-Line Voltage Meter and the reading must be  Gen 1
approximately equal to the generator  Gen 2
rated voltage.  Gen 3
 Gen 4
Form CETI-CC-MMXVIII
`
NEW CALUYA POWERPLANT Revision
COMISSIONING CHECKLIST Revision Date
Control No.

 Passed
Easygen generator current
 Failed
measurement configuration must be
2.2. Generator Current equal to the rated generator current.
 Gen 1
The CT Ratio of the digital power meter
 Gen 2
setting must be equal to the actual
 Gen 3
installed current transformer.
 Gen 4
 Passed
 Failed
Other parameter readings must reflect
2.2. Other Generator Parameter on Easygen and digital power meter
 Gen 1
readings and must be approximately equal to
 Gen 2
the actual parameter of Generator
 Gen 3
 Gen 4
Check the phase sequence of all
generators using phase sequence  Passed
3. Phase sequence of Generators
tester. They must all have the same  Failed
phase sequence.
Preliminaries:
1. Open all Feeder breakers
2. Close the Tie breaker

Close GCB of one generator manually


to the dead bus and manually
synchronize each generators using  Passed
Synch Check mode. Verify zero voltage  Failed
difference on each line of the two
4. Synch Check generators when synchroscope is on 12  Gen 1
o’ clock.  Gen 2
 Gen 3
Ex. G1 dead bus close, G2 in Synch  Gen 4
Check mode. Measure L1 of G1 and L1
of G2 then L2 and L3 respectively.

NOTE: The Easygen will not issue


generator circuit breaker command
when in Synch Check mode.
Preliminaries:
1. Open all Feeder breakers
2. Close the Tie breaker  Passed
 Failed
Synchronize G1 to G2 then G3 to G4. If
5. Synchronize in Run mode okay proceed with the synchronization  Gen 1
of the 4 units.  Gen 2
 Gen 3
NOTE: Always observed the circulating  Gen 4
current of the generators. If not zero it
must be very minimal.
Form CETI-CC-MMXVIII
`
NEW CALUYA POWERPLANT Revision
COMISSIONING CHECKLIST Revision Date
Control No.

Preliminaries:
1. Open Tie CB
2. Open all MVSG
3. Synchronize G1 and G2

Configure the trip setting of the trip


unit of Feeder 1 as per the conducted
coordination study.
6. Energization of Feeder 1 and  Passed
The transformer will be energized upon
Transformer 1  Failed
closing the feeder 1 circuit breaker.
Check phase sequence on the Feeder 1
going to Transformer. The phase
sequence be equal to the phase
sequence of the generators.

NOTE: Test the switching (3) three


times to ensure that inrush current will
not cause nuisance tripping.

Upon energization of the transformer,


verify the voltage reading of the digital
power meter on the MVSG 1. The
voltage reading must be approximately
equal to the high side of the
7. Validation of the voltage reading in  Passed
transformer which is 13.8 kV.
MVSG 1 Digital Power Meter  Failed
NOTE: Make sure that the CT and PT
ratio of the Digital Power Meter are
equal on the actual installed
instrument transformer nameplate.

Configure the setting of the


8. Configuration of REF601 Protection  Passed
overcurrent protection relay based on
Relay for MVSG 1 and 2  Failed
the coordination study.

Preliminaries:
1. Close Feeder 1
2. Open Tie CB
3. Open MVSG 2
4. Open LBS 1 and LBS 2
 Passed
9. Energization of the MVSG 1 5. Open Disconnect Switch
 Failed
Close the VCB of the MVSG 1. Check the
protection relay if no unwanted alarms
and check the parameters of the digital
power meter.
Form CETI-CC-MMXVIII
`
NEW CALUYA POWERPLANT Revision
COMISSIONING CHECKLIST Revision Date
Control No.

Preliminaries:
1. Open Tie CB
2. Close MVSG 1
3. Synchronize G1 and G2

10. Energization of the MVSG 1 and Close the feeder 1 circuit breaker while  Passed
Transformer 1 the VCB of the MVSG 1 is closed.  Failed

NOTE: Test the switching of FCB 1 (3)


three times to ensure that inrush
current will not cause nuisance tripping
to the MVSG.
Preliminaries:
1. Open Disconnect Switch
2. Open MVSG 2  Passed
11. Closing of Load Break Switches
 Failed
Close the load break switch 1 and 2.
Observe the switching if normal.
Preliminaries:
1. Open Disconnect Switch
2. Open Feeder 2

Close the VCB of the MVSG 2, this will


energized the Transformer 2 from the  Passed
12. Energization of the MVSG 2
high voltage side. Use the phase  Failed
sequence on the low voltage side of the
transformer. The phase sequence must
be the same with the Transformer 1
low voltage side and generators as
done in item #3 and #6.

Preliminaries:
1. Open Disconnect Switch
2. Open Feeder 2

Close the VCB of MVSG 2. Observe the


13. Energization of MVSG 2 and switching if normal and no alarms  Passed
Transformer 2 indicated on the protection relay.  Failed

NOTE: Test the switching of VCB (3)


three times to ensure that inrush
current will not cause nuisance tripping
to the MVSG 2.
Form CETI-CC-MMXVIII
`
NEW CALUYA POWERPLANT Revision
COMISSIONING CHECKLIST Revision Date
Control No.

Upon energization of the transformer,


verify the voltage reading of the digital
power meter on the MVSG 2. The
voltage reading must be approximately
equal to the high side of the
14. Validation of the voltage reading  Passed
transformer which is 13.8 kV.
in MVSG 1 Digital Power Meter  Failed
NOTE: Make sure that the CT and PT
ratio of the Digital Power Meter are
equal on the actual installed
instrument transformer nameplate.

Close the Tie CB and Feeder circuit


15. Synchronization of 4 Generators  Passed
breaker 2. Start the synchronization of
and energization of T1 and T2  Failed
G3 and G4 to G1 and G2.
Preliminaries:
1. Open the Fuse going to MDP

Close the disconnect switch. Measure


16. Energization of the Revenue  Passed
the secondary voltage going to the
Meter  Failed
revenue meter before closing the
control fuses to energize the revenue
meter. Check voltage reading of the
revenue meter.

Close the Fuse going to the service


transformer to be energized. Check the
voltage on the low voltage side of the
transformer and it must be
17. Energization of the Service approximately equal to the indicated  Passed
Transformer voltage on the transformer nameplate.  Failed
Use phase sequence tester to check the
phase sequence on the low voltage
side of the transformer and it must be
equal to result on item #3, #6 and #12.
Upon energization of the transformer,
close the control fuses to energize the
digital power meter on the MDP. Verify
the voltage reading, it must be
18. Validation of the voltage reading  Passed
approximately equal to the 220V.
in MDP Digital Power Meter  Failed
NOTE: Make sure that the rated
voltage is based on the low voltage
output of the installed transformer.
Upon verification of the voltage, close
19. Energization of the Main  Passed
the main breaker of the MDP and close
Distribution Panel  Failed
its branches to start loading.
Form CETI-CC-MMXVIII
`
NEW CALUYA POWERPLANT Revision
COMISSIONING CHECKLIST Revision Date
Control No.

Monitor the load and record all


parameters of the digital power meters
20. Validation of all metering  Passed
and controllers especially power and
parameters  Failed
current. Verify accuracy of the readings
especially on the Revenue Meter.

OVERALL EVALUATION REMARKS


 Approved
 Disapproved
 For Revision

The above mentioned checklist are conducted and the result are accepted by all parties involved during the testing.
The signatures of the below specimen certify that this document is true and correct.

Date Company
Position

________________________ _______________ ___________________________


_________________________
Signature over Printed Name

________________________ _______________ ___________________________


_________________________
Signature over Printed Name

________________________ _______________ ___________________________


_________________________
Signature over Printed Name

________________________ _______________ ___________________________


_________________________
Signature over Printed Name