Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
`
NEW CALUYA POWERPLANT Revision
COMISSIONING CHECKLIST Revision Date
Control No.
CLIENT DETAILS
Client Marcbilt Construction Inc. Date March 28, 2019
Address Caluya Island, Antique Sales Order No. SO2018-002
Passed
Easygen is in Auto Mode. The setpoint Failed
will adjust automatically by the
1.4. Generator Automatic
controller and the frequency bias must Gen 1
Frequency Control
be approximately 50% during no load Gen 2
operation. Gen 3
Gen 4
2. Validation of Parameter Readings
Passed
Generator voltage must be reflected Failed
on both Easygen and Digital Power
2.1. Generator Line-Line Voltage Meter and the reading must be Gen 1
approximately equal to the generator Gen 2
rated voltage. Gen 3
Gen 4
Form CETI-CC-MMXVIII
`
NEW CALUYA POWERPLANT Revision
COMISSIONING CHECKLIST Revision Date
Control No.
Passed
Easygen generator current
Failed
measurement configuration must be
2.2. Generator Current equal to the rated generator current.
Gen 1
The CT Ratio of the digital power meter
Gen 2
setting must be equal to the actual
Gen 3
installed current transformer.
Gen 4
Passed
Failed
Other parameter readings must reflect
2.2. Other Generator Parameter on Easygen and digital power meter
Gen 1
readings and must be approximately equal to
Gen 2
the actual parameter of Generator
Gen 3
Gen 4
Check the phase sequence of all
generators using phase sequence Passed
3. Phase sequence of Generators
tester. They must all have the same Failed
phase sequence.
Preliminaries:
1. Open all Feeder breakers
2. Close the Tie breaker
Preliminaries:
1. Open Tie CB
2. Open all MVSG
3. Synchronize G1 and G2
Preliminaries:
1. Close Feeder 1
2. Open Tie CB
3. Open MVSG 2
4. Open LBS 1 and LBS 2
Passed
9. Energization of the MVSG 1 5. Open Disconnect Switch
Failed
Close the VCB of the MVSG 1. Check the
protection relay if no unwanted alarms
and check the parameters of the digital
power meter.
Form CETI-CC-MMXVIII
`
NEW CALUYA POWERPLANT Revision
COMISSIONING CHECKLIST Revision Date
Control No.
Preliminaries:
1. Open Tie CB
2. Close MVSG 1
3. Synchronize G1 and G2
10. Energization of the MVSG 1 and Close the feeder 1 circuit breaker while Passed
Transformer 1 the VCB of the MVSG 1 is closed. Failed
Preliminaries:
1. Open Disconnect Switch
2. Open Feeder 2
The above mentioned checklist are conducted and the result are accepted by all parties involved during the testing.
The signatures of the below specimen certify that this document is true and correct.
Date Company
Position