Sei sulla pagina 1di 113

Microgrid Design

Considerations

Dr. Arindam Maitra, EPRI


September 8, 2016

Part 3 of 3 © 2015 Electric Power Research Institute, Inc. All rights reserved.
Outline – Microgrid Design and Analysis Tutorial
Part II

Time Topics
14:30-15:00 Design analysis
• Needs and Key Interconnection Issues (Arindam Maitra)
15:30-17:30
Design analysis (cont.)
• Methods and Tools
• Case Studies
 #1: Renewable Rich Microgrids - Protection Case Studies
(Mohamed El Khatib)
 #2: Rural radial
 #3: Secondary n/w
17:00-17:30 Q&A
17:30 Adjourn

2
© 2015 Electric Power Research Institute, Inc. All rights reserved.
Microgrids

 Optimization of microgrid design is challenging and


inherently contains many unknowns…

Regulatory Issues
Value of Resiliency

System Design
Challenges
Engineering Studies

Costs

3
© 2015 Electric Power Research Institute, Inc. All rights reserved.
Integrating Customer DER with Utility Assets

Customer Utility Assets


Assets

Micro Grid
Controller SCADA/DMS/
/ DERMS* Enterprise

Integrate
Energy Storage*
d Grid

Isolating Device*

Distribution
Transformer
*New assets

4
© 2015 Electric Power Research Institute, Inc. All rights reserved.
Microgrid Types
 Commercial/Industrial Microgrids: Built with the goal of reducing demand and costs
during normal operation, although the operation of critical functions during outages is
also important, especially for data centers.

 Community/City/Utility and Network Microgrids: Improve reliability of critical


infrastructure, deferred asset investment, emission and energy policy targets and also
promote community participation.

 University Campus Microgrids: Meet the high reliability needs for research labs,
campus housing, large heating and cooling demands at large cost reduction
opportunities, and lower emission targets. Most campuses already have DG resources,
with microgrid technology linking them together. They are usually large and may be
involved with selling excess power to the grid. Some of these facilities typically serve
as emergency shelters for surrounding communities during extreme events

 Public Institutional Microgrids: Improve reliability and lower energy consumptions at


facilities impacting public health and safety, including hospitals, police and fire stations,
sewage treatment plants, schools, public transport systems, and correctional facilities.
Additional requirement of uninterrupted electrical and thermal service increases
attractiveness of CHP-based district energy solutions
5
© 2015 Electric Power Research Institute, Inc. All rights reserved.
Microgrid Types
 Military Microgrids: Military microgrids focus on high reliability for mission-critical loads,
strong needs for cyber and physical security, DoD energy cost reduction, and
greenhouse gas emission reduction goals at the operating bases.

 Rural Microgrid Communities: Remote microgrid communities are typically connected


to rural distribution system where it is prohibitive due to the distance or a physical
barrier to bring in new transmission service for backup. Many already use diesel
generation. They microgrids offer best candidate to incorporate renewable energy,
improve system reliability targets, and defer investment and reduce supply chain risk.

6
© 2015 Electric Power Research Institute, Inc. All rights reserved.
Microgrid Configurations Depending on Location and Purpose

7
© 2015 Electric Power Research Institute, Inc. All rights reserved.
Micro-grid: Operating as an “Island” Isolated from the
Bulk Supply
Circuit Breaker Isolating Device
– when open the system
operates as micro-grid
“Islanded” Facility
Utility
Source Trip
Signal

Islanding Control
(opens/closes breaker as needed to
facilitate independent operation –
must provide synchronization)

Electrical Island
DG
DG Able to Carry Load on
Island and Provide Proper
Voltage and Frequency

8
© 2015 Electric Power Research Institute, Inc. All rights reserved.
“Islanding” for Reliability Enhancement

“Islanded” campus area


during utility system outages

Building
Load

13.2 kV Feeder
Building
Load
Utility Substation

Building
Load
Utility System
Interface Breaker

D D Building Building
G G Load Load

DG trip settings for DG coordinated to allow


utility system interface breaker to trip during
utility faults so that stable transition to
islanded state is achieved for the campus
without interruption of DG service
9
© 2015 Electric Power Research Institute, Inc. All rights reserved.
A Six Home Microgrid

House 1 House 2 House 3


Distribution
Transformer
Isolating Power System
Device Secondary
Utility System (120/240 V)
Primary (13.2 kV)

Utility System 50 KVA House 4 House 5 House 6


Interface & Inverter
Controller
(Synchronization, fault
protection, islanding DC Bus
detection, etc.)
Fuel
Cell Charge
Regulator

Thermal Energy
Storage
Storage Heat
Distribution

10
© 2015 Electric Power Research Institute, Inc. All rights reserved.
A Single Building
Multiple Sources, Storage, and Heat Recovery

Serves as Isolation Point


Utility System Interface
& Protection Control for Micro-grid mode of AC Bus
operation Building
Utility
Source Electrical
Circuit Loads
Breaker
Circuit Status/control
20 kW Breaker signals paths to/from
Wind electrical loads
Energy Master
Source System
INVERTER Controller Status/control signal
Rectification paths to/from thermal
and Filtering loads
DC Bus

Charge/Discharge
Regulator
Building
Heat
Energy 200 kW Recovery Thermal
Storage Fuel Cell Loads

11
© 2015 Electric Power Research Institute, Inc. All rights reserved.
A Campus Microgrid System

Dormitory A Dormitory B Administrative


Isolating Device (opens
during micro-grid mode) Building
Campus Owned
500 kVA 500 kVA 300 kVA Distribution (13.2 kV)
Utility System
Primary Connection
(13.2 kV)

Utility System To Other 75 kVA


Voltage
Interface Control Campus
Regulator
Generator
(Synchronization, fault
Step Up Loads
protection, islanding detection,
Student Academic
etc.) Transformer Heat Distribution Union Building B
Paralleling Bus (4.8 kV)
Communication & Control Signal Path
Generator
Protection 1.75 1.75 1.75 Academic Building A
MVA 300
and Control MVA MVA
800 kVA kVA
Gen Gen Gen
Load
control

Heat Recovered Heat Distribution


from ICE Units
12
© 2015 Electric Power Research Institute, Inc. All rights reserved.
Microgrid Design Parameters

Urban Rural Non-Utility Remote /


Utility Utility Microgrids Island
 Number of customers served Microgrids Microgrids Microgrids

 Physical length of circuits and types Commercial /


Industrial Clusters
Remote
Planned Communities
of loads to be served Application
Downtown Islanding
University Campus
and Loads
Areas

 Voltage levels to be used Load Support


Residential
Development
Geographical
Islands

 Feeder configuration (looped, Improved Reliability;


Reliability and
Power Quality Electrification of
networked, radial) Main Drivers Outage Management;
Enhancement; Remote Areas
Renewable and CHP Integration
Energy Efficiency;

 Types of distributed energy


Improved Reliability;
resources utilized Fuel Diversity;
Premium Power
Quality;
Supply
Availability
Congestion Management;
Benefits CHP Integration;
Greenhouse Gas Reduction;
 AC or DC microgrid Upgrade Deferral;
Demand Response
Management
Integration of
Renewables
Ancillary Services

 Heat-recovery options Grid- Primary Mode of


Primary Mode of Operation Never
Connected Operation
 Desired power quality and reliability
Nearby faults or
levels System Disturbances
Nearby faults or System
Intentional Disturbances
 Methods of control and protection Islanding
Approaching Storms
Times of Peak
Energy Prices
Always Islanded

 Controllers Approaching Storms

Source: Johan Driesen and Farid Katiraei, “Design for Distributed Energy Resources,” IEEE Power & Energy Magazine,
May/June 2008

13
© 2015 Electric Power Research Institute, Inc. All rights reserved.
Microgrid Design Elements

• Are the fault contributions from • Are DERs able to regulate the voltage and
DERs sufficient to allow frequency within the island?
satisfactory operation of • Any issues with parallel grid operation?
protection systems? • How is re-synchronization checked
• Are existing protection schemes against criteria such as out-of-phase, large
adequate? change in voltage?

Microgrids

Need a microgrid controller

Plan, design, operate, control, monitor and optimize seamlessly


14
© 2015 Electric Power Research Institute, Inc. All rights reserved.
Microgrid Detailed Technical Design
Site Descriptions

Microgrid Project Objectives

Design Basis and Rationale

Performance Criteria
• Electrical & Thermal Needs
• Generation Assets
• Critical Load Needs
• Power Distribution Equip.

DER & Microgrid Controller


Control Needs
Communication Needs
Codes & Standards
15
© 2015 Electric Power Research Institute, Inc. All rights reserved.
DER Characterization
Renewables Fossil Fuels Tech
▪ Solar Photovoltaics ▪ Boiler Electric Storage
▪ Solar Thermal ▪ Fuel Cell
• Aggregate capacity of all units (kwh)
Microturbine
▪ Wind Solar
▪ Microturbine Photovoltaics
• Maximum charge rate
• Max Power (kW) • #Genset
▪ NG of modules
(fraction of total capacity charge in one hour)
• Sprint capacity (% of power) • Module
▪ Diesel Electric Vehicles
rating (kW DC)
(backup)

Maximum discharge rate
• # of sprint hours (hours) • Module •Size Multiple
(m2) locations
(fraction of total capacity discharge per hour)
• Fuel type • Efficiency • (%)
Min connect/disconnect SOC
Energy Storage Thermal
• Minimum stateTech
of charge
• Efficiency (ratio) • Inverter•size Max(kW charge
AC) hours
▪ Electrical (Power, Energy) • Charge
▪ Heat Pumpefficiency
• CHP capable? (yes/no) • Total land • area
Battery
(m2) size
▪ Thermal (Chiller, Refrig.) ▪ CHP
• Discharge efficiency
• Alpha (power to heat ratio) • Efficiency
----------------------------------
▪ HVACR
• Decay/self-discharge (fraction of total capacity per
• NOx emissions rate (kg/hr) • Capital •costDecay
($)
▪ Solar hour)
Thermal
• Maximum annual operating hours (hours) Lifetime• (years)
• ----------------------------------
etc.
• Minimum loading (% of power) • • O&M
Fixedfixed
costcosts
($) ($/year) SOC
---------------------------------- • • O&M variable
Variable Costcosts
($/kw($/year/kW)
or $/kwh)
• Capital cost ($) Other
• Lifetime (years)
• Lifetime (years) ▪ Electric Vehicles Disconnect
• O&M fixed costs ($/year)
Connect
• O&M fixed costs ($/year)
• O&M variable costs ($/year/unit)
• NOx treatment costs ($/kg)
t

16
© 2015 Electric Power Research Institute, Inc. All rights reserved.
Variable Distributed Energy Assets within Microgrid

Source: PNNL
17
© 2015 Electric Power Research Institute, Inc. All rights reserved.
Key Considerations in Design for Energy Storage

 Standby Power Loss


– Storage is primarily needed
when the microgrid is islanded
– Standby power loss will reduce
the efficiency of the microgrid

• Response time
– For seamless transition, response
time must be very fast
– This is more than just battery
response time – communications
latency and control functions also
play a role

18
© 2015 Electric Power Research Institute, Inc. All rights reserved.
Isochronous / Droop Modes of Operation
 Isochronous - Isochronous control
mode means that the frequency (and
voltage) of the electricity generated is
held constant, and there is zero
generator droop.
 Droop Control Mode - strategy
commonly applied to generators for
frequency control (and occasionally
voltage control) to allow parallel
generator operation (e.g. load sharing).
 For grid-tied microgrids – all the DG
and storage resources operate in
droop mode and the utility is the
isochronous generator reference.
 For off-grid microgrids – one
generating unit is designated to run in
isochronous mode and all other follow
in droop mode. Larger units and
higher inertia prime movers are
normally the reference machine. PV
inverters are nearly always operating in
droop mode. Battery inverters may
operate either way when generating.
19
© 2015 Electric Power Research Institute, Inc. All rights reserved.
Controller Integration

20
Source: EPRI DOE SHINES Project © 2015 Electric Power Research Institute, Inc. All rights reserved.
Microgrid Technical Challenges : Protection

 Not enough short-circuit current in Microgrid mode for


protection to sense and operate
– Voltage-based protection was recommended : No
need for multiple settings group to support grid or
islanded operation
 May require additional equipment and change in
protection settings.
 Insulation coordination could be an issue
 Microgrid operation may result in loss of effective ground
reference

Keeping protection scheme simple translates into improved


dependability as well as much simpler analysis in the event of
misoperation
21
© 2015 Electric Power Research Institute, Inc. All rights reserved.
For a small microgrid: need to understand the load
Daily, from hourly to cycles in single family residence Knoxville, TN

8.0 kWmax 10.7 kWmax


85.1 kWh 85.1 kWh

44% Load factor 33%

14.8 kWmax 26.2 kWmax


85.1 kWh 85.1 kWh

24% 14%

22
© 2015 Electric Power Research Institute, Inc. All rights reserved.
PQ Enhancements Possible

Instant Islanding to mitigate campus


interruptions caused by feeder faults
Proactive islanding due to “expected” feeder
interruption or voltage sag (e.g. approaching
lightning storm)
Partial voltage sag mitigation by means of DG
voltage support during fault!
Improved local voltage flicker and regulation
due to lower impedance of power system

23
© 2015 Electric Power Research Institute, Inc. All rights reserved.
Low Voltage Ride-Through
 No low voltage ride-through requirements in the current IEEE
Std1547-2003 version (or the amendments)
 A full revision of the 1547 is under way – inclusion of ride-through
requirements is considered
 The CA Rule 21 ride-through requirements will likely inform the IEEE
Std 1547 ride-through requirements

The inverter must stop


producing power but be ready
to produce power again if the
voltage starts to normalize
before the inverter is allowed
to
24
trip © 2015 Electric Power Research Institute, Inc. All rights reserved.
Dynamic Models and Controls

25
© 2015 Electric Power Research Institute, Inc. All rights reserved.
Micro-Grid Switching - MV vs LV

From Utility
From Utility
Typical Main Switch 12 kV
Typical Main Switch 12 kV
MV-CB
MV-CB

Point Of
Control

12 kV JC
Jn. Box 12 kV

Service 12 kV/
Service 12 kV/ Xfmr 208V
Xfmr 208V

LV-CB LV-CB
Point Of
Control
Building Building Building
Load Load PV

26
© 2015 Electric Power Research Institute, Inc. All rights reserved.
Micro-Grid Switching at MV Level
From Utility Approach:
Typical Main Switch 12 kV  Circuit breakers are available only at 12kV main
ring. No 12kV circuit breakers downstream.
MV-CB
 Each circuit breaker controls a group of
Point Of transformers/buildings.
Control
 Control is at the group level. No individual
Jn. Box 12 kV control at building level
Consequences:
 Switching OFF a transformer on 12kV side
disconnects both building loads and connected
PV. This results in loss of generation (PV on non
critical buildings) when resources are needed
Service 12 kV/ during islanded operation.
Xfmr 208V
 This design necessitates permanently assigning
buildings as critical and non-critical. It is not
possible to reassign them later.
Building  12KV switching could cause high transformer
Load
inrush currents during black start. Mitigating
equipment may be required if storage inverters
are not able to handle this high inrush current.

27
© 2015 Electric Power Research Institute, Inc. All rights reserved.
Micro-Grid Switching at LV
From Utility
Approach:
Typical Main Switch 12 kV  Control is shifted to the Low Voltage side.
MV-CB
 Transformers are connected to buildings through
Low Voltage distribution boards.
 This creates the ability to separately control loads
JC and generation within the buildings.
12 kV
Consequences:
 No loss of generation (PV on non critical
buildings) when loads are disconnected during
islanded operation.
Service 12 kV/
Xfmr 208V  Ability to reassign buildings as critical / non-
critical as and when needed.
LV-CB LV-CB
 As loads are disconnected from the LV side it is
Point Of
Control possible to reestablish the MV ring through soft
Building Building start with all transformers connected. This could
Load PV
reduce inrush current significantly.

28
© 2015 Electric Power Research Institute, Inc. All rights reserved.
Transformer inrush current and its impact

 Inrush current during the energizing could be much higher than


the full rated current. It is short lived – a few cycles only.
 Inrush currents can be as high as 6 and 18 times the rated
current. Magnitude of inrush current depends on several factors –
e.g.
– Primary voltage
– Transformer saturation curve
– Short circuit capacity of the network – lower the short circuit level, lower
the inrush current
 Impact
– Inrush currents are reactive and can cause voltage drops
– Inrush currents do not normally pose any challenge in grid connected
mode as rotary generators are designed to handle these high currents
– However inverters are not designed to carry these. Typically they can
handle up to 2 to 3 times their rated current but not more.
29
© 2015 Electric Power Research Institute, Inc. All rights reserved.
Transformer Energizing: Equivalent Circuit

The short-circuit strength of the circuit determines the


magnitude of the inrush current during transformer energizing.

In differential equation: 𝜕l(𝑖, 𝑡) 𝜕𝑖(𝑡)


𝑣𝑠 𝑡 = 𝑍𝑠 𝑖 𝑡 + 𝑋𝑙𝑘 𝑖 𝑡 +
𝜕𝑖(𝑡) 𝜕𝑡
l(𝑖, 𝑡) = the total magnetic flux linkage
𝑖 𝑡 = inrush current when energized

In a strong system, 𝑍𝑠 is small. The inrush current 𝑖 𝑡 will be larger.


In a weak system, 𝑍𝑠 is large. The inrush current 𝑖 𝑡 will be smaller.

30
© 2015 Electric Power Research Institute, Inc. All rights reserved.
Transformer Core Saturation Characteristics: I-V

31
© 2015 Electric Power Research Institute, Inc. All rights reserved.
Transformer Energizing: Full-Voltage Energizing
With a Typical Saturation Curve
 Transformer is unloaded energized at bus full voltage. Short-
circuit strength is x
 1.5 MVA, 12.47 kV/480V, 5.07%
Short-circuit capacity at 12.47 kV bus = 300 MVA
(for now - Ygnd Ygnd)
Short-circuit capacity at 12.47 kV bus = 30 MVA
 Rated transformer
4.6x
current = 70 Arms = 98 Apk
3.5x

32
© 2015 Electric Power Research Institute, Inc. All rights reserved.
Transformer Energizing: Full-Voltage Energizing
With a Very Flat Saturation Curve
 Transformer is unloaded energized at bus full voltage.
 1.5 MVA, 12.47 kV/480V, 5.07% (for now - Ygnd Ygnd)
 Ratedcapacity
Short-circuit transformer current
at 12.47 kV bus = 300 MVA= 70 Short-circuit
Arms =capacity98 Apk
at 12.47 kV bus = 30 MVA

20x

9x

33
© 2015 Electric Power Research Institute, Inc. All rights reserved.
Design Analysis Load Analysis

unacceptable

voltage
overvoltage

DER Sizing & Design Microgrid Controller


limits Architecture & Design

Load Only time 


Watts

Load and PV
Design Analysis
Impedance  Approach

Location √
no impact • Steady State load flow Relay
desensitization
• System Dynamic

Current
unserved energy

• Harmonics
Energy

case by case
Energy exceeding
normal
look needed
• Flicker
Time 

Location X
• Controls
Potential risk
• Operation seq. Impedance 

Distribution System Modeling, • Fault Current


Simulation & Optimization • Black Start Protection & Reliability

34
© 2015 Electric Power Research Institute, Inc. All rights reserved.
Microgrid Design Analysis

Commissioning
Data Collection Modeling Impact Studies
& Operation

o Network models o Scenarios o Steady state o Model validation


• Load types o Model validation o Fault analysis o Real time ops &
• DER types
o Grid impact o Protection monitoring
• Operation
o Stability studies
o Protection info

35
© 2015 Electric Power Research Institute, Inc. All rights reserved.
Key interests

Load flow

• Is the micro grid gen(s) is enough to support the islanded load?


• Verify compliance to planning & voltage stability requirements

Protection analysis

• Is existing protection adequate?


• If not, try various options

Dynamic studies

• Events (loss of large load, load step & fault clearing capabilities)
• Fault Ride Through capabilities of various inverter-based DERs
36
© 2015 Electric Power Research Institute, Inc. All rights reserved.
Detailed Design Analysis – Tools
Source: LBNL Paper LBNL-6708E

A variety of MC capabilities
requires a variety of models to
understand
• Performance
• Grid interaction
• System Protection Scheme
Impact
OpenDSS/Grid Lab D/DEW

PSCAD/EMTP-RV/MATLAB DesignBase

DIGSILENT
All
PSS/SINCAL

CYMDIST
Need to apply a consistent modeling
SynerGEE
framework
Allow existing models to feed new analysis Transient Dynamic
Time-Series
Analysis/Slow
Time-Series
Analysis/SS Steady State
Dynamics Steps

Microseconds Milliseconds Seconds Minutes Hours Days

37
© 2015 Electric Power Research Institute, Inc. All rights reserved.
Available Tools
Software Tool Affiliated Org. Tool Type
CYMDIST CYME International T&D Inc. Planning and simulation of distribution networks,
including load flow, short-circuit, and network
optimization analysis.
DER-CAM Lawrence Berkeley National Techno-economic tool for microgrid design and
Laboratory (LBNL) operation.
DesignBase Power Analytics Broad platform for electrical system design, simulation,
and optimization.
EMTP-RV POWERSYS Solutions Power system transients simulation, load flow,
harmonics.
EUROSTAG Tractebel Engineering GDF Power system dynamics simulation; full range of
Suez transient, mid- and long-term stability; steady-state
load flow computation.
GridLAB-D Pacific Northwest National Distribution system simulation and analysis.
Laboratory (PNNL)
HOMER Homer Energy LLC, National Techno-economic tool for microgrid design and
Renewable Energy operation.
Laboratory (NREL)
OpenDSS Electric Power Research Distribution system simulation and analysis.
Institute (EPRI)
PowerFactory DIgSILENT GmbH Power system analysis tool for load flow and
harmonics in transmission, distribution, and industrial
networks.
PSCAD Manitoba HVDC Research Power system transient simulation, load flow
Center simulation.
PSS/E Siemens Power Technologies Load flow, dynamic analysis, and harmonic analysis of
International (Siemens PTI) utility and industrial networks.
38
© 2015 Electric Power Research Institute, Inc. All rights reserved.
Simulation Tools - Comparison

Study Power
Power Flow, Short Relay Arc Harmonic Transient Dynamic Quasi Steady-
Flow,
unbalanced Circuit Coordination Flash Analysis Analysis Analysis State Analysis
Tool balanced

EMTP-RV,
Simulink,
PSCAD

Aspen, Cape

DesignBase,
PowerFactory

PSLF, PSS/E

OpenDSS

GridLAB-D

Best choice

Can be done, but not preferred choice

Cannot be done

39
© 2015 Electric Power Research Institute, Inc. All rights reserved.
Case # 1:Protection Case Studies
(Mohamed El Khatib)

Renewable Based Microgrids

40
© 2015 Electric Power Research Institute, Inc. All rights reserved.
Case # 2: Rural Radial Community
(Arindam Maitra)

41
© 2015 Electric Power Research Institute, Inc. All rights reserved.
Case Study: Two Remote Rural Communities

3.25MW of Load
6.5MW of DG

42
© 2015 Electric Power Research Institute, Inc. All rights reserved.
One-line diagram of the 34.5-kV
R55 R173
Existing 34.5 KV Existing
Recloser Recloser 34.5 KV

Plant Load: 5MW


4.8 KV

Plant Load: 1MW

Plant Load: 1.8MW

Wind plant : 6.6 MW

Sync DG:
0.416 MW

Wind Turbine: Type 2 induction generator with rotor resistor control.


This type of turbine needs a stiff transmission grid and a strong synchronous source for stable
operation and can introduce oscillations if it remains connected during islanded operation.
They require external reactive support to maintain voltage, which is typically provided by static
or/and dynamic compensation

43
© 2015 Electric Power Research Institute, Inc. All rights reserved.
Case Study: Reliability Assessments In Rural Areas of
New York
Fault Exposure Scenario #1

 Electricity customers in rural areas Proposed


Existing 34.5 KV Proposed Existing
of NY have been experiencing Reclosure Reclosure Reclosure 34.5 KV Reclosure

power outages lasting 10 hours &


longer, which far exceeds the Plant Load: 5MW

Customer Average Interruption 4.8 KV


Proposed

Duration Index (CAIDI) targets Plant Load: 1MW


Proposed
PQ Meter
2 MWHR Energy
Storage
Plant Load: 1.8MW

Proposed
1 MWHR Energy
Storage Wind plant : 6.6 MW

 Average statewide CAIDI target is Sync DG:


0.416 MW
Microgrid 1

~ 2 hours
Fault Exposure Scenario #2

Proposed
Existing 34.5 KV Proposed Existing
34.5 KV Reclosure
Reclosure Reclosure Reclosure

 This problem is due, in part, to the


fact that many remote areas of Plant Load: 5MW
4.8 KV
New York State are fed radially Proposed
PQ Meter
Proposed
2 MWHR Energy
Plant Load: 1MW Storage
and have only a single Plant Load: 1.8MW

transmission or sub-transmission Proposed


1 MWHR Energy
Storage Wind plant : 6.6 MW
supply line that feeds these areas
Sync DG:
Microgrid 2
0.416 MW

44
© 2015 Electric Power Research Institute, Inc. All rights reserved.
Design Study

 Rural electrification in areas with otherwise poor reliability is the key


driver to evaluate microgrid as a possible solution

– Many remote communities are situated in locations without a backup


transmission or sub-transmission connection

– Restoration time is quite high

– Microgrids can play a role in reducing fault investigation time, shorter


outage duration and lower costs for first responders

– Operating remote communities as a microgrid


 Complete transition from grid-connected operation to micro-grid operation
within 15 minutes following the loss of the supply line
 Supply at least 50% of the customers in the Wethersfield and 50%
customers in Orangeville area for at least (8) hrs

45
© 2015 Electric Power Research Institute, Inc. All rights reserved.
Case Study: Focus Areas

−Define the Modes of Operations – Based on a permanent fault location


on 34.5 kV supply line and system protection requirements, different microgrid
scenarios are identified. Additional equipment or changes in the circuit
configuration to facilitate stable operation of the microgrids is proposed

−System Protection Study – Identify the required enhancements to


protections system for the area under study during microgrid conditions.

− A high-level protection system design (relay types, communication needs, etc.) that
are needed to accommodate normal and microgrid operation

−Fault Location Study – Develop improved fault locating algorithms for a


utility-supplied distribution circuit

− Emphasis was on 34.5 kV line and underlying 4.8 kV system as well to evaluate the
possible local microgrid effects at the 4.8 kV side.

− Develop improved fault locating algorithms in PSCAD

46
© 2015 Electric Power Research Institute, Inc. All rights reserved.
Possible Microgrid Configurations

 Microgrid “OW”: both circuits


operate as a unified microgrid

 Microgrid “W”: Circuit operates as


a standalone microgrid

 Microgrid “O”: Circuit operates as


a standalone microgrid

47
© 2015 Electric Power Research Institute, Inc. All rights reserved.
Technical Limitations with Current Protection

Fault Condition # 1:
– Grid Connected Mode: Fault Exposure Scenario #1

 For a permanent fault between Existing 34.5 KV Proposed Existing


Proposed
Reclosure
Reclosure Reclosure Reclosure 34.5 KV
Attica and Orangeville, recloser
R55 will open. Since R55 is the
only upstream recloser both Plant Load: 5MW
4.8 KV
circuits with be out of service Proposed
PQ Meter
Proposed
2 MWHR Energy
Storage
Plant Load: 1MW

 Need for local generation


Plant Load: 1.8MW

Proposed

 Important to isolate the fault


1 MWHR Energy
Storage Wind plant : 6.6 MW

Sync DG:
Microgrid 1
0.416 MW

– EPRI proposes a new recloser


at Exchange St Rd P122. This
will allow Orangeville and
Wethersfield to be served as
microgrid (“OW”) with energy
storage while the fault is being
cleared
48
© 2015 Electric Power Research Institute, Inc. All rights reserved.
Technical Limitations with Current Protection System
(cont.)

Fault Condition # 2: Fault Exposure Scenario #2

– Grid Connected Mode:


Proposed
Existing 34.5 KV Proposed Existing
34.5 KV Reclosure
Reclosure Reclosure Reclosure

 Permanent fault between


recloser R173 and Plant Load: 5MW

Wethersfield, recloser R173 4.8 KV


Proposed
will open to save Wetherfield Plant Load: 1MW
Proposed
PQ Meter
2 MWHR Energy
Storage
Plant Load: 1.8MW

 Isolate the 4.8KV system in Proposed


Wethersfield to prevent back 1 MWHR Energy
Storage Wind plant : 6.6 MW
feed from Wind farm (& Microgrid W
Energy storage system Sync DG:
0.416 MW
proposed as part of the
microgrid mode)
 In this scenario, Orangeville
and Boxler plant remain
connected to the Attica
substation in “grid-tie” mode.
– EPRI proposes a new recloser
at J197/J199. Wethersfield will
operate as a standalone
microgrid (“W”)
49
© 2015 Electric Power Research Institute, Inc. All rights reserved.
Attica 34.5kV R122 (new)
Orangeville Tap
R55

1 3
1
Wind Farm

R173 (Form 6)
New relay
3 - set of 3 wye-gnd
2.5MVA
connected VTs
34.5kV:4.8kV

X 1 – single VT

Wethersfield
storage R199 (new)
1
battery 1
500kVA 3

Beckwith M-3410A Y
Boxler Farm storage
battery 2

50
© 2015 Electric Power Research Institute, Inc. All rights reserved.
Permanent fault occurs here

Orangeville Tap

X Wind Farm
R55 R122 R173

X
Wethersfield

R199
500kVA

open
closed
Y
in reclosing
cycle Boxler Farm
Scenario - permanent fault between R55 and R12
51
© 2015 Electric Power Research Institute, Inc. All rights reserved.
• X and Y opened by 34.5kV voltage protection before first reclose of R55
• R55 in reclosing cycle

Orangeville Tap

X Wind Farm
R55 R122 R173

X
Wethersfield

R199
500kVA

open
closed
Y
in reclosing Boxler Farm
cycle Scenario - permanent fault between R55 and R12
52
© 2015 Electric Power Research Institute, Inc. All rights reserved.
• R55 locks out

Orangeville Tap

X Wind Farm
R55 R122 R173

X
Wethersfield

R199
500kVA

open
closed
Y
in reclosing Boxler Farm
cycle Scenario - permanent fault between R55 and R12
53
© 2015 Electric Power Research Institute, Inc. All rights reserved.
• R122, R173, and R199 open

Orangeville Tap

X Wind Farm
R55 R122 R173

X
Wethersfield

R199
500kVA

open
closed
Y
in reclosing Boxler Farm
cycle Scenario - permanent fault between R55 and R12
54
© 2015 Electric Power Research Institute, Inc. All rights reserved.
• Both battery systems come back online and close X & Y

Orangeville Tap

X Wind Farm
R55 R122 R173

X
Wethersfield

R199
500kVA

open
closed
Y
in reclosing Boxler Farm
cycle Scenario - permanent fault between R55 and R12
55
© 2015 Electric Power Research Institute, Inc. All rights reserved.
• R199 will close using hot bus – dead line

Orangeville Tap

X Wind Farm
R55 R122 R173

X
Wethersfield

R199
500kVA

open
closed
Y
in reclosing Boxler Farm
cycle Scenario - permanent fault between R55 and R12
56
© 2015 Electric Power Research Institute, Inc. All rights reserved.
• R173 will close using sync-check
• Complete island established

Orangeville Tap

X Wind Farm
R55 R122 R173

X
Wethersfield

R199
500kVA

open
closed
Y
in reclosing Boxler Farm
cycle Scenario - permanent fault between R55 and R12
57
© 2015 Electric Power Research Institute, Inc. All rights reserved.
• Fault is removed and R55 manually closed

Orangeville Tap

R55 R122 R173 Wind Farm

X
Wethersfield

R199
500kVA

open
closed
Y
in reclosing Boxler Farm
cycle Scenario - permanent fault between R55 and R1
58
© 2015 Electric Power Research Institute, Inc. All rights reserved.
• R122 closes sync-check
• System normal

Orangeville Tap

R55 R122 R173 Wind Farm

X
Wethersfield

R199
500kVA

open
closed
Y
in reclosing Boxler Farm
cycle Scenario - permanent fault between R55 and R12
59
© 2015 Electric Power Research Institute, Inc. All rights reserved.
Recommendations - Protections

• 34.5kV protection and control of micro grid scheme is voltage based


• Voltage protection disconnects energy storage batteries prior to entering
microgrid operation
• Voltage protection detects and clears 34.5kV faults that occur during microgrid
operation

• Ferroresonance suppression is prudent for 34.5kV wye-grounded VTs


as well as using VTs with high saturation knee point (e.g. 2.0 per unit)

• Low voltage current based protection (e.g. 4.8kV feeders) will have to be
evaluated based on energy storage devices capability to source fault current
or alternative protection should be investigated – not addressed in this section

• Setting and reclosing setting changes needed on R55 and R173 as well as the
additional protection & control described in this section for microgrid operation

60
© 2015 Electric Power Research Institute, Inc. All rights reserved.
Proposed Protection, Monitoring, & Control
Modifications

WNY Wind
Corp. 6.6 MW

Attica Attica Prison Orangeville STA. 19


STA. 12 STA. 34.5 kV
R55 R122 R173
34.5 kV 1.12 mi 6.3 mi 0.2 mi 6.1 mi Vestas TAP
34.5 kV

0.1 mi
J192
Attica Prison
Wethersfield STA. 23
Thevenin equivalent 34.5 kV
source for Orangeville STA. 19

R199
Attica substation 4.8 kV
Orangeville 4.8-kV
PQ48V Wethersfield STA. 23
circuit and load
4.0 mi 4.8 kV

PQ48B
Boxler Farm Wethersfield 4.8-kV
480V, 416 kW Boxler DG circuit and load
4.8 kV

61
© 2015 Electric Power Research Institute, Inc. All rights reserved.
Proposed System Level Modifications – Energy Storage
System
Proposed
Existing 34.5 KV Proposed Existing
34.5 KV recloser
recloser recloser recloser

Plant Load: 5MW


4.8 KV
Proposed
Proposed 2 MWHR Energy
Plant Load: 1MW PQ Meter Storage
Plant Load: 1.8MW

Proposed
1 MWHR Energy
Storage Wind plant : 6.6 MW

Sync DG:
Microgrid OW –
0.416 MW Orangeville & Wethersfield

• 2 Separate ES systems proposed.


− Closer to the Loads at Orangville and Wethersfield
− Valid for independent operations of Orangville and
Wethersfield
62
© 2015 Electric Power Research Institute, Inc. All rights reserved.
Fault Location Analysis

WNY Wind
Corp. 6.6 MW
Cooper Form
SEL PG10 Type 6
Attica Attica Prison Orangeville STA. 19
STA. 12 STA. 34.5 kV
R55 R122 R173
34.5 kV 1.12 mi 6.3 mi 0.2 mi 6.1 mi Vestas TAP
34.5 kV

0.1 mi
J192
Attica Prison
Wethersfield STA. 23
Thevenin equivalent 34.5 kV
source for Orangeville STA. 19

R199
Attica substation 4.8 kV
Orangeville 4.8-kV
PQ48V Wethersfield STA. 23
circuit and load
4.8 kV

4.0 mi
PQ48B
Boxler Farm Wethersfield 4.8-kV
480V, 416 kW circuit and load

Number of Monitor Samples/cycle Voltage level Actual Fault Circuit Data useful for
events location model fault location

12 R55 4 34.5 kV Unknown ASPEN Yes


OneLiner
10 R173 16 Limited

63
© 2015 Electric Power Research Institute, Inc. All rights reserved.
Line Exposed to Faults in Grid Connected Mode

 Scenario G1: Multiple single line-to-ground faults applied in Line Section 1, between reclosers R55 and R122

 Scenario G2: Multiple single line-to-ground faults applied in Line Section 2, between reclosers R173 and R199

 Scenario G3: Multiple line-to-line faults applied in Line Section 3, between PQ48V and PQ48B

WNY Wind
Corp. 6.6 MW

Attica Attica Prison Orangeville STA. 19


STA. 12 STA. 34.5 kV
R55 R122 R173
34.5 kV 1.2 mi 6.3 mi 0.2 mi 6.1 mi Vestas TAP
Line Section 1 Line Section 2 34.5 kV

0.1 mi
J192
Attica Prison
Wethersfield STA. 23
Thevenin equivalent 34.5 kV
source for Orangeville STA. 19

R199
Attica substation 4.8 kV
Orangeville 4.8-kV
PQ48V Wethersfield STA. 23
circuit and load
4.8 kV
Section 3
Line
4.0 mi

PQ48B
Boxler Farm Wethersfield 4.8-kV
480V, 416 kW Boxler DG circuit and load
4.8 kV
64
© 2015 Electric Power Research Institute, Inc. All rights reserved.
Line Exposed to Faults in Microgrid Operation

 Scenario OW1: Multiple line-to-line faults applied in Line Section 2, between reclosers R173 and R199 (in
Microgrid OW operation)

 Scenario OW2: Multiple line-to-line faults applied in Line Section 3, between PQ48V and PQ48B (in Microgrid
OW operation)

 Scenario O1: Multiple line-to-line faults applied in Line Section 3, between PQ48V and PQ48B (in Microgrid O
operation)

Orangeville STA. 19
34.5 kV
R122 R173
0.2 mi 6.1 mi Vestas TAP
Line Section 2 34.5 kV Orangeville STA. 19
0.1 mi 4.8 kV
J192
Orangeville 4.8-kV

Line Section 3
Wethersfield STA. 23 circuit and load PQ48V
Orangeville STA. 19 34.5 kV Orangeville

4.0 mi
4.8 kV Energy Storage
R199

Orangeville 4.8-kV
Wethersfield STA. 23
Line Section 3

circuit and load PQ48V


Orangeville 4.8 kV
4.0 mi

Energy Storage
PQ48B
Boxler Farm
PQ48B 480V, 416 kW Boxler DG
Boxler Farm Wethersfield 4.8-kV 4.8 kV
480V, 416 kW Boxler DG circuit and load Wethersfield
4.8 kV Energy Storage

“Microgrid OW” “Microgrid O”


65
© 2015 Electric Power Research Institute, Inc. All rights reserved.
Fault Location Algorithms Applied in “Grid Connected” Mode

WNY Wind
Corp. 6.6 MW

Attica Attica Prison Orangeville STA. 19


STA. 12 STA. 34.5 kV
R55 R122 R173
34.5 kV 1.12 mi 6.3 mi 0.2 mi 6.1 mi Vestas TAP
34.5 kV
Line Section 1 Line Section 2

0.1 mi
J192
Attica Prison
Wethersfield STA. 23
Thevenin equivalent 34.5 kV
source for Orangeville STA. 19

R199
Attica substation 4.8 kV
Orangeville 4.8-kV
PQ48V Wethersfield STA. 23
circuit and load

Line Section 3
4.8 kV

4.0 mi
PQ48B
Boxler Farm Wethersfield 4.8-kV
480V, 416 kW circuit and load

Scenario Algorithms to be Applied during SLG Faults

One-ended methods (R55) Simple reactance, Takagi, Novosel et al.


Line Section 1
Two-ended method (R55, R122) Two-terminal negative-sequence

Line Section 2 One-ended methods (R173) Simple reactance, Takagi, Novosel et al.

One-ended methods (PQ48B) Simple reactance, Takagi, Eriksson


Line Section 3
Two-ended methods (PQ48B, PQ48V) Two-terminal negative-sequence
66
© 2015 Electric Power Research Institute, Inc. All rights reserved.
Case # 3: Secondary Network
(Arindam Maitra)

67
© 2015 Electric Power Research Institute, Inc. All rights reserved.
Case Study #3: Secondary Network

 Models developed in
OpenDSS, EMTP-RV, &
Power Factory

 Microgeneration types: CHP


behind inverter and PV

 Scenario tested: Small-scale


Distributed CHP units (small
synchronous machine
behind an inverter) + small
scale PV

68
© 2015 Electric Power Research Institute, Inc. All rights reserved.
One Line Diagram

69
© 2015 Electric Power Research Institute, Inc. All rights reserved.
Scenarios

1. Small-scale Distributed CHP units


(small synchronous machine behind
an inverter) + small scale PV 0.3 MVA
BLDG 7
0.05 MVA 0.3 MVA
BLDG 6
0.05 MVA 0.3 MVA
BLDG 5 0.05 MVA
(5917.44X_10384) (5877.44X_M1048) (5829.44X_10385)
kVA = 314.794 kVA = 222.239 kVA = 182.114
2. Small-scale Distributed CHP units
(small synchronous machine behind Inverter Inverter Inverter Inverter Inverter Inverter
an inverter) + small scale PV +
small scale distributed storage M1049 10385

(44X_10384)

(44X_M1048)
(44X_M1049) (44X_10385)

10384

M1048
3. Large-scale Central CHP unit (large M1047
(44X_M1047)

synchronous machine) + small


scale PV VS8360
(44X_VS8360)
BC3998
4. Large-scale Central CHP unit (large 0.025 MVA
(44X_BC3998)
0.025 MVA

Inverter
Inverter
synchronous machine) + small
scale PV + Large-scale central VS4007
(44X_VS4007)
VS3998
(44X_VS3998)
0.15 MVA 0.15 MVA
storage
Inverter

Inverter
303 Vernon Ave 303 Vernon Ave
(5766.44X_BC3998) (5916.44X_BC3998)
5. 100% Large CHP unit (large kVA = 140.5 kVA = 310.728

synchronous machine)
6. 100% Large CHP unit (large
synchronous machine behind an
inverter)

70
© 2015 Electric Power Research Institute, Inc. All rights reserved.
Assumptions

 The LV system is solidly grounded via a dedicated ground link at:


– Distribution supply transformer LV (transformers are Delta-Wye, directly
connected to ground on the secondary side)
– Each LV generator (generators are Y connected to ground)
– LV network protection vaults

 System impedance to ground is maintained at less than 5 ohms


as specified by Client

 The DERs are assumed:


– 3-phase YN connected and the neutral is solidly grounded
– Provide up to 1.8 per unit fault current
– Can sustainably provide fault current, including earth fault current until
fault is cleared or isolated

71
© 2015 Electric Power Research Institute, Inc. All rights reserved.
General philosophy used
 Determine the required level of selectivity for different fault scenarios. Generally, this
can be determined by considering the impact to the customers for different grid faults.

 Group parallel cables connecting common LV nodes together into single ’branches’

 Split the Microgrid into separate regions/zones which with appropriate protection
grading will achieve the desired selectivity.

 Ensure LV grid relays protecting branches directly connected to customers trip first to
remove the fault from the remaining healthy grid as quickly as possible

 Ensure some time delay between tripping of customer branches and any
interconnector circuits connecting together main LV nodes

 Ensure customer relays trip last to ensure healthy generation remains in service post
fault

72
© 2015 Electric Power Research Institute, Inc. All rights reserved.
High selectivity protection zones

73
© 2015 Electric Power Research Institute, Inc. All rights reserved.
Grid Connected Mode – Summer Peak Steady
State Branch Currents and Bus Voltages
From Current Loading
Line ID To Bus
Bus (A) (%)
sec_6643_1 143 17%
sec_6643_2 143 17%
10385 M1047
sec_6644_1 159 20%
sec_6644_2 159 20% Phase A Phase B Phase C
Bus ID
sec_6645_1 129 16% (pu) (pu) (pu)
sec_6645_2 129 16% M1048 0.98 0.98 0.98
sec_6646_1 M1047 M1048 115 14% 10384 0.96 0.96 0.96
sec_6646_2 115 14% 10385 0.97 0.97 0.97
sec_6646_3 115 14% BC3998 0.99 0.99 0.99
sec_6649_1 213 25% M1049 0.96 0.96 0.96
sec_6649_2 M1048 10384 213 25% M1047 0.97 0.97 0.97
sec_6650_1 239 29% VS8360 0.98 0.98 0.98
sec_6651_1 M1049 10384 0 0% VS4007 0.99 0.99 0.99
sec_6751_1 249 29% VS3998 0.99 0.99 0.99
sec_6751_2 BC399 249 29%
M1048
sec_6751_3 8 249 29%
sec_6751_4 249 29%
sec_6754_1 244 29%
sec_6754_2 244 29%
VS8360 M1048
sec_6754_3 244 29%
74
sec_6754_4 244
© 2015 Electric Power29%
Research Institute, Inc. All rights reserved. 74
Summer Peak Steady State and Fault Induced Bus Voltages –
Grid Connected & Islanded
Summer Load Fault @ 10384 Fault @ BC3998 Fault @ M1048
Bus ID Phase Phase Phase Phase Phase Phase Phase Phase Phase Phase Phas Phas
A B C A B C A B C A eB eC
M1048 0.98 0.98 0.98 0.69 0.69 0.69 0.37 0.37 0.37 0.00 0.00 0.00
10384 0.98 0.98 0.98 0.00 0.00 0.00 0.66 0.66 0.66 0.47 0.47 0.47
In grid connected
10385 0.99 0.99 0.99 0.79 0.79 0.79 0.59 0.59 0.59 0.35 0.35 0.35
mode the0.98
BC3998 bus 0.98 0.98 0.79 0.79 0.79 0.00 0.00 0.00 0.32 0.32 0.32
M1047 0.99
voltages of un- 0.99 0.99 0.74 0.74 0.74 0.48 0.48 0.48 0.17 0.17 0.17
VS8360 0.99 0.99 0.99 0.73 0.73 0.73 0.46 0.46 0.46 0.14 0.14 0.14
faulted
VS4007
buses
0.99
are
0.99 0.99 0.86 0.86 0.86 0.33 0.33 0.33 0.55 0.55 0.55
non-zero
VS3998 0.99 0.99 0.99 0.80 0.80 0.80 0.04 0.04 0.04 0.35 0.35 0.35

Summer Load Fault @ 10384 Fault @ BC3998 Fault @ M1048


Bus ID Phase Phase Phase Phase Phase Phase Phase Phase Phase Phase Phase Phase
A B C A B C A B C A B C
M1048 1.00 1.00 1.00 0.13 0.13 0.13 0.05 0.05 0.05 0.00 0.00 0.00
10384 1.00 1.00 1.00 0.00 0.00 0.00 0.09 0.09 0.09 0.05 0.05 0.05
When
10385
islanded
1.01 1.01 1.01 0.15 0.15 0.15 0.07 0.07 0.07 0.03 0.03 0.03
the bus voltages
BC3998 1.00 1.00 1.00 0.14 0.14 0.14 0.00 0.00 0.00 0.02 0.02 0.02
are
M1047close1.00
to zero1.00 1.00 0.14 0.14 0.14 0.06 0.06 0.06 0.01 0.01 0.01
and inadequate
VS8360 1.00 1.00 1.00 0.13 0.13 0.13 0.05 0.05 0.05 0.00 0.00 0.00
for fault location
VS4007 1.00 1.00 1.00 0.14 0.14 0.14 0.00 0.00 0.00 0.02 0.02 0.02
determination
VS3998
75 1.00 1.00 1.00 0.14 0.14 0.14 0.00 0.00 0.00 0.02 0.02 0.02
© 2015 Electric Power Research Institute, Inc. All rights reserved. 75
Changes from Grid Connected Mode to Islanded Mode in
Summer Peak Steady State and Fault Induced Phase A Branch
Currents

Summer Fault @
Line ID From Bus To Bus Fault @ 10384 Fault @ M1048
Load BC3998
sec_6643_1 78% -75% -87% -92%
sec_6643_2
When islanded 78% -75% -87% -92%
10385 M1047
sec_6644_1 78% -75% -87% -92%
fault currents
sec_6644_2 78% -75% -87% -92%
decrease
sec_6645_1
for all 78% -75% -87% -92%
3-phase faults
sec_6645_2 78% -75% -87% -92%
When islanded
sec_6646_1 M1047 M1048 78% -75% -87% -92%
sec_6646_2
line loading 78% -75% -87% -92%
sec_6646_3 78% -75% -87% -92%
increases for
sec_6649_1 -31% -82% -85% -90%
most
sec_6649_2
line
M1048 10384 -31% -82% -85% -90%
sections
sec_6650_1 -31% -82% -85% -90%
sec_6751_1 279% -86% -88% -95%
sec_6751_2 279% -86% -88% -95%
M1048 BC3998
sec_6751_3 279% -86% -88% -95%
sec_6751_4 279% -86% -88% -95%
Total Fault Current at the Fault Location (%) -89% -93% -93%

76
© 2015 Electric Power Research Institute, Inc. All rights reserved.
Modeling Existing Protection

Typical TCC for a


current-limiting fuse

Used representative curves Curve in power factory

77
© 2015 Electric Power Research Institute, Inc. All rights reserved.
Findings and recommendations: Current-Limiting Protection

 Normally the Current limiter (CL) fuse will “melt” when the
current in the fuse element exceeds the current specified by
the fuse’s melt characteristic.

 No enough fault currents from the inverter based gens;


hence there is no compliance to protection standards and
performance metrics during island mode

 Clearly, this type of protection in utilizing current limiters isn’t


sufficient

 Another set of protection strategies need to be adopted


78
© 2015 Electric Power Research Institute, Inc. All rights reserved.
Small-scale Distributed CHP units (small
synchronous machine behind an inverter) + small
scale PV

Circuit breakers

Directional-
Overcurrent

• The overcurrent modules and circuit breakers tip-times


depend on the fault-current amplitude
• The appropriate directional modules were set to trip
slightly after the overcurrent models

79
© 2015 Electric Power Research Institute, Inc. All rights reserved. 79
3 Phase Fault @ 10384

80
© 2015 Electric Power Research Institute, Inc. All rights reserved. 80
3 Phase Fault @ 10384

1
1. D/O module between 10384 and
M1048 trips on overcurrent
2. Circuit breaker at 10384 PCC trips
on overcurrent

81
© 2015 Electric Power Research Institute, Inc. All rights reserved. 81
3 Phase Fault @ 10384

Isolated

Loads and generators at bus 10384 are


isolated

82
© 2015 Electric Power Research Institute, Inc. All rights reserved. 82
3 Phase Fault @ 10384

After fault is cleared bus voltages


recover to normal values

83
© 2015 Electric Power Research Institute, Inc. All rights reserved. 83
1 Phase Fault @ 10384

84
© 2015 Electric Power Research Institute, Inc. All rights reserved. 84
1 Phase Fault @ 10384

1
1. D/O module between 10384 and
M1048 trips on overcurrent
2. Circuit breaker at 10384 PCC trips
on overcurrent

85
© 2015 Electric Power Research Institute, Inc. All rights reserved. 85
1 Phase Fault @ 10384

Isolated

Loads and generators at bus 10384 are


isolated

86
© 2015 Electric Power Research Institute, Inc. All rights reserved. 86
1 Phase Fault @ 10384

After fault is cleared bus voltages


recover to normal values

87
© 2015 Electric Power Research Institute, Inc. All rights reserved. 87
1 Phase Fault (46.6 mΩ) @ 10384

88
© 2015 Electric Power Research Institute, Inc. All rights reserved. 88
1 Phase Fault (46.6 mΩ) @ 10384

1
1. D/O module between 10384 and
M1048 trips on overcurrent
2. Circuit breaker at 10384 PCC trips
on overcurrent

89
© 2015 Electric Power Research Institute, Inc. All rights reserved. 89
1 Phase Fault (46.6 mΩ) @ 10384

Isolated

Loads and generators at bus 10384 are


isolated

90
© 2015 Electric Power Research Institute, Inc. All rights reserved. 90
1 Phase Fault (46.6 mΩ) @ 10384

After fault is cleared bus voltages


recover to normal values

91
© 2015 Electric Power Research Institute, Inc. All rights reserved. 91
Phase-Phase Fault @ 10384

92
© 2015 Electric Power Research Institute, Inc. All rights reserved. 92
Phase-Phase Fault @ 10384

1
1. D/O module between 10384 and
M1048 trips on overcurrent
2. Circuit breaker at 10384 PCC trips
on overcurrent

93
© 2015 Electric Power Research Institute, Inc. All rights reserved. 93
Phase-Phase Fault @ 10384

Isolated

Loads and generators at bus 10384 are


isolated

94
© 2015 Electric Power Research Institute, Inc. All rights reserved. 94
Phase-Phase Fault @ 10384

After fault is cleared bus voltages


recover to normal values

95
© 2015 Electric Power Research Institute, Inc. All rights reserved. 95
Phase-Phase-Ground Fault @ 10384

96
© 2015 Electric Power Research Institute, Inc. All rights reserved. 96
Phase-Phase-Ground Fault @ 10384

1
1. D/O module between 10384 and
M1048 trips on overcurrent
2. Circuit breaker at 10384 PCC trips
on overcurrent

97
© 2015 Electric Power Research Institute, Inc. All rights reserved. 97
Phase-Phase-Ground Fault @ 10384

Isolated

Loads and generators at bus 10384 are


isolated

98
© 2015 Electric Power Research Institute, Inc. All rights reserved. 98
Phase-Phase-Ground Fault @ 10384

After fault is cleared bus voltages


recover to normal values

99
© 2015 Electric Power Research Institute, Inc. All rights reserved. 99
3 Phase Fault @ M1048

100
© 2015 Electric Power Research Institute, Inc. All rights reserved. 100
3 Phase Fault @ M1048

1 3

1. D/O module between 10384 and M1048 trips on


directional
2
2. D/O module between BC3998 and M1048 trips on
directional
3. D/O module between M1047 and M1048 trips on
overcurrent
4. Circuit breaker at M1048 PCC trips on overcurrent
101
© 2015 Electric Power Research Institute, Inc. All rights reserved. 101
3 Phase Fault @ M1048

Isolated Isolated Isolated

Loads and generators at all buses are


isolated

Isolated

102
© 2015 Electric Power Research Institute, Inc. All rights reserved. 102
3 Phase Fault @ M1048

After fault is cleared bus voltages:


1. at 10385 and M1048 are elevated
2. at BC3998 are bellow normal
values
3. at 10384 recover to normal values

103
© 2015 Electric Power Research Institute, Inc. All rights reserved. 103
3 Phase Fault @ BC3998

104
© 2015 Electric Power Research Institute, Inc. All rights reserved. 104
3 Phase Fault @ BC3998

1. D/O module between BC3998 and M1048 trips on


overcurrent
2 2. Circuit breaker at BC3998 PCC trips on
overcurrent

105
© 2015 Electric Power Research Institute, Inc. All rights reserved. 105
3 Phase Fault @ BC3998

Loads and generators at bus BC3998


are isolated

Isolated

106
© 2015 Electric Power Research Institute, Inc. All rights reserved. 106
3 Phase Fault @ BC3998

After fault is cleared bus voltages:


1. at 10384, 10385 and M1048 are
elevated
2. at BC3998 are bellow normal
values

107
© 2015 Electric Power Research Institute, Inc. All rights reserved. 107
3 Phase Fault @ 10385

108
© 2015 Electric Power Research Institute, Inc. All rights reserved. 108
3 Phase Fault @ 10385

1. D/O module between 10385 and M1048 trips on


directional
2. Circuit breaker at 10384 PCC trips on overcurrent

109
© 2015 Electric Power Research Institute, Inc. All rights reserved. 109
3 Phase Fault @ 10385

Isolated

Loads and generators at bus 10385 are


isolated

110
© 2015 Electric Power Research Institute, Inc. All rights reserved. 110
3 Phase Fault @ 10385

After fault is cleared bus voltages:


1. at 10385 are elevated
2. at 10384, M1048, and BC3998 are
bellow normal values

111
© 2015 Electric Power Research Institute, Inc. All rights reserved. 111
Summary
“Microgrids” brings many technical needs: Good PSA tools available

• Network  Grid requirements

• Objective  Controllability

• Scenarios  Monitoring

• Modeling  Reliability

No one-size fits all protection scheme works for all microgrids

Best protection scheme depends on microgrid objective

Continue testing various protection schemes


Action plan
Level of dynamic studies details depends on so many
factors i.e. gen types, operation philosophy etc.
112
© 2015 Electric Power Research Institute, Inc. All rights reserved.
Together…Shaping the Future of Electricity

113
© 2015 Electric Power Research Institute, Inc. All rights reserved.

Potrebbero piacerti anche