Sei sulla pagina 1di 112

MADHYA PRADESH POWER TRANSMISSION CO. LTD.

SHAKTI BHAWAN RAMPUR: JABALPUR

VOLUME –II

PART-7
Technical Book Serial No.
MPPTCL/TECH/PROC/07/July15

TECHNICAL SPECIFICATION FOR SUPPLY


OF EHV EQUIPMENTS AND MATERIAL FOR
SUB-STATIONS AND FEEDER BAYS

O/o CHIEF ENGINEER (PROCUREMENT)


MPPTCL, JABALPUR
Volume-II contains eight booklets as under:-

Section Description Technical Book


Serial No.
Part-1 TECHNICAL SPECIFICATION FOR MPPTCL/TECH/
SUPPLY OF 400KV/220KV, 315MVA PROC/01/JULY15
POWER TRANSFORMERS
Part-2 TECHNICAL SPECIFICATION FOR MPPTCL/TECH/
SUPPLY OF 400KV/132KV, 100MVA PROC/02/JULY15
POWER TRANSFORMERS
Part-3 TECHNICAL SPECIFICATION FOR MPPTCL/TECH/
SUPPLY OF 400KV, 125MVAR REACTOR PROC/03/JULY15
Part-4 TECHNICAL SPECIFICATION FOR MPPTCL/TECH/
SUPPLY OF 220KV/132KV, 160MVA PROC/04/JULY15
POWER TRANSFORMERS

Part-5 TECHNICAL SPECIFICATION FOR MPPTCL/TECH/


SUPPLY OF 220KV/33KV, 50MVA PROC/05/JULY15
POWER TRANSFORMERS
Part-6 TECHNICAL SPECIFICATION FOR MPPTCL/TECH/
SUPPLY OF 132KV/33KV, 63MVA PROC/06/JULY15
POWER TRANSFORMERS
Part-7 TECHNICAL SPECIFICATION FOR MPPTCL/TECH/
SUPPLY OF 132KV/33KV, 40MVA PROC/07/JULY15
POWER TRANSFORMERS
Part-8 TECHNICAL SPECIFICATION FOR MPPTCL/TECH/
400/220/132/33KV EQUIPMENTS PROC/08/JULY15
( 3 BOOKLETS) MPPTCL/TECH/
PROC/09/JULY15
MPPTCL/TECH/
PROC/10/JULY15

All the above eight booklets are in the form of separate


books. This book refers to:-

PART-7
TECHNICAL SPECIFICATION FOR 132/33 KV, 40 MVA
POWER TRANSFORMERS
Please note that the modifications in technical specifications are
indicated in Appendix-1, enclosed in Volume-I of the Tender
document.
Contents

Description of document Page No.


Technical specification for transformer 1-65
Annexures and appendix for 132KV, 40MVA Power Transformer
Annexure I - Principal Technical particulars 66-68
Annexure II - List of Fittings and Accessories 69-72
Annexure III - Test certificates to be furnished
73-75
for accessories
Annexure IV - Schedule of Inspection
76
Windows
Annexure V - Schedule of Valves 77-78
Annexure VI(A)- Drawings & Data to be
79-81
furnished
Annexure VI(B)- List of drawings to be
82
furnished alongwith bid
Annexure VII - Calculations required to be
83-86
furnished
Annexure VIII - Details of Inspection Program
87-91

Annexure IX - List of Hand Tools and Jacks 92


Annexure X - Description of equipment for
93
schedule of rates & prices
Annexure XI - List of vendors for major items
94-97
of transformer
Appendix I - Calculation for Hot Spot
winding temperature for EHV 98-99
transformers
Appendix II - Technical particulars to be
100
filled-in by bidder

List of abbreviations used in technical


101-102
specification –
VOLUME II, PART-7

TECHNICAL SPECIFICATION FOR 40 MVA ,


132/33 KV POWER TRANSFORMERS

1.0 SCOPE :

1.1 This specification covers design, engineering, manufacture,


assembly, stage inspections and testing before supply and delivery
including unloading on plinth at our substation sites of 132/33KV,40 MVA,
three phase transformers complete with all fittings, accessories, associated
equipment including oil for first filling including wastage & 10% extra of that
quantity specified herein which are required for efficient and trouble free
operation as specified hereunder.

1.2 It is not the intent to specify completely herein all the details of
the design and construction of equipment. However, the equipment shall
conform in all respects to high standards of engineering, design and
workmanship and shall be capable of performing the duties specified
herein. The offered transformers shall be complete with all components
necessary for their effective and trouble free operation. Such components
shall be deemed to be within the scope of Bidders supply irrespective of
whether those are specifically brought out in this specification or not. The
transformers should be free from Polychlorinated Biphenyls
(PVB/PCB).

1.3 The Purchaser will interpret the meanings of drawings and


specification and shall have the power to reject any work or material
which, in his judgment is not in accordance therewith. The offered
transformers shall be complete with all components necessary for their
effective and trouble free operation. Such, components shall be deemed to
be within the scope of Bidders supply irrespective of whether those are
specifically brought out in this specification and/or the commercial order or
not.

2.0 STANDARDS:

2.1 The transformers and associated accessories shall conform to


the latest issues/amendments of standards as given below, and report of
the committee for standardization of the parameters and specification of class
132 KV equipment, except to the extent explicitly modified in this
specification. Transformers conforming to any other authoritative standards
meeting better quality and ensuring better performance are also acceptable.
Bidder shall specifically indicate deviations if any from the INDIAN
STANDARDS.

MPPTCL/TECH/PROC/07/JULY 15 1 of 105
Volume-II, Part-7

THE APPLICABLE INDIAN/INTERNATIONAL STANDARDS FOR POWER


TRANSFORMERS AND ASSOCIATED ACCESSORIES ETC.

INTERNATIONAL
INDIAN AND
STANDARD TITLE INTERNATIONALLY
NUMBER RECOGNISIED
STANDARD
IS-2026 Power Transformers IEC-60076(Part I to 5)
(Part 1 to 5 )
CBIP Publi- Manual on Power Transformers
cation
No.295
IS-335 Insulating oil for transformers IEC-296,BS-148.
IS1866- Electrical maintenance and Supervision
2000 of mineral insulating oil in equipment.
IS-2099 Bushings for alternating Voltage above IEC-60137(2008)
1000V.
IS-2312 Fans (Cooler fans)
IS-2705. Current Transformers. IEC 60044
IS-325. Three phase Induction motors. IEC-34.
IS-375 & Marking & arrangements for switch
IS-996 gear, bus bars, main connections &
auxiliary wiring.
IS-3407. Gas & oil operated relays.
IS-10028 Code of practice for installation and
(Part 1to3) maintenance of transformers.
IS-2147. Degree of protection provided by IEC 60529,IEC60947
enclosures for low voltage switch gear
and control.
IS-5. Colours for ready mix paints.
IS-6272 Industrial cooling fans.
DOC.ETD16 Draft standard by BIS for revision of IS- IEC 60354
(3703) 6600 for Guide for loading of oil
immersed transformers.
OLTC IEC 60214
IS 8478 Application Guide for OLTC IEC 60542
IS 10561 Application Guide for Power IEC 60076-8
Transformer.
IS 13964 Method of measurement of Transformer NEMA-TR1
Sound levels.
IS 2071 Methods of High Voltage Testing IEC 60060
(Part 1 to 3)
IS 6209 Methods for Partial Discharge IEC 60270
Measurements
IS 2165 Insulation Coordination IEC 60071
IS 5561 Terminal connectors

MPPTCL/TECH/PROC/07/JULY15 2 of 105
Volume-II, Part-7

INTERNATIONAL
INDIAN AND
STANDARD TITLE INTERNATIONALLY
NUMBER RECOGNISIED
STANDARD
Short Circuit Current – calculation of IEC 865(part I & II)
effects
IS-5553 Shunt Reactors, Neutral/Earthing IEC 60289
Reactor and Arc Suppression Coil
IS:335 Insulating oils for transformers and IEC:60296, BS:223
switchgears
IS -1886 Code of practice for installation and
maintenance of transformers.

Supervision and Maintenance guide for IEC 60422


Mineral Insulating Oil in Electrical
Equipment
Method of Sampling of Liquid dielectrics IEC 60475
Guide for the Sampling of Gases and of IEC 60567
Oil from Oil-filled Electrical Equipment
for the Analysis of Free and Dissolved
Gases
Digital Recorders and Software for High IEC 61083
Voltage Impulse testing
Specification for radio disturbance and CISPR 16
immunity measuring apparatus
Guidelines for conducting design reviews Cigre Publication 202
for transformers 100 MVA and 123 kV
and above.
Metal oxide surge arrestors without IEC 99-4
gaps
Selection and application IEC 99-5
recommendation
Indian Electricity Rule 1956

2.2 In case equipment conforms to other International standards which


ensure equivalent or better performance than specified under cl 2.1 then
the English version of such standards or the relevant extracts of same shall
be forwarded with the bid and the salient features of comparison shall be
brought out separately.

2.3 The electrical installation shall meet requirements of Indian


Electricity Rules, 1956 and IS-1886,"Code of practice for installation &
maintenance of Transformers" as amended till date.

2.4 It has been experienced that the weight of core lamination,


weight of copper, weight of steel, weight of Transformer Tank along with
Fittings and Accessories and quantity of oil for first filling including wastage
& 10% extra of that quantity, total weight of core + winding after assembly

MPPTCL/TECH/PROC/07/JULY15 3 of 105
Volume-II, Part-7

and total weight of transformer are indicated in the technical bid by the
manufacturers on tentative basis and at the time of submission of
drawing, wide variations in these quantities take place. This is not in
order and it will be obligatory on the part of the Bidder to ensure that all
these details are worked out carefully and only correct figures after proper
design are offered in the technical bid. It may be noted that at the time of
submission of final drawings, variation in these weights beyond the limits of
(+) 5% shall not be permitted.

2.5 It will also be obligatory on the part of the manufacturer to furnish


details of calculations for quantity (weight & size) of core material, quantity
(weight & size) of copper material, calculations for thermal and dynamic
short circuit withstand capability of transformer, calculations for pressure
relief valve, adequacy of size of AIRCELL Bag, volume of oil for adequate
cooling with calculations of size of conservator and other details as called
for in the specification. Furnishing of these calculations along-with technical
bid is a must. All the data should be supported with calculation details.

2.6 Interconnection : The transformers are meant for service as


interconnecting transformers and shall be capable of being energized either
from 132 KV side or 33 KV side. The power transformer shall be capable of
being loaded at rated power on the 132 KV and 33 KV sides at its full rating
(lagging or leading or mixed load). On Load Tap Changer shall be suitable for
such operation. The OLTC shall be suitable for bidirectional flow of power.

3.0 SERVICE CONDITIONS :

3.1 Climatic Conditions : The transformers and its accessories to be


supplied against this specification shall be suitable for satisfactory
continuous operation under the following tropical conditions.

1. Location At various substations within


the State of Madhya Pradesh
2. Max. Ambient air temp. (oC) 50
3. Min ambient air temp (oC) -5
4. Maximum daily average ambient air 40
temperature(oC)
5. Maximum yearly weighted average 32
temperature (oC)
6. Maximum Relative humidity (%) 95 (sometimes reaches
saturation.)
7. Average annual rainfall (cm) 125
8. Max. Wind pressure (Kg/sq.m.) 150
9. Max. Altitude above mean sea level 1000
(Metres)
10. Isoceraunic level (Average number of 50
thunderstorm days per year)
11. Seismic level (horizontal acceleration) 0.3g

MPPTCL/TECH/PROC/07/JULY15 4 of 105
Volume-II, Part-7

Moderately hot and humid tropical climate, conducive to rust and


fungus growth. Tropical Protection Shall conform to IS:3202 titled “ climate
proofing of electrical equipments” and BS: 1014 : titled “protection of
electrical power equipments against the climatic condition”. The transformer
tank fittings and radiators including all accessories shall be designed to
withstand seismic acceleration equivalent to 0.3 g. Special precautions shall
be taken to prevent mal-operation of Buchholz relay under such condition.

3.2 Auxiliary Power Supply : Auxiliary electrical equipment shall be


suitable for operation on the following supply system.

a. Power Devices 0.415 KV, 3phase, 4wire 50Hz. neutral grounded AC


(like drive motors) supply.
b. DC Alarm, 220V or 110volts DC, ungrounded 2wire
control & (Substation wise exact details shall be furnished to
protective the successful Bidder).
devices
c. Lighting. 230V, single phase, 50Hz. AC supply.

Bidders scope include supply of interconnecting cables, terminal


boxes etc. The above supply voltage may vary as indicated below and all
devices shall be suitable for continuous operation over the entire range of
voltages.

i) AC supply : Voltage Variation of –25% to +10%;Frequency


+/- 4%
ii) DC supply : Voltage Variation of -20% to + 10%.

All accessories requiring AC or DC supply shall perform


satisfactorily for voltage variation as above.

4.0 GENERAL TECHNICAL REQUIREMENTS :

4.1 Duty Requirements

a) The transformers and all its accessories like CTs etc., shall
be designed to withstand without injury, the thermal and
mechanical effects of any external short circuit to earth and of
short circuits at the terminals considering infinite bus
arrangement of values specified as under :
132KV - 40KA for 3 secs.
33KV - 31.5KA for 3 secs.
b) Over Loading : The transformer shall be capable of being
loaded in accordance with IS:6600. There shall be no limitation
imposed by windings, bushings, tap changer etc. of
transformer. Transformer & all its accessories shall be liberally
rated to allow 10% over loading at all taps on continuous
basis without exceeding the temperature limits specified in
clause 6.0.

MPPTCL/TECH/PROC/07/JULY15 5 of 105
Volume-II, Part-7

The transformer shall be capable of being operated without


danger on each tapping at the rated KVA with specified voltage
variation corresponding to the voltage of that tapping with
normal temperature rise. The design adopted to achieve this
shall be indicated in detail in the Bid.

Transformer shall be capable of operating under the natural


cooled condition up to the specified load i.e. as ONAN rating.
The forced air cooling equipment shall come into operation by
pre-set contacts of winding temperature indicator and the
transformer shall operate as a forced air cooled unit i.e. as
ONAF. Cooling shall be so designed that during total failure of
power supply to cooling fans the transformer shall be able to
operate at full load for Ten(10) minutes without the calculated
winding hot spot temperature exceeding 140 deg.C. Also
stopping of two cooling fans should not have any effect on the
cooling system. Transformers fitted with two coolers (cooling
banks) each capable of dissipating 50 per cent of the loss at
continuous maximum rating shall be capable of operating for
20 minutes in the event of failure of the blowers associated
with one cooler, without the calculated winding hot spot
temperature exceeding 140oC at continuous maximum rating.

c) Over Voltage : The transformers shall be capable of being


operated on continuous basis at 10% excess voltage than the
rated voltage specified at each tap.

4.2 Radio Interference & Noise Level:

4.2.1 The transformers shall be designed with particular attention for


suppression of maximum harmonic voltage especially the third and fifth so as
to eliminate wave form distortion and minimize interference with
communication circuits.

4.2.2 The noise level, when energized at normal voltage and frequency
with fans running shall not exceed, when measured under standard
conditions, the values specified in NEMA,TR-I.

4.3 Stresses : Transformer shall be capable of withstanding Electrical,


thermal and mechanical stresses on any winding caused by forces due to
symmetrical or asymmetrical external fault.

4.4 Frequency & Magnetic Induction:

4.4.1 The transformers shall be suitable for continuous operation for a


frequency variation of (+) plus (-) minus 4% from normal 50Hz without
exceeding the specified temperature rise. For considerations of over fluxing,
the transformer shall be suitable for continuous operation for values of over
fluxing factor up to 1.1.
V FN
The over fluxing factor being { -- x -- }
VN F

MPPTCL/TECH/PROC/07/JULY15 6 of 105
Volume-II, Part-7

4.4.2 The working flux density shall not exceed 1.65 Tesla for offered no
load losses and the maximum flux density in any part of core and yoke at
110% rated voltage combined with (-) 4% frequency variation shall preferably
not exceed the value of 1.90 Tesla as per CBIP manual no 295. For
manufacturing of Power transformer, core laminations of various specifications
are available and therefore while selecting the working flux density, the
Bidders will have to comply with the requirements of cl.4.4.1 & 4.4.3.

4.4.3 For the selected flux density, the transformer shall have minimum
of following over fluxing capabilities , such that while meeting the above
requirement saturation of transformer core shall not take place under any
circumstances. Transformer shall accept, without injurious heating, combined
voltage & frequency fluctuation, which produces the following over fluxing
conditions :

Over Fluxing Factor Period


1.50 Less than 2 seconds
1.40 5.0 seconds
1.25 60 seconds
1.10 Continuous

The Bidder shall also indicate 160% & 170% over voltage/over
fluxing withstand capability period. Over fluxing withstand characteristics up
to 170% shall be submitted along with the bid.

4.4.4 Detailed calculations for maximum flux density and magnetizing


current for core material shall be furnished to substantiate the above
requirement. The manufacturer shall enclose details of Core Material with
thickness of lamination, type designation and source of raw material and it’s
characteristic curves. All characteristic curves of material including Voltage Vs
Flux Density and Loss per Kg Vs Flux Density are to be enclosed with Bid
clearly indicating Flux Density selected for calculation of core losses (No load
loss). On the basis of these data, for the Flux Density and core material
chosen verification of Saturation Flux Density shall be done by the purchaser,
to know the margin considered in operating Flux Density .

4.4.5 The maximum current density for design of power transformers


within specified limits of transformer losses shall not exceed the limits of 300
amps per sq.cm.

4.4.6 All other requirement of magnetic circuit shall be as per latest issue
of CBIP Manual no 295.

4.4.7 The transformers shall be either core type or shell type


construction, oil immersed, ONAN/ONAF with external heat exchangers and
shall be suitable for outdoor service as inter connecting and/or step-down
transformers suitable for parallel operation with the existing transformer
having tertiary winding already in service at the EHV substation where these
transformers are to be commissioned. The rating and electrical characteristics
of the transformers shall be strictly as specified in this specification. For
matching the parameters required for parallel operation with existing unit,
details shall be intimated to successful Bidder.

MPPTCL/TECH/PROC/07/JULY15 7 of 105
Volume-II, Part-7

4.5 All the transformers shall be suitable for continuous operation with
frequency variation of +/- 4% from normal 50 Hz . Combined voltage &
frequency variation should not exceed the rated V/f ratio by 10 %.

5. INSULATION

5.1 Impulse & Power Frequency Voltage Withstand Values : For


rated nominal system voltage of 33KV & 132KV following minimum power
frequency and impulse withstand voltage should be offered for the windings.

System Highest System Power Frequency Impulse


Voltage Voltage Withstand Withstand
Voltages Voltage
33KV 36KV 95KV rms 250KVp
132KV 145KV 230KV rms 550KVp

5.2 The HV winding of the transformers shall have graded


insulation. The insulation class of the neutral end of the winding
shall be graded to 95 KV. The 33KV winding shall have full insulation
for 33KV i.e. 250 KVp impulse and 95KVrms power frequency.

6.0 TEMPERATURE RISE : Each transformer shall be capable of


operating continuously at its normal rating & 10% over load condition
without exceeding temperature limits as specified below. The maximum
ambient temperature shall be taken as 50 degree C and type of cooling be
suitably adopted to limit the temperature rise within the safe limit of
operation.

Type Of Cooling Temperature-Rise


Windings Oil
ONAN (Air natural). 50oC 45oC
ONAF (Air forced) 50oC 45oC.

7.0 FREQUENCY : All the transformers shall be suitable for continuous


operation with a frequency variation of + 4% to -4% from normal 50 Hz
without exceeding the specified temperature rise.

8.0 IMPEDANCE : The percentage impedance of the power transformer


shall be 10% on 40 MVA base. manufacturer shall indicate the guaranteed
impedance, tolerances and also the impedance on all taps for the offered
transformers. Impedance shall include positive and zero sequence and shall
be expressed in terms of the branches of the star connected equivalent
diagrams on all the specified MVA base and the range shall be given for each
branch of the equivalent circuit turn. It may be noted that if required the
percentage impedance should be designed identical to the existing
transformer of any make in case parallel operation is desired. The IS
tolerance on all matching taps are acceptable. Confirmation regarding
requirement of parallel operation should be given in the Bid.

MPPTCL/TECH/PROC/07/JULY15 8 of 105
Volume-II, Part-7

It
may be noted by the manufacturer that for the purpose of
matching impedance of transformer, included in scope of this Bid,
between 132KV & 33KV windings, the Bidders are not permitted to use
reactor or reactor/capacitor assembly. The design of the main winding should
take care of the requirement of impedances as specified in this Bid
document and for this purpose, no reactor or reactor/capacitor should be
used.

9.0 MAXIMUM LOSSES:

9.1 Maximum Losses : While the Bidders may offer their own design, it
may be noted that the transformer losses at 75 deg. C. at rated Output.
Rated Voltage and rated frequency should not exceed the following
maximum limits which include tolerances as per IS :

a) No load losses (Iron losses). : 20 KW


b) Load(Copper losses) + Auxiliary losses. : 100 KW
including stray loss in KW

9.2 The No load losses in kilowatts (including BIS tolerance) at rated


voltage and rated frequency and the total load losses in kilowatts at rated
output, rated voltage and rated frequency at 75oC shall be guaranteed by
the Bidder. It may be noted that the losses of the Transformer shall not
exceed during final testing of the transformer, if the same exceeds from the
maximum Ceiling limit of Transformer losses as detailed in 9.1 above the
Transformer shall not be accepted

9.3 Heat Run Test:

One 40 MVA 132 KV power transformer of each manufacturer (if


there are more than one manufacturer) shall be subject to heat run test
(Temperature rise test).

10.0 COOLING : The Bidder may offer ONAN / ONAF type of cooling
for these transformers. The ONAF rating for each transformer winding shall
be 125% of ONAN rating achieved by cooling. The ONAF cooling shall be in
two groups each of 50% capacity. Adequate no. of standby cooling fans
shall be provided for 20% additional cooling per bank, in line with requirement
indicated in clause 15.1 ( C ).

11.0 CONSTRUCTION DETAILS : The features and construction details


of power transformer shall be in accordance with the requirements stated
hereunder

11.1 Tank
(A) As required in CBIP specification, the tank shall be of Bell type
construction for 40 MVA transformers covered under this
specification. Top cover of Bell type construction shall be
welded to the tank body.

MPPTCL/TECH/PROC/07/JULY15 9 of 105
Volume-II, Part-7

(B) Tank shall be of welded construction and fabricated from


tested quality low carbon steel suitable for welding & of
following minimum sheet thickness.
Tank cover - 20 mm, Sides including inspection covers- 10
mm , Base - 20 mm, turret size-6 mm.
(C) All seams and those joints not required to be opened at site
shall be factory welded and wherever possible they shall
be double welded. After completion of tank construction and
before painting, 'Dye Penetration Test' shall be carried out on
welded parts of jacking bosses, lifting lugs and all load
bearing members.
(D) Tank stiffeners shall be provided for general rigidity and these
shall be designed to prevent retention of water.

(E) The tanks shall be designed to withstand the following


without permanent distortion.
(i) Mechanical shocks during transportation.
(ii) Vacuum filling of oil at 10 milli torr in transformer with
all fittings.
(iii) Continuous internal pressure of 35 kN/m2 over normal
hydrostatic pressure of oil.
(iv) Short circuit forces &
(v) Under seismic condition /events both horizontal/vertical.

(F) Where ever possible the transformer tank and its accessories
shall be designed without pockets wherein gas may collect.
Where pockets can not be avoided, pipes shall be provided to
vent the gas into the main expansion pipes if any.

(G) The shields shall be such that no magnetic fields shall exist
outside the tank. They shall be of magnetically permeable
material. If required impermeable shields shall be provided
at the coil ends. Tank shield shall not resonate when excited at
the natural frequency of the equipment.

(H) The tank shall be provided with :


(i) Lifting lugs suitable for lifting the equipment complete
with oil.
(ii) A minimum of four jacking pads in accessible position
at 500mm height to enable the transformer complete
with oil to be raised or lowered using hydraulic or screw
jacks. The location of jacking pads shall be such that
there should not be any interference with the civil
foundation of rails in either direction i.e. longitudinal or
transverse. A typical drawing no. MPPTCL/40MVA/01 for
providing jacking pad is enclosed with the Bid
specification.
(iii) Suitable haulage holes shall be provided.

MPPTCL/TECH/PROC/07/JULY15 10 of 105
Volume-II, Part-7

(I) (i) Inspection cover/access windows & Manholes:


Suitable man-hole with a welded flange and a properly
gasketted bolted cover having of minimum thickness of
10 mm shall be provided on the tank cover. The man-
hole shall be of sufficient size to offer easy access to the
lower ends of the bushings, terminal etc. The
requirement of inspection windows and manholes have
been stipulated in Annexure-IV & Bidders have to
confirm compliance of the same in their Bid.
(ii) Space for free movement in Transformer Tank for
inspection:
Details of passage & free space provided inside the
main tank should be indicated in concerned drawing to
allow free movement of at-least two persons for
inspection of active parts etc. To be more specific it
may please be noted that minimum clearance from
outer most winding/connection leads/supports to
tank shall not be less than 300 mm on all 4 sides
with suitable platform on bottom of the tank to
facilitate free movement of person all around inside
the tank.

(J) All bolted connections to the tank shall be fitted with


suitable oil tight gaskets which shall give satisfactory service
under all operating conditions. Special attention shall be given
to the methods of making the hot oil tight joints between
the tank and the cover as also between the cover and the
bushings and all other outlets to ensure that the joints can be
remade satisfactorily and easily with the help of semi skilled
labour. Where compressible gaskets are used, stoppers/
runners shall be provided to prevent over compression.

(K) Suitable guides shall be provided for positioning the various


parts during assembly or dismantling. Adequate space shall
be provided between the cores and windings assembly and
the bottom of the tank for collection of any sediment.

(L) The design of the tank, lifting lugs shall be such that the
complete transformer assembly filled with oil can be lifted with
the use of these lugs without any damage or distortions.

(M) For the complete transformer we have clearly brought out our
requirement of various types of valves in Annexure V enclosed
brings out details of type, size and quantity of valves which are
to be provided at various locations. This requirement has to
be confirmed by the Bidders without any deviation.

(N) It may be noted that all gasketted joints shall be grooved one
using ‘O’ rings of nitrile rubber or better, such as the joints
between bushing turret and bushing flange, inspection covers
of inspection windows and all other openings provided for the
purpose of inspection of internal parts of the transformer etc.
The main bell tank gasket between upper tank and bottom

MPPTCL/TECH/PROC/07/JULY15 11 of 105
Volume-II, Part-7

tank shall be single piece ‘O’ ring cord/gasket of nitrile rubber


or material of better quality. The gasketting arrangement shall
be grooved one with proper stopper to avoid over
compression. It is to be noted that one additional set of
gaskets shall be delivered by the bidder alongwith
transformer to replace the used gaskets at the time of
erection of the unit.
(O) One detachable bolted type mild steel (MS) ladder with anti-
climbing arrangement shall be provided. Ladder for climbing
up to & over top cover of power transformers shall be
mechanically sturdy enough to bear the load of healthy
maintenance staff without any shake/jerks. The arrangement
shall not be detached after erection and commissioning of the
unit, hence shall be provided with padlock locking arrangement
for anti-climbing device. On the upper top of the ladder,
provision for support shall be made. However, the
arrangement of the ladder shall be to purchaser’s approval.
Collapsible ladder shall not be acceptable to us. Also, suitable
mild steel (MS) ladder shall be provided for conservator tank.
(P) Suitable earthing bridge between upper and lower tank shall be
provided at least on two places each on HV & LV side and one
place on other both sides.
(Q) The thickness of transformer wheel base plate (roller
mounting) shall be 32 mm so as to avoid its bending during
dragging of transformer on rails .

11.2 Tank Cover


(a) The tank cover shall be sloped to prevent retention of rain
water and shall not distort when lifted.
(b) Inspection cover/man holes shall be provided as per Annexure-
IV.
(c) The tank covers shall be fitted with pockets at the position of
maximum oil temperature of MCR (Maximum Continuous
Rating) for inserting bulbs of oil and winding temperature
indicators. It shall be possible to remove these bulbs without
lowering the oil in the tank. The thermometer shall be fitted
with a captive sensor to prevent the ingress of water.
(d) Bushings, turrets, covers of inspection openings, thermometer,
pockets etc., shall be designed to prevent ingress of water into
or leakages of oil from the tank.
(e) All bolted connections shall be fitted with weather-proof, hot oil
resistant gasket in between, for complete oil tightness. If
gasket is compressible, metallic stoppers shall be provided to
prevent over-compression.
(f) A minimum of three nos. PRD shall be provided above
each phase winding.

MPPTCL/TECH/PROC/07/JULY15 12 of 105
Volume-II, Part-7

11.3 Undercarriage:
(a) The transformer tank shall be supported on a structural steel
base equipped with forged steel or cast steel single flanged
wheels suitable for moving the transformer completely filled
with oil.
(b) Jacking pads/steps shall be provided. It shall be possible to
change the direction of the wheels through 90 deg. when the
transformer is lifted on jacks to permit movement of the
transformer both in longitudinal and transverse direction.
(c) The track/rail gauge shall be 1676 mm along the longer side,
as well as along the shorter axis. However Rails shall be placed
perpendicular to the bushing line.
(d) Pulling eyes shall be provided to facilitate movement/pulling of
the transformers and these shall be suitably braced in a
vertical direction so that bending does not occur when the pull
has a vertical component.

11.4 Axles And Wheels:


(a) The transformers are to be provided with flanged bi-directional
wheels and axles. These shall be so designed as not to deflect
excessively to interfere with the movement of the transformer.
Wheels shall be provided with suitable bearings which shall be
rust and corrosion resistant. Fittings for lubrication shall also
be provided.
(b) Suitable locking arrangement along-with foundation bolts shall
be provided for the wheels to prevent accidental movement of
transformer. The locking arrangement shall be such that it can
be locked with plinth of transformer. The length of the
arrangement should be adequate to cover height of the rail. No
floating type locking arrangement shall be accepted.
(c) The wheels are required to swivel and they shall be arranged
so that they can be turned through an angle of 90 degrees
when the tank is jacked up to clear of rails. Means shall be
provided for locking the swivel movements in positions parallel
to and at right angles to the longitudinal axis of the tank (i.e.
longitudinal & transverse directions).
(d) To facilitate uniform distribution of transformer weight two
nos. props each on front & rear side along longer axis to be
provided.

11.5 Anti Earthquake/Transport Clamping Device:


(a) To prevent transformer movement during earthquake,
clamping device shall be provided for fixing transformer to the
foundation. The Bidder shall supply necessary bolts for
embedding in the concrete foundation. The arrangements shall
be such that the transformer can be fixed to or unfastened

MPPTCL/TECH/PROC/07/JULY15 13 of 105
Volume-II, Part-7

from these bolts as desired. The fixing of the transformers to


the foundations shall be designed to withstand seismic events
to the extent that a static co-efficient of 0.3g. applied in the
direction of least resistance to that loading will not cause the
transformer or clamping devices as well as bolts to be over
stressed..
(b) Locking arrangement to eliminate relative movement between
top yoke/active parts with the transformer tank shall be sturdy
enough to bear transport hazards taking in to account the poor
road conditions and also considering that road transportation
of transformer will not be on hydraulic trailers

11.6 Conservator Tank:


(a) The conservator tank shall be of minimum thickness of 8 mm
and it shall have adequate capacity between highest and
lowest visible levels to meet the requirement of expansion of
the total cold oil volume in the transformer and cooling
equipment from minimum ambient temperature to 100oC.
(b) The conservator tank shall be bolted into position so that it can
be removed for cleaning purposes.
(c) Magnetic oil gauge (MOG) & prismatic oil level gauge
having three overlapped windows on one side of
conservator and on opposite side of conservator, plain oil
gauge with three overlapped windows shall be provided
to indicate oil level inside the conservator at each
location. Proper arrangement to ensure visibility of oil level
from ground be also ensured .
(d) Conservator shall be provided in such a position as not to
obstruct the electrical connections to the transformer.
(e) In order to avoid congestion and to facilitate operation and
maintenance activities, the main conservator and OLTC
conservator shall be provided on opposite sides of the main
tank. Further, there shall be adequate space for manual
operation of OLTC.
(f) Separate conservator tank shall be provided for OLTC.
(g) The size of the conservator shall be so designed as to
accommodate approximately 10% volume of total quantity of
oil in the transformer.
(h) Suitable arrangement shall be made for providing a foot rest
with easy & access arrangement to facilitate maintenance/
operation at top of the conservator, on magnetic oil level
gauge and buchholz relay.
(i) The design of conservator shall be such that the air is not
trapped between air cell and main conservator. Suitable
magnetic oil level gauge and prismatic glass shall also be
provided for OLTC Conservator.

MPPTCL/TECH/PROC/07/JULY15 14 of 105
Volume-II, Part-7

11.7 Tank Earthing Arrangement : Two earthing pads complete with


two number tapped holes M10 bolts plain and spring washer suitable for
connection to 50X8 mm GI flat shall be provided each at position close to two
diagonally opposite bottom corners of tank. Earthing strips up to the ground
level and its connection with station earth pit shall be provided by the Bidder.

11.8 Pressure Relief Device : A minimum of 3 (three) number of


pressure relief devices of reputed make and reliable quality shall be
provided on each transformer and these shall be mounted preferably
on the tank cover above each phase winding. Bidders must submit
calculations to prove that the no and capacity of pressure relief device with
location of each PRV provided on the transformer will adequately meet our
requirement. The quantity of three numbers is on the basis that two numbers
will be required as per design calculation and one number additional PRD shall
be provided from the point of view of additional safety.

Constructional and design details of pressure relief device must be


furnished and it should be proved by calculation that the size and operating
pressure setting of pressure relief device is adequate, considering the rating
of the transformer and quantity of oil in the transformer. Furnishing of this
information is a must. These PRD's shall be of sufficient size for rapid release
of any pressure that may be generated in the tank and which may result in
damage to the equipment. The device shall operate at a static pressure of less
than the hydraulic test pressure of transformer tank. It shall be mounted
directly on the tank. One set of electrically insulated contacts shall be
provided for alarm & tripping along-with the recommendations.

11.9 Relays:

11.9.1 Buchholz Relay : A double float type Buchholz relay along with
suitable moulded type cover to avoid ingress of moisture/ rain water shall be
provided. All the gases evolved in the transformer shall collect in this relay.
The relay shall be provided with a test cock suitable for a flexible pipe
connection for checking its operation and for taking gas sample. A copper or
stainless steel tube, shall be connected from the gas collector to a valve
located about 1200mm above ground level to facilitate sampling of gas while
the transformer is in service. The device shall be provided with two electrically
independent ungrounded contacts, one for alarm on gas accumulation and the
other for tripping on sudden rise of pressure. The contacts of relay shall be
properly housed, sealed and gasketted to make the arrangement water proof.
Entry of moisture/water in the contact chamber needs to be eliminated. Cable
entry to terminal box of buchholz relay should be made through bottom of
relay.

11.9.2 Oil Surge Relay (OSR) : From our past experience, it is found that
undesired tripping of Power Transformers is occurring on oil surge relay
(OSR)and Buchholz relay operation actuating due to accumulation of water
inside relay pockets. The water accumulation takes place through entry point
of cable gland. In view of above, the design and placement of Alarm & trip

MPPTCL/TECH/PROC/07/JULY15 15 of 105
Volume-II, Part-7

contact assembly of OSR and Buchholz Relay should be improved to take care
of the following requirements:

(a) The cable entry to terminal box of OSR should be made through bottom
of relay. Also the OSR relay should be protected from rain water by
providing proper cover on it.

(b) In order to ensure exit/drainage of accumulated water from inside the


relay, a fine hole should be made in terminal box of relay.

Note : The Bidders shall ensure that the compartments housing relay
contacts of Pressure Relief Valve , Buchholz Relay and Oil Surge Relay are
made absolutely water and vermin proof. The compartment housing contacts
of OSR,PRV and Buchholz Relay shall be tested for water proof at the time of
inspection and effectiveness of water proofing shall be demonstrated at the
time of inspection. This should be noted carefully by the Bidder and
specifically confirmed in their bid.

11.10 Temperature Indicator :

11.10.1 Oil Temperature Indicator (OTI) :Transformers shall be provided


with a 150mm dial type thermometer with maximum pointer for top oil
temperature indication. The thermometer shall have adjustable two
electrically isolated heavy duty alarm and trip contacts, maximum reading
pointer and resetting device mounted in the Fan control cubicle (FCC). A
temperature sensing element suitably located in a pocket on top oil shall be
provided. This shall be connected to the OTI by means of capillary tubing.
Accuracy class of OTI shall be plus or minus 1.0% or better. The OTI shall be
provided with anti vibration mounting.

11.10.2 Winding Temperature Indicator (WTI)


(a) WTI for measuring the winding temperature of the windings
shall be provided. It shall comprise of the following
(i) Temperature sensing element.
(ii) Image coil.
(iii) Auxiliary CTs, if required, to match the image coil, shall
be provided.
(iv) 150mm dia local indicating instrument with maximum
reading pointer mounted in FCC/marshalling box and with
four adjustable electrically isolated heavy duty contacts
(two for control of cooling equipment, one for high
winding temperature alarm and other for trip) shall be
provided. The WTI shall be provided with anti vibration
mounting.
(v) Calibration device.
(b) In addition to the (a) above, repeater dial of WTI for each
winding shall be provided for Remote winding temperature
indication. It shall be suitable for flush mounting on RTCC

MPPTCL/TECH/PROC/07/JULY15 16 of 105
Volume-II, Part-7

panel. A precision potentiometer mounted inside the case shall


function as a transmitter to operate a repeater for RWTI. The
transmitter shall be directly connected to the repeater.
(c) Auxiliary supply, if required in RTCC panel for RWTI, shall be
220V or 110V DC only.
(d) Accuracy class of WTI as well as RWTI shall be plus or minus
1.0% or better.
(e) Any special cables required for shielding purpose for
connection between cooler control cabinet and remote winding
temperature indicator control circuit shall be in Bidder’s scope
of work.
(f) WTI CT ratio shall be embossed on secondary winding terminal
box.
Note Some of the manufacturers have a practice to directly install winding
temperature indicator (WTI) and oil temperature indicator (OTI) on
the body of the transformer in open. This is not acceptable & it is
obligatory on the part of the Bidders to enclose OTI & WTI and all
such accessories in a separate Fan Control Cubicle (FCC) cum
Marshalling Box .

11.11 Core:
a) The core shall be constructed from high grade, non- ageing,
low loss, Cold Rolled Super Grain oriented (CRGO) silicon steel
laminations of HI-B grade steel or better. All stipulations under
clause 4.4 should be considered while selecting material of
core. Interlamination resistance shall be as per BS601
Part 5 method of July 1973. The Bidder shall furnish the
details of steel laminations i.e. type alongwith hysterisis
loss curve (B-H curve) etc.
(b) After being sheared, the laminations shall be treated to remove
all burrs and shall be re-annealed to remove all residual
stresses.
(c) The design of the magnetic circuit shall be such as to avoid
static discharges, development of short circuit paths within
itself or to the earthed clamping structure and production of
flux component at right angles to the plane of laminations
which may cause local heating.
(d) The core shall be provided with lugs suitable for lifting
complete core & coil assembly of transformer.
(e) Core Belting : The core shall be rigidly clamped by belting to
ensure adequate mechanical strength. Core and winding shall
be capable of withstanding the vibrations & shock during
transport, installation, service and adequate provision shall be
made to prevent movement of core & winding relative to tank
during these conditions. The location, size and material of
belting shall be clearly indicated in drawing which shall be
submitted with Bid. Bolted type core construction shall not
be acceptable.

MPPTCL/TECH/PROC/07/JULY15 17 of 105
Volume-II, Part-7

(f) All steel sections used for supporting the core shall be
thoroughly sand blasted after cutting, drilling and welding.
(g) Each core lamination shall be insulated with a material that will
not deteriorate due to pressure and hot oil.
(h) The insulation of core to bolts and core to clamps plates
shall be able to withstand a voltage of 2KV RMS for one
minute.
(i) The maximum flux density in any part of the core and yoke at
rated MVA, 110% voltage and (-) 4% frequency at any tap
shall not exceed 1.90 Tesla. The Bidder shall provide saturation
curve of the core material proposed to be used and
calculations to demonstrate that the core is not over fluxed
under stringent condition of transformer operation.
(j) Bidder will offer the core for inspection & approval by
the purchaser during the manufacturing stage. Bidder's
call notice for this purpose should be accompanied with
the following documents, as applicable, as a proof
towards use of prime core material.
i) Invoice of the supplier
ii) Mill's Test Certificate
iii) Packing List
iv) Bill of lading
v) Bill of entry certificate by customs.

(k) Core material shall be directly procured either from the


manufacturer or through their accredited marketing
organization of repute and not through any agent.
(l) Bidder should have in-house Core Cutting facility for proper
monitoring & control on quality and also to avoid any
possibility of mixing of prime material with defective/second
grade material. However, in case if in house core cutting
facility is not available at manufacturers works in that case
cutting from other sources shall also be accepted subject to
condition that manufacturer shall be solely responsible for
proper monitoring & control on quality and also to avoid any
possibility of mixing of prime material with defective/second
grade material.
(m) Oil ducts shall be provided wherever necessary to ensure
adequate cooling. The winding structure and major insulation
shall not obstruct the free flow of oil through such ducts.
Where the magnetic circuit is divided into pockets by cooling
ducts parallel to the plane of laminations or by insulating
material above 0.254 mm. Thick, tinned copper strip bridging
pieces shall be inserted to maintain electrical continuity
between pockets. The design of the magnetic circuit shall be
such as to avoid static discharge development of short circuit
path within itself or to the earthed clamping structure and
production of flux components at right angles to the plane of
the laminations which may cause local heating.

MPPTCL/TECH/PROC/07/JULY15 18 of 105
Volume-II, Part-7

(n) Core shall not directly rest on the bottom metal sheet of
transformer tank. Around 3 mm or more free space for oil
insulation shall be made between the core and bottom sheet of
transformer tank. A 5 mm FRP Insulating sheet shall be
provided to take care of core earthing due to accidental
slippage of stampings. Also in addition to this extra
insulation thickness of 5 mm or more FRP sheet be
provided at the bottom of resting shoes of end frame
with proper fixing arrangement to avoid accidental
slippage, damages etc.

11.12 Windings:
(a) The Bidder shall ensure that windings of all transformers are
made in dust proof, conditioned atmosphere. The Bidder shall
furnish the facilities available at their works alongwith the bid.
(b) The conductors shall be of electrolytic grade copper as per
relevant IS. The maximum current density for design of
transformers within specified limits of transformer losses shall
not exceed the limits of 300 amps per sq.cm.
(c) The insulation of transformer windings and connections shall
be free from insulating compounds which are liable to soften,
ooze out, shrink or collapse or be catalytic and chemically
active in transformer oil during service.
(d) Coil assembly and insulating spacers shall be so arranged as to
ensure free circulation of oil and to reduce the hot spot of the
winding. The conductor shall be transposed at sufficient
intervals in order to minimize eddy currents and equalize the
distribution of currents and temperature along the winding.
(e) The LV winding should withstand short circuit faults/forces of
the transformer upto the prescribed fault levels on HV & LV
sides against mechanical and thermal stresses.
(f) Best insulating material shall be used and compression of the
windings after drying out shall be carried out at a pressure
exceeding one and a half to twice the force which can occur in
the transformer; to impart greater mechanical strength to the
windings against heavy short circuit stresses.
(g) The windings shall be so designed that all coil assemblies of
identical voltage ratings shall be interchangeable and field
repairs to the windings can be made readily without special
equipment. The coils shall be supported between adjacent
sections by insulating spacers, and the bracings and other
insulation used in the assembly of the winding shall be
arranged to ensure free circulation of the oil to reduce hot
spots in the windings.
(h) The coil insulation shall be treated with suitable insulating
varnish or equivalent compound wherever necessary to
develop the full electrical strength of the winding. All materials
used in the insulation and assembly of the winding shall be

MPPTCL/TECH/PROC/07/JULY15 19 of 105
Volume-II, Part-7

insoluble, non-catalytic and chemically inactive in the hot


transformer oil and shall not soften or otherwise be adversely
affected under the operating conditions.
(i) All threaded connections shall be provided with locking
facilities. All leads from the winding to the terminal connectors
and bushings shall be rigidly supported to prevent injury from
vibration. Guide tubes shall be used where practicable.
(j) Windings shall be subjected to a shrinkage treatment before
final assembly so that no further shrinkage occurs during
service. Adjustable device shall be provided for taking up any
possible shrinkage of coils in service. After shrinkage process,
the windings shall be clamped securely in place so that they
will not be displaced or deformed during short circuits. The
assembled core and windings shall be vacuum-dried and
suitably impregnated before removal from the treating tank.
The copper conductors used in the coil structure shall be best
suited to the requirements and all permanent current carrying
joints in the windings and the leads shall be crimped or brazed
preferably by high frequency brazing system and shall be
finalized at the time of drawing approval.
It is observed that many manufacturers are using sectored
clamping arrangement at top as well as bottom for clamping of
the windings. This type of arrangement is considered to be not
suitable for EHV grade power transformers. In this regard, it
may be noted that both top & bottom clamping rings to be
provided for clamping of windings shall be of one piece single
ring. The top & bottom clamping rings should be of
minimum thickness 60 mm thk with proper safety
margins based on design and shall be in one piece to
make the clamping arrangement sturdy. Sectored
pressure/clamping rings are not acceptable. The single
pressing/clamping ring shall be provided with adequate
number of pressure/jacking points as per design. Since
sectored ring arrangement shall not be accepted hence
bidder should ensure and confirm this specific
requirement in the technical questionnaire.

(k) Bidder will offer the Copper and insulating material for
windings for inspection & approval by the purchaser during the
manufacturing stage. Bidder's call notice for the purpose
should be accompanied with the following documents, as
applicable, as a proof towards use of prime Copper and
insulating material for windings .
i) Invoice of the supplier
ii) Mill's Test Certificate
iii) Packing List
iv) Bill of lading
v) Bill of entry certificate by customs.

MPPTCL/TECH/PROC/07/JULY15 20 of 105
Volume-II, Part-7

(l) Core, Copper and insulating material for windings shall be


directly procured either from the manufacturer or through their
accredited marketing organisation of repute and not through
any agent.
(m) Certificate : Supplier shall provide purchaser details of
procurement of raw materials i.e., core, insulation & copper.
Supplier shall also record a certificate as under :
" CERTIFICATE "

It is certified that the Transformer shall be


manufactured by --------- (Name of manufacturer) out of
the core, insulating and winding material procured as per
details indicated in specification. We are agreeable to
undertake third party inspection of Transformer during its
manufacture or of raw materials, at the sole discretion of
MPPTCL without any extra cost.
If at any stage it is found that the transformer is not
manufactured out of the raw material indicated
specification, the transformer shall be liable for rejection by
MPPTCL and transformer shall be replaced by (name of
manufacturer) at no extra cost to MPPTCL.
Signature of Authorised
Signatory with Seal of manufacturer

(o) The Purchaser also reserves the right to carry out stage
inspections at other stages also, for which advance intimation
shall be given and all necessary cooperation shall be rendered
by the supplier.

11.13 Bushings :

(a) The electrical & mechanical characteristics of bushings shall be


in accordance with IS-3347 & IS-2099 ( latest version ) & IEC
60137(2008 or latest version).

(b) The bushings shall have high factor of safety against leakage
to ground and shall be so located as to provide adequate
electrical clearances between bushings and also between the
bushings and grounded parts. Bushings of identical
voltage rating shall be of similar BCT and inter
changeable. All bushings shall be equipped with suitable
terminals of approved type and size and all external current
carrying contact surfaces shall be adequately silver plated. The
insulation class of the high voltage neutral bushing shall be
properly coordinated with the insulation class of the neutral of
the high voltage winding.

(c) All main winding and neutral leads shall be brought out
through outdoor type bushings which shall be so located that

MPPTCL/TECH/PROC/07/JULY15 21 of 105
Volume-II, Part-7

the full flashover strength will be utilized and the adequate


phase clearance shall be realized.

(d) Each bushing shall be so coordinated with the transformer


insulation that all flashovers will occur outside the tank.

(e) All porcelain used in bushings shall be of the wet process,


homogeneous and free from cavities or other flaws. The
glazing shall be uniform in color and free from blisters, burns
and other defects.

(f) (i) For 33KV winding & neutral , the bushing shall be of OIP
condenser of 72.5KV class of draw rod type/solid stem
type.
(ii) The bushings of 145 KV class shall be of OIP condenser of
draw rod type (DR) only.
(iii) Tan-delta of all bushings shall be 0.005 (max.)during
testing at manufacturer’s works.

(g) All bushings shall have puncture strength greater than the dry
flashover value.

(h) Main winding terminals shall be solder-less terminals and shall


be of the type and size specified.

(i) The spacing between the bushings must be adequate to


prevent flashover between phases under all conditions of
operation. The clearances shall be as follows :

1min. Clearance
Impulse Power in mm
S. Nominal Voltage Creepage
Current Withstand Frequency
N System Class Of Distance
Rating Voltage withstand Ph to Ph to
o Voltage Bushing in mm
(Kvp) Voltage Ph. E
Kv(rms)
1 132KV 145KV 1250A 650 275 3625 1430 1270
2 33KV 72.5KV 1250A 325 140 1813 700 660

The Bidders are required to confirm clearances and no change/


reduction in clearances shall be acceptable. The clearances
shall be clear distances in air after accounting for
clamps/connectors dimensions to be mounted on the stud of
bushings.
(j) Special adjustable arcing horns shall be provided for the HV
bushings. For 72.5KV class bushings, arcing horns are not
required.
(k) The Bidder is requested to furnish the guaranteed withstand
voltage for the above and also furnish a calibration curve with
different settings of the coordination gap to the purchaser to
decide the actual gap setting. Bidder's recommendations are
also invited in this respect.

MPPTCL/TECH/PROC/07/JULY15 22 of 105
Volume-II, Part-7

(l) The bushings shall be capable of withstanding without injury


the electrical, thermal and mechanical effects of external short
circuits. The 145 KV bushings shall be rated for short time
thermal current rating of 40 KA for 3 seconds and 72.5 KV
Bushings, for 31.5KA for 3 seconds.
(m) All the transformers covered under this specification shall be
utilized in heavily polluted atmosphere. In view of this the
Bidders while offering prices for the transformers against this
contract may please note that the offer should be made out
based on the creepage for the bushings @ 25mm per KV based
on the voltage of 72.5KV/145KV. Thus in the quoted prices of
transformer cost of bushings should be included based on a
creepage distance of 25mm per KV.
(n) All O.I.P. Condenser bushings shall be provided with :
(i) Oil level gauge.
(ii) Oil filling plug and drain valve, if not hermetically sealed.
(iii) Tap for capacitance/tan delta test.
(o) The bushings with current transformers are specified, hence
the bushings shall be removable without disturbing the current
transformers.
(p) Porcelain used in bushing manufacture shall be homogenous,
free from laminations, cavities and other flaws or imperfections
that might affect the mechanical or dielectric quality and shall
be thoroughly vitrified tough and impervious to moisture.
Glazing of porcelain and bushing shall be of uniform brown
color free from blisters and burrs.
(q) Bushing turrets shall be provided with suitable vent pipes
which shall be connected to route any air/gas collection
through the Buchholz relay.
(r) For Bushings of all voltage class, the arrangement for
connection of winding/neutral terminal shall be indicated .
(s) From the end point of the condenser of the bushing which will
protrude inside the transformer OR the bottom termination
point of bushing, sufficient clearance should be available so
that in case any other make bushing is installed problem in this
regard may not arise. Maximum length of condenser portion,
which can be easily accommodated, should be clearly indicated
by the Bidder.
(t) The LV take off arrangement within the transformer is of
utmost importance hence due care shall be taken while
providing this arrangement inside the transformer tank. The
connecting lug of LV winding with the bushing bottom terminal
pad should match with the current rating of the bushing. The
size of the LV winding lug shall be of suitable rating to match
with the maximum load current of the transformer to be fed
through extreme tap of OLTC meeting requirements of IS-

MPPTCL/TECH/PROC/07/JULY15 23 of 105
Volume-II, Part-7

6600. In this regard, the clamping arrangement of LV


winding with two lugs having two holes with two hole
terminals on counter part of the bushing pad are not
acceptable. In case of such arrangement, it will have to
be ensured that the counter part of winding lead/lug i.e.
bushing terminal is with four holes or vice versa. Similar
arrangement shall be ensured for termination of neutral
lead on neutral bushing pad.
(u) Size of turret for particular rating of bushing should be inline
with requirements specified by the bushing supplier in respect
of min dia. & lower insulation arcing distance etc.

11.14 Bushing Current Transformers:


(a) Current transformers shall comply with IS:2705.
(b) One no. bushing CT of Ratio 200/1 on each phase of HV
winding & one no. CT of Ratio 800/1 on each phase of LV
winding i.e 3 nos for HV & 3 nos for LV winding, one no.
bushing CT of Ratio 200/1 for HV neutral and 800/1 for LV
neutral shall be provided for each outdoor Transformer.
(c) It shall be possible to remove turret mounted CTs from the
transformer tank without removing the tank cover. Necessary
precaution shall be taken to minimize the eddy currents and
local heat generated in the turret.
(d) All secondary leads shall be brought to a terminal box near
each bushing. These terminals shall be wired out to cooler
control cabinet using separate cables for each core.
(e) For the thermal image coil of winding temperature indicator,
‘CT’ with suitable ratio and class may be used.

11.15 Terminal Marking : The terminal marking and their physical


position shall be in accordance with IS:2026.

11.16 The positioning of HV & LV bushings shall be such that skew


jumpering is avoided. The middle phase primary & secondary bushing center
line shall be parallel to side axis of the transformer body.

12.0 EARTHING ARRANGEMENT :

12.1 NEUTRAL EARTHING ARRANGEMENT: The neutral terminal of the


star connected HV/ LV winding shall be brought up to the ground level
through two tinned copper flat strips of size 50x6mm which shall be supported
on transformer tank horizontal/ vertical by porcelain insulators of adequate
voltage class. The number of insulators shall be sufficient to provide a
mechanically sturdy arrangement. Necessary mechanical supports on the
tank for mounting of the insulators shall be made. The KV class rating of
insulators shall commensurate with the rating/ KV class of neutral design. It
may be ensured that connection of the neutral strips to neutral bushings at
one end shall be made using a terminal connector suitable for connection to
the neutral bushing terminal and to receive 2x50x6 mm tinned copper strips

MPPTCL/TECH/PROC/07/JULY15 24 of 105
Volume-II, Part-7

on the other side. The connection between the bushing and transformer’s
earth pit shall be through 2x50x6 mm tinned copper strips single run without
any joint connection/brazing/ welding etc. In case of problem in availability of
single run tinned copper strips, it may be accepted with single joint. However,
joint to be provided shall be subject to approval of purchaser. The other end
of the earth connection to the earth pit shall also be through terminal
connector suitable to receive 2x50x6 mm copper strips at one end and to
receive MS flat and / or twin ACSR zebra conductor on the other end. The
length of the copper strips shall be suitable for providing a joint less
connection between transformer neutral and earth pit and details in this
regard shall be intimated to the successful Bidder based on
transformer/substation layout design. A typical arrangement is shown in drg.
No “MPPTCL/40MVA/02” of this specification for neutral earthing.

12.2 CORE EARTHING ARRANGEMENT : The bidder should note our


requirement in this regard very clearly. It is required to bring out leads from
core, end frame and tank to the top of the transformer through only three
insulated bushings. The arrangement shall be housed in a box at the top cover
of transformer tank with provision for interconnection between the studs of
bushings. The bushing housing shall have a suitable cover with gasket to make
the arrangement waterproof. A clear marking (engraved/punched) shall
be made to indicate that the housing contains core/end frame/ tank
earthing arrangement. Please note that stickers/flags/tags/painted
marking for identification shall not be accepted. A typical sketch of
general arrangement needed by purchaser is shown in drawing no.
MPPTCL/40MVA/03 of this specification. Arrangement shall be such that even
after removal of connections, oil shall not leak. Removable shorting strips
between the three bushing shall be provided. It may be noted that internal
earthing of any nature between core and End frame should not be provided.
Earthing at site shall be done by interconnecting the three bushings through
shorting strips. This arrangement is to facilitate checking of multiple core
earthing in the transformer.

It may be noted that :


a) any alternative arrangement is not acceptable and therefore bidder
must confirm provision of three bushings as desired above.
b) Once transformer reaches site, before unloading from the trailor the
position of core earthing shall be checked and in case any problem of
multiple core earthing is observed, delivery of Transformer will not be
taken.

The insulated cable to be used for core to Bushing connection & end
frame to Bushing connection should be of good quality with proper
grounding arrangement. The size and number of strands of cable shall
be subject to purchaser’s approval.

MPPTCL/TECH/PROC/07/JULY15 25 of 105
Volume-II, Part-7

13.0 AUXILIARY POWER SUPPLY FOR OLTC, COOLER CONTROL


AND POWER CIRCUIT

13.1 Duplicate (Two) auxiliary power supplies of 0.4 KV, three phase,
four(4) wire shall be provided by the purchaser at cooler control cabinet and
for OLTC drive.

13.2 All loads shall be fed by one of the two feeders through an
electrically interlocked automatic transfer switch housed in the cooler control
cabinet, for tap changer control and cooler control circuits.

13.3 Design features of the transfer switch shall include the following :
i) Provision for the selection of one of the feeders as normal
source and other as standby.
ii) Upon failure of the normal source, the loads shall be
automatically transferred after an adjustable time delay to the
standby source.
iii) Indication to be provided at cooler control cabinet & RTCC for
failure of normal source and for transfer to standby source and
also for failure to transfer.
iv) Automatic re-transfers to normal source without any
intentional time delay following re-energisation on the normal
source.
v) Both the transfer & re-transfer shall be dead transfers and AC
feeders shall not be paralleled at any time.

13.4 AC feeder shall be brought to the OLTC cabinet (Cooler Control


Cabinet) by the Bidder, after suitable selection at cooler control cabinet. The
Bidder shall derive AC power for control circuit from the AC feeder as
mentioned above by using appropriately rated dry type transformers. If the
control circuit is operated by DC supply then suitable converters to be
provided by the Bidder to be operated from AC Power source.

13.5 Necessary isolating switches and HRC fuses shall be provided at


suitable points as per approved scheme of purchaser.

14.0 TAP CHANGING EQUIPMENT :

14.1: GENERAL REQUIREMENT

a) OLTC gear shall be motor operated for local as well as remote operation.
An external hand wheel/handle shall be provided for local manual
operation. This hand wheel/handle shall be easily operable by a man
standing at ground level.

(b) Arrangement shall be made for securing and padlocking the tap changer
wheel in any of the working positions and it shall not be possible for
setting or padlocking the wheel in any intermediate position. The
arrangement shall be such that no padlock key can be inserted unless all
contacts are correctly engaged and switch set in a position where no open
or short circuit is possible. An indicating device shall be provided to show
the tap in use.

MPPTCL/TECH/PROC/07/JULY15 26 of 105
Volume-II, Part-7

(c) The design of OLTC shall be on the principle of “Constant Flux Design
“(CFVV) wherein HV (132KV ) voltage would be varied in the range of
(+)5 % to (-)15 % in steps of 1.25 % so as to provide constant voltage
of 33 KV on LV side. While through current rating of OLTC shall be based
on cl.2.3.2 of IS 8478,the purchaser desires to obtain OLTC with higher
voltage and current rating from the point of view of better performance.
In view of this, the bidder shall offer OLTC for 40 MVA transformer
suitable for rated voltage and rated current as mentioned in the following
table :
Rating of OLTC
OLTC on
Transformer Minimum Tap Range
Winding Voltage
Rating Current (In steps of
(HV) Rating
Rating 1.25%)
132 KV, 40
132KV 66KV/132KV* 300 Amp. (+)5% to (-)15%
MVA

*Suitable for 132KV neutral end

d) The OLTC motor should be capable of smooth and trouble free operation
with supply voltage variation of 0.415KV +10% & -25%.

14.2 ON LOAD TAP CHANGING GEAR (OLTC):

(a) The details of the method of diversion of the load current during tap
changing, the mechanical construction of the gear and the control
features for OLTC gear alongwith detailed drawings on the inner view and
the arrangement of connections shall be submitted with the Bid.
Information regarding the service experience on the gear and a list of
important users shall also be furnished. The tap changer shall change the
effective transformation ratio without producing phase displacement.

(b) The current diverting contacts shall be housed in a separate oil chamber
not communicating with the oil in main tank of the transformer.

(c) The contacts shall be accessible for inspection without lowering oil level in
the main tank and the contact tips shall be replaceable.

(d) The Bidder shall indicate the safeguards employed to take care of harmful
arcing at the current diverting contacts in the event of operation of the
OLTC gear under overload conditions (overloading capability as per IS
6600) of the transformer. Necessary tools and tackles shall be provided
alongwith main supply for maintenance of OLTC gear.

(e) The OLTC oil chamber shall have oil filling and drain valves, oil sampling
valve, relief vent and oil level gauge/glass. It shall also be fitted with an
oil surge relay. For accommodating oil expansion of OLTC a separate
conservator tank shall be provided.

MPPTCL/TECH/PROC/07/JULY15 27 of 105
Volume-II, Part-7

(f) The diverter switch or arcing switch shall be designed so as to ensure that
its operation once commenced shall be completed independently of the
control relays or switches, failure of auxiliary supplies etc. To meet any
contingency which may result in incomplete operation of the diverter
switch, adequate means shall be provided to safeguard the transformer
and its ancillary equipments.

(g) Drive mechanism chamber shall be mounted on the tank in accessible


position. It should be adequately ventilated and provided with anti
condensation metal clad heaters. All contactors, relay coils and other
parts shall be protected against corrosion, deterioration due to
condensation, fungi etc.

(h) The control feature shall provide the following :

i) LOCAL-REMOTE selector switch mounted in the local control cubicle


shall switch control of OLTC for lower/ raise functions in local or
remote mode as selected.

ii) The LOCAL-REMOTE selector switch shall have at-least two spare
contacts per position which are closed in that position but open in
the other position.

iii) A RAISE-LOWER CONTROL SWITCH shall be provided in the local


control cubicle. The switch shall be spring loaded to return to the
Centre "OFF" position and shall require movement to the RIGHT to
raise the voltage of the transformer. Movement to the left shall
lower the voltage. Alternatively push button type arrangement of
standard design may be provided.

iv) An OFF-ON tap changer control switch shall be provided in the OLTC
local control cabinet of transformer. The tap changer shall be
inoperative in the OFF position. Also the OFF-ON switch shall have
atleast one spare contact per position which is closed in that position
but open in the other position.

v) Operating mechanism for on load tap changer shall be designed to


go through one step or tap change per command. Subsequent tap
changes shall be initiated only by a new or a repeat command.

vi) On load tap changer shall be equipped with a time delay in complete
STEP alarm consisting of a normally open contact which closes, if
the tap changer fails to make a complete tap change. The alarm
shall not operate for momentary loss of auxiliary power.

vii) The selsyn units or approved equivalents shall be installed in the


local OLTC control cabinet to provide tap position indication for the
transformer. Complete mounting details shall be included with
approved diagram.

viii) Transformer load tap changer shall be equipped with a fixed resistor
network capable of providing discrete voltage steps for input to the
supervisory system. Any other approved / established design for
remote indication of tap position shall also be acceptable.

MPPTCL/TECH/PROC/07/JULY15 28 of 105
Volume-II, Part-7

(i) Limit switches shall be provided to prevent overrunning of the mechanism


and in addition, a mechanical stop shall be provided to prevent over-
running of the mechanism under any condition.

(j) Limit switches may be connected in the control circuit of the operating
motor provided that a mechanical-de-clutching mechanism is
incorporated.

(k) Thermal device or other means shall be provided to protect the motor
and control circuit. All relays, switches, fuses etc. shall be mounted in the
drive mechanism chamber and shall be clearly marked for the purpose of
identification.

(l) A permanently legible lubrication chart shall be fitted within the driving
mechanism chamber.

(m) Any "DROP DOWN" tank associated with the tap changing apparatus shall
be fitted with guide rod to control the movements during lifting or
lowering.

(n) A five digit counter shall be fitted to the tap changing equipment to
indicate the number of operations performed.

(o) All relays and operating devices shall operate correctly at any voltage
between the limits specified.

(p) It shall not be possible to operate the electric drive when the manual
operating gear is in use.

(q) It shall not be possible for any two controls to be in operation at the
same time.

(r) The equipment shall be suitable for supervisory control and indication
with make before break multi-way switch, having one potential free
contact for each tap position. This switch shall be provided in addition to
any other switch/switches which may be required for remote tap position.

(s) Operation from the local or remote control switch shall cause one tap
movement only until the control switch is returned to the off position
between successive operations.

(t) All electrical control switches and the local operating gear shall be clearly
labeled in a suitable manner to indicate the direction of tap changing.

(u) Transfer of source failure of one AC supply shall not affect tap changing
operation.

(v) For the purpose of operation of OLTC, based on design of manufacturer,


transition resistor could be used. However, no component of OLTC
including transition resistor shall be housed inside main transformer tank.
The design of the transition resisters should be liberal to ensure
suitability during tap change operation at rated current including over
loading capability and system short circuits.

MPPTCL/TECH/PROC/07/JULY15 29 of 105
Volume-II, Part-7

(w) The location and design of OLTC shall be such that in the event of any
repair / maintenance , it should be possible to take out various parts
from the OLTC and other accessories and fittings mounted on the
transformer particularly equalizing pipes etc do not infringe /obstruct.

14.3 MANUAL CONTROL : The cranking device for manual operation of the
OLTC gear shall be removable and suitable for operation by a man standing
on ground level. The mechanism shall be complete with the following :

i) Mechanical tap position indicator which shall be clearly visible to the


person operating tap changer manually at the transformer.

ii) A mechanical operation counter.

iii) Mechanical stoppers to prevent over-cranking of the mechanism beyond


the extreme tap positions.

iv) The manual control considered as back up to the motor operated load tap
changer control shall be interlocked with the motor to block motor start-
up during manual operation. The manual operating mechanism shall be
labeled to show the direction of operation for raising the voltage and
vice-versa.

14.4 ELECTRICAL CONTROL This includes Local Electrical control and


Electrical remote control from remote control panel. The control circuits shall
have the following features:

(i) An interlock to cut off electrical control automatically upon recourse


being taken to the manual control in emergency.

(ii) Reinforcement of the initiating impulse for a tap change, ensuring a


positive completion once initiated to the next (higher or lower) tap.

(iii) Step-by-step operation ensuring only one tap change from each tap
changing impulse and lock-out of the mechanism if the control switch (or
push button) remains in the "Operate Position".

(iv) An interlock to cut-out electrical control when it tends to operate the


gear beyond either of the extreme tap positions.

(v) An electrical interlock to cut-off a counter impulse for reverse step


change being initiated during a progressing tap change and until the
mechanism comes to rest and resets circuits for a fresh position. Suitable
interlocks shall be provided to prevent operation of OLTC beyond
extreme tap with a mechanical/electrical lockable switch.

(vi) Protection apparatus, considered essential by the Bidder according to


specification.

14.5 REMOTE ELECTRICAL GROUP CONTROL The OLTC control scheme


offered shall have provision of remote electrical group control during parallel
operation of transformers. This is in addition to independent control of OLTC.

(i) A four position selector switch having MASTER, FOLLOWER,


INDEPENDENT and OFF position shall be provided in the remote OLTC

MPPTCL/TECH/PROC/07/JULY15 30 of 105
Volume-II, Part-7

control panel for each transformer. This shall be wired to enable operator
to select operation of OLTC in either Master, Follower or Independent
mode.

(ii) Out of step relays with timer contacts shall also be provided to give
alarm and indication in case of tap positions in all the transformers under
group control being not in same position.

(iii) Master Position : If the selector switch is in MASTER position, it shall


be possible to control the OLTC units in the FOLLOWER mode by
operating the controls of the MASTER unit Independent operation of the
units under FOLLOWER mode shall have to be prevented. However, the
units under independent mode will be controlled independently.

(iv) Follower Position : If the selector switch is in FOLLOWER mode,


control of OLTC shall be possible only from MASTER panel.

(v) Independent Position : In this position of Selector Switch, Control of


OLTC of individual unit only shall be possible.

14.6 LOCAL OLTC CONTROL CUBICLE The Auxiliary devices for electrical
control of the OLTC shall be housed in a weather proof cubicle. It shall be
complete with the following :

i) A circuit breaker/contactor with thermal overload devices for


controlling the AC auxiliary supply to the OLTC motor.

ii) Cubicle light with door switch.

iii) Space heaters to prevent condensation of moisture.

iv) Padlocking arrangement for hinged door of cabinet.

v) Cable terminal glands for power and control cables to the OLTC gear.

14.7 REMOTE TAP CHANGER CONTROL PANEL (RTCC)

Remote tap changer control panel to be supplied by the Bidder shall consist
of :

i) Actuating switch for electrical raise/lower control.

ii) Remote tap position indicator.(preferred digital type)

iii) Signal lamps for Tap changer in progress and Tap changer out of
step.

iv) Auxiliary devices for remote electric group control of OLTC.

v) Annunciation scheme with the following :

(a) Fan fail (for all fans individual windows).


(b) AC supply fail.
(c) Stand by fan fail.
(d) Stand by fan on.

MPPTCL/TECH/PROC/07/JULY15 31 of 105
Volume-II, Part-7

(e) OLTC motor over loaded.


(f) OLTC control supply fail.
(g) OLTC at extreme position i.e. lowest & highest voltage tap.
(h) Two spare windows.

vi) Indicating Devices : Following lamp indications shall be provided in


Remote tap changer control cubicle /panel

- Fan "ON", Fan "OFF"


- Cooling system "On Automatic Control".
- Cooling system "On Manual".
- Selector switch in auto or manual.
- 0.4 KV cooler supply auto changeover.
- Control supply failure main and standby.
- one potential free initiating contact for all the above indications
shall be wired independently to the terminal blocks of cooler
control cabinet exclusively for owner's use.

vii) Remote OTI with repeater unit.

viii) WTI repeater unit.

ix) Voltmeter for indicating HV & LV voltage.

x) Schedule of equipments for RTCC panel shall be as under:

1. Name plate – “remote OLTC and cooler control cubicle’’


2. Indicating lamp-“OLTC control supply on ’’ ( red)
3. Indicating lamp-“tap change in progress ’’ ( yellow)
4. Indicating lamp-“OLTC out of step’’ ( red)
5. Indicating lamp-“OLTC motor trip ’’ ( red)
6. Cooler mode selector (auto-off-on)
7. OLTC sequence selector switch.(OFF-INT-FOLL-MAST.)
8. Emergency stop push button for tap change operation. (red)
9. Auxiliary contactor for OLTC out of step monitoring.
10. Out of step timer.
11. Voltmeter for HV. (0-150 KV)
12. Remote oil temperature indicator.
13. Voltmeter for LV. (0-40 KV)
14. Terminal blocks.
15. Cubicle lamp.
16. Door switch.
17. HRC cartridge fuse holder with link for cubicle illumination circuit.
18. Neutral link.

MPPTCL/TECH/PROC/07/JULY15 32 of 105
Volume-II, Part-7

19. Earth bus.


20. HRC cartridge fuse holder with link for HV volt meter.
21. HRC cartridge fuse holder with link for LV volt meter..
22. HRC cartridge fuse holder with link for RWTI and ROTI circuit.
23. Selector switch for HV volt meter.
24. Selector switch for LV volt meter.
25. Remote winding temperature indicator.
28. “OLTC control switch’’
29. Tap position indicator (digital).

xi. a. HV digital Voltmeter of accuracy class 0.5 provided for indicating HV


voltage shall be scaled for voltage range 0-150 KV (phase to phase)
and shall be suitable for use with PT ratio 132KV/110 volt. The HV
digital voltmeter shall be precisely calibrated so as to indicate 132KV
Voltage on voltmeter scale corresponding to input voltage of 110 Volt
(phase to phase).

b. LV digital Voltmeter of accuracy class 0.5 provided for indicating LV


voltage shall be scaled for voltage range 0-40 KV (phase to phase)
and shall be suitable for use with PT ratio 33KV/110 volt. The LV
digital voltmeter shall be precisely calibrated so as to indicate 33KV
Voltage on voltmeter scale corresponding to input voltage of 110 Volt
(phase to phase).

c. Auxiliary supply required for operation of both HV & LV voltmeters


shall be of 110 /220 V DC.

Note:- The operating switches and devices in the RTCC panel are to
be provided at suitable height i.e. these should be accessible
to operator in standing conditions.

15.0 COOLING EQUIPMENT

15.1 The design shall take into account the following requirements
a) The oil cooling system of transformer shall be designed using
2x50% radiator banks. The arrangement shall be subject to
approval by the purchaser based on substation layout and
positioning of other neighboring switch yard equipments.
Coolers/radiators shall with stand pressure / vacuum conditions
specified for the tank. All coolers/ radiators shall be attached
and mounted on the transformer tank through header.
Cooler/radiators and header shall be tank supported
subject to specific approval from the purchaser.
b) Each radiator bank / block shall have its own set of cooling
fans, shut off valves, lifting lugs, top and bottom oil filling
valves, air release plugs, drain valves and if considered
necessary based on design thermometer pocket fitted with

MPPTCL/TECH/PROC/07/JULY15 33 of 105
Volume-II, Part-7

captive screw cap on the inlet and outlet, in line with valve
schedule as per Annexure-V.
c) Each radiator bank shall be provided with at least 20%
standby (spare)cooling fans. These spare fans shall be duly
mounted and shall also be wired up complete with required
protective devices and be identified with each radiator bank.
While working out number of spare fan for 20% additional
cooling per bank, if 20% quantity works out in fraction , the
spare fans to be provided shall be next whole number.
d) Cooling fans shall be designed to meet overloading
requirements as per clause 4.1 (b)
e) The exhaust air flow from cooling fan shall not be directed
towards the main tank in any case.
f) It is to be noted that mounting of cooling fans on
bottom of the radiator banks is not acceptable to us.
Cooling fans for each radiator bank shall be located so as to
prevent ingress of rain water. Each fan shall be suitably
protected by galvanised wire guard.
g) The cooler and its accessories shall preferably be hot dipped
galvanised or corrosion resistant paint shall be applied to it.
h) Each cooling fan shall be provided with starter thermal
overload and short circuit protection and also single phase
preventor.
i) Each radiator shall be provided with suitable lifting lugs and
shut off/air release/sampling valves as per Annexure-V. The
sheet thickness of radiator tube shall be of minimum of 1.2
mm.
j) Expansion joints, one each on top and bottom cooler pipe
connections as per ‘a’ above.
k) Air release device/plug and oil drain plug on oil pipe
connections.
l) The cooling Fans shall be mounted on separate foundation at
bottom of externally mounted radiator Banks. Mounting of
Cooling fans directly on Radiators or on transformer tank is not
acceptable . The radiator’s mounting arrangement is to be
indicated by the Bidder in his Bid.
m) Cooling fan support shall be of adequate strength to avoid
bending etc.
n) The mounting arrangement of cooling fans shall be subject to
drawing approval from MPPTCL.

15.2 Cooling Equipment Control (ONAN/ONAF Cooling)


a) Automatic operation control (switching in and out) of fans shall
be provided (with temperature change) from contacts of
winding temperature indicator. The Bidder shall recommend
the setting of WTI for automatic change over of cooler control

MPPTCL/TECH/PROC/07/JULY15 34 of 105
Volume-II, Part-7

from ONAN to ONAF. The setting shall be such that hunting i.e.
frequent start stop operations for small temperature difference
do not occur.
b) Suitable manual control facility for cooler fans shall be
provided.
c) Selector switches and push buttons, shall also be provided in
the cooler control to disconnect the automatic control and
start/stop the fans manually.

15.3 Indicating devices


- Fan ‘ON’ , Fan ‘OFF’
- Cooling system ‘on automatic control’.
- Cooling system ‘on manual’.
- Selector switch in auto or manual for cooler.
- A.C. auxiliary cooler supply auto change over.
- Cooler supply failure for main /standby.
- Cooling fan failure for each fan.
- Control supply failure for main and standby.

One potential free initiating contact for all the above indications
shall be wired independently to the terminal block of cooler control
cabinet exclusively for purchaser’s use.

16.0 LOCAL OLTC CONTROL CABINET, COOLER CONTROL CABINET


& REMOTE TAP CHANGER CONTROL PANEL:
a) Each three phase transformer unit shall be provided with local
OLTC control cabinet, cooler control cabinet OR fan control
cubicle (FCC) and RTCC panel. The total height of RTCC panel
shall be 2250mm to match with the height of other control &
relay panels. Local OLTC control cabinet shall be mounted on
the transformer. The thickness of front panel, door frame etc.
shall be 3mm (10 SWG),while doors & side panels may be 2
mm (14 SWG) and gland plate shall be of minimum thickness 4
mm.
b) The cooler control cabinet or FCC shall not be mounted directly
on transformer tank .Please note that FCC shall be grouted
away from the main tank thus the length of capillary tubes of
all oil and winding temperature indicating meter shall be
sufficient to connect OTI and WTI meters in the FCC. The
cooler cabinet shall have all necessary devices meant for cooler
control and local temp. indicators. All the contacts of various
protective devices mounted on the transformer shall also be
wired up to the terminal Board in the cooler control cabinet. All
the secondary terminals of the bushing CT's shall also be wired
upto the terminal Board at the cooler control cabinet.
c) The cooler control cabinet shall have two(2) sections. One
section shall have the control equipment exclusively meant for
cooler control. The other section shall house the temperature
indicators, aux. CT's and the terminal Boards meant for
termination of various alarm and trip contacts. Alternatively

MPPTCL/TECH/PROC/07/JULY15 35 of 105
Volume-II, Part-7

the two sections may be provided as two separate panels


depending on the standard practices of the Bidder.
d) The cooler control cabinet, Local OLTC cabinet and RTCC Panel
shall be provided with non disconnecting stud type terminal
blocks. Each of the terminal blocks in the above panels should
have 20% spare terminals exclusively for purchaser’s use. All
the necessary terminals for remote connection to purchaser’s
panel shall be wired upto the cooler control cabinet. Necessary
shorting of terminals shall be done at the cooler control
cabinet, local OLTC cabinet and remote OLTC panel. All the CT
secondary terminals in the cooler control cabinet shall have
provision for short circuiting to avoid CT open circuit while it is
not in use.
e) The local OLTC control cabinet shall house all necessary
devices meant for OLTC control and indication.
f) Following cabling are specifically excluded from the scope of
the Bidder. However, interconnection drawings for the same
are to be submitted by the Bidder.
i) Cabling between Remote OLTC Panel to Cooler Control
Cabinet.
ii) Cabling between Remote OLTC panel to Local OLTC
Cabinet.
iii) Cabling between Remote OLTC to Purchaser's Panel.
iv) Cabling between Cooler Control Cabinet to Purchaser's
Panel.
v) Cabling between Local OLTC Cabinet to Purchaser's Panel.

16.1 The degree of protection shall be IP-55 in accordance with IS-2147.

16.2 The temperature indicators shall be so mounted that the dials are
not above 1600mm from ground level. Glazed door of suitable size
shall be provided for convenience of reading.

16.3 A space heater and cubicle lighting with ON-OFF switch shall be
provided.

16.4 Terminal Blocks:


a) The terminal blocks to be provided shall be fully enclosed with
removable covers and made of moulded, non inflammable
plastic material with block and barriers moulded integrally.
Such block shall have washer and binding screws for external
circuit wire connections, a white marking strip for circuit
identification and moulded plastic cover. All terminals shall be
clearly marked with identification numbers or letters to
facilitate connection to external wiring.
b) All internal wiring to be connected to the external equipment
shall terminate on terminal blocks, preferably vertically
mounted on the side of each panel. The terminal blocks shall

MPPTCL/TECH/PROC/07/JULY15 36 of 105
Volume-II, Part-7

be 1100 V grade and have 10 amps continuous rating,


moulded piece, complete with insulated barriers, non-
disconnecting stud type terminals, washers, nuts and lock
nuts. Terminal block design shall include a white fiber marking
strip with clear plastic, slip-on/clip-on terminal cover. Markings
on the terminal strips shall correspond to wire number and
terminal numbers on the wiring diagrams.
c) Terminal blocks for current transformer secondary leads shall
be provided with test links and isolating facilities. Also current
transformer secondary leads shall be provided with short
circuiting and earthing facilities.
d) Unless otherwise specified, terminal blocks and wiring shall be
suitable for connecting the following conductors on each side.
For all circuits except current transformer circuits minimum of
two nos. 2.5 mm2 copper.
For all CT circuits minimum of four nos. 4.0 mm2 copper.
e) There shall be a minimum edge to edge clearance of 250 mm
between the first row of terminal blocks and the associated
cable gland plate. Also the clearance between two rows of
terminal blocks shall be a minimum of 150 mm.
f) Arrangement of the terminal block assemblies and the wiring
channel within the enclosure shall be such that a row of
terminal blocks is run parallel and in close proximity along
each side of the wiring duct to provide for convenient
attachment of internal panel wiring. The side of the terminal
block opposite the wiring duct shall be reserved for the owner's
external cable connection. All adjacent terminal blocks shall
also share this field wiring corridor. A steel strip shall be
connected between adjacent terminal block rows at 450mm
intervals for support of incoming cables.
g) The number and sizes of the owner's multi core incoming cable
will be furnished to the successful Bidder.

16.5 One Cooler Control Cabinet and OLTC local control cabinet shall be
tested for IP-55 protection in accordance with IS-2147 (Category-I) at
ERDA/CPRI.

16.6 The gaskets shall be of neoprene rubber.

17.0 PAINTING:

17.1 It has been observed that certain units received in the past
by us are not having good quality painting on inside & out side and
with passage of time peeling of flakes of paint takes place. In view of
this the Bidders are requested to furnish in a separate sheet painting
procedure adopted by them for internal & external surfaces of the
tank. This is an essential requirement and details should be confirmed
by the Bidders in their offer. The internal and external surfaces including
oil filled chambers and structural steel work to be painted shall be shot or

MPPTCL/TECH/PROC/07/JULY15 37 of 105
Volume-II, Part-7

sand blasted to remove all rust and scale of foreign adhering matter or
grease. All steel surfaces in contact with insulating oil shall be painted with
two coats of heat resistant, oil insulating varnish.

17.2 All steel surfaces exposed to weather shall be given a primary coat
of zinc chromate, second coat of oil and weather resistant varnish of a colour
distinct from primary and final two coats of glossy oil and Epoxy light gray
paint in accordance with shade no.401 of IS-5.For each transformer oil paints
should be obtained from same source to ensure compatibility & proper finish.

17.3 All paints shall be carefully selected to withstand extremes of


weather. The paint shall not scale off or crinkle or be removed by abrasion
due to normal handling. The process of painting should be clearly described.

17.4 The minimum thickness of each coat of outside painting of tank


shall be 20 microns and the total thickness shall be minimum 80 microns.

17.5 Bolts & Nuts :All bolts and nuts exposed to weather shall be hot
dipped galvanised/cadmium plated.

18.0 WIRING & CABLING:


(a) All external cabling will be carried out by the purchaser based
on wiring diagram & interconnection schedule to be supplied by
the Bidder. Cable box/sealing end shall be suitable for
following types of cables :-
i) POWER SUPPLY 0.4KV : 1100volts grade PVC
insulated armoured
aluminum cable .
ii) CONTROL CABLE : 1100volts grade PVC
insulated 7/0.737mm
stranded armoured copper
cable .
Size of the Purchaser’s cable will be intimated to the
successful Bidder after detailed engineering.
(b) Compression type cable gland shall be provided for
termination of power and control cables.
(c) All controls, alarms, indicating and relaying devices
provided with the transformer shall be wired upto the
terminal blocks inside the Cooler Control Cabinet.
(d) All devices and terminal blocks with the Cooler Control
Cabinet shall be clearly identified by symbols corresponding to
those used on applicable schematic or wiring diagrams.
(e) Not more than 2 wires shall be connected to one terminal.
Each terminal shall be suitable for connecting two 7/0.737mm
stranded copper conductors from each side.
(f) All internal wiring shall be securely supported, neatly
arranged, readily accessible and connected to equipment
terminals and terminal blocks.

MPPTCL/TECH/PROC/07/JULY15 38 of 105
Volume-II, Part-7

(g) Engraved code identification plastic ferrules marked to


correspond with schematic diagrams shall be fitted at both
ends of wires. Ferrules shall fit tightly on wires and shall not
fall off when the wire is disconnected from terminal block.
(h) The schematic diagrams of circuitry shall be available in the
respective cabinets (local OLTC control cabinet , local fan
control cubicle and RTCC panel). The diagrams shall be
mounted on the inner side of door of cubicle/cabinets. The
arrangements shall be such that it is not be possible to remove
the diagram from its place and diagrams are long lasting
(engraved type).

19.0 TERMINAL CONNECTORS:

19.1 Terminal connectors for HV & LV side bushings shall be suitable


for single/double Zebra ACSR (28.62mm) conductor and suitable for
horizontal and /or vertical take off arrangement i.e. universal type.
Regarding neutral earthing, details have been indicated in clause no. 12.1 of
this specification and arrangement shall be as per drawing no.
MPPTCL/40MVA/02. Two (2) no. terminal connectors for Earth pit end
connection suitable for double (twin) Zebra ACSR (28.67 mm) conductor shall
also be supplied loose as per drawing no. MPPTCL/40MVA/04 .

19.2 Bushing terminals shall be provided with terminal connectors of


approved type and size for connection to external parts. Terminal connectors
offered must have been successfully type tested as per IS-5561.

19.3 All terminal connectors shall be manufactured out of gravity dye


casting process only and shall be free from blow holes, surface blisters,
cracks and cavities. All sharp edges and corners shall be blurred and
rounded off. The aluminum alloy castings, if used, shall conform to
relevant IS.

19.4 No part of the clamp shall be less than 12mm thickness.

19.5 All bolts, nuts and washers shall be of Hot Dip Galvanised.

19.6 For bimetallic clamps , bimetallic strip of not less than 2 mm


thickness shall be provided.

19.7 Flexible connectors, if provided shall be made from tinned copper


sheets.

19.8 Size of terminal (bushing stud)/conductor ( ACSR Zebra ) for which


the clamp is designed and also rated current under site conditions shall be
embossed/ punched on each part of the clamp, except hardware.

19.9 All current carrying parts shall be designed and manufactured to


have minimum contact resistance. Clamps shall be designed corona
controlled.
19.10 The nominal current rating and short time current rating of terminal
connectors shall match the corresponding rating of respective bushings.

MPPTCL/TECH/PROC/07/JULY15 39 of 105
Volume-II, Part-7

20.0 INSULATING OIL REQUIRED FOR TRANSFORMERS:

20.1 Transformer oil shall be supplied by the Bidder. The offered Price
of transformers therefore, should include first filling of oil( including
wastage) & 10% extra of that quantity. The quantity of oil for first filling
including wastage and 10% extra of that quantity should be indicated by the
Bidder in kilo-liters and in kg. The design of the transformer shall be based
on the characteristic of EHV transformer oil as per relevant IS.

20.2 The transportation of transformer may be arranged either with N2


gas filled condition or duly oil filled condition. In case of oil filled condition
prior permission from MPPTCL will have to be obtained by the contractor and
an undertaking by the turnkey contractor will have to be submitted for
carrying out transportation at their own risk and responsibility. In case of N2
gas filled condition suitable arrangement will have to be ensured by the
contractor so that the pressure of gas is regularly maintained during transit
and upto the date of filling of oil. For this purpose, necessary gas
cylinders with regulator shall be supplied on non returnable basis.
Additional gas cylinders required for recouping and maintaining of
positive Nitrogen pressure upto filling of oil should be supplied by the
manufacturer of Transformers and the offered price should take into
account this requirement.

20.3 The quality of the oil supplied with transformer shall conform to the
oil parameters specified in this clause. No inhibitors shall be used in the oil.
The oil samples of transformer will be drawn for the oil used at factory &
site as follows.
i. Prior to filling
ii. Before and after heat run test / pre-commissioning test
iii. Before energizing.

All tests as per IS:335 (latest revision) shall be conducted on oil


samples.

20.4 Sufficient quantity of oil necessary for first filling of main tank,
coolers, radiators and conservators etc. upto the proper level plus anticipated
quantity of wastage of oil during first filling shall be supplied in tankers. Please
note, wastage means quantity of oil absorbed during initial filling at works for
testing. In addition to the oil needed for first filling, 10% extra quantity of oil
for topping up in future, shall be supplied in non-returnable containers
suitable for outdoor storage. Therefore, total quantity of oil required for first
filling shall be measured at works at the time of testing on unit subjected to
heat run test.

20.5 The supplier shall dispatch the transformer in an atmosphere of


pressurized Nitrogen. In this case, necessary arrangement shall be ensured
by the supplier to take care of pressure drop of nitrogen during transit and
storage till completion of oil filling during erection. A gas pressure testing
valve with necessary pressure gauge and adapter valve shall be provided.

MPPTCL/TECH/PROC/07/JULY15 40 of 105
Volume-II, Part-7

20.6 The supplier shall warrant and confirm that oil to be used for the
transformer testing at Works & oil to be supplied for the transformer is free
from Polychlorinated Biphenyls (PVB/PCB). The transformer oil to be used
and supplied by the bidder for first filling at site shall be new oil of EHV Grade-
I having technical specification mentioned hereunder . Hence Oil to be used
by the manufacturers at factory for the purpose of testing at their
works shall be of similar or better quality having parameters matching
with the parameters specified in the specification. Specific approval of
oil test results of oil proposed to be used for testing of transformer in
factory shall be obtained by the manufacturer from the purchaser
before first filling in the unit. MPPTCL shall not accept any other oil for
testing purposes having lower parameters than those specified in the
Bid. Bidders should specifically confirm this requirement in their offer.

Sl.
Characteristics Requirement Method of Test
No
1. 2. 3. 4.
1. Appearance The oil shall be clear A representative
and transparent and sample of oil shall be
free from suspended examined in a 100
matter or sediment mm thick layer at
ambient
temperature.
2. Density at 29.5oC 0.89 gm/cm3 IS:1448
(maximum)
3. Kinematics viscosity at 27 CST IS:1448
27oC (minimum).
4. Interfacial tension at 0.04 N/m IS:6104
27oC (minimum).
5. Flashpoint Pensky 140oC IS:1448
Marten (closed)
(minimum).
6. Pour point. (maximum) -6 oC IS:1448
7. Neutralization value 0.01 mg KOH/g IS:335 Appendix
(Total acidity maximum) `A’, IEC 62021
8. Corrosive Sulphur Non-corrosive IS:335 Appendix `B’
9. Electric strength IS:6792
(breakdown voltage)
Minimum.
a. New unfiltered oil (as 40 KV (rms)
received condition).
b. After filtration
60 KV (rms)
10. Dielectric dissipation 0.002 IS:6262
factor (tan delta) at
90oc Maximum.

MPPTCL/TECH/PROC/07/JULY15 41 of 105
Volume-II, Part-7

Sl.
Characteristics Requirement Method of Test
No
1. 2. 3. 4.
11. Specific resistance
(resistivity)
a. at 90oC Minimum. 100x1012 ohm.cm IS:6103
b. at 27oC Minimum. 1500X1012 ohm.cm
12. Oxidation stability IS:335 Appendix `C’
a. Neutralisation value 0.20 mg KOH/g
after oxidation,
maximum. 0.02 percent by
b. Total sludge, after weight
oxidation Maximum
13. Presence of oxidation The oil shall not IS:335
inhibitor contain antioxidant Appendix `D’
inhibitors .
14. SK value 6% maximum IS:335
15. Water content, 10 ppm IS:2362,IS 13567
maximum.
16. Ageing characteristics As per ASTM-D
after accelerated ageing 1934, IS 12177,IEC
(open Breaker method 62021
with copper catalyst)
a) Resistivity
2.5x1012 ohm.cm
i. 27oc (min.)
ii. 90oc 0.2x1012 ohm.cm
b) Tan delta at 90oc (min.)
c) Total acidity 0.15 (max.)
d) Sludge content 0.05 mg
by weight KOH/gm(max.)
0.05% (max)

MPPTCL/TECH/PROC/07/JULY15 42 of 105
Volume-II, Part-7

Sl.
Characteristics Requirement Method of Test
No
1. 2. 3. 4.
17. Oil sample taken from
the transformer after
the completion of site
processing and tested in
approved manner shall
have the following
values before
commissioning of the
transformer. Minimum 70 KV Tested in accordance
i. Break down withstand with IS :335
strength Maximum of 10 ppm
ii. Moisture content 35x1012 ohm.cm
iii. Resistivity at 90oc (min)
minimum
iv. Interfacial Tension 0.04 N/M (min)
at 27oc
v. Dielectric 0.002 (max.)
dissipation factor at
90 oC
18 N-dm analysis
CA% 4 –6%
CN% 40-43%
CP% 51-54%

20.7 AIR CELL : Our technical specification calls for supply of power
transformers with air cell type oil preservation system of PRONOL, make
only. It is obligatory on the part of the Bidders to clearly submit complete
constructional and technical details of sealing arrangement, duly supported
with technical details, pamphlets and dimensional drawings. While
furnishing details for the above sealing arrangement the Bidders must
confirm clearly that the size and capacity of sealing arrangement is
adequate for the transformer and for the quantity of oil required for the
transformers. Necessary calculation/documentary proof shall be furnished.

20.8 Air cell type oil preservation system included with each transformer
shall ensure as under:
(a) The air inlet of COPS (Conservator Oil preservation System)
shall be properly fitted on the conservator for leak proof
arrangement to ensure that the air does not come in contact
with oil under any circumstances.
(b) The size and capacity of the COPS (Conservator Oil
preservation System) shall be selected to suit the design of
Conservator and to ensure proper operation for the quantity of
oil in the unit with the proper allowances. The COPS shall be of
reputed make, proven design and of established performance.

MPPTCL/TECH/PROC/07/JULY15 43 of 105
Volume-II, Part-7

Details in this regard are to be submitted with the offer by the


Bidder for verification . The Bidder is required to submit
calculation with bid to prove adequacy of air cell & its size.
(c) The Bidder shall clearly indicate in the manual the procedure
for installation of COPS and precautions to be taken at the
time of first oil filling under vacuum in the transformer.

20.9 THERMOSYPHON FILTER: Atleast two Nos. of Thermosyphon filter


arrangement each of capacity 1/5th of the total oil flow in the cooler shall be
provided with rigid support (i.e., slotted one not acceptable) on the
transformer along with connecting piping, isolating valves at either end, drain
plug shall be mounted on the transformer. It will have Alumina trap and will
be designed in such a way that 1/5th of the forced oil circulation passes
through it. The quantity of absorbent will be 0.25% of the total weight of total
oil in the transformer, cooler, conservator etc. Spare alumina for one time
replacement shall be also supplied by the supplier. The location of
Thermosyphon filter should be in such a way that same do not interfere with
any of the existing equipments. The Thermosyphon filter shall be located at
diagonally opposite points of transformer. The connecting pipes of
Thermosyphon filter to tank shall be provided with flexible couplings. It may
be noted that rigid supports shall be provided for thermosyphon filter i.e.,
slotted type of fixing arrangement is not acceptable.

20.10 Silicagel breather : Minimum 2 nos. dehydrating filter Silica Gel


Breathers each of 100% breathing capacity are required and the same shall
be provided. Size of breather and its pipe connection is to be indicated.
However, each breather of minimum capacity of 8 Kg having its pipe
connection of minimum size of one inch dia shall be preferable. Suitable
arrangement for parallel mounting of breathers shall be made for connecting
both the Silica Gel Breather to the main conservator.The passage of air should
be through dual filter & Silica Gel. Silica Gel shall be isolated from atmosphere
by an oil seal. Adequate supports are required to be provided for pipe
connection to avoid any swing in air.

The capacity of silicagel breather shall be adequate to ensure supply of dry air
only for the volumetric expansion/contraction of oil keeping in view the total
quantity of oil in the unit. The container of the breather shall be made of
metal with glass enclosure along its periphery to ensure that the transparency
(to verify the colour of dehydrating agent) is maintained during operation
directly under sunlight (ultra violet rays) for long life. The quantity of the
dehydrating agent shall be sufficient keeping in view the climatic condition
specified and that the breather will be maintained generally two times in a
year. This applies to all the breathers provided with the transformer.

20.11 TRANSPORTATION CONFIGURATION OF POWER TRANSFORMER:


In order to conduct low voltage field testing on power transformers before
unloading/commissioning at site to determine the internal condition, the
transformer shall be transported with :

a) Small bushing (12 KV) may be installed on the bushing cover plate to
represent the actual bushing.

MPPTCL/TECH/PROC/07/JULY15 44 of 105
Volume-II, Part-7

b) Winding leads may be routed, secured and electrically isolated from the
tank walls and active part.
c) Temporarily tests leads may be used to connect the winding leads by
the small bushings (which will be removed before erection of the main
bushings).

The details of arrangement for transport configuration of Power Transformer


(which shall be adopted by Manufacturer) shall be submitted by the
Manufacturer to the Purchaser for approval. The price quoted by the Bidder
should take into account this requirement.

21.0 FITTINGS & ACCESSORIES FOR THE POWER TRANSFORMERS

21.1 The Bidders submit a specific confirmation that the transformers


will be supplied complete with all fittings and accessories exactly in line with
various requirements indicated in Annexure II in this technical specification.
The basic offered cost must take into consideration cost of all fittings and
accessories as under and indicated elsewhere in this specification.

21.2 The equipments and accessories furnished with the


transformer shall be suitably mounted on the transformer for ease of
operation, inspection and maintenance and the mounting details shall be
subject to the approval of the purchaser. All valves shall be provided either
with blind companion flanges or with pipe plugs for protection.

21.3 Indication, alarm and relay equipment shall have contacts suitable
for operation with 110V/220V DC supply. Any other accessories or
appliances recommended by the manufacturer for the satisfactory
operation of the transformer shall also have 110V/220V DC as input.
a) OLTC and its controls shall be as per clause 14.
b) All cabinets & panels shall be conforming to
stipulations under Clause-16 .
c) All 145KV, 72.5KV phase and 72.5 KV neutral bushings shall be
of OIP condenser type and as per Clause 11.13 .

21.4. Equalizing pipes for maintaining equal pressure between main tank
and OLTC and at various other locations as per design shall be provided.
These equalizing pipes shall be routed such as not to create any obstruction.

21.5 Accessories, which are not included in the above schedule


but details of which are given in Bid specification and which are necessary for
satisfactory operation of Transformer shall be deemed to have been
included in the accepted price without any extra cost to the Purchaser.

21.6 It may be noted that all the name plates/rating plates/diagram


plates on transformer shall be engraved type/anodized type and shall be fixed
using rivets/spot welding method. The method of printing of letters on the
R&D plate shall be such that inscriptions shall not fade by ultra violet rays and
other adverse weather conditions under which the same is subject to during
service life of transformers.

MPPTCL/TECH/PROC/07/JULY15 45 of 105
Volume-II, Part-7

(a) Rating & Diagram Plate: In the R&D plate following additional
information over & above as specified in the IS/CBIP specification shall
be provided.
- Weight of the copper for windings
- Weight of the core laminations for core
- Weight of insulation
- Weight of steel
- Untanking weight (Core & Coil)
- Weight of Transformer Tank along with Fittings &
Accessories
- Percentage Impedance at all taps
- HV winding resistance of all phases at all taps
- LV winding resistance of all phases
- Weight of the oil for first filling in Kg/Liters
- Total quantity of oil (including wastage) and 10% extra
quantity in Kg/Liters
- If required two separate R & D plates may be used.

(b) Valve Schedule Plate: In the valve schedule plate, at least two views
should be inscribed so that location of all the valves provided on the
transformer could be indicated/visualised. In the table of valve
schedule plate, details of valves viz. type of valve, material of valve,
size of valve & position of valve during transportation and after
commissioning shall be clearly indicated. The size of the letter shall be
such that the same be visible clearly to a person standing away at a
distance of one meter from the respective vertical face of the
transformer.
(c) Instruction Plate For Oil Filling in the Conservator with Air Cell:
An instruction plate shall be provided for oil filling in the conservator
having air cell type breathing arrangement. In addition to the
instructions for oil filling on this plate, a diagram indicating mounting
details of MOLG, oil level gauges, air cell inside the conservator with a
pictorial view of conservator including make, type & size of air cell shall
also be inscribed. The location of plate should be such that same is
visible to operating personal from a distance as mentioned in (b)
above.

22.0 CENTRE OF GRAVITY : The centre of gravity of the assembled


transformer shall be low and as near to the vertical centre line as possible.
The transformer shall be stable with or without oil. If the centre of gravity is
eccentric relative to track gauge either with or without oil, its location shall
be shown on the outline drawing.

23.0 PACKING:

23.1 The packing may be in accordance with the Bidder's standard


practice but Bidder should give full particulars of packing for the approval of
the purchaser. Special arrangements should be made to facilitate handling
and to protect the projecting connections for damage in transit.

MPPTCL/TECH/PROC/07/JULY15 46 of 105
Volume-II, Part-7

23.2 The transformer shall be transported filled with inert gas preferably
Nitrogen gas. The Bidder shall ensure that adequate pressure of gas is
maintained inside the tank throughout during transportation by sending
escorts and required apparatus and equipment with the transformers.

23.3 All parts shall be adequately marked to facilitate field erection.


Boxes and crates shall be marked with the contract number and shall have
a packing list enclosed showing the parts contained therein. however the
verification of accessories shall be done in presence of suppliers
representative.

24.0 TESTS:

24.1 The manufacturer shall carryout routine test ,additional routine


tests and type tests on the transformers as per the relevant Indian
Standard IS-2026 with latest amendments , IEC 60076,CBIP Publication No
295,IEEE or any equivalent International Standard .The details of tests are
specified hereunder. It should be specifically noted by the Bidder that testing
of each & every transformer included in this Bid specification shall be carried
out at the manufacturer’s works in fully assembled condition complete with all
fittings & accessories.

24.2 ROUTINE TESTS AND ADDITIONAL ROUTINE TESTS: All routine


tests and additional routine Tests detailed under clauses 24.2.1 & 24.2.2
herein under will be carried out on each transformer on "free of cost" basis, in
accordance with IS:2026 part-I.

24.2.1 ROUTINE TESTS:


a) Measurement of winding resistance as per cl.16.2 of IS 2026
Part I. The winding resistance shall be measured on all taps
and of all the three phases and values be recorded in
respective test certificates.
b) Measurement of voltage ratio at all taps and checking of
voltage vector relationship as per cl.16.3 of IS 2026 Part I.
c) Measurement of Impedance voltage/ short circuit impedance
& load loss (at principal tap & extreme taps) as per cl.16.4 of
IS 2026 Part I, IEC 60076.Also measurement of Impedance
voltage/ short circuit impedance at all taps at low voltage.
d) Measurement of no load loss at 90%,100%,110% of rated
voltage & no load current as per cl.16.5 of IS 2026 Part I.
e) Measurement of insulation resistance as per cl. 16.6 of IS
2026 Part I.
f) Dielectric tests as per cl.16.7 of IS 2026 Part I, IEC 60076 as
per latest version.
g) All tests on OLTC as per cl.16.9 of IS 2026 Part I, IEC 60214.
h) Measurement of Tan-Delta, Capacitance & IR values (i.e top to
test tap and test tap to earth) of HV ,LV & Neutral bushings
before & after tests on transformer .

MPPTCL/TECH/PROC/07/JULY15 47 of 105
Volume-II, Part-7

i) Low voltage AC, magnetic balance and magnetizing current


three phase & single phase at normal tap for field reference.
The test shall be carried out only after ensuring proper
demagnetization of the core so as to achieve proper results.
j) Impulse Test on line terminals as per IS 2026 part III.
k) Measurement of leakage current between core – frame – tank
at rated voltage (during no load loss measurement) and at
rated current (during load loss measurement).

Note : DGA test of oil of main tank of transformer before (initial) & after
completion of all testing shall be done and test results shall be submitted to
the purchaser.

24.2.2 ADDITIONAL ROUTINE TESTS:

(A) Insulation Resistance : Insulation Resistance


measurement shall be done for 15 Secs. , 60 secs. and 600
secs. Duration. Polarization Index (PI) shall be clearly
recorded on test report for 600 sec /60 sec values and D.A.R.
for 60 sec/15 sec values. Minimum preferred IR values for 60
Sec at 60oC shall be 1000 M.Ohms.
PI value : PI value (i.e. ratio of IR Values for 600 sec /
IR Values for 60 sec) for winding should be greater than
2.0.

(B) Magnetic Circuit Test :After assembly, core shall be tested


for 1 minute at 2000 volts AC between all bolts, side plates &
structural steel work. Immediately prior to the despatch of the
transformer from works of manufacturer, the magnetic
circuit shall be tested for one minute at 2 KV AC between the
Core & Earth and leakage current shall also be recorded.

(C) Oil Leakage Test on Tank : All Transformer tank with its
active part as assembled for type test (i.e. including pipe work
and cooling equipment and excluding PRV and conservator
when air cell is provided) shall be subjected to a
pressure corresponding to twice the normal head of oil or to
normal pressure plus 35 kN/ m.sq. whichever is lower
measured at the base of the tank and will be maintained
for 12 hours during which time no leakage shall occur. Before
conducting the pressure test, the following are to be taken
care of :
(i) Pressure relief valve are to be removed and the opening
blanked .
(ii) Transformer and tap changer conservators are to be
disconnected.
(iii) Diverter switch compartment of tap changer to be
connected with transformer tank for equalising the
pressure on both sides.

MPPTCL/TECH/PROC/07/JULY15 48 of 105
Volume-II, Part-7

(iv) Oil should be completely filled and all trapped air


released.

(D) Capacitance & Tan-delta Test on winding: The


measurement of capacitance and tan delta to determine
capacitance between winding & earth shall be carried out in
mode UST, GST & GSTg both before and after series of
dielectric tests by Ampere turn method. For temperature
correction factors IEEEC 57.90 shall be referred. For clarity
measurement of Capacitance & Tan-delta of winding shall be
carried out as under:-
- HV/LV+E(GST)
- LV/HV+E(GST)
- HV/E (GSTg)
- LV/E(GSTg)
-HV/LV(UST)
The measured Tan delta values of winding shall not
exceed 0.45% at 200C (degree Centigrade) temperature.
In case Tan delta of transformers during testing at
works of manufacturer is measured above maximum
ceiling of 0.45% at 200C (degree Centigrade)
temperature, then MPPTCL reserves right not to accept
such of the transformer. This requirement is to be
confirmed specifically by the Bidders in their offer.

(E) Test Results of calibration & measurement reports of WTI &


OTI , ratio test for all CTs and measurement of knee point
voltage , IR value and winding resistance for bushing CT.
(F) Checking & recording of following:
a. IR values
i. Between Core and End frame
ii. Between Core and Tank
iii. Between End frame and main Tank.
The measured IR values should be more than 1000 M
Ohms. This requirement is to be confirmed
specifically by the Bidders in their offer.

b. Measurement and recording of currents with


application of 400 volts, 3phase, AC supply on HV
side with LV side shorted, as under
i. Between Core and Tank.
ii. Between Core and End frame
iii. Between End frame and Tank
iv. Between neutral and short circuited links with neutral
grounded and ungrounded conditions.

NOTE: The details of arrangements provided outside the main


tank for connecting core, end frame and main tank body shall be
indicated on a diagram , to be attached with the test reports.

MPPTCL/TECH/PROC/07/JULY15 49 of 105
Volume-II, Part-7

(G) Magnetising current measured with LT supply.

No Particulars With Single phase With Three phase


supply supply
Volts. Amps. Volts. Amps.
a On HV
side
b On LV side

(H) Magnetic balance test on HV and LV side

(I) Pressure Relief Device Test : All pressure relief devices


provided in each transformer shall be subject to test for its
successful operation. It shall operate before reaching the test
pressure specified in clause 24.3 (C) of this specification. The
device shall seal off after the excess pressure has been
relieved.
(J) Frequency Response Analysis (SFRA) Test on
Transformer : The SFRA test shall be conducted by the
manufacturer at manufacturers works using his own SFRA test
set and also SFRA test shall be conducted by the manufacturer
at site using same SFRA test set at the time of erection &
commissioning of unit.

(K) Measurement of Dew point prior to despatch of the unit,


filled with N2 gas: Dew point is the temperature at which
water vapours present in the gas filled in the transformer
begins to condense. The transportation of transformer from the
factory of manufacturer’s works upto the purchaser’s site is
done with dry Nitrogen gas filled condition, due to weight
limitation. Positive gas pressure say 0.25 kg/cm2 is normally
maintained during transportation as well as during storage. In
case positive pressure is not maintained then due to
hygroscopic properties of insulation used in transformer
possibility of absorption of moisture in insulation can not be
overruled. Therefore to check the dryness of insulation,
measurement of dew point at factory prior to despatch and on
receipt of unit at site is necessary and to be carried out. It
may be noted that dew point shall be measured at factory prior
to despatch. Temperature, pressure and dew point at the time
of gas filling (reading taken after stabilisation) shall be taken
and painted on the transformer tank. The minimum
permissible value of dew point shall be (–)25oC at normal
temperature and pressure.
(L) Functional tests on auxiliary equipments i.e. OTI,WTI,
valves etc as per CBIP publication no 295.

24.3 TYPE TESTS : Following Type Tests shall be conducted on one


transformer of each manufacturer (if there are more than one manufacturer)
as per IS:2026 Part I, IEC , CBIP publication no 295:

MPPTCL/TECH/PROC/07/JULY15 50 of 105
Volume-II, Part-7

(A) Temperature Rise Test : This test as per cl. 16.8 of IS:2026(Part-
II) shall be conducted at the lowest voltage tap having maximum
current with 10% over load condition. The supplier before carrying
out such tests, shall submit detailed calculations showing the
alternatives possible, on various taps and for different ratings
(ONAN/ONAF), of the transformer and shall recommend the
combination that results in highest temperature rise, for the test.

Gas chromatographic analysis of oil shall be conducted before and


after heat run test and the values shall be recorded in the test
report. The sampling shall be in accordance with IEC-60567. For
the evaluation of the gas analysis in temperature rise test, a
method will be proposed which is based on the rate of increase of
particular gases and the permissible limits of minimum detectable
value of gases and the maximum limit will be mutually discussed
and agreed upon between the Purchaser and Supplier. This shall be
treated as reference during maintenance of transformer in future.
The calibration of OTI and WTI shall be done by Transformer
Manufacturer and these calibrated OTI,WTI shall be used during
testing of transformer. The Sr.No. of WTI,OTI shall be recorded
during testing of transformer and these indicators only shall be
supplied with the transformer. During test the manufacturer
selects suitable tap from CT based on gradient between the reading
of WTI & OTI . This tap position is to be clearly recorded on test
report so that selection of correct tap could be done at site to avoid
discrepancy in temperature gradient recorded during factory test and
the value recorded at site.
(B) Tank tests : Following Vacuum and Pressure tests shall be carried
out on one transformer tank of each fabricator.
(a) Vacuum Test (Fabrication stage) : One transformer
tank of each design shall be subjected to the vacuum of
760 mm of Hg. The tanks designed for full vacuum (760 mm
of mercury at sea level or the barometric reading at the
location of test) shall be tested at a maximum internal
pressure of 3.33 kN/m.sq. (25 mm of Hg) for one hour i.e.
760-25=735 mm of Hg at sea level and (Barometric reading -
25mm Hg) at other location. The permanent deflection of
flat plates after vacuum has been released shall not exceed
the values specified below:

Horizontal Length of flat Permanent


plate (in mm) Deflection (in mm)
Up to and including 750 5
751 to 1250 6.5
1251 to 1750 8
1751 to 2000 9
2001 to 2250 11
2251 to 2500 12.5
2501 to 3000 16
Above 3000 19

MPPTCL/TECH/PROC/07/JULY15 51 of 105
Volume-II, Part-7

Note:-During Vacuum testing, provision of any kind of


internal supports are not acceptable. This fact is to be
kept in view while finalizing design of tank.
(b) Pressure Test (Fabrication stage) : One transformer tank
of each design , its radiator, conservator vessel ,and other
fittings together or separately shall be subjected to a
pressure corresponding to twice the normal head of oil or to
normal pressure plus 35 kN/m2, whichever is lower, measured
at the base of the tank and will be maintained for 1 hour
during which time no leakage shall occur. The permanent
deflection of the flat plate after the excess pressure has been
released shall not exceed the figures specified above for
vacuum test as per clause 24.3(C)(a).
Note:- Permanent deflection both under vacuum and
pressure test shall be within permissible limits separately, as
detailed above.

24.4 SPECIAL TESTS : Following special tests other than type and
routine tests shall also be carried out as per IS:2026 Part-I on one
transformer of each manufacturer (if there are more than one manufacturer) :
a) Measurement of zero seq. impedance as per CL.16.10 of IS:2026
Part-I.
b) Measurement of acoustic noise level as per CL.16.12 of
IS:2026 Part-I,NEMA TR1 & IEC 60076-10. Detailed calculations &
conditions outlined in the IEEE standard C 57.12.12.90 shall be
followed.
c) Measurement of power taken by fans as per cl.16.14 of
IS:2026 Part-I.
d) Measurement of harmonic level of no load current and total
harmonic distortion of voltage & current as per CL.16.13 of IS:2026
Part-I. Details of rms voltage applied & print out of Harmonic Analyser
shall be enclosed with report.
e) One Cooler Control Cabinet and OLTC cabinet of each type of
transformer shall be tested for IP:55 protection in accordance
with IS:2147 (Category-I) at ERDA/CPRI.
f) Test to prove over fluxing capability of transformer.

24.5 To summarize the requirement of tests for 132KV 40MVA


power transformers covered in this Bid specification, are as
under :

Number of
Clause
Nature of tests transformers to Test charges
No.
be tested
1 2 3 4

MPPTCL/TECH/PROC/07/JULY15 52 of 105
Volume-II, Part-7

24.2.1 Routine tests & On each unit While offering for the Bid, cost
& additional routine of all these tests for specified
24.2.2. tests no. of units as per column ‘3’
24.3 Type test: should be included in the total
(A) Temperature On one unit Bid price. Thus no additional
rise test included in Bid charges shall be payable for
any of the tests and
(B) Vacuum and On One unit of
therefore, offered Bid price
pressure test Bid
should account for all the
24.4 Special tests On One unit of costs to be incurred for this
Bid purpose
24.7 Tests at site On each unit
included in Bid

Note : It is to be noted that after complete final testing of the unit ,


it should be kept charge at rated voltage for adequate time to ensure
proper demagnetization of core i.e. demagnetization of core shall be
ensured prior to dispatch of the unit.

24.6 Oil to be used by manufacturers at factory for the purpose of


testing at their works shall be of similar or better quality having
parameters matching with the parameters specified in the
specification. Specific approval of oil test results of oil proposed to be
used for testing of transformer in factory shall be obtained by the
manufacturer from the purchaser before first filling in the unit.
MPPTCL shall not accept any other oil for testing purposes having
lower parameters than those specified in the Bid.

25. TESTS AT SITE :On delivery /receipt, after erection at site, the
transformer shall be subject to the following tests, in presence of supplier's
engineer.
(i) Immediately upon receipt of transformer at site and before
unloading of transformer from trailer, core earthing , end
frame earthing & tank earthing shall be checked . Only after
satisfactory verification that there is no multiple core earthing
in transformer, unloading of transformer shall be undertaken.
ii) Insulation resistance test and polarisation index.
iii) Ratio and polarity test.
iv) DGA of oil and Dielectric, Tan-Delta, resistivity & moisture
content test of oil.
v) OLTC operational test at each tap for lower and raise operation
of tap changer.
vi) Magnetic balance test and measurement of magnetizing
current.
vii) Vector group test.
viii) Percentage Impedance test at all taps.
ix) Short circuit current measurement at low voltage and at all
taps.

MPPTCL/TECH/PROC/07/JULY15 53 of 105
Volume-II, Part-7

x) Measurement of winding resistance at all taps.


xi) Tangent – Delta, capacitance and insulations resistance tests
of bushings.
xii) Leakage current between core & tank, core & end frame , end
frame & tank and between short circuited links & neutral in
grounded and un grounded conditions.
xiii) Dew point measurement & recording of pressure of Nitrogen
gas on receipt of transformer at site on trailer.
xiv) SFRA test
xv) After receipt of transformer at site physical inspection shall be
done for checking any physical damage to transformer tank &
accessories. Further data of Impact recorder shall be analysed
for any changes before unloading of transformer.

26.0 CHECKS & TESTS : Following checks & tests shall be carried out by
Manufacturer at different stages of manufacture & supply of transformer and
these reports shall be sent to the purchaser for records :

(i) Assembled Transformer:

a) Check completed transformer against approved out line drawing,


provision for all fittings, finish level etc.
b) Jacking test on the assembled Transformer.
c) Measurement and recording of temperature and drying time during
vacuum treatment.
d) Check for completeness of drying by measuring IR values & Tan Delta.
e) Certification of all test results.

(ii) Preshipment Checks at Manufacturer's Works:


a) Check for interchangeability of components of similar Transformers for
mounting dimensions.
b) Check for proper packing and preservation of accessories like
radiators, bushings, explosion vent, dehydrating breather, rollers,
buchholz relay, control cubicle, connecting pipes, conservator etc.
c) Check for proper provision of bracings to arrest the movement of core
and winding assembly inside the tank.
d) Gas tightness test to conform tightness.
e) Derivation of leakage rate and ensure adequate reserve gas capacity.

(iii) Commissioning Checks at site :


a) Check the colour of silicagel breather.
b) Check the oil level in the breather housing, conservator tank, cooling
system, condenser housing etc.
c) Check the bushings for conformity of connection to the line etc.
d) Check for correct operation of all protection and alarms.
i) Buchholz relay
ii) Excessive winding temperature
iii) Excessive oil temperature
iv) Low oil flow

MPPTCL/TECH/PROC/07/JULY15 54 of 105
Volume-II, Part-7

v) Low oil level indication


e) Check for adequate protection on electric circuit supplying the
accessories.
f) Insulation resistance measurement
g) Check for cleanliness of the Transformer and the surroundings.

27.0 TEST REPORTS : After all tests have been completed seven certified
copies of each test report shall be furnished. Each report shall supply the
following information :-
i) Complete identification data including serial number of the
transformer.
ii) Method of application, where applied, duration and
interpretation of results for each test. Complete diagram of
test circuits and details of test equipments including auxiliary
transformer, Instrument transformer shall be furnished.
iii) Where ever applicable parameters to be corrected to 75º C
temperature.
iv) Test certificates of all the accessories and stage
inspections.

28.0 TOOLS : The transformer shall be supplied with a full outfit of tools,
spanners, special tools for assembling and dismantling transformers with a
rack for holding them as per Annexure IX. All spanners shall be double ended
& case hardened. The quantity of each item of tools shall be indicated by the
Bidder in Bid.

29.0 DRAWINGS & INSTRUCTION MANUALS

29.1 SPECIFIC REQUIREMENT FOR GENERAL ARRANGEMENT


DRAWING: For our 132 KV switch yard, the bay width adopted is 9.6 metres.
Following points shall be kept in view while finalizing General Arrangement
drawing of the transformer.

i. Along transverse direction (i.e. the parallel to the Bushing line)


spread of the transformer from one extreme end to the other
extreme end shall be limited to 9.6 meters. This spread shall be
distributed symmetrically with respect to the centre line of the
transformer ( i.e. 4.8 meters on either sides) This is an essential
requirement to avoid encroachment of the transformer body in the
adjoining bay.

ii. Along the longitudinal direction the 132 KV lightning arrestor are
located at a distance of 6.0 meters & the 33 KV lightning arrestor
are located at a distance of 4.0 meters from centre line of the
transformers. While deciding arrangement of location of the
accessories, this requirement needs to be kept in view from
consideration of clearances.

MPPTCL/TECH/PROC/07/JULY15 55 of 105
Volume-II, Part-7

29.2 The drawings for each items of transformer and its accessories are
to be submitted to MPPTCL at the time of obtaining approval of manufacturer.

29.3 As soon as possible after the award of the contract the manufacturer
shall supply Instruction Manual. This Instruction Manual shall be hard
bound manual shall contain set of all approved drawings, instruction books,
manufacturer’s catalogue of all bought items & fittings, operation &
maintenance manuals , spare part bulletin.

(a) Two copies of each drawing mentioned above and Instruction


Manual shall be sent along with the transformer & its accessories
to site. Further a CD containing soft copy of all drawings in
AutoCAD , instructions manuals and other relevant details in
acrobat or MS word shall be sent with transformer to site . This
CD shall contain AutoCAD software and acrobat reader software
also.

(b) Ten (10) sets of hard bound folders containing copies of approved
drawings, instruction manuals shall be sent to order placing
authority within a fortnight of approval of drawings. Further, Six
(6) CDs containing soft copy of all drawings in AutoCAD ,
instructions manuals and other relevant details in Acrobat or MS
word shall be sent to order placing authority. These CDs shall
contain AutoCAD software and acrobat reader software also.

30.0 The offered price shall include cost of drawing / manuals as


detailed out in Annexure VI(A).

31.0 DESIGN CALCULATIONS & DESIGN DATA TO BE ENCLOSED WITH


BID : All the important data of the transformer i.e. Net weight of bare copper
in each winding , Weight of core without clamping fixtures , Weight of core
and windings, Cross section of the core, Flux density calculations ,
Calculations for short circuit current and its duration , Current density during
short circuit , Calculations showing withstand capability of windings for
thermal & mechanical stresses during short circuit conditions , Mechanical
Design of transformer tank etc should be invariably submitted by the Bidder .
After placement of detailed contract the final design calculations shall be
submitted for our verification and records .

Submission of design calculations and data with technical bid is a


necessary requirement and those Bids will be rejected wherein these
data & calculations is not found . It may be noted by the Bidders that
no correspondence with the bidder in this regard shall be made after
opening of technical & commercial offer. All responsibility for
Submission of design calculations and data with the Bid is therefore of
the Bidder & non furnishing of same may run the risk of rejection
/non responsiveness of the Bid.

31.1 SHORT CIRCUIT WITHSTAND CAPABILITIES :

MPPTCL/TECH/PROC/07/JULY15 56 of 105
Volume-II, Part-7

31.1.1 The calculations to prove dynamic and thermal short circuit withstand
capability of transformer shall be submitted by the Bidder for the fault level
indicated as under
132 KV - 40 KA for 3 secs.
33KV - 31.5KA for 3 secs.

It may be noted by the Bidders that calculations for short circuit withstand
capability for two winding transformer shall be submitted. Results of
calculations shall be submitted with the bid. The design of winding assembly,
which is to be furnished in the drawing as per Sr. No. (e) of Annexure VI(A)
should be commensurating with these calculations. The details of clamping
ring shall be indicated in the drawing .

31.1.2 Design of Tank : Complete mechanical design of transformer tank


including details of stiffeners shall be submitted . The tank shall be designed
to withstand the following without permanent distortion.

(i) Mechanical shocks during transportation.


(ii) Vacuum filling of oil at 10 milli torr in transformer with all fittings.
(iii) Continuous internal pressure of 35 kN/m2 over normal hydrostatic
pressure of oil.
(iv) Short circuit forces &
(v) Under seismic condition /events both horizontal/vertical .

The calculations for tank stiffeners shall be submitted with the bid to prove
no. & size of stiffeners are adequate to withstand full vacuum & pressure.
Drawing of tank shall be submitted indicating stiffners .

31.1.3 Design of Static End Rings (SER) and Magnetic Shunts : Details
of Static End Rings (SER) and magnetic shunts, if provided, shall be submitted
with the bid with calculations. A drawing indicating locations, size, material of
SER and magnetic shunts shall be submitted with the Bid.

31.1.4 Overfluxing Capability: A curve to prove suitability of transformer to


withstand various Overfluxing conditions for the duration indicated in clause
4.4.1 to 4.4.3 without core saturation shall be furnished with the Bid .

31.1.5 Cooling Calculations: Calculations of tank surface for heat


dissipation, details of radiators, fans for ONAN & ONAF cooling shall be
provided with the bid.

31.2 DESIGN DATA : On the basis of offered flux density and current
density, the Bidder shall furnish following design calculations & data. :

31.2.1 Core Data: Details of core material i.e Name of Manufacturer,


Manufacturer’s type designation for core , thickness of core, curve for Loss Vs
Flux density, No of steps of Core & No of limbs, gross core area , stacking
factor , Net core area ,height & width of core window, center to center
distance of limb, voltage per turn, wt. of core material, working flux density ,
core loss in watts per kg marked on graph for grade of core material &

MPPTCL/TECH/PROC/07/JULY15 57 of 105
Volume-II, Part-7

selected flux density, building factor and calculated no load loss in watts,
guaranteed no load loss.

Design data for core shall be submitted with the bid. A drawing indicating
details of core i.e. limbed construction, step width & thickness , core belting,
top & bottom yoke plate etc shall be submitted with the Bid .

31.2.2 Winding Data : wt. of copper for windings ie. for HV, LV, tap, cross
sectional area ,current density, type of coil, ID/OD/mean dia of coils, size of
winding conductor including parallels, no. of turns per phase, no of spacers,
length of mean turn, weight of copper without paper covering, resistance per
phase of winding at 75 deg C,I2R loss at 75 deg C & normal tap, eddy current
& stray loss at 75 deg C , total copper loss at 75 deg C , guaranteed
transformer losses at 75 deg C.

Complete details of Insulation components i.e. Top & Bottom clamping rings,
washers , Pressboard blocks & cylinders, Pressboard spacers & Phase barriers,
Pressboard segments etc shall be submitted indicating qty , thickness in mm,
width & height , wt. Design data for winding as per clause 31.2.2 shall be
submitted with the bid.

Dimensioned drawings indicating details of winding, ducts, insulation, take off


arrangement, clamping ring, pressure points etc shall be submitted with the
Bid .

31.3 QUANTITY OF OIL : Complete calculations of oil quantity to be utilized


in transformer for first filling shall be submitted. The calculations shall indicate

(i) Volume of tank including turrets, conservator main & OLTC ,volume
of headers & Radiators, oil quantity in OLTC & thermosyphon filter.

(ii) Oil displacement by Active parts i.e. core - coil assembly.

31.4 CAPACITY OF CONSERVATOR & SIZE OF AIR CELL : While furnishing


details of conservator & air cell type sealing arrangement, the Bidder shall
submit details & calculations for adequacy of size and capacity of Pronal make
air cell for the rating of the power transformer and also for the quantity of oil
required. Catalogue of Pronal should be enclosed with the Bid clearly marking
type designation of selected size of Air cell. A drawing indicating complete
details of conservator with Air cell shall be submitted .

31.5 CAPACITY OF PRESSURE RELIEF DEVICE : Our specification calls for


supply of pressure relief device for all power transformers. Bidders must
submit calculation with the bid to prove that the capacity/rating of pressure
relief device and locations of the same for the transformer will adequately
meet our requirement. Constructional and design details of pressure relief
device must be furnished and it should be proved by calculation that the size
and setting of pressure relief device is adequate considering the rating of the
transformer and quantity of oil in the transformer.

A drawing indicating complete details of PRDs & their locations on tank shall
be submitted .

MPPTCL/TECH/PROC/07/JULY15 58 of 105
Volume-II, Part-7

31.6 LIMITS OF TEMPERATURE RISE & HOT SPOT WINDING


TEMPERATURE : The limits of temperature rise for windings, oil and hot spot
have been specified. Temperature rise calculations at rated full load, 110%
load and 125% load considering 100% cooler banks, 50% cooler banks and
without coolers shall be furnished as indicated below :

(a) 100 % Loading : (i) 20 minutes duration - 100 % cooler bank


- 50 % cooler bank
- without cooler bank
(ii) 10 minutes duration - 100 % cooler bank
- 50 % cooler bank
- without cooler bank

(b) 110 % Loading : (i) 20 minutes duration - 100 % cooler bank


- 50 % cooler bank
- without cooler bank
(ii) 10 minutes duration - 100 % cooler bank
- 50 % cooler bank
- without cooler bank
(c) 125 % Loading : (i) 20 minutes duration - 100 % cooler bank
- 50 % cooler bank
- without cooler bank
(ii) 10 minutes duration - 100 % cooler bank
- 50 % cooler bank
- without cooler bank

The calculations shall indicate temperature gradient (for all windings i.e.
HV,LV,tap), load losses at lowest tap for all windings , Eddy current & stray
losses, thermal Constant Value & calculations with parameters affecting the
values for above conditions for top oil temperature & winding hot spot
temperature .

The Calculations for Hot Spot winding Temperature and Calculations for
Temperature Rise shall be submitted with the bid.

31.7 CAPACITY OF FILTER & BREATHER :

31.7.1 NUMBER OF THERMOSYPHON FILTER AND CAPACITY OF EACH


THERMOSYPHON FILTER : The Bidder shall submit details & calculations
for adequacy of size and capacity of thermosyphon filter for the oil
quantity in the power transformer . While furnishing details of thermosyphon
filter arrangements, the Bidder must confirm clearly the number of
thermosyphon filter, its size and capacity is adequate for the rating of power
transformer. The Bidder shall submit details & calculation to prove for
adequacy of size and capacity of thermosyphon filter with the bid.

31.7.2 CAPACITY OF SILICA GEL BREATHER : The Bidder shall submit


details & calculations for adequacy of size and capacity of silica gel breather
for the oil quantity in the power transformer with the bid.

31.8 RATING OF ON LOAD TAP CHANGER (OLTC) : It has been our


experience that due to inadequate rating of OLTC elements, the failure of

MPPTCL/TECH/PROC/07/JULY15 59 of 105
Volume-II, Part-7

OLTC components or pitting of contacts have been observed before the


claimed period for maintenance. To verify the adequacy and suitability of the
OLTC components, it is necessary to furnish the calculations for selecting
the proper rating of transition resistance as well as the normal current
rating of OLTC. The calculations shall include the temperature rise of the
OLTC diverter switch and also the short circuit current considered for
calculation of temperature rise.

Calculations shall be submitted to prove that the current rating of OLTC is


adequate for the rating of the transformer winding taking in to account the
over loading capability as per IS 6600 . The basis for selection of transition
resistance and its current carrying capacity shall also be submitted. In this
regard the circulating current in tap winding during tap change operation
through transition resistance shall be taken in to consideration. Adequacy of
insulation provided in the OLTC between various parts needs to be established
with specific reference to the voltage between two taps. Confirmation shall be
given that the OLTC is suitable for bidirectional flow of current. The through
current capacity shall be adequate to handle on continuous basis the winding
current including over loading as per IS 6600. The through current rating and
the rating of transition resistance shall take in to account the short time
current rating of the winding. Capability to handle short circuit current to be
established by calculations and also by test reports. The above Calculations
for OLTC shall be submitted with the bid.

31.9 Capacity of Nitrogen Cylinder, pressure in Nitrogen Cylinder to be used


during transportation of transformer shall be submitted with the bid.

31.10 The Bidder shall carry out optimization of Dielectric design of


insulation including electromagnetic design, overload & short circuit withstand
capabilities. During design , transformer modeling shall be done & finite
element software (FEM) may be used.

31.11 Please note that submission of above calculations with


technical bid is a must and in absence of the above, the Bid will
be treated as non responsive and rejected. It is assured that these data
will be kept strictly confidential by MPPTCL.

32.0 QUALITY ASSURANCE PROGRAMME : The Bidders must establish


that a proper quality assurance program is being followed by them for
manufacture of power transformers. In order to ensure this, suitable QAP
should form a part of the technical bid, which will be submitted
against this Bid specification. The quality Assurance Program must have
a structure as detailed in the following paragraphs.

32.1 Customers Specifications And Contract Review : The quality


assurance and failure prevention starts with careful study and scrutiny of
our technical specifications and requirements. The supplier shall carefully
study all the technical parameters and other particulars & the supplier shall
categorically give his confirmation that these requirements shall be met
in a satisfactory manner.

MPPTCL/TECH/PROC/07/JULY15 60 of 105
Volume-II, Part-7

32.2 Design Control : The supplier shall furnish the checks


exercised in design calculations particularly in respect of short circuit
forces and method of clamping end coil to show the healthiness of the
design. The salient features of design together with the certificates of
design engineers will have to be made available to the Purchaser.

32.3 Engineering Documents :The supplier shall give complete


information regarding copper conductor, insulating paper, core materials,
tap changer, gaskets etc. bringing out the detailed description and
specification of these items with explanation as to how our requirements are
being met in this respect.

32.4 Procurement Document Control & Purchased Material &


Services : The supplier shall indicate the various sources of the items namely
copper conductor, insulating paper, core material, tap changer and other
items such as gaskets etc. are being procured. The type of checks,
quantum of checks and acceptance norms shall be intimated and random
test and check results should be made available for inspection whenever
so desired. The vendor list for various bought out items shall be submitted
with the Bid and the same shall be subject to purchaser’s approval. However,
no change in vendor list shall be acceptable after placement of order and list
of vendors shall be freezed at the time of placement of order. Furnishing
of following certificates is essential ;
i) Certificate and proof in the form of bill of lading for
purchase of core material either directly from abroad
manufacturers or their accredited selling agent.
ii) Certificate and proof in the form of bill of lading for purchase
of EC grade copper from National & International reputed
manufacturers or from their accredited selling agents.

It will however be obligatory on the part of Bidder to allow third


party inspection of all important material e.g. copper, core material,
Insulating cylinder etc. Bidder shall furnish certificate that the transformer
shall be manufactured with the input material approved by the Purchaser
and in case during independent third party inspection any of the above
material is found different than from approved list of vendors, in that case
Purchaser reserves the right to summarily reject complete transformer
and the manufacturer has to replace complete unit made out from all input
material from the vendors approved by the Purchaser.

32.5 Programme Chart : Based on above QAP and offered delivery


schedule a tentative program chart indicating period for various
manufacturing/testing activities shall be submitted along with QAP . The
program chart should specify periods for various activities i.e. design,
ordering of new materials, assembly, testing etc.

It should be noted by the Bidders that submission of QAP with the Bid
is an essential requirement and such of the Bids wherein QAP is not
found shall be rejected by the Purchaser.

MPPTCL/TECH/PROC/07/JULY15 61 of 105
Volume-II, Part-7

33.0 INSPECTION AND TESTING

33.1 Inspection

33.1.1 The Purchaser shall have access at all times to the works and all
other places of manufacture where the transformers are being manufactured
and the Bidder shall provide all facilities for unrestricted inspection of the
Bidder’s works, raw materials, manufacture of all the accessories and for
conducting necessary tests as detailed herein.

33.1.2 The successful Bidder shall keep the Purchaser informed in advance
of the time of starting and of the progress of manufacture of equipment
at its various stages of manufacturing, so that arrangements could be
made for inspection.

33.1.3 No material shall be dispatched from its point of manufacture


unless the material has been satisfactorily inspected and tested.

33.1.4 The acceptance of any quantity of Transformer & its accessories


shall in no way relieve the successful Bidder of his responsibility for
meeting all the requirement of this specification and shall not prevent
subsequent rejection if such equipments are later found to be defective.
Acceptance of condition regarding stage inspection at various stages which
will be intimated to successful Bidders shall be the essence of the contract to
be placed against this Bid.

33.2. Inspection Programme :The Bidder shall chalk out a detailed


inspection and testing program for manufacturing activities for the various
components. An indicative program of inspection as envisaged by the
Purchaser is given in Annexure-VIII. The Purchaser reserves the right to get
carried out any tests by a third party. All Cost of inspection/tests shall be
borne by the Bidder.

33.3 Stage Inspections

33.3.1 The supplier shall indicate the inspections and checks carried out
at various stages of the manufacture of the transformers. A complete
record of stage inspection would be kept by the supplier and this record
should be made available for inspection by the representative of the
Purchaser. The supplier should indicate the manufacturing program and
the Purchaser will have a right to depute its inspecting officers during
the manufacture. Some of the inspecting stages are tank during fabrication,
coil winding , core building, assembly of coil on core, the condition of the coil
and core after the treatment in vacuum chamber, assembly within the
transformer tank together with application of tap changer.

33.3.2 It may be noted that stage inspection for first unit or all the units
,at our discretion , shall be done by us at the following stages.

MPPTCL/TECH/PROC/07/JULY15 62 of 105
Volume-II, Part-7

(a) Fabrication stage of tank: After fabrication, tank shall be inspected


for measurement of its dimensions, thickness of sheets used and
leakage test by applying requisite pressure/vaccum.
(b) Building up of Core : After the core is built but before its
clamping, our representative will inspect the core to take
complete weight of the core and also to measure approximate core
loss. If necessary, a small strip of core shall also be taken for
testing at CPRI, Banglore or at any other testing lab. of repute
(c) Preparation of Winding : Once the coils are prepared but before
the same are fitted on to the core, stage inspection shall be done
to take various measurements and also for weighment of total weight
of coil of each voltage class. Measurement of resistance shall be taken
and for this purpose, a small piece of conductor for each type of
winding shall be made available by the manufacture.
(d) Core Coil Assembly before & After VPD or Drying out
The Bidder has to submit with the Bid complete details of
Drying out process of transformer adopted in its works. The
details should include cycle, description , termination rate ,
process diagram , size of oven , measurement method of
moisture extracted etc . Failure of the Bidder to comply with
this requirement shall result in rejection of the Bid.
(e) Final Assembly of Transformer after boxing in of active material

Apart from the above, the Purchaser also reserves the right to carry out stage
inspections at other stages also, for which advance intimation shall be
given and all necessary cooperation shall be rendered by the manufacturer.

33.4 Final Inspection and Testing:

33.4.1 At the time of final inspection, the supplier shall identify each
and every item/accessories/fittings of the particular transformer under
testing. Unless all the items are identified, the manufacture will not be
treated as complete. Serial number of bushings, serial number of tap changer
and other accessories shall be entered into the test report to ensure that the
same are supplied with the transformer. Various tests stipulated in IS
shall be performed in the presence of purchaser’s engineers or when the
inspection waiver has been given, in such a case, the testing shall be
done at the manufacturer's works as per IS stipulations and same should
be confirmed by documentary evidence by way of Test Certificate which
shall be got approved by the purchaser.

33.4.2 The WTI & OTI shall be calibrated during testing of transformer
and Serial Nos. of these instruments shall be recorded in test reports.
The WTI & OTI used during testing shall be dispatched with the transformer
so that installation of same OTI & WTI on transformer is done which are
utilized during testing of transformer at suppliers works. The Bushings
and Radiators on Transformer (if heat run test is conducted ) during testing
of transformer at manufacturers works are required to be supplied with the
same transformer to avoid any mismatch / misalignment etc. during

MPPTCL/TECH/PROC/07/JULY15 63 of 105
Volume-II, Part-7

assembly of transformer. This should be noted for strict compliance and


confirmed specifically.

33.4.3 Whenever inspection call for a particular transformer is given, the


letter of inspection call will accompany the following:

a. List of various fittings and accessories which are ready at the works
and will be offered for inspection. The Inspecting Officer will carry
the list and check the items declared to have been offered for
inspection
b. It is expected that before a transformer is finally offered for
inspection, internal testing of the transformer for various
important parameters like winding resistance, transformer
losses, IR values etc are already done. Routine test report for such
tests shall also accompany the letter of inspection call so that the
Inspecting Officer at the time of inspection may verify the
parameters brought out in the preliminary report. Details of all
tests should be clearly brought out.
c. In case for any reasons inspection is not completed or
equipment is not found to be complete with all accessories as per
confirmation given with the letter of inspection call, the
Purchaser will reserve the right to recover the complete cost of
deputation of inspecting team to the works of the manufacturer.

34.0 STORAGE, HANDLING & SHIPPING :

When the transformer is declared ready, the manufacturer has


to identify each and every item associated with this unit and a `Complete
Packing List shall be prepared in advance. The equipments shall be stored
and handled properly in shipping depot, while the same is under process
of dispatch. The manufacturer should ensure dispatch of all the related items
and accessories with a particular unit of transformer along with tank.

Tap changer, bushing, radiators and other accessories of the


transformer should not be withheld for use subsequently on units for testing
purposes. If there are any items procured from sub-contractors which are to
be directly installed like instrumentation, panels, control gear etc. test and
inspection report for the same shall be kept separately and made available to
purchaser’s inspecting officers.

It may be noted that NO CHANGE in any accessory or


associated equipments after passing all the test successfully shall be
allowed and if this is subsequently detected it shall be binding on the Bidder
to replace with the same item with which the initial test were conducted at
his part failing which the entire test shall become null and void. The
Purchaser at his discretion may consider for rejection of the units thus
supplied. The entire cost, for replacement of such rejected units thus
supplied and for repeating acceptance test, shall be borne by the Bidder.

35.0 COMPLETENESS OF EQUIPMENT AND BOUGHT OUT ITEMS

MPPTCL/TECH/PROC/07/JULY15 64 of 105
Volume-II, Part-7

The Bidders must furnish the following information along with


technical bid.

35.1 A list of all the accessories which will be supplied with the
transformer should be furnished. This should be as per Annexure II & III.
While furnishing the list of accessories, items which will be manufactured by
the main manufacturer and balance items, which will be procured from sub-
suppliers should be clearly identified and intimated.

35.2 It is obligatory on the part of Bidder to ensure that supply of all


accessories as per Annexure-II are made alongwith Main Tank or prior to
delivery of Main Tank so that erection and commissioning work of
Transformer can be completed properly and uninterruptedly .The date of
supply of last accessory will be treated as date of delivery of transformer
and penalty shall be imposed upto a maximum of 10 % for delay in supply
and supply bills will be processed accordingly.

35.3 The responsibility for obtaining timely supplies of bought out


items will rest on the Bidder and only on this basis, delivery period will be
offered in the Bid.

35.4 It may be noted that in case of damages/shortages due to


improper packing or any other negligence ,replenishment shall be arranged
within 45 days of being noticed by the purchaser . If this is not done, date
of delivery of such accessory will be treated as date of delivery of main
equipment and full penalty shall be recoverable from the Bidder on total
cost of the equipment. This should be confirmed.

35.5 For bought out items, responsibility for guarantee and obtaining
immediate replacement in case any defects are noticed and in case defective
supply of any item is reported will rest on the Bidder.

35.6 In case for attending to defect in any accessory or inspection/


replacement of the accessory, which may be bought out item for the
Bidder; services of engineer of original manufacturer is required, the same will
be organized on immediate basis by the Bidder at his cost.
35.7 The bidders are required to furnish in their bid, the following details
of packages for supply of complete quantity of materials/one complete
equipment:

i. Total number of packages


ii. Dimensional details of each package.
iii. Weight of each package.
iv. Nature of content (i.e. fragile or non-fragile)

In addition, the bidder from outside India offering CIF prices shall
also indicate the port of entry in India.

36.0 For all power transformer included in the Bid specification ,


provisions and stipulations as per CBIP Manual on Transformers in regard to
the following except as modified in this document should be strictly adopted

a) Design and standardisation.

MPPTCL/TECH/PROC/07/JULY15 65 of 105
Volume-II, Part-7

b) Galvanising.
c) Labels.
d) Nuts & bolts.
e) Cleaning & Painting.
f) Prevention of acidity.
g) Continuous maximum rating & over loads.
h) Duty under faults conditions for stabilizing windings.
i) Flux density and magnetizing current.
j) Vibration & noise.
k) Suppressions of harmonics.
l) Magnetic circuit and mechanical construction of cores.
m) Constructional arrangements for winding.
n) Earthing arrangements.
o) Cooling plant for the transformers.
p) Temperature indicating device and alarm.
q) Gas actuated relays.
r) Marshalling box/control cubicle, panel drives & Mechanism Box
s) Control connection and instrument wiring.
t) Drying out, transport and erection.
u) Valves and air release plugs.

37.0 REQUIREMENT FOR TRANSPORTATION OF TRANSFORMERS:

The Bidders shall include charges for fitting atleast one Electronic
impact recorder (on returnable basis) during transportation of Transformers to
measure the magnitude and duration of the impact in all three directions. The
acceptance criteria and limits of impact in all three directions which can be
withstood by the equipment during transportation and handling shall be
submitted by the supplier during detailed engineering. The recording shall
commence in the factory before despatch and must continue till the unit is
installed on its foundation. The data of electronic impact recorder(s) shall be
down-loaded at site and a soft copy of it shall be handed over to Engineer-
incharge. Further, within three weeks the supplier shall communicate the
interpretation of the data. In the unlikely event of impact recorder output not
available at site, the equipment shall be thoroughly internally inspected by the
manufacturer’s representative before erection at site to ensure healthiness of
the equipment.

Further the supplier shall mount Vehicle tracking system (GPRS/ GPS/
GSM based) to track the exact position of the vehicle on which the power
transformer is being loaded for transportation and during detailed engineering
take approval for the equipment installed.

MPPTCL/TECH/PROC/07/JULY15 66 of 105
Volume-II, Part-7

38.0 Please ensure the bid document containing number of pages


have been properly page numbered and each page is signed by the
Bidder. All bid documents including Annexures should be indexed
properly and Index of the document should be enclosed/placed at
the beginning of the bid document.

MPPTCL/TECH/PROC/07/JULY15 67 of 105
Volume-II, Part-7

ANNEXURE –I
PRINCIPAL PARAMETERS FOR 132/33 KV, 40 MVA
POWER TRANSFORMER
The transformers shall conform to the following specific parameters described
here under :-
No. DESCRIPTION PARAMETERS
1 Type of power transformer/ Two winding, Three phase suitable for
installation out door installation
2 Type of mounting Mounted on rails
Centre to centre distance 1676 mm +
Rail width on both direction i.e
longitudinal and transverse.
3 Suitable for system frequency 50 Hz
4 Rated voltage ratio: HV/LV 132/33 KV
5 No. of phases Three
6 No. of windings Two
7 Type of cooling ONAN/ONAF
8 MVA Rating corresponding to
a. ONAN Cooling (80%) 32 MVA
b. ONAF Cooling (100%) 40 MVA
9 Method of connection HV - Star
LV - Star
10 Connection Symbol (Vector Ynyno
group)
11 System earthing Solidly/ Effectively earthed
12 Percentage Impedances, Voltage 10%
on normal tap and MVA base
corresponding to HV/LV
rating and with
applicable tolerances as per IS
13 Ohmic value of HV/LV short
circuit Impedance as viewed
from HV side
Supplier to furnish
a. Max. Voltage Tapping
b. Minimum Voltage Tapping
c. Normal Voltage Tapping
14 Anticipated continuous loading Not to exceed 110% of its rated
HV and LV capacity.

15 Tap Changing gear


i. Type ON LOAD
ii. Provided on Taps on HV for variation of HV
voltage to provide constant 33 KV
iii. Tap range Voltage.
(-)15% to (+)5%.

MPPTCL/TECH/PROC/07/JULY15 68 of 105
Volume-II, Part-7

No. DESCRIPTION PARAMETERS


iv. Tap step 1.25%
v. Voltage and current rating 66KV/132 KV(Suitable for132KV
neutral end), 300Amp (min.).
16 Over voltage operating capability 110% rated voltage continuous,
and Duration 125% rated voltage for 60 seconds,
140% rated voltage for 5 seconds.
17 Minimum Air core reactance of 20%
HV Windings
18 Minimum knee point voltage 110% rated voltage
19 Flux Density
a. Working Flux density in 1.65 Tesla
any part of core and yoke at
rated MVA, frequency and
normal voltage .
1.90 Tesla
b. Maximum flux density in
any part of core and yoke
at 110% voltage and (-)
4% frequency variation shall
not exceed
20 Insulation levels for windings HV/LV
a. 1.2/50 micro second wave 550/250
shape lightening impulse
withstand(kVp)
230/95
b. Power frequency voltage
withstand(KV rms)
21 Type of winding insulation
a. HV winding Graded
b. LV winding Full
22 System short circuit level and 40 KA for 3 sec. for 132KV
duration for which the 31.5 kA for 3 sec for 33KV
transformer shall be able to
withstand thermal and dynamic
stresses (kA rms/sec)
23 Noise level when energized at As per NEMA-TR1 Standards
rated voltage and frequency but (Copy of NEMA-TR1 Standards to be
without load. furnished)
24 Permissible temperature rise
Over ambient temp of 50 0C
i. of top oil measured by
45C
thermometer
50C
ii. of winding measured by
resistance
25 Minimum clearance in air (mm) PHASE TO PHASE PHASE TO GROUND
a. HV (132) 1430 1270
b. LV ( 33) 700 600

MPPTCL/TECH/PROC/07/JULY15 69 of 105
Volume-II, Part-7

No. DESCRIPTION PARAMETERS


26 Terminals : (Bushings)
a. HV winding line end 145 KV OIP condenser
b. HV/LV winding Neutral end 72.5KV OIP condenser
c. LV winding 72.5KV OIP condenser
27 Max. Radio Interference voltage 1000 micro volt
level at 1 MHz. & 266 kV rms
phase to ground voltage for HV
winding
28 Cooling Equipments :
a. Number of banks Two 50% cooler banks
b. Number of Fans Adequate number of Fans for ONAF
cooling and standby Fans for 20%
additional cooling, in each bank
29 Bushings :
a. Voltage Rating ( KVrms ) 145KV/72.5KV
b Current Rating (Amps) 1250/1250A
c. Insulation level
i. Lightning impulse 650/325
withstand(KVp)
ii. One minute power 275/140
frequency withstand
voltage (KV rms)
3625/1813
iii. Creepage distance (mm)
30 a) Bushing Current Transformer HV LV
for purchaser’s use
i. Type Single phase ring type turret mounted
ii. Current Ratio HV:LV(A/A) 200/1 800/1
iii. Quantity 3 nos 3 nos
iv. Knee point voltage (V) 1000V 1000V
v. Accuracy class PS PS
vi. Secondary resistance (Ohms) As per requirement or < one ohm
vii. No. of cores One One
b) Neutral side C.T. for HVN LVN
Purchaser’s use (for
restricted E/F protection):
i. Type Single phase ring type turret
ii. Quantity mounted
iii. No. of cores 1 no 1 no
iv. Current Ratio (A/A) One One
v. Class of accuracy 200/1 800/1
vi. Max. secondary winding PS PS
resistance As per requirement or < 1.5 ohm

MPPTCL/TECH/PROC/07/JULY15 70 of 105
Volume-II, Part-7

ANNEXURE - II

LIST OF FITTINGS AND ACCESSORIES


TO BE PROVIDED WITH EACH POWER TRANSFORMER.

1. Each transformer shall be provided with the following accessories.


i One no. Dial type Thermometers for oil : A dial type
indicating thermometer with repeater of robust pattern
mounted inside FCC at a convenient height to read the
temperature in the hottest part of the oil and fitted with alarm
and trip contacts. ROTI shall also be mounted on RTCC
panel.
ii Three nos. WTI, two nos. for HV (on extreme phases) &
one no. for LV winding (on middle phase) :
These shall be indicating type, with repeater responsible to
the combination of top oil temperature and winding current,
calibrated to follow the hottest spot temperature of the
transformer winding. The winding temperature indicator shall
operate a remote alarm before the hottest spot temperature
approaches a dangerous value and it shall automatically
actuate the cooling fan Motors.
iii RWTI : These shall be as per cl. 11.10 of Section-I. A
precision potentiometer mounted inside the case shall function
as a transmitter to operate a repeater for RWTI. For HV
winding the transmitter shall be directly connected to the
repeater. For the LV winding the transmitter shall be
connected to a Resistance Transducer, which will supply DC
for operating repeater.
iv One magnetic type oil level gauge with low level alarm
contacts and dial showing minimum, maximum and normal oil
levels for main conservator & OLTC conservator .
v One prismatic oil level guage of overlapped type on MOG side
and one plain oil level gauge of over lapped type on other side
of the main conservator shall also be provided.
vi Valves (As Per Annexure V) In the Annexure-V of valve
schedule, 4 nos. valves are required to be provided in each
Thermosyphon filter. Out of 4 nos., 2 nos. shall be provided
for the purpose of disconnecting the oil flow between the main
tank and Thermosyphon filter and 2 nos. are to be provided
for the purpose of filtration of charge of the Thermosyphon
without disconnecting the Thermosyphon from body .
vii Minimum 3 nos. pressure relief valves. The quantity of these
valves should commensurate with the quantity of oil in the
transformer and also location of valves should be properly
designed to adequately release the excessive pressure.
viii A set of air release valves on the top and on the radiators and
also at appropriate places.

MPPTCL/TECH/PROC/07/JULY15 71 of 105
Volume-II, Part-7

ix One thermometer pocket for mercury in glass type


thermometer.
x One double float gas detector relay(Buchholz relay) with alarm
and tripping contacts to detect accumulation of gas and
sudden changes of oil pressure, complete with shutoff valves
and flanges couplings to permit easy removal without lowering
oil level in the main tank, a blend valve for gas venting, and
test valve. Make of buchholz relay shall be as per our
discretion.
xi Heat exchangers or radiators complete with shut of valves and
with facility for oil draining arrangement.
xii a. Two oil conservator, with required accessories, one for
main tank and other for OLTC. Two nos Silica gel
Breathers with main Conservator & one no. for OLTC
Conservator.
b. Air cell type breathing arrangement with oil preserving
equipment complete in all respects of PRONOL make
only.
xiii Eye bolts and lugs on all parts for easy handling.
xiv Two grounding earthing terminals at diagonally opposite
corner of tank.
xv One rating and diagram plate.
xvi A set of minimum 4 nos. flanged bi-directional wheels for rail
mounting (for 1676 mm rail gauge.)
xvii Set of fans required for ONAF cooling of the transformer with
following information
a. Number of Radiator Banks.
b. Required no of cooling fans (Industrial duty of
adequate voltage & rpm) be provided in each bank to
ensure 100% ONAF rating of the transformer. As per
our specification, for each bank 20% additional cooling
fan is to be included which will be duly wired-up.
xviii Suitable jacking lugs and haulage holes.
xix Inspection window & main holes with bolted cover as per
Annexure-IV.
xx Adequate no of Thermosyphon filter assembly (minimum 2
nos) with suitable supports, valves and pumps for forced but
slow circulation of Transformer oil .
xxi Lifting arrangement for the complete transformer, core coil
assembly and also tank.
xxii One detachable bolted type MS ladder each on main tank and
conservator tank.
xxiii For the purpose of taking earthing connection from the
neutral bushing, adequate number of brackets with small

MPPTCL/TECH/PROC/07/JULY15 72 of 105
Volume-II, Part-7

support insulators shall be provided on the body of the tank


so that earthing could be arranged by Purchaser near the
earthing pit of transformer itself.
xxiv A separate weather proof FCC (Fan/Cooler control) cubicle
containing dial type thermometer and winding temperature
indicator and terminals of dial type thermometer, winding
temperature indicator, buchholz relay, MOG, control of fans
etc.
Please note provision of separate Fan Control Cubicle (FCC)
is a must. FCC shall be suitably dimensioned to accommodate
the following :-
a The wiring from RTCC shall be brought to marshalling box
and for terminating the same adequate numbers of
suitably rated terminal connectors shell be provided.
b Necessary cable glands shall be included in the scope of
supply. The cable gland and the hole on gland plate for
cable entry shall be provided.
c Arrangement for terminating the connecting leads of
OTI, WTI, buchholz, magnetic oil level gauge etc. shall be
made in the marshalling box. It should be possible to
read OTI and WTI readings without opening the box
through suitable glass window. All trip alarm and
repeater signals will be transferred to control room for
which arrangement will have to be made.
d Starters for cooling fans shall be housed in marshalling box
and necessary switches for local operation of fans shall be
provided.
e Local remote control switch for OLTC shall be provided.
f Space heater with switch, cubicle illumination lamp,
fuses, links overload protection arrangement for motors
and other accessories shall be included in the scope of
supply.
xxv One set of indoor RTCC (Remote tap changer control) cubicle
complete with provision for remote operation of OLTC, as
independent or master/follower scheme, with oil and
winding temperature repeater, tap position indicator with
annunciation for fan group ON/OFF and cooler supply fail
indication and Tap changer in progress including OTI repeater
& WTI remote indicator operated by remote sensors.
xxvi One set of erection manual/relevant drawing/leaflets should be
secured permanently inside the RTCC cubicle as a guide line for
site erection and commissioning.
xxvii Three separate connection i.e. connection from core,
connection from end frame and connection from tank shall
be brought out on to a terminal box with cover. Arrangement
for inter connecting these terminals in the terminal box shall also

MPPTCL/TECH/PROC/07/JULY15 73 of 105
Volume-II, Part-7

be provided. This arrangement shall facilitate verification of


core, end frame and tank insulation.
xxviii Mounting of radiators on the 33KV side of 72.5KV
bushing should be avoided. In no case, the radiators
should be projected above the main tank height.
xxix All transformers shall be supplied with a full outfit of tools,
spanners, jacks, special tools as per Annexure IX for
assembly and all spanners shall be double ended and of very
good quality of " Gedore " or "Taparia " or equivalent make.

2. The equipments and accessories furnished with the transformer


shall be suitably mounted on the transformer for ease of operation, inspection
and maintenance and the mounting details shall be subject to the approval
of the purchaser. All valves shall be provided either with blind companion
flanges or with pipe plugs for protection.

3. Indication, alarm and relay equipment shall have contacts suitable for
operation with 110V/220V DC supply. Any other accessories or appliances
recommended by the manufacturer for the satisfactory operation of the
transformer shall also have 110V/220V DC as input.
4. a. OLTC and its controls shall be as per clause 14 Section-I
of specification.
b. All cabinets & panels shall be conforming to
stipulations under Clause-16 of Section -I of specifications.
c. All 132KV, 33KV and neutral bushings shall be of OIP
condenser type and as per Clause 11.13 of Section I of
specification.
5. Provision for Measurement of Degree of Polymerisation of
Insulation of Winding of Transformer :- To assess the life of paper
insulation of winding , a provision is to be made inside the transformer . For
this purpose, a container of insulating material of good electrical, mechanical
& chemical properties having free circulation of oil through it shall be provided
at suitable location where maximum oil temperature is expected. In the
container, atleast 10-12 spools of paper having size not more than one cm be
placed . The container shall be closed and there should not be any possibility
of spools coming out from the container due to natural circulation as well
turbulence of oil during fault etc.
Location of the container shall be selected such that spools may be
removed from the container as and when required by the purchaser during
service of transformer for the purpose of testing of insulating material for
“Degree of Polymerisation” (DP test).

6. COMPATABILITY FOR SCADA OPERATIONS :

The transformer should be compatible for SCADA connectivity.


Further, TPI, ROTI and RWTIs shall suit the following operation through
SCADA.

MPPTCL/TECH/PROC/07/JULY15 74 of 105
Volume-II, Part-7

1. TPI indication on SCADA.


2. Winding Temperature Indications on SCADA.
3. Oil Temperature Indication on SCADA.

The necessary fittings required for above SCADA operation are to be


provided in addition to the conventional fittings.

7. Control cables of adequate length for body protection (viz. Buchholz


relay/PRV etc.) needs to be laid on the tank cover /wall through appropriate
arrangement using cable trays for termination of either ends with proper
leveling.

8. Accessories, which are not included in the above Annexure


but details of which are given in bid specification and which are
necessary for satisfactory operation of transformer shall be deemed
to have been included in the accepted price without any extra cost
to the purchaser.

MPPTCL/TECH/PROC/07/JULY15 75 of 105
Volume-II, Part-7

ANNEXURE -III

LIST OF TRANSFORMER ACCESSORIES AND THEIR TEST-


CERTIFICATES
TO BE SUBMITTED BY MANUFACTURERS/APPROVED VENDORS

S. Accessory Ref. Std. Test-certificates required


No.
1 Condenser IS2099, 1. Appearance, construction and dimensional
Bushing IEC60137 check
2. Test for leakage of internal filling at
a pressure of 1.0 kg/cm2 for 12hours.
3. Insulation resistance IS 2099
measurement with 2000V megger.
4. Dry/wet power frequency voltage
withstand test.
5. Dry/wet power frequency voltage
withstand test for test tap insulation
6. Partial discharge measurement up to 1.5
UN/_/3 KV.
7. Measurement of tangent delta and
capacitance.
2. Pronol IEC 1. Dimensional check,
inflation/Deflation at 10
inflation/Deflation at 10 KPa
2. Pressure test at 10 KPa for 24 Hr.
3. OLTC IS 2026 1. Oil tightness test for the 8468 diverter
part I, switch oil chamber at an oil pressure of
IEC 60214 0.5 kg/cm2 at 100 degree centigrade for 1
hour.
2. Mechanical operation test.
3. Operation sequence measurement
4. Insulation resistance measurement using
2000V megger
5. Power frequency voltage withstand test on
diverter switch to earth and between even
and odd contacts.
6. Power frequency voltage withstand test
on tap selector-between stationary
contacts, between max. and min. taps,
between phases and supporting frames,
between phases.
7. Operation test & dielectric test of complete
OLTC.
4. Winding IS 1. Calibration test
Temp 2. Dielectric test at 2 kV for one minute.
Indicator & 3. Accuracy test for indication and switch
Oil Temp

MPPTCL/TECH/PROC/07/JULY15 76 of 105
Volume-II, Part-7

S. Accessory Ref. Std. Test-certificates required


No.
Indicator setting scales.
4. Test for adjustability of switch setting
5. Test for switch rating
6. Measurement of temperature rise with
respect to the heater coil current.
5. Pressure IS13947 1. Functional test with Compressed air to
Relief valve check bursting pressure, indicating flag
operation and switch operation.
2. Dielectric test at 2 KV for one minute.
3. Switch contact testing at 5A, 240 Volt AC.
4. Leakage test at 75% operating pressure
for 1Hr.
6. Cooling Fan IS 2312 1. Appearance, construction and dimensional
and motor check.
assembly 2. Insulation resistance measurement
3. Dielectric test at 1.5 KV between
winding and body for one minute
4. Operation check.
5. Power consumption, RPM, Current.
7. Buchholz IS:3407 1. Leak test with transformer oil at a
Relay pressure of 3 kg/cm2 for 30 minutes at
ambient temperature for relay casing.
2. Insulation resistance measurement with
500V megger.
3. Dielectric test at 2 kV for 1 minute
4. Elements test at 1.75 kg/cm2 for 15
minutes using transformer oil at ambient
temperature.
5. Loss of oil and surge test.
6. Gas volume test
7. Mechanical strength test
8. Velocity calibration test
9. Appearance construction and dimensional
check.
8. Oil Level IS 1. Appearance, construction and dimensional
gauge check
including 2. Dielectric test at 2 KV for 1 minute
MOG 3. Switch contact test at 5A 240V AC
4. Switch operation for low level alarm
5. Test for oil levels
9. Pressed Steel IS513 1. Appearance, construction & dimensional
Radiators check.
2. Air pressure test at 2 kg/cm2 under
water for 15 minutes

MPPTCL/TECH/PROC/07/JULY15 77 of 105
Volume-II, Part-7

S. Accessory Ref. Std. Test-certificates required


No.
10. OLTC Control IS 1. Appearance, construction & dimensional
cubical/Cooler check.
Control 2. Electric operation
cubicle 3. Insulation resistance measurement using
500 V meggar at ambient temperature
4. Dielectric test at 2kV for 1 minute
11. Bushing IS: 2705 1. Appearance, construction & dimensional
Current check. Polarity Check, Measurement of
Transformers insulation resistance.
2. H V power frequency test.
3. Determination of ratio error and phase
angle of measuring and protection BCTs
4. Interturn insulation test
5. Exciting current characteristic test,
Secondary winding resistance
measurement
12. Terminal IS5561 1. Dimensional check construction
connector 2. Tensile test, resistance test
3. Galvanisation test as per IS 2633 on
galvanized parts .
13 Silica Gel IS 1.Pressure tests
Breather 2. Visual & dimension tests
3. Operation test
4. silica gel test
5. Oil compatibility test

MPPTCL/TECH/PROC/07/JULY15 78 of 105
Volume-II, Part-7

ANNEXURE-IV

SCHEDULE OF INSPECTION COVER/ACCESS WINDOWS

Size
(Length x Qty.
No. Particulars
Width) (Nos.)
(mm x mm)

1 Inspection cover (man hole) 450x900 1

Inspection cover/ Access Window


2 400x900 1
for OLTC

Inspection cover/ Access Window


3 500X500 3
for HV Bushing

Inspection cover/ Access Window


4 500x500 3
for LV Bushing

Inspection cover/ Access Window


5 500x500 2
for Neutral Bushing .
Inspection cover/ Access Window
for inspection of active parts /
6 As per design requirement
connections etc. as per
manufacturer’s design
Inspection cover/ Access Window
7 for visual inspection internal As per design requirement
parts

MPPTCL/TECH/PROC/07/JULY15 79 of 105
Volume-II, Part-7

ANNEXURE-V

SCHEDULE OF VALVES

Item Description of Valves Size Qty Type


(Design)
1 Oil inlet valve for Radiator header 200NB 2 Gate valve
2 Oil outlet valve for Radiator header 200NB 2 Gate valve
3 Top Oil filter valve 50NB 2 Gate valve
4 Bottom Oil filter valve 50NB 4 Gate valve
5 Top oil sampling valve 15NB 1 Globe valve
6 Bottom oil sampling valve 15NB 1 Globe valve
7 Drain plug bottom tank 25NB 2
8 Drain valve (Tank) 100NB 1 Butterfly valve
9 Drain valve (Tank) 100NB 1 Gate valve
10 Radiator Isolating valve 100NB As per Butterfly valve
11 Drain plug on radiators ½ ” Bsp design

12 Air release plug on radiators ½ ” Bsp


13 Drain cum filter valve on header 50NB 4 Globe valve
14 Drain plug on header ½ ” Bsp 4 --
15 Air release plug on header ½ ” Bsp 4
16 Drain plug on inlet pipe ½ ” Bsp 2
17 Drain plug on outlet pipe ½ ” Bsp 2
18 Air release valve on tank cover 15NB 2 Gate valve
19 Pressure release valve (Main tank) 150NB 3
20 Valve for DGA 25NB 2 Gate valve
21 Thermosyphon drain valve 15NB 2 Globe valve
22 Thermosyphon filter valve 50NB 4 Gate valve
23 Drain plug on Thermosyphon filter ½ ” Bsp 2
24 Air release plug on Thermosyphon ½ ” Bsp 2
filter
25 Thermosyphon isolating valve 100NB 4 Butterfly valve
26 Oil surge relay isolating valve 25NB 2 Globe valve
27 OLTC equalizing valve 15NB 1 Gate valve
28 OLTC suction valve 25NB 1 Globe valve
29 OLTC Conservator drain valve 15NB 1 Globe valve
30 Buccholz relay isolating valve 80NB 2 Gate valve
31 Valve for Vacuum breaking during oil 25NB 1 Gate valve
filling
32 Gas Sampling valve ¼” Bsp 2 Gate valve

MPPTCL/TECH/PROC/07/JULY15 80 of 105
Volume-II, Part-7

Item Description of Valves Size Qty Type


(Design)
33 Main conservator Drain valve 50NB 1 Gate valve
34 Main conservator Air release valve 25NB 1 Gate valve
35 Main Breather isolating valve 25NB 1 Gate valve

* NOTE: 1. All valves shall have position indicators to indicate the status i.e.
valves are in open or shut position.
2. All valves shall be made of gun metal (GM); cast iron valves are
not acceptable.
3. All plugs shall be made of cast iron (CI)/GM
NB- Normal Bore – mm.

MPPTCL/TECH/PROC/07/JULY15 81 of 105
Volume-II, Part-7

ANNEXURE –VI(A)

DRAWINGS AND DATA TO BE FURNISHED BY THE BIDDER.

The following drawings and data for each items are to be submitted
with the Bid

(a) Outline dimensional drawings of transformer and its accessories


including conservator complete with Bill of material and details of
all parts, their quantity, rating & name of Vendors indicating
clearances of transformer body from live terminals i.e. HV,LV.

(b) Drawing of transformer tank with location of inspection windows,


thickness of side/bottom/top of tank, details of stiffener.

(c) Drawing indicating limbed core construction with complete details of


no., width and wt. of core laminations with size of steps; thickness of
core laminations ; dimension of window; size of limbs; Gross and net
core ; wt. of complete core.

(d) Drawing indicating core belting arrangement with details of belting,


belting material etc.

(e) Large scale dimensioned drawings for HV & LV windings of the


transformer; size and no. of parallel of HV, LV and of cooling ducts,
coil clamping arrangement, no./size & location of pressure screws,
clamping ring; top yoke arrangement etc. The details should
commensurate with the short circuit calculations submitted by you for
each rating of transformer

(f) Detailed drawing of transformer tank with complete core and winding
indicating clearances inside transformer tank as also passage and
space for free movement of at least two persons for inspection of
active parts etc .

(g) Schematic diagram showing the flow of oil in the cooling system as
well as each limb and winding. Longitudinal and cross-sectional views
showing the duct sizes, cooling pipes etc. for the
transformers/radiators drawn to scale .

(h) Drawings giving the weights for foundations.

(i) Combined Rating and diagram plate including tap changing, which
should also include details of guaranteed and measured no load and
load losses as also winding resistances and percentage impedances at
all taps.

(j) Schematic control and wiring diagram for all auxiliary equipment
and control cubicle.

(k) Drawing showing constructional details, dimensions, mechanical


& technical particulars of bushings. Arrangement of terminals and

MPPTCL/TECH/PROC/07/JULY15 82 of 105
Volume-II, Part-7

details of connection of bushing shall also be indicated in drawing with


their technical particulars.
(l) Transportation drawing of transformer.
(m) Details of fittings and cable box.
(n) Drawing showing arrangement and details of tap changing gear
including selector switch, diverter switch and drive mechanism.

(o) Valve Schedule plate.


(p) Oil filling instruction plate for conservator fitted with Air cell breather
arrangement including equalizing arrangement if any required at
the time of taking full Vacuum at site.

(q) Drawing and instruction for fitting of Air Cell.


(r) Drawing of conservator indicating internal details of air cell MOG, oil
level gauge and silica gel breather pipe fitting arrangement.

(s) Drawings of all HV & LV bushings with complete details meeting TS


requirement.

(t) Drawings of HV,LV & neutral terminal connectors indicating plate


thickness, no. of nut bolts with size and other details.

(u) Drawing of foldable & detachable ladder with its complete details and
fitting arrangement on transformer/ conservator tank.

(v) Drawing for HV/LV neutral earthing arrangement indicating voltage


rating of insulators and its fitting arrangements, size of copper strips,
terminal connectors etc.

(w) Detailed drawing indicating two views of all valves provided in the
transformer tank.

(x) Drawing of Thermosyphon filter with fixing arrangement with


transformer tank.

(y) Detailed internal drawing of transformer indicating transportation


locking arrangement provided to avoid shifting of core assembly.

(z) Drawing showing weights of transformers, cooling fan structures, FCC


structures with distance from central line of transformer for casting of
civil foundation for transformer and associated equipments.

(aa) Drawing of Earthing terminal box showing earthing arrangement for


core, end frame, tank giving details of voltage class and current rating
of terminal bushings.

(ab) Drawing indicating insulation thickness details and other arrangement


provided between core assembly and bottom yoke and base of bottom
of tank.

(ac) Drawing indicating details of ‘O’ ring gasketting arrangement provided


in transformer tank covers.

MPPTCL/TECH/PROC/07/JULY15 83 of 105
Volume-II, Part-7

(ad) Detailed Drawing of jacks.


(ae) Drawing of stiffeners provided on top, each faces/sides of tank with
their number and size.

(af) Drawing indicating number, location, size of shields/ magnetic shunts


and its material provided inside the tank as per clause 11.1 (g).

(ag) Drawing indicating internal details of transformer giving complete


details of clearances from live parts.

(ah) Drawing of internal LV winding termination arrangement indicating


minimum clearance between core and LV take off lead.

(ai) Drawing of Neutral Current Transformer with details of its mounting


arrangement.

(aj) Drawing for Lead termination to bottom of HV & LV bushings.

(ak) Internal drawing & design of Core & Winding indicating all attachment
with identification numbers, description including take-off arrangement
of lead connection for Core & End frame and related Bill of Material

(al) Locking arrangement drawing for tank top cover, core & winding with
complete dimension & details.

(am) Plan view of the bottom of Bell Tank for complete details of core coil
resting arrangement, indicating clearly dimensional details, material of
insulation, clamping arrangement with details of nuts/ bolts, clearance
from all sides provided at bottom.

(an) Drawing indicating complete details, dimension & mounting


arrangement of OLTC inside the tank with respect to End frame.

(ao) Drawing indicating complete details, dimensions & fixing arrangement


of static end rings if used.

(ap) Other relevant drawings.

As soon as possible after the award of the contract the manufacturer shall
supply four (4) copies of the drawings as listed out above, which will
describe the equipment in details for approval and shall subsequently
provide ten complete sets of final drawings, one of which shall be auto-
positive suitable for taking blue prints. Ten sets of instruction books,
operation and maintenance manuals and spare part bulletin, shall be
supplied. In addition to above two sets of manuals and drawings with test
certificates for each unit to be despatched as per despatch instructions.

MPPTCL/TECH/PROC/07/JULY15 84 of 105
Volume-II, Part-7

ANNEXURE – VI (B)

LIST OF DRAWINGS TO BE FURNISHED ALONGWITH BID AND


DETAILS TO BE SUBMITTED WITH THE BID

S.No. Particulars
1 OGA drawing of transformer
2 List of fittings & accessories for OGA
3 Drawing for HV,LV , neutral OIP Condenser bushings
4 Makes of various accessories and source of raw material
5 Universal type bimetallic terminal connector for HV,LV, Neutral
6 Conservator with air cell breathing arrangement
7 Thermosyphon filter assembly with pump & without pump
8 Internal clearances detailed drawing
9 Dimensional details for transportation of transformer.
10 Radiator arrangement
11 Core earthing arrangement box
12 Yoke binding details
13 Neutral earthing arrangement
14 Foundation details
15 List of tools & tackles
16 Bottom locking & insulating arrangement
17 Core insulation details
18 MS Ladder
19 Sealing arrangement between top & bottom shell.
20 OLTC Conservator with breather arrangement
21 Drawings for various types of valves.
22 Core shunt fixing arrangement
23 Rating & diagram plate
24 Valve schedule plate
25 Oil filling instruction plate for conservator with air cell.
26 Roller assembly with anit-earthquake arrangement
27 Coil clamping arrangement
28 Oil flow diagram
29 Winding details arrangement with dimension
30 Core details with design data
31 Over fluxing curve
32 Drawing for tank stiffener & magnetic shunt inside transformer with
calculation.
33 Schematic drawings for OLTC, FCC & RTCC .
34 Cooler control cubicle cum marshalling box with schematic
35 RTCC panel drawing
36 Drawing for static end ring
37 Complete dimensioned details of bottom tank

MPPTCL/TECH/PROC/07/JULY15 85 of 105
Volume-II, Part-7

ANNEXURE VII

DESIGN CALCULATIONS & DESIGN DATA REQUIRED


TO BE ENCLOSED WITH THE BID FOR POWER TRANSFORMER

It should be specifically noted by the Bidders that submission of


following Design Calculations & Design Data with the offer is
necessary and bids wherein these calculations are not found enclosed
shall run risk of rejection.

(1) SHORT CIRCUIT WITHSTAND CAPABILITIES : The calculations to


prove dynamic and thermal short circuit withstand capability of transformer
as per clause 31.1.1 shall be submitted for the fault level indicated as
under:

132KV - 40 KA for 3 secs.


33KV - 31.5KA for 3 secs.

Results of calculations shall be submitted with the bid. The design of winding
assembly, which is to be furnished in the drawing as per Sr. No. (e) of
Annexure VI(A) should be commensurating with these calculations. The
details of clamping ring shall be indicated in the drawing .

(2) DESIGN DATA OF CORE & WINDING : On the basis of offered flux
density and current density, the Bidders shall furnish furnish following
design calculations & data. Calculations regarding wt. of core & copper and
also calculations for losses will be brought out to justify the offered
transformer losses. :

(A) Core Data: Details of core material i.e Name of Manufacturer,


Manufacturer’s type designation for core , thickness of core, curve for
Loss Vs Flux density, No of steps of Core & No of limbs, gross core area
, stacking factor , Net core area ,height & width of core window, center
to center distance of limb, voltage per turn, wt. of core material,
working flux density , core loss in watts per kg marked on graph for
grade of core material & selected flux density, building factor and
calculated no load loss in watts, guaranteed no load loss. Design data for
core as per clause 31.2.1 shall be submitted with the bid. A drawing
indicating details of core i.e. limbed construction, step width & thickness
, core belting, top & bottom yoke plate etc shall be submitted with the
Bid .

(B) Winding Data: wt. of copper for HV,LV, tap , cross sectional area ,
current density, type of coil, ID/OD/mean dia of coils, size of winding
conductor including parallels, no. of turns per phase, no of spacers,
length of mean turn, weight of copper without paper covering, resistance
per phase of winding at 75 0C, I2R loss at 75 0C & normal tap, eddy
current & stray loss at 750C, total copper loss at 750C, guaranteed
transformer losses at 75 0C.

MPPTCL/TECH/PROC/07/JULY15 86 of 105
Volume-II, Part-7

Complete details of Insulation components i.e. Top & Bottom clamping


rings, washers , Pressboard blocks & cylinders, Pressboard spacers &
Phase barriers, Pressboard segments etc shall be submitted indicating
qty , thickness in mm, width & height , wt. Design data for winding as
per clause 31.2.2 shall be submitted with the bid.

Dimensioned drawings indicating details of winding , ducts, insulation ,


take off arrangement, clamping ring , pressure points etc shall be
submitted with the Bid .

(3) DESIGN OF TANK : Complete mechanical design of transformer tank


including details of stiffeners as per clause 31.1.2 shall be submitted . The
tank shall be designed to withstand the following without permanent
distortion.
(i) Mechanical shocks during transportation.
(ii) Vacuum filling of oil at 10 milli torr in transformer with all fittings.
(iii) Continuous internal pressure of 35 kN/m2 over normal hydrostatic
pressure of oil.
(iv) Short circuit forces &
(v) Under seismic condition /events both horizontal/vertical .

The calculations for tank stiffeners shall be submitted with the bid to prove
no. & size of stiffeners are adequate to withstand full vacuum & pressure .
Drawing of tank shall be submitted indicating stiffners .

(4) DESIGN OF STATIC END RINGS (SER) AND MAGNETIC SHUNTS :


Details of Static End Rings (SER) and magnetic shunts , if provided , with
calculations as per clause 31.1.3 shall be submitted with the bid. A drawing
indicating locations, size, material of SER and magnetic shunts shall be
submitted with the Bid .

(5) QUANTITY OF OIL : Complete calculations of oil quantity to be utilized


in transformer for first filling shall be submitted with the bid. The calculations
shall indicate

(i) Volume of tank including turrets, conservator main & OLTC ,volume
of headers & Radiators, oil quantity in OLTC & thermosyphon filter.

(ii) Oil displacement by Active parts i.e. core - coil assembly,

(6) CAPACITY OF CONSERVATOR & SIZE OF AIR CELL : While furnishing


details of conservator & air cell type sealing arrangement, the Bidder shall
submit details & calculations for adequacy of size and capacity of Pronal
make air cell for the rating of the power transformer and also for the
quantity of oil required with the bid. Catalogue of Pronal should be enclosed
with the Bid clearly marking type designation of selected size of Air cell. A
drawing indicating complete details of conservator with Air cell shall be
submitted .

MPPTCL/TECH/PROC/07/JULY15 87 of 105
Volume-II, Part-7

(7) CAPACITY OF PRESSURE RELIEF DEVICE : Bidders must submit


calculation with the bid to prove that the capacity/rating of pressure relief
device and locations of the same for the transformer will adequately meet our
requirement. Constructional and design details of pressure relief device must
be furnished and it should be proved by calculation that the size and
setting of pressure relief device is adequate considering the rating of the
transformer and quantity of oil in the transformer. A drawing indicating
complete details of PRDs & their locations on tank shall be submitted .

(8) CALCULATIONS FOR TEMPERATURE RISE & HOT SPOT WINDING


TEMPERATURE : The limits of temperature rise for windings, oil and hot spot
have been specified in Volume II . Temperature rise calculations at rated full
load, 110% load and 125% load considering 100% cooler banks, 50% cooler
banks and without coolers shall be furnished as indicated below :

(a) 100 % Loading : (i) 20 minutes duration - 100 % cooler bank


- 50 % cooler bank
- without cooler bank
(ii) 10 minutes duration - 100 % cooler bank
- 50 % cooler bank
- without cooler bank
(b) 110 % Loading : (i) 20 minutes duration - 100 % cooler bank
- 50 % cooler bank
- without cooler bank
(ii) 10 minutes duration - 100 % cooler bank
- 50 % cooler bank
- without cooler bank
(c) 125 % Loading : (i) 20 minutes duration - 100 % cooler bank
- 50 % cooler bank
- without cooler bank
(ii) 10 minutes duration - 100 % cooler bank
- 50 % cooler bank
- without cooler bank

The calculations shall indicate temperature gradient (for all windings i.e.
HV,LV,tap), load losses at lowest tap for all windings , Eddy current & stray
losses, thermal Constant Value & calculations with parameters affecting the
values for above conditions for top oil temperature & winding hot spot
temperature .The Calculations for Hot Spot winding Temperature and
Temperature Rise shall be submitted with the bid.

(9) COOLING CALCULATIONS : Calculations of tank surface for heat


dissipation, details of radiators, fans for ONAN & ONAF cooling shall be
provided with the bid.

(10) OVERFLUXING CAPABILITY: A curve to prove suitability of


transformer to withstand various Overfluxing conditions for the duration
indicated in clause 4.4.1 to 4.4.3 without core saturation shall be furnished
with the Bid.

MPPTCL/TECH/PROC/07/JULY15 88 of 105
Volume-II, Part-7

(11) CAPACITY OF FILTER & BREATHER :

(A) Number and Capacity of each Thermosyphon Filter : The Bidder


shall submit details & calculations for adequacy of size and capacity of
thermosyphon filter for the oil quantity in the power transformer.
While furnishing details of thermosyphon filter arrangements, the
Bidder must confirm clearly the number of thermosyphon filter, its size
and capacity is adequate for the rating of power transformer. The
Bidder shall submit details & calculation to prove for adequacy of size
and capacity of thermosyphon filter with the bid.

(B) Capacity of Silica Gel Breather : The Bidder shall submit details &
calculations for adequacy of size and capacity of silica gel breather
for the oil quantity in the power transformer with the bid.

(12) RATING OF ON LOAD TAP CHANGER (OLTC) : To verify the


adequacy and suitability of the OLTC components, it is necessary to
furnish the calculations for selecting the proper rating of transition
resistance as well as the normal current rating of OLTC. The
calculations shall include the temperature rise of the OLTC diverter
switch and also the short circuit current considered for calculation of
temperature rise.

Calculations shall be submitted to prove that the current rating


of OLTC is adequate for the rating of the transformer winding taking in
to account the over loading capability as per IS 6600 . The basis for
selection of transition resistance and its current carrying capacity shall
also be submitted. In this regard the circulating current in tap winding
during tap change operation through transition resistance shall be
taken in to consideration. Adequacy of insulation provided in the OLTC
between various parts needs to be established with specific reference
to the voltage between two taps. Confirmation shall be given that the
OLTC is suitable for bidirectional flow of current. The through current
capacity shall be adequate to handle on continuous basis the winding
current including over loading as per IS 6600. The through current
rating and the rating of transition resistance shall take in to account the
short time current rating of the winding. Capability to handle short
circuit current to be established by calculations and also by test
reports. The above Calculations for OLTC shall be submitted with the
bid

(13) Capacity of Nitrogen Cylinder, pressure in Nitrogen Cylinder to be used


during transportation shall be submitted with the bid.

Note : Bidders may please note that submission of above


calculations & design data as mentioned in clause 31 and in this
Annexure with technical bid is an essential requirement of
the Bid.

MPPTCL/TECH/PROC/07/JULY15 89 of 105
Volume-II, Part-7

ANNEXURE VIII

DETAILS OF INSPECTION PROGRAMME

1. INSPECTION PROGRAMME :

1.1 Manufacturer shall chalk out a detailed inspection and testing


programme for various manufacturing activities for the different
components, fittings & accessories. The MPPTCL also reserves the right to
carryout any tests by a third party at its sole discretion. All Costs of
inspection/ tests shall be borne by Manufacturer.

2.2 STAGE INSPECTIONS :

2.2.1 Manufacturer shall indicate the inspections and checks carried out at
various stages of the manufacture of the transformer. A complete record of
stage inspection shall be kept by Manufacturer and this record shall be made
available for inspection by the representative of the MPPTCL. Manufacturer
shall indicate the manufacturing programme and the MPPTCL will have a right
to depute its inspecting officers during the manufacture. The inspecting stages
shall be Fabrication of Tank & Conservator, core building, coil winding ,
assembly of coil on core, the condition of the coil and core after the
treatment in vacuum chamber, assembly within the transformer tank
together with application of tap changer etc .

2.2.2 It may be noted that stage inspections for all the units shall be done
by us at the following stages as per the different formats enclosed :

(i) STAGE I : Stage Inspection of Transformer Tank and Conservator


after fabrication. After fabrication, tank & conservator shall be inspected for
measurement of its dimensions, thickness of sheets used and leakage test by
applying requisite pressure.
In this stage following shall be measured ,recorded & checked in Format I
(A,B,C) .

(A) Format I (A) : Inspection of Tank & Conservator

a) Certification of chemical composition and mechanical properties


of plates.
b) Welder's and weld procedure qualification.
c) Testing of electrodes for quality of base materials as per ASME.
d) Dimensional check and visual Inspection of weld .
e) Crack detection, of major strength weld seams by dye
penetration test.
f) Measurement of film thickness of inside and outside of X'mer tank
and conservator
i) Oil insoluble varnish
ii) Zinc chromate paint
iii) Light grey paint
g) Check correct dimensions between wheels, rotation of wheels
through 90 deg.

MPPTCL/TECH/PROC/07/JULY15 90 of 105
Volume-II, Part-7

h) Check for physical properties of materials for lifting lugs, jacking


pads, etc. All load bearing welds including lifting lug and jacking
parts shall be subjected to DP test.
i) Leakage test of conservator and tank.
j) Pressure and vacuum test of tank.
k) Surface cleaning by sand or shot blasting.
l) Certification of all test results.

(B) Format I (B) : Inspection of Valves as per Schedule of Valves

(C) Format I (C) : Inspection of Tank for Inspection Windows.

(ii) STAGE II : Stage Inspection of Transformer Core during Core


Building : After the core is built but before its clamping,
MPPTCL representative shall inspect the core to take complete
weight of the core and also to measure approximate core loss. If
necessary, a small strip of core shall also be taken for testing at CPRI,
Bangalore at our discretion or at any other testing lab. of repute for
measurement of specific loss .

During this stage, following documents shall be verified by our


inspector as a proof towards use of prime core material material for
manufacturer of transformer ordered by us .
i) Invoice of the supplier
ii) Mills test certificate
iii) Packing list
iv) Bill of lading
v) Bill of entry certificate by custom's.

The core material shall be directly procured either from the


manufacturer or through their accredited reputed marketing
organisation but not through any agent. A copy of all above
documents shall be sent with joint inspection report for MPPTCL
records.

In this stage, following shall be measured, recorded & checked in


Format II (A,B,C)

(A) Format II (A) : Report in respect of Raw material viz core,


copper, insulating material ,tank steel etc.: Details of various raw
material shall be recorded viz. Name of Supplier/Sub supplier, Test
Certificate, QAP Report , Invoices, Bill of Lading ,bill of entry etc.

(B) Format II (B) : Report in respect of Accessories: Details of


accessories Viz Buchholz relay, Pressure Relief device, Axles and
wheels, Winding and oil temperature indicators , Cooling fan and
radiator, Condenser Bushing & Bushing Current Transformer, OLTC, Oil
level gauge ,OLTC Cubicle and fan control cubicle, RTCC , Valves,
Clamps, Air Cell Breather, Pronol Bag etc. shall be recorded i.e. Make,
Rating, Factory Test Certificate, QAP Report , Invoices etc.

MPPTCL/TECH/PROC/07/JULY15 91 of 105
Volume-II, Part-7

(C) Format II (C) : Inspection of Core .

a) Checking of in house or vendor core cutting facilities. Sample


testing of core steel for checking specific total loss, ductility and
bend properties, resistivity, ageing , magnetisation characteristics
and thickness.
b) Check on the quality of surface insulation & surface finish;
Measurement of thickness and hardness of varnish on stampings;
Solvent resistance test to check that varnish does not react in hot
oil; Check over quality of varnish on stamping, to ensure uniform
shining colour, no hot spots, no over burnt varnish layer and no
bubbles on varnished surface.
c) Check on the amount of burrs i.e. cutting & edge; Bow Check on
stampings.
d) During core building dimension, leaning or waviness of core,
tightening torque, dia of resiglass tap to be checked.
e) Check for the over laping stampings. Corners of the sheets are to
be apart.
f) Visual and dimensional check during assembly stage.
g) Check for interlaminar insulation between core sections after
pressing.
h) Visual and dimensional check for straightness and roundness of
core.
i) High voltage test on fully built core 2 kV for one minute
between core & yoke bolts, core & core clamps, core clamps & yoke
bolts, core loss measurement, weighment of core.
j) Certification of all test results.

(iii) STAGE III : Stage Inspection of Winding after their preparation


: Once the coils are prepared but before the same are fitted on to
the core, stage inspection shall be done to take various measurements
and also for weighment of total weight of coil of each voltage class.
Measurement of winding resistance shall be also done. A small piece of
conductor for each type of winding shall be made available by the
manufacturer to our representative.

During this stage, following documents shall be verified by MPPTCL


inspector as a proof towards use of prime copper and insulating material
for manufacturer of transformer ordered by us :

i) Invoice of the supplier


ii) Mills test certificate
iii) Packing list
iv) Bill of lading
v) Bill of entry certificate by custom's.

The winding and insulating material shall be directly procured either


from the manufacturer or through their accredited reputed marketing
organisation but not through any agent. A copy of all above documents
shall be sent with joint inspection report for our records.

MPPTCL/TECH/PROC/07/JULY15 92 of 105
Volume-II, Part-7

In this stage, following shall be measured, recorded & checked in Format


III.

(A) Winding:

a) Sample check on winding conductor for mechanical


properties and electrical conductivity.
b) Visual dimensional checks on conductor for scratches,
dent marks etc.
c) Sample check on insulating paper for PH value, electric
strength.
d) Check for the reaction of hot oil on insulating paper.
e) Check for the bonding of the insulating paper on conductor.
f) Check and ensure that physical condition of all materials taken
for
winding is satisfactory and free of dust.
g) Check for absence of short circuit between parallel strands.
h) Check for brazed joints wherever applicable.
i) Measurement of voltage to be carried out when core/yoke is
completely restacked and all connections ready.
j) Conductor-enamel test for checking of cracks, leakage and pin
holes.
k) Conductor-flexibility test.
l) Heat shrink test for enamelled wire.
m) Measurement of no. of turns, cross sectional area of each
winding , winding resistance and weighment of windings.
n) Certification of all test results.

(B) Insulating Material:

a) Sample check for physical & chemical properties of material.


b) Check for dielectric strength.
c) Visual and dimensional checks.
d) Check for the reaction of hot oil on insulating materials.
e) Dimensional stability test at high temperature for insulating
material.
f) Tracking resistance test on insulating material.
g) Certification of all test results.

(iv) STAGE IV : Stage Inspection of Core – Coil Assembly before


Vapour Phase Drying / Dryout : In this stage , following shall be
measured, recorded & checked in Format IV.

a) Check Clamping Ring with approved drawing. Check Core Belting,


Check condition of insulation on the conductor & between the
windings.
b) Check insulation distance between high voltage & low voltage
connections with respect to earth and other parts.
c) Insulation test of core earthing .
d) Check for proper cleanliness and absence of dust etc.
e) Certification of all test results.

MPPTCL/TECH/PROC/07/JULY15 93 of 105
Volume-II, Part-7

(v) STAGE V : Stage Inspection of Core – Coil Assembly after Vapour


Phase Drying / Dryout : In this stage , following shall be measured,
recorded & checked in Format V.

a) Measurement and recording of temperature and drying time during


vacuum treatment.
b) Check for completeness of drying by measuring IR values & Tan
Delta.
c) Measure minimum clearance from all sides/bottom/top.
d) Certification of all test results.

(vi) STAGE VI : Inspection of Final Assembly of Transformer after


boxing in of active material : Complete details of all bought
accessories , their test certificates shall be appended. Minutes of
meeting shall record overall workmanship and other pertinent details.

a) Check completed transformer against approved out line


drawing, provision for all fittings, finish level etc.
b) Jacking test on all the assembled Transformers.

Pre-shipment Checks at Manufacturer's Works:

a) Check for interchangeability of components of similar


Transformers for mounting dimensions.
b) Check for proper packing and preservation of accessories like
radiators, bushings, explosion vent, dehydrating breather, rollers,
buchholz relay, control cubicle, connecting pipes, conservator etc.
c) Check for proper provision of bracings to arrest the movement
of core and winding assembly inside the tank.
d) Gas tightness test to conform tightness.
e) Derivation of leakage rate and ensure adequate reserve gas
capacity.

2.2.3 Details of Procurement : Manufacturer shall provide us complete


details of procurement of raw materials i.e. core, insulation and copper .
Manufacturer shall also record a certificate .

2.2.4 The MPPTCL also reserves the right to carry out stage
inspections at other stages also, for which advance intimation shall
be given and all necessary cooperation shall be rendered by the
manufacturer.

MPPTCL/TECH/PROC/07/JULY15 94 of 105
Volume-II, Part-7

ANNEXURE IX

LIST OF HAND TOOLS FOR SUPPLY


ALONG WITH EACH 132 KV, 40 MVA TRANSFORMER

A) One tool box consisting of the following Hand tools of GEDORE


or TAPARIA make shall be supplied with each transformer

1. SPANNERS
a) Double Open Ended Spanner Set : 1 set of 10 nos spanners of size
6x7, 8x9, 10x11, 12x13, 14x15, 16x17,18x19, 20x22, 24x27 and
30x32.
b) Ring Spanner Set : 1 set of 12 nos spanners of size 6x7, 8x9,
10x11, 12x13, 14x15, 16x17, 18x19, 20x22, 21x23, 24x27, 25x28
and 30x32
c) Tubular Box Double Ended Spanners with 2 nos Tommy Bars
(100 & 150 mm long) : 1 set of 8 nos spanners of size 8x9, 10x11,
12x13, 14x15, 16x17, 18x19, 20x22 and 21x23.
d) Hexagon Bit socket set with suitable Tommy Bar : 1 set of 15
nos sockets of size 10, 11, 12, 13, 14, 15, 16, 17,18, 19, 20, 21, 22,
23, 24.

2. ADJUSTABLE WRENCHES: 1No. wrench each of size 25mm & 35mm

3. STANDARD TORQUE WRENCH : 1 No. each of following

Torque range Square Head width Head


drive depth
1-7 Kg mtr ½ inch 30mm 45 mm
7-35 Kg mtr ½ inch 32mm 55mm

4. SCREW DRIVERS : 1 set comprising of 1 no of following sizes -

Head of Bit Ø Length of Total length of


(mm) (mm) steel (mm) Screw
Driver(mm)
3,0 3,0 75 155
4,0 4,0 100 190
5,5 5,5 125 225
8,0 6,0 150 250
8,0 8,0 175 285
10,0 9,0 200 310

5. PLIERS : 1 no each of Flat Nose, Round Nose, Side Cutting

6. GASKET PUNCH : 1 set comprising of size 8, 10, 12, 14, 16, 18, 20,
22, 24, 25mm.

MPPTCL/TECH/PROC/07/JULY15 95 of 105
Volume-II, Part-7

Annexure-X

DESCRIPTION OF EQUIPMENT FOR SCHEDULE OF RATES & PRICES


For this Bid which includes 132 KV 40 MVA transformers, description of main
equipments and other items should be brought out exactly as per details
furnished herein and accordingly schedule of price should be enclosed with
the Bid.

Item Description Quantity


Nos. (Nos)
1. Supply of 40 MVA 132/33KV, Three phase ONAN/ ONAF As
cooled transformer fitted with Pronol air-cell, and all per price
accessories/ fittings as described under annexure II , duly Schedule
passed all routine additional routine and acceptance tests as
per IS-2026 with one set of tools as per annexure IX
complete with first filling of oil including wastage & 10%
extra of that quantity & meeting all technical requirement
as per Part-1 of Volume II & annexure I. The offered cost
includes cost of all tests as per clause 24.5 and conforming to
all requirements as described in bid document. The
transformers shall be supplied fitted with Impact Recorder
(on returnable basis) during transportation of Transformers
and Vehicle tracking system (GPRS/ GPS/ GSM based) to
track the exact position of the vehicle during transportation
of Transformers as per clause no. 37.0.
2 Unit price of following items included in the Offered cost of
transformer mentioned above shall be Offered separately.
a) Charges for fitting Impact Recorder (on returnable basis)
during transportation of Transformers and Vehicle tracking
system (GPRS/ GPS/ GSM based) to track the exact position
of the vehicle during transportation of Transformers as per
clause no. 37.0

SIGNATURE
WITH SEAL OF BIDDER

MPPTCL/TECH/PROC/07/JULY15 96 of 105
Volume-II, Part-7

ANNEXURE –XI

LIST OF VENDORS FOR MAJOR ITEMS OF TRANSFORMER

The vendors of various major items from whom procurement was made by
various suppliers of transformers and quality of which was found acceptable
are listed below. However, Major items/inputs in transformers have to
conform to highest quality standards and these items/inputs procured from
any vendors meeting the required specification would be acceptable.

S. No. Name of Item Supplier


1. CRGO M/s Nippon steel corporation, Japan
M/s JFE Steel corp., Japan ( Erstwhile
M/s Kawasaki Corp. Japan)
M/s AK Steel,USA
M/s Armco, USA,
M/s Posco,Korea
M/s Covefi, France
M/s Salzgittar, Germany
M/s Usinor, France
M/s Transfer, France
M/s Mitsubishi, Japan.
M/s AST Terni, Italy
M/s EBG India Pvt Limited, (Indian
Agent) for M/s GELSE NKIRCHEN,
Germany
M/s British Steel Corporation , UK
M/s Thyseen Krupp Group of Companies
2. (a) Winding copper & M/s Invex Filli Isolati Speciali s.p.a. Italy
conductor M/s Sam Dong Korea
M/s Asta, Austria
M/s Smit Draad, Holland
M/s Incab Industries, Jamshedpur
M/s Sterlite Industries, Mumbai
M/s Hindalco Industries
M/s Bhandary Powerlines Private Limited
(BPPL), Manipal.
M/s BCPL Conductors Private Limited,
Manideep, Bhopal.
M/s Bhandary Powerlines Private Limited
(BPPL),Vadodara.
M/s Shakti Insulated Wires,Mumbai
M/s KSH International Pvt Limited, Taloja
M/s Delta-Trans Conductor, Mumbai
M/s Vijay Electricals, Hyderabad
M/s RIMA Transfomers & Conductors Pvt.

MPPTCL/TECH/PROC/07/JULY15 97 of 105
Volume-II, Part-7

S. No. Name of Item Supplier


Limited, Bangalore.
M/s Lacroix and Kress (GMBH) germany
M/s Pirellicavi Italy
M/s Shree Cable & Conductors
M/s Chandra Metals,allahabad
(b) CTC Conductor M/s Sam Dong Korea
M/s Invex Filli Isolati Speciali s.p.a. Italy
M/s Loc Roix AND KRESS – Germany
M/s Chandra Portico ltd silvassa
M/s KSH International Pvt. Ltd, Chakan
M/s Shree Cable & Conductors Bhopal
3. Precompressed M/s H. Weidmann, Switzerland
press Board & press M/s ABB fige Holms, Swedan
Board components M/s Senapathy Whiteley, Banglore
M/s Raman Board, Mysore
4. Insulating Material M/s Dupont, USA
M/s Senapathy Whiteley, Banglore
M/s H. Weidmann, Switzerland
M/s Munksio
M/s Amotfors, Sweden
M/s Krammerer
5. Air Cell M/s PRONAL, France
M/s PRONAL, Asia manufacturing SDN
BHD Malaysia
6. Gaskets M/s Talbros, Faridabad
M/s Cortica, Chennai
M/s Packing & Jointing, Chennai
M/s Indian Rubber Products, Haridwar
M/s Bombay Oil Seal Mfg. Mumbai
M/s MGM Rubber Kolkata
M/s Bharat Corrub Industries, Vadodara.
M/s Indian Cork Industries, Bahadarpur
M/s Nu-cork, Gurgaon
7. OIP Condensor M/s BHEL
bushing M/s CGL
M/s TELK
M/s ASEA-MICAFIL
M/s Passonivilla
8. Terminal Connector M/s Best & Crompton, Chennai
M/s PeeVee Engg., Bangalore
M/s Milind Engg., Mumbai

MPPTCL/TECH/PROC/07/JULY15 98 of 105
Volume-II, Part-7

S. No. Name of Item Supplier


M/s Nootan, Baroda
M/s Utsav, Baroda
M/s Vinayak and Co., Mumbai
M/s Megha Engg. Enterprises, Chennai
M/s Klemmen Engg. Corporation ,
Chennai
9. OTI/WTI with M/s Accurate Control,UK
repeater M/s AKM, Swedan
M/s Perfect Control, Chennai, India
M/s Preci Measure, Banglore
M/s Radix Electrosystems Pvt. Ltd/ Radix
Pyrotech India

10. Magnetic oil gauge M/s Sukrut Udyog, Pune


M/s Yogya, Jhansi
11. Buchholz Relay & Oil M/s Fukuda Instrument, Japan
surge relays M/s Atvus,Calcutta
M/s English Electric, Chennai
M/s Prayog; M/s BHEL
M/s Instrument and Control, Vadodara
12. Pressure Relief M/s Qualtrol, USA
Device M/s GE, USA;
M/s Sukrut Udyog, Pune
13. Fan & Motor M/s Marathon Electric Motors (India) Ltd,
Kolkata (Erstwhile M/s Areva, (Alstom),
Kolkata)
M/s CGL, Mumbai
M/s Khaitan, Kolkata.
M/s EPC, Kolkata
14. Un-impregnated M/s Permali Wallace Bhopal
Densified laminated M/s Kit ply Assam
wood M/s Mysore Polymers Banglore
M/s Narmada Forest Ind. Pvt. Ltd.
Bhopal.
M/s Western India Plywood , Kerala
M/s Dehonite, Germany
M/s Surendra Composites, Bhopal
M/s Rochling Engineering plastics,
Germany
15. Valves M/s Leader
M/s Bombay Metal & Alloys
M/s Audco
M/s Petson

MPPTCL/TECH/PROC/07/JULY15 99 of 105
Volume-II, Part-7

S. No. Name of Item Supplier


M/s Manixon
M/s Creseant
M/s Precision Engg. Kottayam,
M/s Eapen Joseph, Kottayam
M/s Apex Piping Systems, Jalandhar
M/s Liberty Engg., Mumbai
M/s Niton Valves, Mumbai
M/s Eapen Joseph & co., Coimbatore
M/s GG Valves ,Udaipur
16. MCB Ms Siemans
M/s MDS
M/s S&S
M/s Havell’s
17. Fuse M/s Siemens/ S&S / Areva / Havell’s
18. Tank Steel M/s SAIL
M/s Essar
19. OLTC Complete M/s BHEL
M/s TELK
M/s Easun, Madras, M/s CTR, Pune
20. Terminal Blocks M/S ELMEX
M/S Technoplast,
M/S Tosha
21. Silica gel Breather M/S Yogya Enterprises, Jhansi.
M/S Anusen Industries, Pune.
M/s Instruments & Controls , Vadodara,
India
22. Transformer oil M/s Apar Limited, Mumbai
M/s Savita Chemicals Ltd, New Mumbai
23. Radiator M/s CTR Manufacturing Industries, Pune
M/s Thermal Transformer Product,
Bangalore
M/s Exotherm, Bangalore.
M/s P.E. Engg. Hyderanad.
M/s Hitech Radiators Pvt.Ltd, Mumbai
M/s BHEL, Bhopal

24. Oil flow indicator M/s Sukrut Udyog, Pune

MPPTCL/TECH/PROC/07/JULY15 100 of 105


Volume-II, Part-7

APPENDIX I

Calculation for Hot Spot winding temperature for EHV transformers

Overloading capability of the transformer and also the loading


capability of transformer with and without cooling fans (coolers) for a
short period of 10/20 minutes with out exceeding temperature rise of
winding beyond specified limits have been indicated in the technical
specification. In this regard following calculation based on maximum
ambient air temperature as 50 degree centigrade and maximum
yearly average weighted air temperature as 32 degree centigrade
using the under mentioned formulae or any other authentic formulae
shall be furnished.

-t/ τ 2y
θc = θa + Δ θ b0 + (Δ θ b- Δ θbo) ( 1- e ) + (Δ θ c τ - Δ θb τ) k

2 x
 ( 1+dk )
Δ θb = Δ θ br --------------
 ( 1+d) x

Where

θa = Weighted ambient temperature (cooling medium)

θc = Winding hot-spot temperature at K load = θa + Δ θc

θcr = Winding hot-spot temperature at rated load

Δ θc = Winding hot-spot temperature rise at K load

Δ θcr = Winding hot-spot temperature rise at rated load

θbo = Original oil temperature

θb = Top oil temperature at K load = θa + Δ θb

θbr = Top oil temperature at rated load

Δ θb = Top oil temperature rise at load K

Δ θbr = Top oil temperature rise at rated power

t = Time duration in hours of any load power

τ = Oil air thermal time constant of transformer at rated


load, in hours

K = Ratio of any load/rated load = S /Sr

MPPTCL/TECH/PROC/07/JULY15 101 of 105


Volume-II, Part-7

K1 = Ratio of initial load/rated load = S1 /Sr

K1 = Ratio of permissible load/rated load = S2 /Sr

K2 = Ratio of permissible load/rated load

x = Exponent for oil rise

y = Exponent for winding rise

d = Ratio of load loss at rated load/no load loss.

a = Subscript representing ambient (cooling medium)

b = Subscript representing top oil

c = Subscript representing hot-spot of winding

r = Subscript representing rated value.

SIGNATURE
WITH SEAL OF
BIDDER

MPPTCL/TECH/PROC/07/JULY15 102 of 105


Volume-II, Part-7

APPENDIX II

TECHNICAL PARTICULARS TO BE FILLED-IN BY BIDDER

S. No. Particulars Values


1 Maximum flux density (Tesla)
2 Maximum current density (Amp/sq.cm)
3 Magnetising current (mA)
4 Short time current rating (Amp.)
5 Losses
a. No load Losses (KW)
b. Load Losses including stray losses
(KW)
c. Auxiliary losses (KW)
6 Impedance voltage (Percentage)
7 Weight of copper (Kg)
8 Weight of core (Kg)
9 Weight of core + winding (Kg)
10 Quantity of oil
a. For first filling including wastage
(KL/Kg)
b. 10% extra of ‘a’ (KL/Kg)
11 Total weight of Transformer. (Kg)
12 Transport weight of main tank
a. with oil (Kg)
b. without oil (Kg)

SIGNATURE
WITH SEAL OF BIDDER

MPPTCL/TECH/PROC/07/JULY15 103 of 105


Volume-II, Part-7

List of Abbreviation used in technical specification

1. OLTC - On load tap changer


2. OIP - Oil impregnated paper
3. DL type - Draw lead type
4. COPS - Conservator oil preservation system
5. RTCC - Remote tap changer cubicle
6. Cl - Clause
7. IEEMA - Indian Electrical & Electronics Manufacturing
Association
8. KV - Kilo voltage
9. KW - Kilo Watt
10. IV - Intermediate voltage
11. LV - Low voltage
12. VPD - Vapour phase drying
13. ONAN - Oil natural air natural
14. ONAF - Oil natural air forced
15. OFAF - Oil forced air forced
16. CBIP - Central Board of Irrigation and Power
17. OTI - Oil temperature indicator
18. WTI - Winding temperature indicator
19. KA - Kilo Ampere
20. TC - Terminal connector or test certificates as
applicable
21. V - Voltage
22. f - Frequency
23. VN - Normal voltage
24. FN - Normal frequency
25. CT - Current Transformer
26. PT - Potential Transformer
27. Xmer - Transformer.
28. PRD - Pressure Relief Device
29. PRV - Pressure Relief valve
30. MOLG - Magnetic Oil Level Gauge
31. OSR - Oil Surge Relay
37. Isc - RMS value of symmetrical short ckt current,KA
38. V - rated voltage of system ,KV
39. Zt - short ckt impedance of transformer ,Ohms
40. Zs - short ckt impedance of system ,Ohms
41. θ1 - final temperature in degree centigrade
42. θ0 - Initial temperature in degree centigrade
43. J - short ckt current density ,amp/mm sq.
44. t - duration of short ckt in secs
45. Iph - rated phase current in amps
46. Zpu - per unit impedance
47. Rdc - DC resistance of the per phase of winding at 75
degree centigrade

MPPTCL/TECH/PROC/07/JULY15 104 of 105


Volume-II, Part-7

48. Hw - height of winding in cm


49. N - no of turns per phase of winding
50. Dmi - mean diameter of inside winding ,cm
51. Bi - thickness of inside winding conductor ,cm
52. E - modulus of elasticity of conductor, cm
53. Sn - rated KVA
54. Pu - per unit impedance
55. Fa - axial imbalance force, Kg
56. Ai - (no of spacers x length x width ) for inner
winding
57. Ao - (no of spacers x length x width ) for outer
winding
58. m - no of conductors in the radial direction= no of
turns x no of parallel conductor
59. bo - thickness of outer winding conductor, cm
60. Dmo - mean diameter of outer winding, cm
61. Ao - supported area of outer radial spacers
62. F - total axial force in MT
63. D - mean diameter of clamping ring ,cm
64. b - width of clamping ring ,cm
65. t - thickness of clamping ring ,cm
66. n - no of jacking or clamping points
67. mA - milli ampere
68. kg - kilogram
69. kl - kilolitre
70. temp. - temperature
71. max. - maximum
72. min. - minimum
73. vol. - volume

MPPTCL/TECH/PROC/07/JULY15 105 of 105

Potrebbero piacerti anche