Sei sulla pagina 1di 1

Howard Street Howard Street

60.35 metres 80.47 metres

Title Boundary

129.75 metres
74.83 metres

74.83 metres

Bendigo Creek Reserve


Lot 1 Lot 2

Building 60.35 metres


demolished, as
part of capital Removed from Removed from
works project site by site by
Department of Department of Buildings, dashed
Education Education red, to be
removed from site
at completion of
new building.

Title Lots Plan


Multi Purpose
Room
RL: +187.900 Site Area
Lot 1 - Land Victoria TP951458G
Parish: Sandhurst
Netball Court Township: Epsom
Crown Allotment: 53(PT)

Area: 4527m²

Lot 2 - Land Victoria TP951459E


Accessible WC
Parish: Sandhurst
3 Township: Epsom
Art/Craft
GPLA 7 GPLA 8
Crown Allotment: 54
Existing Removed from Administration
Transportables site by
Title Boundary

Department of
Principal Withdrawal 2
Canteen
Withdrawal 3 Area: 8448m²
Sick Bay
Repositioned on site Education GPLA 3 GPLA 4

Reception
Staff Work
Space 1
Staff Work
Space 2
Total Site Area: 12975m²
Buildings, dashed red, to be
Assist Principal Breakout Space
removed from site at Cloak
Art/Breakout 2

Gallery
completion of new building. Library
Librarian Space Main Building - Part B
Workroom RL: +187.900 m
Main Building - Part A Outdoor Wet Area Amphitheatre 2
RL: +187.900 m Learning Space
Quiet 1 Note:
Adjoining RL: +187.900 m Breakout Space
1
Girls Toilet
Vacant Library
Quiet 2
1. Refer Civil Engineers drawings and specification for all
Removal of Transportables locations of underground stormwater pipes and pits etc.
Farm

Bendigo Creek Reserve


Existing at completion of construction Withdrawal 1
Land Transportables works to be confirmed, 2. Refer Fire Engineer drawings and specifications for all
GPLA 9 GPLA 10 locations of underground fire mains and hydrants
subject to school enrolments GPLA 1 Boys Toilet
Repositioned on site Staff Work GPLA 2
Space 3. Refer Electrical Engineers drawings and specification for all
Interview
types and location for all electrical services, including but not
limited to underground conduits and pits.

Staff Centre / Amphitheatre 1 GPLA 5 GPLA 6 4. Refer Landscape Architects drawings and specifications for
Lounge RL: +187.400 m all locations of landscaping, paving and outdoor furniture.

Title Boundary
rev no. revision note date
/ Design Development Preliminary - 08/07/2016
1. Amendment to Canteen Area &
Staff/Accessible W.C. 2.
Portable location development
A Design Development submission 26/08/2016

Title Boundary

Existing Playground
& Future Adventure
Adjoining Play &
Vacant Sensory/Nature
Farm Land Play
Entry to school from MELBOURNE BENDIGO
Bendigo Creek Trail
Suite 110 111 Mollison Street
134-136 Cambridge Street Bendigo
Collingwood, Victoria 3066 Victoria 3550
T 03 9329 0399 T 03 5443 0055
F 03 9326 5473 F 03 5441 4981

eplus@eplusarchitecture.com.au
www.eplusarchitecture.com.au
This Drawing shall be read in conjunction with all other drawings
1. and specifications.
Before commencement of any works, on site confirmation of
2. dimensions shown is the responsibility of the individual
contractor.
3. DO NOT SCALE THESE DRAWINGS. Where dimensions are not
shown and are deemed to be necessary, reference must be
Tit made to the Architect.
le 4. This drawing is Copyright and may not be used or reproduced in
Bo
un whole or in part without the express written permission of the
da Architect.
ry
project name
Epsom Primary School
Redevelopment
project address
Howard Street, Epsom,
Vic. 3551
client name
Department of Education
Site Plan - Proposed
drawing title
Scale: 1 : 250

north
Site Plan - Proposed
Boundary fence to be
reconstructed along actual
property line to part of
South boundary drawn checked
M.K. L.H.
date
26/08/2016
scale @
As indicated
job no.
15-033
drawing no. revision

A1.03 A