CONSTRUCTION PROGRAMME (REVISED) - FOR ISBB R01 & R02 - LALIT BHAWAN - PREPARED AS ON 20 OF MAY'19
REMARKS /
Sl. No. ACTIVITY DURATION START DATE END DATE MAY JUNE JULY
REQUIREMENTS

ISBB R02
EXPANSION JOINT - INSTALLATION & CONCRETING
CONCRETING 1 24-05-19 24-05-19
RA2 RETAINING WALL CH 539-610

FOUNDATION-STAGE 1
EXCAVATION 4 20-06-19 23-06-19

PCC 4 24-06-19 27-06-19

REINFORCEMENT FIXING 4 28-06-19 01-07-19

FORMWORK 2 02-07-19 03-07-19

CONCRETING 1 04-07-19 04-07-19

FOUNDATION-STAGE 2
EXCAVATION 4 05-07-19 08-07-19

PCC 4 09-07-19 12-07-19

REINFORCEMENT FIXING 4 13-07-19 16-07-19

FORMWORK 2 17-07-19 18-07-19

CONCRETING 1 19-07-19 19-07-19

RETAINING WALL 1ST LIFT STAGE 1


REINFORCEMENT FIXING 3 06-07-19 08-07-19

FORMWORK 5 09-07-19 13-07-19

CONCRETING 1 14-07-19 14-07-19

RETAINING WALL 1ST LIFT STAGE 2


REINFORCEMENT FIXING 3 15-07-19 17-07-19

FORMWORK 5 18-07-19 22-07-19

CONCRETING 1 23-07-19 23-07-19

RETAINING WALL 2ND LIFT STAGE 1


REINFORCEMENT FIXING 3 24-07-19 26-07-19

FORMWORK 5 27-07-19 31-07-19

CONCRETING 1 01-08-19 01-08-19

RETAINING WALL 2ND LIFT STAGE 2


REINFORCEMENT FIXING 3 02-08-19 04-08-19

FORMWORK 5 05-08-19 09-08-19

CONCRETING 1 10-08-19 10-08-19

Page 1 of 4
Enclosure To Letter No: SPS/LPC/01/1088/2019 Dated-20/05/19
TH
CONSTRUCTION PROGRAMME (REVISED) - FOR ISBB R01 & R02 - LALIT BHAWAN - PREPARED AS ON 20 OF MAY'19
REMARKS /
Sl. No. ACTIVITY DURATION START DATE END DATE MAY JUNE JULY
REQUIREMENTS

RA1 RETAINING WALL

FOUNDATION-STAGE 1
RETAINING WALL
4 10-06-19 13-06-19
EXCAVATION DRAWING
PCC 4 14-06-19 17-06-19

REINFORCEMENT FIXING 4 18-06-19 21-06-19

FORMWORK 2 22-06-19 23-06-19

CONCRETING 1 24-06-19 24-06-19


FOUNDATION-STAGE 2

EXCAVATION 4 25-06-19 28-06-19

PCC 4 29-06-19 02-07-19

REINFORCEMENT FIXING 4 03-07-19 06-07-19

FORMWORK 2 07-07-19 08-07-19

CONCRETING 1 09-07-19 09-07-19


RETAINING WALL 1ST LIFT STAGE 1

REINFORCEMENT FIXING 3 26-06-19 28-06-19

FORMWORK 5 29-06-19 03-07-19

CONCRETING 1 04-07-19 04-07-19


RETAINING WALL 1ST LIFT STAGE 2

REINFORCEMENT FIXING 3 05-07-19 07-07-19

FORMWORK 5 08-07-19 12-07-19

CONCRETING 1 13-07-19 13-07-19


RETAINING WALL 2ND LIFT STAGE 1

REINFORCEMENT FIXING 3 14-07-19 16-07-19

FORMWORK 5 17-07-19 21-07-19

CONCRETING 1 22-07-19 22-07-19


RETAINING WALL 2ND LIFT STAGE 2

REINFORCEMENT FIXING 3 23-07-19 25-07-19

FORMWORK 5 26-07-19 30-07-19

CONCRETING 1 31-07-19 31-07-19

Page 2 of 4
Enclosure To Letter No: SPS/LPC/01/1088/2019 Dated-20/05/19
TH
CONSTRUCTION PROGRAMME (REVISED) - FOR ISBB R01 & R02 - LALIT BHAWAN - PREPARED AS ON 20 OF MAY'19
REMARKS /
Sl. No. ACTIVITY DURATION START DATE END DATE JULY AUGUST SEPTEMBER
REQUIREMENTS

ANTI CRASH BARRIER


DECK PORTION-RHS

REINFORCEMENT FIXING 3 27-06-19 29-06-19

FORMWORK 8 30-06-19 07-07-19

CONCRETING 2 08-07-19 09-07-19

FORMWORK REMOVAL 1 10-07-19 10-07-19


DECK PORTION-LHS

REINFORCEMENT FIXING 3 10-07-19 12-07-19

FORMWORK 8 13-07-19 20-07-19

CONCRETING 4 21-07-19 24-07-19

FORMWORK REMOVAL 1 25-07-19 25-07-19


RA1 PORTION-LHS

REINFORCEMENT FIXING 2 01-08-19 02-08-19

FORMWORK 4 03-08-19 06-08-19

CONCRETING 1 07-08-19 07-08-19

FORMWORK REMOVAL 1 10-08-19 10-08-19


RA2 PORTION-LHS

REINFORCEMENT FIXING 2 11-08-19 12-08-19

FORMWORK 4 13-08-19 16-08-19

CONCRETING 1 17-08-19 17-08-19

FORMWORK REMOVAL 1 20-08-19 20-08-19


END KERB

REINFORCEMENT FIXING 1 25-07-19 25-07-19

FORMWORK 4 26-07-19 29-07-19

CONCRETING 2 30-07-19 31-07-19

FORMWORK REMOVAL 1 03-08-19 03-08-19

HAND RAIL FIXING & PAINTING 3 04-08-19 06-08-19


INTERMEDIATE KERB

REINFORCEMENT FIXING 1 01-08-19 01-08-19

FORMWORK 2 02-08-19 03-08-19

CONCRETING 1 04-08-19 04-08-19

FORMWORK REMOVAL 1 07-08-19 07-08-19

RAISED FOOTPATH CONCRETING 2 10-08-19 11-08-19

Page 3 of 4
Enclosure To Letter No: SPS/LPC/01/1088/2019 Dated-20/05/19
TH
CONSTRUCTION PROGRAMME (REVISED) - FOR ISBB R01 & R02 - LALIT BHAWAN - PREPARED AS ON 20 OF MAY'19
REMARKS /
Sl. No. ACTIVITY DURATION START DATE END DATE AUGUST SEPTEMBER OCTOBER
REQUIREMENTS

WEARING COURSE

MASTIC ASPHALT 4 24-07-19 27-07-19

ASPHALTIC CONCRETE 4 28-07-19 31-07-19


APPROACHES
RA1 PORTION

FILTER MEDIA & SAND FILLING 10 01-08-19 10-08-19

GSB 7 11-08-19 17-08-19

DLC 10 18-08-19 27-08-19

PQC 10 28-08-19 06-09-19


NO DRAWINGS
10 07-09-19 16-09-19
ANTI CRASH BARRIER/KERB AVAILABLE
RA2 PORTION

FILTER MEDIA & SAND FILLING 10 11-08-19 20-08-19

GSB 7 18-08-19 24-08-19

DLC 10 28-08-19 06-09-19

PQC 10 07-09-19 16-09-19


NO DRAWINGS
10 17-09-19 26-09-19
ANTI CRASH BARRIER/KERB AVAILABLE
OPENING TO TRAFFIC

OPENING TO TRAFFIC 1 27-09-19 27-09-19

Page 4 of 4