EASTERN RAILWAY

No. F/CWM/OFF/13 Jamalpur, dated 28-05-19

Chief Workshop Engineer


Eastern Railway
Kolkata

Sub: Compliance to Notes of GM’s Annual Inspection at Jamalpur


Workshop on 25-02-2019.
Ref: GM/ER’s Inspection Note No.G.300/16-1(G)/GM dated 02-04-2019.
Reference above compliance/remark of the point pertaining to Jamalpur Workshop is appended below.
SN Shop/Items Compliance/Remarks
1.0 Miss Muffet
1.1 The rejuvenated Steam Shunting Locomotive, Noted.
Miss Muffet was inspected. The working and
scope of work undertaken was explained.
1.2 It was also satisfying to take the heritage run in the Noted.
locally refurbished 4 Wheeler along with Miss
Muffet from WRS-II to WTC.
2.0 BTC
2.1 The facilities in Welding Training Centre at BTC, Noted
Jamalpur were inspected. They were found to be
equipped with modern welding simulator as well
as contemporary welding machines.
2.2 The workshop should ensure that all welders are Noted. Upgradation of Welders is in process. On
trained and their skills upgraded through quality date, 18.56% and 29.46% of welders are graded
training at this facility. with A & A+ resp. Re-gradation of ‘C’ grade
welder has started from 01.04.19. Till date 82
gradation test is completed but result awaited
from CMT Lab. Welding development course will
start in May’19 for no grade welders to develop
their skills. Upgradation of ‘B’ Grade welders will
be as per training calendar of BTC 2018-19. BTC
target is to achieve at least 70% Grade Welder in
2019-20.
3.0 Jamalpur Jack Manufacturing Shop:

3.1 The newly developed Jamalpur Jack Noted.


Manufacturing Shop in the erstwhile Forge Shop
was inspected.
3.2 Various components used in manufacture of Noted.
Jamalpur Jacks were displayed and the process of
Jack manufacture was explained.
3.3 One set of newly developed 35T Jamalpur Jack Noted.
was demonstrated on load.
SN Shop/Items Compliance/Remarks
3.4 It was also highlighted that future jacks It will be implemented for all future procurement
manufactured by Jamalpur Workshop will be after successful commissioning of 01 set of 05
equipped with digital display and load indicators. Jacks.
4.0 Crane Shop:
4.1 172nd Tower Car of SDAH Division was flagged To reduce the cycle time of Tower Car POH,
off after POH. Proposal for 04 Nos. Hydrostatic Static Power
Pack as a unit exchange spare already have
In light of a number of Overdue POH Tower Cars been sent to HQ for inclusion in RSP 2019-20.
lying in Divisions, Jamalpur Workshop should
make efforts to minimise the cycle time of Tower
Car POH and thereby increase the number of
Tower Car POH. The Shop should use Unit
Exchange Spares for reduction the Cycle Time.
Action for Unit Exchange Spares should be taken
immediately.
4.2 Newly manufactured 140T Crane No. 144033 of Noted.
Adra Division was flagged off.
4.3 The progress of work in the newly constructed Noted.
shop in the Workshop was inspected.
4.4 Jamalpur Workshop should endeavour to reduce In view of staff strength, the cycle time of
the cycle time of Crane POH and manufacturing manufacturing/POH/MLR work is very tight.
activities thereby freeing up space for the However, necessary effort is being taken to
enhanced demand of Crane POH and reduce the cycle time of140T Crane schedule.
manufacture.
4.5 Efforts should be made to judiciously plan Planned expansion of Crane Shop is under
expansion of the shop while ensuring streamlined Dy.CE(Const.). However, regular chasing is being
movement of material. done. Completion of shed expansion will provide
more berthing space to undertake POH/MLR Mfg.
Activities simultaneously for 03 Cranes at a time.
4.6 The shop should explore possibility of removing Housekeeping of Crane Material has been done
idle/slow moving items from under the Crane, to provide sufficient area for manufacturing and
manufacturing area thereby freeing space for POH POH of 140T Crane. However, due to sudden
and manufacture activities. arrival of Heavy Structure items against long
period orders, a shortage of working space has
arisen. Efforts are being made to tackle the
problem.
5.0 Wagon Manufacturing Shop (5S Certified
Shop)
5.1 The major components going into manufacture of Noted. It is planned to outsource various
wagons were displayed. Majority of the components for BOXN-HL which is already
components were shop manufactured. The Shop incorporated in 400 BOXN-HL estimates and in
should explore the feasibility of outright purchase due course more and more components will be
of small component thereby sparing space and outsourced, so that spared manpower will be
manpower for increasing the outturn. utilized for assembly and other works thus
increasing the Outturn.
SN Shop/Items Compliance/Remarks
Comparative differences in the under frame of
BOXN-HL & BVCM along with the bogies were Noted.
5.2 elaborated. It was heartening to know that the
Shop is fully equipped to manufacture many types
of Wagons.
5.3 The BVCM wagon built for first time at JMPW was Noted.
inspected and then flagged off.

5.4 One newly erected BOXN HL wagon was More welders are being upgraded to A & A+
inspected. There is scope of improvement in the Category, which will result in giving better weld
welding quality. quality to works. Also planning is made for having
BOX manipulator for rotating the wagon which
would result in downhand welding of Corner joint
of End wall & Side wall , Crib angle, End angle
etc.
6.0 WRS-III, IV & V:
6.1 The Wagon POH outturn has improved over last 2 Noted. With completion of sanctioned umbrella
years but it needs to be further increased to 600 work it will be possible to achieve Wagon POH
Wagons/month in the near future. target of 550 to 600 wagons/month.
6.2 Proposed Shed extension work of WRS-IV was Wagon POH outturn increased from 375
inspected. While Berthing capacity will further wagons/month in 2017-18 to 439 wagons/month
increase but shop should also strive for complete in 2018-19. This is an increase of 17 % without
utilization of existing berthing capacity and any enhancement in berthing capacity and
reduction of Wagon POH cycle time for increase of without any addition in wagon POH infrastructure.
outturn. Jamalpur workshop will further strive for
improvement.
6.3 Various wagon components were displayed. Noted. Stocking of CBC components as per
Procurement of CBC component of improved improved drawing/specification has already been
drawing (WD-70-BD) needs to be expedited. done. Store Dept. at HQ may be advised
accordingly.
6.4 The work of retro-fitment of Twin Pipe in existing Noted.
wagons which were sanctioned under RSP should
be expedited.
7.0 Pilot Training School :
7.1 During the inspection of PTS, training system for Noted.
Loco Pilot was briefed and also simulator training
was explained.
7.2 Interaction done with trainees. They are satisfied Noted.
with the training and other hostel facilities.
8.0 Meeting with BOs:
8.1 Scrap disposal should be taken up on Mission Noted. 74 Condemned Machines offered to stores
Mode and all available scrap materials should be for sale through as is where is basis. All other
handed over to Stores at the earliest. condemned machines are send to NSY through
SN Shop/Items Compliance/Remarks
NS-11.
8.2 Dy.CMM raised the issue of fencing and isolating Administrative approval of CWM/JMP has already
the scrap yard at South End of the Workshop. been obtained after technical feasibility report.
Amongst JMP, KPA & LLH, JMP is the only Shop DTE/JMP has already been advised to start
which is having the scrap yard inside the Shop construction work vide L.No.F/Stores/Gen.Sec./04
premises. dt 10/04/19.
In the light of recent problems related to scrap
disposal faced by Shop, this is a very important
work and needs to be examined immediately.
Detailed plan to be drawn & proposal should be
initiated.
8.3 With the increase in the Wagon POH Outturn, Noted.
there shall be a need for capacity enhancement of
Exchange Yard at JMP station. This needs to be
examined by MLDT Division.
8.4 PCEE has raised the issue of 9-10 overdue Tower Steps are being taken to immediately liquidate the
Wagons. Jamalpur Workshop should take overdue Tower Car.
immediate steps to liquidate the overdue. POH of one Tower Car completed.
Open Tender of 06 power packs through Works
Contract is under process.
04 Nos. Hydrostatic Power Pack is under
procurement through COS.
8.5 Jamalpur Hospital is in the need of urgent posting Posting order of one paediatrician at Jamalpur
of a Paediatrician. PCMD may look into this. Hospital has been issued from the HQ but he has
not yet joined.
8.6 Immediate and thorough cleaning of all Water On proposal is under preparation for cleaning of
Bodies from Weeds etc. inside Railway premises weeds from water bodies.
should be taken up.
8.7 There were many complaints regarding poor On proposal has been shortlisted in out of turn
condition of roads inside Railway Colony. This basis. The tender will be called after sanction of
should be got attended immediately. competent authority.
9.0 Interaction with Unions:
9.1 Representatives of different unions met and Noted.
handed over their memorandum.
10.0 Railway Main Hospital :
10.1 The Registration time for the patient at 9.00 a.m. A proposal has already been prepared and is
to 1.00 p.m. & 4.00 p.m. to 5.00 p.m. It should be under accounts vetting.
displayed in front of the Registration counter.
10.2 No CCTV is available in the hospital premises. It 03 Nos. CCTV is already commissioned in
should be installed immediately. emergency room and adjacent verandas Kiosk
Ayushman Bharat. In other places the work is in
progress it will be completed in due course.
10.3 One after another, each Ward/Room should be Noted & to be done on priority basis.
thoroughly renovated.
10.4 Electric load of Hospital to be assessed and a new Load analysis has been done & estimate for DG
DG set should be provided. Set of 125 KVA has been uploaded in Law Book
SN Shop/Items Compliance/Remarks
19-20 for kind sanction.

11.0 Munger Pontoon Pumping Station:


11.1 A new Water Treatment Plant should be planned Noted and to be proposed.
on the nearby land.
12.0 GENERAL :
12.1 Revision of Pension- All 7028 cases are PPO for 7028 Pre-16 cases are being sent to
completed and for 95 pending cases direct access concerned CPPC in phased manner regularly and
to ARPAN to be examined & resolved in also ensured for complete disposal in a short
consultation with Accounts. 203 Postal cases span. In order to finalization of 203 postal cases,
finalization is to be expedited. 67 pending NPS mapping already completed & all efforts are being
cases enrolment to be followed up (duly ensuring made for revision of postal cases. Revision of 95
that long absent cases are terminated soon). cases under Pre-16 is under process. Accts
Deptt./JMP has been approached for Service
Records and current details of Bank Scroll as per
requisition. As soon as the same is provided by
Accts Deptt., revision of 95 cases will be done
immediately.
12.2 Long absent cases- Total-180, SF5 issued- 157, All BO’s have been reminded on 13.03.19 for
Finalized- 134 (113 has been removed, Case speedy finalisation of DA proceedings.
dropped – 09, Death-05, Resignation-01, Retired-
02, Resumed duty-04). Pending 46 cases should
also be finalized soon.
12.3 APARs – Finalization should be monitored and It is being monitored and followed up with BO’s.
followed up with all BO’s and Age & Service Service Record is under process and soon it will
Review to be finalised. SR verification due be finalised. List of SR to come from other
because of SR’s from other Railways to be Railway/Div/Workshop has been prepared and
followed up & if required to be address by HQs, effort is being taken to bring these early for the
detailed list to be given. Digitization of SR’s & verification of SR. Digitisation of SR have been
AEBAS to be consistently implemented. done except those to come from other
Rly/Div/WS. On receipt, steps will be taken for
Digitisation of left over SR. AEBAS is on & being
continuously monitored by deputing staff.
12.4 POH Unit Cost: As compared to last year, the Comparison of cost of POH evolved in 2017-18
outturn of Diesel Loco POH is increased and 2018-19 are as under:
marginally by 4.48%, but it is seen that the POH (A) POH unit Cost of LOCO:-
Unit Cost is increased significantly by 23.5%. Also, (Fig in crores)
it was found that the outturn of wagon POH
increased by 19.04% while Unit Cost increased by 2017-18 2018-19
Year
4.52%. (up to Mar) (Up to Feb)
Outturn 40 51
Labour &
26.30 34.46
LOC
Material &
16.50 30.19
MOC
High Value 19.87 28.63
SN Shop/Items Compliance/Remarks
& others
Total 62.67 93.28
It is observed that unit cost of Loco POH
increased due to increase in Labour, Material and
High Value items.
(B) POH unit Cost of Wagon:-
2017-18 2018-19
Year
(Up to Mar) (Up to Feb)
Outturn 4499 4797
Due to increase in outturn approx 298 wagons in
2017-18 and 18-19 up to Feb, Unit cost of wagon
only increased by 4.52%.
12.5 Drawal of Stores: Reason for excess drawal of Year 2017-18 2018-19 Diff.
Stores from Stock till date is required to be Outturn of
reviewed and analysed keeping in view the 83 90 07
Loco
increased outturn and nature of POH activities.
Outturn of
4499 5262 763
Wagon
Drawal of
129.39 157.80 27.41
Store

Since outturn of Loco, Wagon and similar


activities are increased in 2018-19 hence drawal
of excess store seems to be genuine.

12.6 Incentive Payment: An upward trend of 29.68% Category wise incentive strength for artisan has
has been noticed as compared to the last year in been revised after cadre structuring (vide Rly.
the total incentive paid till end of Jan’19, which is Board letter No. Pc-111/2016/CRC/1 New Delhi
required to be reviewed and analysed. dt. 30.09.2016 and it was implemented in JMPW
w.e.f. 01.10.2017 for incentive purpose after
cadre structuring the highly skilled artisan has
been increased from Oct. 17 (Sr.Tech. 16% to
26%,Tech.I 44% to 51%),hence incentive
payment is more in the year 2018-2019 (Apr’2018
to Jan’2019).
12.7 O.T. Hours: It was found that there is a huge OT of various units was pending due to an error in
increase in OT hours booked as compared to the the work order in the previous Financial year. The
last year. In fact, the increase is 159% over the spending has increased due to the payment of
last year. Accordingly, there is a quantum jump in arrear OT in this Financial year.
expenditure booked on this account. Detailed
analysis should be done to know the reason for
such enhancement.
12.8 Further it was advised to consider the possibility of Turbo ventilators are being provided in the
installation of Skylight/Sun beam at the roof of the workshop as exhaust fan. For better illumination
workshop shed for natural light during day time more transparent sheets are being provided on
like LLH workshop to be done and also Natural air the roof top. The same to be increased in future.
SN Shop/Items Compliance/Remarks
exhaust fan to be provided at roof top of shed.
12.9 Installation of Solar Power Plant using the open Provision of Rooftop Solar PV modules at various
roof of office buildings and IRIMEE buildings to be locations in Jamalpur Workshop has already been
expedited. sent to REMCL vide L.No. F/Dy.CEE/OFF(Data)/
49/76 dtd 12.03.19 & 02 Nos. 10 KWp Solar
Power Plant for IRIMEE building has already
been uploaded in IRPSM in PH-65.
12.10 Provision of 100% LED in service buildings to be 75% LED in service buildings has already been
completed. achieved & the target of 100% will be completed
shortly
12.11 Hanging/undressed haphazardly cables as Cable dressing work is under progress as per
different locations to be dressed. planned shutdown program.
12.12 Installation of standby Pump-motor set for reliable TR for Stand-by Pump–Motor set has been done
water supply to colonies, hospitals, workshop, from this end. The same is under procurement
station etc. process through store.
12.13 One transformer of 3 MVA,(33/11 KV (make Areva Defective transformers are being repaired by
T&D India Ltd. Date of Installation 31.12.11) is outside agencies.
defective since 30.03.15.

Other transformer of 3 MVA, 33/11 KV (make


Areva T&D India Ltd. Date of Installation 19.01.12)
is defective since 31.05.15

These defective transformers should be repaired


at the earliest.
12.14 Protection system including MCBs and Fuses Provision for tripping facility at every Substation is
should be in working condition at every sub-station under proposal stage & will be done by outside
with individual tripping facility. Its proper agency.
functioning must be ensured by suitable testing on
periodic basis.
13.0 In appreciation of good work done, some Group Noted.
Cash Awards were announced, which is being
communicated separately.

(Naresh Kumar)
Chief Works Manager