Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
EXECUTIVE ENGINEER
P.W.D,P & I.W.T DIVISION
RAMANAGARA
CONSTRUCTION OF BRIDGE ACROSS VRUSHABHAVATHI ON ROAD CONNECTING
DODDAKURUBARAHALLI TO DODDAKALLABALU IN HAROHALLI HOBLI,
KANAKAPURA TALUK, RAMANAGARA DISTRICT
DESIGN SHEETS
NOTE
The Bridge site was inspected by the Executive Engineer Ramanagaram Divisioin along with Assistant
Executive Engineer, Kanakapura, Field Officers, the Contractor and the Consultants on 17th Feb 2017. It was
observed from the Geotechnical report that soft rock is present for a considerable depth and the trial bores
have not been extended to hard rock.
In view of the standing water and presence of harmful elements in the water the top region of soft rock would
have detiriorated and may not have good resisting properties.Also the position of abutment requires a review.
following decisions were taken at site:
1) The pile termination level to be fixed at 3 diameters below the soft rock indicated in Geotech
report and GAD
2) Providing 6mm liners upto top of soft rock
3) Shifting of abutment by 5m relatively towards Industrial area side
4) Cantilever returns is sufficient
The designs have been carried out on the above lines.
Working stress constants
m = 280 Limited 10
3σcbc
n = mσcbc
mσcbc + σst
j = n
1 -
3
Q = 1 σcbc . j.n
2
Ast = M d = M
σst . j.d Q.b
Loadings
IRC Class A - two lanes
IRC 70RW - one lane
Design data :-
Overall length of abutment = 8450 mm
Length of Abutment b/w piles = 8050 mm L W/H ratio
Overall height of abutment. = 7675 mm H
Depth of superstructure = 2250 mm at Edge
Ht of dirtwall + pedestal = 2314 mm H1
Depth (Abutment cap top to top of pile cap.) = 3561 mm H2
Width of abutment stem portion at top = 1200 mm B2
Width of abutment stem portion at base = 1200 mm B2'
Width of pile cap portion = 1900 mm B1
Width of pile cap portion = 1900 mm B3
Depth of pile cap portion at end = 1800 mm
Depth of pile cap portion near wall = 1800 mm
Depth of pile cap portion at end = 1800 mm
Depth of pile cap portion near wall = 1800 mm
Total width at base = 5200 mm B
Live load surcharge = 1.2 m
Reference :-
I.R.C : 6 -2014 (Section : II ) - Loads & stresses
I.R.C : 78 -2014 (Section : VII ) - Foundations and substructure.
I.R.C : 21 -2000 (Section : III ) - Plain and reinforced cement concrete.
I.S 2911 (Section 2) Bored cast-in-situ concrete piles
Grade of steel = Fe500
Density of Concrete = 25 KN/m 3
Free board = 1.2 m
200
8450 8050
200
2.314
T o Abut= 100.436
4.850
2.536
T of Base = 97.900
10.200
Stability analysis:
lever arm
compon unit wt. total wt (m) about Mo
sl.no ents Fig.no l (m) b (m) h or d (m) volume (m3) (KN/m3) (KN) x (KNm)
1 Abt. Wall 1 1 8.05 1.200 2.536 24.498 25.000 612.444 2.500 1531.110
2 Return wall 2 0 0 0.000 0.000 0.000 25.000 0.00 4.050 0.0
3 Base slab 3 1 8.05 5.200 1.800 75.348 25.000 1883.700 2.600 4897.620
Soil
behind
4 abt 4 1 0 0.000 0.000 0.000 0.000 0.000 0.000 0.000
5 Dirt wall 5 1 8.05 0.3 2.014 4.86381 25 121.595 3.25 395.1846
Reaction
from supr
6 str 1 2750.0 2.5 6875
7 Aapproach slab 1 3.500 0 0.3 0 25 0.000 4.050 0
Total stabising moment = ΣMr= 13698.91
10 Braking and other forces 6 200.000 2.536 507.200
11 Earth quake force 124.500 4.186 521.157
58.800 2.918 171.578
0.000 4.075 0.000
0.000 4.075 0.000
1 4
0.825
e x = 0.271
Max= 1261.03 KN
Min= 528.216 KN
Max load on pile is less than pile capacity Hence safe
Reinforcement in pile
cross sectinal area of pile = 1130973.36 mm2
Longitudinal steel = 0.8 % of cross sectional area
= 0.8 1130973.36 = 9047.787 mm2
100
Maximum reaction on the corner pile= 1261.030 KN Moment due to all loads in piles 1,2,3
Depth of pile cap assumed= 1.500 m load on one side of pile cap 2267.543 KN
Depth of soil above cap= 0.500 m Eccentricity= cnetre of pile to centre of bearing=
3
Density of soil= 18.000 KN/m 1.675 m
3
Density of concrete= 25.000 KN/m Max BM at centre of pile = 3798.135 KNm
Dia of the pile= 1.200 m 449.483 KNm
Thickness of abutment= 1.200 m Maxshear per m= 268.348 KN
Distance from centre of pile to face of abutment=
1.100
Length of abutment= 8.400 m
Critical load on the abutment= 3484.039 KN
Projection of cap beyond abutment width in the longitudinal direction
1.90 m
Effective width for pile = 1.2a + b1
a= 1.100
b1= 1.200
beff= 2.52 restricted to 2.65 m
Design for flexure:
Wt of soil above pile cap per meter= 17.1 KN
wt of pile cap per metre= 71.25 KN
Moment per m due to wt of pile cap within eff., Width at face of abut=
128.606 KNm
Moment per m due to wt of soil at face of abut/pier=
30.87 KNm
Moment per m due to pile reaction at face of abut/pier=
287.90 KNm
Design moment per m= 128.42 KNm
Design constants
Grade of concrete= M 25
grade of steel = Fe 500
m= 10
бst= 319.992 N/mm 2
2
бcbc= 11.106 N/mm 13.3
m= 10
n1= 0.26
j= 0.91
Q= 1.31
Es= 2.00E+05 N/mm 2
2
Ec= 32500 N/mm
σcc= (table 9 of IRC21-2000) 6.75 N/mm 2
σcbc= (table 9 of IRC21-2000) 8.33 N/mm 2
Transverse Reinforcement:
Total load on piles 1 & 4
805.77 KN
Distance from centre of pile to return face 0.80 m
Transverse moment= 123.96 KNm per metre
Mv= 124.0 KNm clear cover 50 mm
Effective Depth Reqd "deff" = M cutoff depth 75 mm
QxB Bar Dia 25 mm
deff reqd: = 124.0 x 1000000
1.31 x 1000
= 308 mm < 1662.5 mm Hence O.K
deff provided = 1800 - 75 - 12.5 - 50
= 1662.5 mm
Ast reqd = M
s st x j x d
\ Ast reqd = 123.96 x 1000000
319.99 x 0.91 x 1662.50
2
= 255 mm
2
As1 = 490.874 cm
No of bars Reqd: = 254.91 = 1 Nos
490.874
Spacing of Bars = 1000 = 1925.6 mm
1 1925.6
So provide 20 mm dia bars , 150 mm c/c spacing
Grade of Concrete = 25 N/mm2 Allow - ten 670 Allow -comp 7500 KN/m2
Total Height of Pier = 1290 mm
Grade of steel = Fe500
3
Density of Concrete = 25.00 KN/m
Free board = 1.20 m
SBC of soil = 400.00 KN/m2
References.
I.R.C :- 6 - 2010 - Loads & Stresses.
I.R.C :- 21 - 2000 - Plain and Reinforced cement concrete
1200
100.400
2500 2500 300
0
0
750 750 1200
3400
1600
6500 1290
1200
2000
98.800
Bearing Stress in pier cap 3783.33 KN/m2 safe Min DeadLoad Case
y
0.80 3.60 0.80
0.80
1
2
5.2 m
x x
3.60
3 4
0.8
y
5.2 m
2.Longitudinal forces:
a) Braking forces
i) One train Class 70R 0.2*1000/2 +0.03*(1455+613.8+803.6)
186.17 KN
b)Force due to shear rating at one span dislodge condition
3.Transverse Force :
a) Braking force
i)one train 70 R 100 kN
b)Force due to shear rating at one span dislodge condition=
0
Force due to shear rating at normal condition
0 KN
Force due to wind on super structure
460.7 KN
4.Longitudinal moment:
a) Due to braking:
Due to one train of 70R
height= 4450 mm
Moment= 828.4654 KNm
5)Transverse Moments
a)Due to braking: 70R height= 4450 mm
Moment= 445.00 KNm
Load on piles:
Total load= 5773.55 KN
Longitudinal moment= 1525.40 KNm
Transverse moment= 4372.40 KNm
No of piles= 4
Max= 2285.93 KN
Min= 600.8446 KN
Density of Concrete 25 KN/m3
Dia of the pile 1.2 m
Thickness of pier 1.2 m
Distance from centre of pile to face of pier 1.20 m
m 10
k 0.258
j 0.914
Q or R = 0.981
Bending Moment along Z Dirn.due to pile reaction due to 3 and 4 at the face of pier = 3987.12 kN-m
= 766.755 kN-m/m
Shear in X Direction = 3322.6 kN
= 638.962 kN/m
Calculation of Flexural Reinforcement:
BM along Z- direction
6
Effective depth required d = 766.75 x 10
0.98 x 5200
= 384.00 mm > 1700 mm
6 2
Area of steel Ast = 766.75 x 10 = 2055.87 mm
240 x 0.91 x 1700
2/
= 395.3595 mm m
2
Minimum steel Ast,min = 0.12 x 1000 x 1800 = 2160 mm
100
using 20 mm dia bars, No of bars reqd = 2160 = 6.9
314.16 say 7
At top x- direction
2
Minimum steel Ast,min = 0.12 x 1000 x 1700 = 2040 mm
100
using 20 mm dia bars, No of bars reqd = 2040 = 7.0
314.16 say 7
2
= 3600 mm